JP4524755B2 - Side wall construction method for underground tank - Google Patents

Side wall construction method for underground tank Download PDF

Info

Publication number
JP4524755B2
JP4524755B2 JP2005253199A JP2005253199A JP4524755B2 JP 4524755 B2 JP4524755 B2 JP 4524755B2 JP 2005253199 A JP2005253199 A JP 2005253199A JP 2005253199 A JP2005253199 A JP 2005253199A JP 4524755 B2 JP4524755 B2 JP 4524755B2
Authority
JP
Japan
Prior art keywords
placement
concrete
area
placing
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2005253199A
Other languages
Japanese (ja)
Other versions
JP2007063894A (en
Inventor
三雄 永島
淳 松井
雅徳 土屋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2005253199A priority Critical patent/JP4524755B2/en
Publication of JP2007063894A publication Critical patent/JP2007063894A/en
Application granted granted Critical
Publication of JP4524755B2 publication Critical patent/JP4524755B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、たとえばLNG地下式貯蔵タンクのような大規模な鉄筋コンクリート造の地下タンクの構築に際して、その側壁を効率的に施工するための方法に関する。   The present invention relates to a method for efficiently constructing a side wall of a large-scale reinforced concrete underground tank such as an LNG underground storage tank.

この種の地下タンクの構築に際しては一度の多量のコンクリートを広範囲にわたって打設する必要があることから、従来一般には地上部に配置したポンプ車から打設箇所までコンクリートを圧送するための打設管路を予め設置しておき、打設管路に接続した鉛直ホースを取り回しつつ順次引き上げていってコンクリートを層状に打設していくことが一般的である。そのような施工法の一例として、たとえば特許文献1には、水平に設置した打設管路に予め多数本の鉛直ホースをそれぞれ自動開閉バルブを介して接続しておき、それら自動開閉バルブを適切なタイミングで開閉するように制御しながらコンクリートを打設していくという自動打設制御方法が提案されている。
特開平7−189487号公報
When constructing this type of underground tank, it is necessary to cast a large amount of concrete once over a wide area. Conventionally, a placement pipe for pumping concrete from a pump car placed on the ground to a placement site is generally used. It is common to place the road in advance, and pull up the concrete in layers by sequentially pulling up the vertical hose connected to the placement pipe. As an example of such a construction method, for example, in Patent Document 1, a large number of vertical hoses are connected in advance to a horizontally placed installation line through automatic open / close valves, and these automatic open / close valves are appropriately used. An automatic placement control method has been proposed in which concrete is placed while being controlled to open and close at an appropriate timing.
JP-A-7-189487

ところで、大規模な地下タンクの側壁を施工するに際して上記のような手法で地上部から地下に向かってコンクリートを打設する場合、一般には1ロットの打設高さを可及的に大きくした方が、打設工事のみならず配筋工事や型枠工事、さらには打ち継ぎ部の処理についても効率的であると考えられるが、実際上は打設高さをあまり大きく設定すると鉛直ホース内における材料分離や閉塞を生じる懸念があって施工品質や施工効率がかえって低下してしまう場合があることから、従来においては1ロット当たりのコンクリート打設高さをあまり大きく設定できず、通常では8.5mから最大でも10m程度とすることが限界とされている。   By the way, when constructing the side wall of a large underground tank, when placing concrete from the ground to the basement using the method described above, in general, the placement height of one lot should be as large as possible. However, it is considered efficient not only for placement work but also for bar arrangement work, formwork work, and processing of joints, but in practice, if the placement height is set too high, Since there is a possibility that material separation or blockage may occur and the construction quality and construction efficiency may be lowered, the concrete placement height per lot cannot be set so large conventionally. The limit is about 5 m to 10 m at the maximum.

図7にそのような従来一般の工法の一具体例を示す。これは、山留めおよび止水壁として先行施工した地中連続壁1の内側を掘削して底版2を施工した後、地中連続壁1の内面側にたとえば全高が42mにも及ぶような大規模な側壁3を施工する場合の適用例であって、図示しているようにまず側壁3の下部に対して打設高さを3m程度に設定した2ロット(♯1ロットおよび♯2ロット)の打設を行った後、打設高さを限界に近い8〜9m程度に設定して4ロット(♯3ロット〜♯6ロット)の打設を順次行い、最後に頂部(♯7ロット)を打設するようにしている。つまり、この場合は、側壁3の底部や頂部の特殊部位に対しては独立にコンクリート打設を行うことは止むを得ないとしても、単なる中間部の施工についても打設高さの限界から4ロットものコンクリート打設を必要とするものであり、したがって打ち継ぎ部も全体で6カ所にも及ぶものであった。   FIG. 7 shows a specific example of such a conventional general construction method. This is a large scale in which, for example, the total height of the underground continuous wall 1 reaches 42 m after excavating the inside of the underground continuous wall 1 previously constructed as a mountain retaining and water blocking wall and constructing the bottom plate 2. As shown in the figure, first, two lots (# 1 lot and # 2 lot) in which the placement height is set to about 3 m with respect to the lower portion of the side wall 3 are shown. After the placement, the placement height is set to about 8-9m, which is close to the limit, and 4 lots (# 3 lot to # 6 lot) are placed sequentially, and finally the top (# 7 lot) is placed. I try to cast it. In other words, in this case, it is unavoidable to perform concrete placement independently on the bottom and top special portions of the side wall 3, but the construction of the mere intermediate portion is also limited to 4 from the limit of the placement height. It required lots of concrete to be cast, and therefore the joints were in total 6 locations.

