JPH0657957B2 - Reverse floor construction method - Google Patents

Reverse floor construction method

Info

Publication number
JPH0657957B2
JPH0657957B2 JP62112220A JP11222087A JPH0657957B2 JP H0657957 B2 JPH0657957 B2 JP H0657957B2 JP 62112220 A JP62112220 A JP 62112220A JP 11222087 A JP11222087 A JP 11222087A JP H0657957 B2 JPH0657957 B2 JP H0657957B2
Authority
JP
Japan
Prior art keywords
floor
working
girder
serves
beams
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP62112220A
Other languages
Japanese (ja)
Other versions
JPS63277341A (en
Inventor
敏行 佐藤
哲哉 森田
亨 人見
一郎 向井
成海 田代
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP62112220A priority Critical patent/JPH0657957B2/en
Publication of JPS63277341A publication Critical patent/JPS63277341A/en
Publication of JPH0657957B2 publication Critical patent/JPH0657957B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、地下階の逆打ち施工方法に関するものであ
り、通常の地下階の階高よりも大きな階高を有する地下
階を構築するのに利用される。
TECHNICAL FIELD The present invention relates to a reverse floor construction method for constructing a basement floor having a floor height larger than that of a normal basement floor. Used for.

〔従来の技術〕[Conventional technology]

逆打ち工法によって地下階を構築する場合、構築された
上位階の床構造体が山止め壁の支保工の役目を果たすの
で、切梁等の支保工を設けないのが普通である。
When the basement floor is constructed by the upside down construction method, since the constructed floor structure of the upper floor serves as the support work for the mountain retaining wall, it is usual not to provide the support work such as the cut beams.

しかしながら、逆打ち工法においても、地下階の階高が
通常の階高(3.5m〜4.5m)よりも大きい場合、山止め壁
の強度(曲げ剛性など)を増大させてこれに対処するの
では、山止め壁の工事費が膨大なものとなり、不経済で
あるから、地下階までの中間付近に切梁を設置して山止
め壁を支保することがある。
However, even in the upside down construction method, if the floor height of the basement floor is larger than the normal floor height (3.5 m to 4.5 m), it may not be possible to deal with this by increasing the strength (bending rigidity, etc.) of the retaining wall. Since the construction cost of the retaining wall is huge and it is uneconomical, a retaining beam may be installed to support the retaining wall by installing a girder near the basement floor.

従来、この切梁としては、H型鋼が使用されていた。Conventionally, H-shaped steel has been used as the cross beam.

また切梁ではなく、腹起こしを対象にした従来技術では
あるが、特公昭61-35331号公報によってRC造の支保工
が知られている。これは、山止め壁に沿わせて設けた上
位の支保工(腹起こし)に鋼製の吊り型枠を吊り下げ支
持させ、当該吊り型枠内に配筋、コンクリート打設を行
って、下位のRC造支保工を築造し、以後、吊り型枠を
順次下方へ転用して同様な工程を繰り返すことにより、
上から下へと順次、RC造の支保工を築造していくもの
である。
Further, although it is a conventional technique that is intended not for the timber but for the abdomen, the support structure of RC construction is known from Japanese Patent Publication No. 61-35331. This is because a steel suspension formwork is suspended and supported by an upper support (abdomen up) provided along the mountain stop wall, and the reinforcement form and concrete are placed in the suspension formwork, By constructing the RC construction support of, after that, the hanging form is diverted downward and the same process is repeated,
The RC construction will be built in order from top to bottom.

〔発明が解決しようとする問題点〕[Problems to be solved by the invention]

前者の従来例においては、次のような問題点があった。
即ち、逆打ち工法であるが故に切梁用の長尺鉄骨の搬
入、搬出が非常に困難であり、また階高が大きいが故
に、床構造体用型枠、鉄筋やその他の質材の搬入、転用
等も困難であり、安全確保の必要上、作業能率が低下
し、工事費が増大するなどの問題があった。
The former conventional example has the following problems.
That is, it is very difficult to carry in and carry out long steel frames for beams because of the reverse construction method, and since the floor height is large, the formwork for floor structures, the reinforcing bars and other quality materials are carried in. However, diversion is difficult, and there is a problem that work efficiency is lowered and construction cost is increased due to the necessity of ensuring safety.

