JPH04285297A - Method for constructing underground space - Google Patents

Method for constructing underground space

Info

Publication number
JPH04285297A
JPH04285297A JP3075668A JP7566891A JPH04285297A JP H04285297 A JPH04285297 A JP H04285297A JP 3075668 A JP3075668 A JP 3075668A JP 7566891 A JP7566891 A JP 7566891A JP H04285297 A JPH04285297 A JP H04285297A
Authority
JP
Japan
Prior art keywords
plate
underground space
plasticizer
lead guide
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3075668A
Other languages
Japanese (ja)
Inventor
Takahiro Tsubota
隆宏 坪田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP3075668A priority Critical patent/JPH04285297A/en
Publication of JPH04285297A publication Critical patent/JPH04285297A/en
Pending legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To safely and economically construct an underground space within a short period of construction and at a low noise level without requiring the conveyance and back filling of surface soil, disturbing activities above the ground and being obstructed by any existing buried object. CONSTITUTION:Lead guides 12 are buried along an underground space after the excavation of a work zone and a plasticizer is substituted for earth and sand in a plate insert portion. Arched hollow plates 122 are inserted along the lead guides 12 and concrete 38 is packed in the hollow portion of each plate and an underground space 4 is excavated after the concrete becomes stiff.

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【発明の利用分野】この発明は、地下空間の造出方法に
関する。
FIELD OF THE INVENTION This invention relates to a method for creating underground space.

【0002】0002

【従来技術】地下空間の造出は、主としてオープンカッ
ト工法や、シールド工法で行われている。シールド工法
では、コンクリートの硬化までの間、仮枠で掘削した地
下空間を支えるため崩落の危険性が有り、地下の浅い部
分では用いることができない。またシールド工法では、
掘削した土砂を泥水化して排出するため、排出量がきわ
めて大きい。このため都市部での地下空間の造出は、主
としてオープンカット工法で行われている。オープンカ
ット工法は、地下空間を形成する部分をオープンカット
するため、地上の交通等への妨げとなり、工事に伴う騒
音も大きい。オープンカット工法の他の問題として、地
下空間の部分までの土砂を削り取り、地下空間の造出後
に埋め戻さねばならないため、削り取り、埋め戻す土砂
の量が多く、作業量が増加すると共に、途中の土砂の保
管場所が必要になる点がある。またオープンカット工法
では、ガス管、水道管、下水管等が施行の妨げとなり、
鉄道の高架や小さな物でも建物等があると、施行が困難
となる。
BACKGROUND OF THE INVENTION Underground spaces are mainly created using open cut construction methods and shield construction methods. In the shield construction method, the excavated underground space is supported with temporary frames until the concrete hardens, so there is a risk of collapse, and it cannot be used in shallow underground areas. In addition, with the shield method,
Since the excavated earth and sand is turned into muddy water and discharged, the amount of discharge is extremely large. For this reason, underground space creation in urban areas is mainly carried out using the open cut method. The open-cut construction method involves cutting open the part that forms the underground space, which obstructs above-ground traffic, and also generates a lot of noise during construction. Another problem with the open cut construction method is that the earth and sand must be scraped down to the underground space and backfilled after the underground space has been created. There is a need for a place to store the soil. In addition, with the open cut construction method, gas pipes, water pipes, sewage pipes, etc. become obstacles to construction.
Enforcement becomes difficult if there are elevated railways or small buildings.

【0003】0003

【発明の課題】この発明の課題は、(1)  表土の搬
出、埋め戻しの必要がなく、(2)  地上活動を妨げ
ることなく施行ができ、(3)  工期が短く、(4)
騒音が少なく、(5)  ガス管や建物の基礎等の既存
の埋設物が工事の障害にならず、(6)  崩落の危険
性がないため安全な、地下空間の造出方法を提供するこ
とにある。
[Problems of the Invention] The problems of this invention are: (1) There is no need to remove or backfill topsoil, (2) construction can be carried out without interfering with above-ground activities, (3) the construction period is short, and (4)
To provide a method for creating an underground space that is safe because it is low in noise, (5) existing buried objects such as gas pipes and building foundations do not obstruct construction work, and (6) there is no risk of collapse. It is in.

【0004】0004

【発明の構成】この発明は、作業空間を掘削する工程と
、掘削した作業空間から形成目標の地下空間に沿ってリ
ードガイドを差し込む工程と、差し込んだリードガイド
により方向を定めながらプレートを形成目標の地下空間
の天井部に沿って差し込む工程と、プレートの下部を掘
削し地下空間を造出する工程とを設けた、地下空間の造
出方法にある。プレートは、例えば地下空間の天井部と
床部とに対応した2枚のプレートとする。より好ましく
はプレートは、形成目標の地下空間の側面と天井とに対
応したアーチ型のプレートとし、一気に地下空間の天井
と両壁とを形成できるようにする。この発明ではプレー
トで天井部を形成した後に地下空間の掘削を行い、それ
までの工程ではリードガイドやプレートの差込みが主な
ものである。このためこの発明では、崩落の恐れなしに
地下空間を造出できる。
[Structure of the Invention] This invention comprises a process of excavating a work space, a process of inserting a lead guide from the excavated work space along a target underground space, and a process of forming a plate while determining the direction by the inserted lead guide. A method for creating an underground space includes a step of inserting the plate along the ceiling of the underground space, and a step of excavating the lower part of the plate to create an underground space. The plates are, for example, two plates corresponding to the ceiling and floor of the underground space. More preferably, the plate is an arch-shaped plate that corresponds to the sides and ceiling of the underground space to be formed, so that the ceiling and both walls of the underground space can be formed at once. In this invention, the underground space is excavated after the ceiling is formed with plates, and the main steps up to that point are insertion of lead guides and plates. Therefore, with this invention, an underground space can be created without fear of collapse.

