JPH0469270B2 - - Google Patents
Info
- Publication number
- JPH0469270B2 JPH0469270B2 JP61024112A JP2411286A JPH0469270B2 JP H0469270 B2 JPH0469270 B2 JP H0469270B2 JP 61024112 A JP61024112 A JP 61024112A JP 2411286 A JP2411286 A JP 2411286A JP H0469270 B2 JPH0469270 B2 JP H0469270B2
- Authority
- JP
- Japan
- Prior art keywords
- foundation
- hydraulic cylinder
- jack
- support device
- lower base
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000009412 basement excavation Methods 0.000 description 4
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 238000009415 formwork Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000010276 construction Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は、地盤沈下により基礎杭と共に沈下し
た重量構造物を、ジヤツキ等により扛上させる方
法に関するものである。DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method of lifting a heavy structure, which has sunk together with a foundation pile due to ground subsidence, by using a jack or the like.
(従来の技術)
重量構造物を構築するに当つては、通常、地中
に多数の基礎杭を先端が岩盤等の支持層に達する
まで打ち込み、その上に基礎を設けて構造物を作
るのであるが、これら基礎杭が充分に支持層に達
していなかつた場合は、構造物は地盤の沈下によ
り基礎杭と共に沈下して基礎杭先端が支持層上に
安定するまで下降を続け、この結果、構造物は全
面的に沈下、あるいは不同沈下して一方に傾斜し
てしまう。(Prior art) When constructing a heavy structure, the structure is usually constructed by driving a large number of foundation piles into the ground until the tips reach a supporting layer such as bedrock, and then setting a foundation on top of the piles. However, if these foundation piles do not reach the support layer sufficiently, the structure will sink together with the foundation piles due to ground subsidence and continue to descend until the tip of the foundation pile is stable on the support layer. The structure may sink completely, or may settle unevenly and tilt to one side.
このような状態となつた構造物をもとの状態に
復元するには、第3図に示すように構造物9の基
礎下面に当る部分を掘削して基礎杭8の上部を露
出させたのち、その隣接する一方の杭上端を切除
し、これら切除された基礎杭上面またはこれに代
る仮基礎台上面と構造物の基礎下面との間にジヤ
ツキ10′を挿入して構造物9を押し上げ、所要
高さとしたのち、この基礎下部分を型枠で囲み、
そこにコンクリートを流し込んで全体を定着させ
るものであるが、この場合、構造物を平均に押し
上げるために、多数のジヤツキ10′は一斉に操
作され、かつ油圧シリンダーによる押上げと同時
に押し上げた構造物が下降しないように適宜の枕
材を少しずつ押し込んで行く必要がある。 In order to restore a structure in such a state to its original state, as shown in Figure 3, excavate the area corresponding to the lower surface of the foundation of the structure 9 to expose the upper part of the foundation pile 8. , remove the upper end of one of the adjacent piles, and push up the structure 9 by inserting a jack 10' between the removed upper surface of the foundation pile or the upper surface of a temporary foundation instead of this and the lower surface of the foundation of the structure. , After achieving the required height, surround the lower part of this foundation with formwork,
Concrete is poured there to fix the whole structure, but in this case, in order to evenly push up the structure, a large number of jacks 10' are operated at the same time, and the structure is pushed up at the same time as the hydraulic cylinder is pushed up. It is necessary to push in appropriate pillow material little by little to prevent it from descending.