後者の従来技術を切梁に応用し、RC造の切梁とするこ
とによって、上記の問題点の多くを解決することが可能
である。即ち、切梁をRC造とした場合は、地下階の床
構造体の構築後、切梁を破砕し、コンクリートのガラス
として取り扱えるので場外搬出が容易となり、しかも掘
削作業に支障のない範囲で、RC造切梁の梁幅を任意に
設定できるので、RC造切梁を幅広にして、階高中間部
での作業床に兼用することが可能になる等の利点が得ら
れる。
Many of the above problems can be solved by applying the latter conventional technique to a girder to form a RC girder. That is, in the case where the cutting beam is RC construction, after the construction of the floor structure of the basement floor, the cutting beam can be crushed and handled as concrete glass, so that it can be easily carried out of the site, and within a range that does not hinder excavation work. Since the beam width of the RC beam can be set arbitrarily, it is possible to widen the RC beam to be used as a working floor in the middle part of the floor height.

しかしながら、RC造の切梁兼用作業床とした場合、土
圧による軸力(水平力)を受けたとき、切梁兼用作業床
の中央部が上方へ曲がる危険性があり、そのため、破砕
を前提とした仮設材であるにもかかわらず、本設の床構
造体と同様な梁付きの断面形状としたり、厚さの著しく
厚いものにする必要があった。従って、コンクリートや
鉄筋の使用量が多く、解体撤去時のはつり作業も面倒な
ものとなり、しかも切梁兼用作業床のための吊り型枠が
必要であるなど、全体として不経済であった。
However, in the case of an RC-made working floor that also serves as a girder, when axial force (horizontal force) due to earth pressure is applied, there is a risk that the central portion of the working floor that serves both as a girder will bend upwards, and therefore crushing is a prerequisite. Despite being a temporary material, it was necessary to have a cross-sectional shape with a beam similar to that of the floor structure of the main installation or to have a significantly thicker thickness. Therefore, the amount of concrete and rebar used is large, the work of removing the dismantled and removed pieces is troublesome, and a hanging formwork for a working floor that also serves as a girder is required.

本発明の目的は、逆打ち工法によって階高の大きい地下
階を構築するにあたり、階高の中間付近に設置する切梁
をRC造の切梁兼用作業床とした場合に発生する上記の
問題点を解消することにある。
The object of the present invention is to construct a basement floor with a large floor height by the upside down construction method, and the above-mentioned problems that occur when the cutting beam installed near the middle of the floor height is an RC construction working beam To solve the problem.

〔問題点を解決するための手段〕[Means for solving problems]

上記の目的を達成するために、本発明が講じた技術的手
段は、次の通りである。即ち、本発明による地下階の逆
打ち施工方法は、上位階の床構造体を構築し且つ山止め
壁の内側の地盤を所定深度まで掘り進めた後、掘削底に
土間コンクリートを打設してRC造の切梁兼用作業床を
築造し、当該切梁兼用作業床を前記上位階の床構造体に
吊り下げ支持させ且つ当該切梁兼用作業床と上位階の床
構造体との間に仮設支柱を介在させた状態で、当該切梁
兼用作業床の下方の地盤を所定深度まで掘削して下位階
の床構造体を構築することを特徴としている。
The technical means taken by the present invention to achieve the above object are as follows. That is, the underground floor reverse construction method according to the present invention constructs the floor structure of the upper floor and digs the ground on the inner side of the retaining wall to a predetermined depth, and then places earth concrete on the excavated bottom. An RC-built working floor that also serves as a girder is hung, and the working floor that also serves as a girder is hung and supported by the floor structure of the upper floor, and is temporarily installed between the working floor that also serves as the girder and the floor structure of the upper floor. It is characterized by constructing a floor structure on the lower floor by excavating the ground below the working floor that also serves as a girder to a predetermined depth while interposing columns.

