JPH06185084A - Basement floor body structure of building - Google Patents

Basement floor body structure of building

Info

Publication number
JPH06185084A
JPH06185084A JP4334401A JP33440192A JPH06185084A JP H06185084 A JPH06185084 A JP H06185084A JP 4334401 A JP4334401 A JP 4334401A JP 33440192 A JP33440192 A JP 33440192A JP H06185084 A JPH06185084 A JP H06185084A
Authority
JP
Japan
Prior art keywords
columns
basement
floor
construction
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP4334401A
Other languages
Japanese (ja)
Other versions
JP2605563B2 (en
Inventor
Hiroshi Katsumata
浩 勝間田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP4334401A priority Critical patent/JP2605563B2/en
Publication of JPH06185084A publication Critical patent/JPH06185084A/en
Application granted granted Critical
Publication of JP2605563B2 publication Critical patent/JP2605563B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To reduce the period and cost of a constitution employing the reverse placing process. CONSTITUTION:Girders 2 below the first floor are made of steel structure (S made) and columns are made of RC having a permanent substructure column 3 (temporary post) in the inside. The girders 2 made of S are connected to the column with high-tension bolts. The floor slab 7 is placed by a construction method without use of posts. And also construction works such as forms of beam, bar arrangement erection of struts supporting forms for placing concrete and floor slabs, reinforcement of the ground for posts, are not necessary. Moreover, the joint work of the girder 2 made S and the structural post 3 is simplified.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、建築物の地階におけ
る架構等の躯体構造(逆打工法で築造する地階躯体)に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a frame structure such as a frame in a basement of a building (a basement frame constructed by a reverse driving method).

【0002】[0002]

【従来の技術およびこの発明が解決しようとする課題】
従来、この種の地階の躯体構造としては、逆打工法を採
用する工事においても、鉄筋コンクリート造(RC造)
や鉄骨鉄筋コンクリート造(SRC造)を採用するケー
スが多い。
Prior Art and Problems to be Solved by the Invention
Conventionally, as the structure of the basement structure of this type, reinforced concrete construction (RC construction) is used even in the construction employing the reverse driving method.
Steel reinforced concrete construction (SRC construction) is often adopted.

【0003】しかし、地階の躯体構造をRC造やSRC
造にすると、長い工期と高い工事費とを必要とすること
になる。
However, the base structure of the basement is made of RC or SRC.
The construction requires a long construction period and high construction cost.

【0004】この発明は前述した事情に鑑みて創案され
たもので、その目的は逆打工法を採用した工事の工期短
縮とコスト低減とを図ることができる建築物の地階躯体
構造を提供することにある。
The present invention was devised in view of the above-mentioned circumstances, and an object thereof is to provide a basement structure structure for a building which can reduce the construction period and cost of the construction employing the reverse driving method. It is in.

【0005】[0005]

【課題を解決するための手段】この発明の地階躯体構造
によれば、1階以下の大梁を鉄骨造(S造)とし、柱を
構真柱(仮設柱)を内蔵したRC造とする。また、S造
の大梁は構真柱に高力ボルト接合とする(取り合いは構
真柱付きのガセットプレートと大梁のウエブプレー
ト)。さらに、床スラブは支柱不要の工法を採用する。
According to the basement skeleton structure of the present invention, the large beams below the first floor are made of steel frame (S) and the pillars are made of RC having built-in true pillars (temporary pillars). In addition, the S-structured girders are joined to the true columns with high-strength bolts (as for the gusset plate with the true columns and the web plate of the girders). In addition, the floor slab will be constructed without columns.

【0006】そして、このような地階躯体構造とするこ
とにより、梁の型枠工事や配筋工事およびコンクリート
工事を不要とする。また、床スラブの型枠を支えるため
の支柱を立てる工事や支柱を支える地盤を補強する工事
を不要とする。さらに、S造の大梁と構真柱の接合工事
を簡略化することができるようにしたものである。
[0006] By adopting such a basement skeleton structure, beam formwork, bar arrangement work and concrete work are unnecessary. In addition, it is not necessary to construct a pillar to support the formwork of the floor slab or to reinforce the ground supporting the pillar. Further, it is possible to simplify the work of joining the S-structured large beam and the true column.

【0007】[0007]

【実施例】以下、この発明の建築物における地階躯体構
造を、図示する実施例によって説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The basement structure of a building according to the present invention will be described below with reference to the illustrated embodiments.

