JPH05112930A - Construction method of underground continuous wall - Google Patents

Construction method of underground continuous wall

Info

Publication number
JPH05112930A
JPH05112930A JP27780791A JP27780791A JPH05112930A JP H05112930 A JPH05112930 A JP H05112930A JP 27780791 A JP27780791 A JP 27780791A JP 27780791 A JP27780791 A JP 27780791A JP H05112930 A JPH05112930 A JP H05112930A
Authority
JP
Japan
Prior art keywords
vertical hole
elements
concrete
trailing
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP27780791A
Other languages
Japanese (ja)
Other versions
JP3147437B2 (en
Inventor
Toshihiko Murata
俊彦 村田
Mine Ishizaka
峯 石坂
Yukinori Miyoshi
行規 三善
Shinichi Nagase
信一 永瀬
Kazuo Suzuki
和夫 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP27780791A priority Critical patent/JP3147437B2/en
Publication of JPH05112930A publication Critical patent/JPH05112930A/en
Application granted granted Critical
Publication of JP3147437B2 publication Critical patent/JP3147437B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE:To make it possible to surely position an excavator and secure a vertical attitude thereof in the case a longitudinal hole for a succeeding element is excavated between two preceding elements and to enable stable excavation while securing an accurate cutting line accordingly. CONSTITUTION:A reinforced cage 2 having parting members 3 and 3 on both ends in the direction of a construction joint is erected in a longitudinal hole 1 for a preceding element, the outsides of the parting members 3 and 3 are filled with gravel or crushed stone 7, and concrete 4 is placed to the other part to construct preceding elements 8. After that, a longitudinal hole 9 for a succeeding element is excavated between the two preceding elements 8 by an excavator 10, a reinforced cage is erected into the longitudinal hole 9 for the succeeding element, and the concrete 4 is placed to construct the succeeding element 9 together with the preceding elements 8 as a unit.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、地中に複数体の先行
エレメント(壁体)を構築し、これら先行エレメント間
に後行エレメントを先行エレメントと一体的に構築する
ことにより地中連続壁を構築する地中連続壁の施工方法
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an underground continuous wall by constructing a plurality of leading elements (walls) in the ground and integrally constructing a trailing element between the leading elements and the leading element. The present invention relates to a method of constructing an underground continuous wall for building a building.

【0002】[0002]

【従来の技術】一般に、地中連続壁は土留め壁や構造物
の基礎などとして構築されるものであるが、今日、比較
的広く実施されている方法としては以下に述べるような
方法が知られている。
2. Description of the Related Art Generally, underground continuous walls are constructed as earth retaining walls and foundations of structures. However, the following methods are widely used today. Has been.

【0003】まず、地中に、地中連続壁の部分を構成す
る複数体の先行エレメント(壁体)を略1体のエレメン
トの長さ分を隔てた状態に構築する。これらの先行エレ
メントは最初に縦穴を掘削し、この縦穴内に鉄筋かごを
建て込み、つづいてコンクリートを打設することにより
構築する。先行エレメントを施工できたら、隣接する左
右2体の先行エレメント間を掘削して後行エレメント用
の縦穴を掘削する。
First, a plurality of preceding elements (walls) forming a part of the underground continuous wall are constructed in the ground in such a manner that the length of one element is separated. These preceding elements are constructed by first drilling a vertical hole, building a reinforced cage in the vertical hole, and then placing concrete. When the preceding element can be constructed, the adjacent left and right two preceding elements are excavated and the vertical hole for the succeeding element is excavated.

【0004】この縦穴の掘削と並行して前記先行エレメ
ントの打ち継ぎ方向の端面を所定寸法(通常片端面10セ
ンチ程度) 切削除去する。
In parallel with the excavation of the vertical hole, the end face of the preceding element in the splicing direction is cut and removed by a predetermined size (usually about 10 cm on one end face).

【0005】先行エレメントの端面を切削除去するの
は、端面に付着したスライムの除去と、いわゆる打ち継
ぎ面の目荒しのためである。しかる後に、先行エレメン
トと同様にこの後行エレメント用の縦穴内に鉄筋かごを
建て込み、コンクリートを打設することにより先行エレ
メントと一体的に後行エレメントを施工して地中連続壁
の全体を施工するものである。
The reason why the end face of the preceding element is cut and removed is to remove the slime adhering to the end face and to so-called roughen the joint surface. After that, as in the case of the preceding element, a reinforcing steel cage is built in the vertical hole for this succeeding element and the latter element is constructed integrally with the preceding element by placing concrete to construct the entire underground wall. It is to be constructed.

