JP3147437B2 - Construction method of underground diaphragm wall - Google Patents

Construction method of underground diaphragm wall

Info

Publication number
JP3147437B2
JP3147437B2 JP27780791A JP27780791A JP3147437B2 JP 3147437 B2 JP3147437 B2 JP 3147437B2 JP 27780791 A JP27780791 A JP 27780791A JP 27780791 A JP27780791 A JP 27780791A JP 3147437 B2 JP3147437 B2 JP 3147437B2
Authority
JP
Japan
Prior art keywords
vertical hole
concrete
partition member
constructing
underground continuous
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP27780791A
Other languages
Japanese (ja)
Other versions
JPH05112930A (en
Inventor
俊彦 村田
峯 石坂
行規 三善
信一 永瀬
和夫 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP27780791A priority Critical patent/JP3147437B2/en
Publication of JPH05112930A publication Critical patent/JPH05112930A/en
Application granted granted Critical
Publication of JP3147437B2 publication Critical patent/JP3147437B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は、地中に複数体の先行
エレメント(壁体)を構築し、これら先行エレメント間
に後行エレメントを先行エレメントと一体的に構築する
ことにより地中連続壁を構築する地中連続壁の施工方法
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an underground continuous wall by constructing a plurality of preceding elements (walls) in the ground and constructing a succeeding element integrally with the preceding elements between the preceding elements. The present invention relates to a method for constructing an underground continuous wall for constructing a wall.

【0002】[0002]

【従来の技術】一般に、地中連続壁は土留め壁や構造物
の基礎などとして構築されるものであるが、今日、比較
的広く実施されている方法としては以下に述べるような
方法が知られている。
2. Description of the Related Art In general, underground continuous walls are constructed as earth retaining walls or foundations of structures, but the following methods are known as methods relatively widely practiced today. Have been.

【0003】まず、地中に、地中連続壁の部分を構成す
る複数体の先行エレメント(壁体)を略1体のエレメン
トの長さ分を隔てた状態に構築する。これらの先行エレ
メントは最初に縦穴を掘削し、この縦穴内に鉄筋かごを
建て込み、つづいてコンクリートを打設することにより
構築する。先行エレメントを施工できたら、隣接する左
右2体の先行エレメント間を掘削して後行エレメント用
の縦穴を掘削する。
[0003] First, a plurality of preceding elements (walls) constituting a part of an underground continuous wall are constructed in the ground so as to be separated from each other by the length of substantially one element. These antecedent elements are constructed by first drilling a well, building a reinforced cage into the well and then casting concrete. When the preceding element can be constructed, the vertical hole for the succeeding element is excavated by excavating between two adjacent left and right preceding elements.

【0004】この縦穴の掘削と並行して前記先行エレメ
ントの打ち継ぎ方向の端面を所定寸法(通常片端面10セ
ンチ程度) 切削除去する。
[0004] In parallel with the excavation of the vertical hole, the end face in the joining direction of the preceding element is cut and removed by a predetermined size (usually about 10 cm on one end face).

【0005】先行エレメントの端面を切削除去するの
は、端面に付着したスライムの除去と、いわゆる打ち継
ぎ面の目荒しのためである。しかる後に、先行エレメン
トと同様にこの後行エレメント用の縦穴内に鉄筋かごを
建て込み、コンクリートを打設することにより先行エレ
メントと一体的に後行エレメントを施工して地中連続壁
の全体を施工するものである。
The reason why the end face of the preceding element is cut off is to remove slime adhering to the end face and so-called roughening of the joint face. Then, like the preceding element, a reinforcing bar is erected in the vertical hole for the succeeding element, and concrete is cast to construct the succeeding element integrally with the preceding element and the entire underground continuous wall is constructed. It is to be constructed.

【0006】[0006]