【0008】建物4における地階躯体構造1(図1〜図
5参照)は、1階以下の大梁2を鉄骨造とすると共に、
柱を構真柱3(仮設柱)が内蔵されている鉄筋コンクリ
ート造とし、鉄骨造の大梁2は構真柱3に、取り合いを
鉄骨柱付きのガセットプレート5と大梁のウエブプレー
ト6とした高力ボルト接合とし、床スラブ7は支柱不要
の工法を採用してなっている。
In the basement structure structure 1 (see FIGS. 1 to 5) of the building 4, the girders 2 below the first floor are made of steel frame and
The pillar is made of reinforced concrete with a built-in structure pillar 3 (temporary pillar), the steel-framed large beam 2 is the structure pillar 3, and the connection is a gusset plate 5 with a steel pillar and a web plate 6 of the large beam. The floor slab 7 is bolted, and a construction method that does not require columns is used.

【0009】このような構成からなる地階躯体構造1を
採用しての建物の施工は、次に述べるようにして行う。
Construction of a building employing the basement frame structure 1 having such a structure is carried out as follows.

【0010】先ず、場所打ちコンクリート杭8のコンク
リート打設直後(生コンクリートが固まらないうち)に
所定の位置に構真柱3を建てる。なお、この構真柱3に
は予め工場でガセットプレート5を取り付けておく。
First, immediately after the concrete is cast into the cast-in-place concrete pile 8 (while the ready-mixed concrete is not set), the true-column 3 is erected at a predetermined position. In addition, the gusset plate 5 is attached to the structure pillar 3 in advance at the factory.

【0011】次に、1次根切りの後、1階のS造大梁2
を構真柱3に取り付け、1階のスラブを施工する。な
お、取合方法は、構真柱取り付けのガセットプレート5
に、鉄骨梁のウエブプレート6を高力ボルト接合する。
Next, after the first root cutting, the S-shaped large beam 2 on the first floor
Is attached to the structure pillar 3 and the slab on the first floor is constructed. In addition, the mounting method is the gusset plate 5 of the true column mounting.
Then, the web plate 6 of the steel frame beam is bolted with high strength.

【0012】この高力ボルト接合におけるボルト孔は一
般的には円形であるが、構真柱3の建て入れ精度の悪さ
を考慮して、水平方向のルーズホールにする場合もあ
る。このルーズホールは、ガセットプレート5のみの場
合、鉄骨梁のみの場合、両方の場合がある。
The bolt hole in this high-strength bolt connection is generally circular, but it may be a loose hole in the horizontal direction in consideration of poor installation accuracy of the true column 3. This loose hole may be the case of only the gusset plate 5, the case of only the steel frame beam, or the case of both.

【0013】次に、2次根切りの後、地下1階のS造大
梁を構真柱3に取り付け、地下1階のスラブを施工す
る。なお、取合方法は前述したS造大梁2を構真柱3に
取り付ける時と同じである。
Next, after the secondary root cutting, the S-shaped large beam on the first basement floor is attached to the structure pillar 3, and the slab on the first basement floor is constructed. The joining method is the same as that used when the S-beams 2 are attached to the true columns 3 described above.

【0014】そして、地下が3階以上の場合も、前述し
た作業を繰り返す。また、構真柱3がH形鋼,角形の鋼
管,丸形の鋼管いずれの場合も、施工方法と、構真柱3
およびS造大梁の接合方法とは同じである。
Then, even when the basement is on the third floor or above, the above-mentioned work is repeated. In addition, regardless of whether the structure column 3 is H-shaped steel, square steel pipe, or round steel pipe, the construction method and the structure column 3
And the method of joining the S beam is the same.

【0015】[0015]

【発明の効果】この発明によれば、地階の躯体工事に要
する工期を大幅に短縮することができると共に、地階の
躯体工事に要する工費(コスト)を軽減することができ
る。また、型枠工事,配筋工事,コンクリート工事が大
幅に減少するので、現場作業員を少なくすることができ
る。
According to the present invention, the construction period required for the basement frame construction work can be significantly shortened and the construction cost (cost) required for the basement frame construction work can be reduced. Further, since the formwork, rebar work and concrete work are significantly reduced, it is possible to reduce the number of site workers.

【0016】さらに、建設廃棄物(特に使えなくなった
型枠材)が減少すると共に、現場に搬入する資材の量を
少なくすることができる。しかも、雨天の場合でも、土
の掘削工事や地階の躯体工事を行うことができる。
Further, the amount of construction waste (particularly, the mold material that cannot be used) is reduced, and the amount of material to be carried into the site can be reduced. Moreover, even in the case of rain, excavation work of soil and skeleton work of the basement can be performed.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明の地階躯体構造を示す概略図である。FIG. 1 is a schematic view showing a basement structure structure of the present invention.

【図2】図4のA部拡大図である。FIG. 2 is an enlarged view of part A in FIG.

【図3】図5のB−B線断面図である。3 is a sectional view taken along line BB of FIG.

【図4】この発明の地階躯体構造の別態様を示す概略図
である。
FIG. 4 is a schematic view showing another embodiment of the basement skeleton structure of the present invention.

【図5】図7のC−C線断面図である。5 is a cross-sectional view taken along the line CC of FIG.

【符号の説明】[Explanation of symbols]

1…地階躯体構造、2…大梁、3…構真柱、4…建物、
5…ガセットプレート、6…ウエブプレート、7…床ス
ラブ、8…場所打ちコンクリート杭。
1 ... Basement frame structure, 2 ... Large beam, 3 ... Structural column, 4 ... Building,
5 ... Gusset plate, 6 ... Web plate, 7 ... Floor slab, 8 ... Cast-in-place concrete pile.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 1階以下の大梁を鉄骨造とすると共に、
柱を構真柱(仮設柱)が内蔵されている鉄筋コンクリー
ト造とし、前記鉄骨造の大梁は構真柱に取付け、取り合
いは構真柱付きのガセットプレートと大梁のウエブプレ
ートとの高力ボルト接合とし、床スラブは支柱不要の工
法を採用してなることを特徴とする建築物の地階躯体構
造。
1. A girder below the first floor is made of steel frame,
The columns are made of reinforced concrete with built-in structure columns (temporary columns), the steel-framed large beams are attached to the structure columns, and the connection is a high-strength bolt connection between the gusset plate with the structure columns and the web plate of the beam. The floor slab has a basement structure of a building characterized by adopting a construction method that does not require columns.
JP4334401A 1992-12-15 1992-12-15 Basement structure of building Expired - Lifetime JP2605563B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4334401A JP2605563B2 (en) 1992-12-15 1992-12-15 Basement structure of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4334401A JP2605563B2 (en) 1992-12-15 1992-12-15 Basement structure of building

Publications (2)

Publication Number Publication Date
JPH06185084A true JPH06185084A (en) 1994-07-05
JP2605563B2 JP2605563B2 (en) 1997-04-30

Family

ID=18276957

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4334401A Expired - Lifetime JP2605563B2 (en) 1992-12-15 1992-12-15 Basement structure of building

Country Status (1)

Country Link
JP (1) JP2605563B2 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5864710U (en) * 1981-10-24 1983-05-02 株式会社クボタ Connection structure of built-in columns used for reverse pouring method
JPS61266732A (en) * 1985-05-20 1986-11-26 Shimizu Constr Co Ltd Reverse driving work

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5864710U (en) * 1981-10-24 1983-05-02 株式会社クボタ Connection structure of built-in columns used for reverse pouring method
JPS61266732A (en) * 1985-05-20 1986-11-26 Shimizu Constr Co Ltd Reverse driving work

Also Published As

Publication number Publication date
JP2605563B2 (en) 1997-04-30

Similar Documents

Publication Publication Date Title
JPH11100854A (en) Building and foundation structure therefor
JP2002030672A (en) Structure of joining foundation pile to pier base and method of constructing the structure
JPH082181Y2 (en) Foundation for steel structures
JPH06185084A (en) Basement floor body structure of building
JP3586121B2 (en) Mixed structure of reinforced concrete column and steel beam and its construction method
JPH06185085A (en) Basement floor body construction of building
JP2967530B2 (en) Basement building construction method
JP2000273880A (en) Pile head connecting method
JPH09296459A (en) Steel encased reinforced concrete
JP2775330B2 (en) How to rebuild buildings using steel columns
JPH07103583B2 (en) Construction method for large span underground structure
JPH0748847A (en) Steel frame column base section structure for building with underground floor and underground skeleton construction method
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPS61266732A (en) Reverse driving work
JPH0718681A (en) Connecting method for precast concrete pillar and foundation section
JP3138982B2 (en) Building with mixed structure and its construction method
JPH0868115A (en) Connecting structure for column/beam and construction method for underground skeleton using it
JPS6217233A (en) Foundation base column
JPH03253613A (en) Construction of earth retaining in excavated ground
JPH0376929A (en) Steel-framed foundation
JP2605484B2 (en) Steel construction method in building construction
JP2779346B2 (en) Building structure
JPH0886020A (en) Structural frame of building
JPH06287998A (en) Constructing method for preliminary assembling of reinforced concrete composite beam
JPH0841913A (en) Underground structure of building having no internal column at underground floor and below and its construction method

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19961203