JPH04203028A - Reverse driving method for underground building - Google Patents

Reverse driving method for underground building

Info

Publication number
JPH04203028A
JPH04203028A JP2330340A JP33034090A JPH04203028A JP H04203028 A JPH04203028 A JP H04203028A JP 2330340 A JP2330340 A JP 2330340A JP 33034090 A JP33034090 A JP 33034090A JP H04203028 A JPH04203028 A JP H04203028A
Authority
JP
Japan
Prior art keywords
pile
piles
ready
ground
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2330340A
Other languages
Japanese (ja)
Other versions
JP2567990B2 (en
Inventor
Masahide Tanimaru
谷丸 正英
Yoshihiro Fujita
佳広 藤田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Mitani Sekisan Co Ltd
Original Assignee
Obayashi Corp
Mitani Sekisan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp, Mitani Sekisan Co Ltd filed Critical Obayashi Corp
Priority to JP2330340A priority Critical patent/JP2567990B2/en
Publication of JPH04203028A publication Critical patent/JPH04203028A/en
Application granted granted Critical
Publication of JP2567990B2 publication Critical patent/JP2567990B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE:To shorten a term of works and to reduce the cost by a method wherein an existing pile to which a concrete pile with an outer shell steel pipe is connected is used as a high strength pile, the existing pile is driven in a ground, and a structure main column is erected on the existing pile. CONSTITUTION:Ordinary excavation is carried out down to an underground first floor, a hole 2 for placing a pile is excavated in a given position from a ground 1, and stabilizing liquid (a) is poured in the hole 2. A concrete pile with an outer shell steel pipe which is covered with a steel pipe is used in the hole 2 and as a high strength pile 3 and an existing pile 4 to which a steel pipe pile 5 is connected is driven therein. A pipe is inserted in the pile 5, the portion in the vicinity of a bottom part of the pile 5 is filled with a foundation solidifying liquid (b), and a structure main column 6 is driven in a pile 5 part. Level precision is ensured by fixed installation of the pile 6, and simultaneously with ground construction at the upper part of the column 6, construction is carried out from the upper layer toward the lower layer of an underground floor. This method shortens the term of works and reduce the cost.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は地下構築用逆打工法に係り、特に、高強度杭に
外殻鋼管付きコンクリート抗または鋼管杭を接続して構
成した既製杭を使用した地下構築用逆打工法に関する。
[Detailed Description of the Invention] (Industrial Application Field) The present invention relates to a reverse driving method for underground construction, and in particular to a ready-made pile constructed by connecting a high-strength pile with a concrete shaft with an outer shell steel pipe or a steel pipe pile. Regarding the reverse pouring method used for underground construction.

(従来の技術) 一般に地階を有する建物の構築を行う場合、予め建物全
体の基礎下端までの根伐を行い、最下層となる地階の基
礎コンクリートを打設した後、例えば地下4階、同3階
、同2階、同1階、地上1階というように、下層から上
層へとコンクリートを打設しっつ構築を行っている。
(Prior art) Generally, when constructing a building with a basement, the roots of the entire building are cut down to the bottom of the foundation in advance, and the foundation concrete for the lowest basement floor is poured. The building is being constructed from the bottom to the top, with concrete being poured from the bottom to the top, starting with the first floor, second floor, first floor, and first floor above ground.

