JPH06173459A - Beam member mounting method - Google Patents

Beam member mounting method

Info

Publication number
JPH06173459A
JPH06173459A JP35214992A JP35214992A JPH06173459A JP H06173459 A JPH06173459 A JP H06173459A JP 35214992 A JP35214992 A JP 35214992A JP 35214992 A JP35214992 A JP 35214992A JP H06173459 A JPH06173459 A JP H06173459A
Authority
JP
Japan
Prior art keywords
girder
pier
piers
yard
beam member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP35214992A
Other languages
Japanese (ja)
Other versions
JP3138949B2 (en
Inventor
Souji Kanai
壮次 金井
Setsuo Kamijo
節夫 上條
Mineo Kobayashi
峯男 小林
Masayuki Okochi
政之 大河内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP04352149A priority Critical patent/JP3138949B2/en
Publication of JPH06173459A publication Critical patent/JPH06173459A/en
Application granted granted Critical
Publication of JP3138949B2 publication Critical patent/JP3138949B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE:To install a beam member without causing obstruction for vehicles in traffic under the same. CONSTITUTION:Bridge piers 31 are installed in a position confronting the site where a planned building is to be constructed, and an assembly yard is installed on the side opposite the planned place for one of the piers 31, and a support gate 42 fixed with a ground anchor 43 is installed on the oversurface of the assembly yard. Through this support gate 42, a girder 11 is moved toward the mating pier 31 from upon the assembly yard, and the foremost extremity of another girder 11 to be moved next is coupled with the tail of the girder 11 using a coupling tool. The girder 11 is set on the piers 31 on both sides, and the coupling tool is removed, and the set girder is moved along the piers 31.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、軌道や道路などの上方
に構築する建設物の梁部材の架設方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a beam member of a construction constructed above a track, a road or the like.

【0002】[0002]

【従来の技術】従来、軌道や道路などの交通機関上を跨
いで、この交通機関上に建設物を構築する場合、構築予
定位置の近辺に大型クレーンなどを配置し建設物部材を
移送して、建設物を構築していた。
2. Description of the Related Art Conventionally, when constructing a construction on a transportation facility such as a track or a road, a large crane or the like is placed near the planned construction position to transfer the construction material. , Was building a construction.

【0003】[0003]

【発明が解決しようとする問題点】前記した従来の構築
方法にあっては、建設物の構築予定場所が軌道や道路な
どの交通機関の上方に位置し、その構築予定場所の周辺
がビルなどに囲まれている場合、大型クレーンなどを配
置する場所が確保することが困難である。このような状
況においては、交通機関を一定期間閉鎖して建設物の構
築を行わなくてはならない。
In the conventional construction method described above, the planned construction site is located above a transportation system such as a track or a road, and the area around the planned construction site is a building or the like. When surrounded by, it is difficult to secure a place to place a large crane. In such a situation, transportation must be closed for a certain period to construct the building.

【0004】[0004]

【本発明の目的】本発明は以上の問題を解決するために
成されたもので、その目的とするところは、下方を往来
する交通機関に支障を来たすことなく行える梁部材の架
設方法を提供することにある。
SUMMARY OF THE INVENTION The present invention has been made to solve the above problems, and an object of the present invention is to provide a method of constructing a beam member that can be carried out without obstructing a transportation system passing below. To do.

【0005】[0005]

【問題点を解決するための手段】本発明は、建築物の構
築予定地を挟んで対向する位置に橋脚を設置し、一方の
該橋脚の構築予定地の反対側に組立ヤードを設置し、該
組立ヤードの上面にはグラウンドアンカーで固定された
支持門が設置され、組立ヤード上から前記支持門内を通
して、対向する橋脚に向けて桁を移動させ、該桁の後端
に連結具により次に移動する桁の先端を連結させ、桁を
両側の橋脚上に架設した後、前記連結具を取り外し、架
設した桁を橋脚に沿って移動させて行う梁部材の架設方
法である。また本発明は、各橋脚の外側に組立ヤードを
設置し、各組立ヤードから対向する橋脚に向けて桁を移
動させ、各橋脚のほぼ中央で各桁を連結して行うこと特
徴とする上記に記載の梁部材の架設方法である。
According to the present invention, bridge piers are installed at positions facing each other across a planned construction site of a building, and an assembly yard is installed on the opposite side of the planned construction site of one of the piers. A support gate fixed by a ground anchor is installed on the upper surface of the assembly yard, and the girder is moved from above the assembly yard through the support gate toward the opposite pier, and then connected to the rear end of the girder by a connecting tool. This is a method of constructing a beam member, in which the ends of the moving girders are connected to each other, the girders are installed on the bridge piers on both sides, the connecting tool is removed, and the installed girders are moved along the bridge piers. Further, the present invention is characterized in that an assembly yard is installed outside each pier, the girder is moved from each assembly yard toward the opposite pier, and each girder is connected approximately at the center of each pier. It is the method of constructing the beam member described.