【0006】[0006]

【発明が解決しようとする課題】ところで、上記従来工
法において、隣接する左右2体の先行エレンメント間に
後行エレメント用の縦穴を掘削する際に、掘削機を左右
2体の先行エレメント間のちょうど中間部にセットし、
後行エレメント用の縦穴の掘削と並行して先行エレメン
トの端面を切削するが、先行エレメントがコンクリート
製であるため、特に掘削の初期段階、つまり左右2体の
先行エレメントの上端面部に掘削機の掘削ドリルが掛か
り、掘削及びエレメント端面の切削を開始しようとする
時に、硬質であるコンクリートに掘削機のドリルがスム
ーズに食いつかずに、いわゆる逃げを生じてしまう。こ
のため、位置ずれを起こして正しい切削ラインを確保で
きないばかりでなく、掘削機の安定を欠いて偏荷重を招
くといった不都合を生ずる場合が多々あった。
By the way, in the above conventional method, when excavating a vertical hole for a trailing element between two adjacent left and right leading elements, the excavator is placed between the left and right leading elements. Just set it in the middle part,
The end face of the leading element is cut in parallel with the excavation of the vertical hole for the trailing element. However, since the leading element is made of concrete, especially in the initial stage of excavation, that is, the upper end face portions of the two leading elements on the left and right sides of the excavator. When the excavator drill hangs up and attempts to start excavation and cutting of the end face of the element, the drill of the excavator does not bite smoothly into the hard concrete, causing a so-called escape. For this reason, there are many cases where not only the correct cutting line cannot be secured due to the positional deviation, but also the excavator lacks stability and causes an unbalanced load.

【0007】この発明はこのような前記従来の課題を解
決するために提案されたもので、隣接する左右2体の先
行エレメント間に後行エレメント用の縦孔を掘削する際
に、掘削機の位置決め及び安定した保持を確実にでき、
これにより正確な切削ラインを保持しつつ安定した掘削
を可能にした地中連続壁の施工方法を提供することを目
的とする。
The present invention has been proposed in order to solve the above-mentioned conventional problems. When excavating a vertical hole for a trailing element between two adjacent left and right leading elements, Positioning and stable holding can be ensured,
An object of the present invention is to provide a method for constructing a continuous underground wall which enables stable excavation while maintaining an accurate cutting line.

【0008】[0008]

【課題を解決するための手段】この発明にかかる地中連
続壁の施工方法は、構築しようとする地中連続壁をその
構築方向に複数体のエレメントに分割し、最初に、先行
エレメント用の縦穴を一定間隔おきに掘削し、当該縦穴
にコンクリートを打設して先行エレメントを構築し、つ
づいて、これら先行エレメント間に前記先行エレメント
の打ち継ぎ方向の端面を切削しつつ後行エレメント用の
縦穴を掘削し、当該後行エレメント用の縦穴にコンクリ
ートを打設して先行エレメントと一体的に後行エレメン
トを構築して地中連続壁を構築する地中連続壁の施工方
法において、前記先行エレメント用の縦穴に打ち継ぎ方
向の端部に仕切り部材を有する鉄筋かごを建て込み、こ
の仕切り部材の外側の空間部に砂利若しくは砕石を充填
し、他の部分にコンクリートを打設して先行エレメント
を構築し、つづいて、この隣接する左右2体の先行エレ
メント間に後行エレメント用の縦穴を掘削機によって掘
削し、この後行エレメント用の縦穴の中に鉄筋かごを建
て込みコンクリートを打設して前記先行エレメントと一
体的に後行エレメントを構築して地中連続壁を施工する
ことにより前記目的を達成するものである。
A method of constructing an underground continuous wall according to the present invention divides an underground continuous wall to be constructed into a plurality of elements in the construction direction, and first, for the preceding element. Vertical holes are drilled at regular intervals, concrete is placed in the vertical holes to construct a preceding element, and then, while cutting the end face of the preceding element in the joining direction between these preceding elements, for the succeeding element. In the method for constructing a continuous underground wall by drilling a vertical hole and placing concrete in the vertical hole for the subsequent element to construct a backward element integrally with the preceding element, A reinforcing bar cage with a partition member at the end in the direction of splicing is built in the vertical hole for the element, and the space outside this partition member is filled with gravel or crushed stone, and the other part is filled with coke. A cleat is cast to construct a leading element, and then a vertical hole for a trailing element is drilled by an excavator between two adjacent left and right leading elements, and a reinforcing bar is placed in the vertical hole for the trailing element. The above object is achieved by constructing a car, placing concrete, constructing a trailing element integrally with the preceding element and constructing a continuous underground wall.