このように、従来においては大規模な側壁3の施工に際してのコンクリート打設のロット数が多くならざるを得ないことから、打設作業のみならず配筋作業や型枠作業、打ち継ぎ部の処理も含めて側壁施工に関わる全ての作業に多大の手間と費用を要するものであり、そのことがこの種の地下タンクの構築に際しての施工性改善を阻む一因ともなっている。   Thus, since the number of concrete placement lots in the conventional construction of the large-scale side wall 3 has to be increased, not only the placement work but also the placement work, the formwork work, and the joint part. All the work related to the side wall construction including the processing requires a lot of labor and cost, which is one of the factors hindering the improvement of workability when constructing this kind of underground tank.

上記事情に鑑み、本発明は地下タンクの構築における側壁コンクリートの打設に際して1ロットの打設高さを支障なく大きく設定でき、それにより施工性を改善し得る有効適切な工法を提供することを目的としている。   In view of the above circumstances, the present invention provides an effective and appropriate construction method that can set the placement height of one lot large without hindrance when placing side wall concrete in the construction of an underground tank, thereby improving workability. It is aimed.

本発明は、鉄筋コンクリート造の地下タンクの構築に当たって地上部からコンクリートを打設して側壁を形成するための地下タンクの側壁施工方法であって、1ロットのコンクリート打設領域に対する配筋作業と型枠作業を行う際には、その打設領域全体を下段打設領域と上段打設領域とに区分して、それら下段打設領域と上段打設領域の境界部で上段打設領域の最底部に対しては配筋の一部を後施工することとしてそこにコンクリート打設作業のための作業スペースを確保しておき、当該打設領域全体に対してコンクリートを打設するに際しては、下段打設領域に対してコンクリートを打設するための下段打設管路を地表部から前記作業スペースに配置した下段打設管路としての水平管路を通して下段打設領域まで設置するとともに、上段打設領域に対してコンクリートを打設するための上段打設管路を地表部から上段打設領域の最上部に配置した上段打設管路としての水平管路を通して上段打設領域まで予め設置しておいて、まず下段打設管路により下段打設領域に対するコンクリート打設を行った後、下段打設管路を撤去するとともに作業スペースに対する配筋の後施工を行い、引き続いて上段打設管路により上段打設領域に対するコンクリート打設を行うことを特徴とするものである。 The present invention is a method for constructing a side wall of an underground tank for forming a side wall by placing concrete from the ground part in constructing an underground tank of reinforced concrete structure. when performing the frame work, the entire droplet formation regions by dividing the lower punch installation zone and the upper punch installation zone, the bottom-most of the upper punch installation zone at their lower punch installation zone and the upper hitting region where the boundary For this, a part of the bar arrangement will be post-installed, and a working space for concrete placement work will be secured there. When placing concrete in the entire placement area, we established a lower punch設管passage for pouring concrete from the surface portion to the lower punch installation zone through the horizontal line of the lower punch設管path disposed in the working space for installation zone, the upper Previously established the upper punch設管passage for pouring the concrete against installation zone from the surface portion to the upper punch installation zone through the horizontal line of the upper punch設管path disposed on top of the upper punch installation zone First, after placing concrete in the lower casting area using the lower casting pipe, the lower casting pipe is removed and post-installation of the work space is performed, followed by the upper casting pipe. The concrete is placed in the upper placement area by a road.

作業スペースに対して後施工により配筋する鉄筋としては、端部に定着頭部もしくはフック部を一体に形成した定着筋を用い、その定着筋を剪断補強筋として作業スペースに配筋すれば良い。   As a reinforcing bar to be laid after work on the work space, it is only necessary to use a fixing bar that is integrally formed with a fixing head or a hook part at the end, and the fixing bar is arranged as a shear reinforcement bar in the work space. .