【発明が解決しようとする課題】ところで、上記従来工
法において、隣接する左右2体の先行エレンメント間に
後行エレメント用の縦穴を掘削する際に、掘削機を左右
2体の先行エレメント間のちょうど中間部にセットし、
後行エレメント用の縦穴の掘削と並行して先行エレメン
トの端面を切削するが、先行エレメントがコンクリート
製であるため、特に掘削の初期段階、つまり左右2体の
先行エレメントの上端面部に掘削機の掘削ドリルが掛か
り、掘削及びエレメント端面の切削を開始しようとする
時に、硬質であるコンクリートに掘削機のドリルがスム
ーズに食いつかずに、いわゆる逃げを生じてしまう。こ
のため、位置ずれを起こして正しい切削ラインを確保で
きないばかりでなく、掘削機の安定を欠いて偏荷重を招
くといった不都合を生ずる場合が多々あった。
In the above-mentioned conventional method, when excavating a vertical hole for a succeeding element between two adjacent left and right preceding elements, the excavator is moved between the two right and left preceding elements. Just set in the middle,
The end face of the preceding element is cut in parallel with the excavation of the vertical hole for the succeeding element. However, since the preceding element is made of concrete, especially in the initial stage of excavation, that is, at the upper end surface of the left and right preceding elements, the excavator is used. When a drill is used to start drilling and cutting of the end face of the element, the drill of the excavator does not bite into the hard concrete so that a so-called escape occurs. For this reason, not only is it not possible to secure a correct cutting line due to displacement, but also there are many cases in which the stability of the excavator is lost and an eccentric load is caused.

【0007】この発明はこのような前記従来の課題を解
決するために提案されたもので、隣接する左右2体の先
行エレメント間に後行エレメント用の縦孔を掘削する際
に、掘削機の位置決め及び安定した保持を確実にでき、
これにより正確な切削ラインを保持しつつ安定した掘削
を可能にした地中連続壁の施工方法を提供することを目
的とする。
The present invention has been proposed in order to solve the above-mentioned conventional problems. When excavating a vertical hole for a succeeding element between two adjacent left and right preceding elements, the present invention has been proposed. Positioning and stable holding can be ensured,
Accordingly, it is an object of the present invention to provide a method of constructing an underground continuous wall that enables stable excavation while maintaining an accurate cutting line.

【0008】[0008]

【課題を解決するための手段】以上の課題を解決するた
めの手段として、この発明に係る地中連続壁の施工方法
は、先行エレメント用の縦穴を掘削し、この縦穴内にコ
ンクリートを打設して先行エレメントを一定間隔おきに
構築し、つづいて隣接する先行エレメント間に後行エレ
メント用の縦穴を前記先行エレメントの打ち継ぎ方向の
端面を切削しつつ掘削し、この後行エレメント用の縦穴
内にコンクリートを打設して先行エレメントと一体をな
す後行エレメントを構築して地中連続壁を構築する地中
連続壁の施工方法において、先行エレメント用の縦穴内
に、コンクリート打ち継ぎ方向の上部の両端部に仕切り
部材を有する鉄筋かごを建て込み、つづいて先行エレメ
ント用の縦穴内に前記仕切り部材の下端までコンクリー
トを打設し、つづいてこの仕切り部材の外側の空間部に
砂利または砕石を充填し、かつ前記仕切り部材の内側に
コンクリートを打設して先行エレメントを構築し、つづ
いて隣接する先行エレメント間に後行エレメント用の縦
穴を掘削機によって、前記左右仕切り部材で切削ライン
を保持しつつ、前記砂利または砕石とともに掘削し、つ
づいてこの後行エレメント用の縦穴内に鉄筋かごを建て
込みかつコンクリートを打設することにより、前記仕切
り部材をコンクリート中に埋め殺しかつ先行エレメント
と一体の後行エレメントを構築する。
As a means for solving the above problems, a method of constructing an underground continuous wall according to the present invention is to excavate a vertical hole for a preceding element and cast concrete into the vertical hole. The preceding elements are constructed at regular intervals, and then a vertical hole for the succeeding element is excavated between adjacent preceding elements while cutting the end face in the joining direction of the preceding element. In a method of constructing an underground continuous wall by casting concrete inside and constructing a subsequent element that is integral with the preceding element and constructing an underground continuous wall, the concrete joining direction in the vertical hole for the preceding element is Reinforcing cages having partition members at both upper ends are erected, and concrete is poured into the vertical hole for the preceding element up to the lower end of the partition member. A space outside the lever member is filled with gravel or crushed stone, and concrete is cast inside the partition member to construct a leading element, and then a vertical hole for a succeeding element is provided between adjacent preceding elements. The excavator, the left and right partition members with cutting line
While excavating with the gravel or crushed stone, and then laying a reinforcing cage in the vertical hole for the succeeding element and placing concrete, thereby embedding the partition member in concrete and leading element Construct a follow-up element with

【0009】[0009]

【実施例】以下、この発明に係る地中連続壁の施工方法
を図1〜図9に基づいて順をおって説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A method for constructing an underground continuous wall according to the present invention will be described below with reference to FIGS.

【0010】 まず、先行エレメント用の縦穴1を掘
削する。縦穴1は略エレメント1体分の間隔を確保しな
がら必要数掘削する。
First, a vertical hole 1 for a preceding element is excavated. The required number of vertical holes 1 is excavated while securing an interval of approximately one element.

【0011】 つづいて、先行エレメント用の各縦穴
1内に鉄筋かご2を建て込む(図1参照)。鉄筋かご2
は、構築しようとする地中連続壁の規模に応じて必要量
の鉄筋を縦横に配して組み立てられ、その上部の幅方向
の両端部に鉄板などからなる仕切り部材3が取り付けら
れている(図7,8,9 参照) 。
Subsequently, a reinforcing cage 2 is built in each vertical hole 1 for the preceding element (see FIG. 1). Reinforcing basket 2
Is assembled by arranging a required amount of reinforcing bars vertically and horizontally according to the scale of the underground continuous wall to be constructed, and a partition member 3 made of an iron plate or the like is attached to both ends of the upper part in the width direction ( See Figures 7, 8, and 9).

【0012】仕切り部材3は、例えば鉄板を使用した場
合には、厚さ6〜12mm、長さ3〜4m程度有し、か
つ、幅が先行エレメント用の縦穴1の幅と略同等のもの
が使用されている。尚、この仕切部材3はコンクリート
中に埋め殺されてしまうものである。
For example, when an iron plate is used, the partition member 3 has a thickness of about 6 to 12 mm, a length of about 3 to 4 m, and a width substantially equal to the width of the vertical hole 1 for the preceding element. It is used. The partition member 3 is buried in the concrete and killed.

【0013】 つづいて、縦穴1内にコンクリート4
を打設する(図1参照)。コンクリート4の打設には、
コンクリートの分離を防止して緻密なコンクリートが得
られるようにトレミー管5を使用するものとする。尚、
トレミー管5はコンクリートの打設終了後、速やかに撤
去する。
Subsequently, concrete 4 is placed in the vertical hole 1.
(See FIG. 1). For placing concrete 4,
The tremy tube 5 is used so that concrete can be prevented from separating and dense concrete can be obtained. still,
The tremy tube 5 is removed immediately after the concrete is poured.

【0014】コンクリート4が仕切り部材3の下端まで
達したら、左右仕切り部材3の外側の空間部6に砂利や
砕石7などの掘削し易い材料を地表面まで充填しなが
ら、左右仕切り部材3,3 の内側にのみコンクリート4を
地表面まで連続して打設する(図2参照)。このように
して個々の先行エレメント8が構築される(図3参
照)。
When the concrete 4 reaches the lower end of the partition member 3, the space portion 6 outside the left and right partition member 3 is filled with an easily excavated material such as gravel or crushed stone 7 to the ground surface while the right and left partition members 3, 3 are being filled. Concrete 4 is continuously poured into the ground only to the inside of the ground (see FIG. 2). In this way, the individual preceding elements 8 are constructed (see FIG. 3).

【0015】この場合、隣接する左右先行エレメント8,
8 の仕切り部材3,3 間の間隔L1 は、後行エレメント用
の縦穴9の幅W(掘削機の掘削幅)よりやや大きめとし
(10〜50mm程度) 、また、左右先行エレメント8,8 間
の間隔L2 は、左右先行エレメント8,8 の仕切り部材3,
3 間の間隔L1 よりも左右空間部6の幅Sの2倍程度
(220 〜300 mm程度) だけ狭くする(図4,5参照)。
In this case, the adjacent left and right preceding elements 8,
Distance L 1 between the partition member 3,3 8 slightly with larger than the width W of the vertical hole 9 for the trailing element (excavation width of the excavator) (about 10 to 50 mm), also lateral preceding elements 8,8 distance L 2 between the partition member 3 of the right and left preceding elements 8,8,
Than the distance L 1 between 3 about twice (about 220 to 300 mm) of the width S of the left and right space portions 6 only to narrow (see FIGS. 4 and 5).

【0016】 各先行エレメント8の施工が終了した
ら、左右2体の先行エレメント8,8 間の中心部に掘削機
10を設置し、後行エレメント用の縦穴9の掘削を開始す
る(図5参照)。
When the construction of each preceding element 8 is completed, the excavator is located at the center between the two right and left preceding elements 8
10 is installed, and excavation of the vertical hole 9 for the succeeding element is started (see FIG. 5).