ところが、このような順打ち工法においては、地下部分
構築後に地上部分を構築しなければならす工期が長くな
るため、近年、逆打工法が多く使用されるようになって
きている。逆打工法は、建物の柱を立設すべき地面の所
定位置に予め基礎杭を打ち、該基礎杭の上に建込んだ構
真柱の上部での地上施工と同時に、従来とは逆に根伐お
よびコンクリート打設を地階上層から下層に向って行う
工法である。例えばコンクリート打設を行う地下部分か
純鉄筋構造(RC構造)、地上部分か鉄骨・鉄筋コンク
リート構造(SRC構造)の場合、ます地表面から柱と
なる位置に縦穴を掘削し、コンクリート注入により基礎
杭を作る。このようにして構成される基礎杭は通常、場
所打杭と呼ばれる。この基礎杭の上に、仮の支柱である
構真柱を立て、この構真柱の上から上部の鉄骨を立てて
地上部分の施工を行うと同時に、地下部分の根伐を行い
、上層階から下層階に向って地下部分を徐々にコンクリ
ート打設して、施工するものである。
However, in such a forward pouring method, the construction period required to construct the above-ground portion after the underground portion is constructed becomes long, so in recent years, the reverse pouring method has been increasingly used. In the reverse driving method, foundation piles are driven in advance at predetermined positions on the ground where building columns are to be erected, and at the same time ground construction is carried out on the top of the structural pillars erected on top of the foundation piles. This method involves cutting down roots and pouring concrete from the upper basement level to the lower level. For example, in the case of an underground part or pure reinforced concrete structure (RC structure) where concrete is poured, or an above ground part or steel reinforced concrete structure (SRC structure), a vertical hole is drilled from the ground surface to the position where the column will be placed, and the foundation pile is poured by concrete. make. Foundation piles constructed in this way are usually called cast-in-place piles. On top of these foundation piles, we will erect temporary pillars, or structure pillars, and then erect the upper steel frame on top of these pillars to construct the above-ground section. At the same time, we will cut down the roots of the underground section, and Construction is carried out by gradually pouring concrete into the underground section from the beginning to the lower floors.

このような逆打工法によると、地上部分と地下部分とか
同時に施工できるので、工期短縮を有効に図れる。
According to such a reverse construction method, the above-ground and underground sections can be constructed at the same time, thereby effectively shortening the construction period.

(発明が解決しようとする課題) ところで従来の逆打工法では、基礎杭として場所打杭が
使用されており、この場所打杭に4RM柱か建込まれて
いる。また直接基礎の場合でも、仮設として場所打杭を
打設していた。
(Problems to be Solved by the Invention) In the conventional reverse driving method, a cast-in-place pile is used as a foundation pile, and a 4RM column is erected on this cast-in-place pile. Even in the case of direct foundations, cast-in-place piles were driven as temporary construction.

しかし、場所打杭の形成自体においても一定の工期がか
かり、かつコスI・もかかることから、さらに工期短縮
および低コスト化の余地かある。
However, since the formation of cast-in-place piles itself takes a certain amount of time and costs I, there is room for further shortening the construction time and lowering costs.

本発明はこのような事情に鑑みてなされたもので、従来
に比して、なお−層の工期短縮および低コスト化か図れ
る地下構築用逆打工法を提供することを目的とする。
The present invention has been made in view of the above circumstances, and it is an object of the present invention to provide a reverse pouring method for underground construction that can shorten the construction period and reduce the cost of construction of layers compared to the conventional method.

(課題を解決するための手段) 本発明は、地階を有する建物の地下構築に際し、該建物
の柱を立設すべき地面の所定位置に予め基礎杭を打ち、
該基礎杭の上に建込んだ構真柱の上部ての地上施工と同
時に、根伐および地階上層から下層に向うコンクリート
打設を行う地下構築用逆打工法において、上記基礎杭と
して、高強度杭に鋼管杭を接続した既製杭を使用し、該
既製杭を地中に打込んだ後、該既製杭の上へ構真柱を建
込むようにしたことを特徴とする。
(Means for Solving the Problems) When constructing a building having a basement underground, the present invention includes driving foundation piles in advance at predetermined positions on the ground where pillars of the building are to be erected,
In the reverse pouring method for underground construction, which involves cutting the roots and pouring concrete from the upper basement level to the lower level at the same time as above-ground construction of the upper part of the structural pillars erected on the foundation piles, high-strength The present invention is characterized in that a ready-made pile in which a steel pipe pile is connected to the pile is used, and after the ready-made pile is driven into the ground, a structural pillar is erected on top of the ready-made pile.