施工するべき側壁内に埋め込まれる鋼製の埋め込み足場を採用し、該埋め込み足場を使用して配筋作業および型枠作業を行うとともに、下段打設管路および上段打設管路を埋め込み足場に支持して設置すると良い。   Adopting steel embedded scaffolds embedded in the side walls to be constructed, and using the embedded scaffolds to perform the reinforcement work and formwork, and the lower and upper placement pipes as the embedded scaffolds It should be installed in support.

本発明によれば、1ロットの打設領域を上下に区分してそれらの間に作業スペースを確保して、双方の打設領域に対してコンクリートを独立に打設するための下段打設管路および上段打設管路を予め設置しておくとともに、それら下段打設管路および上段打設管路の途中にそれぞれ水平管路を設けておくので、打設作業の途中で一時的に作業を中断して作業スペースからの打設管路の撤去とそこへの配筋作業を行う必要はあるものの、実質的に打設領域全体に対するコンクリート打設を連続的にほぼ一気に行うことが可能であり、それにより1ロット当たりの打設高さを従来よりも十分に大きく設定することが可能であって格段に効率的な施工が可能であり、工期短縮と工費削減を実現することができる。 According to the present invention, a lower placement pipe for dividing a placement area of one lot into upper and lower portions, securing a working space between them, and placing concrete independently for both placement areas. Road and upper placement pipes are installed in advance , and horizontal pipes are provided in the middle of the lower and upper placement pipes, so work temporarily during the placement work. Although it is necessary to remove the placement pipe line from the work space and perform the reinforcement work there, it is possible to perform concrete placement almost continuously over the entire placement area at a stretch. In this way, the placement height per lot can be set sufficiently larger than that of the prior art, so that the construction can be performed much more efficiently, and the construction period can be shortened and the construction cost can be reduced.

特に、作業スペースに後施工する配筋として定着頭部もしくはフック部を有する定着筋を用いることにより、作業スペースにおける配筋作業を迅速に行うことができる。また、側壁内にそのまま埋め込まれる鋼製の埋め込み足場を用いることにより、配筋および型枠作業をより効率的に行い得るし、打設配管を埋め込み足場によって安定に支持して容易に設置することができる。   In particular, by using a fixing bar having a fixing head or a hook portion as a bar arrangement to be post-installed in the work space, the bar arrangement work in the work space can be quickly performed. In addition, by using steel embedded scaffolds that are embedded as they are in the side walls, reinforcement and formwork work can be performed more efficiently, and the installation piping can be installed with stable support by the embedded scaffolds. Can do.

図1〜図6は本発明の施工方法の実施形態を示すものである。本実施形態は図7に示したものと同規模の地下タンクにおける側壁3を施工するに際し、コンクリート打設を全4ロット(♯1ロット〜♯4ロット)で行うようにしたものであり、特に側壁3の底部と頂部を除く中間部に対する打設は2ロット(♯2ロット〜♯3ロット)のみで行うようにしたものである。すなわち、図7に示した従来一般の施工方法による場合には、中間部に対しては1ロット当たりの打設高さを8〜9m程度に制限して4ロットに分けて行う必要があったのに対し、本実施形態では1ロット当たりの打設高さを従来の2倍程度の17m以上に設定し、それにより中間部におけるロット数を従来よりも半減させてわずか2ロットのみで行うものとしている。   1 to 6 show an embodiment of the construction method of the present invention. In the present embodiment, when the side wall 3 in the underground tank of the same scale as that shown in FIG. 7 is constructed, concrete placement is performed in all four lots (# 1 lot to # 4 lot). Placing the intermediate portion excluding the bottom and top of the side wall 3 is performed in only two lots (# 2 lot to # 3 lot). That is, in the case of the conventional general construction method shown in FIG. 7, it was necessary to divide the intermediate portion into four lots by limiting the placement height per lot to about 8 to 9 m. On the other hand, in this embodiment, the placement height per lot is set to 17 m or more, which is about twice that of the conventional one, so that the number of lots in the intermediate portion is halved from the conventional one and only two lots are performed. It is said.

但し、1ロット当たりの打設高さを単にそのように大きくしたのでは、上述したように打設に際しての鉛直ホース内で材料分離や閉塞を生じる懸念があるので、それを回避するべく、本実施形態では以下のような工程を採用している。   However, simply increasing the placement height per lot as described above may cause material separation or blockage in the vertical hose during placement as described above. In the embodiment, the following steps are employed.