しかし、ジヤツキを載架した基礎杭の切除上面
は少面積であるたら枕材を入れる余裕がなく、こ
のためジヤツキ10′としては、第4図に示すよ
うに油圧シリンダ7′の上方にネジ部1′を有する
一般にユニバーサルジヤツキと呼ばれるものが使
用され、油圧シリンダ7′を介して少しずつ押し
上げるごとに、ネジ部1′のネジを回動して構造
物が下降しないように保持している。こうして所
要高さに達したならば、各ジヤツキに接続されて
いた油圧ポンプよりの配管をはずしたのち、当該
基礎下部を型枠で囲み、そこにコンクリートを充
填して、各ジヤツキごと全体を一体化する。 However, if the area of the excised upper surface of the foundation pile on which the jack is mounted is small, there is no room for inserting the pillow material, and for this reason, the jack 10' has a threaded section above the hydraulic cylinder 7', as shown in Fig. 4. 1' is generally used, and each time the structure is pushed up little by little via a hydraulic cylinder 7', the screw of the threaded part 1' is rotated to hold the structure from falling. . Once the required height has been reached, the piping from the hydraulic pump connected to each jack is removed, and the lower part of the foundation is surrounded with formwork, filled with concrete, and the entire jack is assembled into one piece. become
(発明が解決しようとする問題点)
しかし、上記方法において用いられるジヤツキ
10′は狭あいな基礎杭上面と載架するため、第
4図に示したように上方に長く、つまり油圧シリ
ンダ7′部分とネジ部1′により実際の上昇高さの
2倍以上の高さであるから、前記第3図に示すよ
うに構造物下面を基礎杭の間をくぐつて、このジ
ヤツキ使用できる高さまで掘削することは非常に
手間を要する作業であり、また、掘削工費がない
ので工費がかさむ。ジヤツキ10′自体は分解で
きない一体製品であつて、重量が180〜360Kgもあ
るが人力運搬に頼よらざるを得ず、上記掘削とと
もに作業が極めて困難である。さらに、扛上を終
つてコンクリート打ちするときには、このジヤツ
キを取り去ることはできないから、各ジヤツキは
すべてコンクリート中に埋没され、いわゆる埋没
しされるので極めて不経済である。(Problems to be Solved by the Invention) However, since the jack 10' used in the above method is mounted on the upper surface of the foundation pile in a narrow space, it is extended upwardly as shown in FIG. Since the height is more than twice the actual height due to the screw part 1' and the screw part 1', the lower surface of the structure should be passed between the foundation piles and excavated to a height where this jack can be used, as shown in Figure 3 above. This is a very time-consuming task, and since there is no excavation cost, the construction costs are high. The jack 10' itself is a one-piece product that cannot be disassembled and weighs 180 to 360 kg, but must be carried by hand, making it extremely difficult to work with the excavation described above. Furthermore, when pouring concrete after the lifting, it is not possible to remove the jacks, so all the jacks are buried in the concrete, which is extremely uneconomical.
(問題点を解決するための手段)
これに対し、本発明は油圧シリンダ部分とネジ
部分を別体に作り、しかもネジ部分が油圧シリン
ダ部分を取りまく受台に形成すれば、その高さを
上昇高さに近づけることができ、かつコンクリー
ト打ちに当つては、この受台だけを埋没すればよ
いことに着目し、しかも、この受台のネジ部分
は、油圧シリンダにより押し上げられた構造物を
単に下降しないように支えるだけのものであるか
ら、ネジ構造も極めて簡単なものでよい点に着目
して完成されたものである。(Means for solving the problem) In contrast, the present invention makes the hydraulic cylinder part and the threaded part separate, and if the threaded part is formed into a pedestal surrounding the hydraulic cylinder part, the height of the hydraulic cylinder part can be increased. We focused on the fact that only this pedestal needs to be buried when pouring concrete, and the threaded part of this pedestal can be used to easily hold the structure pushed up by a hydraulic cylinder. It was completed with the focus on the fact that the screw structure could be extremely simple since it only serves to support it so that it does not fall.
(発明の実施例)
第1図は本発明を実施するに当つて使用する扛
上支持装置1を示す。第1図から明らかなよう
に、装置全体は方形の下部台板2の上面各隅部に
それぞれ直管3を立設するとともに、方形の上部
台板4の下面各隅部に螺杆5を垂下取付し、これ
らの螺杆5にナツト6を各々螺合して、各螺杆5
を上記直管3に挿入して形成され、各ナツト6を
一定高さにセツトすることにより上下台板4,2
間の間隔を所定高さに定めることができる。上下
台板4,2の大きさは上端を切除された基礎杭の
上面に安定して載架できる大きさであり、かつ各
直管3の間隔は油圧シリンダ7を自由に出入れで
きる寸法になつている。なお、本発明の装置を使
用する際には、上端を切除された基礎台の上面と
しては、仮基礎台の上面を使用することもでき
る。またこの扛上支持装置は上下転倒状態で使用
してもよいことは勿論である。(Embodiment of the Invention) FIG. 1 shows a lifting support device 1 used in carrying out the present invention. As is clear from FIG. 1, the entire device has straight pipes 3 erected at each corner of the upper surface of a rectangular lower base plate 2, and screw rods 5 hanging from each corner of the lower surface of a rectangular upper base plate 4. and screw the nuts 6 onto these screw rods 5, respectively, to tighten each screw rod 5.
is formed by inserting it into the straight pipe 3, and by setting each nut 6 at a constant height, the upper and lower base plates 4, 2
The interval between the two can be set to a predetermined height. The upper and lower base plates 4 and 2 are large enough to be stably mounted on the top surface of the foundation pile whose upper end has been cut off, and the intervals between the straight pipes 3 are such that the hydraulic cylinder 7 can be freely inserted and removed. It's summery. Note that when using the device of the present invention, the upper surface of a temporary foundation can also be used as the upper surface of the foundation with its upper end cut off. Of course, this lifting support device may also be used in an upside down state.