〔作用〕[Action]

上記の構成によれば、掘削底に土間コンクリートを打設
してRC造の切梁兼用作業床を築造するので切梁兼用作
業床の底型枠や当該底型枠のための支保工が不要であ
る。
According to the above-mentioned structure, since the concrete floor is placed on the excavated bottom to construct the RC beam work floor that also serves as a girder, there is no need for a bottom formwork for the work platform that serves both as a girder and support work for the bottom formwork. Is.

RC造の切梁兼用作業床は山止め壁を支保する切梁とし
ての役目を果たす他、作業通路や床構造体用型枠や鉄筋
等の資材置き場として利用される。
The RC working floor also serving as a girder serves as a girder that supports the mountain retaining wall, and is also used as a work passage, a floor structure formwork, and a material storage space for reinforcing bars and the like.

RC造の切梁兼用作業床を上位階の床構造体に吊り下げ
支持させ且つ当該切梁兼用作業床と上位階の床構造体と
の間に仮設支柱を介在させた状態で、当該切梁兼用作業
床の下方の地盤を掘削するので、切梁兼用作業床を極端
に厚くしたり、切梁兼用作業床の下面に梁を築造して曲
げ剛性を高めなくても、山止め壁に作用する土圧によっ
て、切梁兼用作業床の中央部が上下いずれの方向にも曲
がる虞れがない。
In the state in which an RC-structured working floor also serving as a girder is suspended from and supported by a floor structure of an upper floor, and a temporary support column is interposed between the working floor serving also as a girder and the floor structure of the upper floor, Since the ground below the combined working floor is excavated, it works on the mountain retaining wall without making the working floor also used for beams and girders extremely thick or for increasing the bending rigidity by building beams on the lower surface of the working floor for both beams and girders. There is no risk that the central portion of the working floor that also serves as a girder will bend in either the upper or lower direction due to the earth pressure.

〔実施例〕〔Example〕

以下、本発明の実施例を図面に基づいて説明する。 Embodiments of the present invention will be described below with reference to the drawings.

図において、1は柱列や連続壁等による山止め壁、2は
RC造の切梁兼用作業床であり、構築の済んだ上位階
(例えば地上1階)の床構造体3にねじ節鉄筋(両端部
にのみねじ部を形成した鋼棒でもよい)等より成る複数
本の吊り棒4で吊り下げ支持されており、且つ当該切梁
兼用作業床2と前記床構造体3との間には、吊り棒4に
よる吊下げ位置の近傍部にパイプサポート等の仮設支柱
5を介在させ、切梁兼用作業床2の上下二方向への変形
を、つまり吊り棒4によって下方への変形を、仮設支柱
5によって上方への変形を夫々防止すべく構成してあ
る。6a,6bは座金である。吊り棒4の上下両端部には、
六角ナット、六角長ナット(ねじ節鉄筋用のカップラ
ー)等のナット部材7が螺着されている。8はRC造の
腹起こし、9は地下階の柱を示す。10は梁である。
In the figure, 1 is a retaining wall made up of columns or continuous walls, and 2 is an RC-structured working floor for beams and girders. It is suspended and supported by a plurality of suspension rods 4 made of (steel rods having threaded portions only at both ends) or the like, and between the working beam 2 also serving as a girder and the floor structure 3. Intervenes a temporary support column 5 such as a pipe support in the vicinity of the position of suspension by the suspension rod 4 to deform the working floor 2 that also serves as a beam in two directions, that is, the suspension rod 4 deforms downward. The temporary columns 5 are configured to prevent upward deformation. 6a and 6b are washers. At the upper and lower ends of the hanging rod 4,
A nut member 7 such as a hexagonal nut or a hexagonal long nut (a coupler for a thread-bar rebar) is screwed on. Reference numeral 8 indicates an RC angry belly, and reference numeral 9 indicates a basement pillar. 10 is a beam.