【0009】[0009]

【実施例】以下、この発明に係る地中連続壁の施工方法
を図1〜図9に基づいて順をおって説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A method for constructing a continuous underground wall according to the present invention will be described below in order with reference to FIGS.

【0010】 まず、先行エレメント用の縦穴1を掘
削する。縦穴1は略エレメント1体分の間隔を確保しな
がら必要数掘削する。
First, the vertical hole 1 for the preceding element is excavated. The required number of vertical holes 1 is excavated while securing a space for approximately one element.

【0011】 つづいて、先行エレメント用の各縦穴
1内に鉄筋かご2を建て込む(図1参照)。鉄筋かご2
は、構築しようとする地中連続壁の規模に応じて必要量
の鉄筋を縦横に配して組み立てられ、その上部の幅方向
の両端部に鉄板などからなる仕切り部材3が取り付けら
れている(図7,8,9 参照) 。
Subsequently, the reinforcing cage 2 is built in each vertical hole 1 for the preceding element (see FIG. 1). Rebar cage 2
Is assembled by arranging the required amount of reinforcing bars vertically and horizontally according to the scale of the underground continuous wall to be constructed, and partition members 3 made of iron plates or the like are attached to both ends of the upper part in the width direction ( (See Figures 7,8,9).

【0012】仕切り部材3は、例えば鉄板を使用した場
合には、厚さ6〜12mm、長さ3〜4m程度有し、か
つ、幅が先行エレメント用の縦穴1の幅と略同等のもの
が使用されている。尚、この仕切部材3はコンクリート
中に埋め殺されてしまうものである。
The partition member 3 has a thickness of 6 to 12 mm and a length of 3 to 4 m, for example, when an iron plate is used, and has a width substantially equal to the width of the vertical hole 1 for the preceding element. It is used. The partition member 3 is buried in the concrete.

【0013】 つづいて、縦穴1内にコンクリート4
を打設する(図1参照)。コンクリート4の打設には、
コンクリートの分離を防止して緻密なコンクリートが得
られるようにトレミー管5を使用するものとする。尚、
トレミー管5はコンクリートの打設終了後、速やかに撤
去する。
Subsequently, concrete 4 is placed in the vertical hole 1.
(See Figure 1). For placing concrete 4,
The tremie pipe 5 is used so that the concrete can be prevented from being separated and dense concrete can be obtained. still,
The tremie pipe 5 is promptly removed after the concrete is poured.

【0014】コンクリート4が仕切り部材3の下端まで
達したら、左右仕切り部材3の外側の空間部6に砂利や
砕石7などの掘削し易い材料を地表面まで充填しなが
ら、左右仕切り部材3,3 の内側にのみコンクリート4を
地表面まで連続して打設する(図2参照)。このように
して個々の先行エレメント8が構築される(図3参
照)。
When the concrete 4 reaches the lower end of the partition member 3, the space 6 on the outside of the left and right partition member 3 is filled with an easily excavable material such as gravel and crushed stone 7 to the ground surface while the left and right partition members 3, 3 are filled. Concrete 4 is continuously cast to the ground surface only inside the ground (see Fig. 2). In this way the individual predecessor elements 8 are constructed (see FIG. 3).

【0015】この場合、隣接する左右先行エレメント8,
8 の仕切り部材3,3 間の間隔L1 は、後行エレメント用
の縦穴9の幅W(掘削機の掘削幅)よりやや大きめとし
(10〜50mm程度) 、また、左右先行エレメント8,8 間
の間隔L2 は、左右先行エレメント8,8 の仕切り部材3,
3 間の間隔L1 よりも左右空間部6の幅Sの2倍程度
(220 〜300 mm程度) だけ狭くする(図4,5参照)。
In this case, the adjacent left and right preceding elements 8,
The interval L 1 between the partition members 3, 3 of 8 is slightly larger than the width W of the vertical hole 9 for the trailing element (excavation width of the excavator) (about 10 to 50 mm), and the left and right preceding elements 8, 8 The distance L 2 between the partition members 3 of the left and right preceding elements 8,8 is
It is narrowed by about twice the width S of the left and right space 6 (about 220 to 300 mm) than the distance L 1 between the three (see FIGS. 4 and 5).