すなわち、本実施形態においても基本的には従来と同様にコンクリート打設の各ロットに対応して配筋作業や型枠作業をロット単位で行うものであり、したがってたとえば♯2ロットに対するコンクリート打設に先だって♯2ロット全体に対する配筋作業と型枠作業を実施するのであるが、本実施形態ではその際に♯2ロット全体をさらに下段打設領域(♯2−1)と上段打設領域(♯2−2)とに区分し、その境界部に対する配筋の一部を後施工することとしてそこにコンクリート打設作業のための作業スペース4を一時的に確保するものとしている。同様に、♯3ロット全体に対する配筋作業と型枠作業の際には、♯3ロット全体をさらに下段打設領域(♯3−1)と上段打設領域(♯3−2)とに区分して、その境界部に対する配筋の一部を後施工することとしてそこにコンクリート打設作業のための作業スペースを一時的に確保するものとしている。   That is, in this embodiment as well, basically, in the same manner as in the prior art, the placement work and the formwork work are performed in units of lots corresponding to each lot of concrete placement, and therefore, for example, concrete placement for # 2 lot Prior to this, the arrangement work and the formwork for the entire # 2 lot are performed. In this embodiment, the entire # 2 lot is further divided into a lower placement area (# 2-1) and an upper placement area ( # 2-2), and a part of the bar arrangement for the boundary portion is post-installed, and a work space 4 for concrete placement work is temporarily secured there. Similarly, in the case of bar arrangement work and formwork for the entire # 3 lot, the entire # 3 lot is further divided into a lower placement area (# 3-1) and an upper placement area (# 3-2). Then, as a part of the bar arrangement for the boundary portion is post-constructed, a work space for concrete placement work is temporarily secured there.

本実施形態の施工方法の具体的な作業工程を図2〜図5を参照して説明する。本実施形態は、基本的には図7に示した従来の工法による場合と同様に、先行施工した地中連続壁1の内側を掘削し、底版2を先行施工するとともに、側壁3の最底部を底版2と一体となるように♯1ロットにより施工した後、上記のように側壁3の中間部を♯2ロット〜♯3ロットとして順次施工していくものである。なお、側壁3の施工に際してはタンク内に枠組み足場5を設置し、それを作業足場として内外の配力筋と主筋6とそれらを連結する剪断補強筋7を主体とする配筋を行い、かつ型枠8を支持フレーム9を介して枠組み足場5によって支持するとともに、型枠8を支持するためのセパレータ(図示略)の先端は地中連続壁1に対して固定するようにしている。また、本実施形態では、上記の枠組み足場5に加え、施工するべき側壁3内にそのまま埋め込まれる鋼製の埋め込み足場10(図2では図示略)を設置して、その埋め込み足場10も利用して配筋作業および型枠作業を行うとともに、後述する打設管路11(11A、11B)を埋め込み足場10により支持して設置するようにしている。   The concrete work process of the construction method of this embodiment is demonstrated with reference to FIGS. In the present embodiment, basically, as in the case of the conventional construction method shown in FIG. Is constructed in # 1 lot so as to be integrated with the bottom plate 2, and then the middle portion of the side wall 3 is constructed sequentially as # 2 lot to # 3 lot as described above. In the construction of the side wall 3, a frame scaffold 5 is installed in the tank, and the reinforcement is mainly composed of the inner and outer strength bars, the main bars 6, and the shear reinforcement bars 7 connecting them, and the working scaffold. The mold 8 is supported by the framework scaffold 5 via the support frame 9 and the tip of a separator (not shown) for supporting the mold 8 is fixed to the underground continuous wall 1. In this embodiment, in addition to the framework scaffold 5 described above, a steel embedded scaffold 10 (not shown in FIG. 2) that is embedded as it is in the side wall 3 to be constructed is installed, and the embedded scaffold 10 is also used. In addition, the placement work and the formwork work are performed, and the placement pipeline 11 (11A, 11B), which will be described later, is supported and installed by the embedded scaffolding 10.

図2は♯2ロットに対してコンクリートを打設する直前の状態、すなわち♯2ロット全体に対する配筋作業および型枠作業が終了し、コンクリートを打設するための打設管路11(11A、11B)を設置した状態を示している。この状態では、上述したように♯2ロット全体が下段打設領域(♯2−1)と上段打設領域(♯2−2)とに区分されていて、その境界部である上段打設領域(♯2−2)の最底部においては2段の剪断補強筋7が配筋されずに残されることにより、この時点ではその位置に作業員が通行できる程度の作業スペース4が確保されている。   FIG. 2 shows a state immediately before placing concrete for # 2 lot, that is, the placement work and the formwork for the entire # 2 lot are finished, and placement pipe 11 (11A, 11A, 11B) is shown. In this state, as described above, the entire # 2 lot is divided into the lower placement area (# 2-1) and the upper placement area (# 2-2), and the upper placement area which is the boundary portion thereof. At the bottom of (# 2-2), the two-stage shear reinforcement bars 7 are left without being arranged, and at this point, a work space 4 is secured to allow workers to pass therethrough. .