【0017】縦穴9の掘削に際し、初期段階において
は、左右先行エレメント8,8 の切削が不要で、しかも掘
削し易い砂利や砕石6を掘削するため仕切り部材3の下
端部までスムーズに掘り進めることができ、それ以降、
左右先行エレメント8,8端面の切削を伴いながら本来の
掘削が行われる。
In the initial stage of the excavation of the vertical hole 9, it is not necessary to cut the left and right preceding elements 8 and 8, and the excavation of the gravel or crushed stone 6 that is easy to excavate is performed smoothly to the lower end of the partition member 3. After that,
The original excavation is performed while cutting the left and right preceding elements 8, 8 end faces.

【0018】係る場合、左右先行エレメント8,8 の仕切
り部材3,3間の間隔L1 が、縦穴9の幅W(L1
2 )と略等しくしてあるため、先行エレメント8の切
削が開始されても、位置ずれを起こさず、正しい切削ラ
インを確保することができる。
In such a case, the interval L 1 between the partition members 3 of the left and right preceding elements 8 is equal to the width W (L 1 >) of the vertical hole 9.
L 2) and for substantially made equal, even if the cutting of the preceding element 8 is started, without causing any positional deviation, it is possible to ensure proper cutting line.

【0019】尚、仕切り部材下端部までの初期段階の掘
削には、掘削機10以外の例えば、バックホー、クラムシ
ェル等を使用し、それ以降の掘削に掘削機10を使用して
もよい。
In the initial stage excavation up to the lower end of the partition member, for example, a backhoe, a clamshell or the like other than the excavator 10 may be used, and the excavator 10 may be used for subsequent excavation.

【0020】 縦穴9の掘削が完了したら先行エレメ
ント8のときと同様に、縦穴9の中に鉄筋かご(図省
略)を建て込み、コンクリート4を打設することにより
後行エレメント11を先行エレメント8と一体的に構築す
る(図6参照)。尚、後行エレメント11は、複数個所で
並行して行うことにより工期の短縮化を図るものとす
る。
When the excavation of the vertical hole 9 is completed, similarly to the case of the preceding element 8, a reinforcing bar (not shown) is erected in the vertical hole 9, and concrete 4 is cast, so that the succeeding element 11 is replaced with the preceding element 8. (See FIG. 6). The following element 11 is intended to shorten the construction period by performing the operation at a plurality of locations in parallel.

【0021】図10は、円筒形状地下構造物などのように
曲面状の地中連続壁を構築する場合を示したものであ
る。係る場合、先行エレメント8の左右仕切り部材3,3
を構築される地中連続壁の曲率に応じて鉄筋かご2の端
部に斜めに添え付けることにより、構築しようとする地
中連続壁の曲率に対応させるものとする。
FIG. 10 shows a case where a curved underground continuous wall such as a cylindrical underground structure is constructed. In such a case, the left and right partition members 3, 3 of the preceding element 8
Is obliquely attached to the end of the reinforcing steel cage 2 in accordance with the curvature of the underground continuous wall to be constructed, so as to correspond to the curvature of the underground continuous wall to be constructed.

【0022】[0022]

【発明の効果】この発明は、以上説明したように構成さ
れているため、以下に記載するような効果を奏する。
Since the present invention is configured as described above, it has the following effects.

【0023】隣接左右先行エレメント間に後行エレメン
ト用の縦穴を掘削機によって掘削する際に、掘削機の位
置の定まる初期段階の掘削は、先行エレメントの切削を
伴わず、しかも、切削し易い砂利や砕石を掘削するた
め、後行エレメントの初期段階の掘削をきわめてスムー
ズに行うことができる。
When a vertical hole for a succeeding element is excavated between adjacent left and right preceding elements by an excavator, excavation at an initial stage in which the position of the excavator is determined does not involve cutting of the preceding element and is easy to cut. In order to excavate rocks and crushed stones, the excavation of the succeeding element in the initial stage can be performed extremely smoothly.

【0024】また、左右仕切り部材によって初期段階の
掘削機の位置決め及び姿勢維持が確実になされるため、
掘削機の逃げを阻止し、正確な掘削ラインを保持しつ
つ、安定して掘削を行うことができる。
Further, since the positioning and posture of the excavator in the initial stage are surely maintained by the left and right partition members,
Excavation can be stably performed while preventing the excavator from escaping and maintaining an accurate excavation line.