【0016】 各先行エレメント8の施工が終了した
ら、左右2体の先行エレメント8,8 間の中心部に掘削機
10を設置し、後行エレメント用の縦穴9の掘削を開始す
る(図5参照)。
When the construction of each preceding element 8 is completed, the excavator is placed in the center between the two preceding elements 8 on the left and right.
10 is installed and the excavation of the vertical hole 9 for the trailing element is started (see FIG. 5).

【0017】縦穴9の掘削に際し、初期段階において
は、左右先行エレメント8,8 の切削が不要で、しかも掘
削し易い砂利や砕石6を掘削するため仕切り部材3の下
端部までスムーズに掘り進めることができ、それ以降、
左右先行エレメント8,8端面の切削を伴いながら本来の
掘削が行われる。
When excavating the vertical hole 9, in the initial stage, it is not necessary to cut the left and right preceding elements 8,8, and in order to excavate the gravel and the crushed stone 6 which are easy to excavate, the excavation is smoothly advanced to the lower end of the partition member 3. And after that,
The original excavation is performed while cutting the left and right preceding elements 8 and 8 end faces.

【0018】係る場合、左右先行エレメント8,8 の仕切
り部材3,3間の間隔L1 が、縦穴9の幅W(L1
2 )と略等しくしてあるため、先行エレメント8の切
削が開始されても、位置ずれを起こさず、正しい切削ラ
インを確保することができる。
In such a case, the distance L 1 between the partition members 3, 3 of the left and right preceding elements 8, 8 is determined by the width W (L 1 > of the vertical hole 9).
Since it is substantially equal to L 2 ), even if the cutting of the preceding element 8 is started, no positional deviation occurs and a correct cutting line can be secured.

【0019】尚、仕切り部材下端部までの初期段階の掘
削には、掘削機10以外の例えば、バックホー、クラムシ
ェル等を使用し、それ以降の掘削に掘削機10を使用して
もよい。
Incidentally, a backhoe, a clamshell or the like other than the excavator 10 may be used for the initial stage excavation to the lower end of the partition member, and the excavator 10 may be used for the subsequent excavations.

【0020】 縦穴9の掘削が完了したら先行エレメ
ント8のときと同様に、縦穴9の中に鉄筋かご(図省
略)を建て込み、コンクリート4を打設することにより
後行エレメント11を先行エレメント8と一体的に構築す
る(図6参照)。尚、後行エレメント11は、複数個所で
並行して行うことにより工期の短縮化を図るものとす
る。
When the vertical hole 9 has been excavated, as in the case of the preceding element 8, a reinforcing bar cage (not shown) is built in the vertical hole 9 and the concrete 4 is placed to move the trailing element 11 to the preceding element 8. (See FIG. 6). In addition, the succeeding element 11 is intended to shorten the construction period by performing it at a plurality of locations in parallel.

【0021】図10は、円筒形状地下構造物などのように
曲面状の地中連続壁を構築する場合を示したものであ
る。係る場合、先行エレメント8の左右仕切り部材3,3
を構築される地中連続壁の曲率に応じて鉄筋かご2の端
部に斜めに添え付けることにより、構築しようとする地
中連続壁の曲率に対応させるものとする。
FIG. 10 shows a case where a curved underground continuous wall such as a cylindrical underground structure is constructed. In this case, the left and right partition members 3, 3 of the preceding element 8
According to the curvature of the underground continuous wall to be constructed, it is attached obliquely to the end of the reinforcing bar cage 2 to correspond to the curvature of the underground continuous wall to be constructed.

【0022】[0022]

【発明の効果】この発明は、以上説明したように構成さ
れているため、以下に記載するような効果を奏する。
Since the present invention is constructed as described above, it has the following effects.

【0023】隣接左右先行エレメント間に後行エレメン
ト用の縦穴を掘削機によって掘削する際に、掘削機の位
置の定まる初期段階の掘削は、先行エレメントの切削を
伴わず、しかも、切削し易い砂利や砕石を掘削するた
め、後行エレメントの初期段階の掘削をきわめてスムー
ズに行うことができる。
When excavating a vertical hole for a trailing element between adjacent left and right preceding elements by an excavator, the excavation at the initial stage where the position of the excavator is determined does not involve cutting the preceding element and is easy to cut gravel. Since excavation of rocks and crushed stones, excavation of the trailing element in the initial stage can be performed extremely smoothly.

