JPH06294136A - Soil improvement pile - Google Patents

Soil improvement pile

Info

Publication number
JPH06294136A
JPH06294136A JP8202693A JP8202693A JPH06294136A JP H06294136 A JPH06294136 A JP H06294136A JP 8202693 A JP8202693 A JP 8202693A JP 8202693 A JP8202693 A JP 8202693A JP H06294136 A JPH06294136 A JP H06294136A
Authority
JP
Japan
Prior art keywords
pile
foundation
ground
gravel
soft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP8202693A
Other languages
Japanese (ja)
Inventor
Seiji Hamazuka
政治 浜塚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP8202693A priority Critical patent/JPH06294136A/en
Publication of JPH06294136A publication Critical patent/JPH06294136A/en
Pending legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Foundations (AREA)

Abstract

PURPOSE:To reinforce a bearing capacity of a foundation ground in a soft ground by enveloping an outer peripheral surface of large-sized gravel piles prepared under a post of a structure with a material having a specified strength and durability. CONSTITUTION:With an earth drilling machine or the like, a pile hole 2 is excavated in a soft ground A under a post where the load of a structure is concentrated. A bag-attached cage 5 made of a mesh sheet is mounted to a reinforcing bar frame 3 and inserted into the pile hole 2. Then, gravels 6 are filled in the cage 5, thereby building a gravel pile. A gravel mat 7 is spread to a foundation where blind concrete is cast on the mat 7, thereby building up a structural skeleton B in the order of a pressure resistant board 8 and an underground beam 9 and the foundation. Then, when this is aplied to a soft cohesive soil gound, if the other part which excludes a soil improvement pile sinks, the load is concentrated on the gravel pile made of large-sized gravels 6 so that the gravel pile 6 is bulged horizontally so that it may work again as a direct foundation as a whole and stabilize the foundation ground gradually. This construction makes it possible to reinforce a bearing capacity of the foundation ground.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は軟弱粘性土地盤や、液状
化するような砂地盤等の如き軟弱地盤の改良工法及び地
盤改良杭に係るものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for improving soft ground such as soft and viscous ground and liquefied sand ground, and ground improvement piles.

【0002】[0002]

【従来の技術】前記軟弱粘性土地盤や液状化するような
ゆるい砂地盤では、通常は杭基礎にするのが一般的であ
る。
2. Description of the Related Art In the case of the soft and viscous ground and the loose sand that is liquefied, it is common to use a pile foundation.

【0003】[0003]

【発明が解決しようとする課題】前記したような軟弱地
盤で、2〜3階建の建物を杭基礎で設計する場合、不経
済であり、たとえ地盤改良を行っても直接基礎にする方
が経済的な場合が多い。また粘性土の圧密沈下、あるい
は液状化に伴う砂層の圧縮沈下に対して杭は追従しない
ので、構造物の基礎下に空隙が生じる。
It is uneconomical to design a 2-3 floor building with a pile foundation in the soft ground as described above, and it is better to use the foundation directly even if the ground is improved. Often economical. In addition, since the pile does not follow the consolidation settlement of the cohesive soil or the compression settlement of the sand layer due to liquefaction, voids occur under the foundation of the structure.

【0004】本発明は前記従来技術の有する問題点に鑑
みて提案されたもので、その目的とする処は、軟弱地盤
において、基礎底盤の支持力増強及び液状化対策が図ら
れる地盤改良杭を提供する点にある。
The present invention has been proposed in view of the above problems of the prior art, and an object of the present invention is to provide a ground improvement pile which is capable of strengthening the bearing capacity of the foundation floor and taking measures against liquefaction in soft ground. It is in the point of providing.

【0005】[0005]

【課題を解決するための手段】前記の目的を達成するた
め、本発明に係る地盤改良杭は、構造物の柱下に造成さ
れた太径の砂利杭の外周面を、所要の強度と耐久性を有
する材料で包覆して構成されている。請求項2の発明
は、前記砂利杭の外周面を十分な強度と耐性を有するメ
ッシュシートで包覆したものである。
In order to achieve the above-mentioned object, the ground improvement pile according to the present invention has the required strength and durability for the outer peripheral surface of a large-diameter gravel pile formed under a pillar of a structure. It is covered with a material having properties. According to the invention of claim 2, the outer peripheral surface of the gravel pile is covered with a mesh sheet having sufficient strength and resistance.