【0005】[0005]

【実施例】実施例1 作業区画の掘削(図1) 実施例の工程を順を追って説明する。最初に、図1に示
す横穴掘り用の作業区画2を掘削する。例えば設ける地
下空間の断面が8m×8mであれば、地下空間の大きさ
よりもやや大きい、10m×10m程度の断面の作業区
画2を掘削する。またこの場合の作業区画2は、例えば
20m〜40m間隔で掘削する。図において、4は地下
空間の形成部、6は矢板で、作業区画2の反対側の面に
も設ける。作業区画2の掘削と掘削後の作業は例えば夜
間に行い、中間は作業区画2に図示しない蓋をし、交通
等の障害とならないようにする。実施例ではプレート等
を油圧で土中に差し込むので、土圧に抗してプレート等
を差し込めるように支持板7を設ける。図にはコンクリ
ート壁を用いた支持板7を示したが、作業区画2の底面
に基礎を打ち込んで、これを支持板としても良い。支持
板7により、プレートの差込み等に用いる土木機械を支
持する。
[Example] Example 1 Excavation of work area (FIG. 1) The steps of the example will be explained step by step. First, a work section 2 for horizontal hole digging shown in FIG. 1 is excavated. For example, if the cross section of the underground space to be provided is 8 m x 8 m, a work section 2 with a cross section of about 10 m x 10 m, which is slightly larger than the size of the underground space, is excavated. Further, in this case, the work section 2 is excavated at intervals of, for example, 20 m to 40 m. In the figure, 4 is an underground space forming part, and 6 is a sheet pile, which is also provided on the opposite side of the work area 2. The excavation of the work zone 2 and the work after the excavation are performed, for example, at night, and the work zone 2 is covered with a lid (not shown) in the middle so as not to become an obstruction to traffic. In this embodiment, the plates and the like are inserted into the soil using hydraulic pressure, so the support plate 7 is provided so that the plates and the like can be inserted against the earth pressure. Although the support plate 7 using a concrete wall is shown in the figure, a foundation may be poured into the bottom of the work area 2 and this may be used as the support plate. The support plate 7 supports the civil engineering machine used for inserting plates and the like.

【0006】リードガイド柱差込み穴の掘削(図2)作
業区画2を掘削すると、掘削機を降ろし、オーガ8等で
地下空間の形成部4の4隅に、プレート用リードガイド
柱の差込み穴10を掘削する。この場合に、作業区画2
の間隔が40mと長い場合には、例えば向かい合う双方
の作業区画2からリードガイド柱の差込み穴10を掘り
進めて、中央でドッキングさせる。また間隔が20mと
短い場合には、一方の作業区画2から掘り進めて他方の
作業区画2まで貫通させる。プレートを地下空間の天井
部のみに設ける場合、リードガイド柱の差込み穴は上部
の2隅とする。
Drilling holes for inserting lead guide columns (FIG. 2) After excavating the work section 2, the excavator is lowered and holes 10 for inserting lead guide columns for the plate are drilled at the four corners of the underground space forming part 4 using an auger 8 or the like. excavate. In this case, work area 2
If the interval is as long as 40 m, for example, insert holes 10 for the lead guide pillars are dug from both opposing work sections 2, and the lead guide pillars are docked at the center. If the distance is as short as 20 m, the excavation is continued from one working section 2 to the other working section 2. If the plate is installed only on the ceiling of the underground space, the insertion holes for the lead guide pillars shall be at the top two corners.

【0007】リードガイド柱の埋め込み(図3)掘削し
たリードガイド柱の差込み穴10に、プレート用のリー
ドガイド柱12(例えば鋼製)を埋め込む。20mの長
さのリードガイド柱12を作業区画2に持ち込むことは
困難なので、リードガイド柱12を数本に分け、継ぎな
がらリードガイド柱12を完成する。図の14はリード
ガイド柱の先端部で、埋設を容易にするため先端を尖ら
してあり、16はリードガイド柱の継ぎ足し部である。 リードガイド柱12を中央でドッキングさせる場合、先
端14もそれに応じた形状とする。
Embedding the lead guide pillar (FIG. 3) A lead guide pillar 12 (made of steel, for example) for a plate is embedded in the insertion hole 10 of the lead guide pillar that has been excavated. Since it is difficult to bring the 20 m long lead guide pillar 12 into the work section 2, the lead guide pillar 12 is divided into several pieces and is completed by joining them together. Reference numeral 14 in the figure is the tip of the lead guide column, which has a sharpened tip to facilitate embedding, and 16 is a supplementary portion of the lead guide column. When the lead guide column 12 is docked at the center, the tip 14 is also shaped accordingly.

【0008】プレート差込み部の土質改良(図4)リー
ドガイド柱12,12間のプレートの差込み部を土質改
良し、可塑性を与える。このために、先ずプレートの差
込み部に穴18を間隔を置いて複数掘り、土砂を除去す
る。次いで土砂を除去した穴18に、可塑剤20を注入
する。可塑剤20の材質には例えば粘土、熱可塑性合成
樹脂等を用い、プレートの差込み時に変形してプレート
の差込みを可能にするものであれば良い。好ましい可塑
剤20の材料は粘土を油で混練したもので、プレートの
断面積よりもやや大きな面積で可塑剤20を注入して置
く。可塑剤20の注入間隔は施行部の土質により変え、
例えば元々粘土質で可塑性の高い土質では可塑剤20の
注入は省略しても良い。一方硬い土質では、リードガイ
ド柱12,12の間のプレート差込み部の土砂を、全面
的に可塑剤で置き換える。一気に全面的に置き換えると
穴18が崩れるので、一部を置き換えた後に、他の部分
に穴18を堀りそこを置き換える。通常の土質では間を
置いて可塑剤20による土砂の置き換えを行い、土質の
可塑性に応じ可塑剤20の注入間隔を定める。注入した
可塑剤20は穴18の奥では軟質で、入口部に近づく程
硬質となる。
Improving the soil quality of the plate insertion part (FIG. 4) The soil quality of the plate insertion part between the lead guide columns 12 and 12 is improved to give it plasticity. For this purpose, first, a plurality of holes 18 are dug at intervals in the insertion portion of the plate, and earth and sand are removed. Next, a plasticizer 20 is injected into the hole 18 from which the earth and sand have been removed. The material of the plasticizer 20 may be, for example, clay, thermoplastic synthetic resin, etc., as long as it deforms when the plate is inserted and allows the plate to be inserted. A preferred material for the plasticizer 20 is clay kneaded with oil, and the plasticizer 20 is injected in an area slightly larger than the cross-sectional area of the plate. The injection interval of plasticizer 20 is changed depending on the soil quality of the area to be applied.
For example, if the soil is originally clayey and highly plastic, the injection of the plasticizer 20 may be omitted. On the other hand, in hard soil, the earth and sand in the plate insertion portion between the lead guide columns 12, 12 is completely replaced with plasticizer. If the entire area is replaced at once, the hole 18 will collapse, so after replacing one part, the hole 18 is dug in another part and replaced there. For normal soil conditions, the soil is replaced with plasticizer 20 at intervals, and the injection interval of plasticizer 20 is determined depending on the plasticity of the soil. The injected plasticizer 20 is soft in the depths of the hole 18, and becomes harder as it approaches the entrance.

