JPH04289400A - Segment carrier - Google Patents

Segment carrier

Info

Publication number
JPH04289400A
JPH04289400A JP3078316A JP7831691A JPH04289400A JP H04289400 A JPH04289400 A JP H04289400A JP 3078316 A JP3078316 A JP 3078316A JP 7831691 A JP7831691 A JP 7831691A JP H04289400 A JPH04289400 A JP H04289400A
Authority
JP
Japan
Prior art keywords
segment
segments
chain
frame
gripping device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3078316A
Other languages
Japanese (ja)
Inventor
Junichi Shibano
柴野 潤一
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
NKK Corp
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NKK Corp, Nippon Kokan Ltd filed Critical NKK Corp
Priority to JP3078316A priority Critical patent/JPH04289400A/en
Publication of JPH04289400A publication Critical patent/JPH04289400A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

PURPOSE:To enhance the efficiency of carrying work by providing a carrying means of segments to a skeleton extended from the rear of a shield excavator, and providing a locking projection provided to the carrying means so that it is positioned to a regular position against an automatic holder. CONSTITUTION:When a segment S1 is suspended from a trolley truck 31 with a hoist 27 at the rear end of a skeleton 3 and is lowered along guide frames 10 and 10 to place it on a roller 9, a locking section 8 of a chain 7 is penetrated. After that, a hanger bolt 29 is removed from the segment S1, and when the chain 7 is driven, the segment S1 is pulled forward by the locking projection 8 to carry it forward, and the locking projection 8 is brought into contact with a stop 11 to halt the chain 7. An erector 22 is stopped so that a hanger screw 24 of an automatic holder 23 reaches right above a grout hole SH of the segment S1, the hanger screw 24 is screwed into a screw-hole of the grout hole SH to lift up, and the erector 28 is rotated to place the segment S1 to a specific assembly position.

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【産業上の利用分野】本発明は、シールド掘進機のため
のセグメント搬送装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a segment conveying device for a shield tunneling machine.

【0002】0002

【従来の技術】シールド掘進機のための従来のセグメン
ト搬送装置の中で最も一般的なものを図5ないし図7に
示すごとくであった。
2. Description of the Related Art Among the conventional segment conveying devices for shield tunneling machines, the most common one is shown in FIGS. 5 to 7.

【0003】図5において、21はトンネル掘削のため
のシールド掘削機であり、その後部にはエレクタ22を
有している。該エレクタ22の背面には、セグメントS
1をトンネル面に取りつけるためにもち上げるセグメン
ト用自動把持装置23を回転自在に備えている。該自動
把持装置23は、セグメントS1 のグラウトホールに
設けられたねじ孔に螺入される吊りねじ24を有し、シ
リンダ25の駆動によって螺入後にセグメントS1 を
持ち上げることができるようになっている。
In FIG. 5, 21 is a shield excavator for tunnel excavation, and has an erector 22 at its rear. On the back of the erector 22, there is a segment S.
1 is rotatably provided. The automatic gripping device 23 has a hanging screw 24 that is screwed into a screw hole provided in the grout hole of the segment S1, and can lift the segment S1 after screwing in by driving a cylinder 25. .

【0004】さらに、上記シールド掘削機21からは後
方にクレーンレール26が延出していて、これにホイス
ト27が走行自在に設けられている。該ホイスト27の
フック28には吊りボルト29が掛けられている。また
、トンネル壁面を形成する既設のセグメントS上には走
行レール30が敷設されていて該走行レール30上をト
ロッコ台車31により設置前のセグメントS1 を搬送
するようになっている。
Furthermore, a crane rail 26 extends rearward from the shield excavator 21, and a hoist 27 is provided on this rail so as to be movable. A hanging bolt 29 is hung on a hook 28 of the hoist 27. Furthermore, a traveling rail 30 is laid on the existing segment S forming the tunnel wall surface, and the segment S1 before installation is transported on the traveling rail 30 by a trolley cart 31.