【0025】さらに、仕切り部材の外側の空間部には、
スペーサーボックス等といった定形部材を設置するので
はなく砂利や砕石などの不定形部材を充填するため、先
行エレメントと後行エレメントとの打ち継ぎ部の形状を
自由に変えることができ、従って、構築しようとする地
中連続壁に任意の曲率をつけることにより任意曲面形状
の地中連続壁も簡単に施工できる。
Further, in the space outside the partition member,
In order to fill in irregular members such as gravel and crushed stones instead of installing fixed members such as spacer boxes, the shape of the joint between the preceding element and the succeeding element can be changed freely, so let's build The underground continuous wall having an arbitrary curved surface shape can be easily constructed by giving an arbitrary curvature to the underground continuous wall.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この発明の施工方法を示す先行エレメントの施
工当初の正面図である。
FIG. 1 is a front view of a preceding element at the beginning of construction showing a construction method of the present invention.

【図2】この発明の施工方法を示す先行エレメントの施
工終了間際の正面図である。
FIG. 2 is a front view of the preceding element immediately before the completion of construction, showing the construction method of the present invention.

【図3】この発明の施工方法によって構築された先行エ
レメントの正面図である。
FIG. 3 is a front view of a preceding element constructed by the construction method of the present invention.

【図4】この発明の施工方法によって構築された隣接す
る左右先行エレメントの正面図である。
FIG. 4 is a front view of adjacent left and right preceding elements constructed by the construction method of the present invention.

【図5】この発明の施工方法を示す後行エレメント用の
縦穴掘削時の正面図である。
FIG. 5 is a front view showing a construction method of the present invention when excavating a vertical hole for a succeeding element.

【図6】この発明の施工方法によって構築された先行エ
レメント及び後行エレメントの正面図である。
FIG. 6 is a front view of a leading element and a trailing element constructed by the construction method of the present invention.

【図7】この発明の施工方法で使用される鉄筋かごの正
面図である。
FIG. 7 is a front view of a reinforcing cage used in the construction method of the present invention.

【図8】図7に示す鉄筋かごの平面図である。FIG. 8 is a plan view of the reinforcing cage shown in FIG. 7;

【図9】鉄筋かごの設置状態を示す平面図である。FIG. 9 is a plan view showing an installation state of a reinforcing cage.

【図10】この発明の他の施工方法を示す先行エレメン
トの平面図である。
FIG. 10 is a plan view of a preceding element showing another construction method of the present invention.

【符号の説明】[Explanation of symbols]

1…先行エレメント用の縦穴、2…鉄筋かご、3…仕切
り部材、4…コンクリート、5…トレミー管、6…空間
部、7…砂利や砕石、8…先行エレメント、9…後行エ
レメント用の縦穴、10…掘削機、11…後行エレメント。
DESCRIPTION OF SYMBOLS 1 ... Vertical hole for preceding element, 2 ... Reinforcing cage, 3 ... Partition member, 4 ... Concrete, 5 ... Tremy tube, 6 ... Space, 7 ... Gravel and crushed stone, 8 ... Leading element, 9 ... For trailing element Vertical hole, 10 ... excavator, 11 ... trailing element.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 三善 行規 東京都港区元赤坂1丁目3番8号 鹿島 建設株式会社東京支店内 (72)発明者 永瀬 信一 東京都港区元赤坂1丁目2番7号 鹿島 建設株式会社内 (72)発明者 鈴木 和夫 東京都港区元赤坂1丁目2番7号 鹿島 建設株式会社内 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Yukiki Miyoshi 1-3-8 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. Tokyo Branch (72) Inventor Shinichi Nagase 1-2-2 Moto-Akasaka, Minato-ku, Tokyo No. 7 Kashima Construction Co., Ltd. (72) Inventor Kazuo Suzuki Kashima Construction Co., Ltd. 1-2-7 Moto-Akasaka, Minato-ku, Tokyo