また、♯2ロット全体に対する打設管路11としては、下段打設領域(♯2−1)に対する下段打設管路11Aと、上段打設領域(♯2−2)に対する上段打設管路11Bとが予め独立に設置されている。各打設管路11(11A、11B)は、いずれも、地表部に配置されるポンプ車12に接続される主管路13と、その主管路13に接続されて打設領域内に水平に配置される水平管路14と、その水平管路14に接続されて取り回される鉛直ホース15からなるもので、各打設管路11(11A、11B)はいずれも上記の埋め込み足場10に支持されて設置されている。そして、上段打設管路11Bにおける水平管路14は通常のように♯2ロット全体の最上部(つまり♯2−2ロットの最上部)に配置されているが、下段打設管路11Aにおける水平管路14は上記の境界部(♯2−2ロットの最底部)に確保された上記の作業スペース4内に配置されており、これによりその作業スペース4を利用して下段打設領域(♯2−1)に対するコンクリート打設作業を支障なく行うことができるようになっている。なお、各打設管路11によるコンクリート打設に際しては特許文献1に示されているような打設制御を行っても良く、そのためには各打設管路11に自動開閉バルブや制御装置を備えておけば良い。   Further, as the placement line 11 for the entire # 2 lot, the lower placement line 11A for the lower placement area (# 2-1) and the upper placement line for the upper placement area (# 2-2). 11B is installed independently in advance. Each of the placement pipes 11 (11A, 11B) is arranged horizontally in the placement area connected to the main pipe 13 connected to the pump car 12 arranged on the surface and the main pipe 13. The horizontal conduit 14 and the vertical hose 15 connected to the horizontal conduit 14 are routed, and each of the placement conduits 11 (11A, 11B) is supported by the embedded scaffold 10 described above. Has been installed. The horizontal pipeline 14 in the upper placement pipeline 11B is arranged at the top of the entire # 2 lot (that is, the top of the # 2-2 lot) as usual, but in the lower placement pipeline 11A. The horizontal pipe 14 is disposed in the work space 4 secured at the boundary portion (the bottom of the # 2-2 lot), so that the lower placement area ( The concrete placing work for # 2-1) can be performed without any trouble. In addition, when placing concrete in each placement pipeline 11, placement control as shown in Patent Document 1 may be performed. For that purpose, an automatic opening / closing valve and a control device are provided in each placement pipeline 11. You should prepare.

本実施形態の工法により♯2ロット全体に対してコンクリートを打設するには、図2に示しているように作業スペース4の部分を残して♯2ロット全体に対する配筋を行い、かつ♯2ロット全体に対する型枠を組み立て、下段打設管路11Aと上段打設管路11Bの双方を予め設置した後、まず下段打設管路11Aを通して下段打設領域(♯2−1)に対するコンクリート打設を行い、引き続いて上段打設管路11Bを通して上段打設領域(♯2−2)に対してコンクリート打設を行う。   In order to place concrete on the entire # 2 lot by the method of the present embodiment, as shown in FIG. 2, bar arrangement is performed on the entire # 2 lot leaving the work space 4 portion, and # 2 After assembling the mold for the entire lot and installing both the lower casting line 11A and the upper casting line 11B in advance, the concrete is first placed in the lower casting area (# 2-1) through the lower casting line 11A. Then, concrete placement is performed on the upper placement area (# 2-2) through the upper placement pipeline 11B.

すなわち、まず下段打設領域(♯2−1)に対して、ポンプ車12から下段打設管路11Aを通してコンクリートを圧送し、作業員が鉛直ホース15を取り回しつつ順次引き上げていってコンクリートを層状に打設充填していく。   That is, first, concrete is pumped from the pump car 12 through the lower casting pipe 11A to the lower casting area (# 2-1), and the worker sequentially pulls up the vertical hose 15 and pulls the concrete in layers. I will continue to fill.

そのようにして、図3に示すように下段打設領域(♯2−1)に対するコンクリート打設が完了したら、図4に示すように下段打設管路11Aの全てを速やかに撤去するとともに、図5に示すように作業スペース4に対して配筋の後施工を速やかに行う。すなわち、作業スペース4を確保するために配筋せずに残しておいた2段の剪断補強筋7を配筋する。この場合、剪断補強筋7としては通常の鉄筋を用いることでも良いが、端部に定着頭部16aを一体に形成した定着筋16を2本1組として使用して、それを内外の主筋6の間に配筋すればその配筋作業を容易にかつ迅速に行うことができる。   Thus, when the concrete placement for the lower placement area (# 2-1) as shown in FIG. 3 is completed, all of the lower placement pipeline 11A is quickly removed as shown in FIG. As shown in FIG. 5, the post-arrangement of the work space 4 is quickly performed. In other words, in order to secure the work space 4, the two-stage shear reinforcement bars 7 left without being arranged are arranged. In this case, a normal reinforcing bar may be used as the shear reinforcing bar 7, but two fixing bars 16 each having a fixing head 16a integrally formed at the end portion are used as a set, and the main reinforcing bars 6 are used as inner and outer main bars 6. If the bars are arranged between the two, the arrangement work can be performed easily and quickly.

