JPH0718681A - Connecting method for precast concrete pillar and foundation section - Google Patents

Connecting method for precast concrete pillar and foundation section

Info

Publication number
JPH0718681A
JPH0718681A JP15888493A JP15888493A JPH0718681A JP H0718681 A JPH0718681 A JP H0718681A JP 15888493 A JP15888493 A JP 15888493A JP 15888493 A JP15888493 A JP 15888493A JP H0718681 A JPH0718681 A JP H0718681A
Authority
JP
Japan
Prior art keywords
foundation
section
pillar
column
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15888493A
Other languages
Japanese (ja)
Inventor
Satoshi Kobayakawa
敏 小早川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP15888493A priority Critical patent/JPH0718681A/en
Publication of JPH0718681A publication Critical patent/JPH0718681A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

PURPOSE:To provide a connection section reducing the execution cost and labor and having no structural weak point by extending a pillar leg section connected to a foundation section to a foundation bottom section, and chipping the concrete at the connection section to an underground beam. CONSTITUTION:After a pile B and the foundation work are completed, a precast concrete pillar A is erected at a prescribed position and temporarily fixed. A pillar leg section is extended to a foundation bottom section, thereby the fixing length of a pillar main reinforcement 1 to the foundation section is assured. The concrete of the pillar leg section connected to the foundation section on the precast concrete pillar A is chipped. The main reinforcement 5 of an underground beam is arranged in the pillar A via the chipping section 3. The auxiliary reinforcement 6 of the underground beam and a footing section are arranged, a formwork is assembled, then concrete is placed on the foundation section. The precast concrete pillar A and the foundation section are integrated at the same time.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はプレキャストコンクリー
ト柱(以下PC柱と称する)と基礎部の接合方法に係る
ものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for joining precast concrete columns (hereinafter referred to as PC columns) and foundations.

【0002】[0002]

【従来の技術】従来、PC柱と基礎部とを接合する際、
図4に示すように地中梁a及びフーチングよりなる基礎
部を施工する時点で柱主筋bを設置しておき、基礎部の
コンクリートを打設したのち、柱主筋接合用スリーブ金
物cを内蔵したPC柱dを建込み、同PC柱dのスリー
ブ金物cに前記柱主筋bを接合して同スリーブ金物cに
グラウトすることによってPC柱と基礎部とを接合して
いた。
2. Description of the Related Art Conventionally, when joining a PC pillar and a foundation,
As shown in FIG. 4, the pillar main bar b is installed at the time of constructing the foundation consisting of the underground beam a and the footing, the concrete of the foundation is placed, and then the column main bar joining sleeve metal c is built in. The PC pillar d is built in, the pillar main bar b is joined to the sleeve metal c of the PC pillar d, and the PC pillar and the foundation are joined by grouting.

【0003】図中eは捨コンクリート、fは杭である。In the figure, e is waste concrete and f is a pile.

【0004】[0004]

【発明が解決しようとする課題】前記従来技術において
は、予め基礎部に設置する柱主筋の位置精度を確保する
ため、多大の労力と費用を要する。また柱主筋接合用ス
リーブ金物及びグラウトに多大の費用を要する。更に柱
脚部にヒンジゾーンが発生する場合は、柱主筋の接合部
が構造上の弱点となる惧れがある。
In the above-mentioned prior art, a great deal of labor and cost are required in order to secure the positional accuracy of the column main bars installed in advance on the foundation part. Also, a large amount of cost is required for the column main joint sleeve hardware and grout. Further, when a hinge zone is generated in the column base, there is a possibility that the joint portion of the column main bar becomes a structural weak point.

【0005】本発明は前記従来技術の有する問題点に鑑
みて提案されたもので、その目的とする処は、施工性が
向上され、経済性に優れ、構造上、合理的なPC柱と基
礎部の接合方法を提供する点にある。
The present invention has been proposed in view of the problems of the above-mentioned prior art. The object of the present invention is to improve the workability, excel in economic efficiency, and structurally rational PC columns and foundations. The point is to provide a method of joining the parts.

【0006】[0006]

【課題を解決するための手段】前記の目的を達成するた
め、本発明に係るPC柱と基礎部の接合方法によれば、
基礎部と接合する柱脚部を基礎底部まで延設するととも
に、地中梁との取合い部のコンクリートを欠截してなる
プレキャストコンクリート柱を基礎部に建て込んだの
ち、地中梁及びフーチング部の配筋をして、基礎部のコ
ンクリートを打設するものである。
In order to achieve the above-mentioned object, according to the method of joining a PC column and a base portion according to the present invention,
After extending the column base that joins with the foundation to the bottom of the foundation and building a precast concrete column that lacks the concrete at the part where the underground beam is connected, the underground beam and footing part. The reinforcement of concrete is done and the concrete of the foundation is poured.