まt:本発明は、地階を有する建物の地下構築に際し、
該建物の柱を立設すべき地面の所定位置に予め基礎杭を
打ち、該基礎杭の上に建込んだ構真柱の上部での地上施
工と同時に、根伐および地階上層から下層に向うコンク
リート打設を行う地下構築用逆打工法において、上記基
礎杭として、高強度杭に外殻鋼管付きコンクリート杭を
接続した既製杭を使用し、該既製杭を地中に打込んだ後
、該既製杭の上へ構真柱を建込むようにしたことを特徴
とする。
Mat: The present invention provides for underground construction of a building having a basement,
Foundation piles are driven in advance at predetermined positions on the ground where the pillars of the building are to be erected, and at the same time as ground construction is carried out on the upper part of the structural pillars erected on top of the foundation piles, root cutting and work is carried out from the upper basement level to the lower level. In the reverse driving method for underground construction in which concrete is placed, ready-made piles consisting of high-strength piles and concrete piles with outer shell steel pipes are used as the foundation piles, and after the ready-made piles are driven into the ground, It is characterized by the structure pillars being built on top of ready-made piles.

さらに、上記既製杭へ根固め固定液を注入して、上記構
真柱を固定設置するようにしたことを特徴とする。
Furthermore, the structure pillar is fixedly installed by injecting a foot hardening fixing liquid into the ready-made pile.

(作 用) 上述した本発明の工法によれば、高強度杭に外殻鋼管付
きコンクリート杭または鋼管杭を接続した既製杭を、基
礎杭として使用するので、比較的大掛かりな地下掘削を
伴う場所打杭を使用する場合に比へて、−層の工期短縮
および低コスト化か図れるものとなる。
(Function) According to the construction method of the present invention described above, prefabricated piles in which concrete piles with outer shell steel pipes or steel pipe piles are connected to high-strength piles are used as foundation piles, so they can be used in locations that require relatively large-scale underground excavation. Compared to the case of using driven piles, the construction period and cost of the -layer can be shortened and costs reduced.

既製杭を構成する高強度抗としては、十分な強度を有す
る杭であれば、PC杭、PHC杭並びに外殻鋼管付きコ
ンクリート杭等の他、様々な杭を採用することかでき、
その形成法としても遠心力成型によるものなと、種々の
成型法によるものを採用することかできる。
As the high-strength shafts that make up the ready-made piles, various piles can be used as long as they have sufficient strength, such as PC piles, PHC piles, and concrete piles with outer shell steel pipes.
As for its formation method, centrifugal force molding or various molding methods can be employed.

また既製杭の上へ建込んだ構真柱は、既製杭へ根固め固
定液を注入して固定設置されるので、構真柱の位置決め
および保持も確実である。
Furthermore, since the structural pillars built on top of ready-made piles are fixed by injecting the foundation hardening fixative into the ready-made piles, the positioning and holding of the structural pillars is also reliable.

(実 施 例) 以下、本発明の実施例を第1図を参照して説明する。(Example) Embodiments of the present invention will be described below with reference to FIG.

本実施例では基本的には、地階を有する建物の地下構築
に際し、建物の柱を立設すべき地面の所定位置に予め基
礎杭を打ち、基礎杭の上に建込んだ構真柱の上部での地
上施工と同時に、根伐および地階上層から下層に向うコ
ンクリ−1・打設を行う地下構築用逆打工法において、
基礎杭として、亮強度杭3に鋼管杭5を接続した既製杭
4を使用し、既製杭4を地中に打込んだ後、既製杭4の
上へ横真柱6を建込むようにしている。また、既製杭4
の中へ根固め固定液すを注入して構真柱6を固定設置す
るようにしている。
In this example, basically, when constructing a building with a basement underground, foundation piles are driven in advance at predetermined positions on the ground where the pillars of the building are to be erected, and the upper part of the structural pillars erected on top of the foundation piles is used. In the reverse pouring method for underground construction, which involves cutting the roots and pouring concrete from the upper basement level to the lower level at the same time as above-ground construction,
A ready-made pile 4 in which a steel pipe pile 5 is connected to a light-strength pile 3 is used as a foundation pile, and after the ready-made pile 4 is driven into the ground, a horizontal straight column 6 is erected on top of the ready-made pile 4. In addition, ready-made piles 4
The structure pillar 6 is fixedly installed by injecting a foot hardening fixing solution into the hole.

建物で杭基礎の場合、地層の状態、施工性、コストおよ
び工期等を考慮して、既製杭4て設計される場合は多い
。しかも最近ては既製杭4の杭径も大型化し、Φ800
〜Φ1000等の既製杭4が使用されることもある。
In the case of a pile foundation for a building, ready-made piles 4 are often designed in consideration of the condition of the strata, workability, cost, construction period, etc. Moreover, recently, the diameter of ready-made pile 4 has also increased to Φ800.
Ready-made piles 4 such as ~Φ1000 may be used.