地下階の逆打ち施工方法を工程順に説明すると次の通り
である。
The reverse construction method for the basement floor will be described in the order of steps as follows.

先ず、第3図(イ)に示すように、山止め壁1の内側の
地盤をある程度掘削して地上1階の床構造体3を構築し
た後、前記地盤を所定深度まで掘り進める。掘削底11に
は、以後の掘削作業に必要な開口部を残した状態に、切
梁兼用作業床成型用の側型枠12や腹起こし成型用の型枠
13を設置し、且つ床構造体3には、吊り棒4の上端部を
ナット部材7で支持させ、吊り棒4の下端部には座金6a
を介してナット部材7を螺着しておく。
First, as shown in FIG. 3 (a), the ground inside the retaining wall 1 is excavated to some extent to construct the floor structure 3 on the ground floor, and then the ground is dug to a predetermined depth. In the state where the opening necessary for the subsequent excavation work is left on the excavation bottom 11, the side formwork 12 for double-cutting and working floor molding and the formwork for belly-up formation
13 is installed, and the upper end of the hanging rod 4 is supported by the nut member 7 on the floor structure 3, and a washer 6a is attached to the lower end of the hanging rod 4.
The nut member 7 is screwed on via.

この状態で、前記型枠12,13内に配筋すると共に土間コ
ンクリートを打設して、第3図(ロ)に示すように、切
梁兼用作業床2及び腹起こし8を築造する。ここで土間
コンクリートとは、掘削底11に底型枠を敷設することな
く直接的に打設するコンクリートを意味するが、ビニー
ル等の防水シートを敷設してコンクリート打設を行う場
合も包含している。
In this state, the concrete frames 12 and 13 are laid out and concrete is poured into the soil to build a working floor 2 also serving as a cross beam and an abdomen 8 as shown in FIG. Here, the earth concrete means concrete that is directly placed on the excavated bottom 11 without laying a bottom formwork, but also includes the case where concrete is placed by laying a waterproof sheet such as vinyl. There is.

切梁兼用作業床2及び腹起こし8に所要強度が発現した
後、第3図(ハ)の破線で示すように、切梁兼用作業床
2と前記床構造体3との間に、前記仮設支柱5を介在さ
せ、切梁兼用作業床2の上方への変形を阻止させる。つ
まり切梁兼用作業床2は吊り棒4により下方への変形が
阻止され、仮設支柱5により上方への変形が阻止される
ことになる。この状態で切梁兼用作業床2の下方を所定
深度まで掘削する。
After the required strength is developed in the working beam 2 for both beams and the abdomen 8, the temporary construction is performed between the working floor 2 for both beams and the floor structure 3 as indicated by the broken line in FIG. 3C. The pillar 5 is interposed to prevent the work floor 2 which also serves as a girder from being deformed upward. That is, the working beam 2 that also serves as a girder is prevented from being deformed downward by the suspension rod 4 and is prevented from being deformed upward by the temporary support column 5. In this state, the work floor 2 which also serves as a beam is excavated to a predetermined depth.