【0006】[0006]

【実施例1】以下図面を参照しながら建設物における桁
の架設方法について説明する。 <イ>橋脚及び作業台の構築(図1、図2) ビル51に囲まれた線路22の両脇に線路22に沿って
橋脚31及び32を構築する。この橋脚31及び32
は、例えば鉄筋コンクリートで形成する。橋脚31及び
32の高さは、往来する電車21の架線の高さ以上に設
定する。橋脚31上面で後述する作業台41の延長位置
に支承車輪32を設置する。ビル51間の狭い場所を利
用し、橋脚31に隣接させて作業台41を構築する。
作業台41は、建設物の基礎部材となる桁11の組み立
て又は送り出しを行う場所であり、前記橋脚31の上面
と同じ高さに構築する。作業台41の上面に支持門42
を設置する。支持門42は、図2に示す様に、作業台4
1から送り出された桁11の後方が浮上しないよう支持
する部位である。この支持門42は、門型の形状を呈し
ており、橋脚32の方向に開口した向きに設置される。
支持門42の上端面から下方の地中に向けてグラウンド
アンカー43を打設して支持門42を固定する。このグ
ラウンドアンカー43により、桁11の浮上に対する支
持耐力を十分に確保できる。支持門42の内面には、支
持車輪45を設置する。また、作業台41の上面に支承
車輪44を設置する。
[Embodiment 1] A method of constructing a girder in a building will be described below with reference to the drawings. <A> Construction of bridge pier and work platform (FIGS. 1 and 2) Pier 31 and 32 are constructed along the track 22 on both sides of the track 22 surrounded by the building 51. This pier 31 and 32
Is formed of, for example, reinforced concrete. The height of the bridge piers 31 and 32 is set to be higher than the height of the overhead line of the train 21 which is coming and going. The support wheels 32 are installed on the upper surface of the pier 31 at extended positions of a workbench 41 described later. A work table 41 is constructed adjacent to the pier 31 using a narrow space between the buildings 51.
The workbench 41 is a place for assembling or sending out the girder 11 which is a foundation member of the building, and is constructed at the same height as the upper surface of the pier 31. A support gate 42 is provided on the upper surface of the workbench 41.
Set up. The support gate 42, as shown in FIG.
This is a part that supports the rear of the girder 11 sent out from No. 1 so as not to float. The support gate 42 has a gate shape, and is installed in a direction of opening toward the pier 32.
The ground anchor 43 is driven from the upper end surface of the support gate 42 toward the ground below to fix the support gate 42. With this ground anchor 43, it is possible to sufficiently secure the supporting strength against the floating of the girder 11. Support wheels 45 are installed on the inner surface of the support gate 42. In addition, support wheels 44 are installed on the upper surface of the workbench 41.