【0009】プレートの差込み(図5〜図7)次いで鋼
製のプレート22を、リードガイド柱12に添わせて方
向を定め、例えば数m毎に接続しながら差し込む。この
ような事が可能なのは、リードガイド柱12,12間の
土砂を可塑剤20で置き換えたからである。プレート2
2を差し込むと、可塑剤20は変形して一部はプレート
22の周囲に逃げ、大部分はプレート22の先端の穴か
らプレート22の内部に入る。プレート22の内部に入
った土砂や可塑剤20の一部は、土圧の低い部分ではプ
レート22の穴24から周囲に流出し、周囲を固める。 逆に土圧の高い部分や周囲の地盤との摩擦が大きい部分
では、周囲の土砂や可塑剤20が穴24からプレート2
2の中空部に入る。この過程で周囲の土圧が均一になる
。可塑剤20を粘土を油で混練したものとしておくと、
プレート22の差込み時に可塑剤20に加わる圧力や可
塑剤20の変形で油が浸み出し、プレート22の表面に
沿って油が広がり、上下の地盤との摩擦が減少する。ま
た可塑剤20をプレート22の差込み部の全面に注入し
、可塑剤20の注入面積をプレート22の面積よりもや
や広くして置くと、プレート22は上下の地盤と直接で
はなく、可塑剤20を介して間接的に接触し、上下の地
盤とプレート22間の摩擦が減少する。これらのため差
込みが容易になる。20mの長さのプレート22を作業
区画2に持ち込むことは難しいので、プレート22は先
端部26,継ぎ足し部28に分割し、継ぎながら1枚の
プレート22とする。プレート22の差込みは奥に行く
ほど難しくなるが、可塑剤20も穴18の奥に行くほど
軟質なので差込みが容易になる。
Inserting the plate (FIGS. 5 to 7) Next, the steel plate 22 is oriented along the lead guide column 12 and inserted, connecting each other at intervals of, for example, several meters. This is possible because the earth and sand between the lead guide columns 12, 12 is replaced with the plasticizer 20. plate 2
2, the plasticizer 20 is deformed and a part of it escapes around the plate 22, and most of it enters the inside of the plate 22 through the hole at the tip of the plate 22. Some of the earth and sand and plasticizer 20 that have entered the inside of the plate 22 flow out from the holes 24 of the plate 22 to the surrounding area in areas where the earth pressure is low, and harden the surrounding area. Conversely, in areas with high earth pressure or areas with large friction with the surrounding ground, surrounding earth and sand and plasticizer 20 will flow through the holes 24 to the plate 2.
Enter the hollow part 2. This process equalizes the surrounding earth pressure. If the plasticizer 20 is made by kneading clay with oil,
When the plate 22 is inserted, oil oozes out due to the pressure applied to the plasticizer 20 and the deformation of the plasticizer 20, and the oil spreads along the surface of the plate 22, reducing friction with the ground above and below. In addition, if the plasticizer 20 is injected into the entire surface of the insertion part of the plate 22 and the injection area of the plasticizer 20 is made slightly wider than the area of the plate 22, the plate 22 is not directly connected to the ground above and below, but the plasticizer 20 The friction between the upper and lower ground and the plate 22 is reduced. These make insertion easy. Since it is difficult to bring a plate 22 with a length of 20 m into the work area 2, the plate 22 is divided into a tip part 26 and a joining part 28, and the plate 22 is made into one piece by joining them. Inserting the plate 22 becomes more difficult as it goes deeper into the hole 18, but since the plasticizer 20 also becomes softer as it goes deeper into the hole 18, it becomes easier to insert it.

【0010】図6にプレート22の継ぎ足し部28を、
図7に硬質鋼の先端部26を示す。先端部26や継ぎ足
し部28は、2枚の鋼板を桁31で支え、中空部32を
形成したものである。2枚の鋼板の内、外板29には穴
24を設けて、先端の開口から入り込んだ土砂や可塑剤
20が周囲の地盤に逃げ、あるいは逆に周囲から可塑剤
20や土砂が中空部32に入り込むようにする。またコ
ンクリートの注入時には、中空部32に注入したコンク
リートが穴24から外部の地盤に入り込んで、プレート
22が地盤に結合するのを助けるようにする。更に穴2
4から外部に逃げたコンクリートで、外板29の表面を
部分的に覆わせ、外板29の腐食を抑制する。外板29
は周囲の地盤による腐食の恐れがあるため、内板30と
中空部32に注入したコンクリートで地下空間の構造体
が得られるように、内板30を外板29よりも肉厚とす
る。内板30の内面は地下空間の天井面や床面として利
用するので、内板30には穴24を設けない。中空部3
2に注入するコンクリートが相互に結合するように、桁
31には穴27を設ける。プレート22の先端部26は
硬質鋼製とし、内板30の先端部33や外板29の先端
部34をエッジ状に尖らせ、桁31の先端部35も刃状
として、差込みを容易にする。ここで2つの先端部33
,34をエッジが向い合うようにし(図7の左端参照)
、可塑剤20や土砂が中空部32に導き入れられて、プ
レート22の差込みが容易になるようにする。
FIG. 6 shows the additional part 28 of the plate 22.
FIG. 7 shows the hard steel tip 26. The tip portion 26 and the additional portion 28 are formed by supporting two steel plates with a girder 31 and forming a hollow portion 32. A hole 24 is provided in the outer plate 29 of the two steel plates, so that the dirt and plasticizer 20 that entered through the opening at the tip escape to the surrounding ground, or conversely, the plasticizer 20 and dirt from the surrounding area are trapped in the hollow part 32. Try to get into it. Furthermore, when pouring concrete, the concrete poured into the hollow portion 32 enters the external ground through the hole 24 to help the plate 22 bond to the ground. More hole 2
The surface of the outer panel 29 is partially covered with the concrete escaped from the outer panel 4 to the outside, and corrosion of the outer panel 29 is suppressed. Outer panel 29
Since there is a risk of corrosion due to the surrounding ground, the inner plate 30 is made thicker than the outer plate 29 so that the concrete poured into the inner plate 30 and the hollow part 32 can form a structure for the underground space. Since the inner surface of the inner plate 30 is used as the ceiling surface and floor surface of the underground space, no hole 24 is provided in the inner plate 30. Hollow part 3
Holes 27 are provided in the girder 31 so that the concrete poured into the girders 2 and 2 are bonded to each other. The tip 26 of the plate 22 is made of hard steel, the tip 33 of the inner plate 30 and the tip 34 of the outer plate 29 are edge-shaped, and the tip 35 of the girder 31 is also blade-shaped to facilitate insertion. . Here the two tips 33
, 34 so that their edges face each other (see the left end of Figure 7).
, the plasticizer 20 and earth and sand are introduced into the hollow part 32 so that the plate 22 can be easily inserted.