しかる後、第3図(ニ)に示すように、地下1階の床構
造体3を構築する。床構造体3には、コンクリート打設
に先立って吊り棒4を挿通し、吊り棒4下端部には、座
金6aを介してナット部材7を螺着しておく。次いで、掘
削底11に切梁兼用作業床成型用の側型枠12や腹起こし成
型用の型枠13を設置し、配筋及び土間コンクリートの打
設を行って、第3図(ホ)に示すように、2段目の切梁
兼用作業床2及び腹起こし8を築造する。これらに所要
強度が発現した後、同図に破線で示すように、2段目の
切梁兼用作業床2と地下1階の床構造体3との間に仮設
支柱5を介在させ、仮設支柱5と吊り棒4で当該切梁兼
用作業床2の上下方向の変形を阻止した状態で、その下
方を所定深度まで掘削し、第3図(ヘ)に示すように、
地下2階の床構造体3を形成し、以下、同様な工程を繰
り返すのである。
Thereafter, as shown in FIG. 3D, the floor structure 3 on the first basement floor is constructed. The suspension rod 4 is inserted into the floor structure 3 prior to the concrete pouring, and the nut member 7 is screwed to the lower end portion of the suspension rod 4 via the washer 6a. Next, on the excavated bottom 11, the side formwork 12 for forming the working beam and the workbed and the formwork 13 for forming the bellows are installed, and the reinforcement and the soil concrete are placed, and as shown in FIG. As shown, the working floor 2 which also serves as a girder and the abdomen 8 of the second stage are built. After the required strength is developed in these, as shown by the broken line in the figure, the temporary support pillar 5 is interposed between the second-level working floor 2 also serving as a girder and the floor structure 3 on the first basement floor, and the temporary support pillar is provided. In a state in which the vertical beam 5 and the suspension rod 4 are prevented from being deformed in the vertical direction, the working floor 2 also serving as a beam is excavated to a predetermined depth, and as shown in FIG.
The floor structure 3 on the second basement floor is formed, and thereafter, the same steps are repeated.

尚、1段目の切梁兼用作業床2の吊り棒4と2段目の切
梁兼用作業床2の吊り棒4とは、互いに分離されたもの
でもよく、第3図(ニ),(へ)に示すような所定長さ
の継ぎ足し棒4′を用いて適当な時期まで連結してお
き、上段の切梁兼用作業床2を下段の切梁兼用作業床2
の吊下げ支持に併用してもよい。また図示の実施例で
は、1段目の切梁兼用作業床2、地下1階の床構造体
3、2段目の切梁兼用作業床2、地下2階の床構造体3
の順に施工したが、1段目と2段目の切梁兼用作業床2
を築造した後、1段目の切梁兼用作業床2と2段目の切
梁兼用作業床2との中間部に地下1階の床構造体3を構
築し、3段目の切梁兼用作業床2を築造した後、2段目
の切梁兼用作業床2と3段目の切梁兼用作業床2との中
間部に地下2階の床構造体3を構築するようにしてもよ
い。
The hanging rod 4 of the working floor 2 for both beams and girders and the hanging rod 4 of the working floor 2 for both beams and girders may be separated from each other, as shown in FIG. (2) are connected to each other until a suitable time by using a connecting rod 4'having a predetermined length, and the upper working beam 2 for both beams and working beams for lower beams 2
It may be used together with the suspension support of. Further, in the illustrated embodiment, the working floor 2 for both beams and the first floor, the floor structure 3 for the first basement floor, the working floor 2 for both the beams and second floor, and the floor structure 3 for the second basement floor
Construction work was done in this order, but the working floor for both beams and beams for the first and second steps
After the construction, a floor structure 3 on the first basement floor is constructed in the middle between the first-level working beam and double-purpose working beam 2 and the third-level working beam is also used. After constructing the work floor 2, the floor structure 3 on the second basement floor may be constructed at an intermediate portion between the second-tier beam-combined work floor 2 and the third-stage beam-combined work floor 2. .

図中、14は地下階の外壁コンクリートである。前記切梁
兼用作業床2や腹起こし8は、それらが不要になる都
度、はつり取って撤去してもよく、最下階まで施工した
後、最下段のものから順次解体撤去してもよい。また図
示の実施例では、腹起こし8もRC造としたが、腹起こ
し8については鉄骨を使用してもよい。
In the figure, 14 is concrete on the outer wall of the basement floor. The working floor 2 that also serves as a girder and the abdomen 8 may be removed and removed each time they are no longer needed, or after the construction has been completed up to the lowest floor, the ones at the lowest stage may be disassembled and removed. Further, in the illustrated embodiment, the abdomen 8 is also made of RC, but steel may be used for the abdomen 8.

〔発明の効果〕〔The invention's effect〕

本発明は、上述した構成よりなるから、次の効果を奏し
得るのである。
Since the present invention has the above-mentioned configuration, the following effects can be obtained.