【0007】[0007]

【作用】本発明によれば前記したように、PC柱の柱脚
部が基礎底部まで延設され、前記PC柱の柱主筋の基礎
部に対する定着長さが確保されるとともに、PC柱を建
て込む際、自立させることができる。また前記PC柱に
おける基礎部と接合する柱脚部のコンクリートが欠截さ
れているので、同欠截部を介して地中梁主筋を柱内に配
筋することが可能となり、基礎部のコンクリートを打設
することによって、PC柱と基礎部とが一体化される。
According to the present invention, as described above, the column base of the PC column is extended to the bottom of the foundation, the fixing length of the main column of the PC column to the foundation is secured, and the PC column is built. Can be self-reliant when plugged in. Further, since the concrete of the column base portion that joins with the foundation portion of the PC column is cut off, it becomes possible to arrange the main reinforcement of the underground beam in the column through the cutout portion, and the concrete of the foundation part The PC pillar and the base portion are integrated by driving.

【0008】[0008]

【実施例】以下本発明を図示の実施例について説明す
る。Aは中空のPC柱で柱主筋1及び柱帯筋2が内蔵さ
れ、基礎部と取合う柱脚部のコンクリートが欠截され、
同欠截部3に前記柱主筋1及び柱帯筋2の一部が露出し
ている。図中4は中空部である。
The present invention will be described below with reference to the illustrated embodiments. A is a hollow PC column in which the column main reinforcement 1 and the column sill 2 are built in, and the concrete of the column base portion which is compatible with the foundation is deleted.
Part of the column main bar 1 and the column ridge bar 2 is exposed in the same cutout portion 3. In the figure, 4 is a hollow part.

【0009】杭B及び地業終了後、前記PC柱Aを所定
位置に建て込み、支柱、ワイヤー等を用いて仮固定す
る。次いで地中梁の主筋5及び肋筋6並にフーチング部
の配筋を行い、続いて型枠7を組み立てたのち柱脚部と
同時に基礎部のコンクリートを打設する。かくして前記
PC柱Aの欠截部3を介してPC柱Aと基礎部とが一体
化される。図中、8は捨コンクリートである。
After the pile B and the earthwork are finished, the PC pillar A is built in a predetermined position and temporarily fixed by using a pillar, a wire and the like. Next, the footing portion is laid out along with the main reinforcements 5 and the ribs 6 of the underground beam, and then the formwork 7 is assembled and then the concrete of the foundation is placed at the same time as the column base. Thus, the PC pillar A and the base portion are integrated with each other through the cutout portion 3 of the PC pillar A. In the figure, 8 is waste concrete.

【0010】なお中空PC柱の場合、柱頭部よりコンク
リートを打設することもでき、また、柱断面形状は角
形、円形でもよい。
In the case of a hollow PC column, concrete can be poured from the column head, and the column cross section may be square or circular.

【0011】[0011]

【発明の効果】本発明は前記したように、PC柱が基礎
部と接合する柱脚部を基礎底部まで延設し、地中梁との
取合い部を欠截して構成されていて、前記PC柱を基礎
部に建て込んで地中梁及びフーチング部の配筋をして基
礎部のコンクリートを打設し、同基礎部とPC柱とが同
PC柱の欠截部を介して一体化されるものであって、本
発明によれば、予め基礎部に柱主筋を設置することがな
いので、同鉄筋の配筋のための労務及び費用が不要とな
り、また主筋接合用スリーブ金物及びグラウトの費用が
不要となる。更に柱脚部での主筋の接合部が位置しない
ので、同接合部に基因する構造上の弱点が生じる惧れが
ない。
As described above, the present invention is constructed by extending the column base portion where the PC column is joined to the foundation portion to the bottom portion of the foundation and omitting the connection portion with the underground beam. The PC pillar is built in the foundation, the underground beams and footing are laid out, and the concrete of the foundation is placed. The foundation and the PC pillar are integrated through the cutouts of the PC pillar. According to the present invention, since the column main bar is not installed in the foundation in advance, labor and cost for arranging the reinforcing bar are unnecessary, and the sleeve metal for connecting the main bar and the grout are unnecessary. The cost of will be unnecessary. Furthermore, since the joint of the main muscles at the column base is not located, there is no fear that structural weakness due to the joint will occur.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係るPC柱と基礎部の接合方法の実施
状況を示す縦断面図である。
FIG. 1 is a vertical cross-sectional view showing an implementation state of a method for joining a PC column and a base portion according to the present invention.

【図2】図1の横断平面図である。2 is a cross-sectional plan view of FIG.

【図3】PC柱の斜視図である。FIG. 3 is a perspective view of a PC column.

【図4】従来方法の実施状況を示す正面図である。FIG. 4 is a front view showing an implementation status of a conventional method.

【符号の説明】[Explanation of symbols]

A PC柱 B 杭 1 柱主筋 2 柱帯筋 3 欠截部 4 中空部 5 地中梁の主筋 6 地中梁の肋筋 7 型枠 8 捨コンクリート A PC Column B Piles 1 Column main bar 2 Column girder 3 Missing part 4 Hollow part 5 Main beam of underground beam 6 Ribs of underground beam 7 Formwork 8 Waste concrete

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 基礎部と接合する柱脚部を基礎底部まで
延設するとともに、地中梁との取合い部のコンクリート
を欠截してなるプレキャストコンクリート柱を基礎部に
建て込んだのち、地中梁及びフーチング部の配筋をし
て、基礎部のコンクリートを打設することを特徴とする
プレキャストコンクリート柱と基礎部の接合方法。
1. A precast concrete column formed by extending a column base portion connecting to a foundation to the bottom of the foundation and removing concrete in an area where an underground beam is connected to the foundation, A method of joining a precast concrete column and a foundation, which comprises placing concrete in the foundation by arranging the center beam and footing.
JP15888493A 1993-06-29 1993-06-29 Connecting method for precast concrete pillar and foundation section Pending JPH0718681A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15888493A JPH0718681A (en) 1993-06-29 1993-06-29 Connecting method for precast concrete pillar and foundation section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15888493A JPH0718681A (en) 1993-06-29 1993-06-29 Connecting method for precast concrete pillar and foundation section

Publications (1)

Publication Number Publication Date
JPH0718681A true JPH0718681A (en) 1995-01-20

Family

ID=15681495

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15888493A Pending JPH0718681A (en) 1993-06-29 1993-06-29 Connecting method for precast concrete pillar and foundation section

Country Status (1)

Country Link
JP (1) JPH0718681A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007270455A (en) * 2006-03-30 2007-10-18 Maeda Corp Precast column manufacturing method and precast column erection method
JP2015048686A (en) * 2013-09-04 2015-03-16 鹿島建設株式会社 Joint structure, and construction method for joint structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007270455A (en) * 2006-03-30 2007-10-18 Maeda Corp Precast column manufacturing method and precast column erection method
JP2015048686A (en) * 2013-09-04 2015-03-16 鹿島建設株式会社 Joint structure, and construction method for joint structure

Similar Documents

Publication Publication Date Title
JP3671344B2 (en) Joint structure between foundation pile and column base and its construction method
JPH0718681A (en) Connecting method for precast concrete pillar and foundation section
JP2000160687A (en) Construction method for composite structure and precast concrete column
JPH10299003A (en) Foundation work using precast concrete member
JP2520364B2 (en) Construction method of underground structure
JPH06316964A (en) Method for constructing joint of precast reinforced concrete column and beam
JPH1162247A (en) Construction method for building skeleton utilizing existing foundation slab
JP2000273880A (en) Pile head connecting method
JP2763488B2 (en) Prefabricated pillar and inverted ramen prefabricated construction method
JPH0452815B2 (en)
JPH10131300A (en) Execution method for building by preceding erection of steel frame
JPH0376929A (en) Steel-framed foundation
JP2537053B2 (en) Digging pillar pile method of building
JPH0410935B2 (en)
JP2775330B2 (en) How to rebuild buildings using steel columns
JPH02274917A (en) Construction engineering method of basement floor
JP2002115324A (en) Column base unit, column integrated column base fixing foundation structure using the column base unit, and construction method therefor
JPS61266732A (en) Reverse driving work
JPH0754355A (en) Foundation for small-scale building
JPH04237731A (en) Constructing method for rc pillar with core reinforcement bar
JPH1113015A (en) Arch slab type viaduct, and its execution method
JPH05112947A (en) Execution method of foundation
JPH05112949A (en) Execution method of foundation
JPH0718671A (en) Execution method for pile draft foundation utilizing existing foundation
JPH03132521A (en) Strut construction method of basement floor excavation work