したがって、既製杭4をそのまま利用して逆打工法を採
ることも十分可能である。
Therefore, it is fully possible to use the ready-made piles 4 as they are and use the reverse driving method.

なお、本実施例では地下1階以上かSRC構造、地下2
階以下がRC構造の建物の構築について説明されている
In addition, in this example, the floor above the basement level, the SRC structure, the second basement floor
The construction of a building with an RC structure below the floors is explained.

まず、地下1階まで通常の根伐を行う。そして、建物支
柱を立設すべき所定位置に、地表面]から杭設置用の穴
2を各種flai削工法によって1′It1]則する。
First, perform regular root cutting down to the first basement floor. Then, holes 2 for installing piles are drilled from the ground surface at predetermined positions where building supports are to be erected using various flaying methods.

なお、穴2か崩れないよう、ベントナイト等の安定液a
を穴2内に注入する。
In addition, to prevent hole 2 from collapsing, add a stabilizer such as bentonite a.
Inject into hole 2.

この穴2に、基礎杭として既製杭4を打込み、必要な芯
出しを行う。本実施例ではこの既製杭4は、高強度杭3
として鋼管被覆を施した外殻鋼管付きコンクリート柱を
使用し、これに鋼管杭5を接続して構成されている。高
強度抗3としては、この他十分な強度を有する杭であれ
は、PC抗。
A ready-made pile 4 is driven into this hole 2 as a foundation pile, and necessary centering is performed. In this embodiment, this ready-made pile 4 is a high-strength pile 3
A concrete column with a steel pipe outer shell coated with a steel pipe is used as a concrete pillar, and a steel pipe pile 5 is connected to this. Other high-strength piles with sufficient strength are PC piles.

PHC杭等、様々な杭を採用することかでき、その形成
法としても遠心力成型によるものなと、種々の成型法に
よるものを採用することかできる。
Various types of piles such as PHC piles can be used, and their formation methods can include centrifugal force molding and various other molding methods.

なお、7は補強プレートである。Note that 7 is a reinforcing plate.

そして、このように構成された既製杭4を地中に打込ん
だ後、この既製杭4の上に構真柱6を建込む。これに先
立ち、パイプまたはホース等を鋼管杭5部分の中へ挿入
し、鋼管杭5の底部付近に根固め固定液すを充填してお
(。そして、この鋼管杭5部分へ構真柱6を建込むよう
にする。
After the ready-made pile 4 configured as described above is driven into the ground, the structural pillar 6 is erected on top of the ready-made pile 4. Prior to this, a pipe or hose, etc. is inserted into the steel pipe pile 5 section, and a foot hardening fixing solution is filled near the bottom of the steel pipe pile 5. I will try to build it up.

このようにして、鋼管杭5の中へ根固め固定液すを注入
して構真柱6を固定設置することにより、レベル精度を
羅保するとともに、鋼管杭5、ひいては既製杭4と構真
柱6とを一体化させる。
In this way, by injecting the foot hardening fixing solution into the steel pipe pile 5 and fixing the structure pillar 6, the level accuracy is maintained, and the steel pipe pile 5, and by extension the ready-made pile 4, and the structure pillar 6 are fixedly installed. Integrate with pillar 6.

この後、構真柱6の上部での地上施工と同時に、根伐お
よび地階上層から下層に向う施工を行う。
After this, at the same time as above-ground construction on the upper part of the structure pillar 6, root cutting and construction from the upper basement floor to the lower floor are performed.

以上の本実施例によれば、逆打工法で要求される支持力
か、既製杭4のΦ800〜Φ1000て可能な200 
t〜300tてあれば、従来のような場所打杭を利用す
る必要なく、比較的ローコストで対応できることが確認
された。
According to the above-mentioned embodiment, the bearing capacity required by the reverse driving method is 200 mm, which is possible with the diameter of Φ800 to Φ1000 of the ready-made pile 4.
It was confirmed that if the weight is 300 tons, there is no need to use conventional cast-in-place piles, and it can be done at a relatively low cost.

また、本実施例によれば、高強度杭3に鋼管杭5を接続
した既製杭4を基礎杭として使用するので、比較的大掛
かりな地下掘削等を伴う場所打杭を使用する場合に比べ
て、なお−層の工期短縮および低コスト化か図れるもの
となる。
Furthermore, according to this embodiment, ready-made piles 4, which are high-strength piles 3 and steel pipe piles 5 connected, are used as foundation piles, so compared to the case where cast-in-place piles are used, which requires relatively large-scale underground excavation, etc. Furthermore, it is possible to shorten the construction period and reduce the cost of the layer.

また既製杭4の上へ建込んだ構真柱6は、鋼管杭5の中
へ根固め固定液すを注入して固定設置されるので、構真
柱6の位置決めおよび保持も確実である。
Moreover, since the structural pillars 6 built on top of the ready-made piles 4 are fixedly installed by injecting the hardening fixing liquid into the steel pipe piles 5, the positioning and holding of the structural pillars 6 is also reliable.

なお、前記実施例では、既製杭4として高強度杭3に鋼
管杭5を接続したものを適用したが、本発明はこれに限
らす、高強度抗3に外殻鋼管付きコンクリート杭を接続
したものなと、各種既製杭を適用できることは勿論であ
り、このような場合にも同様な効果を発揮する。
In addition, in the above-described embodiment, a high-strength pile 3 connected to a steel pipe pile 5 was used as the ready-made pile 4, but the present invention is not limited to this. Of course, various ready-made piles can be used, and similar effects can be achieved in such cases as well.

(発明の効果) 以上のように本発明によれば、基礎杭として、高強度杭
に外殻鋼管付きコンクリート抗または鋼管杭を接続した
既製杭を使用するので、比較的大掛かりな地下掘削を伴
う場所打杭を使用する場合に比べて、なお−層の工期短
縮および低コスト化か図れる等の優れた効果か奏される
(Effects of the Invention) As described above, according to the present invention, a ready-made pile in which a high-strength pile is connected to a concrete pile with an outer shell steel pipe or a steel pipe pile is used as a foundation pile, which requires relatively large-scale underground excavation. Compared to the case of using cast-in-place piles, excellent effects such as shortening the construction period and cost reduction of the layer are achieved.

また、既製杭の上へ建込んだ横真柱を、既製杭へ根固め
固定液を注入して固定設置するので、構真柱の位置決め
および保持も確実である。
In addition, since the horizontal main pillars built on top of ready-made piles are fixedly installed by injecting the root hardening fixative into the ready-made piles, the positioning and retention of the main pillars is also reliable.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の一実施例を示す説明図である。 3・・・・高強度抗    4・・・・・既製杭5・・
・鋼管杭     6・・・構真柱b・・根固め固定液
FIG. 1 is an explanatory diagram showing one embodiment of the present invention. 3... High strength pile 4... Ready-made pile 5...
・Steel pipe pile 6... Structure pillar b... Root hardening fixing solution

Claims (3)

