JPH0452375A - Method for constructing subsequent placing member in construction method of reverse placing - Google Patents

Method for constructing subsequent placing member in construction method of reverse placing

Info

Publication number
JPH0452375A
JPH0452375A JP16210090A JP16210090A JPH0452375A JP H0452375 A JPH0452375 A JP H0452375A JP 16210090 A JP16210090 A JP 16210090A JP 16210090 A JP16210090 A JP 16210090A JP H0452375 A JPH0452375 A JP H0452375A
Authority
JP
Japan
Prior art keywords
concrete
placing
hose
formwork
mold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP16210090A
Other languages
Japanese (ja)
Inventor
Yasunori Shigemoto
重本 保則
Itoshi Izumi
和泉 意登志
Toshio Saito
俊夫 斉藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP16210090A priority Critical patent/JPH0452375A/en
Publication of JPH0452375A publication Critical patent/JPH0452375A/en
Pending legal-status Critical Current

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

PURPOSE:To enhance the workability, safety, and efficiency by constructing concrete placing of a subsequent placing member by means of press-in of concrete from the lower portion of a mold. CONSTITUTION:A mold tie-in jig 15 having a nonreturn valve mechanism is interposed in the end of a hose 2 and concrete is placed from the lower portion of a mold using the hose 2. As a result, air that tends to be contained in the concrete is also pushed out toward the upper portion of the mold and the concrete is raised while in a uniformly mixed state wherein separation of aggregates does not occur. Dense, strong, and durable concrete can thus be placed without leaving any hollow portion and can also be finished in such a manner that only a protrusion which can be easily hoisted is left.

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は、逆打ち工法における後打ち部材の構築方法に
関する。
DETAILED DESCRIPTION OF THE INVENTION "Field of Industrial Application" The present invention relates to a method for constructing a post-cast member in a reverse casting method.

「従来の技術」 逆打ち工法とは、山留め壁を支持する仮設部材(山留め
部材)の切ぼり・復起しを用いず、掘削とともに地下躯
体の床スラブ−1梁、柱を施工し、これに土庄、水圧を
負担させながら順次堀り下げていく工法である。
``Conventional technology'' The reverse construction method does not involve cutting out or restoring temporary members (mounting retaining members) that support retaining walls, but instead involves excavating and constructing the floor slab-1 beams and columns for the underground framework. This is a construction method in which the excavation is carried out one after another while applying the burden of water pressure.

この工法は、地下躯体の梁、床スラブを山留め部材とし
て利用するので、他の工法にくらべて発生応力は少ない
、また、1階の床がまず施工され、山留壁頭部が固定さ
れるので、根切り期間中の変形量は比較的小さい。1階
床スラブは作業床として早くから利用でき、地上階、地
下階も同時に施工されるため工期は短縮される。よって
、山留め部材として利用しない柱、壁等は後打ち部材と
して、地下階の床スラブの施工後に構築される。その施
工態様は、第2.3図に示される通りである。
This construction method uses the beams and floor slabs of the underground structure as retaining members, so less stress is generated compared to other construction methods.Also, the first floor floor is constructed first, and the head of the retaining wall is fixed. Therefore, the amount of deformation during the root pruning period is relatively small. The first-floor floor slab can be used as a work floor from an early stage, and the construction period is shortened because the ground floor and basement floor are constructed at the same time. Therefore, columns, walls, etc. that are not used as retaining members are constructed as post-cast members after the basement floor slab is constructed. The construction mode is as shown in Fig. 2.3.

すなわち、第2図は、壁等の型枠1の上端からコンクリ
ート打設用ホース2を、挿入並びに空気抜き出来るよう
斜め上方に向けてアゴ出し3させて開口し、この開口部
よりコンクリート打設用ホース2を挿入し、コンクリー
ト4を打設するとした場合である。
That is, in FIG. 2, a hose 2 for concrete pouring is opened from the upper end of a formwork 1 such as a wall with a jaw 3 extending diagonally upward so that it can be inserted and air removed, and the concrete pouring hose 2 is opened from the upper end of a formwork 1 such as a wall. This is a case where the hose 2 is inserted and concrete 4 is poured.

