JPH06108793A - Shield process and segment manufacturing facility used therefor - Google Patents

Shield process and segment manufacturing facility used therefor

Info

Publication number
JPH06108793A
JPH06108793A JP4260254A JP26025492A JPH06108793A JP H06108793 A JPH06108793 A JP H06108793A JP 4260254 A JP4260254 A JP 4260254A JP 26025492 A JP26025492 A JP 26025492A JP H06108793 A JPH06108793 A JP H06108793A
Authority
JP
Japan
Prior art keywords
segment
concrete
tunnel
ground
components
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP4260254A
Other languages
Japanese (ja)
Inventor
Toshio Watanabe
俊雄 渡辺
Kazuo Miyazawa
和夫 宮沢
Shinichi Nishimura
晋一 西村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP4260254A priority Critical patent/JPH06108793A/en
Publication of JPH06108793A publication Critical patent/JPH06108793A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

PURPOSE:To reduce the labor for transportation and to lower the cost by manufacturing segments with the use of a segment manufacturing facility which is installed in a tunnel in rear of a shield machine for excavating the ground, and by using these segments so as to construct the tunnel. CONSTITUTION:Components 7 is introduced and stocked in a storage bin 8 from a truck 25 which has transported the components 7 from a shaft base 9 on the ground to a base 11, through a material filling pipes 10 and a material press-feed pipe 12. Then the components 7 are delivered from the storage bin 8 by means of a conveyer device 14, and are then shifted onto a material stocker 13. Then, they are introduced into a batches plant 20 by means of a belt conveyer 23, and the components are respectively weighed and are kneaded so as to produce concrete. A reinforcement cage is assembled in a form 24, and then the concrete is placed therein. Then after steam curing in a steam curing chamber 22, a segment A is parted and is then cured underwater. Further, the ground in a tunnel 4 is excavated, the segment A is cylindrically laid in the excavated tunnel 4a by means of an elector mechanism in a shield machine 3. The above-mentioned steps are repeated.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、例えば、超大口径のト
ンネルをシールド工法により構築するのに好適なシール
ド工法およびそれに用いるセグメント製造設備に関する
ものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a shield construction method suitable for constructing, for example, a tunnel having an extremely large diameter by a shield construction method and a segment manufacturing facility used for the shield construction method.

【0002】[0002]

【従来の技術】一般に、シールド工法は、外形円筒状の
スキンプレートを有するシールド掘削機の前部に設けら
れたカッタ装置で地山を掘削しつつ、スキンプレート内
で円筒分割体たるセグメントを組み立て、さらにこのセ
グメントの前端に反力をとってシールド掘削機内部の推
進ジャッキを伸長させることでシールド掘削機全体を前
方に推進させ、これらの工程を繰り返すことで地中にト
ンネルを構築する工法である。
2. Description of the Related Art In general, a shield method is used to assemble a segment that is a cylindrical divided body in a skin plate while excavating the ground with a cutter device provided in the front part of a shield excavator having a skin plate having an outer cylindrical shape. In addition, a reaction force is applied to the front end of this segment to extend the propulsion jack inside the shield excavator to propel the entire shield excavator forward, and by repeating these steps, a tunnel is built underground. is there.

【0003】従来、このようなシールド工法に用いるセ
グメントは、地上の工場で予め製造し、工場からトラッ
ク等により運搬して、構築すべきトンネルの坑内に搬送
した後、組み立てている。
Conventionally, a segment used for such a shield construction method is manufactured in advance at a factory on the ground, transported from the factory by a truck or the like, transported to the inside of a tunnel to be constructed, and then assembled.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上述し
たような従来のシールド工法においては、例えば直径2
0m以上の超大口径のトンネルを構築する場合には、セ
グメントは1ピース当り10トン近くにもなり、工場か
らの運搬,坑内への搬送には、重量物であるがうえ、そ
の取り扱いに多大な労力を必要とし、さらには危険を伴
う作業となる。また、工場からの運搬にトラックを用い
ると、毎日、多数のトラックが現場に出入りすることに
なる(例えば、1日当り、直径20m,壁厚1m,長さ
6mのトンネルを構築するためには、10トントラック
で90台/日)。このため、地上においてトラックの荷
卸しに広大なスペースを有するうえ、搬送コストも膨大
なものになる。
However, in the conventional shield construction method as described above, for example, the diameter is 2
When constructing a tunnel with an ultra-large diameter of 0 m or more, the number of segments is close to 10 tons per piece, which is heavy for transporting from factories and underground, and is also extremely difficult to handle. It is a labor-intensive and even dangerous task. Also, if trucks are used for transportation from the factory, many trucks will come and go to the site every day (for example, in order to construct a tunnel with a diameter of 20 m, a wall thickness of 1 m, and a length of 6 m per day, 90 trucks / day for a 10-ton truck). Therefore, there is a vast space for unloading trucks on the ground, and the transportation cost is enormous.

【0005】また、上記の問題に対し、セグメントを使
用せず、場所打ちコンクリートで覆工すると、前述した
シールド機の推進のための反力を支持することができ
ず、セグメントの持つ機能を満たすことができない。本
発明は、以上のような点を考慮してなされたもので、容
易かつ安全にセグメントを坑内の組立現場に供給し、か
つコストを低減することができるシールド工法およびそ
れに用いるセグメントの製造装置を提供することを目的
とする。
In contrast to the above problems, if the segment is not used and lining with cast-in-place concrete is performed, the reaction force for propelling the shield machine described above cannot be supported and the function of the segment is satisfied. I can't. The present invention has been made in consideration of the above points, and a shield construction method capable of easily and safely supplying a segment to an assembly site in a mine and reducing the cost, and a segment manufacturing apparatus used for the shield construction method. The purpose is to provide.

【0006】[0006]

【課題を解決するための手段】請求項1に係る発明は、
シールド工法において、セグメントを、地山を掘削する
シールド機の後方の、予め構築した坑内で製造して、製
造された該セグメントを用いてトンネルを形成すること
を特徴としている。
The invention according to claim 1 is
The shield construction method is characterized in that a segment is manufactured in a pre-built mine behind a shield machine for excavating the natural ground, and a tunnel is formed using the manufactured segment.

【0007】請求項2に係る発明は、シールド工法に用
いられるセグメントの製造設備であって、坑内に、コン
クリートを構成するセメント,骨材,水等の構成物を地
上から供給する供給機構と、前記構成物からコンクリー
トを混成するコンクリート製造機構と、コンクリートを
型枠に打設・締固めする打設・締固め機構と、型枠に打
設・締固めしたコンクリートを養生する養生機構とを含
むセグメント製造設備を設けてなることを特徴としてい
る。
The invention according to claim 2 is a manufacturing facility for a segment used in a shield construction method, which comprises a supply mechanism for supplying constituents such as cement, aggregate, and water constituting concrete from the ground into the mine, Includes a concrete manufacturing mechanism that mixes concrete from the above components, a casting and compacting mechanism that casts and compacts concrete into a formwork, and a curing mechanism that cures the concrete that is cast and compacted into the formwork. It is characterized by the provision of segment manufacturing equipment.

【0008】[0008]

【作用】請求項1記載の発明では、シールド工法におい
て、セグメントを、地山を掘削しつつ前進するシールド
機の後方の予め構築した坑内で製造して、製造されたセ
グメントを掘削した坑内で組み立てることによりトンネ
ルが形成される。
According to the first aspect of the present invention, in the shield construction method, the segment is manufactured in a pre-constructed mine behind a shield machine that advances while excavating the natural ground, and the manufactured segment is assembled in the excavated mine. As a result, a tunnel is formed.

【0009】請求項2記載の発明では、坑内に、コンク
リートを構成するセメント,骨材,水等の構成物を地上
から供給する供給機構と、前記構成物からコンクリート
を混成するコンクリート製造機構と、コンクリートを型
枠に打設・締固めする打設・締固め機構と、型枠に打設
・締固めしたコンクリートを養生する養生機構とを含む
セグメント製造設備を設けて、坑内において、このセグ
メント製造設備により、地上から供給された骨材からコ
ンクリートを混成し、このコンクリートを型枠に打設・
締固めし、養生してセグメントが製造される。
According to the second aspect of the present invention, a supply mechanism for supplying constituents such as cement, aggregate, and water, which constitute concrete, into the mine from above, and a concrete manufacturing mechanism for mixing concrete from the constituents. A segment manufacturing facility including a casting / compacting mechanism for casting / compacting concrete on the formwork and a curing mechanism for curing the concrete poured / compacted on the formwork is provided to produce this segment in the mine. With the equipment, concrete is mixed from the aggregate supplied from the ground, and this concrete is placed in the formwork.
The segment is manufactured by compacting and curing.

【0010】[0010]

【実施例】以下、本発明のシールド工法によりトンネル
を構築する一実施例を図1ないし図3を参照して説明す
る。まず、図1に示すように、地盤1に、通常どおり立
坑2を所定の深さまで掘削した後に、立坑2内には、地
山を掘削するカッタ機構,セグメントを組み立てるエレ
クタ機構等を備えたシールド機3を降ろし、立坑2の底
部から略水平方向に向けて掘削する。図1は、このシー
ルド機3を掘進させて所定の長さ、例えば100m、を
掘削し、トンネル4を構築した状態を示している。トン
ネル4の既に掘削の完了した坑内4aには、通常と同様
に地上の工場で製造されたセグメント5,5,…を搬入
し、円環状に組み立てる。工場からのセグメント5の運
搬,坑内への搬送は、この所定の長さのトンネル4を構
築するためのセグメント5,5,…のみである。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment for constructing a tunnel by the shield construction method of the present invention will be described below with reference to FIGS. First, as shown in FIG. 1, after a vertical shaft 2 is normally excavated to a predetermined depth in the ground 1, a shield mechanism including a cutter mechanism for excavating natural ground, an erector mechanism for assembling segments, etc. is provided in the vertical shaft 2. The machine 3 is lowered and the bottom of the vertical shaft 2 is excavated in a substantially horizontal direction. FIG. 1 shows a state in which the tunnel 4 is constructed by excavating the shield machine 3 to excavate a predetermined length, for example, 100 m. Segments 5, 5, ... Produced in a factory on the ground are carried into the tunnel 4a, which has already been excavated, in the tunnel 4 and assembled in an annular shape. The transportation of the segment 5 from the factory and the transportation into the mine are only the segments 5, 5, ... For constructing the tunnel 4 of this predetermined length.

【0011】次に、以下のようにして、坑内4aにセグ
メントを製造するセグメント製造設備6を設置する。ま
ず、立坑2内に、コンクリートを構成するセメント,
砂,砂利,水等の構成物7を貯蔵する管状の貯蔵ビン8
を鉛直方向に設ける。この貯蔵ビン8には、立坑2の地
上開口部2a周囲部に設けた立坑基地9から貯蔵ビン8
に構成物7を圧送する材料注入管10を設け、さらに、
立坑基地が大きくとれない場合に主要道路近辺の公共用
地等に設けられたベース11から貯蔵ビン8に構成物7
を圧送する材料圧送管12を地盤1に埋設する。
Next, a segment manufacturing facility 6 for manufacturing a segment is installed in the downhole 4a as follows. First, in the shaft 2, cement that constitutes concrete,
Tubular storage bottle 8 for storing components 7 such as sand, gravel, and water
Is provided in the vertical direction. The storage bin 8 is provided from a vertical shaft base 9 provided around the above-ground opening 2a of the vertical shaft 2 to the storage bin 8.
A material injection pipe 10 for pumping the composition 7 to the
When the vertical shaft base cannot be taken large, the components 7 are stored in the storage bin 8 from the base 11 provided on the public land near the main road.
A material pressure-feeding pipe 12 for pressure-feeding is embedded in the ground 1.

【0012】次いで、貯蔵ビン8の底部8aの側方の坑
内4aに、構成物7を必要量のみストックする材料スト
ッカー13を設ける。この材料ストッカー13と貯蔵ビ
ン8の供給口8bとの間には、搬送装置14を設ける。
この搬送装置14は、トンネル4の掘削方向に向けて延
びるレール14aを備え、このレール14a上を走行す
る運搬車14bにより、貯蔵ビン8から材料ストッカー
13に構成物7を適時搬送するものである。上記の貯蔵
ビン8,材料注入管10,材料圧送管12,材料ストッ
カー13,搬送装置14とから供給機構15が構成され
ている。
Next, a material stocker 13 for stocking only the necessary amount of the constituent 7 is provided in the mine 4a on the side of the bottom 8a of the storage bin 8. A conveying device 14 is provided between the material stocker 13 and the supply port 8b of the storage bin 8.
The transfer device 14 includes a rail 14a extending toward the excavation direction of the tunnel 4, and a transport vehicle 14b traveling on the rail 14a transports the component 7 from the storage bin 8 to the material stocker 13 at appropriate times. . A supply mechanism 15 is configured by the storage bin 8, the material injection pipe 10, the material pressure feed pipe 12, the material stocker 13, and the transfer device 14.

【0013】次いで、材料ストッカー13の側方に、ト
ンネル4の下部を遮蔽する仕切板16,16を、トンネ
ル4の延在する方向に沿って、例えば100m程の間隔
をおいて設置する。仕切板16,16間のトンネル4の
底部には、図2に示すように、防水シート17を敷設す
る。そして、この仕切板16,16と防水シート17と
に囲まれた空間内に水を満たし、水中養生槽(養生機
構)18を形成する。この水中養生槽18は、コンクリ
ートで造られたセグメントを一定期間(例えば2週間程
度)水中に浸して養生するものである。
Next, partition plates 16 and 16 for shielding the lower part of the tunnel 4 are installed beside the material stocker 13 along the direction in which the tunnel 4 extends at intervals of, for example, about 100 m. As shown in FIG. 2, a waterproof sheet 17 is laid on the bottom of the tunnel 4 between the partition plates 16 and 16. Then, the space surrounded by the partition plates 16 and 16 and the waterproof sheet 17 is filled with water to form an underwater curing tank (curing mechanism) 18. The underwater curing tank 18 is for curing by immersing a segment made of concrete in water for a certain period (for example, about 2 weeks).

【0014】次いで、水中養生槽18の上方に水平面を
有する仮設床19を設ける。この仮設床19の上面に、
バッチャープラント(コンクリート製造機構)20と打
設・締固め装置(打設・締固め機構)21と蒸気養生室
(養生機構)22とを、トンネル4の掘削方向に沿って
設置する。また、ベルトコンベア23を、バッチャープ
ラント20と前記材料ストッカー13との間に架設す
る。さらに、上記以外にも、セグメントAを製造するの
に必要な装置,備品等を設置する。
Next, a temporary floor 19 having a horizontal surface is provided above the underwater curing tank 18. On the upper surface of this temporary floor 19,
A batcher plant (concrete manufacturing mechanism) 20, a casting / compacting device (casting / compaction mechanism) 21, and a steam curing chamber (curing mechanism) 22 are installed along the excavation direction of the tunnel 4. Further, the belt conveyor 23 is installed between the batcher plant 20 and the material stocker 13. Further, in addition to the above, equipment, equipment, etc. necessary for manufacturing the segment A are installed.

【0015】バッチャープラント20は、コンクリート
を構成する構成物7のセメント,砂,砂利,水等の自動
計量機構と、自動計量機構により計量した構成物7を混
練りしてコンクリートを混成する混練り機構とを備える
ものである。打設・締固め装置21は、形成すべきセグ
メントAの型枠24内に鉄筋が組まれた鉄筋カゴを組み
付け、この型枠24内に、バッチャープラント20によ
り混成されたコンクリートを打設・締固めするものであ
る。蒸気養生室22は、打設・締固めされた型枠24内
のコンクリートを高温の水蒸気で養生する室を備えるも
のである。
The batcher plant 20 mixes concrete by mixing the automatic measuring mechanism for cement, sand, gravel, water, etc. of the constituent 7 constituting the concrete and the constituent 7 measured by the automatic measuring mechanism. And a kneading mechanism. The pouring / compacting device 21 assembles a rebar cage in which rebars are assembled in the formwork 24 of the segment A to be formed, and pours concrete mixed by the batcher plant 20 into the formwork 24. It is to be compacted. The steam curing chamber 22 has a chamber for curing the concrete in the cast and compacted formwork 24 with high temperature steam.