以上のようにして♯2ロット全体のうち下段打設領域(♯2−1)に対するコンクリート打設と、下段打設管路11Aの撤去、作業スペース4に対する配筋作業を行ったら、引き続き今度は上段打設管路11Bを通して上段打設領域(♯2−2)に対して通常のようにコンクリート打設を行う。♯2ロット全体に対するコンクリート打設が完了したら♯3ロットに対する作業に移行して同様の手順を繰り返す。   If the concrete placement for the lower placement area (# 2-1) of the entire # 2 lot, the removal of the lower placement pipeline 11A, and the bar placement work for the work space 4 are performed as described above, this time, Concrete pouring is performed as usual in the upper placing area (# 2-2) through the upper placing conduit 11B. When the concrete placement for the entire # 2 lot is completed, the operation is shifted to the # 3 lot and the same procedure is repeated.

なお、作業スペース4に対する配筋は、上記のような定着筋16を2本1組として用いることに代えて、たとえば図6(a)に示すように端部にフック部17aを形成した定着筋17を2本1組として用いたり、あるいは同図(b)に示すように定着頭部16aを形成した定着筋16と、フック部17aを形成した定着筋17とを組み合わせて用いることでも良い。   In the arrangement of the working space 4, instead of using the above two fixing bars 16 as one set, for example, as shown in FIG. 6A, a fixing bar having a hook portion 17 a formed at the end. 17 may be used as one set, or as shown in FIG. 5B, the fixing muscle 16 having the fixing head 16a and the fixing muscle 17 having the hook portion 17a may be used in combination.

本実施形態の工法によれば、1ロットのコンクリート打設工程の途中で一時的に打設作業を中断して下段打設管路11Aの撤去と一部の配筋の後施工を行う必要はあるものの、実質的に1ロットの打設領域全体に対するコンクリート打設を連続的にほぼ一気に行うことが可能であり、それにより1ロット当たりの打設高さを従来の倍程度まで大きく設定し得て格段に効率的な施工が可能となり、工期短縮と工費削減を実現することができる。勿論、打設高さを倍程度に設定するとはいっても、下段打設管路11Aには上段打設領域(♯2−2)の最底部の作業スペース4内に水平管路14を配置するとともに、上段打設管路11Bには上段打設領域(♯2−2)の最上部に水平管路14を配置して、それら水平管路14を介してコンクリート打設を行うことにより、下段打設領域(♯2−1)と上段打設領域(♯2−2)のそれぞれにおいては打設高さを従来と同程度の範囲で行うことが可能であり、したがって鉛直ホース15での材料分離や閉塞が生じることもなく、単に打設高さを大きくする場合のような施工効率や施工品質の低下が懸念されることもない。 According to the construction method of the present embodiment, it is necessary to temporarily suspend the placing operation in the course of one lot of concrete placing process, to remove the lower placing pipe line 11A, and to carry out the post-construction of some bars. Although it is possible, it is possible to perform concrete placement substantially continuously over the entire placement area of one lot at a stretch, so that the placement height per lot can be set as large as double the conventional placement. Therefore, the construction is much more efficient, and the construction period can be shortened and the construction cost can be reduced. Of course, although the casting height is set to about double , the horizontal pipeline 14 is arranged in the lowermost working space 4 of the upper casting area (# 2-2) in the lower casting pipe 11A. At the same time, a horizontal pipe 14 is arranged at the uppermost part of the upper casting area (# 2-2) in the upper casting pipe 11B, and concrete casting is performed through these horizontal pipes 14, thereby lowering the lower casting pipe 11B. In each of the placement area (# 2-1) and the upper placement area (# 2-2), it is possible to perform the placement height within the same range as in the prior art. There is no separation or blockage, and there is no concern about deterioration in construction efficiency and construction quality as in the case of simply increasing the placement height.

以上で本発明の実施形態を説明したが、上記実施形態はあくまで好適な一例であって本発明は上記実施形態に限定されるものでは勿論なく、たとえばコンクリート打設のためのロット数の設定やその工程の詳細、側壁における配筋や型枠の具体的な構成、地中連続壁の要否、枠組み足場や埋め込み足場の有無、その他に関しては、本発明の要旨を逸脱しない範囲内において施工するべき地下タンクの規模や形態、用途に応じて適宜の設計的変更が可能である。   Although the embodiment of the present invention has been described above, the above embodiment is merely a preferred example, and the present invention is not limited to the above embodiment. For example, the setting of the number of lots for placing concrete Concerning the details of the process, the concrete arrangement of reinforcement and formwork in the side walls, the necessity of underground continuous walls, the presence or absence of framework scaffolds and embedded scaffolds, etc., construction is performed within the scope of the present invention. Appropriate design changes can be made according to the scale, form and use of the underground tank.