以下に、本発明の装置を使用して重構造物を扛
上支持する順序を説明する。まず、前記従来の方
法と同じように構造物の基礎下面を掘削するので
あるが、その深さは、掘削後、上端を切除された
基礎杭の上面(または仮基礎台の上面)から構造
物の下面に至る高さが扛上支持装置1を装入でき
る高さであればよく、すなわち短縮時における油
圧シリンダ7の高さより若干高い程度でよい。こ
うして、切除された基礎杭8の頂面に構造物9の
基礎下面との間に扛上支持装置1を位置させ、上
記台板4,2の間に油圧シリンダ7を収容する。
(第2図A)
油圧シリンダ7を、別に設けた油圧ポンプ機構
を介して作動させ、上部台板4共に構造物9の基
礎を押し上げ、この状態でナツト6を回動し各直
管3の口縁に圧接させる。(第2図B)
油圧シリンダ7のピストンを下降させて、扛上
支持装置1から外方に取り出す。(第2図C)
このようにして、油圧シリンダ7を回収し、次
いでコンクリートを打ち込んで全体を一体化して
作業を終了する。 Below, the sequence of hoisting and supporting a heavy structure using the apparatus of the present invention will be explained. First, the lower surface of the foundation of the structure is excavated in the same way as in the conventional method, but after excavation, the depth is determined from the upper surface of the foundation pile (or the upper surface of the temporary foundation) with the upper end cut off to the structure. It is sufficient that the height reaching the lower surface of the hydraulic cylinder 7 is a height that allows the lifting support device 1 to be inserted, that is, it may be slightly higher than the height of the hydraulic cylinder 7 when it is shortened. In this way, the lifting support device 1 is positioned between the top surface of the excised foundation pile 8 and the lower surface of the foundation of the structure 9, and the hydraulic cylinder 7 is housed between the base plates 4 and 2.
(Fig. 2A) The hydraulic cylinder 7 is operated via a separately provided hydraulic pump mechanism to push up the foundation of the structure 9 together with the upper base plate 4. In this state, the nut 6 is rotated to remove each straight pipe 3. Press it against the rim of the mouth. (FIG. 2B) The piston of the hydraulic cylinder 7 is lowered and taken out from the lifting support device 1. (Fig. 2C) In this way, the hydraulic cylinder 7 is recovered, and then concrete is poured to integrate the entire structure and the work is completed.
(効果)
本発明は以上説明したように、扛上支持装置1
内に油圧シリンダ7を収容した状態で作業を開始
するのであるから、前記したように掘削深さは従
来の略半分でよく、また、扛上支持装置1は上昇
された構造物の下降を防ぐだけの力があればよい
から、例えば螺杆5としてネジ鉄筋、また直管3
として単なる鉄管を利用して扛上支持することが
でき、かつ軽量の上下台板4,2を別々に運ぶこ
とができるから作業容易であり、また構造が簡単
な安価であり、方形の上部台板と下部台板の各隅
部にそれぞれ支柱を配置したので上下台板の間に
油圧ジヤツキを挿入取出すのが容易であり、各支
柱は軽量でよく、更にコンクリートの流入がよく
扛上した重構造物の支持も極めて満足に達成され
るという多くの利点がある。(Effects) As explained above, the present invention provides the lifting support device 1.
Since the work is started with the hydraulic cylinder 7 housed inside, the excavation depth can be approximately half of the conventional depth as described above, and the hoisting support device 1 prevents the elevated structure from descending. For example, screw reinforcing bar can be used as screw rod 5, or straight pipe 3 can be used as screw rod 5.
It can be lifted and supported using a simple iron pipe, and the lightweight upper and lower base plates 4 and 2 can be carried separately, making the work easy. Since columns are placed at each corner of the board and the lower baseplate, it is easy to insert and remove the hydraulic jack between the upper and lower baseplates, and each column is lightweight, and furthermore, concrete can flow easily into heavy structures. There are many advantages in that the support of is also achieved very satisfactorily.
第1図および第2図は本発明の装置の使用状態
を示し、第1図は扛上支持装置の斜面図、第2図
A〜Cは扛上する状態を示す正面図、第3図は扛
上作業に当り構造物下方は掘削した状態の一般説
明図、第4図は従来使用されているジヤツキの正
面図である。
1……扛上支持装置、2……下部台板、3……
直管、4……上部台板、5……螺杆、6……ナツ
ト、7……油圧シリンダ、8……基礎杭、9……
構造物。
1 and 2 show the device of the present invention in use, FIG. 1 is a perspective view of the lifting support device, FIGS. 2A to 2C are front views showing the lifting state, and FIG. A general explanatory diagram shows the state in which the lower part of the structure has been excavated during hoisting work, and FIG. 4 is a front view of a conventionally used jack. 1... Lifting support device, 2... Lower base plate, 3...