一方、第3図は、壁等の型枠1の上端に上階床スラブ5
を貫通して取付けたコンクリート打設用のスリーブ6を
接続させて、コンクリート4を当該スリーブ6を介して
打設するとした場合である。
On the other hand, in Fig. 3, an upper floor slab 5
This is a case where a sleeve 6 for concrete pouring is attached through the sleeve 6 and the concrete 4 is poured through the sleeve 6.

尚、地下1階フロアに相当する上記のスラブ5の階にお
ける後打ちは、図示の如く1階床スラブ7より粱8を垂
下貫通してスリーブ9を挿着し、当該スリーブ9を介し
て打設されることもある。これは、1階では未だ壁構築
がなされていないため、下階の壁厚部に垂下貫通がとり
行なえるからである。
Incidentally, for post-casting on the floor of the slab 5, which corresponds to the first basement floor, as shown in the figure, a sleeve 9 is inserted through the pipe 8 hanging down from the first floor slab 7, and a sleeve 9 is inserted through the sleeve 9. Sometimes it is set up. This is because the walls have not yet been constructed on the first floor, so it is possible to penetrate through the wall thickness of the lower floor.

叙上の第3図に示す後打ちは、上端が粱8で閉塞された
条件のもとでなされるので、既述のアゴ出し3の如く、
壁等の型枠1の上端部には、空気抜きを確保しなければ
ならない。
The after-stroke shown in Fig. 3 above is done under the condition that the upper end is closed with the katana 8, so like the chin extension 3 mentioned above,
Air ventilation must be ensured at the upper end of the formwork 1, such as a wall.

第4図a −dは、この各種の空気抜き手段を示す。す
なわち、梁8下端面に突き合う壁型枠1を所定間隙(1
0前程度)のスリット10を介して突き合わせる(a)
。壁等の型枠1を粱8の先端面より所定間隙(10m程
度)前方にずらして設置して、スリット11を介在させ
る(b)。粱8下端面に突き合う壁等の型枠1上端部に
所定径(10〜18 mm程度)の透孔16群を穿設す
る(c)。粱8下端面に突き合う壁等の型枠1上端部に
所定間隔をもって減圧管12を設置する(d)。
Figures 4a-d show these various air venting means. That is, the wall formwork 1 that abuts the lower end surface of the beam 8 is spaced at a predetermined gap (1
(a)
. A formwork 1 such as a wall is set so as to be shifted forward by a predetermined gap (about 10 m) from the tip end surface of the katana 8, and a slit 11 is interposed therebetween (b). A group of 16 through holes having a predetermined diameter (approximately 10 to 18 mm) are bored in the upper end of the formwork 1, such as a wall that abuts the lower end surface of the casing 8 (c). Decompression pipes 12 are installed at predetermined intervals at the upper end of the formwork 1, such as a wall that abuts the lower end surface of the casing 8 (d).

「発明が解決しようとする課題」 従来の後打ちにあっては、第2図の場合では、アゴ型枠
を設置しなければならず、また、コンクリート打設に際
して足場13が必要となるばかりでなく、この足場13
上でホース2を支持するという重労働に耐えねばならな
い。さらに、型枠l脱型後、第5図に示す如く連らなっ
て突き出たアゴ部のコンク!I −) 14を折らなけ
ればならない煩わしさがある。
"Problems to be Solved by the Invention" In conventional post-casting, in the case shown in Figure 2, jaw forms must be installed, and scaffolding 13 is also required when pouring concrete. Not this scaffolding 13
It has to withstand the hard work of supporting the hose 2 on top. Furthermore, after removing the formwork l, the concavities of the jaws protruded in a row as shown in Figure 5! I-) There is a hassle of having to fold 14.

尚、このアゴ部の折りは、第6図a、bに示されるが、
上階の床スラブ5等がフラットスラブでなく、粱8下端
と床スラブ5との間に充分な間隔が確保されている場合
(a)には差し支えは無いが、フラットスラブであって
充分な間隔が確保し得ない場合(b)には、頭がつかえ
て、無理な姿勢が強いられ、危険であると共に非能率と
なる。かかる事情は第2図に示すコンクリート打設に際
しても同じである。
Incidentally, the folding of this jaw part is shown in Figures 6a and b,
If the floor slab 5 etc. on the upper floor is not a flat slab and there is a sufficient distance between the lower end of the floor 8 and the floor slab 5, there is no problem with (a), but if it is a flat slab and there is sufficient space. If the distance cannot be secured (b), the head gets stuck and the person is forced to take an awkward posture, which is both dangerous and inefficient. This situation is the same when concrete is poured as shown in FIG.

第3図の場合では、コンクリート打設後スリーブ6.9
を取り除かねばならない、スリーブ入れが極めて困難で
ある、スリーブ抜き跡の孔埋めをしなければならない等
の煩わしさがある。さらに、いずれの場合にあっても、
上方からコンクリートを投入するため、コンクリートの
自由落下高さが大きくなり、また落下途中で鉄筋等の障
害物に衝突し、コンクリートの骨材分離を生起し易く、
特に階高が高い場合や、鉄筋が輻検して配設されている
場合等にこのような影響が出易い、またコンクリート落
下時の巻込み空気によって打上りコンクリートにジャン
カ、大きな気泡の発生を生起する、等の問題点がある。
In the case of Fig. 3, the sleeve 6.9 after concrete pouring
There are some troubles such as having to remove the sleeve, making it extremely difficult to insert the sleeve, and having to fill in the hole where the sleeve was removed. Furthermore, in any case,
Since concrete is poured from above, the free fall height of the concrete becomes large, and the concrete is likely to collide with obstacles such as reinforcing bars during the fall, causing aggregate separation of the concrete.
This effect is particularly likely to occur when the floor height is high or when reinforcing bars are placed with a concave inspection.In addition, the air entrained when concrete falls can cause junk and large air bubbles to form in the poured concrete. There are problems such as:

本発明は、不安定な足場上でのコンクリート打設ホース
の支持やアゴ研りのような厳しい作業や、スリーブを介
してのコンクリート打設の要、さらには、上方からコン
クリートを打設することに起因する不都合を全て解消し
た後打ち部材の構築方法を提供することを目的としてい
る。
The present invention is useful for supporting concrete pouring hoses on unstable scaffolding, for severe work such as jaw grinding, for concrete pouring through sleeves, and for pouring concrete from above. It is an object of the present invention to provide a method for constructing a post-cast member that eliminates all the inconveniences caused by.

「課題を解決するだめの手段」 上記目的を達成するために、本発明の構築方法にあって
は、後打ち部材のコンクリート打設を型枠下部よりコン
クリートを圧入してするとしたものである。
"Another Means to Solve the Problem" In order to achieve the above object, in the construction method of the present invention, concrete is poured into the post-cast member by press-fitting the concrete from the lower part of the formwork.

「作用」 上記のように構成された後打ち部材の構築方法によるな
らば、既述した上方からコンクリートを投入する場合に
発生した問題は全て解消する。すなわち、コンクリート
を上方より投入するのではなくして、下部より圧入する
とした工法は、順打ち工法のもとで、特開昭56−93
974号公報、特開昭64−62555号公報等に提案
されているが、このように下部よりコンクリートを圧入
することにより空気を巻込む事なく連続して打設する事
が出来、圧入範囲のコンクリートはコンクリート圧送装
置による加圧力と、自重とによって加圧された状態で打
設されるので、コンクリート内部に含まれようとする空
気も上部に押し出されるのでコンクリートの中間に空洞
部が残ることなく密実で強度があり、耐久性のあるコン
クリートが打設され、且つコンクリートが骨材分離のな
い平均した混合状態のまま上昇するので、鉄筋等が障害
となることがなく、比重差によるコンクリート内部の質
変差もなく平均した強度を持ったコンクリート壁等を形
成することができる。
``Operation'' If the method for constructing the post-cast member configured as described above is used, all the problems that occur when concrete is poured from above, as described above, are solved. In other words, the construction method in which concrete is pressed in from the bottom instead of from above is known as the sequential pouring method and was developed in Japanese Patent Application Laid-Open No. 56-93.
This method has been proposed in Japanese Patent Publication No. 974, Japanese Patent Application Laid-Open No. 64-62555, etc., but by press-fitting concrete from the bottom in this way, it is possible to pour concrete continuously without entraining air, and it is possible to cover the press-in range. Concrete is placed under pressure due to the pressure from the concrete pumping device and its own weight, so any air that would otherwise be contained inside the concrete is forced upwards, so no hollow space remains in the middle of the concrete. Dense, strong, and durable concrete is poured, and the concrete rises in an evenly mixed state with no aggregate separation, so there are no obstacles such as reinforcing bars, and the internal structure of the concrete due to differences in specific gravity is eliminated. It is possible to form concrete walls, etc. with average strength without any change in quality.

さらに、コンクリート打設用ホース2は壁等の型枠1の
下部に接続されることとなる結果、不安定な足場上での
該ホース2支持、アゴ発生、スリーブを介してのコンク
リート打設の要が全て無いものとなる。
Furthermore, since the concrete pouring hose 2 is connected to the lower part of the formwork 1 such as a wall, the hose 2 is supported on unstable scaffolding, jaws are generated, and concrete pouring through the sleeve is difficult. All the essential points will be lost.

「実施例」 実施例について図面を参照して説明すると、第1図にお
いて、コンクリート打設用ホース2は型枠1の下部に接
続される。
"Example" An example will be described with reference to the drawings. In FIG. 1, a concrete casting hose 2 is connected to the lower part of a formwork 1.

当該ホース2は上方よりコンクリートを打設する場合と
異なり、打設したコンクリートの圧を受けることとなる
ので、先端に何んらかの対型枠取合用の治具15を介在
させて取り行なわれると共に当該治具15等に圧入コン
クリートの逆流を阻止する逆留め弁機構を確保するとし
なければならない。
Unlike when concrete is poured from above, the hose 2 will be subjected to the pressure of the poured concrete, so a jig 15 for connecting to the formwork should be interposed at the tip of the hose 2. At the same time, it is necessary to ensure that the jig 15 etc. has a non-return valve mechanism to prevent the backflow of the press-fitted concrete.

例えば、前記公報に提案のものにあっては、開閉弁を備
えた圧入口金物を型枠下部に穿孔の接続孔外側に取り付
け、これにコンクリートホース2の先端を接続している
For example, in the method proposed in the above-mentioned publication, an injection port metal fitting equipped with an on-off valve is attached to the outside of a connecting hole bored in the lower part of the formwork, and the tip of the concrete hose 2 is connected to this.

型枠1の上端については、梁8で閉塞されることは、下
部よりの打設にあっても障害となることは変わりがなく
、第4図a −dに列挙の処置は同様に採られる。
The fact that the upper end of the formwork 1 is blocked by the beam 8 remains an obstacle even when pouring from the lower part, and the measures listed in Figures 4a-d are taken in the same way. .

しかして、後打ち部材はコンクリートの骨材分離、ジャ
ンカ、気泡の発生等の不都合を伴うことなくしてコンク
リートの打設がなされる。また、コンクリート打設に際
しては、足場13は不要であり、アゴの発生も無く、ス
リーブの煩わしさも存在しない。
As a result, concrete can be placed in the post-cast member without causing problems such as separation of concrete aggregates, formation of junks, and generation of air bubbles. Further, when pouring concrete, the scaffolding 13 is not required, there are no jaws, and there is no troublesome sleeve.

「発明の効果」 本発明は、以上説明したように構成されているので、以
下に記載されるような効果を奏する。
"Effects of the Invention" Since the present invention is configured as described above, it produces the effects described below.

(1)型枠は従来通りでよい(アゴ型枠が無い)。(1) The formwork can be the same as before (no jaw formwork).

(2)コンクリートの打込みに伴う足場は不要となり、
安全である。
(2) Scaffolding is no longer required when pouring concrete;
It's safe.

(3)型枠上端に確保せねばならない開口部はコンクリ
ート打設用ホース挿入用ではなく、空気抜きのための小
開口であるため、コンクリートのこぼれが少なく、しい
ては、仕上げ折りも簡易な突起しか残らない。
(3) The opening that must be secured at the top of the formwork is not for inserting a hose for concrete placement, but is a small opening for venting air, so there is less spillage of concrete, and the finish folding can be done easily using the projections. Only that remains.

(4)アゴが生じることがなく、アゴ研りの必要がない
ので、面倒な補修が存在しなくなる。
(4) There are no jaws and there is no need to sharpen the jaws, so there is no need for troublesome repairs.

(5)打設コンクリートを沈下のない (体積変化のな
い)ものにすると、打継部のグラウトも不要となり、省
力化になる。
(5) By making the poured concrete non-settling (no volume change), there is no need for grouting at the joints, resulting in labor savings.

(6)コンクリートの材料分離、多大な空気の差込みが
極めて少なくなる。
(6) Separation of concrete materials and the introduction of a large amount of air are extremely reduced.

【図面の簡単な説明】 第1図は本発明方法の説明図、第2.3図は従来の方法
の説明図、第4図a % dは型枠における空気抜き手
段の各側の説明図、第5図はアゴの説明図、第6図a、
bはアゴ研り作業の説明図である。 1・・・型枠、  2・・・コンクリート打設用ホース
、3・・・アゴ出し、  4・・・コンクリート、  
5・・・上階床スラブ、  6・・・スリーブ、  7
・9.1階床スラブ、8・・・梁、  9・・・スリー
ブ、 1o・・・スリット、 11・・・スリット、 
12・・・減圧管、 13・・・足場、コンクリート、
 15・・・治具、 16・・・透孔。 14・・・ ブラシ7ソ 2−−−コン7リートj1叙唱−丁一ス5−−−上?7
床スラづ 8−’J!   9 12−璃1c+   13 16−、l)L ドー型棹 4−−−コン7+1−ド アー1 ?1殊スラづ 11−m−スリット 15−−−シ舎コ( 3−−−アコ′tし 6−−−スリーづ′ スリー7゛   1o−一一スリット
[Brief Description of the Drawings] Fig. 1 is an explanatory diagram of the method of the present invention, Figs. 2 and 3 are explanatory diagrams of the conventional method, Fig. 4 a % d are explanatory diagrams of each side of the air venting means in the formwork, Figure 5 is an explanatory diagram of the jaw, Figure 6a,
b is an explanatory diagram of jaw polishing work. 1...Formwork, 2...Hose for concrete placement, 3...Jaw extension, 4...Concrete,
5...Upper floor slab, 6...Sleeve, 7
・9.1st floor slab, 8...beam, 9...sleeve, 1o...slit, 11...slit,
12... pressure reducing pipe, 13... scaffolding, concrete,
15...Jig, 16...Through hole. 14... Brush 7 So 2 --- Con 7 Lit j 1 Choral - Cho 1 Su 5 --- Above? 7
Tokosurazu 8-'J! 9 12-Li 1c+ 13 16-, l) L Do type rod 4---Con 7+1-Door 1? 1 special slot 11-m-slit 15--shishako (3---Ako'tshi6---three-zu' three 7゛ 1o-11 slit

Claims (1)

【特許請求の範囲】[Claims] (1)後打ち部材のコンクリート打設を型枠下部よりコ
ンクリートを圧入してするとしたことを特徴とする逆打
ち工法における後打ち部材の構築方法。
(1) A method for constructing a post-cast member in a reverse casting method, characterized in that concrete is poured into the post-cast member from the bottom of the formwork.
JP16210090A 1990-06-20 1990-06-20 Method for constructing subsequent placing member in construction method of reverse placing Pending JPH0452375A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16210090A JPH0452375A (en) 1990-06-20 1990-06-20 Method for constructing subsequent placing member in construction method of reverse placing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16210090A JPH0452375A (en) 1990-06-20 1990-06-20 Method for constructing subsequent placing member in construction method of reverse placing

Publications (1)

Publication Number Publication Date
JPH0452375A true JPH0452375A (en) 1992-02-20

Family

ID=15748059

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16210090A Pending JPH0452375A (en) 1990-06-20 1990-06-20 Method for constructing subsequent placing member in construction method of reverse placing

Country Status (1)

Country Link
JP (1) JPH0452375A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06272380A (en) * 1993-03-18 1994-09-27 Osaka Gas Co Ltd Concrete placement method and placement chute in inverted lining method
KR101230986B1 (en) * 2010-06-16 2013-02-15 주식회사 한빛구조엔지니어링 Constructing method for underground external wall using form with concrete placing inlet and vibrator inlet for preventing concrete counterflow
JP2016204835A (en) * 2015-04-15 2016-12-08 株式会社竹中工務店 Thicker concrete placing method for exterior wall

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06272380A (en) * 1993-03-18 1994-09-27 Osaka Gas Co Ltd Concrete placement method and placement chute in inverted lining method
KR101230986B1 (en) * 2010-06-16 2013-02-15 주식회사 한빛구조엔지니어링 Constructing method for underground external wall using form with concrete placing inlet and vibrator inlet for preventing concrete counterflow
JP2016204835A (en) * 2015-04-15 2016-12-08 株式会社竹中工務店 Thicker concrete placing method for exterior wall

Similar Documents

Publication Publication Date Title
CA1117280A (en) Method of forming and pouring manhole bases
JPH0452375A (en) Method for constructing subsequent placing member in construction method of reverse placing
CN105064500A (en) Balcony beam slab inner side filling wall body and main body structure integral casting construction method
JP4611108B2 (en) Integrated construction method of pile and column
JPH05118036A (en) Waling material
CN211173101U (en) Hanging-free hole type embedded sleeve device
JP4636298B2 (en) Underwater concrete placement equipment
JPH0820945A (en) Foot protection at front end of foundation pile and device therefor
CN212153437U (en) Steel bar connection structure for large-volume concrete bearing platform post-cast strip construction
JPH07324376A (en) Method for constructing reinforced concrete structure
CN215211038U (en) Plain type concrete dado pours auxiliary device
CN218405887U (en) Partition wall connection structure for steel construction building
JP5608060B2 (en) Housing construction method and formwork for following housing
CN209975867U (en) Prefabricated constructional column structure
JPS62244965A (en) Concrete bucket apparatus
JPH0688342A (en) Constructing method of post
JP3021610U (en) Wire mesh for floor filling work for pipes
JPH04119053U (en) Steel pipe column filling concrete placement equipment
JPS58156661A (en) Earth-floor concrete casting method
JPS6062328A (en) Treatment of head of cast-in-place pile
JPH03262875A (en) Method for casting concrete in steel-pipe column and opening therefor
JPS6335767B2 (en)
JP4524755B2 (en) Side wall construction method for underground tank
JPH0260809B2 (en)
JPS60192019A (en) Joint structure for underground continuous wall