本発明の実施形態を示すもので、タンク側壁に対するコンクリート打設工程のロット設定を示す図である。The embodiment of the present invention is shown, and is a diagram showing lot setting of a concrete placing process on a tank side wall. 同、♯2ロットに対するコンクリート打設直前の状況を示す図である。It is a figure which shows the condition immediately before concrete placement with respect to # 2 lot. 同、♯2ロットにおける下段打設領域に対するコンクリート打設が完了した状態を示す図である。It is a figure which shows the state which concrete placement with respect to the lower stage placement area in # 2 lot was completed. 同、下段打設配管を撤去した状態を示す図である。It is a figure which shows the state which removed the lower stage installation piping. 同、作業スペースに配筋を後施工した状態の一例を示す図である。It is a figure which shows an example of the state which carried out the post-installation in the working space. 同、作業スペースに配筋を後施工した状態の他の例を示す図である。It is a figure which shows the other example of the state which carried out the post-installation in the work space. 従来一般のタンク側壁に対するコンクリート打設工程のロット設定を示す図である。It is a figure which shows the lot setting of the concrete placement process with respect to the conventional general tank side wall.

符号の説明Explanation of symbols

1 地中連続壁
2 底版
3 側壁
4 作業スペース
5 枠組み足場
6 主筋
7 剪断補強筋
8 型枠
9 支持フレーム
10 埋め込み足場
11 打設管路
11A 下段打設管路
11B 上段打設管路
12 ポンプ車
13 主管路
14 水平管路
15 鉛直ホース
16 定着筋
16a 定着頭部
17 定着筋
17a フック部
DESCRIPTION OF SYMBOLS 1 Underground continuous wall 2 Bottom plate 3 Side wall 4 Work space 5 Framework scaffold 6 Main reinforcement 7 Shear reinforcement 8 Formwork 9 Support frame 10 Embedded scaffold 11 Placing pipeline 11A Lower placement pipeline 11B Upper placement pipeline 12 Pump car 13 Main Line 14 Horizontal Line 15 Vertical Hose 16 Anchor Muscle 16a Anchor Head 17 Anchor Muscle 17a Hook

Claims (3)

鉄筋コンクリート造の地下タンクの構築に当たって地上部からコンクリートを打設して側壁を形成するための地下タンクの側壁施工方法であって、
1ロットのコンクリート打設領域に対する配筋作業と型枠作業を行う際には、その打設領域全体を下段打設領域と上段打設領域とに区分して、それら下段打設領域と上段打設領域の境界部で上段打設領域の最底部に対しては配筋の一部を後施工することとしてそこにコンクリート打設作業のための作業スペースを確保しておき、
当該打設領域全体に対してコンクリートを打設するに際しては、下段打設領域に対してコンクリートを打設するための下段打設管路を地表部から前記作業スペースに配置した下段打設管路としての水平管路を通して下段打設領域まで設置するとともに、上段打設領域に対してコンクリートを打設するための上段打設管路を地表部から上段打設領域の最上部に配置した上段打設管路としての水平管路を通して上段打設領域まで予め設置しておいて、
まず下段打設管路により下段打設領域に対するコンクリート打設を行った後、下段打設管路を撤去するとともに作業スペースに対する配筋の後施工を行い、引き続いて上段打設管路により上段打設領域に対するコンクリート打設を行うことを特徴とする地下タンクの側壁施工方法。
In constructing a reinforced concrete underground tank, a side wall construction method for an underground tank for placing concrete from the ground to form a sidewall,
When performing bar arrangement work and formwork for a single lot of concrete placement area, the entire placement area is divided into a lower placement area and an upper placement area, and the lower placement area and the upper placement area are divided. As the bottom of the upper placement area at the boundary of the installation area, a work space for concrete placement work is secured there as a post-installation of part of the bar arrangement,
When placing concrete in the entire placing area, a lower placing pipe in which a lower placing pipe for placing concrete in the lower placing area is disposed in the work space from the surface portion. Is installed up to the lower placement area through the horizontal pipe as the upper placement pipe where the upper placement pipe for placing concrete in the upper placement area is placed from the surface to the top of the upper placement area. Pre-installed up to the upper placement area through the horizontal pipeline as the installation pipeline ,
First, after placing the concrete in the lower placement area using the lower placement pipe, remove the lower placement pipe and perform post-laying of the work space, and then continue the upper placement using the upper placement pipe. A method for constructing a side wall of an underground tank, wherein the concrete is placed in an installation area.
請求項1記載の地下タンクの側壁施工方法であって、
作業スペースに対して後施工により配筋する鉄筋として、端部に定着頭部もしくはフック部を一体に形成した定着筋を用い、その定着筋を剪断補強筋として作業スペースに配筋することを特徴とする地下タンクの側壁施工方法。
It is the side wall construction method of the underground tank of Claim 1,
As a reinforcing bar to be laid after work on the work space, a fixing bar with a fixed head or hook part formed integrally at the end is used, and the fixing bar is placed in the work space as a shear reinforcement. The underground tank side wall construction method.
請求項1または2記載の地下タンクの側壁施工方法であって、
施工するべき側壁内に埋め込まれる鋼製の埋め込み足場を採用し、該埋め込み足場を使用して配筋作業および型枠作業を行うとともに、下段打設管路および上段打設管路を埋め込み足場に支持して設置することを特徴とする地下タンクの側壁施工方法。
It is the side wall construction method of the underground tank of Claim 1 or 2,
Adopting steel embedded scaffolds embedded in the side walls to be constructed, and using the embedded scaffolds to perform the reinforcement work and formwork, and the lower and upper placement pipes as the embedded scaffolds Side wall construction method for underground tanks, characterized by supporting and installing.
JP2005253199A 2005-09-01 2005-09-01 Side wall construction method for underground tank Expired - Fee Related JP4524755B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005253199A JP4524755B2 (en) 2005-09-01 2005-09-01 Side wall construction method for underground tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005253199A JP4524755B2 (en) 2005-09-01 2005-09-01 Side wall construction method for underground tank