【0007】<ロ>桁の組立及び送り出し(図2) 作業台41上で桁11aの組み立てを行う。桁11a
は、構築する建設物の基礎として構成する鉄骨部材であ
る。組み立てながら桁11aの先端を支持門42内に挿
通し、さらに支承車輪32上に移動させて、徐々に桁1
1aを橋脚32に向けて送り出す。桁11aを半分以上
送り出し、桁11aの重心が支承車輪32を越えると、
桁11aの先端が下方に向く。この時、桁11aの後端
は支持門42内の支持車輪43で上方から支持されるの
で、桁11aを水平に送り出し続けることができる。ま
た、支持門42をグラウンドアンカー43で固定してい
るので、支持門42が引き抜けることはない。ある程度
桁11aを送り出して空いた作業台41上で次に送り出
す桁11bを組み立てる。そして、桁11aの後端に桁
11bの先端を連結具12で連結する。この状態で、桁
11aが橋脚32に到達するまで送り出す。この時、桁
11aの後端は支持門42を通過してしまうが、連結し
た桁11bの重量と桁11bの支持門42による支持と
により、桁11aを水平を維持して送り出し続けること
ができる。桁11の送り出しは、支持車輪43又は支承
車輪32をモータなどの駆動源により駆動する様に構成
し、支持車輪43又は支承車輪32に回転力を付与して
行う。尚、この送り出しの方法については、桁11の後
方からジャッキにより押し出すなどのその他公知の方法
で行っても良い。
<B> Assembly and delivery of girder (FIG. 2) The girder 11a is assembled on the work table 41. Digit 11a
Is a steel frame member that is configured as a basis of a building to be constructed. While assembling, insert the tip of the girder 11a into the support gate 42, and move it further onto the support wheels 32 to gradually move the girder 1a.
1a is sent toward the pier 32. When the girder 11a is sent out more than half and the center of gravity of the girder 11a exceeds the bearing wheels 32,
The tip of the girder 11a faces downward. At this time, since the rear end of the girder 11a is supported from above by the support wheels 43 in the support gate 42, the girder 11a can be continuously fed horizontally. Further, since the support gate 42 is fixed by the ground anchor 43, the support gate 42 does not pull out. The girder 11b is sent out to some extent, and the girder 11b to be sent out next is assembled on the vacant work table 41. Then, the tip of the girder 11b is connected to the rear end of the girder 11a by the connecting tool 12. In this state, the girder 11a is fed until it reaches the pier 32. At this time, the rear end of the girder 11a passes through the support gate 42, but due to the weight of the connected girder 11b and the support of the girder 11b by the support gate 42, the girder 11a can be kept horizontal and continuously sent out. . The supply of the girder 11 is performed by driving the support wheels 43 or the support wheels 32 by a drive source such as a motor and applying a rotational force to the support wheels 43 or the support wheels 32. As for the feeding method, other known methods such as pushing out from behind the girder 11 with a jack may be used.

【0008】<ハ>桁の切離し及び移動(図3) 送り出した桁11aの先端が橋脚32まで到達したら、
連結具12を取り外して、桁11aと桁11bを切り離
す。桁11aを橋脚31及び32の長手方向に沿って所
定位置まで移動させる。その移動方法としては、例え
ば、橋脚31及び32上面に設置した台車又はすべり板
の上に桁11aを載せ、油圧ジャッキ又はウインチ等を
駆動源として移動させることができる。このような移動
方法を採用すれば、桁11aの滑動抵抗を低減でき、能
率良く行うことができる。
<C> Separation and movement of girder (Fig. 3) When the tip of the sent girder 11a reaches the pier 32,
The connecting tool 12 is removed to separate the girder 11a and the girder 11b. The girder 11a is moved to a predetermined position along the longitudinal direction of the piers 31 and 32. As a moving method, for example, the girder 11a can be placed on a bogie or a sliding plate installed on the upper surface of the bridge piers 31 and 32, and the girder 11a can be moved by using a hydraulic jack or winch as a drive source. If such a moving method is adopted, the sliding resistance of the girder 11a can be reduced and the girder 11a can be efficiently moved.

【0009】<ニ>最終桁の送り出し 順次桁11の送り出し、連結、橋脚31及び32上の移
動を行う。そして、最終の桁11を送り出す際には、あ
る程度重量を有する仮桁部材を最終の桁11の後端に連
結し送り出しを行う。送り出しを終了後、最終の桁11
と仮桁部材を切り離す。以上の様に、全ての桁11の架
設作業を終えたら、桁11間に梁部材等を配設して使用
目的に応じた建設物を構築する。本実施例は、電車の線
路の上方に構築する建設物の梁部材の架設方法である
が、建設物の下方は電車の線路や道路などの交通機関に
限らず、建物などが建っている場合などであってもよ
い。
<D> Sending out the last girder Sequentially sending out the girders 11, connecting them, and moving them on the piers 31 and 32. When the final girder 11 is sent out, a temporary girder member having a certain weight is connected to the rear end of the final girder 11 and sent out. After sending out, the final digit 11
And disconnect the temporary girder member. As described above, after the work of constructing all the girders 11 is completed, a beam member or the like is arranged between the girders 11 to construct a building according to the purpose of use. Although the present embodiment is a method of constructing a beam member of a construction to be constructed above a railroad track of a train, when the building is not limited to a transportation line such as a railroad track or a road below the construction, And so on.

【0010】[0010]

【実施例2】図4に示す様に、本実施例は、橋脚31と
橋脚32との距離が長い場合に用いる方法であり、橋脚
31の外側に作業台41aを設置し、橋脚32の外側に
作業台41bを設置して建設物を構築するものである。
桁の架設方法は、それぞれ橋脚31及び32から桁11
を送り出し、橋脚31と橋脚32のほぼ中央で桁11a
と桁11aとを連結し、桁11aの後端に連結した桁1
1bを切り離し、連結した桁11aを橋脚31及び32
に沿って所定位置まで移動させる。そして、桁11を全
て架設した後に、桁11間に梁部材等を配設して建設物
を構築する。本実施例の様に、橋脚31と橋脚32との
距離が長い場合など、橋脚31及び32の両側から桁1
1を送り出せば、安全に桁11の架設作業を行うことが
できる。
[Embodiment 2] As shown in FIG. 4, this embodiment is a method used when the distance between the pier 31 and the pier 32 is long. A work platform 41a is installed outside the pier 31 and the outside of the pier 32 is installed. The workbench 41b is installed in the building to construct a building.
The method of erection of girders is from girders 31 and 32 to girder 11 respectively.
Girder 11a at the center of pier 31 and pier 32
And girder 11a are connected to each other, and girder 1 connected to the rear end of girder 11a
1b is separated, and the connected girder 11a is connected to the piers 31 and 32.
Move to a predetermined position along. Then, after all the girders 11 have been installed, a beam member or the like is arranged between the girders 11 to construct a building. When the distance between the pier 31 and the pier 32 is long as in the present embodiment, the girder 1 is inserted from both sides of the piers 31 and 32.
When 1 is sent out, the work of installing the girder 11 can be safely performed.

【0011】[0011]

【発明の効果】本発明は以上説明したようになるから次
のような効果を得ることができる。 <イ> 周囲をビルなどに囲まれた線路や道路などの交
通機関の上方に、交通機関の往来に支障を来たすことな
く建設物を構築することができる。
Since the present invention is as described above, the following effects can be obtained. <A> It is possible to construct a structure above a transportation system such as a railroad or a road surrounded by buildings without hindering traffic.

【0012】<ロ> 建設物の基礎部材となる梁部材、
例えば桁を組立ヤードから送り出して架設するので、桁
の架設作業に広い場所を必要としない。
<B> A beam member serving as a base member of a construction,
For example, since the girder is sent out from the assembly yard and is erected, a large space is not required for the erection work of the girder.

【図面の簡単な説明】[Brief description of drawings]

【図1】 建設物の構築工程の説明図FIG. 1 is an explanatory diagram of a construction process of a building.

【図2】 桁の送り出し工程の説明図FIG. 2 is an explanatory view of a step of sending out a girder.

【図3】 桁の移動工程の平面図FIG. 3 is a plan view of the step of moving the girder.

【図4】 実施例2の説明図FIG. 4 is an explanatory diagram of the second embodiment.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 大河内 政之 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 ─────────────────────────────────────────────────── ─── Continued Front Page (72) Inventor Masayuki Okouchi 1-25-1 Nishishinjuku, Shinjuku-ku, Tokyo Taisei Corporation

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 建築物の構築予定地を挟んで対向する位
置に橋脚を設置し、 一方の該橋脚の構築予定地の反対側に組立ヤードを設置
し、 該組立ヤードの上面にはグラウンドアンカーで固定され
た支持門が設置され、 組立ヤード上から前記支持門内を通して、対向する橋脚
に向けて桁を送り出し、 該桁の後端には連結具により
次に送り出し予定の桁の先端を連結させて行い、 桁を
両側の橋脚上に架設した後、前記連結具を取り外し、 架設した桁を橋脚に沿って移動させて行う、 梁部材の架設方法。
1. A bridge pier is installed at a position facing each other across a planned construction site of a building, an assembly yard is installed on the opposite side of the planned construction site of one of the piers, and a ground anchor is provided on the upper surface of the assembly yard. A support gate fixed with is installed, and a girder is sent from above the assembly yard through the support gate toward the opposing pier, and the rear end of the girder is connected by a connecting tool to the tip of the girder to be sent next. The method of erection of beam members, in which the girders are erected on the piers on both sides, the connecting tool is removed, and the erected girders are moved along the piers.
【請求項2】 各橋脚の外側に組立ヤードを設置し、 各組立ヤードから対向する橋脚に向けて桁を移動させ、 各橋脚のほぼ中央で各桁を連結して行うこと特徴とす
る、 前記請求項1に記載の梁部材の架設方法。
2. An assembling yard is installed outside each pier, a girder is moved from each assembling yard toward an opposing pier, and each girder is connected at substantially the center of each pier, The method for constructing a beam member according to claim 1.
JP04352149A 1992-12-10 1992-12-10 How to install beam members Expired - Fee Related JP3138949B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP04352149A JP3138949B2 (en) 1992-12-10 1992-12-10 How to install beam members

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP04352149A JP3138949B2 (en) 1992-12-10 1992-12-10 How to install beam members

Publications (2)

Publication Number Publication Date
JPH06173459A true JPH06173459A (en) 1994-06-21
JP3138949B2 JP3138949B2 (en) 2001-02-26

Family

ID=18422116

Family Applications (1)

Application Number Title Priority Date Filing Date
JP04352149A Expired - Fee Related JP3138949B2 (en) 1992-12-10 1992-12-10 How to install beam members

Country Status (1)

Country Link
JP (1) JP3138949B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010265608A (en) * 2009-05-12 2010-11-25 Takenaka Komuten Co Ltd Method for moving skeleton, and structure
JP2010265607A (en) * 2009-05-12 2010-11-25 Takenaka Komuten Co Ltd Method for moving skeleton, and structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010265608A (en) * 2009-05-12 2010-11-25 Takenaka Komuten Co Ltd Method for moving skeleton, and structure
JP2010265607A (en) * 2009-05-12 2010-11-25 Takenaka Komuten Co Ltd Method for moving skeleton, and structure

Also Published As

Publication number Publication date
JP3138949B2 (en) 2001-02-26

Similar Documents

Publication Publication Date Title
JP2009191458A (en) Construction apparatus for bridge, construction method for floor slab, and construction method for bridge
JP2008274637A (en) Construction method for continuous viaduct
JP3440422B2 (en) Bridge construction method and bridge construction device
EP0796373B1 (en) Continuous incrementally erecting viaduct construction system
JP2003253620A (en) Cable stayed bridge and its construction method
CN103806374A (en) Assembled road steel bridge overall track erection and push system and process
JPH06173459A (en) Beam member mounting method
JP4880374B2 (en) How to build a bridge
JP2001348816A (en) Installing method and device of precast segment overhanging installing bridge
JPH11158814A (en) Method of constructing portal pier for viaduct
JP3905099B2 (en) Hand girder delivery construction method for bridge girder
JP2001098512A (en) Method for erecting and removing road striding bridge by frame with jack device
CN109797657B (en) Cast-in-situ bridge template support system device and bridge cast-in-situ construction method
JP2001020225A (en) Erection method of bridge and equipment therefor
WO2022083380A1 (en) Overhead cover structure system applicable in operational railway line and implementation method for system
JPH0336362B2 (en)
CN112610244A (en) Prefabricated part for expanding existing elevated operation subway station platform and installation method thereof
CN206173812U (en) Novel construction of continuous beam displacement device of bridge
JP4210157B2 (en) How to connect between bridge girder of ramen type bridge
CN219260758U (en) Trolley for cast-in-situ cover plate culvert wall construction
CN108330842B (en) Bridge girder erection machine for erection construction of large-span reinforced concrete composite girder and construction method
JP2690345B2 (en) Bridge construction method and equipment
JP2000230204A (en) Elevated track construction method and device
CN117468350A (en) Construction system for rapid construction of box girder and rapid construction method of steel box girder
JPH11158817A (en) Balancing erection construction for bridge at height and transferable slinging lifting device therefor

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 9

Free format text: PAYMENT UNTIL: 20091215

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 9

Free format text: PAYMENT UNTIL: 20091215

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 10

Free format text: PAYMENT UNTIL: 20101215

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20111215

LAPS Cancellation because of no payment of annual fees