Straight pipe, 4...Top plate, 5...Screw rod, 6...Nut, 7...Hydraulic cylinder, 8...Foundation pile, 9...
Structure.
Claims (1)
管を挿入しその突出部にナツトを螺合して伸縮自
在とした4本の支柱からなり、該支柱を上下台板
の間の各隅部に、上下台板の間に油圧ジヤツキを
挿入取出し可能に配置したことを特徴とする重構
造物扛上支持装置。1 Consists of a rectangular upper and lower base plate, and four telescoping pillars made by inserting a spiral pipe into a straight pipe and screwing a nut into the protruding part, and attaching the pillars to each corner between the upper and lower base plates. A heavy structure hoisting support device characterized in that a hydraulic jack is arranged between the upper and lower base plates so that it can be inserted and taken out.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2411286A JPS62182323A (en) | 1986-02-07 | 1986-02-07 | Lifting of heavy structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2411286A JPS62182323A (en) | 1986-02-07 | 1986-02-07 | Lifting of heavy structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS62182323A JPS62182323A (en) | 1987-08-10 |
JPH0469270B2 true JPH0469270B2 (en) | 1992-11-05 |
Family
ID=12129245
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2411286A Granted JPS62182323A (en) | 1986-02-07 | 1986-02-07 | Lifting of heavy structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS62182323A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013245450A (en) * | 2012-05-24 | 2013-12-09 | Mase Kensetsu Kk | Existing pile bearing force regenerating and sinking correction method |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4703233B2 (en) * | 2005-03-30 | 2011-06-15 | 報国エンジニアリング株式会社 | Building foundation reinforcement method and structure |
JP5090804B2 (en) * | 2007-07-02 | 2012-12-05 | 株式会社Wasc基礎地盤研究所 | Construction method and foundation support structure of ready-made piles |
JP5466675B2 (en) * | 2011-07-28 | 2014-04-09 | 興和鋼管株式会社 | Heavy load support device and non-settlement repair or prevention method using the device |
CN103912137B (en) * | 2014-04-18 | 2016-06-15 | 江苏东南特种技术工程有限公司 | The lifting gear of buildings lifting construction |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5479905A (en) * | 1977-12-08 | 1979-06-26 | Sekisui House Kk | Method of horizontally returning tilted building |
-
1986
- 1986-02-07 JP JP2411286A patent/JPS62182323A/en active Granted
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5479905A (en) * | 1977-12-08 | 1979-06-26 | Sekisui House Kk | Method of horizontally returning tilted building |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013245450A (en) * | 2012-05-24 | 2013-12-09 | Mase Kensetsu Kk | Existing pile bearing force regenerating and sinking correction method |
Also Published As
Publication number | Publication date |
---|---|
JPS62182323A (en) | 1987-08-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US2686420A (en) | Slab lifting apparatus | |
US2720017A (en) | Method of erecting buildings | |
US4787779A (en) | Method and apparatus for raising and supporting a foundation | |
JPH0469270B2 (en) | ||
JPH09144050A (en) | Upward pushing method of construction | |
JPS6145022B2 (en) | ||
JPH09111848A (en) | Underground retarding structure | |
JP2633199B2 (en) | How to build a concrete foundation | |
JPH10317391A (en) | Foundation structure for steel tower and method for constructing the same | |
JPH11172701A (en) | Method for constructing masonry wall | |
JPH0711773A (en) | Column erection method and column base supporting device | |
JPS62296019A (en) | Fixing structure of steel skeleton column base for foundation concrete | |
JP3030374B2 (en) | Construction method and equipment for trussed pillar | |
JPS5935655Y2 (en) | foundation lifting device | |
JPH05485B2 (en) | ||
JPH10121503A (en) | Foundation construction of building on soft ground | |
JPH0379490B2 (en) | ||
JPH083614Y2 (en) | Gravestone basics | |
JPS60230475A (en) | Construction of cylindrical structure | |
JPS59187907A (en) | Support and holding construction | |
JPS594755A (en) | Slide type frame apparatus for casting concrete structure | |
JPH1037530A (en) | Method for assembling four stone such as gravestone and four-stone leveler therefor | |
JPS58222218A (en) | Method and apparatus for concrete sheathing and timbering work in underground structure | |
JPH0886097A (en) | Method of sill lifting construction of house | |
JPS6121277A (en) | Building of underground tank |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |