JPH05340109A - Column jointing method in construction of new structure - Google Patents

Column jointing method in construction of new structure

Info

Publication number
JPH05340109A
JPH05340109A JP17781592A JP17781592A JPH05340109A JP H05340109 A JPH05340109 A JP H05340109A JP 17781592 A JP17781592 A JP 17781592A JP 17781592 A JP17781592 A JP 17781592A JP H05340109 A JPH05340109 A JP H05340109A
Authority
JP
Japan
Prior art keywords
temporary
column
foundation pile
girder
permanent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP17781592A
Other languages
Japanese (ja)
Other versions
JP2799266B2 (en
Inventor
Tatsuo Nakajima
達夫 中島
Akira Seto
明 瀬戸
Katsuhide Kawasaki
勝秀 川崎
Masatake Yasumoto
匡剛 安本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
J R HIGASHI NIPPON CONSULTANTS
J R HIGASHI NIPPON CONSULTANTS KK
Toda Corp
East Japan Railway Co
Original Assignee
J R HIGASHI NIPPON CONSULTANTS
J R HIGASHI NIPPON CONSULTANTS KK
Toda Corp
East Japan Railway Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by J R HIGASHI NIPPON CONSULTANTS, J R HIGASHI NIPPON CONSULTANTS KK, Toda Corp, East Japan Railway Co filed Critical J R HIGASHI NIPPON CONSULTANTS
Priority to JP17781592A priority Critical patent/JP2799266B2/en
Publication of JPH05340109A publication Critical patent/JPH05340109A/en
Application granted granted Critical
Publication of JP2799266B2 publication Critical patent/JP2799266B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE:To make it possible to join a permanent column with a temporary beam carried laterally and hence facilitate joint work in a column joint method in the construction of a new building. CONSTITUTION:A temporary beam 4b is installed to a temporary bearing pile at a position deviated by a specified quantity from a permanent column installation position where a temporary rack is built on the temporary beam. Then, after a foundation pile and the temporarily fit-up permanent beam are constructed, the temporary beam 4b is carried up to the permanent column installation position by using a transfer device. The lower part of a permanent column 23 is once turned into an adjustable state in every direction, say horizontally and vertically so that a lower part 11a of a column joint material for the temporary installation beam may be positioned with the upper part 23a of the permanent column 23 and then jointed with each other. The lower part of the permanent column 23 is installed to a foundation pile 22, fastened and fixed with anchor bolts 31. Mortar 32 is filled up around the foundation pile 22, thereby producing one piece structure.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、鉄道や道路などの交通
路又は類似の構造物の上に新しく構造物を建造する場合
に適した新建造物の構築における柱の接合方法に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of joining pillars in constructing a new structure suitable for constructing a new structure on a traffic route such as a railway or a road or a similar structure.

【0002】[0002]

【従来の技術】一般に、交通路の機能を損なうことな
く、交通路上や駅舎上に新しい建物を構築する方法で
は、公益性を重視し、安全性を確保するために、地下部
の構築工、土留杭、残土搬出、プラットホームの覆工等
の施工作業が、例えば、き電停止後に行なわれることに
なり、作業時間を長くとることができない、また、工事
期間中には、架線や線路脇での近接作業が続き、安全面
での注意が特に必要であり、更に、基礎杭施工時には建
設資材を吊込むためのクレーンが必要であり、地下の作
業空間では吊込み高さが制限されるため大口径あるいは
長尺の基礎杭を構築することが困難である、等の種々の
障害がある。
2. Description of the Related Art Generally, in a method of constructing a new building on a traffic road or a station building without impairing the function of the traffic road, in order to secure public safety and to secure safety, an underground construction work, Construction work such as retaining piles, removal of remaining soil, and lining of the platform will be done after the stop of feeding, for example, and the working time cannot be taken long. Since close work of the building continues, special attention is required in terms of safety, and a crane for suspending construction materials is required when constructing foundation piles, and the lifting height is limited in the underground work space. There are various obstacles such as difficulty in constructing large diameter or long foundation piles.

【0003】このような障害を排除して新建造物を構築
する方法として、既存の構造物において仮設支持杭を適
宜な間隔を置いて立設し、該仮設支持杭に仮設桁を本設
の柱部材設置位置から所定量ずらした位置に架設し、該
仮設桁上に仮設構台を構築してこの仮設構台上から基礎
杭と本設柱を構築した後に、前記仮設桁を移動装置によ
り前記本設柱部材設置位置にまで移動させて新建造物の
桁となし、前記仮設構台上で新構造物の構築作業を行っ
て既存構造物の稼働を可能にしつつ新建造物を構築する
こととした方法が知られている。
As a method of constructing a new building by eliminating such obstacles, temporary support piles are erected at an appropriate interval in an existing structure, and a temporary girder is permanently installed on the temporary support piles. The temporary girder is erected at a position displaced by a predetermined amount from the member installation position, a temporary gantry is constructed on the temporary girder, and the foundation pile and the main installation column are constructed from the temporary gantry, and then the temporary girder is moved to the main installation by a moving device. A method is known in which the structure is moved to the column member installation position to form a girder for a new structure, and the construction of the new structure is performed on the temporary gantry to enable the operation of the existing structure while constructing the new structure. Has been.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、本設柱
に対して仮設桁を所定量水平移動させ、前記本設柱の上
部と継ぎ材の下部とを位置合わせし溶接して接合するに
は、高さ方向や横方向で多少の寸法誤差は免れず正確な
位置合わせが困難であり、無理に接合させると溶接時に
歪が生じる場合がある等の問題があった。
However, in order to move the temporary girder horizontally with respect to the main installation column by a predetermined amount, align the upper part of the main installation column and the lower part of the joint material and weld them together, There is a problem that some dimensional errors in the height direction and the lateral direction are unavoidable and accurate alignment is difficult, and if they are forcibly joined, distortion may occur during welding.

【0005】本発明の目的は、上述した欠点に鑑みなさ
れたもので、本設柱と横移動してきた継ぎ材との接合を
無理なく接合でき接合作業の容易な新建造物の構築にお
ける柱の接合方法を提供することにある。
The object of the present invention has been made in view of the above-mentioned drawbacks, and it is possible to join the main installation pillar and the laterally moved joint material without difficulty, and to join the pillars in the construction of a new building in which the joining operation is easy. To provide a method.

【0006】[0006]

【課題を解決するための手段】本発明に係る既存構造物
の稼働可能な新建造物の構築方法の上記課題を解決し、
目的を達成するための要旨は、既存の構造物とその付属
施設を稼働させつつ、それらの上に新建造物を構築する
際に、仮設支持杭を適宜な間隔を置いて立設し、該仮設
支持杭に本設構造体となる仮設桁を本設の柱部材設置位
置から所定量ずらした位置に架設し、該仮設桁上に仮設
構台を構築してこの仮設構台上から基礎杭とこれに仮止
めされる本設柱を構築した後に、前記仮設桁を移動装置
により前記本設の柱部材設置位置にまで移動させ、前記
本設柱の下部を基礎杭から一旦前後左右方向及び上下方
向に調節可能な状態にして前記仮設桁の柱用継ぎ材の下
部と前記本設柱の上部とを位置合わせ後に互いに接合
し、その後前記本設柱の下部を前記基礎杭にアンカーボ
ルトで本締めして固定するとともにその周囲にモルタル
を充填して一体化させたことに存する。
[Means for Solving the Problems] The above problems of the method for constructing a new building capable of operating an existing structure according to the present invention are solved,
The gist to achieve the purpose is to operate existing structures and their ancillary facilities, and at the time of constructing a new structure on them, set up temporary support piles at appropriate intervals and A temporary girder to be the main structure is erected on the support pile at a position shifted by a predetermined amount from the installation position of the main pillar member, a temporary gantry is constructed on the temporary girder, and the foundation pile and the After constructing the main column to be temporarily fixed, the temporary girder is moved to the main column member installation position by the moving device, and the lower part of the main column is temporarily moved in the front-back, left-right direction and up-down direction from the foundation pile. In an adjustable state, the lower portion of the column splice material of the temporary girder and the upper portion of the main installation column are aligned and joined to each other, and then the lower portion of the main installation column is fully fastened to the foundation pile with anchor bolts. And fix it together and fill the mortar around it It consists in the.