【0016】次に、以上のようにして、トンネル4の坑
内4aに設置された上記の構成のセグメント製造装置6
により、図3に示す二点鎖線B内の様にして、形成すべ
きセグメントAを製造する。まず、地上の立坑基地9,
ベース11までコンクリートを構成する構成物7を運搬
してきたトラック25等から、材料注入管10,材料圧
送管12を通して、構成物7を貯蔵ビン8内に送り込
み、ストックする。次いで、必要な量の構成物7を、搬
送装置14により貯蔵ビン8内から搬出し、材料ストッ
カー13に移載する。
Next, as described above, the segment manufacturing apparatus 6 having the above-mentioned structure installed in the tunnel 4a of the tunnel 4
Thus, the segment A to be formed is manufactured as shown by the double-dotted line B in FIG. First, the ground shaft base 9,
The component 7 is fed into the storage bin 8 through the material injection pipe 10 and the material pressure feed pipe 12 from the truck 25 or the like that has transported the component 7 constituting the concrete to the base 11, and is stocked. Then, the required amount of the constituents 7 is carried out from the storage bin 8 by the carrying device 14 and transferred to the material stocker 13.

【0017】次いで、構成物7を、ベルトコンベア23
により材料ストッカー13からバッチャープラント20
に投入し、自動計量機構によりセメント,砂,砂利,水
等の各構成物7を所定量、計量した後、混練りしてコン
クリートを混成する。一方、形成すべきセグメントAの
型枠24内に、鉄筋カゴを組み付け、バッチャープラン
ト20の所定の位置に設置する。そして、混成したコン
クリートを型枠24に打設して、締固めし、その後にコ
ンクリートの表面仕上げをする。
Next, the component 7 is transferred to the belt conveyor 23.
From material stocker 13 to batcher plant 20
Then, each constituent 7 such as cement, sand, gravel, and water is weighed in a predetermined amount by an automatic measuring mechanism, and then kneaded to mix concrete. On the other hand, the rebar cage is assembled in the form 24 of the segment A to be formed and installed at a predetermined position of the batcher plant 20. Then, the mixed concrete is poured into the form 24 to be compacted, and then the surface of the concrete is finished.

【0018】次いで、この型枠24を蒸気養生室22に
搬入して、一定期間、蒸気養生をする。次いで、形成さ
れたセグメントAを型枠24から脱型し、このセグメン
トAを水中養生槽18に浸して、例えば2週間、水中養
生する。上記のようにしてトンネル4の坑内4aで、セ
グメントAが製造され、図3に示した二点鎖線B内の工
程が行われることになる。
Next, the mold 24 is carried into the steam curing chamber 22 and steam cured for a certain period. Next, the formed segment A is demolded from the mold 24, and the segment A is immersed in the underwater curing tank 18 to be cured in water for 2 weeks, for example. As described above, the segment A is manufactured in the downhole 4a of the tunnel 4, and the process within the chain double-dashed line B shown in FIG. 3 is performed.

【0019】一方、図1に示したトンネル4の掘進方向
前方のシールド機3に設けられたカッタ機構により、地
山を掘進し、シールド機3に備えられたエレクタ機構に
より、前記セグメント製造設備6により製造されたセグ
メントAを、掘削した坑内4aに円筒状に組み立てる。
そして、組み立てたセグメントAの前端に反力をとって
シールド機3内部の推進ジャッキを伸長させることでシ
ールド機3全体を前方に推進させ、これらの工程を繰り
返すことで地盤1中にトンネル4を構築する。
On the other hand, the cutter mechanism provided in the shield machine 3 in front of the tunnel 4 shown in FIG. 1 excavates the natural ground, and the erector mechanism provided in the shield machine 3 excels the segment manufacturing facility 6 The segment A manufactured by is assembled in the excavated downhole 4a in a cylindrical shape.
Then, a reaction force is applied to the front end of the assembled segment A to extend the propulsion jack inside the shield machine 3 to propel the entire shield machine 3 forward, and by repeating these steps, the tunnel 4 is formed in the ground 1. To construct.

【0020】以上、上述したように、坑内4aに、コン
クリートを構成する構成物7を地上から供給する供給機
構15と、構成物7からコンクリートを混成するバッチ
ャープラント20と、コンクリートを型枠24に打設・
締固めする打設・締固め装置21と、型枠24に打設・
締固めしたコンクリートを養生する蒸気養生室22,水
中養生槽18とを含むセグメント製造設備6を設けたの
で、坑内4aにおいて、セグメントAを製造することが
できる。これにより、構成物7を地上から供給するのみ
でよく、運搬のためのトラックの数を大幅に削減するこ
とができるので、搬送コストも大幅に削減することがで
き、さらに地上におけるトラックからの荷卸しのスペー
スを大幅に縮小することができる。
As described above, as described above, the supply mechanism 15 for supplying the constituent 7 constituting concrete to the underground 4a from the ground, the batcher plant 20 for mixing concrete from the constituent 7, and the concrete form 24 Placed on
Placing / compacting device 21 for compaction and placing / compacting on form 24
Since the segment manufacturing facility 6 including the steam curing chamber 22 for curing the compacted concrete and the underwater curing tank 18 is provided, the segment A can be manufactured in the downhole 4a. As a result, the components 7 need only be supplied from the ground, and the number of trucks for transportation can be greatly reduced, so that the transportation cost can be significantly reduced, and further, the unloading from the truck on the ground can be performed. The space can be reduced significantly.

【0021】また、シールド工法において、セグメント
Aを、地山を掘削しつつ前進するシールド機3の後方
の、予め構築した坑内4aに設置したセグメント製造設
備6により製造して、製造されたセグメントAを掘削し
た坑内4aで組み立てることによりトンネル4が構築さ
れる。これにより、工場からのセグメント5の運搬,坑
内への搬送は、セグメント製造設備6を設置するための
所定の長さ、例えば100m、のトンネル4を構築する
ためのセグメント5,5,…のみであり、重量物である
セグメント5の運搬,搬送のための労力を大幅に低減す
ることができ、危険作業を低減することができるので、
作業を容易かつ安全に行うことができる。
Further, in the shield construction method, the segment A is manufactured by the segment manufacturing equipment 6 installed in the prefabricated downhole 4a behind the shield machine 3 which moves forward while excavating the natural ground, and the manufactured segment A is manufactured. The tunnel 4 is constructed by assembling the inside of the excavated underground 4a. Thereby, the transportation of the segment 5 from the factory and the transportation into the mine are performed only by the segments 5, 5, ... For constructing the tunnel 4 having a predetermined length for installing the segment manufacturing facility 6, for example, 100 m. Therefore, the labor for transporting and transporting the heavy segment 5 can be significantly reduced, and dangerous work can be reduced.
Work can be performed easily and safely.

【0022】さらに、立坑2の地上開口部2a周囲部の
立坑基地9以外に、主要道近辺の公共用地にベース11
を設け、このベース11から構成物7を圧送できる構成
とした。これにより、例えば、都心など用地が狭く、立
坑基地9に十分な面積を確保することが困難な場合等に
おいても、支障なく構成物7の供給を行うことができ
る。
Further, in addition to the vertical shaft base 9 around the above-ground opening 2a of the vertical shaft 2, a base 11 is provided on a public land near the main road.
Is provided, and the structure 7 can be pressure-fed from the base 11. Accordingly, for example, even when the site is narrow such as in the center of the city and it is difficult to secure a sufficient area for the shaft base 9, it is possible to supply the constituents 7 without trouble.

【0023】なお、上記実施例において、トンネル4の
坑内4aに、セグメント製造設備6を設置したが、この
セグメント製造設備6を移動可能な構成として、シール
ド機3の前進にともなって、トンネル4内を前進する構
成としてもよい。これにより、構築すべきトンネル4が
長距離の場合においても、セグメントAの坑内搬送距離
を極力短くすることが可能である。
In the above embodiment, the segment manufacturing equipment 6 is installed in the tunnel 4a of the tunnel 4, but the segment manufacturing equipment 6 is configured to be movable, and the inside of the tunnel 4 is advanced as the shield machine 3 advances. May be configured to move forward. As a result, even when the tunnel 4 to be constructed has a long distance, the underground transportation distance of the segment A can be shortened as much as possible.

【0024】[0024]

【発明の効果】以上説明したように、請求項1に係るシ
ールド工法によれば、シールド工法において、セグメン
トを、地山を掘削しつつ前進するシールド機の後方の予
め構築した坑内で製造して、製造されたセグメントを掘
削した坑内で組み立てることによりトンネルが形成され
る。これにより、重量物であるセグメントを工場から坑
内に運搬・搬送するための労力を大幅に低減することが
でき、また危険作業を低減することができ、作業を容易
かつ安全に行うことができる。
As described above, according to the shield construction method of the first aspect, in the shield construction method, the segment is manufactured in the pre-built mine behind the shield machine that advances while excavating the natural ground. A tunnel is formed by assembling the manufactured segments in the excavated mine. As a result, it is possible to significantly reduce the labor for transporting and transporting the heavy load segment from the factory into the mine, and it is possible to reduce the dangerous work, so that the work can be performed easily and safely.

【0025】請求項2にかかるセグメント製造設備によ
れば、坑内に、コンクリートを構成するセメント,骨
材,水等の構成物を地上から供給する供給機構と、前記
構成物からコンクリートを混成するコンクリート製造機
構と、コンクリートを型枠に打設・締固めする打設・締
固め機構と、型枠に打設・締固めしたコンクリートを養
生する養生機構とを含むセグメント製造設備を設けて、
坑内においてセグメントが製造することができる。これ
により、請求項1にかかる方法を実現し得、さらに、骨
材を地上から供給するのみで、坑内においてセグメント
を製造することができるので、運搬のためのトラックの
数を大幅に削減することができ、搬送コストを大幅に削
減することができる。さらに、地上におけるトラックか
らの荷卸しのスペースを大幅に縮小することができる。
According to the segment manufacturing facility of the second aspect, the supply mechanism for supplying the constituents such as cement, aggregate, and water constituting the concrete from the ground into the mine, and the concrete for mixing the concrete from the constituents. A segment manufacturing facility including a manufacturing mechanism, a casting / compacting mechanism for casting / compacting concrete on the formwork, and a curing mechanism for curing the concrete cast / compacted on the formwork,
The segment can be manufactured in the downhole. As a result, the method according to claim 1 can be realized, and since the segment can be manufactured in the mine by only supplying the aggregate from the ground, the number of trucks for transportation can be significantly reduced. Therefore, the transportation cost can be significantly reduced. Furthermore, the space for unloading trucks on the ground can be significantly reduced.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明にかかるシールド工法およびそれに用い
るセグメント製造設備を示す正断面図である。
FIG. 1 is a front sectional view showing a shield construction method according to the present invention and a segment manufacturing facility used for the shield construction method.

【図2】本発明にかかるセグメント製造設備を示す側断
面図である。
FIG. 2 is a side sectional view showing a segment manufacturing facility according to the present invention.

【図3】本発明にかかるシールド工法を示す工程図であ
る。
FIG. 3 is a process drawing showing a shield construction method according to the present invention.

【符号の説明】[Explanation of symbols]

4 トンネル 6 セグメント製造設備 7 構成物 15 供給機構 18 水中養生槽(養生機構) 20 バッチャープラント(コンクリート製造機構) 21 打設・締固め装置(打設・締固め機構) 22 蒸気養生室(養生機構) 4a 坑内 A セグメント 4 Tunnels 6 Segment manufacturing equipment 7 Components 15 Supply mechanism 18 Underwater curing tank (curing mechanism) 20 Batcher plant (concrete manufacturing mechanism) 21 Casting / compacting device (casting / compacting mechanism) 22 Steam curing room (curing) Mechanism) 4a Underground A segment