【0006】[0006]

【作用】本発明に係る地盤改良杭は、荷重の集中する柱
下に造成された太径の砂利杭より構成され、外周面をメ
ッシュシートの如き所要の強度と耐久性を有する材料よ
り構成されているので、軟弱粘性土地盤に適用された場
合、前記地盤改良杭以外の部分が沈下すると、同地盤改
良杭に荷重が集中し、太径の砂利杭より構成された地盤
改良杭に荷重が集中し、その結果、前記砂利杭が横にふ
くれて、再び全体的に直接基礎として働く。以上の繰り
返しによって徐々に基礎地盤が安定していく。
The ground improvement pile according to the present invention is composed of a large-diameter gravel pile formed under a column where a load is concentrated, and its outer peripheral surface is composed of a material having a required strength and durability such as a mesh sheet. Therefore, when applied to soft and viscous ground, when the parts other than the soil improvement piles sink, the load is concentrated on the soil improvement piles and the load is applied to the soil improvement piles composed of large-diameter gravel piles. Concentration, as a result of which the gravel stakes swell to the side and once again act as a direct foundation as a whole. By repeating the above, the foundation ground will gradually stabilize.

【0007】一方、砂地盤の如き軟弱地盤の液状化に対
しては、地震時に一時的に地盤が液状化しても、所要の
強度と耐久性を有する材料で包覆された砂利杭が自立す
るとともに、軟弱地盤の間隙水を抽出し、間隙水圧を消
散せしめるドレーンの機能を果し、液状化防止の働きを
するものである。
On the other hand, with respect to liquefaction of soft ground such as sand ground, even if the ground is temporarily liquefied during an earthquake, the gravel pile covered with a material having the required strength and durability can stand on its own. At the same time, it serves to prevent liquefaction by extracting the pore water of the soft ground and functioning as a drain that dissipates the pore water pressure.

【0008】[0008]

【実施例】以下本発明を図示の実施例について説明す
る。構造物における荷重の集中する柱下部の軟弱地盤A
に、アースドリル機等を使用して掘削バケット1によっ
て杭孔2を掘削し、(図1(イ)参照)同杭孔2内に、
鉄筋フレーム3にメッシュシート4等よりなる袋付き鉄
筋篭5を取付けて挿入する。(図1(ロ)参照) 次いで図1(ハ)に示す如く同袋付き鉄筋篭5に砂利6
を充填して砂利杭を構築し、基礎に砂利のマット7(グ
ラベルマット)を敷設する。(図1(ニ)参照) 前記砂利のマット7上に捨コンクリートを打設して耐圧
版8、地中梁9と基礎から順に構造物躯体Bを構築す
る。図中10は地下水である。
The present invention will be described below with reference to the illustrated embodiments. Soft ground A under the column where the load is concentrated in the structure
In addition, the pile hole 2 is excavated by the excavation bucket 1 using an earth drill machine or the like (see FIG. 1 (a)).
A rebar cage 5 with a bag made of a mesh sheet 4 or the like is attached to the rebar frame 3 and inserted. (See FIG. 1 (b)) Next, as shown in FIG. 1 (c), the reinforced concrete basket 5 with the bag is attached to the gravel 6
To build a gravel pile, and lay a gravel mat 7 (gravel mat) on the foundation. (Refer to FIG. 1D) Waste concrete is placed on the gravel mat 7 to construct the structure skeleton B in order from the pressure plate 8, the underground beam 9 and the foundation. In the figure, 10 is groundwater.

【0009】図示の実施例は前記したように構成されて
いるので、軟弱粘性土地盤においては、地盤改良杭以外
の部分が沈下すると、地盤改良杭に荷重が集中し、その
結果、砂利杭より構成された地盤改良杭が横方向にふく
れて、再び全体的に直接基礎として働く。以上の繰り返
しによって、軟弱地盤Aは徐々に安定していく。
Since the illustrated embodiment is constructed as described above, in the soft and viscous ground, when the parts other than the ground improvement piles sink, the load concentrates on the ground improvement piles, and as a result, it is better than the gravel piles. The constructed soil improvement pile swells in the lateral direction and again acts as a direct foundation as a whole. By repeating the above, the soft ground A gradually becomes stable.