【0011】プレート中空部の土砂の排出(図8)プレ
ート22の差込みの終了後に、プレート22の中空部3
2に残った土砂や可塑剤20を完全にかき出す。例えば
ブラシでかき出し、水洗して残った土砂や可塑剤を完全
に除くようにする。
Discharging earth and sand from the hollow part of the plate (FIG. 8) After the insertion of the plate 22 is completed, the hollow part 3 of the plate 22
Completely scrape out the remaining soil and plasticizer 20. For example, scrape it out with a brush and wash it with water to completely remove any remaining dirt or plasticizer.

【0012】コンクリートの注入(図9)この後、リー
ドガイド柱12やプレート22の中空部32に、コンク
リート38を注入する。この結果、リードガイド柱12
やプレート22は鉄骨コンクリート構造体の骨格となる
。注入したコンクリート38は、桁31に設けた穴27
で隣の中空部32のコンクリートと結合する。またコン
クリート38の一部は穴24から地盤にしみ出し、外板
29の腐食を抑制するとともに、プレート22を地盤に
結合する役割も果たす。
Pouring Concrete (FIG. 9) After this, concrete 38 is poured into the hollow portions 32 of the lead guide columns 12 and plates 22. As a result, the lead guide column 12
The plate 22 becomes the skeleton of the steel concrete structure. The poured concrete 38 is poured into the hole 27 made in the girder 31.
It is joined to the concrete in the adjacent hollow part 32. In addition, a portion of the concrete 38 seeps into the ground through the holes 24, suppressing corrosion of the outer panel 29, and also serves to connect the plate 22 to the ground.

【0013】支柱の形成(図10) コンクリート38を注入するとプレート22の強度が増
し、土圧を支えられるようになる。2枚のプレート22
,22の間の部分を局所的に掘削し、支柱40や側壁(
仮壁)を構築し、プレート22の下部を全面的に掘削し
ても崩れないようにする。支柱40の本数や側壁の厚さ
は、土質に応じて定めれば良い。
Forming the Support Pillar (FIG. 10) When concrete 38 is poured, the strength of the plate 22 increases and it becomes able to support the earth pressure. two plates 22
, 22 was locally excavated, and the pillars 40 and side walls (
A temporary wall) is constructed to prevent collapse even if the entire lower part of the plate 22 is excavated. The number of pillars 40 and the thickness of the side walls may be determined depending on the soil quality.

【0014】地下空間の完成(図11)この後、プレー
ト22の間の地下空間を掘削し、地下空間42を完成す
る。側壁を44として示す。設けた地下空間42は、横
に1本あるいは複数本の地下空間を増設する、あるいは
地下空間42に直角の向きに地下空間を増設する際の作
業エリアとしても利用できる。
Completion of underground space (FIG. 11) After this, the underground space between the plates 22 is excavated to complete the underground space 42. The side wall is shown as 44. The provided underground space 42 can also be used as a work area when one or more underground spaces are added laterally, or when an underground space is added at right angles to the underground space 42.

【0015】地下空間42の延伸工程を図12に示す。 中央の2つの作業区画2,2間の地下空間42が完成す
ると、次の作業区画との間の地下空間を造出する。もち
ろん多数の作業区画2を同時に設け、全工区を同時に施
行しても良い。
The process of extending the underground space 42 is shown in FIG. When the underground space 42 between the two central work sections 2, 2 is completed, an underground space between the two work sections 2 and 2 is created. Of course, a large number of work sections 2 may be provided at the same time, and all the work sections may be executed at the same time.

【0016】地下空間の幅を広げるには、1本の地下空
間42が完成すると、リードガイド柱12を兼用しなが
ら隣接した地下空間42を設け、この間の土砂を排除し
て連続した一体の地下空間とすれば良い(図13)。
In order to widen the width of the underground space, once one underground space 42 is completed, an adjacent underground space 42 is created which also serves as the lead guide column 12, and the earth and sand between these spaces are removed to create a continuous, integrated underground space. It may be a space (Figure 13).

【0017】実施例の特徴と変形とを示す。先ず作業区
画2の掘削は例えば40m〜20m間隔で行えば良く、
掘削後は夜間のみ作業し、中間は蓋をしておけば、交通
等の障害とならない。作業区画2以外はオープンカット
しないので、地下空間42の上部に建物や鉄道の高架部
等があっても問題とならない。ガス管や水道管、下水管
等は通常地下2〜3mよりも浅い部分に埋設されており
、地下空間42は通常これよりも深く設けるので、ガス
管等が工事の妨げとならない。また他の建物の基礎や鉄
道の高架等がある場合には、これらの基礎よりも深く地
下空間42を設ければ良い。即ち作業区画2を設けるこ
とができれば、施行は容易である。実施例の工法は、大
都市での浅い地下部分での施行に適しているが、作業区
画2を深くすれば大深度での施行にも用いることができ
る。また作業区画2の間隔が短い場合には、一方の作業
区画2のみで作業を行い、他方の作業区画2へ向けて施
行する。作業区画2の間隔が大きい場合には、双方の作
業区画2,2から施行を進め、中央でドッキングさせる
ようにする。なおこの工法は、工区の一部をオープンカ
ットやシールド等の在来工法と組み合わせて用いても良
い。
[0017] Characteristics and modifications of the embodiment will be shown. First, excavation in work zone 2 may be carried out at intervals of 40 m to 20 m, for example.
After excavation, work should be done only at night, and if the area in between is covered, it will not cause an obstruction to traffic. Since no open cuts are made in areas other than the work zone 2, there is no problem even if there are buildings, elevated railway sections, etc. above the underground space 42. Gas pipes, water pipes, sewage pipes, etc. are usually buried shallower than 2 to 3 meters underground, and the underground space 42 is usually provided deeper than this, so the gas pipes etc. do not interfere with the construction work. Furthermore, if there are foundations of other buildings or elevated railroad tracks, the underground space 42 may be provided deeper than these foundations. That is, if the work section 2 can be provided, implementation is easy. The construction method of the embodiment is suitable for construction in shallow underground areas in large cities, but it can also be used in construction at great depths by making the work section 2 deeper. Further, when the intervals between the work sections 2 are short, the work is carried out only in one work section 2 and executed toward the other work section 2. If the distance between the work sections 2 is large, the work will be carried out from both work sections 2, 2, and docked at the center. Note that this construction method may be used in combination with conventional construction methods such as open cut and shield construction for part of the construction area.