【0007】[0007]

【作用】このように、本発明に係る新建造物の構築にお
ける柱の接合方法によれば、仮設桁を本設の桁に転用さ
せる際に、仮設桁の継ぎ材の下部と本設の柱の上部との
位置合わせが、本設の柱を仮止めにしておくことによ
り、ボルト穴の調節しろ内での調節が容易なものとな
り、更に不自然な応力・変形が生じない。
As described above, according to the method of joining columns in the construction of a new structure according to the present invention, when the temporary girder is diverted to the main girder, the lower part of the joint material of the temporary girder and the main girder are separated. For the alignment with the upper part, by temporarily fixing the main column, the bolt holes can be easily adjusted within the adjustment margin, and further unnatural stress and deformation do not occur.

【0008】[0008]

【実施例】以下、添付図面に従って本発明の一実施例を
説明する。第1図乃至第9図は、本発明に係る柱の接合
方法の施工順序を示す説明図である。図1は、駅のプラ
ットホーム1と軌道2に、仮設支持杭3,3…を立設
し、この仮設支持杭3,3…に仮設桁4,4…をクレー
ン5で架設する様子を示している。尚、符号6は前記仮
設支持杭3の補強用のブレース材であり、7はワイヤを
各々示している。
An embodiment of the present invention will be described below with reference to the accompanying drawings. 1 to 9 are explanatory views showing the construction sequence of the method for joining columns according to the present invention. FIG. 1 shows a situation in which temporary support piles 3, 3 ... Are erected on a platform 1 and a track 2 of a station, and temporary girders 4, 4 ... are erected on the temporary support piles 3, 3 ,. There is. Reference numeral 6 is a brace material for reinforcing the temporary support pile 3, and reference numerals 7 are wires.

【0009】前記仮設桁4は後述する本設の主桁若しく
は横桁となるものである。この仮設桁4を架設する位置
は、図2乃至図3に示すように、本設の柱部材設置位置
9に対して基礎杭の口径に応じた移動距離、この場合で
は約2m程度ズレた位置10にする。そして図3に示す
ように、前記仮設桁4,4…をボルト・ナット等で連結
する継ぎ材11,11…を介して縦横方向に格子状にし
て配設する。
The temporary girders 4 are main girders or lateral girders which will be described later. As shown in FIG. 2 to FIG. 3, the position where the temporary girder 4 is installed is a moving distance corresponding to the diameter of the foundation pile, that is, a position displaced by about 2 m in this case from the pillar member installation position 9 of the main installation. Set to 10. Then, as shown in FIG. 3, the temporary girders 4, 4, ... Are arranged in a lattice shape in the vertical and horizontal directions via joint materials 11, 11 ... Which are connected by bolts, nuts and the like.

【0010】よって、平面的に見ると、前記仮設桁4に
おける縦方向の桁4aと、横方向の桁4bとで囲まれた
中に、本設の柱部材を設置すべき位置9があることにな
る。このような、前記仮設支持杭3,3…に前記仮設桁
4,4…をクレーン5で架設作業するには、前記クレー
ン5を空地等に設置して、き電停止後(交通機関の運行
停止後)に行なうものである。
Therefore, when seen in a plan view, there is a position 9 in which the permanently installed pillar member should be installed in the temporary girder 4 surrounded by the longitudinal girders 4a and the lateral girders 4b. become. In order to construct the temporary girders 4, 4 ... On the temporary support piles 3, 3, ... With the crane 5, the crane 5 is installed in an open space or the like, and after feeding stop (operation of transportation means). It will be done after the stop).

【0011】次に、上記の架設された前記仮設桁4,4
…の上に、図3と図4に示すように、覆工受桁12を適
宜間隔で敷設するとともに、ほぼ全面にわたり覆工板1
3を敷設する。この場合、前記本設の柱部材設置位置9
の部分では、基礎杭工事に必要な大きさの開口を形成し
て、前記覆工板13を敷設するものである。
Next, the above-mentioned erected temporary girders 4, 4 are installed.
As shown in FIG. 3 and FIG. 4, lining support girders 12 are laid at appropriate intervals on the top of the ...
3 is laid. In this case, the installation position 9 of the main pillar member
In the portion (1), an opening having a size necessary for foundation pile construction is formed and the lining plate 13 is laid.

【0012】そして、図5に示すように、前記覆工板1
3上にクローラクレーン14を載置する。前記柱部材設
置位置9にて、前記仮設桁4の下面からプラットホーム
1表面まで、基礎杭の構築に必要な大きさで、仮囲い板
15で仮囲いをする。工事中の安全対策のためである。
Then, as shown in FIG. 5, the lining plate 1
The crawler crane 14 is mounted on the table 3. At the pillar member installation position 9, from the lower surface of the temporary girder 4 to the surface of the platform 1, a temporary enclosure plate 15 is used to temporarily enclose the foundation pile. This is for safety measures during construction.

【0013】次に、前記クローラクレーン14でもっ
て、掘削用ドリルビット16を装着したドリルロッド1
7を吊り下げて、前記覆工板13の開口部から降下さ
せ、ロータリーテーブル18を設置して、前記ドリルロ
ッド17を回転させながらリバースサーキュレイション
ドリル工法にて地盤を掘削する。
Next, with the crawler crane 14, the drill rod 1 equipped with the drill bit 16 for excavation.
7 is suspended, lowered from the opening of the lining plate 13, the rotary table 18 is installed, and the ground is excavated by the reverse circulation drill method while rotating the drill rod 17.

【0014】掘削が完了したら、前記クローラクレーン
14を使用して、工場などで予め製造した鉄筋籠(図示
せず)を前記掘削孔19に設置し、場所打ちコンクリー
トを打設して、基礎杭22を構築し(図6参照)、更に
この基礎杭22に本設の柱23を立設する。尚、符号8
は、スタンドパイプを示している。この工法により、前
記柱部材設置位置9,9…に、前記柱23,23…を立
設し、基礎杭22に埋設されたアンカーボルト30で仮
止めする。なお、本例ではリバースサーキュレイション
ドリル工法による基礎杭の施工について説明したが、他
の場所打ち杭工法や既製杭を用いた基礎杭の施工も任意
である
After the excavation is completed, the crawler crane 14 is used to install a rebar cage (not shown) manufactured in advance in a factory or the like in the excavation hole 19, and cast in-place concrete to form a foundation pile. 22 is constructed (see FIG. 6), and a permanent pillar 23 is erected on the foundation pile 22. Incidentally, reference numeral 8
Shows a stand pipe. By this construction method, the pillars 23, 23 ... Are erected at the pillar member installation positions 9, 9 ... And temporarily fixed by the anchor bolts 30 embedded in the foundation pile 22. In this example, the construction of the foundation pile by the reverse circulation drill method was explained, but the construction of the foundation pile using other cast-in-place pile construction methods or ready-made piles is also optional.

【0015】この様にして、本設の柱23を必要数構築
した後に、前記クローラクレーン14を撤収する。これ
らの作業は、前記仮設桁4と仮設レール12と覆工板1
3等からなる仮設構台A上で、昼夜を問わず行なうこと
ができ、しかも、電車等の通行を妨げることがない。ま
た、前記基礎杭22を構築中も、作業用孔を仮囲い板1
5で囲ってあるので、一般人に対する安全性も確保され
ている。次に、前記クローラクレーン14を撤収後に、
前記覆工板13、覆工受桁12を撤収する。
In this way, the crawler crane 14 is removed after the required number of columns 23 have been constructed. These operations are performed by the temporary girder 4, the temporary rail 12, and the lining plate 1.
It can be carried out day and night on the temporary gantry A composed of 3 etc., and does not obstruct the passage of trains and the like. Further, even during the construction of the foundation pile 22, the work holes are temporarily surrounded by the shroud 1.
Since it is surrounded by 5, the safety for the general public is secured. Next, after withdrawing the crawler crane 14,
The lining plate 13 and the lining receiving girder 12 are removed.

【0016】更に、前記仮設支持杭3上の支持レール2
4に移動装置としての油圧ジャッキ25を固定する。そ
して、該油圧ジャッキ25のロッド26先端を前記仮設
桁4若しくは継ぎ材11に連結する。継ぎ材11は、十
字型に工場加工したもので、仮設桁4の縦横方向の桁4
a,4bを現場でボルト接合するものである。
Further, the support rail 2 on the temporary support pile 3 is provided.
A hydraulic jack 25 as a moving device is fixed to the position 4. Then, the tip of the rod 26 of the hydraulic jack 25 is connected to the temporary girder 4 or the joint material 11. The splicing material 11 is a cross-shaped factory processed product.
A and 4b are bolted on site.

【0017】この油圧ジャッキ25は図6に示すよう
に、図面垂直方向に4ケ所に設けたが、勿論仮設桁4の
大きさに応じて、所要数設けるものである。そして、仮
設桁4の縦方向の桁4aと横方向の桁4bと継ぎ材11
とがボルト・ナット等で連結されて一体化した格子桁2
7を、前記油圧ジャッキ25で押出し又は引き込んで、
前記柱部材設置位置9に、前記継ぎ材11が位置するよ
うに移動させる。この場合の移動量は、前記仮設桁4を
柱部材設置位置9に対して位置ズレさせた量であり、基
礎杭の口径に応じて適宜決定するものである。
As shown in FIG. 6, the hydraulic jacks 25 are provided at four positions in the vertical direction of the drawing, but of course, the required number is provided depending on the size of the temporary girder 4. Then, the longitudinal girders 4a, the lateral girders 4b, and the joint members 11 of the temporary girders 4 are provided.
Lattice girder 2 that is integrated by connecting and with bolts and nuts, etc.
7 is pushed out or pulled in by the hydraulic jack 25,
The joint material 11 is moved to the pillar member installation position 9 so as to be located there. The amount of movement in this case is the amount of displacement of the temporary girder 4 with respect to the column member installation position 9, and is appropriately determined according to the diameter of the foundation pile.

【0018】この油圧ジャッキ25による格子桁27の
移動により、前記仮設桁4の縦方向の桁4aが本設の主
桁に、同じく横方向の桁4bが横桁になるものである。
そして、この継ぎ材11の下部11aと、柱23の上部
23aとの接合について説明する。
By moving the lattice girder 27 by the hydraulic jack 25, the longitudinal girders 4a of the temporary girders 4 become main girders and the lateral girders 4b become transverse girders.
Then, the joining of the lower portion 11a of the joint material 11 and the upper portion 23a of the column 23 will be described.

【0019】この接合方法は、図7に示すように、予め
基礎杭22に柱23を、基礎杭22に埋設したアンカー
ボルト30によって仮止めしておく。そして、継ぎ材1
1が前記油圧ジャッキ25によって図7(イ)、(ロ)
に示すように柱23に横方向の位置合わせされた後、柱
23の上部23a及び継ぎ材11の下部11aに溶接作
業用のエレクションピース31,31,…を溶接して固
着する。
In this joining method, as shown in FIG. 7, the pillars 23 are temporarily fixed to the foundation piles 22 in advance by the anchor bolts 30 embedded in the foundation piles 22. And joint material 1
1 by the hydraulic jack 25 shown in FIGS.
After being laterally aligned with the pillar 23, the erection pieces 31, 31, ... For welding work are welded and fixed to the upper portion 23a of the pillar 23 and the lower portion 11a of the joint material 11, as shown in FIG.

【0020】前記エレクションピース31は、図7
(ハ)乃至図9に示すように、柱23の上部23aの対
向面に各々2箇所ずつに合計4個を固着し、同様に継ぎ
材11の下部11aにも対向面に各々2箇所ずつにし
て、かつ前記柱23の上部23aに固着される4個のエ
レクションピース31と対向配置にしてエレクションピ
ース31を合計4個固着する。
The erection piece 31 is shown in FIG.
As shown in (c) to FIG. 9, a total of four pieces are fixed to the upper surface 23a of the pillar 23 at two points on each of the opposite surfaces, and similarly, the lower portion 11a of the joint material 11 is also made to have two points on each of the opposite surfaces. Further, a total of four erection pieces 31 are fixed so as to face the four erection pieces 31 fixed to the upper portion 23a of the pillar 23.

【0021】次に、前記柱23の下部を、前記アンカー
ボルト30のナットを一旦緩めて前後左右方向及び上下
方向に調節可能な状態にする。そして、主桁4aに反力
を取りながら柱23を少し吊上げて、継ぎ材11の下部
11aと柱23の上部23aの位置合わせを行い、前記
対向配置になされたエレクションピース31を当て板3
1aを使用して互いに溶接して柱23と継ぎ材11の位
置決めをする(図8参照)。なお、エレクションピース
31が対向配置にされてできる半円孔の切欠き31b
は、点溶接作業を行うために設けられる切欠きである。
Next, the lower portion of the pillar 23 is temporarily loosened by the nut of the anchor bolt 30 so as to be adjustable in the front-rear, left-right and up-down directions. Then, the column 23 is slightly lifted while applying a reaction force to the main girder 4a, the lower portion 11a of the joint material 11 and the upper portion 23a of the column 23 are aligned, and the erection piece 31 in the facing arrangement is attached to the contact plate 3
The columns 23 and the joint material 11 are positioned by welding them together using 1a (see FIG. 8). It should be noted that the semicircular hole notch 31b formed by disposing the erection pieces 31 facing each other
Is a notch provided for performing a spot welding operation.

【0022】そして、柱23の上部23a端部と継ぎ材
11の下部11a端部とを溶接する。この場合、溶接の
熱で柱23等が変形して歪むのを防止するために、先に
エレクションピース31の固着されていない対向面を各
々溶接し、次にエレクションピース31のある一片側を
溶接する。その後、前記エレクションピース31を全部
柱23と継ぎ材11から撤去させる。そして、残ったエ
レクションピース31のある他側を溶接する。
Then, the end of the upper portion 23a of the column 23 and the end of the lower portion 11a of the joint material 11 are welded. In this case, in order to prevent the columns 23 and the like from being deformed and distorted by the heat of welding, the opposite surfaces of the erection piece 31 that are not fixed are welded first, and then the one side with the erection piece 31 is welded. To do. After that, the erection piece 31 is completely removed from the pillar 23 and the joint material 11. Then, the other side with the remaining erection piece 31 is welded.

【0023】こうして柱23と継ぎ材11の接合が終了
したら、前記アンカーボルト30のナットを再び取り付
けて締結して、図7(ニ)に示すように、基礎杭22の
頭部に無収縮モルタル32を充填する。このようにし
て、柱23と継ぎ材11とが高精度に位置合わされて組
み立てされるものである。この後、前記移動装置25を
撤収し、床型枠を設置後コンクリート打設して床版を構
築する。更に上方に向けてこの床版を作業床として公知
の方法により柱や梁を構築して、軌道2上やプラットホ
ーム1の上に、新しい建物(図示せず)を構築するもの
である。
When the joining of the pillar 23 and the joint material 11 is completed in this way, the nut of the anchor bolt 30 is reattached and fastened, and the non-shrink mortar is attached to the head of the foundation pile 22 as shown in FIG. Fill 32. In this way, the pillar 23 and the joint material 11 are accurately aligned and assembled. After that, the moving device 25 is removed, a floor form is installed, and then concrete is placed to construct a floor slab. Further toward the upper side, pillars and beams are constructed by a known method using this floor slab as a working floor, and a new building (not shown) is constructed on the track 2 and the platform 1.

【0024】[0024]

【発明の効果】以上詳細に説明したように、本発明に係
る柱の接合方法は、既存の構造物とその付属施設を稼働
させつつ、それらの上に新建造物を構築する際に、仮設
構台上から基礎杭とこれに仮止めされる本設柱を構築し
た後に、仮設桁を移動装置により前記本設の柱部材設置
位置にまで移動させ、前記本設柱の下部を基礎杭から一
旦前後左右方向及び上下方向に調節可能な状態にして前
記架設桁の継ぎ材の下部と前記本設柱の上部とを位置合
わせ後に互いに接合し、その後前記本設柱の下部を前記
基礎杭にアンカーボルトで本締めして固定するとともに
モルタルを充填して一体化させた方法なので、前記仮設
桁を本設の主桁等に転用した際の、継ぎ材の下部と本設
の柱の上部との接合作業が容易になるとともに高精度に
組立てができ、仮設桁を本設桁としてそのまま転用する
ので接合作業のやり直しもなく工期の短縮となり、ま
た、その接合において無理な位置合わせにならず歪むこ
とがない。
As described in detail above, the method of joining pillars according to the present invention allows the temporary structure to be used when constructing a new structure on an existing structure and its associated facilities while operating them. After constructing the foundation pile and the main pillar temporarily fixed to this from above, move the temporary girder to the main member pillar installation position by the moving device, and move the lower part of the main pillar from the foundation pile back and forth once. The lower part of the joint material of the erection girder and the upper part of the main installation column are aligned and joined to each other after being adjusted in the left-right direction and the vertical direction, and then the lower part of the main installation column is anchored to the foundation pile. Since it is a method of permanently fastening and fixing with mortar and integrating it with mortar, when joining the temporary girder to the main girder etc. of the main construction, the lower part of the joint material and the upper part of the main construction girder are joined. Work becomes easy and highly accurate assembly is possible. It becomes shorter construction time without rework bonding operation so diverted digits as the 設桁, also, is not distorted not become unreasonable positioning at the junction.

【図面の簡単な説明】[Brief description of drawings]

【図1】仮設桁を架設している様子を示す説明図であ
る。
FIG. 1 is an explanatory diagram showing how a temporary girder is installed.

【図2】仮設桁の配置状態を示す平面図である。FIG. 2 is a plan view showing an arrangement state of temporary girders.

【図3】同じく仮設桁の配置状態を示す平面図である。FIG. 3 is a plan view showing the arrangement of temporary girders.

【図4】同じく仮設構台の側断面図である。FIG. 4 is a side sectional view of the temporary gantry.

【図5】基礎杭を構築している様子を示す説明図であ
る。
FIG. 5 is an explanatory diagram showing a state in which a foundation pile is being constructed.

【図6】仮設構台を移動させる様子を示す説明図であ
る。
FIG. 6 is an explanatory diagram showing a state of moving a temporary gantry.

【図7】(イ)乃至(ニ)は、本設の柱と仮設桁の継ぎ
材を接合する手順を示す説明図である。
7 (a) to (d) are explanatory views showing a procedure for joining a main pillar and a splice material for a temporary girder.

【図8】同じく本設の柱と継ぎ材の接合部の一部拡大正
面図である。
FIG. 8 is a partially enlarged front view of the joint between the main pillar and the joint material.

【図9】図8のB−B線断面図である。9 is a sectional view taken along line BB of FIG.

【符号の説明】[Explanation of symbols]

1 プラットホーム、2 軌道、3 仮設支持杭、4
仮設桁、5 クレーン、9 柱部材設置位置、10 所
定量ずらした位置、11 継ぎ材、12 覆工受桁、1
3 覆工板、15 仮囲い板、19 掘削孔、22 基
礎杭、23 柱、25 移動装置、27 格子桁、30
アンカーボルト、31エレクションピース、32 無
収縮モルタル、A 仮設構台。
1 platform, 2 tracks, 3 temporary support piles, 4
Temporary girder, 5 cranes, 9 pillar member installation position, 10 position shifted by a predetermined amount, 11 joint material, 12 lining support girder, 1
3 lining plate, 15 temporary enclosure plate, 19 excavation hole, 22 foundation pile, 23 pillar, 25 moving device, 27 lattice girder, 30
Anchor bolt, 31 erection piece, 32 non-shrink mortar, A Temporary gantry.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 瀬戸 明 東京都板橋区稲荷台27−D303 (72)発明者 川崎 勝秀 千葉県柏市向原町3−1−510 (72)発明者 安本 匡剛 東京都杉並区阿佐谷南2−7−6 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Akira Seto 27-D303 Inaridai, Itabashi-ku, Tokyo (72) Inventor Katsuhide Kawasaki 3-1-510, Mukaihara-cho, Kashiwa-shi, Chiba (72) Inventor Masayoshi Yasumoto 2-7-6 Minami Asaya, Suginami-ku, Tokyo