【特許請求の範囲】[Claims] (1)地階を有する建物の地下構築に際し、該建物の柱
を立設すべき地面の所定位置に予め基礎杭を打ち、該基
礎杭の上に建込んだ構真柱の上部での地上施工と同時に
、根伐および地階上層から下層に向うコンクリート打設
を行う地下構築用逆打工法において、上記基礎杭として
、高強度杭に鋼管杭を接続した既製杭を使用し、該既製
杭を地中に打込んだ後、該既製杭の上へ構真柱を建込む
ようにしたことを特徴とする地下構築用逆打工法。
(1) When constructing a building with a basement underground, foundation piles are driven in advance at predetermined positions on the ground where the pillars of the building are to be erected, and above-ground construction is carried out above the structural pillars erected on top of the foundation piles. At the same time, in the reverse driving method for underground construction, which involves cutting down roots and pouring concrete from the upper level of the basement to the lower level, ready-made piles consisting of steel pipe piles connected to high-strength piles are used as the foundation piles, and the ready-made piles are placed in the ground. A reverse driving method for underground construction, characterized in that a structural pillar is erected on top of the ready-made pile after being driven into the interior.
(2)地階を有する建物の地下構築に際し、該建物の柱
を立設すべき地面の所定位置に予め基礎杭を打ち、該基
礎杭の上に建込んだ構真柱の上部での地上施工と同時に
、根伐および地階上層から下層に向うコンクリート打設
を行う地下構築用逆打工法において、上記基礎杭として
、高強度杭に外殻鋼管付きコンクリート杭を接続した既
製杭を使用し、該既製杭を地中に打込んだ後、該既製杭
の上へ構真柱を建込むようにしたことを特徴とする地下
構築用逆打工法。
(2) When constructing a building with a basement underground, foundation piles are driven in advance at predetermined positions on the ground where the pillars of the building are to be erected, and above-ground construction is carried out above the structural pillars erected on top of the foundation piles. At the same time, in the reverse driving method for underground construction, which involves cutting down roots and placing concrete from the upper level of the basement to the lower level, ready-made piles consisting of high-strength piles and concrete piles with outer shell steel pipes are used as the foundation piles. A reverse driving method for underground construction, characterized in that after ready-made piles are driven into the ground, structural pillars are erected on top of the ready-made piles.
(3)上記既製杭へ根固め固定液を注入して、上記構真
柱を固定設置するようにしたことを特徴とする請求項1
または2いずれかの項に記載の地下構築用逆打工法。
(3) Claim 1 characterized in that the structural pillar is fixedly installed by injecting a foot hardening fixing liquid into the ready-made pile.
or 2. The reverse pouring method for underground construction as described in any of the above.
JP2330340A 1990-11-30 1990-11-30 Reverse construction method for underground construction Expired - Fee Related JP2567990B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2330340A JP2567990B2 (en) 1990-11-30 1990-11-30 Reverse construction method for underground construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2330340A JP2567990B2 (en) 1990-11-30 1990-11-30 Reverse construction method for underground construction

Publications (2)

Publication Number Publication Date
JPH04203028A true JPH04203028A (en) 1992-07-23
JP2567990B2 JP2567990B2 (en) 1996-12-25

Family

ID=18231528

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2330340A Expired - Fee Related JP2567990B2 (en) 1990-11-30 1990-11-30 Reverse construction method for underground construction

Country Status (1)

Country Link
JP (1) JP2567990B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109898669A (en) * 2019-03-12 2019-06-18 中建三局第一建设工程有限责任公司 A kind of contrary sequence method underground first floor beam-column node construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109898669A (en) * 2019-03-12 2019-06-18 中建三局第一建设工程有限责任公司 A kind of contrary sequence method underground first floor beam-column node construction method

Also Published As

Publication number Publication date
JP2567990B2 (en) 1996-12-25

Similar Documents

Publication Publication Date Title
JP4013182B2 (en) Self-supporting mountain retaining wall method and self-supporting mountain retaining wall
JPH08296243A (en) Construction method for underground structure by precast concrete central pillar
JP2000352296A (en) Method o constructing passage just under underground structure
JP2596798B2 (en) Existing building seismic isolation method
KR100912574B1 (en) Retaining wall system using strut assembly and excavating method using the same
JP2007308951A (en) Method of constructing outer peripheral column by inverted construction method
AU2020100004A4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method
JPH04203028A (en) Reverse driving method for underground building
JP2858998B2 (en) Construction method of temporary supporting column for reverse driving method
JPH0559728A (en) Sheathing work above underground structure
JP2003082691A (en) Execution method for underground structural skeleton
JP2858997B2 (en) Temporary support column used for reverse driving method
JP2565457B2 (en) Structure pillar construction method
JP6851180B2 (en) How to rebuild the building
JP2000355941A (en) Building and its construction method
JP2996113B2 (en) How to build a shaft
JPH0610339A (en) Landslide protection wall made of reinforced concrete and construction thereof
JPH059945A (en) Underground skeleton constructing method
JP4178273B2 (en) Construction method of structural pillars using ready-made piles
JPH0510448B2 (en)
JP2001011874A (en) Construction method for structural stud using precast pile
JPH01250541A (en) Construction of main structural column
JPS6217233A (en) Foundation base column
JP2711748B2 (en) Construction method of large-scale underground space
JPH10280446A (en) Construction method for base-isolated building using inverse driving method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081003

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081003

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091003

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101003

Year of fee payment: 14

LAPS Cancellation because of no payment of annual fees