【0024】また、左右仕切り部材によって初期段階の
掘削機の位置決め及び姿勢維持が確実になされるため、
掘削機の逃げを阻止し、正確な掘削ラインを保持しつ
つ、安定して掘削を行うことができる。
Further, since the left and right partition members reliably position and maintain the posture of the excavator in the initial stage,
The excavator can be prevented from running away and stable excavation can be performed while maintaining an accurate excavation line.

【0025】さらに、仕切り部材の外側の空間部には、
スペーサーボックス等といった定形部材を設置するので
はなく砂利や砕石などの不定形部材を充填するため、先
行エレメントと後行エレメントとの打ち継ぎ部の形状を
自由に変えることができ、従って、構築しようとする地
中連続壁に任意の曲率をつけることにより任意曲面形状
の地中連続壁も簡単に施工できる。
Further, in the space outside the partition member,
Since the irregular shape members such as gravel and crushed stone are filled instead of installing the fixed members such as the spacer box, it is possible to freely change the shape of the joining part between the preceding element and the succeeding element. By giving an arbitrary curvature to the underground continuous wall, the underground continuous wall with an arbitrary curved shape can be easily constructed.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明の施工方法を示す先行エレメントの施
工当初の正面図である。
FIG. 1 is a front view of a preceding element showing the construction method of the present invention at the beginning of construction.

【図2】この発明の施工方法を示す先行エレメントの施
工終了間際の正面図である。
FIG. 2 is a front view of the preceding element showing the construction method of the present invention, just before the completion of construction.

【図3】この発明の施工方法によって構築された先行エ
レメントの正面図である。
FIG. 3 is a front view of a preceding element constructed by the construction method of the present invention.

【図4】この発明の施工方法によって構築された隣接す
る左右先行エレメントの正面図である。
FIG. 4 is a front view of adjacent left and right preceding elements constructed by the construction method of the present invention.

【図5】この発明の施工方法を示す後行エレメント用の
縦穴掘削時の正面図である。
FIG. 5 is a front view showing a construction method of the present invention when excavating a vertical hole for a trailing element.

【図6】この発明の施工方法によって構築された先行エ
レメント及び後行エレメントの正面図である。
FIG. 6 is a front view of a leading element and a trailing element constructed by the construction method of the present invention.

【図7】この発明の施工方法で使用される鉄筋かごの正
面図である。
FIG. 7 is a front view of a reinforcing bar cage used in the construction method of the present invention.

【図8】図7に示す鉄筋かごの平面図である。8 is a plan view of the reinforcing cage shown in FIG. 7. FIG.

【図9】鉄筋かごの設置状態を示す平面図である。FIG. 9 is a plan view showing an installed state of a reinforcing bar cage.

【図10】この発明の他の施工方法を示す先行エレメン
トの平面図である。
FIG. 10 is a plan view of a preceding element showing another construction method of the present invention.

【符号の説明】[Explanation of symbols]