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 シールド工法において、セグメントを、
地山を掘削するシールド機の後方の、予め構築した坑内
で製造して、製造された該セグメントを用いてトンネル
を形成することを特徴とするシールド工法。
1. In the shield construction method, the segments are
A shield construction method characterized in that a tunnel is formed by using the manufactured segment, which is manufactured inside a pre-built mine behind a shield machine for excavating a natural ground.
【請求項2】 シールド工法に用いられるセグメントの
製造設備であって、坑内に、コンクリートを構成するセ
メント,骨材,水等の構成物を地上から供給する供給機
構と、前記構成物からコンクリートを混成するコンクリ
ート製造機構と、コンクリートを型枠に打設・締固めす
る打設・締固め機構と、型枠に打設・締固めしたコンク
リートを養生する養生機構とを含むセグメント製造設備
を設けてなることを特徴とするセグメント製造設備。
2. A manufacturing facility for a segment used in a shield construction method, which comprises a supply mechanism for supplying constituents such as cement, aggregate, and water constituting concrete from the ground into a mine, and concrete from the constituent. Provide segment manufacturing equipment including a mixed concrete manufacturing mechanism, a casting / compacting mechanism for casting / compacting concrete on the formwork, and a curing mechanism for curing the concrete cast / compacted on the formwork. Segment manufacturing equipment characterized by
JP4260254A 1992-09-29 1992-09-29 Shield process and segment manufacturing facility used therefor Withdrawn JPH06108793A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4260254A JPH06108793A (en) 1992-09-29 1992-09-29 Shield process and segment manufacturing facility used therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4260254A JPH06108793A (en) 1992-09-29 1992-09-29 Shield process and segment manufacturing facility used therefor

Publications (1)

Publication Number Publication Date
JPH06108793A true JPH06108793A (en) 1994-04-19

Family

ID=17345495

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4260254A Withdrawn JPH06108793A (en) 1992-09-29 1992-09-29 Shield process and segment manufacturing facility used therefor

Country Status (1)

Country Link
JP (1) JPH06108793A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012072607A (en) * 2010-09-29 2012-04-12 Ishikawajima Constr Materials Co Ltd Manufacturing method of segment and manufacturing facility of segment
CN108756907A (en) * 2018-08-09 2018-11-06 北京崇建工程有限公司 A kind of tunnel support top shield spouting plant

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012072607A (en) * 2010-09-29 2012-04-12 Ishikawajima Constr Materials Co Ltd Manufacturing method of segment and manufacturing facility of segment
CN108756907A (en) * 2018-08-09 2018-11-06 北京崇建工程有限公司 A kind of tunnel support top shield spouting plant
CN108756907B (en) * 2018-08-09 2024-01-30 北京崇建工程有限公司 Tunnel top shield guniting equipment

Similar Documents

Publication Publication Date Title
CN109736354A (en) Tunnel open excavation section main structure construction method
US20030142579A1 (en) Mobile pavement plant
JP4859692B2 (en) Tunnel internal structure construction method
JPH06108793A (en) Shield process and segment manufacturing facility used therefor
CN106321116B (en) A kind of tunnel is dug and the construction method of lining concrete parallel operations
JPH04213695A (en) Segment for shield tunnel
JP4020858B2 (en) Manufacturing method for underground structures
JP2014173290A (en) Tunnel construction method
JPH09151471A (en) Movable form device and work execution method for underground structure using the device
JPH09151470A (en) Work execution method for underground structure
CN111608248A (en) Cast-in-situ rainwater cover plate channel construction method
JP6986803B1 (en) Retaining wall structure and how to build a retaining wall
JPH06167186A (en) Construction method of large sectional shield tunnel
JP3660070B2 (en) Construction surplus soil effective utilization method
CN111636484B (en) Municipal inspection well structure and construction method thereof
JPH1072846A (en) Treatment method of soil
JPH0988103A (en) Method of constructing underground structure
JPH02132295A (en) Constructing method for tunnel lining work
JP2867081B2 (en) Construction method and structure of underground segmental shell
CN115163091A (en) Construction method of comprehensive utilization platform in ultra-long distance small-diameter tunnel
JP2633715B2 (en) Step construction method
JP2023165499A (en) Method for placing lining concrete for tunnel
JP2023157494A (en) Invert mold manufacturing device, invert construction system and invert construction method
JP3545641B2 (en) Backfill method
JPH0873848A (en) Backfilling material and backfilling by utilization of the same

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 19991130