【0010】一方、砂地盤の液状化に対しては、一時的
に地盤が液状化しても、メッシュシート4で包覆された
砂利杭が自立すると同時に、間隙水圧を消散させるた
め、同砂利杭はドレーンの働きを兼ね、液状化防止の働
きもする。図中Cは液状化しない安定化した地層であ
る。
On the other hand, with respect to the liquefaction of sand ground, even if the ground is liquefied temporarily, the gravel pile covered with the mesh sheet 4 becomes self-supporting and, at the same time, the pore water pressure is dissipated. Acts as a drain and also acts as a liquefaction prevention. C in the figure is a stabilized stratum that does not liquefy.

【0011】[0011]

【発明の効果】本発明に係る地盤改良杭は前記したよう
に、構造物の柱下に造成された太径の砂利杭の外周面
を、メッシュシートの如き所要の強度と耐久性を有する
材料で包覆して構成されているので、軟弱な粘性土地盤
では柱下の地盤改良杭をある程度安定した地盤まで下げ
ることによって沈下を抑え、不同沈下も少なくできる。
また本発明の地盤改良杭は砂利杭で構成されているの
で、応力集中が生じると杭の沈下が生じ、応力の再配分
ができる。
As described above, the ground improvement pile according to the present invention is made of a material having a required strength and durability such as a mesh sheet on the outer peripheral surface of a large-diameter gravel pile formed under a pillar of a structure. Since it is constructed by covering with, the soft clay ground can suppress the settlement by lowering the ground improvement pile under the pillar to a certain level of the ground, and the uneven settlement can be reduced.
Further, since the ground improvement pile of the present invention is composed of gravel piles, when stress concentration occurs, sinking of the pile occurs and stress can be redistributed.

【0012】更にまたゆるい砂地盤では、地震時に同地
盤が液状化しても、本発明の地盤改良杭を構成する砂利
杭がしっかりと自立しているので構造物の傾動、転倒が
生じない。また地震がおさまって沈下が生じたら、前記
砂利杭も変形して直接基礎に戻る。
Further, in the loose sand ground, even if the ground soil is liquefied in the event of an earthquake, the gravel pile forming the ground improvement pile of the present invention is firmly self-supporting so that the structure does not tilt or fall. When the earthquake subsides and subsidence occurs, the gravel pile will also be deformed and directly return to the foundation.

【図面の簡単な説明】[Brief description of drawings]

【図1】(イ)(ロ)(ハ)(ニ)は本発明に係る地盤
改良杭の施工工程を示す縦断面図である。
1 (a), (b), (c), and (d) are vertical cross-sectional views showing a process of constructing a soil improvement pile according to the present invention.

【図2】前記地盤改良杭を使用した構造物の基礎部縦断
面図である。
FIG. 2 is a vertical sectional view of a foundation portion of a structure using the ground improvement pile.

【図3】(イ)(ロ)(ハ)(ニ)は図3の構造物の各
基礎杭の平断面図である。
3 (a), (b), (c), and (d) are plan sectional views of each foundation pile of the structure of FIG.

【符号の説明】[Explanation of symbols]

A 軟弱地盤 B 構造物躯体 C 安定化した地層 1 掘削バケット 2 杭孔 3 鉄筋フレーム 4 メッシュシート 5 鉄筋篭 6 砂利 7 砂利のマット 8 耐圧版 9 地中梁 10 地下水 A Soft ground B Structure frame C Stabilized formation 1 Drilling bucket 2 Pile hole 3 Reinforcing frame 4 Mesh sheet 5 Reinforcing bar cage 6 Gravel 7 Gravel mat 8 Pressure plate 9 Underground beam 10 Groundwater