RC造の切梁兼用作業床が山止め壁を支保する切梁と
しての役目を果たす他、作業通路や床構造体用型枠や鉄
筋等の資材置き場として利用されるので、地下階の階高
が大きくても容易かつ安全に作業できる。
The RC floor work floor that also serves as a girder serves as a girder that supports the mountain retaining wall, and is also used as a work passage, a formwork for floor structures, and a material storage space for reinforcing bars, etc. Even if the size is large, you can work easily and safely.

掘削底に土間コンクリートを打設してRC造の切梁兼
用作業床を築造するので切梁兼用作業床の底型枠や当該
底型枠のための支保工が不要である。
Since an earth concrete is cast on the excavated bottom to construct a working floor that is also used as an RC girder, there is no need for a bottom formwork for the working floor that serves both as a girder and support work for the bottom formwork.

殊に、RC造の切梁兼用作業床を上位階の床構造体に吊
り下げ支持させ且つ当該切梁兼用作業床と上位階の床構
造体との間に仮設支柱を介在させた状態で、当該切梁兼
用作業床の下方の地盤を掘削するので、切梁兼用作業床
を極端に厚くしたり、切梁兼用作業床の下面に梁を築造
して曲げ剛性を高めなくても、山止め壁に作用する土圧
によって切梁兼用作業床の中央部が上下いずれの方向に
も曲がる虞れがない。
In particular, in the state where an RC-structured working floor also serving as a girder is suspended from and supported by a floor structure on the upper floor, and a temporary strut is interposed between the working floor serving also as a girder and the floor structure on the upper floor, Since the ground below the working floor that also serves as a beam is excavated, a mountain stopper is not required even if the working floor that also serves as a beam is made extremely thick, or if the beam is built on the lower surface of the working floor that serves as a beam to increase bending rigidity. There is no fear that the central portion of the working floor that also serves as a girder will bend in either the upper or lower direction due to the earth pressure acting on the wall.

従って、コンクリートや鉄筋の使用量が少なくて済み、
解体撤去時のはつり作業も容易であり、切梁兼用作業床
の底型枠や当該底型枠のための支保工が不要であること
と相まって、非常に経済的である。
Therefore, the amount of concrete and rebar used is small,
It is easy to perform the lifting work at the time of dismantling and removal, and it is very economical in combination with the fact that there is no need for the bottom formwork of the working floor that also serves as a girder and the support work for the bottom formwork.

【図面の簡単な説明】[Brief description of drawings]

図面は本発明に係る地下階の逆打ち施工方法の実施態様
を例示し、第1図は要部の断面図、第2図は全体の概略
平面図、第3図(イ),(ロ),(ハ),(ニ),
(ホ),(ヘ)は工程説明図である。 1…山止め壁、2…切梁兼用作業床、3…床構造体、4
…吊り棒、5…仮設支柱。
The drawings exemplify an embodiment of the method for constructing an upside down basement according to the present invention. Fig. 1 is a sectional view of a main part, Fig. 2 is an overall schematic plan view, and Figs. 3 (a) and 3 (b). , (C), (D),
(E) and (f) are process explanatory drawings. DESCRIPTION OF SYMBOLS 1 ... Mountain stop wall, 2 ... Work floor that also serves as beams, 3 ... Floor structure, 4
… Suspension bars, 5… Temporary columns.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 向井 一郎 大阪府大阪市東区本町4丁目27番地 株式 会社竹中工務店大阪本店内 (72)発明者 田代 成海 大阪府大阪市東区本町4丁目27番地 株式 会社竹中工務店大阪本店内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Ichiro Mukai 4-27, Honmachi, Higashi-ku, Osaka City, Osaka Prefecture Takenaka Corporation, Osaka Main Store (72) Inventor Narumi Tashiro 4-27, Honmachi, Higashi-ku, Osaka Takenaka Corporation Osaka Main Store