Publications (2)

Publication Number Publication Date
JP2007063894A JP2007063894A (en) 2007-03-15
JP4524755B2 true JP4524755B2 (en) 2010-08-18

Family

ID=37926399

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005253199A Expired - Fee Related JP4524755B2 (en) 2005-09-01 2005-09-01 Side wall construction method for underground tank

Country Status (1)

Country Link
JP (1) JP4524755B2 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH068609U (en) * 1992-07-07 1994-02-04 大成建設株式会社 Concrete piping structure

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0660527B2 (en) * 1985-07-30 1994-08-10 大成建設株式会社 Pumped material supply piping device
JP3250062B2 (en) * 1993-12-27 2002-01-28 清水建設株式会社 Automatic concrete placement control method
JP3153468B2 (en) * 1996-05-16 2001-04-09 鹿島建設株式会社 Construction method of concrete structure

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH068609U (en) * 1992-07-07 1994-02-04 大成建設株式会社 Concrete piping structure

Also Published As

Publication number Publication date
JP2007063894A (en) 2007-03-15

Similar Documents

Publication Publication Date Title
KR100951097B1 (en) Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
JP5012355B2 (en) Underwater structure reinforcement method, underwater structure
KR20060084203A (en) Method for constructing 2-arch tunnel using steel pile support
KR20090094971A (en) Under ground top-down method
CN104452812A (en) Construction method of basement outer wall
CN206625428U (en) Floor closed system is poured after a kind of pipe well
JP4524756B2 (en) Side wall construction method for underground tank
KR101859440B1 (en) Construction method of contemporary facility of complex steel using connecting means between cofferdam walls
JP2007297826A (en) Method for reinforcing bridge pier with steel plate
JP5303381B2 (en) Demolition method for existing buildings
KR20200092593A (en) Concrete slab of bridge with precast cantilever slab and concrete slab of bridge construction method therefor
JP2007162266A (en) Two-step earth retaining wall and its construction method
KR20100113957A (en) Joint structure and method for constructing slab of underground structures using the same
JP2009228301A (en) Elongation method for bridge pier
KR101267565B1 (en) Construction method of under-ground core part structure in top-down construction procedure
JP4524755B2 (en) Side wall construction method for underground tank
KR20060096706A (en) Deck suspension top-down method of sub-structure
JP6368584B2 (en) Foundation construction method
JP2006299660A (en) Temporary receiving construction method and temporary receiving structure
CN102733602A (en) Hanging-up construction method of air shaft
KR20110050898A (en) Vertical joint frame for improving monolithic concrete
KR20100118482A (en) To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method
KR200418842Y1 (en) Fixing structure between jointing portion of deep-decks
KR200390421Y1 (en) Top-down substructure by deck suspension
KR20130004798A (en) Earth pressure supporting method of walls trench applying construction of none- excavation underground structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080109

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100112

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100119

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100305

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20100423

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20100520

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130611

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4524755

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140611

Year of fee payment: 4

LAPS Cancellation because of no payment of annual fees