JPH05485B2 - - Google Patents

Info

Publication number
JPH05485B2
JPH05485B2 JP3082588A JP3082588A JPH05485B2 JP H05485 B2 JPH05485 B2 JP H05485B2 JP 3082588 A JP3082588 A JP 3082588A JP 3082588 A JP3082588 A JP 3082588A JP H05485 B2 JPH05485 B2 JP H05485B2
Authority
JP
Japan
Prior art keywords
bracket
wall
adjustment member
concrete
retaining wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP3082588A
Other languages
Japanese (ja)
Other versions
JPH01207526A (en
Inventor
Yoshio Furuya
Katsuhiko Nakatani
Hiroshi Suzuki
Yoshuki Yokoyama
Tomio Moriwaki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP3082588A priority Critical patent/JPH01207526A/en
Publication of JPH01207526A publication Critical patent/JPH01207526A/en
Publication of JPH05485B2 publication Critical patent/JPH05485B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 《産業上の利用分野》 本発明は土留支保工に特徴のある地下構造物の
構築法に関する。
DETAILED DESCRIPTION OF THE INVENTION <<Industrial Application Field>> The present invention relates to a method for constructing an underground structure characterized by earth retention shoring.

《従来の技術》 従来の切梁式土留め工法は一般に掘削しながら
山留め壁を構築し、構築した山留め壁を第一段の
腹起し、切梁で支持しながら予定最深部迄逐次に
掘り下げ、従属して第二段、第三段の腹起し、切
梁等で山留め壁を支持しながら掘削をすすめる。
《Conventional technology》 In the conventional strut-type earth retaining method, a retaining wall is generally constructed while excavating, and the constructed retaining wall is raised up on the first stage, supported by struts, and successively dug to the planned deepest point, and then submerged. Then, excavation will proceed while supporting the retaining wall with the second and third stages of uprights, struts, etc.

然る後に最深部の方から腹起し、切梁の下迄内
壁用コンクリートを打ち、これが所要の強度に達
し次第に当該部分の切梁等を取り外し、直上部分
のコンクリートを打ち継ぎ、強度が発現したなら
ばこの部分の切梁を外すのである。この作業を順
次に上方へ向かつて繰り返しながら地下工事が完
了するものであつた。
Afterwards, raise the wall from the deepest point and pour concrete for the inner wall up to the bottom of the struts, and as soon as this reaches the required strength, remove the struts, etc. in that part, and pour concrete directly above to achieve strength. If so, remove the struts in this area. The underground construction was completed by repeating this work one after another, moving upwards.

《発明が解決しようとする課題》 上記従来の工法では内壁用に打設したコンクリ
ートが所要強度に達する迄の期間は切梁を外すこ
とができず、またその上部内壁を構築するのに腹
起し、切梁が支障になる為、切梁等を一度外す必
要があり、異業種間の錯綜と共に工期が長くなる
点を否めなかつた。
[Problem to be solved by the invention] In the above conventional construction method, the struts cannot be removed until the concrete poured for the inner wall reaches the required strength, and it is difficult to construct the upper inner wall. However, since the struts were a hindrance, it was necessary to remove them once, which undeniably caused complications between different industries and lengthened the construction period.

本発明は叙述の問題点に鑑みてなされたもので
あつて、その目的は腹起しや切梁の盛替えを必要
とせず、特に床スラブを設けないか、階高のある
地下構造物の構築工事に有用な工法を提供するこ
とにある。
The present invention was made in view of the problems described above, and its purpose is to eliminate the need for raising or replacing struts, and in particular for underground structures that do not have a floor slab or have a high floor. Our goal is to provide useful construction methods for construction work.

《課題を解決するための手段》 上記目的を達成するために、本発明の地下構造
物の構築法は根切工事に切梁、腹起しなどの支保
工を用いた土留め工法において、ブラケツトの腹
起し側端部に切り離し可能な調整部材を設け、該
調整部材と腹起しとを接続して山留め壁を支持
し、山留め壁の内側に該ブラケツトの調整部材を
後から外せる程度、かつ該腹起しから離して該腹
起しの盛替えを行うことなく山留め壁の内側全面
に内壁を構成するコンクリートを打設し、該打設
コンクリートに所定の強度が発現したならば該ブ
ラケツトの調整部材を外すことにより該腹起しを
撤去するのである。
<Means for Solving the Problems> In order to achieve the above object, the method for constructing an underground structure of the present invention is a method of constructing an underground structure using a bracket in an earth retaining method that uses shoring such as beams and erecting for root cutting work. A detachable adjustment member is provided at the end of the bracket on the side of the bracket, the adjustment member and the bracket are connected to support the retaining wall, and the adjustment member of the bracket is located inside the retaining wall to the extent that it can be removed later, and Concrete constituting the inner wall is poured all over the inside of the retaining wall without repositioning the raised wall away from the raised wall, and when the poured concrete has developed a predetermined strength, the bracket is The tummy tuck is removed by removing the adjustment member.

《作用》 土圧をブラケツトの基端面で受け止め、調整部
材を介して腹起しに伝達する。腹起しは各ブラケ
ツトの調整部材自由端側(先端側)に渡設接続さ
れ、各ブラケツトが受ける土圧を腹起しに伝達
し、この腹起しの対向間に必要に応じて切梁を渡
設し、又は隅角部に火打梁を配した支保工を構成
する。
<<Operation>> Earth pressure is received by the proximal end surface of the bracket and transmitted to the abdominal riser via the adjustment member. The ribs are connected to the free end side (tip side) of the adjustment member of each bracket, transmitting the earth pressure that each bracket receives to the ribs, and inserting a strut between the facing ribs as necessary. or construct shoring with flint beams placed at the corners.

内壁のコンクリートは上記ブラケツトを埋め込
みながら、そのまま全面に打ち込んで、腹起しの
盛替えは行なわない。
Concrete for the inner wall will be poured over the entire surface while embedding the above-mentioned brackets, and no refilling will be performed.

《実施例》 以下、本発明の好適な実施例について図面を参
照にして詳細に説明する。
<<Example>> Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings.

第1図は地下深く掘削する場合、掘削の途中に
おいて約3〜4m掘り下げる毎に山留め壁1を腹
起し2で支持しながら掘り下げた様子を示してい
る。
Fig. 1 shows how, when excavating deep underground, the retaining wall 1 is supported by uprights 2 every time about 3 to 4 meters are dug during the excavation.

第1図では腹起し2と、これを担持あるいは支
承するブラケツト3の詳細を略しているので、第
2図にその一部分の平面を示す。
Since FIG. 1 omits the details of the stand-up 2 and the bracket 3 that carries or supports it, FIG. 2 shows a partial plan view thereof.

掘削した平面形状は概略正方形で、内壁は途中
に床スラブを設けない鉛直壁面である。したがつ
て、山留め壁1は掘削孔の内側に正方形に構成さ
れ、複数のブラケツト3を所要の間隔で同一水準
点に水平に当接配置し、このブラケツト3の頭頂
に腹起し2を渡設するものであるが、ブラケツト
3の頭頂には切り離し可能な調整部材4が具えら
れている。調整部材4はブラケツト3を2段式の
連結物(例えばボルト等で)として得ることもよ
いし、ブラケツト3の頭頂部分を溶断し易いよう
に予め加工しておいてもよい。この調整部材4に
前記腹起し2を接続している。
The planar shape of the excavation is approximately square, and the inner wall is a vertical wall with no floor slab installed in the middle. Therefore, the retaining wall 1 is constructed in a square shape inside the excavation hole, and a plurality of brackets 3 are placed horizontally in contact with the same reference point at required intervals, and a brace 2 is placed on the top of the brackets 3. However, a detachable adjustment member 4 is provided at the top of the bracket 3. The adjusting member 4 may be obtained by connecting the bracket 3 in a two-stage manner (for example, with bolts, etc.), or the top portion of the bracket 3 may be processed in advance so as to be easily cut by melting. The abdominal riser 2 is connected to this adjustment member 4.

ブラケツト3の長さは少なくとも内壁の厚さ以
上とし、これに調整部材4が加わる。また、それ
らの材質は所要の強度を有する鋼製でもコンクリ
ートブロツクでもよい。山留め壁1表面の凸凹に
よつてブラケツト3の先端位置が不揃いになるか
ら、ブラケツト3の基端面と山留め壁1表面との
間に膨張モルタルなどを注入してブラケツト3の
先端が均一になるよう調整するとよい。即ち、腹
起し2への伝達土圧をなるべく均一にする為であ
る。
The length of the bracket 3 is at least the thickness of the inner wall, and the adjustment member 4 is added to this length. Moreover, these materials may be made of steel or concrete blocks having the required strength. Since the tip positions of the brackets 3 will be uneven due to unevenness on the surface of the retaining wall 1, expandable mortar or the like is injected between the base end surface of the bracket 3 and the surface of the retaining wall 1 to make the tips of the brackets 3 uniform. You may want to adjust it. In other words, this is to make the earth pressure transmitted to the upright 2 as uniform as possible.

然して、ブラケツト3の頭頂に設けた調整部材
4に腹起し2を取り付ける。腹起し2は四角形状
に渡設された状態に構成される。そして、その隅
角部にキリンジヤツキ5を介設した火打梁6を架
設している。
Thus, the belly riser 2 is attached to the adjustment member 4 provided at the top of the bracket 3. The belly stand 2 is configured in a rectangular shape. A flint beam 6 with a Kirin jack 5 interposed thereon is installed at the corner thereof.

各キリンジヤツキ5を伸縮調節し、腹起し2の
土圧対抗力を調節している。
Each giraffe jack 5 is adjusted to extend or contract, and the force against earth pressure of the belly raiser 2 is adjusted.

この実施例では掘削孔の平面積が小さく、深い
ので、切梁を使用せずに火打梁6だけで足りる
が、平面積が大きい場合には切梁、方づえを使用
する。
In this embodiment, the planar area of the excavation hole is small and deep, so only the flint beams 6 are sufficient without using struts, but if the planar area is large, struts and crosspieces are used.

山留め壁1の支保工は以上のように構成され、
次に支保工、即ち腹起し2を盛替えることをせず
に、そのまま内壁7のコンクリートを打設する。
このコンクリートは調整部材4を残して打つので
ある。したがつて、ブラケツト3は内壁7内に埋
まつて残る。(第3図)。
The support for the retaining wall 1 is constructed as described above,
Next, the concrete for the inner wall 7 is poured without replacing the shoring, that is, the upright 2.
This concrete is poured leaving the adjustment member 4 intact. Therefore, the bracket 3 remains buried within the inner wall 7. (Figure 3).

こうして、打設コンクリートの強度が発現した
ならば、調整部材4をブラケツト3の頭部から取
り外し、ブラケツト3の頭部についてはモルタル
で埋め込むなどして仕上げる。詳しくは、火打梁
6を外し、腹起し2を解体搬出後に調整部材4を
取り外してブラケツト3の頭部を含めた仕上げ作
業を行い(第4図)、地下工事の主要部分の施工
は終了する。
Once the strength of the poured concrete has been achieved, the adjusting member 4 is removed from the head of the bracket 3, and the head of the bracket 3 is finished by filling it with mortar. In detail, after removing the flint beam 6 and dismantling and transporting the riser 2, the adjustment member 4 was removed and finishing work including the head of the bracket 3 was carried out (Fig. 4), and the construction of the main part of the underground work was completed. do.

尚、実施例では腹起し2と山留め壁1の間にブ
ラケツト3と調整部材4を介在させたものについ
て説明したが、本発明はこれに限らずブラケツト
3と調整部材4を1本ものとした束材を用いても
良い。
In the embodiment, the bracket 3 and the adjusting member 4 are interposed between the riser 2 and the retaining wall 1, but the present invention is not limited to this, and the present invention is not limited to this. You may also use bundled material.

《発明の効果》 以上、本発明の地下構造物の構築法によればブ
ラケツトの頭頂に、即ち腹起し側端部に切り離し
可能な調整部材を設け、内壁表面から腹起しを浮
かせているので、型枠作業等の内壁工事や腹起し
の撤去作業に支障はなく、しかもブラケツトを埋
殺すことにより下部コンクリートの打設後、すぐ
に上部内壁の作業が出来る為、上、下コンクリー
トの打継ぎ面の打設時の日数が短く、コンクリー
トの品質の向上は勿論のこと、腹起しや切梁の盛
替えが不必要になり、異業種間の錯綜もなく、施
工管理の面で有利になるほか、工期も従来に較べ
非常に短縮できる効果がある。内壁のコンクリー
トが所定強度に達するのを待つて次工程に腹起し
を盛替え、順次に内壁コンクリートの打ち継ぎを
行う必要がなくなるからである。
<<Effects of the Invention>> As described above, according to the method of constructing an underground structure of the present invention, a detachable adjustment member is provided at the top of the bracket, that is, at the side end of the riser, and the riser is raised above the inner wall surface. Therefore, there is no problem with the inner wall work such as formwork work or the removal work of the raised bed.Moreover, by burying the brackets, work on the upper inner wall can be started immediately after pouring the lower concrete. The time required for pouring joint surfaces is shortened, which not only improves the quality of concrete, but also eliminates the need for raising and replacing beams, eliminates complications between different industries, and improves construction management. In addition to being advantageous, it also has the effect of significantly shortening the construction period compared to conventional methods. This is because it is no longer necessary to wait for the concrete of the inner wall to reach a predetermined strength, then replace it with a raised wall in the next step, and successively perform pouring of the inner wall concrete.