1…先行エレメント用の縦穴、2…鉄筋かご、3…仕切
り部材、4…コンクリート、5…トレミー管、6…空間
部、7…砂利や砕石、8…先行エレメント、9…後行エ
レメント用の縦穴、10…掘削機、11…後行エレメント。
1 ... Vertical hole for preceding element, 2 ... Reinforcing cage, 3 ... Partition member, 4 ... Concrete, 5 ... Tremy tube, 6 ... Space part, 7 ... Gravel and crushed stone, 8 ... Leading element, 9 ... For trailing element Vertical hole, 10 ... excavator, 11 ... trailing element.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 永瀬 信一 東京都港区元赤坂1丁目2番7号 鹿島建 設株式会社内 (72)発明者 鈴木 和夫 東京都港区元赤坂1丁目2番7号 鹿島建 設株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Shinichi Nagase 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Within Kashima Construction Co., Ltd. (72) Inventor Kazuo Suzuki 1-2-2 Moto-Akasaka, Minato-ku, Tokyo No. 7 Kashima Construction Co., Ltd.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 構築しようとする地中連続壁をその構築
方向に複数体のエレメントに分割し、最初に、先行エレ
メント用の縦穴を一定間隔おきに掘削し、当該縦穴にコ
ンクリートを打設して先行エレメントを構築し、つづい
て、これら先行エレメント間に前記先行エレメントの打
ち継ぎ方向の端面を切削しつつ後行エレメント用の縦穴
を掘削し、当該後行エレメント用の縦穴にコンクリート
を打設して先行エレメントと一体的に後行エレメントを
構築して地中連続壁を構築する地中連続壁の施工方法に
おいて、前記先行エレメント用の縦穴に打ち継ぎ方向の
端部に仕切り部材を有する鉄筋かごを建て込み、この仕
切り部材の外側の空間部に掘削容易な砂利若しくは砕石
を充填し、他の部分にコンクリートを打設して先行エレ
メントを構築し、つづいて、隣接する左右2体の先行エ
レメント間に後行エレメント用の縦穴を掘削機によって
掘削し、この後行エレメント用の縦穴の中に鉄筋かごを
建て込みコンクリートを打設して前記先行エレメントと
一体的に後行エレメントを構築することを特徴とする地
中連続壁の施工方法。
1. An underground continuous wall to be constructed is divided into a plurality of elements in the construction direction, first, vertical holes for preceding elements are excavated at regular intervals, and concrete is placed in the vertical holes. To construct a leading element, and then to drill a vertical hole for a trailing element while cutting the end face of the leading element in the splicing direction between these leading elements, and to place concrete in the vertical hole for the trailing element. In the method of constructing a continuous underground wall by constructing a trailing element integrally with the preceding element to construct a continuous underground wall, a reinforcing bar having a partition member at the end of the vertical hole for the preceding element in the joining direction. Build a car, fill the space outside the partition member with gravel or crushed stone that is easy to excavate, and place concrete in the other part to build the preceding element. Then, a vertical hole for a trailing element is drilled by an excavator between two adjacent left and right leading elements, and a reinforcing bar cage is built in the vertical hole for the trailing element to place concrete and the preceding element is added. A method for constructing a continuous underground wall, characterized by constructing a trailing element integrally with the above.
JP27780791A 1991-10-24 1991-10-24 Construction method of underground diaphragm wall Expired - Fee Related JP3147437B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27780791A JP3147437B2 (en) 1991-10-24 1991-10-24 Construction method of underground diaphragm wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27780791A JP3147437B2 (en) 1991-10-24 1991-10-24 Construction method of underground diaphragm wall

Publications (2)

Publication Number Publication Date
JPH05112930A true JPH05112930A (en) 1993-05-07
JP3147437B2 JP3147437B2 (en) 2001-03-19

Family

ID=17588542

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27780791A Expired - Fee Related JP3147437B2 (en) 1991-10-24 1991-10-24 Construction method of underground diaphragm wall

Country Status (1)

Country Link
JP (1) JP3147437B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102677720A (en) * 2012-05-31 2012-09-19 张永忠 Pebble trenching machine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102677720A (en) * 2012-05-31 2012-09-19 张永忠 Pebble trenching machine

Also Published As

Publication number Publication date
JP3147437B2 (en) 2001-03-19

Similar Documents

Publication Publication Date Title
JP2017210787A (en) Aseismatic structure of cut-and-cover tunnel
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JPH0768705B2 (en) Soil retaining method and its retaining pile
JP2003193495A (en) Underground structure constructing method
JPH0988080A (en) Sheathing structure
JPH10152985A (en) Constructing method of retaining wall
JPH05112930A (en) Construction method of underground continuous wall
JPH06306853A (en) Construction of underground structure
JPS5851092B2 (en) Earth retaining installation method using advance shoring frame
JPH03279600A (en) Construction method of large cavity
JP2001182477A (en) Device of partition iron plate
JPS6062327A (en) Construction of underwater continuous wall
JP2641182B2 (en) Slope stabilization method and slope expansion method
JPH0613770B2 (en) Method of constructing mountain retaining wall with parent pile
JPS5920822B2 (en) Seismic reinforcement method for embankments
JPH05112931A (en) Construction method of underground continuous wall
JP2558414B2 (en) Construction method of the main retaining wall and the retaining wall
JPS5996393A (en) Construction of hollow cavity
JPH0641993A (en) Learned retaining wall
JP2761531B2 (en) Construction method of guide for underground diaphragm wall
JP3089591B2 (en) Circular underground diaphragm wall
JPH11256604A (en) Burying method
JPH05140940A (en) Sheathing method in large depth excavation
JP2988516B2 (en) Construction method of shield excavation wall
JPS63125722A (en) Construction of underground continuous wall

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 19991109

LAPS Cancellation because of no payment of annual fees