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 先行エレメント用の縦穴を掘削し、この
縦穴内にコンクリートを打設して先行エレメントを一定
間隔おきに構築し、つづいて隣接する先行エレメント間
に後行エレメント用の縦穴を前記先行エレメントの打ち
継ぎ方向の端面を切削しつつ掘削し、この後行エレメン
ト用の縦穴内にコンクリートを打設して先行エレメント
と一体をなす後行エレメントを構築して地中連続壁を構
築する地中連続壁の施工方法において、先行エレメント
用の縦穴内に、コンクリート打ち継ぎ方向の上部の両端
部に仕切り部材を有する鉄筋かごを建て込み、つづいて
先行エレメント用の縦穴内に前記仕切り部材の下端まで
コンクリートを打設し、つづいてこの仕切り部材の外側
の空間部に砂利または砕石を充填し、かつ前記仕切り部
材の内側にコンクリートを打設して先行エレメントを構
築し、つづいて隣接する先行エレメント間に後行エレメ
ント用の縦穴を掘削機によって、前記左右仕切り部材で
切削ラインを保持しつつ、前記砂利または砕石とともに
掘削し、つづいてこの後行エレメント用の縦穴内に鉄筋
かごを建て込みかつコンクリートを打設することによ
り、前記仕切り部材をコンクリート中に埋め殺しかつ先
行エレメントと一体の後行エレメントを構築することを
特徴とする地中連続壁の施工方法。
1. A vertical hole for a preceding element is excavated, concrete is poured into the vertical hole to construct a preceding element at regular intervals, and then a vertical hole for a succeeding element is formed between adjacent preceding elements. Excavating while cutting the end face of the preceding element in the splicing direction, placing concrete in the vertical hole for this succeeding element and constructing the following element that is integral with the preceding element to construct an underground continuous wall In the method for constructing an underground continuous wall, in a vertical hole for the preceding element, a reinforcing steel cage having partition members at both upper ends in the concrete splicing direction is erected, and then the partition member is inserted into the vertical hole for the preceding element. Concrete is poured to the lower end, and then the space outside the partition member is filled with gravel or crushed stone, and concrete is filled inside the partition member. A leading hole for the following element between the adjacent preceding elements by an excavator,
By excavating with the gravel or crushed stone while holding the cutting line , and then laying a reinforcing cage in the vertical hole for the succeeding element and placing concrete, the partition member is buried in concrete and A method for constructing an underground continuous wall, comprising constructing a trailing element integral with a preceding element.
JP27780791A 1991-10-24 1991-10-24 Construction method of underground diaphragm wall Expired - Fee Related JP3147437B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27780791A JP3147437B2 (en) 1991-10-24 1991-10-24 Construction method of underground diaphragm wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27780791A JP3147437B2 (en) 1991-10-24 1991-10-24 Construction method of underground diaphragm wall

Publications (2)

Publication Number Publication Date
JPH05112930A JPH05112930A (en) 1993-05-07
JP3147437B2 true JP3147437B2 (en) 2001-03-19

Family

ID=17588542

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27780791A Expired - Fee Related JP3147437B2 (en) 1991-10-24 1991-10-24 Construction method of underground diaphragm wall

Country Status (1)

Country Link
JP (1) JP3147437B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102677720A (en) * 2012-05-31 2012-09-19 张永忠 Pebble trenching machine

Also Published As

Publication number Publication date
JPH05112930A (en) 1993-05-07

Similar Documents

Publication Publication Date Title
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JPH0768705B2 (en) Soil retaining method and its retaining pile
JP6678487B2 (en) How to build an underground structure
JP3147437B2 (en) Construction method of underground diaphragm wall
JPH0988080A (en) Sheathing structure
JP2003193495A (en) Underground structure constructing method
JP3010841B2 (en) Construction method of underground diaphragm wall
JP2766159B2 (en) Excavator and underground diaphragm wall method
JPS5851092B2 (en) Earth retaining installation method using advance shoring frame
JP2001173135A (en) Underground exterior wall of structure and method of construction thereof
JPS5920822B2 (en) Seismic reinforcement method for embankments
JP2636605B2 (en) Construction method of continuous underground wall
JPS6062327A (en) Construction of underwater continuous wall
JP2536701B2 (en) Earth retaining method for deep excavation
JP2824217B2 (en) Construction method of retaining wall and retaining material for retaining wall
JPH09209377A (en) Constructing method for l-shaped retaining wall
JP3776280B2 (en) Mountain fastening method
JP2565452B2 (en) Construction method of self-supporting retaining wall
JP3045907B2 (en) Construction method of continuous wall support pile
JP3049347B2 (en) Earth retaining wall
JP2761531B2 (en) Construction method of guide for underground diaphragm wall
JPH0641993A (en) Learned retaining wall
JPH073781A (en) Method for constructing foundation footing on cast-in-place concrete pile head
JP3089591B2 (en) Circular underground diaphragm wall
JP3066672B2 (en) Groundwater condensing method for underground diaphragm wall

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 19991109

LAPS Cancellation because of no payment of annual fees