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 既存の構造物とその付属施設を稼働させ
つつ、それらの上に新建造物を構築する際に、仮設支持
杭を適宜な間隔を置いて立設し、該仮設支持杭に本設構
造体となる仮設桁を本設の柱部材設置位置から所定量ず
らした位置に架設し、該仮設桁上に仮設構台を構築して
この仮設構台上から基礎杭とこれに仮止めされる本設柱
を構築した後に、前記仮設桁を移動装置により前記本設
の柱部材設置位置にまで移動させ、前記本設柱の下部を
基礎杭から一旦前後左右方向及び上下方向に調節可能な
状態にして前記仮設桁の柱用継ぎ材の下部と前記本設柱
の上部とを位置合わせ後に互いに接合し、その後前記本
設柱の下部を前記基礎杭にアンカーボルトで本締めして
固定するとともにその周囲にモルタルを充填して一体化
させたことを特徴としてなる新建造物の構築における柱
の接合方法。
1. While operating an existing structure and its associated facilities, when constructing a new building on them, temporary support piles are erected at appropriate intervals, and the temporary support piles are provided with a book. A temporary girder to be a construction structure is erected at a position shifted by a predetermined amount from the installation position of the main pillar member, a temporary gantry is constructed on the temporary girder, and it is temporarily fixed to the foundation pile and this from this temporary gantry. After constructing the permanent pillar, the temporary girder is moved to the permanent pillar member installation position by the moving device, and the lower portion of the permanent pillar can be temporarily adjusted in the front-rear, left-right direction, and the vertical direction from the foundation pile. And the lower part of the column joint material of the temporary girder and the upper part of the main installation column are aligned and joined to each other, and then the lower part of the main installation column is fixed to the foundation pile by final tightening with anchor bolts and Characterized by filling mortar around it and integrating it Method of joining pillars in construction of new building.
JP17781592A 1992-06-12 1992-06-12 How to join columns in building a new building Expired - Fee Related JP2799266B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17781592A JP2799266B2 (en) 1992-06-12 1992-06-12 How to join columns in building a new building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17781592A JP2799266B2 (en) 1992-06-12 1992-06-12 How to join columns in building a new building

Publications (2)

Publication Number Publication Date
JPH05340109A true JPH05340109A (en) 1993-12-21
JP2799266B2 JP2799266B2 (en) 1998-09-17

Family

ID=16037583

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17781592A Expired - Fee Related JP2799266B2 (en) 1992-06-12 1992-06-12 How to join columns in building a new building

Country Status (1)

Country Link
JP (1) JP2799266B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015129386A (en) * 2014-01-07 2015-07-16 戸田建設株式会社 Method of forming drive-in working platform pile and its structure
JP2018159178A (en) * 2017-03-22 2018-10-11 大和ハウス工業株式会社 Pile foundation structure and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015129386A (en) * 2014-01-07 2015-07-16 戸田建設株式会社 Method of forming drive-in working platform pile and its structure
JP2018159178A (en) * 2017-03-22 2018-10-11 大和ハウス工業株式会社 Pile foundation structure and construction method thereof

Also Published As

Publication number Publication date
JP2799266B2 (en) 1998-09-17

Similar Documents

Publication Publication Date Title
JP4881555B2 (en) Construction method of underground structure
JPS627344B2 (en)
JP4685341B2 (en) Viaduct construction method
JP3107716B2 (en) Soil retaining wall
KR20210078779A (en) Underground roadway removed upper structure between upper slab and surface of road after constructing the steel continuous wall in the earth by top-down method and method for constructing the same
JP2799266B2 (en) How to join columns in building a new building
US10428516B2 (en) Method and apparatus for repairing a tilt wall construction
JP2979117B2 (en) Building foundation method
CN108457200B (en) Temporary supporting structure for underpinning of curved bridge section pile foundation and construction method
JP3790310B2 (en) Construction method of the building by the prior construction of steel frame
JP2813605B2 (en) Construction foundation and construction method
JP2002030672A (en) Structure of joining foundation pile to pier base and method of constructing the structure
CN112177042A (en) Rail transit station construction method without affecting ground traffic
JPS63280153A (en) Underground inverted lining method
JPH04366229A (en) Temporary corresponding standard used for method of reverse driving construction
JP3849234B2 (en) Reinforced concrete underground outer wall construction method
JP2917328B2 (en) How to build a new building that can operate existing structures
KR102392517B1 (en) Top-down method using by double beam system
JP3700119B2 (en) Pillar construction method
JP4233025B2 (en) How to construct a three-dimensional intersection
KR102523155B1 (en) Connecting structure of middle girder and construction method thereof
JP2900840B2 (en) How to build underground structures
JP3106302B2 (en) How to build underground structures
JPH07103583B2 (en) Construction method for large span underground structure
JPH04185816A (en) Construction of beam in underground wall

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19980602

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20070703

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080703

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090703

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100703

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110703

Year of fee payment: 13

LAPS Cancellation because of no payment of annual fees