【0018】次ぎにこの工法では、支柱40あるいは側
壁44ができるまで、地下空間42の掘削を行わない。 それまでの工程では、プレート22を地中に差し込むだ
けで、崩落の危険性がない。プレート22を土中に差し
込むのは困難であるが、土砂の可塑剤による改質を行い
、差込みを容易にする。差込み時のプレート22は、リ
ードガイド柱12に添わせ、精密に差し込む。
Next, in this construction method, the underground space 42 is not excavated until the pillars 40 or side walls 44 are constructed. In the process up to that point, the plate 22 is simply inserted into the ground, and there is no risk of it collapsing. Although it is difficult to insert the plate 22 into the soil, the soil is modified with a plasticizer to facilitate insertion. At the time of insertion, the plate 22 is aligned with the lead guide column 12 and inserted precisely.

【0019】この結果、実施例では余分の土砂の掘削が
なく、実際に地下空間42を設ける部分の土砂だけを掘
削すれば良い。掘削する土砂の量が少なく、ガス管等に
よる障害がなく、プレート22やリードガイド柱12を
ユニット化して量産できるので、この工法は経済的で、
かつ騒音も少ない。更にプレート22をユニット化でき
るので、現場で天板と床板とを施行する在来工法に比べ
、工期を短縮できる。
As a result, in this embodiment, there is no need to excavate excess earth and sand, and it is only necessary to excavate only the earth and sand in the area where the underground space 42 is to be provided. This construction method is economical because the amount of earth and sand to be excavated is small, there are no obstructions due to gas pipes, etc., and the plates 22 and lead guide columns 12 can be mass-produced as units.
And there is less noise. Furthermore, since the plate 22 can be made into a unit, the construction period can be shortened compared to the conventional construction method in which the top plate and floor plate are installed on site.

【0020】実施例ではプレート22を地下空間42の
上下に設けたが、プレート22の役割は支柱40や側壁
44の形成時の崩落を防止することで、上部のみにプレ
ート22を設けても良い。また正方形あるいは長方形の
地下空間42が望まれるので、プレート22は平らにし
たが、地下空間42の内部に向かって沿った半月状のプ
レートを用いても良い。
In the embodiment, the plates 22 are provided above and below the underground space 42, but the role of the plates 22 is to prevent the columns 40 and side walls 44 from collapsing when they are formed, and the plates 22 may be provided only at the top. . Further, since a square or rectangular underground space 42 is desired, the plate 22 is made flat, but a half-moon-shaped plate extending toward the inside of the underground space 42 may be used.

【0021】実施例2(図14〜図24)第2の実施例
として、アーチ型のプレートを用いたものを示す。この
実施例はプレートをアーチ型にすること以外は実施例1
と同様であり、実施例1に関する説明は特に示した点以
外は全てそのまま実施例2にも当てはまる。プレートを
アーチ型とすることの利点は、支柱の構築(図10)が
不用で、差し込んだプレートをそのまま地下空間の天井
と両壁に用い得ることにある。アーチ型のプレートを土
中に差込み、コンクリートでプレートの中空部を固めれ
ば、崩落の危険性はなく、プレート内部の土砂を掘削し
、床面を形成すれば地下空間を造出できる。プレートを
アーチ型とすることの問題点は、プレート断面積が増加
するため、プレートの差込みへの抵抗が大きいことにあ
る。そこで可塑剤20はプレートの差込み部の全面に対
して行い、プレートの入り込む部分の土砂を全面的に可
塑剤20で置換するものとする。以下に実施例の細部を
説明する。
Embodiment 2 (FIGS. 14 to 24) As a second embodiment, an arch-shaped plate is shown. This example is Example 1 except that the plate is arched.
The explanation regarding the first embodiment also applies to the second embodiment as is, except for the points specifically indicated. The advantage of having arch-shaped plates is that there is no need to construct supports (Fig. 10), and the inserted plates can be used as they are for the ceiling and both walls of the underground space. If an arch-shaped plate is inserted into the soil and the hollow part of the plate is solidified with concrete, there is no risk of it collapsing, and an underground space can be created by excavating the earth and sand inside the plate and forming a floor surface. The problem with having an arched plate is that the cross-sectional area of the plate is increased, which increases the resistance to insertion of the plate. Therefore, the plasticizer 20 is applied to the entire surface of the insertion part of the plate, and the earth and sand in the part where the plate enters is completely replaced with the plasticizer 20. The details of the embodiment will be explained below.

【0022】作業区画2の掘削工程は実施例1と同様に
行い、リードガイド柱12の差込み穴10は地下空間4
の下端部両端に掘削する(図14)。これはアーチ型の
プレートは断面積が大きいため、水平ではなく下にもぐ
ろうとする傾向があり、これをアーチ型プレートの両下
端に添わせたリードガイド柱12で矯正するためである
。もちろんリードガイド柱12は、両下端の2本の他に
、アーチ型プレートの変曲部(天井部と壁部の間の肩の
部分)等にも追加して設けても良い。次いで図15のよ
うにリードガイド柱12を差込む。リードガイド柱12
の構造を図16に示す。
The excavation process of the working section 2 was carried out in the same manner as in the first embodiment, and the insertion hole 10 of the lead guide column 12 was inserted into the underground space 4.
Excavate at both ends of the lower end (Figure 14). This is because the arch-shaped plate has a large cross-sectional area, so it tends to move downward rather than horizontally, and this is corrected by the lead guide pillars 12 attached to both lower ends of the arch-shaped plate. Of course, in addition to the two lead guide pillars 12 at both lower ends, additional lead guide pillars 12 may be provided at the bending part of the arched plate (the shoulder part between the ceiling part and the wall part). Next, the lead guide column 12 is inserted as shown in FIG. Lead guide pillar 12
The structure of is shown in FIG.

【0023】アーチ型プレートの差込み面の全面に可塑
剤20の注入穴18を掘削し、可塑剤20を注入する(
図17)。可塑剤20に特に好ましいものは粘土を油や
フタル酸ジオクチル等で被覆したもので、液状にしてあ
るいは円柱状等の成型体状にして、穴18に注入あるい
は差し込む。可塑剤20で土砂を置き換える部分はアー
チ型プレートの断面積よりもやや広くし、アーチ型プレ
ートが可塑剤20の中を滑って差し込まれるようにする
。また一度に全ての土砂を可塑剤で置換すると穴18が
圧潰するので、穴18を例えば交互に1つ置きに設け、
可塑剤20を注入した後、残りの穴18を掘削して可塑
剤20を注入する。
An injection hole 18 for the plasticizer 20 is drilled on the entire surface of the insertion surface of the arched plate, and the plasticizer 20 is injected (
Figure 17). A particularly preferred plasticizer 20 is clay coated with oil, dioctyl phthalate, etc., which is injected or inserted into the hole 18 in a liquid form or in the form of a cylindrical or other molded body. The part where the earth and sand are replaced by the plasticizer 20 is made slightly wider than the cross-sectional area of the arched plate so that the arched plate can be slid and inserted into the plasticizer 20. Also, if all the earth and sand is replaced with plasticizer at once, the holes 18 will be crushed, so the holes 18 are provided alternately, for example, every other hole.
After injecting the plasticizer 20, the remaining holes 18 are drilled and the plasticizer 20 is injected.