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 構造物の柱下に造成された太径の砂利杭
の外周面を、所要の強度と耐久性を有する材料で包覆し
てなることを特徴とする地盤改良杭。
1. A soil improvement pile, characterized in that the outer peripheral surface of a large-diameter gravel pile formed under a pillar of a structure is covered with a material having required strength and durability.
【請求項2】 前記砂利杭の外周面をメッシュシートで
包覆してなる請求項1記載の地盤改良杭。
2. The ground improvement pile according to claim 1, wherein an outer peripheral surface of the gravel pile is covered with a mesh sheet.
JP8202693A 1993-04-08 1993-04-08 Soil improvement pile Pending JPH06294136A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8202693A JPH06294136A (en) 1993-04-08 1993-04-08 Soil improvement pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8202693A JPH06294136A (en) 1993-04-08 1993-04-08 Soil improvement pile

Publications (1)

Publication Number Publication Date
JPH06294136A true JPH06294136A (en) 1994-10-21

Family

ID=13763023

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8202693A Pending JPH06294136A (en) 1993-04-08 1993-04-08 Soil improvement pile

Country Status (1)

Country Link
JP (1) JPH06294136A (en)

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030012449A (en) * 2001-08-01 2003-02-12 원 회 양 Method of construction for filling up concrete by using the sack for foundation of fabric in under the water.
JP4915827B1 (en) * 2011-07-01 2012-04-11 グラウンドシステム株式会社 Ground strengthening system and ground strengthening method
JP5011456B1 (en) * 2012-02-07 2012-08-29 グラウンドシステム株式会社 Ground liquefaction prevention and strengthening method
CN102704462A (en) * 2012-06-28 2012-10-03 中铁十六局集团第五工程有限公司 Composite treatment grouped piles for soft foundation
CN102828498A (en) * 2012-05-10 2012-12-19 湖南大学 Method for constructing gravel pile of hoop of immersed tube for reinforcing soft foundation
CN103046574A (en) * 2013-01-28 2013-04-17 中国水电顾问集团西北勘测设计研究院 Four-leaf-clover-type concrete bearing platform and prestressed pipe foundation structure of soft foundation fan
CN103243702A (en) * 2013-05-07 2013-08-14 中化二建集团有限公司 Sand wrapped gravel pile construction method
JP2013167144A (en) * 2012-01-16 2013-08-29 Grape Co Ltd Foundation structure and construction method for foundation
JP2013185338A (en) * 2012-03-07 2013-09-19 Kentec Inc Ground reinforcement pile
JP2013221310A (en) * 2012-04-16 2013-10-28 Grape Co Ltd Foundation structure and method for constructing foundation
JP2014077307A (en) * 2012-10-12 2014-05-01 Grape Co Ltd Foundation structure and foundation construction method
CN103966996A (en) * 2013-01-25 2014-08-06 深圳市勘察测绘院有限公司 Gravel pile and manufacturing method thereof
JP2014141785A (en) * 2013-01-22 2014-08-07 Grape Co Ltd Foundation structure
JP2014148865A (en) * 2013-02-04 2014-08-21 Grape Co Ltd Foundation structure
CN104612127A (en) * 2015-01-30 2015-05-13 唐山工业职业技术学院 Three-dimensional deep soft soil composite foundation and construction method
JP2015168944A (en) * 2014-03-05 2015-09-28 株式会社竹中工務店 Foundation structure of building
JP2017150267A (en) * 2016-02-26 2017-08-31 サムシングホールディングス株式会社 Crushed stone pile
CN109162270A (en) * 2018-10-26 2019-01-08 中铁二十局集团第工程有限公司 A kind of soft soil foundation reinforcing method based on the concrete-cored stake of cement concrete
CN109440757A (en) * 2018-11-30 2019-03-08 长沙恒德岩土工程技术有限公司 A kind of foundation reinforcement method for karst region
CN110984118A (en) * 2019-11-29 2020-04-10 中铁二十一局集团有限公司 Loess stratum road bridge foundation treatment method