【0005】かかる従来の装置において、セグメントS
1 は自動把持装置23の位置まで、次の要領で搬送さ
れていた。 ■  トロッコ台車31上に、セグメントS1 を積ん
で走行レール30上を走行させてホイスト27の直下位
置で停止させる。 ■  ホイスト27のフック28から吊りボルト29を
外し、これを作業員がトロッコ台車31上のセグメント
S1 のねじ孔に螺入せしめ、フック28を降下させて
この吊りボルト29に掛ける。 ■  次に、ホイスト27をクレーンレール26に沿っ
てエレクタ22の直前位置まで搬送し受け台上に置く。 ■  しかる後に、作業員がフック28を吊りボルト2
9から外し、ホイスト27を後方に退避させておいて、
作業員が吊りボルト29をセグメントS1 より外す。 ■  次に、エレクタ22を回転させて該エレクタ22
に取り付けた自動把持装置23をセグメント受け台上の
セグメントS1 の上方位置に移動させ、セグメントS
1 のグラウトホールのねじ孔に自動把持装置23の吊
りねじ24を自動操作にてねじ込み把持を行う。 ■  かかる後、把持したセグメントS1 を昇降シリ
ンダ25にて持ち上げエレクタ22を回転させて円周方
向の所定の位置に移動させる。
[0005] In such a conventional device, the segment S
1 was transported to the position of the automatic gripping device 23 in the following manner. (2) The segment S1 is loaded onto the trolley cart 31, and the segment S1 is run on the running rail 30 and stopped at a position directly below the hoist 27. (2) Remove the hanging bolt 29 from the hook 28 of the hoist 27, and the worker screws it into the screw hole of the segment S1 on the trolley cart 31, lowers the hook 28, and hooks it onto the hanging bolt 29. (2) Next, the hoist 27 is transported along the crane rail 26 to a position just in front of the erector 22 and placed on the cradle. ■ After that, the worker attaches the hook 28 to the hanging bolt 2.
9 and evacuate the hoist 27 to the rear.
A worker removes the hanging bolt 29 from segment S1. ■ Next, rotate the erector 22 so that the erector 22
Move the automatic gripping device 23 attached to the segment S1 to a position above the segment S1 on the segment holder, and
The hanging screw 24 of the automatic gripping device 23 is automatically screwed into the screw hole of the grout hole No. 1 to perform gripping. (2) After this, the gripped segment S1 is lifted by the lifting cylinder 25, and the erector 22 is rotated to move it to a predetermined position in the circumferential direction.

【0006】ホイストとトロッコによるセグメントの間
欠的な人力を主体とした搬送装置に対し、最近チェーン
コンベアにセグメントの押し出し用の爪を設けてセグメ
ントを掘削機後方より、掘削機直後に設けたセグメント
組み立て用自動把持装置の下にまで移送する方法が特公
昭63−54119で開示されている。
[0006] In contrast to the intermittent human-powered transportation system for segments using hoists and trolleys, recently segment assembly has been implemented in which a chain conveyor is provided with claws for pushing out the segments, and the segments are placed from the rear of the excavator or immediately after the excavator. Japanese Patent Publication No. 63-54119 discloses a method of transferring the material to the bottom of an automatic gripping device.

【0007】[0007]

【発明が解決しようとする課題】上述のごとくの従来装
置によれば、セグメントはホイストによって吊られて自
動把持装置の位置にもたらされる。このため、グラウト
ホール(ねじ孔)を上記自動把持装置に対し、前後左右
方向において常に一定の位置にもたらすことはきわめて
困難である。これに対処するには、自動把持装置に、グ
ラウトホールの位置を検出する複雑な装置が必要であり
、また検出された信号にもとづいてエレクタあるいは自
動把持装置の駆動を正確に制御させて、グラウトホール
と自動把持装置の吊りねじの位置を合わせるための特別
な駆動装置も必要である。
According to the prior art apparatus as described above, the segments are suspended by a hoist and brought to the position of the automatic gripping device. For this reason, it is extremely difficult to always bring the grout hole (screw hole) to a constant position in the front, back, left and right directions with respect to the automatic gripping device. To deal with this, the automatic gripping device needs a complex device to detect the position of the grout hole, and the detected signal must be used to precisely control the drive of the erector or automatic gripping device to remove the grout. A special drive is also required to align the holes and the hanging screws of the automatic gripping device.

【0008】また、ホイストで1枚づつセグメントを搬
入し退避してから次のセグメントを搬入するのは作業に
無駄時間を生じ作業能率が悪い。
[0008] Furthermore, carrying in segments one by one using a hoist, retracting them, and then carrying in the next segment results in wasted time and poor work efficiency.

【0009】これに加えて、回転するエレクタの直前で
作業員がグラウトホールのねじ孔にねじ込んだ吊りボル
トからホイストのフックを外し、そして上記ねじ孔から
吊りボルトを取り除く作業を行うことは作業空間が狭隘
なため苦渋作業であり危険でもある。
[0009] In addition, it is necessary for the worker to remove the hook of the hoist from the hanging bolt screwed into the screw hole of the grout hole immediately before the rotating erector, and to remove the hanging bolt from the screw hole. Because the space is narrow, the work is difficult and dangerous.

【0010】特公昭63−54119においては、大幅
に人力の軽減が図られているが、チェーンコンベアにセ
グメントの押し出し用の爪で単にセグメントを搬送する
に留まっており、セグメントは自動把持装置の直下に正
しく停止することはできない。このために、自動把持装
置の定位置にないセグメントを把持するために実開平2
−97498「セグメント自動把持装置」等で示される
自動調整機構を設ける必要がある。
[0010] In Japanese Patent Publication No. 63-54119, the human power is significantly reduced, but the segments are simply conveyed by a chain conveyor with claws for pushing out the segments, and the segments are placed directly under the automatic gripping device. cannot be stopped properly. For this purpose, a practical flat 2
-97498 It is necessary to provide an automatic adjustment mechanism such as "segment automatic gripping device".

【0011】本発明はかかる問題を解決し、セグメント
の搬送装置をグラウトホールのねじ孔が常に一定の位置
にて止まるように工夫し、自動把持装置のグラウトホー
ル検出装置や、エレクタあるいは自動把持装置の駆動制
御装置を要することなく、複数のセグメントを順次前方
に送り出し搬送作業の高効率化を図り、さらには、エレ
クタ直前での作業員によるフック及び吊りボルトの取り
はずし作業を省略できて苦渋作業及び危険作業をなくす
ことができるセグメント搬送装置を提供することを目的
とする。
The present invention solves this problem by devising a segment conveying device so that the threaded hole of the grout hole always stops at a fixed position, and by using a grout hole detection device of an automatic gripping device, an erector, or an automatic gripping device. This system allows multiple segments to be sent forward one after another without requiring a drive control device, increasing the efficiency of conveyance work.Furthermore, it eliminates the need for workers to remove hooks and hanging bolts directly in front of the erector, which saves laborious work. An object of the present invention is to provide a segment conveyance device that can eliminate dangerous work.

【0012】0012

【課題を解決するための手段】本発明によれば、上記目
的は、シールド掘進機の後部より延出する架構を有し、
該架構はセグメントの組立のための自動把持装置に対し
走位置となるように既設セグメント上を前方に移動可能
となっており、上記架構には設置前の複数のセグメント
を前後方向で所定距離毎に載置して該セグメントを該架
構に対して前方へ搬送する搬送手段を設け、搬送手段は
上記設置前の各セグメントのグラウトホールに外側から
係止する係止突部を上記所定距離毎に備えていると共に
係止突部が自動把持装置に対し定位置となるように該所
定距離毎に間欠的に該セグメントを搬送可能となってい
ることにより達成される。
[Means for Solving the Problems] According to the present invention, the above object is achieved by having a frame extending from the rear of the shield tunneling machine,
The frame is movable forward over the existing segments so as to be in a running position relative to the automatic gripping device for assembling the segments, and the frame is equipped with a plurality of segments that are held at predetermined distances in the front and back direction before installation. A conveying means is provided for placing the segment on the frame and conveying the segment forward with respect to the frame, and the conveying means has locking protrusions that lock from the outside into the grout hole of each segment before installation, at intervals of the predetermined distance. This is achieved by being able to transport the segment intermittently every predetermined distance so that the locking protrusion is in a fixed position with respect to the automatic gripping device.

【0013】[0013]

【作用】かかる構成の本発明にあっては、設置前の複数
のセグメントは順次と搬送手段上に載かれる。搬送手段
には所定距離毎にセグメントのグラウトホールと係止す
る係止突部を備えており、搬送手段上の各セグメントは
この部材に係止して上記所定距離間隔に位置する。搬送
手段はセグメントを上記所定距離だけ間欠的に搬送する
ので、先頭に位置するセグメントを自動把持装置で把持
した後、次に先頭となるセグメントも同じ位置にもたら
される。かくして、当初に先頭のセグメントのグラウト
ホールの位置を自動把持装置の吊りねじの位置に設定し
ておけば、該自動把持装置による把持は何ら位置調整を
要することなく自動的になされる。
[Operation] In the present invention having such a structure, a plurality of segments before being installed are placed one after another on the conveying means. The conveying means is provided with locking protrusions that lock with the grout holes of the segments at predetermined intervals, and each segment on the conveying means is locked with this member and positioned at the predetermined distance intervals. Since the conveying means intermittently conveys the segment by the predetermined distance, after the segment located at the beginning is gripped by the automatic gripping device, the next leading segment is also brought to the same position. Thus, if the position of the grout hole of the leading segment is initially set at the position of the hanging screw of the automatic gripping device, gripping by the automatic gripping device is automatically performed without any position adjustment.

【0014】[0014]

【実施例】以下、添付図面の図1ないし図4にもとづい
て本発明の実施例を説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments of the present invention will be described with reference to FIGS. 1 to 4 of the accompanying drawings.

【0015】図1は本実施例装置の使用状態での部分断
面正面図である。図2は図1におけるII−II拡大断
面図である。なお、図中、図5ないし図7に示した従来
装置と共通部分には同一符号を付して、その説明を省略
する。
FIG. 1 is a partially sectional front view of the apparatus of this embodiment in use. FIG. 2 is an enlarged sectional view taken along line II-II in FIG. In the figure, parts common to those of the conventional apparatus shown in FIGS. 5 to 7 are designated by the same reference numerals, and their explanations will be omitted.

【0016】本実施例装置において、シールド掘進機2
1から後方に梁部材1が突出して設けられ、該梁部材1
にピン2を介して架構3が接合されている。該架構3は
、枠状をなしてトンネルの長手方向では自動把持装置2
3の位置から走行レール30の前端近傍位置までの範囲
で長く延び、またトンネルの周方向では該トンネル下面
に沿って少なくともセグメント1個分だけの幅をもって
形成されている。
In the device of this embodiment, the shield excavator 2
A beam member 1 is provided to protrude rearward from the beam member 1.
A frame 3 is connected to the frame 3 via pins 2. The frame 3 has a frame shape and has an automatic gripping device 2 in the longitudinal direction of the tunnel.
It extends long from position 3 to a position near the front end of the traveling rail 30, and in the circumferential direction of the tunnel, it is formed with a width equal to at least one segment along the lower surface of the tunnel.

【0017】上記架構3の下部には、長手方向及び、図
2にもよく見られるように周方向の適宜複数位置に車輪
としてのローラ4が設けられていて、架構3の自重及び
荷重を支えつつ該架構3を既設のセグメントS上を移動
可能にせしめている。
At the bottom of the frame 3, rollers 4 as wheels are provided at appropriate positions in the longitudinal direction and in the circumferential direction as well as in FIG. 2, to support the weight and load of the frame 3. At the same time, the frame 3 is made movable on the existing segment S.

【0018】上記架構3の前端部及び後端部にはスプロ
ケット5,6が設けられており、該スプロケット5,6
にチェーン7が枠状の架構3内を前後に間欠走行するよ
うに張設されている。このチェーン7にはセグメントS
1 の1個分の長さもしくはこれより若干長いピッチに
て、セグメントS1 のグラウトホールSHに貫入する
係止突部8が取りつけられていて、上記ピッチを保って
上記架構3の空間内にてセグメントS1 を前方に牽引
可能となっている。また、架構3には、上記ローラ4の
上方位置に、長手方向及び周方向の適宜複数位置に他の
ローラ9が設けられていて、上記チェーン7により牽引
されるセグメントS1 を移動可能に支えている。
Sprockets 5 and 6 are provided at the front and rear ends of the frame 3, and the sprockets 5 and 6
A chain 7 is stretched so as to run intermittently back and forth within the frame-shaped frame 3. This chain 7 has segment S
The locking protrusions 8 that penetrate into the grout holes SH of the segment S1 are attached at a pitch equal to or slightly longer than the length of one grout hole SH of the segment S1. Segment S1 can be towed forward. Further, the frame 3 is provided with other rollers 9 at a plurality of appropriate positions in the longitudinal direction and the circumferential direction above the roller 4, and movably supports the segment S1 pulled by the chain 7. There is.

【0019】上記架構3の後部にはガイド10,10が
設けられており、該ガイド10,10間にセグメントS
1 を入れることにより、停止せるチェーン7に対して
該セグメントS1 が定位置で配置され、グラウトホー
ルSHがチェーン7の係止突部8と係止し合うようにな
っている。そして、チェーン7の前端部における係止突
部8すなわち、これに係止されているセグメントS1 
のグラウトホールが前後方向において自動把持装置23
の吊りねじ24の位置にくるように、該チェーン7の停
止位置が設定される。
Guides 10, 10 are provided at the rear of the frame 3, and a segment S is provided between the guides 10, 10.
1, the segment S1 is placed in a fixed position relative to the chain 7 to be stopped, and the grout hole SH is engaged with the locking protrusion 8 of the chain 7. A locking projection 8 at the front end of the chain 7, that is, a segment S1 locked to this
The automatic gripping device 23 holds the grout hole in the front and back direction.
The stopping position of the chain 7 is set so that it is at the position of the hanging screw 24.

【0020】チェーン7は既述のごとく間欠走行される
が、これは図示せぬ減速手段付モータ等から成る駆動装
置のスイッチを作業員が適宜作動せしめることによりチ
ェーン7を走行駆動し、架構3の所定位置に設けられた
停止スイッチ11にチェーン7の係止突部8が当接する
ことによりチェーン7を停止することにより行われる。 かくして、チェーン7はセグメントS1 を一個づつ自
動把持装置23の位置にまで搬送するようになる。
As described above, the chain 7 is intermittently run, and this is done by the operator operating the switch of the drive device consisting of a motor with a deceleration means (not shown), etc., to drive the chain 7 and move the frame 3. This is done by stopping the chain 7 when the locking protrusion 8 of the chain 7 comes into contact with a stop switch 11 provided at a predetermined position. The chain 7 thus conveys the segments S1 one by one to the position of the automatic gripping device 23.

【0021】かかる本実施例装置にあっては、セグメン
トS1 は次の要領で自動把持装置にまで搬送される。 ■  架構3の後端部で、作業員がトロッコ台車31よ
りセグメントS1 のグラウトホールのねじ孔に吊りボ
ルト29をねじ込みホイスト27により該セグメントS
1 をトロッコ台車31より吊り上げて、架構3のガイ
ドフレーム10,10に沿って降ろしローラ9の上に静
かに置く。 ■  すると、吊り降ろされたセグメントS1 のグラ
ウトホールの下部に停止せるチェーン7の係止突部8が
貫入する。 ■  次に、作業員はホイスト27のフック28を吊り
ボルト29から外しまた吊りボルト29をセグメントS
1 より取り除く。 ■  ここで、作業員がモータを発動するスイッチを押
しチェーン7を駆動させる。セグメントS1 はグラウ
トホールSHに貫入された係止突部8により前方に牽引
される。
In the apparatus of this embodiment, the segment S1 is conveyed to the automatic gripping device in the following manner. ■ At the rear end of the frame 3, a worker screws the suspension bolt 29 into the screw hole of the grout hole of the segment S1 from the trolley cart 31 and uses the hoist 27 to remove the segment S.
1 is lifted from the trolley cart 31 and gently placed on the unloading roller 9 along the guide frames 10, 10 of the frame 3. (2) Then, the locking protrusion 8 of the chain 7 that is stopped at the lower part of the grout hole of the suspended segment S1 penetrates. ■ Next, the worker removes the hook 28 of the hoist 27 from the hanging bolt 29, and also removes the hanging bolt 29 from the segment S.
Remove from 1. ■ Here, the worker presses the switch that activates the motor to drive the chain 7. The segment S1 is pulled forward by the locking protrusion 8 penetrated into the grout hole SH.