【0024】図18にアーチ型プレート122の継ぎ足
し部128を、図19に硬質鋼製の先端部126を示す
。アーチ型プレート122は外板129と肉厚の内板1
30を桁31で結合してアーチ型にし、外板129と内
板130の間に中空部32を設けたものである。もちろ
んこれ以外に、プレート122の肩の部分(天井部と両
側壁部との間の屈曲部)を補強するための梁等を設けて
も良い。またアーチ型プレート122の両下端にはR部
132を設けて、R部132がリードガイド柱12に添
いながら、プレート122が差し込まれるようにする。 更に外板129の表面には穴24を設け、土圧の低い部
分では、中空部32に入り込んだ可塑剤20が外に逃げ
て土圧を均一化し、土圧の高い部分では、外部の可塑剤
20が穴24からプレート122の中に逃げて土圧によ
る摩擦を軽減するようにする。穴24には、コンクリー
ト38の注入時にその一部を穴24から周囲に溢れさせ
てアーチ型プレート122を地盤に結合し、また溢れた
コンクリートで外板129の表面を覆わせて腐食を抑制
する役割もある。桁31には穴27を設け、コンクリー
ト38が桁31に妨げられずに一体に結合するようにす
る。アーチ型のプレート122の先端部126では、外
板129や内板130,桁31に、エッジ状の先端部3
4,33,35を設け、可塑剤20中に容易に差し込ま
れるようにする。またエッジ34,33は互いに向き合
うエッジとし、可塑剤20が中空部38に入り込むよう
にする。
FIG. 18 shows the extension 128 of the arched plate 122, and FIG. 19 shows the hard steel tip 126. The arched plate 122 has an outer plate 129 and a thick inner plate 1.
30 are connected by girders 31 to form an arch shape, and a hollow part 32 is provided between the outer plate 129 and the inner plate 130. Of course, in addition to this, a beam or the like may be provided to reinforce the shoulder portion of the plate 122 (the bent portion between the ceiling portion and both side wall portions). Furthermore, R portions 132 are provided at both lower ends of the arched plate 122, so that the plate 122 is inserted while the R portions 132 follow the lead guide column 12. Furthermore, holes 24 are provided on the surface of the outer panel 129, so that in areas where the earth pressure is low, the plasticizer 20 that has entered the hollow part 32 escapes to the outside and equalizes the earth pressure, and in areas where the earth pressure is high, the plasticizer 20 from the outside is removed. The agent 20 escapes from the hole 24 into the plate 122 to reduce friction due to earth pressure. When concrete 38 is poured into the hole 24, a portion of it overflows from the hole 24 to the surrounding area to connect the arched plate 122 to the ground, and also covers the surface of the outer panel 129 with the overflowing concrete to suppress corrosion. It also has a role. Holes 27 are provided in the girder 31 to allow the concrete 38 to join the girder 31 unhindered. At the tip 126 of the arch-shaped plate 122, an edge-shaped tip 3 is attached to the outer plate 129, the inner plate 130, and the girder 31.
4, 33, and 35 are provided so that they can be easily inserted into the plasticizer 20. Furthermore, the edges 34 and 33 face each other so that the plasticizer 20 enters the hollow portion 38.

【0025】次いで油圧等により、アーチ型プレート1
22を可塑剤20中に差し込む(図20)。この作業は
、油圧装置を備えた土木機械を作業区画2に降ろして行
う。この機械には、リードガイド柱12の差込み穴10
や可塑剤注入穴18の掘削装置、リードガイド柱12の
油圧による差込み装置、あるいは可塑剤20の注入装置
等を一体化し、全ての作業を一台の土木機械で行えるよ
うにするのが好ましい。可塑剤20は、プレート122
よりも広い面積で注入してある。このためプレート先端
のエッジ33,34,35は可塑剤20中に差し込まれ
、外板129や内板130も可塑剤20の中を滑りなが
ら差し込まれる。この結果、プレート122の先端が受
ける抵抗だけでなく、上下左右の地盤からの土圧による
抵抗も減少する。可塑剤20はエッジ33,34が向か
い合う向きなので(図19)、プレート先端の可塑剤2
0はプレート122の中に引き込まれる。このため可塑
剤20は中空部32に入り込み、プレート122を差し
込んでも可塑剤20の層の厚さが膨らまないので、差込
み時の抵抗を小さくできる。プレート122が可塑剤2
0に差し込まれると、可塑剤20から油がしみだし、可
塑剤20の粘土粒子相互の結合が破壊されて、可塑剤2
0の流動性が増す。この結果プレート122の先端部1
26での抵抗が減少する。これは一種のチクソトロピー
であるが、可塑剤20の流動性を増すため、例えばプレ
ート122に超音波等の振動を加えながら差込みを行い
、超音波で粘土粒子相互の結合を弱め油のしみだしを促
進しても良い。しみだした油はプレート122の表面に
油膜を作り、上下左右の地盤からの土圧による摩擦抵抗
を減少させる。またプレート122の外板129や内板
130等にフタル酸ジオクチル等の可塑剤層を塗布して
置き、可塑剤層が剥離しながら抵抗を弱めるようにして
も良い。可塑剤20は、注入穴(図17)の奥程軟質で
手前程硬質である。奥に進む程プレート122への抵抗
が強くなるので、注入穴18の奥で可塑剤20が軟質と
なることは、プレート122の差込みを容易にする。 プレート122の継ぎ足し部128は、例えばはめ合わ
せやボルトナット止め、あるいは溶接等で結合し、一体
のプレート122とする。
[0025] Then, by hydraulic pressure or the like, the arch-shaped plate 1 is
22 into the plasticizer 20 (FIG. 20). This work is carried out by lowering a civil engineering machine equipped with a hydraulic system into the work area 2. This machine has an insertion hole 10 in the lead guide column 12.
It is preferable to integrate the excavating device for the plasticizer injection hole 18, the hydraulic insertion device for the lead guide column 12, the injection device for the plasticizer 20, etc., so that all the work can be performed by one civil engineering machine. The plasticizer 20 is attached to the plate 122
It is injected over a wider area. Therefore, the edges 33, 34, and 35 at the front ends of the plates are inserted into the plasticizer 20, and the outer plate 129 and the inner plate 130 are also inserted while sliding in the plasticizer 20. As a result, not only the resistance to which the tip of the plate 122 is subjected, but also the resistance due to earth pressure from the ground on the upper, lower, right and left sides is reduced. Since the edges 33 and 34 of the plasticizer 20 face each other (Fig. 19), the plasticizer 20 at the tip of the plate
0 is drawn into plate 122. Therefore, the plasticizer 20 enters the hollow portion 32, and even when the plate 122 is inserted, the thickness of the plasticizer 20 layer does not swell, so that the resistance at the time of insertion can be reduced. Plate 122 is plasticizer 2
0, oil seeps out from the plasticizer 20, the bond between the clay particles of the plasticizer 20 is broken, and the plasticizer 2
0 fluidity increases. As a result, the tip 1 of the plate 122
The resistance at 26 is reduced. This is a type of thixotropy, but in order to increase the fluidity of the plasticizer 20, for example, the plate 122 is inserted while applying vibrations such as ultrasonic waves, and the ultrasonic waves weaken the bonds between clay particles and prevent oil from seeping out. May be promoted. The oil that has seeped out forms an oil film on the surface of the plate 122, reducing frictional resistance due to earth pressure from the ground above, below, and to the left and right. Alternatively, a layer of plasticizer such as dioctyl phthalate may be coated on the outer plate 129, inner plate 130, etc. of the plate 122, and the resistance may be weakened as the plasticizer layer peels off. The plasticizer 20 is soft toward the back of the injection hole (FIG. 17) and hard toward the front. Since the resistance to the plate 122 becomes stronger as it goes deeper, the softening of the plasticizer 20 in the depths of the injection hole 18 facilitates the insertion of the plate 122. The additional portions 128 of the plate 122 are connected, for example, by fitting, bolts and nuts, or welding, to form an integral plate 122.