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】上位階の床構造体を構築し且つ山止め壁の
内側の地盤を所定深度まで掘り進めた後、掘削底に土間
コンクリートを打設してRC造の切梁兼用作業床を築造
し、当該切梁兼用作業床を前記上位階の床構造体に吊り
下げ支持させ且つ当該切梁兼用作業床と上位階の床構造
体との間に仮設支柱を介在させた状態で、当該切梁兼用
作業床の下方の地盤を所定深度まで掘削して下位階の床
構造体を構築することを特徴とする地下階の逆打ち施工
方法。
1. After constructing a floor structure of the upper floor and digging the ground inside the cliff wall to a predetermined depth, placing earth concrete on the bottom of the excavation to construct a working floor for RC beams and beams. In the state of being built, the working floor also serving as a girder is hung and supported by the floor structure of the upper floor, and the temporary strut is interposed between the working floor serving as a girder and the floor structure of the upper floor. A method for reverse construction of a basement floor, which comprises constructing a floor structure of a lower floor by excavating the ground below a working floor that also serves as a girder to a predetermined depth.
JP62112220A 1987-05-07 1987-05-07 Reverse floor construction method Expired - Fee Related JPH0657957B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62112220A JPH0657957B2 (en) 1987-05-07 1987-05-07 Reverse floor construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62112220A JPH0657957B2 (en) 1987-05-07 1987-05-07 Reverse floor construction method

Publications (2)

Publication Number Publication Date
JPS63277341A JPS63277341A (en) 1988-11-15
JPH0657957B2 true JPH0657957B2 (en) 1994-08-03

Family

ID=14581258

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62112220A Expired - Fee Related JPH0657957B2 (en) 1987-05-07 1987-05-07 Reverse floor construction method

Country Status (1)

Country Link
JP (1) JPH0657957B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05140937A (en) * 1991-11-21 1993-06-08 Fujita Corp Mounting of strut with underground reverse driving method
JP2560598B2 (en) * 1992-12-25 1996-12-04 鹿島建設株式会社 RC reverse construction method
JP2002188163A (en) * 2000-12-18 2002-07-05 Shimizu Corp First-story floor preceding underground construction method
JP3684347B2 (en) * 2001-11-26 2005-08-17 株式会社ホクコン Construction method of precast concrete water tank
JP6937205B2 (en) * 2017-09-21 2021-09-22 大成建設株式会社 How to build an underground structure

Also Published As

Publication number Publication date
JPS63277341A (en) 1988-11-15

Similar Documents

Publication Publication Date Title
CN109403654B (en) Underpinning and reinforcing method for existing building structure
JPH0657957B2 (en) Reverse floor construction method
JP6855296B2 (en) Building foundation structure and its construction method
KR20200122037A (en) The construction method using a exterio wall of undergound structure
CN110792282B (en) Transformation method of frame column without support underpinning
JP7386095B2 (en) Underground structure construction method
JPS5829922A (en) Constructing method for underground outer wall
JP3122850B2 (en) Construction method of building with basement floor with steel pipe pile foundation
KR100593203B1 (en) a deck supportframe and a construction methed
EP0151626A1 (en) Procedure for making foundations for a structure, and intermediate piece for use in the procedure.
JPH0657958B2 (en) Reverse floor construction method
JPS61109827A (en) Construction of basement
CN212927132U (en) Anti-seismic reinforcing structure of frame structure filled ductile anti-seismic component
CN108589930A (en) Assembly concrete-filled steel tube column-isolated footing-concrete collar tie beam T shape connecting nodes
JPH07103583B2 (en) Construction method for large span underground structure
JP2894217B2 (en) Building structural frame
KR200369485Y1 (en) a deck supportframe
JPH0657769A (en) Underground concrete structure and working method thereof
JPH0759813B2 (en) Underground construction method
JPH06117052A (en) Precast horizontal central pillar
JPH07119464B2 (en) Construction method of earth retaining structure for underground structure and construction member for mountain retaining structure used therefor
JP2023074981A (en) foundation structure
JPS6217233A (en) Foundation base column
JP2023074982A (en) Construction method of foundation structure
JPH0765313B2 (en) Underground construction method

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees