JP2633199B2 - How to build a concrete foundation - Google Patents

How to build a concrete foundation

Info

Publication number
JP2633199B2
JP2633199B2 JP14870794A JP14870794A JP2633199B2 JP 2633199 B2 JP2633199 B2 JP 2633199B2 JP 14870794 A JP14870794 A JP 14870794A JP 14870794 A JP14870794 A JP 14870794A JP 2633199 B2 JP2633199 B2 JP 2633199B2
Authority
JP
Japan
Prior art keywords
concrete
foundation
formwork
bone frame
vertical hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP14870794A
Other languages
Japanese (ja)
Other versions
JPH07331871A (en
Inventor
春起 中本
和己 熊抱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NAKAMOTO KISO KK
Original Assignee
NAKAMOTO KISO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NAKAMOTO KISO KK filed Critical NAKAMOTO KISO KK
Priority to JP14870794A priority Critical patent/JP2633199B2/en
Publication of JPH07331871A publication Critical patent/JPH07331871A/en
Application granted granted Critical
Publication of JP2633199B2 publication Critical patent/JP2633199B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、建築物等の基礎である
コンクリート製基礎(ラップルコンクリートとも言われ
る)の構築方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a concrete foundation (also referred to as wrapped concrete) which is a foundation of a building or the like.

【0002】[0002]

【従来の技術】従来のコンクリート製基礎の構築方法
は、図20に示すように、まずバックホー(ユンボとも
いう)で所定大きさの穴80を掘削し(a)、その底部
81に捨てコンクリート82を打ち(b)、その上に墨
出しを行い(c)、型枠83を構築する(d)。この場
合、型枠83が高い場合には足場84を仮組して作業を
行う。そして、前記型枠83内にコンクリート85を打
設し(e)、コンクリート85が硬化した時点で、作業
者が再度穴80内に入って型枠83を取り外し(f)、
周囲を埋め戻してコンクリート製基礎85を構築してい
た(g)。
2. Description of the Related Art As shown in FIG. 20, a conventional method of constructing a concrete foundation is as follows: first, a hole 80 having a predetermined size is excavated by a backhoe (also called a yumbo) (a), (B), black ink is printed thereon (c), and a mold 83 is constructed (d). In this case, when the form 83 is high, the work is performed by temporarily assembling the scaffold 84. Then, concrete 85 is poured into the form 83 (e), and when the concrete 85 is hardened, the operator again enters the hole 80 and removes the form 83 (f).
The surroundings were backfilled to construct a concrete base 85 (g).

【0003】[0003]

【発明が解決しようとする課題】しかしながら、従来の
コンクリート製基礎の構築方法においては、このように
掘削した穴80の中に作業者が入り作業をしなければな
らなかったので、掘った穴80の崩壊を防ぐため、穴8
0の断面を上部に開く形状にしなければならず、そのた
め穴80を掘った後の排土量及び埋め戻す土量が多いと
いう問題点があった。また、捨てコンクリート82が固
まるまで型枠83が取付けられず、更に型枠83を外す
場合にはコンクリート85が完全に硬化する必要がある
ので、作業に多くの日数(通常15〜20日程度)がか
かるという問題点があった。本発明はこのような事情に
鑑みてなされたもので、掘削時の排土量及び埋め戻す土
量を少なくし、また、型枠大工という技能工を必要とせ
ず、作業の日程を短縮するコンクリート製基礎の構築方
法を提供することを目的とする。
However, in the conventional method of constructing a concrete foundation, a worker had to enter the hole 80 excavated in this way to perform the work. Hole 8 to prevent collapse
Therefore, there is a problem that a large amount of soil is removed after the hole 80 is dug and the amount of soil to be backfilled is large. Further, the form 83 is not attached until the waste concrete 82 is hardened, and when the form 83 is removed, the concrete 85 needs to be completely hardened, so that many days (usually about 15 to 20 days) are required for the work. There was a problem that it took. The present invention has been made in view of such circumstances, and reduces the amount of earth removal during excavation and the amount of soil to be backfilled, and does not require a skilled carpenter, and shortens the work schedule. The purpose of the present invention is to provide a method of building a manufacturing base.

【0004】[0004]

【課題を解決するための手段】前記目的に沿う請求項1
記載のコンクリート製基礎の構築方法は、構築しようと
する基礎よりやや大きめの垂直穴を掘削する第1工程
と、前記垂直穴に、骨枠の外側に板材を固着した上下開
放の型枠を吊り込む第2工程と、前記型枠の外側を部分
的に埋め戻す第3工程と、前記型枠内に、前記埋め戻し
高さと同等か少し低い位置まで、生コンクリートを打設
する第4工程と、前記生コンクリートが固まらない内
に、前記型枠をその下部壁が前記生コンクリートの表面
に少し埋没する位置まで垂直に引き上げる第5工程と、
更に前記第3工程〜第5工程を繰り返して所定高のコン
クリート製基礎を構築するようにして構成されている。
また、請求項2記載のコンクリート製基礎の構築方法
は、請求項1記載の方法において、前記型枠には短脚が
設けられ、吊り込み時に前記短脚の載置部の高さ調整を
行い、該型枠を垂直にセットするようにして構成されて
いる。そして、請求項3記載のコンクリート製基礎の構
築方法は、構築しようとする基礎よりやや大きめの垂直
穴を掘削する第1工程と、構築しようとする前記基礎よ
り少し大きい上下開放の竪型の骨枠を吊り込む第2工程
と、前記骨枠の下部の高さ調整を行って、該骨枠を前記
垂直穴の略中心に垂直に立てる第3工程と、前記骨枠の
内側に板材を仮固定して、型枠を形成する第4工程と、
前記型枠内に生コンクリートを基礎の高さまで打設する
第5工程と、打設した前記コンクリートが硬化した後、
前記骨枠のみを引き上げて除去する第6工程と、前記骨
枠が除去された多数の板材を除去し、コンクリート基礎
の周囲を埋め戻す第7工程とを有して構成されている。
According to the present invention, there is provided a semiconductor device comprising:
The method for constructing a concrete foundation described in the first aspect includes a first step of excavating a vertical hole slightly larger than the foundation to be constructed, and suspending a vertically open formwork having a plate fixed to the outside of a bone frame in the vertical hole. A second step of embedding, a third step of partially backfilling the outside of the formwork, and a fourth step of pouring ready-mixed concrete into the formwork to a position equal to or slightly lower than the backfill height. A fifth step of vertically raising the formwork to a position where the lower wall is slightly buried in the surface of the ready-mixed concrete while the ready-mixed concrete does not solidify;
Further, the third to fifth steps are repeated to construct a concrete base having a predetermined height.
According to a second aspect of the present invention, in the method for constructing a concrete foundation according to the first aspect, a short leg is provided on the formwork, and the height of the mounting portion of the short leg is adjusted during suspension. , The mold is set vertically. The method of constructing a concrete foundation according to claim 3 includes a first step of excavating a vertical hole slightly larger than the foundation to be constructed, and a vertical bone having an upper and lower opening slightly larger than the foundation to be constructed. A second step of suspending the frame, a third step of adjusting the height of the lower portion of the bone frame, and erecting the bone frame vertically to substantially the center of the vertical hole, and temporarily placing a plate material inside the bone frame. A fourth step of fixing and forming a mold;
A fifth step of pouring ready-mixed concrete to the height of the foundation in the formwork, and after the poured concrete has hardened,
It comprises a sixth step of pulling up and removing only the bone frame, and a seventh step of removing a large number of plate members from which the bone frame has been removed and backfilling the periphery of the concrete foundation.

【0005】[0005]

【作用】請求項1、2記載のコンクリート製基礎の構築
方法においては、まず、構築しようとする基礎よりやや
大きめの垂直穴を掘削し、骨枠の外側に板材が固着され
た型枠を吊り込む。これによって、仮に土層が崩壊し易
い場所に基礎を構築する場合であっても、周囲の壁の崩
壊を前記型枠で防止することができる。この場合、前記
型枠の板材は骨枠の外側に固着されているので、土圧が
掛かっても、骨枠によって前記板材の内側への倒れを防
止することができる。次いで型枠の外側を部分的に埋め
戻す。これによって、型枠の板材が外側に倒れようとす
るのを、受け止めることができ、外側の埋め戻し高さと
同等か少し低い位置まで、生コンクリートを打設するこ
とができる。そして、前記生コンクリートが固まらない
内に、型枠をその下部壁が生コンクリートの表面に少し
埋没する位置まで垂直に引き上げる。これによって、外
側の埋め戻された土(砂利、石等も含む)が型枠となっ
て、内側のコンクリートの形状を確保できる。そして、
前記型枠を所定の高さまで引き上げて、上部の型枠とし
て使用するので、型枠の量を減らすことができる。以上
の工程を繰り返すことによって、少ない型枠で深い基礎
を構築することも可能となる。特に、請求項2記載のコ
ンクリート製基礎の構築方法においては、型枠には短脚
が設けられているので、型枠を垂直穴にセットする場合
には、前記短脚が乗る部分だけ、レベル調整を行って型
枠のレベル調整を行えば良い。即ち、仮に型枠に短脚が
無かった場合には、型枠の下部の辺の全ての広い範囲に
ついてレベル調整を行う必要があるが、本発明の場合に
は、短脚の部分(通常、4ケ所)で済むので、レベル調
整の期間短縮を図ることができる。そして、請求項3記
載のコンクリート製基礎の構築方法においては、まず、
構築しようとする基礎よりやや大きめの垂直穴を掘削
し、基礎の大きさより少し大きい上下開放の骨枠を吊り
込む。ここで、該骨枠のレベル調整を行うが、該骨枠の
最下部には水平部材を無くして、短脚を設けることが好
ましい。これによって、短脚の部分のレベルを調整する
ことによって、前記骨枠を垂直に垂直穴に立てることが
できる。そして、前記骨枠内に板材を張って番線等で仮
固定し、型枠を形成する。そして、型枠内に生コンクリ
ートを打設する。この場合、打設したコンクリートによ
って型枠に荷重が掛かるが、型枠を構成する板材は骨枠
の内側に張られているので、外側の骨枠によって荷重が
支持される。次に、前記生コンクリートが硬化した後、
外側の骨枠を引き上げる、これによって板材が自由とな
るので、板材をコンクリートから剥ぎ上部に引き上げて
除去する。この後、コンクリート基礎の周囲を埋め戻し
てコンクリート製基礎が完成する。
In the method for constructing a concrete foundation according to the first and second aspects, first, a vertical hole slightly larger than the foundation to be constructed is excavated, and a formwork having a plate material fixed to the outside of the bone frame is hung. Put in. Thereby, even if the foundation is constructed in a place where the soil layer is likely to collapse, the collapse of the surrounding wall can be prevented by the formwork. In this case, since the plate material of the mold is fixed to the outside of the bone frame, the bone frame can prevent the plate material from falling inward even when earth pressure is applied. The outside of the mold is then partially backfilled. In this way, it is possible to catch the plate material of the form from going to the outside, and it is possible to cast the ready-mixed concrete to a position equal to or slightly lower than the outside backfill height. Then, while the ready-mixed concrete does not solidify, the form is lifted vertically to a position where the lower wall is slightly buried in the surface of the ready-mixed concrete. As a result, the outer backfilled soil (including gravel, stone, and the like) forms a formwork, and the shape of the inner concrete can be secured. And
Since the mold is raised to a predetermined height and used as an upper mold, the amount of the mold can be reduced. By repeating the above steps, a deep foundation can be constructed with a small number of molds. In particular, in the method for constructing a concrete foundation according to claim 2, since the formwork is provided with a short leg, when the formwork is set in a vertical hole, only the portion on which the short leg rides is leveled. The level of the formwork may be adjusted by performing the adjustment. That is, if there is no short leg in the mold, it is necessary to adjust the level over the entire wide range of the lower side of the mold, but in the case of the present invention, the portion of the short leg (usually, (4 places), so that the level adjustment period can be shortened. And in the construction method of the concrete foundation of Claim 3, first,
Drill a vertical hole slightly larger than the foundation to be built, and suspend an open and closed bone frame slightly larger than the foundation. Here, the level of the bone frame is adjusted, but it is preferable to provide a short leg without a horizontal member at the bottom of the bone frame. Thus, by adjusting the level of the short leg portion, the bone frame can be vertically set in the vertical hole. Then, a plate is stretched in the bone frame and temporarily fixed with a number line or the like to form a mold. Then, ready-mixed concrete is poured into the formwork. In this case, a load is applied to the form by the cast concrete, but since the plate material forming the form is stretched inside the bone frame, the load is supported by the outer bone frame. Next, after the ready-mixed concrete has hardened,
The outer bone frame is pulled up, which frees the plate, so that the plate is peeled off the concrete and pulled up to remove it. Thereafter, the surroundings of the concrete foundation are backfilled to complete the concrete foundation.

【0006】[0006]

【実施例】続いて、添付した図面を参照しつつ、本発明
を具体化した実施例につき説明し、本発明の理解に供す
る。ここに、図1〜図10は本発明の第1の実施例に係
るコンクリート製基礎の構築方法の工程説明図、図11
は同方法に使用する型枠の側面図、図12〜図19は本
発明の第2の実施例に係るコンクリート製基礎の構築方
法の工程説明図である。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments embodying the present invention will now be described with reference to the accompanying drawings to provide an understanding of the present invention. Here, FIG. 1 to FIG. 10 are process explanatory diagrams of a method for constructing a concrete foundation according to the first embodiment of the present invention, and FIG.
Is a side view of a mold used in the method, and FIGS. 12 to 19 are process explanatory diagrams of a method of constructing a concrete foundation according to a second embodiment of the present invention.

【0007】まず、図1〜図11を参照しながら、本発
明の第1の実施例に係るコンクリート製基礎の構築方法
について説明する。図1に示すように、まずバックホー
10で構築しようとする基礎より120〜160cm程
度幅の広い深さ約5mの垂直穴11を掘削する。そし
て、図2に示すように予め組み立てた型枠12を前記バ
ックホー10を用いて前記垂直穴11の中央に吊り込
む。
First, a method of constructing a concrete foundation according to a first embodiment of the present invention will be described with reference to FIGS. As shown in FIG. 1, first, a vertical hole 11 having a depth of about 5 m and a width of about 120 to 160 cm wider than a foundation to be constructed with the backhoe 10 is excavated. Then, as shown in FIG. 2, the pre-assembled formwork 12 is hung in the center of the vertical hole 11 using the backhoe 10.

【0008】前記型枠12は平面視して4角形となっ
て、図11に示すように周囲の4本の柱13、及びこれ
らを結ぶ3本の梁14〜16を有する骨枠17と、該骨
枠17の外側を囲む複数の板材(矢板、通常は30mm
×210mm×2〜4m)18からなっている。前記梁
14〜16及び柱13には適当に取付け孔が形成され
て、前記複数枚の板材18は該骨枠17に、番線19あ
るいは必要に応じて木製の当て板を用いて釘付けされ
て、略完全に固定されている。なお、最下部の梁15は
板材18の下端から約50〜60cmの位置に配置され
ている。打設した生コンクリート中に梁15が埋設しな
いようになっている。なお、前記側板18をねじを用い
て骨枠17に固定することも可能である。
The mold 12 has a quadrangular shape in plan view, and as shown in FIG. 11, a bone frame 17 having four surrounding pillars 13 and three beams 14 to 16 connecting them. A plurality of plate members (sheet pile, usually 30 mm) surrounding the outside of the bone frame 17.
× 210 mm × 2 to 4 m) 18. Mounting holes are appropriately formed in the beams 14 to 16 and the pillars 13, and the plurality of plate members 18 are nailed to the bone frame 17 by using a wire 19 or a wooden backing plate as necessary. Almost completely fixed. Note that the lowermost beam 15 is disposed at a position of about 50 to 60 cm from the lower end of the plate 18. The beam 15 is not buried in the poured concrete. The side plate 18 can be fixed to the bone frame 17 using screws.

【0009】前記それぞれの骨枠17の下部には柱13
を板材18の下端から10〜20cm延長して短脚21
が形成され、更に4角の柱13の上部には取付け孔22
が形成されて、シャックル23を用いて吊りワイヤ24
の端部を固定し、図2に示すようにバックホー10で該
型枠12を吊ることができるようになっている。なお、
この型枠12の内側大きさ平面が構築しようとする基礎
の平面と同一になっている。
At the bottom of each bone frame 17 is a column 13
Is extended 10 to 20 cm from the lower end of the
Are formed, and a mounting hole 22 is formed in the upper part of the square pillar 13.
Is formed, and the suspension wire 24 is
Is fixed, and the formwork 12 can be hung by the backhoe 10 as shown in FIG. In addition,
The inner size plane of the mold 12 is the same as the plane of the foundation to be constructed.

【0010】前記型枠12を図3に示すように、垂直穴
11に入れ込むと、穴底25のレベル(平面)は出てい
ないので、該型枠12は傾くことになる。そこで、図4
に示すように、4角の短脚21の下部をはつり機(ピッ
ク、ブレーカー)26が掘って一定のレベルを出し、該
型枠12を垂直に立てる。この場合、垂直穴11の側壁
28の部分的崩壊があっても、型枠12によって内側の
作業者を守ることができる。
When the mold 12 is inserted into the vertical hole 11, as shown in FIG. 3, the level (plane) of the hole bottom 25 does not come out, so that the mold 12 is inclined. Therefore, FIG.
As shown in (1), the lower part of the square short leg 21 is dug by a lifting machine (pick, breaker) 26 to set a certain level, and the formwork 12 is set up vertically. In this case, even if there is a partial collapse of the side wall 28 of the vertical hole 11, the mold 12 can protect the inside worker.

【0011】次に、図5に示すように作業者27が穴底
25を整地する。これによって余分な土砂を除去し、穴
底25と構築する基礎との固着性を増加させる。なお、
ここで、29はタラップである。そして、作業者27を
該垂直穴11から退避させた後、型枠12と垂直穴11
の隙間30を50〜100cm程度埋め戻す。これによ
って、板材18を外側から骨枠17に押し付けて型枠1
2の補強を行うことができる。
Next, as shown in FIG. 5, a worker 27 levels the hole bottom 25. This removes excess earth and sand and increases the adhesion between the hole bottom 25 and the foundation to be built. In addition,
Here, 29 is a ramp. Then, after retracting the worker 27 from the vertical hole 11, the mold 12 and the vertical hole 11 are removed.
Is filled back by about 50 to 100 cm. As a result, the plate 18 is pressed against the bone frame 17 from the outside, and
2 reinforcements can be performed.

【0012】続いて、図6に示すようにコンクリートミ
キサ車31で埋め戻し土砂の高さと同位置まで生コンク
リート32を充填する。なお、生コンクリート32の充
填高さは埋め戻し土砂と略同一であることが好ましく、
少ない場合には工事能率が悪くなり、多くなれば板材1
8が過大な力を受けて破損したり、生コンクリート32
が板材18の隙間から漏れる等の障害が生ずる。
Subsequently, as shown in FIG. 6, a ready-mixed concrete 32 is filled with a concrete mixer truck 31 to the same height as the backfill soil. In addition, it is preferable that the filling height of the ready-mixed concrete 32 is substantially the same as the backfilled earth and sand,
If the number is small, the construction efficiency will be poor.
8 is damaged by excessive force,
Is leaked from the gap of the plate 18.