【図面の簡単な説明】[Brief explanation of the drawing]

図は何れも本発明に関し、施工手順等を説明す
るものであつて、第1図は掘削を終了し、腹起し
を組んだ状態を示す概略の側面図、第2図は第1
図の一部の詳細を示す平面図、第3図は施工の途
中を示す説明図、第4図は地下工事が終了した状
態を示す縦断面図である。 1……山留め壁、2……腹起し、3……ブラケ
ツト、4……調整部材、5……キリンジヤツキ、
6……火打梁、7……内壁。
The figures are all related to the present invention and are used to explain the construction procedure, etc., and Figure 1 is a schematic side view showing the state in which the excavation has been completed and the belly is raised, and Figure 2 is a schematic side view showing the state in which the excavation has been completed and the belly is raised.
FIG. 3 is a plan view showing some details of the figure, FIG. 3 is an explanatory view showing the middle of construction, and FIG. 4 is a vertical sectional view showing the state in which the underground construction is completed. 1...Mountain retaining wall, 2...Horizontal, 3...Bracket, 4...Adjustment member, 5...Kirin jack,
6...flint beam, 7...inner wall.

Claims (1)

【特許請求の範囲】[Claims] 1 根切工事に切梁、腹起しなどの支保工を用い
た土留め工法において、ブラケツトの腹起し側端
部に切り離し可能な調整部材を設け、該調整部材
と腹起しとを接続して山留め壁を支持し、該山留
め壁の内側に該ブラケツトの調整部材が後から外
せる程度、かつ該腹起しから離して該腹起しの盛
替えを行うことなく該山留め壁の内側全面に内壁
を構成するコンクリートを打設し、該打設コンク
リートに所定の強度が発現したならば該ブラケツ
トの調整部材を外すことにより該腹起しを撤去す
ることを特徴とする地下構造物の構築法。
1. In earth retaining construction methods that use shoring such as struts and erecting for root cutting work, a detachable adjustment member is provided at the end of the erected side of the bracket, and the adjustment member and the erected are connected. to support the mountain retaining wall, and to the inside of the mountain retaining wall to such an extent that the adjustment member of the bracket can be removed later, and without having to separate from the belly raiser and replace the belly raiser, on the entire inside of the mountain retainer wall. A method for constructing an underground structure, which comprises placing concrete constituting an inner wall, and removing the raised part by removing the adjusting member of the bracket when the poured concrete has developed a predetermined strength. .
JP3082588A 1988-02-15 1988-02-15 Construction of underground structure Granted JPH01207526A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3082588A JPH01207526A (en) 1988-02-15 1988-02-15 Construction of underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3082588A JPH01207526A (en) 1988-02-15 1988-02-15 Construction of underground structure

Publications (2)

Publication Number Publication Date
JPH01207526A JPH01207526A (en) 1989-08-21
JPH05485B2 true JPH05485B2 (en) 1993-01-06

Family

ID=12314478

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3082588A Granted JPH01207526A (en) 1988-02-15 1988-02-15 Construction of underground structure

Country Status (1)

Country Link
JP (1) JPH01207526A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200255698Y1 (en) * 2001-08-31 2001-12-13 주식회사 홍익기술단 Hexagon concrete body for a pier construction
JP2005201007A (en) * 2004-01-19 2005-07-28 Shimizu Corp Construction method for underground structure

Also Published As

Publication number Publication date
JPH01207526A (en) 1989-08-21

Similar Documents

Publication Publication Date Title
US4107889A (en) Foundation system
CN102383628A (en) Construction device and construction method for post construction of depressing cone of silo structure
JPH05485B2 (en)
JP4611108B2 (en) Integrated construction method of pile and column
JP3002126B2 (en) Temporary receiving method for structures
CN112095659B (en) Recyclable single-side formwork system and construction method
JPS6145022B2 (en)
JP7182485B2 (en) building construction method
CN108978697B (en) Terrace template system and construction method
JP2633199B2 (en) How to build a concrete foundation
JP4049467B2 (en) How to correct uneven settlement of soil concrete
CN214116593U (en) Combined round wood formwork for pile foundation construction
JP3700119B2 (en) Pillar construction method
JPH0469270B2 (en)
JP2006028831A (en) Jacket supporting height adjusting holder
JP3660657B2 (en) Construction method of viaduct
JPH01131723A (en) Method of holding sidewall of deep excaveted hole
JP2678442B2 (en) Construction method of independent foundation and foundation block used for it
RU2011774C1 (en) Method for construction of monolithic foundation
JPS6012494B2 (en) Stray beam jack-up method
JP2004169318A (en) Construction method for bridge pier of viaduct
JPH0393925A (en) Simultaneous construction method of structure above or under ground
JP3690463B2 (en) Construction method of viaduct
EP1662049A2 (en) Method for positioning concrete piles
JP2003278160A (en) Simplified landslide protection wall construction method