【0026】プレート122の差込み後に、可塑剤20
をかき出し、水洗して残った可塑剤20を除く(図21
)。次いでコンクリート38をアーチ型のプレート12
2の中空部32に注入し、鉄骨コンクリートの構造体と
する(図22)。この結果、地下空間の天井と両壁面と
が得られる。コンクリート38が硬化すると、アーチ型
のプレート122は土圧に耐えることができ、内部を掘
削しても崩落の危険性はない。そこで内部の土砂を掘削
し(図23)、コンクリート等の床面140を設ければ
地下空間が完成する(図24)。コンクリート38の硬
化後に、プレート122の内板130の表面を塗装する
と、地下空間4の天井や両側壁として利用できる。
After inserting the plate 122, the plasticizer 20
Scrape it out and wash it with water to remove the remaining plasticizer 20 (Figure 21
). The concrete 38 is then placed on the arched plate 12.
It is injected into the hollow part 32 of No. 2 to form a steel concrete structure (FIG. 22). As a result, a ceiling and both wall surfaces of the underground space are obtained. Once the concrete 38 has hardened, the arched plate 122 can withstand earth pressure and there is no risk of it collapsing even if the interior is excavated. Therefore, the underground space is completed by excavating the earth and sand inside (FIG. 23) and providing a floor surface 140 of concrete or the like (FIG. 24). After the concrete 38 has hardened, if the surface of the inner plate 130 of the plate 122 is painted, it can be used as the ceiling or both side walls of the underground space 4.

【0027】[0027]

【発明の効果】この発明の工法では、以下の効果が得ら
れる。 (1)  実際に地下空間とする部分のみの土砂を掘削
するため、表土の搬出、埋め戻しの必要がない。 (2)  工事の過程で地上に表れるのは作業区画のみ
で、作業区画は間隔を置いて設け、かつ昼間は蓋をでき
る大きさなので、地上活動を妨げることなく施行ができ
る。 (3)  プレートやリードガイド柱等をユニット化し
て量産できるので、工期が短い。 (4)  地上に表れるのが作業区画のみで、掘削搬出
する土砂が少ないため、騒音が少ない。 (5)  作業区画を設けることができれば、ガス管や
建物の基礎等の既存の埋設物が工事の障害にならない。 (6)  崩落の危険性がないので安全である。 (7)  工期が短く掘削する土砂が少なくユニット化
が容易なため、経済的である。
[Effects of the Invention] The construction method of the present invention provides the following effects. (1) Since the earth and sand are excavated only in the area that will actually be used as underground space, there is no need to remove or backfill the topsoil. (2) During the construction process, only the work zones will be visible on the ground, and the work zones will be set up at intervals and are large enough to be covered during the day, so construction can be carried out without interfering with ground activities. (3) Since plates, lead guide columns, etc. can be mass-produced as units, the construction period is short. (4) Only the work area is visible above the ground, and there is less earth and sand to be excavated and transported, so there is less noise. (5) If a work zone can be established, existing buried objects such as gas pipes and building foundations will not interfere with construction work. (6) It is safe because there is no risk of collapse. (7) It is economical because the construction period is short, there is less earth and sand to be excavated, and unitization is easy.

【図面の簡単な説明】[Brief explanation of the drawing]

【図1】実施例での横穴堀り用作業区画の掘削工程の斜
視図である。
FIG. 1 is a perspective view of the excavation process of a work section for horizontal hole digging in an embodiment.

【図2】実施例でのプレート用リードガイド柱差込み穴
の掘削工程の斜視図である。
FIG. 2 is a perspective view of the process of drilling a hole for inserting a lead guide column for a plate in the embodiment.

【図3】実施例でのプレート用リードガイド柱埋め込み
工程の斜視図である。
FIG. 3 is a perspective view of the plate lead guide pillar embedding process in the example.

【図4】実施例でのプレート差込み部の土質改良工程の
斜視図である。
FIG. 4 is a perspective view of the soil improvement process of the plate insertion part in the example.

【図5】実施例でのプレート差込み工程の斜視図である
FIG. 5 is a perspective view of the plate insertion process in the example.

【図6】実施例でのプレートの斜視図である。FIG. 6 is a perspective view of a plate in an example.

【図7】実施例でのプレート先端部の断面図である。FIG. 7 is a sectional view of the tip of the plate in the example.

【図8】実施例でのプレート中空部の土砂の排除工程の
斜視図である。
FIG. 8 is a perspective view of the step of removing earth and sand from the hollow part of the plate in the example.

【図9】実施例でのプレート中空部へのコンクリートの
注入工程の斜視図である。
FIG. 9 is a perspective view of the process of pouring concrete into the hollow part of the plate in the example.

【図10】実施例での支柱と側壁の構築工程の斜視図で
ある。
FIG. 10 is a perspective view of the construction process of the pillar and side wall in the example.

【図11】実施例での完成した地下空間の斜視図である
FIG. 11 is a perspective view of the completed underground space in the example.