【0022】セグメントS1 が1個分前方に搬送され
ると、前方のスプロケット8を通過した係止突部8が停
止11に当接し、ここでチェーン7は停止する。かくし
て順次セグメントS1 を前方に間欠的に送り出すが、
セグメントS1 はそのグラウトホールSHが常に一定
して前後方向において自動把持装置23の吊りねじ24
の位置にて停止する。 ■  しかる後、自動把持装置23の吊りねじ24がセ
グメントS1 のグラウトホール31の真上にくるよう
にエレクタ22を停止させ、吊りボルト24を回転しな
がら昇降シリンダ25によりこれを下げて、吊りねじ2
4をグラウトホールのねじ孔に螺入せしめた後にもち上
げエレクタ28回転させセグメントS1 を所定の組立
位置に配置する。
When the segment S1 is conveyed forward by one segment, the locking protrusion 8 that has passed through the front sprocket 8 comes into contact with the stop 11, and the chain 7 is stopped here. In this way, the segments S1 are sent forward intermittently, but
Segment S1 has its grout hole SH always fixed in the front-back direction when the hanging screw 24 of the automatic gripping device 23
Stop at the position. After that, stop the erector 22 so that the hanging screw 24 of the automatic gripping device 23 is directly above the grout hole 31 of the segment S1, lower it by the lifting cylinder 25 while rotating the hanging bolt 24, and remove the hanging screw. 2
4 into the screw hole of the grout hole, the lifting erector 28 is rotated to place the segment S1 at a predetermined assembly position.

【0023】本発明は上述の実施例に限定されずに変形
が可能である。例えば、搬送手段はローラ及びチェーン
によらずとも、コンベアでも可能である。
The present invention is not limited to the embodiments described above, but can be modified. For example, the conveying means does not have to be rollers and chains, but can also be a conveyor.

【0024】[0024]

【発明の効果】以上のように本発明によれば、自動把持
装置の吊りボルトを貫入せしめるグラウトホールがエレ
クタに対し常に一定の位置となるようにセグメントを搬
送できるので、自動把持装置には従来装置が備えていた
グラウトホールの位置検出のための複雑な装置や自動把
持装置の正確な駆動のための位置が不要となり経済的と
なる。
As described above, according to the present invention, segments can be conveyed so that the grout hole through which the hanging bolt of the automatic gripping device is inserted is always at a constant position relative to the erector. The complicated device for detecting the position of the grout hole and the position for accurate driving of the automatic gripping device, which were provided in the device, are no longer required, making it economical.

【0025】また後方より複数のセグメントを順次前方
に送り出すことにより、ホイストの作業区域が後方の短
い区間となり、ホイストの退避時間が節約でき搬送作業
の高効率化を図ることができる。これに加えて、エレク
タ直前での作業員のフック及び吊りボルトの取り外し作
業を省略できるので苦渋作業及び危険作業をなくすこと
も可能となる。
Furthermore, by sequentially sending out a plurality of segments forward from the rear, the working area of the hoist becomes a short section at the rear, saving time for hoist retraction and making it possible to improve the efficiency of the conveyance work. In addition, it is possible to eliminate laborious and dangerous work by eliminating the need for the worker to remove the hook and hanging bolt immediately in front of the erector.

【図面の簡単な説明】[Brief explanation of the drawing]

【図1】本発明の一実施例装置の使用状態での部分断面
正面図である。
FIG. 1 is a partially sectional front view of an apparatus according to an embodiment of the present invention in a state of use.

【図2】図1におけるII−II拡大断面図である。FIG. 2 is an enlarged sectional view taken along line II-II in FIG. 1;

【図3】図1のチェーンに取りつけられた係止突部の拡
大正面図である。
FIG. 3 is an enlarged front view of a locking protrusion attached to the chain of FIG. 1;

【図4】図3におけるIV−IV断面図である。FIG. 4 is a sectional view taken along line IV-IV in FIG. 3;

【図5】従来装置の使用状態での部分断面正面図である
FIG. 5 is a partially sectional front view of the conventional device in use.