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030012449A (en) * 2001-08-01 2003-02-12 원 회 양 Method of construction for filling up concrete by using the sack for foundation of fabric in under the water.
JP4915827B1 (en) * 2011-07-01 2012-04-11 グラウンドシステム株式会社 Ground strengthening system and ground strengthening method
JP2013167144A (en) * 2012-01-16 2013-08-29 Grape Co Ltd Foundation structure and construction method for foundation
JP5011456B1 (en) * 2012-02-07 2012-08-29 グラウンドシステム株式会社 Ground liquefaction prevention and strengthening method
JP2013185338A (en) * 2012-03-07 2013-09-19 Kentec Inc Ground reinforcement pile
JP2013221310A (en) * 2012-04-16 2013-10-28 Grape Co Ltd Foundation structure and method for constructing foundation
CN102828498A (en) * 2012-05-10 2012-12-19 湖南大学 Method for constructing gravel pile of hoop of immersed tube for reinforcing soft foundation
CN102704462A (en) * 2012-06-28 2012-10-03 中铁十六局集团第五工程有限公司 Composite treatment grouped piles for soft foundation
JP2014077307A (en) * 2012-10-12 2014-05-01 Grape Co Ltd Foundation structure and foundation construction method
JP2014141785A (en) * 2013-01-22 2014-08-07 Grape Co Ltd Foundation structure
CN103966996A (en) * 2013-01-25 2014-08-06 深圳市勘察测绘院有限公司 Gravel pile and manufacturing method thereof
CN103046574A (en) * 2013-01-28 2013-04-17 中国水电顾问集团西北勘测设计研究院 Four-leaf-clover-type concrete bearing platform and prestressed pipe foundation structure of soft foundation fan
JP2014148865A (en) * 2013-02-04 2014-08-21 Grape Co Ltd Foundation structure
CN103243702A (en) * 2013-05-07 2013-08-14 中化二建集团有限公司 Sand wrapped gravel pile construction method
JP2015168944A (en) * 2014-03-05 2015-09-28 株式会社竹中工務店 Foundation structure of building
CN104612127A (en) * 2015-01-30 2015-05-13 唐山工业职业技术学院 Three-dimensional deep soft soil composite foundation and construction method
JP2017150267A (en) * 2016-02-26 2017-08-31 サムシングホールディングス株式会社 Crushed stone pile
CN109162270A (en) * 2018-10-26 2019-01-08 中铁二十局集团第工程有限公司 A kind of soft soil foundation reinforcing method based on the concrete-cored stake of cement concrete
CN109440757A (en) * 2018-11-30 2019-03-08 长沙恒德岩土工程技术有限公司 A kind of foundation reinforcement method for karst region
CN110984118A (en) * 2019-11-29 2020-04-10 中铁二十一局集团有限公司 Loess stratum road bridge foundation treatment method

Similar Documents

Publication Publication Date Title
JPH06294136A (en) Soil improvement pile
KR100964796B1 (en) Method for constructing the steel pipe-concrete composite pile structurized of burying and unifying into the bedrock, and a pile construction
CN100564700C (en) The job practices of lattice type steel column tower crane pedestal
JP4575800B2 (en) Embankment reinforcement structure and reinforcement method
JP3126896B2 (en) Restoration method for uneven settlement structures
KR100313721B1 (en) Method for designing synthetic underground retaining wall by temporary soil protection structure and working process of underground retaining wall of structure
KR100376590B1 (en) Multi-phased underground construction method for wide excavation using permanent structural members as temporary struts
JPH02232416A (en) Foundation pile structure
JP2005016196A (en) Construction method for embankment on backside of substructure
JPS62260919A (en) Small pile for reinforcing foundation ground to earthquake
CN212642730U (en) Collapsible loess area tunnel passes people's air defense structure
JP2651893B2 (en) Foundation pile structure
JP4502442B2 (en) Seismic foundation, seismic building, and pile reinforcement method
KR101020217B1 (en) rock construction structure of using anchor and method thereof
JPH1129927A (en) Ground subsidence preventive foundation pile using old tire block
JP3767710B2 (en) Foundation structure of the building
JPH0617414A (en) Drainage reinforcement pile
JP3780191B2 (en) Building construction method
JPH01226921A (en) Earthquake-proof reinforced revetment construction
JP3614587B2 (en) How to install a shaft in the groundwater under pressure
JP2022091053A (en) Reinforcement body of earth retaining wall, and installation method of reinforcement body
GB2232701A (en) Mini-piled retaining wall and a method for its construction
CN213143125U (en) Yielding and vibration damping composite structure of open-cut tunnel
JP2011043047A (en) Improved/reinforced structure of existing gravity type quay
JPH0886117A (en) Building installation method