【図12】実施例での地下空間の延長工程の斜視図であ
る。
FIG. 12 is a perspective view of the underground space extension process in the example.

【図13】実施例での地下空間の横方向への拡張工程の
斜視図である。
FIG. 13 is a perspective view of the step of expanding the underground space in the lateral direction in the example.

【図14】第2の実施例での、プレート用リードガイド
柱差込み穴の掘削工程の斜視図である。
FIG. 14 is a perspective view of the step of drilling a hole for inserting a lead guide column for a plate in the second embodiment.

【図15】第2の実施例での、プレート用リードガイド
柱埋め込み工程の斜視図である。
FIG. 15 is a perspective view of the plate lead guide pillar embedding process in the second embodiment.

【図16】リードガイド柱の接続工程の斜視図である。FIG. 16 is a perspective view of the process of connecting lead guide columns.

【図17】第2の実施例での、プレート差込み部の土質
改良工程の斜視図である。
FIG. 17 is a perspective view of the soil improvement process of the plate insertion part in the second embodiment.

【図18】第2の実施例での、アーチ型プレートの斜視
図である。
FIG. 18 is a perspective view of an arched plate in a second embodiment.

【図19】第2の実施例での、アーチ型プレート先端部
の要部斜視図である。
FIG. 19 is a perspective view of the main part of the arched plate tip in the second embodiment.

【図20】第2の実施例での、アーチ型プレート差込み
工程の斜視図である。
FIG. 20 is a perspective view of the arch-shaped plate insertion process in the second embodiment.

【図21】第2の実施例での、アーチ型プレート中空部
の土砂の排除工程の斜視図である。
FIG. 21 is a perspective view of the step of removing earth and sand from the hollow portion of the arch-shaped plate in the second embodiment.

【図22】第2の実施例での、アーチ型プレート中空部
へのコンクリートの注入工程の斜視図である。
FIG. 22 is a perspective view of the process of pouring concrete into the hollow part of the arched plate in the second embodiment.

【図23】第2の実施例での、アーチ型プレート中空部
の土砂排除工程の斜視図である。
FIG. 23 is a perspective view of the process of removing earth and sand from the hollow part of the arch-shaped plate in the second embodiment.

【図24】第2の実施例での、完成した地下空間の斜視
図である。
FIG. 24 is a perspective view of a completed underground space in the second embodiment.

【符号の説明】[Explanation of symbols]

2  作業区画 4  地下空間の形成部 6  矢板 7  支持板 10  リードガイド柱差込み穴 12  リードガイド柱 20  可塑剤 22,122  プレート 24  穴 26,126  プレートの先端部 27  穴 28,128  プレートの継ぎ足し部29,129 
 外板 30,130  内板 31  桁 32  中空部 33,34,35  エッジ部 38  コンクリート 40  支柱 42  地下空間 44  側壁 140  床面
2 Work section 4 Underground space formation part 6 Sheet pile 7 Support plate 10 Lead guide post insertion hole 12 Lead guide post 20 Plasticizer 22, 122 Plate 24 Hole 26, 126 Plate tip 27 Hole 28, 128 Plate addition part 29 ,129
Outer panel 30, 130 Inner panel 31 Girder 32 Hollow section 33, 34, 35 Edge section 38 Concrete 40 Support column 42 Underground space 44 Side wall 140 Floor surface

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】  作業空間を掘削する工程と、掘削した
作業空間から形成目標の地下空間に沿ってリードガイド
を差し込む工程と、差し込んだリードガイドにより方向
を定めながらプレートを形成目標の地下空間の天井部に
沿って差し込む工程と、プレートの下部を掘削し地下空
間を造出する工程とを設けた、地下空間の造出方法。
Claim 1: A step of excavating a work space, a step of inserting a lead guide from the excavated work space along the underground space to be formed, and a step of forming a plate while determining the direction by the inserted lead guide. A method for creating an underground space that includes a process of inserting the plate along the ceiling and a process of excavating the lower part of the plate to create an underground space.
【請求項2】  前記のプレートをアーチ型のプレート
とし、このプレートにより地下空間の天井部と両側面部
とを形成することを特徴とする、請求項1に記載の地下
空間の造出方法。
2. The method for creating an underground space according to claim 1, wherein the plate is an arch-shaped plate, and the plate forms a ceiling portion and both side surfaces of the underground space.
JP3075668A 1991-03-14 1991-03-14 Method for constructing underground space Pending JPH04285297A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3075668A JPH04285297A (en) 1991-03-14 1991-03-14 Method for constructing underground space

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3075668A JPH04285297A (en) 1991-03-14 1991-03-14 Method for constructing underground space

Publications (1)

Publication Number Publication Date
JPH04285297A true JPH04285297A (en) 1992-10-09

Family

ID=13582820

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3075668A Pending JPH04285297A (en) 1991-03-14 1991-03-14 Method for constructing underground space

Country Status (1)

Country Link
JP (1) JPH04285297A (en)

Similar Documents

Publication Publication Date Title
KR102153902B1 (en) Slurry wall, construction method for the same and wire mesh assembly
CN106759463A (en) A kind of hypogee and its construction method
JPS60500875A (en) Method and device for constructing reinforced concrete walls underground
JP3893056B2 (en) Construction method of underground structure
JP3829319B2 (en) Construction method of underground hollow structure and its underground hollow structure
KR200362565Y1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof
KR102072889B1 (en) Construction method of smallcaliber composite pile wall using small drilling rig at adjacent building proximity section
JPH0663239B2 (en) Izutsu for landslide prevention and its construction method
JPH04285297A (en) Method for constructing underground space
JPH04285300A (en) Method for constructing underground space
JPH04285298A (en) Method for constructing underground space
JPH06306853A (en) Construction of underground structure
JPH04285299A (en) Method for constructing underground space
KR100654973B1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof
JPS6011178B2 (en) How to install standard piles for continuous underground wall construction
JP2005146756A (en) Earth retaining impervious wall construction method and earth retaining impervious wall formed by it
JPH07139300A (en) Method for constructing underground construction
KR102610909B1 (en) Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking
KR102184081B1 (en) Construction method for perforating goround bore using inverse casing
JPH07150569A (en) Water shielding construction method for underground continuous wall
KR101352429B1 (en) Water-proofing type temporary soil sheathing construction method using crrugated steel plate segments
JPH09111754A (en) Soldier pile cut-of wall construction method
KR102243585B1 (en) Structure of constructing non-excavation type tunnel using steel pipe loof and leading pipe
JP2555838B2 (en) Independent panel mountain retaining method
KR102371284B1 (en) Slurry wall, construction method for the same and wire mesh assembly