【図6】図5におけるVI−VI拡大断面図である。FIG. 6 is an enlarged sectional view taken along VI-VI in FIG. 5;

【図7】セグメントのグラウトホールのねじ孔に吊りボ
ルトを螺入した際のセグメントの断面図である。
FIG. 7 is a cross-sectional view of the segment when a hanging bolt is screwed into the screw hole of the grout hole of the segment.

【符号の説明】[Explanation of symbols]

3  架構 7,8,9  搬送装置 7  チェーン 8  係止突部 9  ローラ 8  係止部材(係止突部) 21  トンネル掘進機 23  自動把持装置 S  既設セグメント S1   設置前のセグメント 3. Frame 7, 8, 9 Conveyance device 7 Chain 8 Locking protrusion 9 Roller 8 Locking member (locking protrusion) 21 Tunnel digging machine 23 Automatic gripping device S Existing segment S1 Segment before installation

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】  シールド掘進機の後部より延出する架
構を有し、該架構はセグメントの組立のための自動把持
装置に対し走位置となるように既設セグメント上を前方
に移動可能となっており、上記架構には設置前の複数の
セグメントを前後方向で所定距離毎に載置して該セグメ
ントを該架構に対して前方へ搬送する搬送手段を設け、
搬送手段は上記設置前の各セグメントのグラウトホール
に外側から係止する係止突部を上記所定距離毎に備えて
いると共に係止突部が自動把持装置に対し定位置となる
ように該所定距離毎に間欠的に該セグメントを搬送可能
となっていることとするセグメント搬送装置。
Claim 1: The shield tunneling machine has a frame extending from the rear thereof, and the frame is movable forward over the existing segments so as to be in a running position with respect to an automatic gripping device for assembling the segments. and a conveying means is provided on the frame for placing a plurality of segments before installation at predetermined distances in the front-back direction and conveying the segments forward with respect to the frame,
The conveying means is provided with locking protrusions that lock into the grout holes of each segment from the outside before installation, at each predetermined distance. A segment conveying device capable of conveying the segment intermittently for each distance.
JP3078316A 1991-03-19 1991-03-19 Segment carrier Pending JPH04289400A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3078316A JPH04289400A (en) 1991-03-19 1991-03-19 Segment carrier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3078316A JPH04289400A (en) 1991-03-19 1991-03-19 Segment carrier

Publications (1)

Publication Number Publication Date
JPH04289400A true JPH04289400A (en) 1992-10-14

Family

ID=13658535

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3078316A Pending JPH04289400A (en) 1991-03-19 1991-03-19 Segment carrier

Country Status (1)

Country Link
JP (1) JPH04289400A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021085210A (en) * 2019-11-27 2021-06-03 株式会社安藤・間 Segment transport device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021085210A (en) * 2019-11-27 2021-06-03 株式会社安藤・間 Segment transport device

Similar Documents

Publication Publication Date Title
JPH04289400A (en) Segment carrier
JP2980865B2 (en) Segment handling equipment for shield machine
CN112377245A (en) Inclined shaft material transportation system and transportation method
JP2588458Y2 (en) Segment installation equipment
CN112298916A (en) Full-automatic transportation loading device for vehicle body plates
JP3372618B2 (en) Mobile transport equipment for tunnel construction materials
JP2549368Y2 (en) Simple luggage carrier
JPH0322399Y2 (en)
JPH0619680Y2 (en) Segment transport supply device
JP2528532B2 (en) Segment transfer device
CN217707989U (en) A equipment for rock gangway tunnelling
JP3303945B2 (en) Segment loading device
CN212637059U (en) Hoisting equipment walking wheel group
CN108340153A (en) Scraper chain assembles device and assembly method
CN214568518U (en) Automatic recovery unit of automobile body plate couple
JP2005104433A (en) Testing apparatus for transportation train
JP3052630B2 (en) Rail tunneling equipment for shield tunnel
SU569499A1 (en) Device for transferring articles from one conveyer to a series of other conveyers arranged in parallel
JP3166963B2 (en) Tracking device for transport vehicles such as segments
JPH0634202Y2 (en) Transport equipment
JP2582924Y2 (en) Transfer device
JPH10131694A (en) Shield tunneling method automating system
JPH05193498A (en) Carrier device for automotive door
JPH0752107Y2 (en) Continuous unloader
KR880002375B1 (en) Transportation apparatus for beam with yarn