【0013】次に、図7に示すように、バックホー10
を用いて、生コンクリート32が固まらない内に型枠1
2を少し引き上げる。この場合の型枠12の引上げ高さ
は型枠12の下部の板材18が生コンクリート32の表
面から少し埋没する位置までとする。それから、再び型
枠12と垂直穴11の隙間30を50〜100cm程
度、土砂で埋め戻して、コンクリートミキサ車31で埋
め戻し高さと同位置まで生コンクリート32を入れる。
Next, as shown in FIG.
While the ready-mixed concrete 32 is not solidified,
Raise 2 slightly. In this case, the pulling height of the mold 12 is set to a position where the plate 18 below the mold 12 is slightly buried from the surface of the ready-mixed concrete 32. Then, the gap 30 between the mold 12 and the vertical hole 11 is backfilled with earth and sand by about 50 to 100 cm, and the fresh concrete 32 is put into the concrete mixer truck 31 to the same height as the backfill height.

【0014】以上の埋め戻しと生コンクリート打設作業
を、生コンクリート打設位置が所定高(2〜3m又はそ
れ以上)になるまで繰り返し、コンクリートの打設高さ
が所定高に到達したなら、図9に示すように、型枠12
が生コンクリート32の表面に少し埋没する位置まで引
上げ(約、50cm程度埋没するのが好ましい)、基礎
上部の土との境界線を明確化するため、生コンクリート
32が硬化した後、型枠12を引き上げ、基礎33の工
事が一応完了する。
The above-mentioned backfilling and ready-cast concrete placement work is repeated until the ready-cast concrete placement position reaches a predetermined height (2 to 3 m or more). As shown in FIG.
Is pulled up to a position where it is slightly buried in the surface of the ready-mixed concrete 32 (preferably about 50 cm buried). And the construction of the foundation 33 is temporarily completed.

【0015】なお、以上の工事は予め用意されたアング
ル材から骨枠17を作りその周囲に板材18を取付けて
型枠12を作るのが1日、型枠12を垂直穴11に入れ
て生コンクリート32を打設し、一応の基礎を構築する
のに2日、打設したコンクリートを養生するのに3日程
度でできるので、合計で6〜7日程度となり極めて作業
工程が短いという利点を有する。また、前記第1の実施
例に係るコンクリート製基礎の構築方法は、垂直穴11
内で作業を行う場合であっても、周囲に型枠12がある
ので、比較的崩壊が起こり易い地盤であっても安全に作
業できる。
In the construction described above, it is one day to form the frame 12 by forming the bone frame 17 from the angle material prepared in advance and mounting the plate 18 around the frame 17 to insert the frame 12 into the vertical hole 11 for one day. It takes about 2 to 2 days to put concrete 32 and build a temporary foundation, and about 3 days to cure the poured concrete. The total work time is about 6 to 7 days. Have. Further, the method for constructing a concrete foundation according to the first embodiment includes the steps of:
Even when the work is performed inside, since the formwork 12 is provided around the work, the work can be performed safely even on the ground that is relatively easily collapsed.

【0016】続いて、図12〜図19を参照しながら、
本発明の第2の実施例に係るコンクリート製基礎の構築
方法を説明する。図12に示すように、バックホー10
で構築しようとする基礎より20〜100cm程度大き
い垂直穴35を掘削し、この中に予めアングル材を組み
立てた骨枠36を吊りワイヤ37等で吊って、図13に
示すように該垂直穴35の中央に前記骨枠36を入れ
る。なお、この骨枠36の下部の4角には短脚38が設
けられている。
Subsequently, referring to FIGS. 12 to 19,
A method for constructing a concrete foundation according to a second embodiment of the present invention will be described. As shown in FIG.
A vertical hole 35 larger than the foundation to be constructed by about 20 to 100 cm is excavated, and a bone frame 36 in which an angle member is assembled in advance is hung by a hanging wire 37 or the like, and as shown in FIG. Put the bone frame 36 in the center of the frame. Short legs 38 are provided at the lower four corners of the bone frame 36.

【0017】そして、図14に示すように前記短脚38
が乗る穴底39を前記はつり機26ではつってレベルを
出し、該骨枠36を垂直に建てる。そして、必要な場合
には、穴底39の整地を行う。次に、該骨枠36の内側
に板材(矢板)40を番線、場合によっては釘等を利用
して張り巡らし、上下開放の型枠41を形成する。この
場合、図15に示すように、骨枠36の上部の梁42及
び中間の梁43と板材40との間に楔44を打ち込み、
板材38を内側に僅少の範囲(1度程度)倒し、図16
に示すように型枠41を垂直穴35内に垂直状態で配置
する。
Then, as shown in FIG.
The hole bottom 39 on which the vehicle rides is lifted by the lifting machine 26 to raise the level, and the bone frame 36 is erected vertically. If necessary, the hole bottom 39 is leveled. Next, a plate material (sheet pile) 40 is stretched around the inside of the bone frame 36 by using a line, and in some cases a nail or the like, to form a vertically open mold frame 41. In this case, as shown in FIG. 15, a wedge 44 is driven between the plate 42 and the upper beam 42 and the intermediate beam 43 of the bone frame 36,
FIG. 16 shows a state in which the plate member 38 is tilted in a small area (about 1 degree) inside.
The mold 41 is placed in the vertical hole 35 in a vertical state as shown in FIG.

【0018】次に、図17に示すように、コンクリート
ミキサー車31で生コンクリート45を型枠41内に構
築しようとする基礎の高さまで流し込み、1〜2日放置
してコンクリートを硬化させる。
Next, as shown in FIG. 17, the ready-mixed concrete 45 is poured into the form 41 by the concrete mixer truck 31 to the height of the foundation to be constructed, and left for 1-2 days to harden the concrete.

【0019】コンクリートが硬化して一応の基礎46が
形成された後、図18(A)に示すように挿入した楔4
4を抜く。この楔44は個々に抜いても良いが、骨枠3
6を少し持ち上げることによって抜いてもよい。この状
態で、図18(B)に示すように、板材40と基礎46
とが離れることになる。図19に示すように骨枠36を
完全に上昇させると、板材40は基礎46から離れるこ
とになるので、全部取り出し、基礎と垂直穴35との間
を埋め戻して一応のコンクリート製基礎が完成する。
After the concrete has hardened to form a temporary foundation 46, the wedge 4 inserted as shown in FIG.
Pull out 4. The wedges 44 may be pulled out individually,
6 may be removed by slightly lifting it up. In this state, as shown in FIG.
And will be separated. When the bone frame 36 is completely lifted as shown in FIG. 19, the plate member 40 is separated from the foundation 46. Therefore, all of the plate members 40 are taken out, and the space between the foundation and the vertical hole 35 is backfilled to complete a temporary concrete foundation. I do.

【0020】なお、第2の実施例に係るコンクリート製
基礎の構築方法は、垂直穴35の側面が比較的硬く崩壊
しにくい地盤の場合に適用でき、垂直穴35を構築後、
型枠41を正確に配置するまでの工程が約1日、生コン
クリート45を打設して硬化するまでの期間が2日程度
であるので極めて短期間の内に工事が完了する。
The method for constructing a concrete foundation according to the second embodiment can be applied to the case where the side surface of the vertical hole 35 is relatively hard and hard to collapse.
Since the process until the mold 41 is accurately arranged is about one day, and the period from when the fresh concrete 45 is cast and hardened is about two days, the construction is completed in a very short time.

【0021】前記実施例においては、板材として木板を
使用したが、十分強度を有する強化プラスチック等であ
ってもよい。また、バックホーを使用して型枠の吊り下
げを行っていたが、クレーン車等を利用することは当然
可能である。また、前記基礎はこの実施例においては、
平面視して四角であったが、円形、楕円形等であっても
本発明は適用される。更には、第1の実施例において、
小型の基礎の構築においては、型枠は予め、金属、FR
P、アルミ、木材あるいはこれらの複合材料によって一
体物として作っていてもよい。
In the above embodiment, a wooden board is used as the board, but a reinforced plastic or the like having sufficient strength may be used. In addition, the formwork is suspended using a backhoe, but it is naturally possible to use a crane truck or the like. Also, the basis is in this embodiment:
Although square in plan view, the present invention is applicable to a circular or elliptical shape. Further, in the first embodiment,
In the construction of small foundations, the formwork is pre-
It may be made of P, aluminum, wood, or a composite material of them as an integral product.

【0022】[0022]

【発明の効果】請求項1及び2記載のコンクリート製基
礎の構築方法は、垂直穴に吊り込んだ型枠の外周を埋め
戻す作業と型枠内に生コンクリートを打設する作業を繰
り返すことによって、所定高のコンクリート製基礎(ラ
ップル基礎)を構築する方法なので、深基礎を少ない型
枠で構築できる。そして、掘削時の排土量及び埋め戻す
土量が少なくて済み、型枠大工等も不要となり、更には
作業日数の短縮をすることができる。請求項3記載のコ
ンクリート製基礎の構築方法においても、型枠大工が不
要となり、極めて短い期間でコンクリート製基礎(ラッ
プル基礎)を構築できる。
According to the first and second aspects of the present invention, the method of constructing a concrete foundation is carried out by repeating the operation of backfilling the outer periphery of the form suspended from the vertical hole and the operation of placing ready-mixed concrete into the form. Since it is a method of constructing a concrete foundation (lapple foundation) having a predetermined height, a deep foundation can be constructed with a small formwork. In addition, the amount of soil removed during excavation and the amount of soil to be backfilled can be reduced, and a formwork carpenter or the like is not required, and the number of working days can be reduced. In the method for constructing a concrete foundation according to claim 3, a formwork carpenter is not required, and a concrete foundation (lapple foundation) can be constructed in an extremely short period of time.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の第1の実施例に係るコンクリート製基
礎の構築方法の工程説明図である。
FIG. 1 is a process explanatory diagram of a method for constructing a concrete foundation according to a first embodiment of the present invention.

【図2】同工程説明図である。FIG. 2 is an explanatory view of the same step.

【図3】同工程説明図である。FIG. 3 is an explanatory view of the same step.

【図4】同工程説明図である。FIG. 4 is an explanatory view of the same step.

【図5】同工程説明図である。FIG. 5 is an explanatory view of the process.

【図6】同工程説明図である。FIG. 6 is an explanatory view of the same step.

【図7】同工程説明図である。FIG. 7 is an explanatory diagram of the same step.

【図8】同工程説明図である。FIG. 8 is an explanatory diagram of the same step.

【図9】同工程説明図である。FIG. 9 is an explanatory diagram of the same step.

【図10】同工程説明図である。FIG. 10 is an explanatory diagram of the same step.

【図11】同方法に使用する型枠の側面図である。FIG. 11 is a side view of a mold used in the method.

【図12】本発明の第2の実施例に係るコンクリート製
基礎の構築方法の工程説明図である。
FIG. 12 is an explanatory diagram of steps of a method for constructing a concrete foundation according to the second embodiment of the present invention.

【図13】同工程説明図である。FIG. 13 is an explanatory diagram of the same step.

【図14】同工程説明図である。FIG. 14 is an explanatory diagram of the same step.

【図15】同工程説明図である。FIG. 15 is an explanatory diagram of the same step.

【図16】同工程説明図である。FIG. 16 is an explanatory diagram of the same step.

【図17】同工程説明図である。FIG. 17 is an explanatory diagram of the same step.

【図18】同工程説明図である。FIG. 18 is an explanatory diagram of the same step.

【図19】同工程説明図である。FIG. 19 is an explanatory diagram of the same step.

【図20】従来例に係るコンクリート製基礎の構築方法
の説明図である。
FIG. 20 is an explanatory diagram of a method of constructing a concrete foundation according to a conventional example.

【符号の説明】[Explanation of symbols]

10 バックホー 11 垂直穴 12 型枠 13 柱 14 梁 15 梁 16 梁 17 骨枠 18 板材 19 番線 21 短脚 22 取付け孔 23 シャックル 24 吊りワイヤ 25 穴底 26 はつり機 27 作業者 28 側壁 29 タラップ 30 隙間 31 コンクリートミキサー車 32 生コンクリート 33 基礎 35 垂直穴 36 骨枠 37 吊りワイヤ 38 短脚 39 穴底 40 板材 41 型枠 42 梁 43 梁 44 楔 45 生コンクリート 46 基礎 DESCRIPTION OF SYMBOLS 10 Backhoe 11 Vertical hole 12 Formwork 13 Column 14 Beam 15 Beam 16 Beam 17 Bone frame 18 Plate material 19 Track 21 Short leg 22 Mounting hole 23 Shackle 24 Suspension wire 25 Hole bottom 26 Hanging machine 27 Worker 28 Side wall 29 Trap 30 Gap 31 Concrete mixer truck 32 Ready-mixed concrete 33 Foundation 35 Vertical hole 36 Bone frame 37 Suspension wire 38 Short leg 39 Hole bottom 40 Plate 41 Formwork 42 Beam 43 Beam 44 Wedge 45 Ready-mixed concrete 46 Foundation

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 構築しようとする基礎よりやや大きめの
垂直穴を掘削する第1工程と、前記垂直穴に、骨枠の外
側に板材を固着した上下開放の型枠を吊り込む第2工程
と、前記型枠の外側を部分的に埋め戻す第3工程と、前
記型枠内に、前記埋め戻し高さと同等か少し低い位置ま
で、生コンクリートを打設する第4工程と、前記生コン
クリートが固まらない内に、前記型枠をその下部壁が前
記生コンクリートの表面に少し埋没する位置まで垂直に
引き上げる第5工程と、更に前記第3工程〜第5工程を
繰り返して所定高のコンクリート製基礎を構築すること
を特徴とするコンクリート製基礎の構築方法。
1. A first step of excavating a vertical hole slightly larger than a foundation to be constructed, and a second step of suspending a vertically open formwork having a plate material fixed to the outside of a bone frame in the vertical hole. A third step of partially backfilling the outside of the formwork, a fourth step of pouring ready-mixed concrete into the formwork to a position equal to or slightly lower than the backfill height, A fifth step of vertically raising the formwork to a position where its lower wall is slightly buried in the surface of the ready-mixed concrete while the form is not set; and repeating the third to fifth steps to further increase the concrete foundation having a predetermined height. A method of constructing a concrete foundation, characterized by constructing a concrete foundation.
【請求項2】 前記型枠には短脚が設けられ、吊り込み
時に前記短脚の載置部の高さ調整を行い、該型枠を垂直
にセットする請求項1記載のコンクリート製基礎の構築
方法。
2. The concrete base according to claim 1, wherein a short leg is provided on the formwork, the height of the mounting portion of the short leg is adjusted during suspension, and the formwork is set vertically. How to build.
【請求項3】 構築しようとする基礎よりやや大きめの
垂直穴を掘削する第1工程と、構築しようとする前記基
礎より少し大きい上下開放の竪型の骨枠を吊り込む第2
工程と、前記骨枠の下部の高さ調整を行って、該骨枠を
前記垂直穴の略中心に垂直に立てる第3工程と、前記骨
枠の内側に板材を仮固定して、型枠を形成する第4工程
と、前記型枠内に生コンクリートを基礎の高さまで打設
する第5工程と、打設した前記コンクリートが硬化した
後、前記骨枠のみを引き上げて除去する第6工程と、前
記骨枠が除去された多数の板材を除去し、コンクリート
基礎の周囲を埋め戻す第7工程とを有してなることを特
徴とするコンクリート製基礎の構築方法。
3. A first step of excavating a vertical hole slightly larger than a foundation to be constructed, and a second step of suspending a vertically-open vertical frame slightly larger than the foundation to be constructed.
And a third step of adjusting the height of the lower part of the bone frame so that the bone frame stands upright at substantially the center of the vertical hole; and temporarily fixing a plate material inside the bone frame, A fourth step of forming the concrete, a fifth step of placing the ready-mixed concrete into the form to the height of the foundation, and a sixth step of pulling up and removing only the bone frame after the poured concrete has hardened. And a seventh step of removing a number of plate members from which the bone frame has been removed and backfilling the periphery of the concrete foundation.
JP14870794A 1994-06-06 1994-06-06 How to build a concrete foundation Expired - Lifetime JP2633199B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14870794A JP2633199B2 (en) 1994-06-06 1994-06-06 How to build a concrete foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14870794A JP2633199B2 (en) 1994-06-06 1994-06-06 How to build a concrete foundation

Publications (2)

Publication Number Publication Date
JPH07331871A JPH07331871A (en) 1995-12-19
JP2633199B2 true JP2633199B2 (en) 1997-07-23

Family

ID=15458805

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14870794A Expired - Lifetime JP2633199B2 (en) 1994-06-06 1994-06-06 How to build a concrete foundation

Country Status (1)

Country Link
JP (1) JP2633199B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5003253B2 (en) * 2007-04-04 2012-08-15 鹿島建設株式会社 RC beam construction method
JP7232714B2 (en) * 2019-05-31 2023-03-03 株式会社安藤・間 how to build a foundation
KR102337202B1 (en) * 2021-04-02 2021-12-10 (주)세정엔지니어링 Rock crushing eco-friendly multi electric excavator for remote control and excavation method using the same

Also Published As

Publication number Publication date
JPH07331871A (en) 1995-12-19

Similar Documents

Publication Publication Date Title
JP2002256573A (en) Foundation for existing foundation reinforcing steel tower and construction method for it
JP2633199B2 (en) How to build a concrete foundation
JPH05500249A (en) Formwork for forming structural beams
US6328503B1 (en) Method for constructing an underground structure
JPH0684690B2 (en) Building basement extension method
JPS6290445A (en) Block for foundation and its manufacture
JP4267175B2 (en) Construction method of underground structure
JP2566197B2 (en) Construction method of underground structure and its equipment
JP4351331B2 (en) Construction method of layered underground structure
JP2001055739A (en) Construction method for artificially excavated pressure receiving plate of slope reinforcing anchor bar
JP4045623B2 (en) Construction method of reinforced concrete underground floor and underground structure constructed by this method
JPH10299003A (en) Foundation work using precast concrete member
JP2838019B2 (en) Caisson blade framing method
JP3567387B2 (en) How to build an underground skeleton
JPS6355277A (en) Construction of liquid storage tank
JPH02248527A (en) Constructing foundation structure
JP3179243B2 (en) Concrete placement method for deep foundation work
EP1662049A2 (en) Method for positioning concrete piles
JP2524892B2 (en) Building foundation method
JP2520037B2 (en) How to build a seismic isolated building
JPH02279822A (en) Construction of foundation and underground beam
JPH04108920A (en) Concrete foundation form and foundation constructing method
JP3328580B2 (en) Construction method of L-shaped retaining wall
JPH048572B2 (en)
JPH0376931A (en) Construction of housing foundation