JPH0414518A - Method for constructing new retaining wall at old retaining wall position on neighboring line - Google Patents
Method for constructing new retaining wall at old retaining wall position on neighboring lineInfo
- Publication number
- JPH0414518A JPH0414518A JP11652090A JP11652090A JPH0414518A JP H0414518 A JPH0414518 A JP H0414518A JP 11652090 A JP11652090 A JP 11652090A JP 11652090 A JP11652090 A JP 11652090A JP H0414518 A JPH0414518 A JP H0414518A
- Authority
- JP
- Japan
- Prior art keywords
- earth
- retaining wall
- earth retaining
- collapse
- embankment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims description 19
- 239000002689 soil Substances 0.000 claims abstract description 21
- 239000004576 sand Substances 0.000 claims abstract description 19
- 238000010276 construction Methods 0.000 claims description 21
- 238000009412 basement excavation Methods 0.000 claims description 19
- 238000005429 filling process Methods 0.000 claims description 3
- 238000011900 installation process Methods 0.000 claims 1
- 239000000463 material Substances 0.000 abstract 3
- 230000006378 damage Effects 0.000 abstract 1
- 230000000694 effects Effects 0.000 description 6
- 229910000831 Steel Inorganic materials 0.000 description 5
- 239000010959 steel Substances 0.000 description 5
- 210000000078 claw Anatomy 0.000 description 4
- 238000010586 diagram Methods 0.000 description 4
- 239000002184 metal Substances 0.000 description 4
- 239000004568 cement Substances 0.000 description 2
- 206010067482 No adverse event Diseases 0.000 description 1
- 230000002411 adverse Effects 0.000 description 1
- 239000008267 milk Substances 0.000 description 1
- 210000004080 milk Anatomy 0.000 description 1
- 235000013336 milk Nutrition 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
- Earth Drilling (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
Description
【発明の詳細な説明】
「産業上の利用分野」
本発明は、近接線(隣接する建物又は境界より10闘の
線、以下単に近接線とする。)上の既設土留め壁位置に
、新設土留め壁を構築する工法に関するものである。DETAILED DESCRIPTION OF THE INVENTION "Field of Industrial Application" The present invention applies to the construction of a new retaining wall at the location of an existing earth retaining wall on the proximity line (the line 10 meters from the adjacent building or boundary, hereinafter simply referred to as the proximity line). It concerns the method of constructing earth retaining walls.
「従来の技術並び二二その課題」
従来近接線上に構築された既設土留め壁を崩壊し・、こ
の位置に新設土留め壁を構築する方法としては、適切な
方法がなく難渋している。``Conventional techniques and their problems'' There is no suitable method for collapsing the existing earth retaining wall built on the adjacent line and constructing a new earth retaining wall in this location, which is difficult.
そしで、一部で施工されている矢板、切梁、蝮おこし等
を利用する工法では、大変な手間と労力を便するもので
あり、多くの課題かある。However, the construction methods that are currently used in some areas, such as using sheet piles, struts, and lintels, save a lot of time and effort, and there are many problems.
し・たかっで、従来の工法では、近接線上の既設土留め
壁が設けられている位置には、新設土留め壁が構築でき
ないといっても過言ではない。However, it is no exaggeration to say that with conventional construction methods, it is not possible to construct a new retaining wall in a location where an existing retaining wall is located on the adjacent line.
「課題を解決するための手段」
上記に鑑み、本発明は、近接線上であっで、かつ既設土
留め壁位置に、新設土留め壁を確実、かつ簡易に構築す
る二とができ、土地の有効利用が図れるようにする為に
、
先ず既設土留め壁の崩壊を防止する為の切梁取付けをす
る。"Means for Solving the Problems" In view of the above, the present invention is capable of reliably and easily constructing a new earth retaining wall on the adjacent line and at the location of the existing earth retaining wall. In order to make effective use of the structure, we will first install struts to prevent the existing retaining walls from collapsing.
その後、最初に、根切り底の土砂を取り除く。この際に
、この根切り地中のほぼ最中部分よりその土留め壁側の
方向に向かってlll[1次掘削し、l1li1次繰り
返して根切り底の土砂を全て掘削し・つつ、一部を残し
・て盛土作業を順次なし・、かつ土留め壁を露出する掘
削盛土を成す。First, remove the soil at the bottom of the root cut. At this time, perform the first excavation from approximately the middle of the root cut in the direction of the earth retaining wall, and repeat the first excavation to excavate all the earth and sand at the bottom of the root cut. Excavation and embankment work will be carried out sequentially, leaving the earth retaining walls exposed.
そしで、この根切り底盛土並びに掘削工程が終了した時
点で、露出された土留め壁を111n次崩壊しつつ、こ
の崩壊瓦礫を盛土隙間に移送し、かつこの崩壊された既
設土留め壁部位に、順次瓦礫、石等の混じりもののない
土砂(以下、良い土とする。)を充填する土盛りをなす
崩壊土盛りを一区画全部に成すと、ここに、基礎の一区
画の土盛りと土留め壁の崩壊が終了する。Then, when this root cutting, bottom embankment and excavation process is completed, the exposed earth retaining wall is collapsed to the 111th degree, and the collapsed debris is transferred to the embankment gap, and the collapsed existing earth retaining wall part is collapsed. If one section is filled with a collapsed earth mound that is filled with earth and sand (hereinafter referred to as "good soil") that is not contaminated with rubble, stones, etc., one section of the earth mound for the foundation and the earth retaining wall will be created. collapse ends.
そこで、続いて次の一区画の土盛りと土留め壁の崩壊に
かかり、先ず既設土留め壁が露出する程度に、土砂で盛
土をなし、一時的な内底面を構成する板肉底面盛土をす
る。Therefore, the next step was to collapse the earth embankment and earth retaining wall. First, we made an embankment with earth and sand to the extent that the existing earth retaining wall was exposed, and then we built a plank bottom embankment to form a temporary inner bottom surface. .
その後前述と工程と同様な、土留め壁の崩壊、瓦礫の排
除並びに土盛りをなす崩壊土盛り作業を成すことにより
、ここに、前記反復一区画の土盛りと土留め壁の崩壊か
終了する。Thereafter, the collapse of the earth retaining wall, the removal of debris, and the collapsing earth embankment work are carried out in the same manner as in the process described above, thereby completing the collapse of the earth embankment and earth retaining wall of the repeated section.
更に、土留め壁の立設方向の長さに対応しで、切梁の撒
去並びに前記反復一区画の土盛りと土留め壁の崩壊を繰
り返し、既設土留め壁位置に良い土の土盛りされる。Furthermore, according to the length of the earth-retaining wall in the erection direction, the scattering of the struts and the repeated soil mounding and collapsing of the earth-retaining wall are repeated, and a good earth mound is built up at the position of the existing earth-retaining wall. .
その後、この土盛り(良い土)位置に新規の土留め壁を
構築する近接線上の既設土留め壁位置に新設土留め壁を
構築する工法である。This is a construction method in which a new earth retaining wall is then constructed at the position of this earth mound (good soil), and a new earth retaining wall is constructed at the position of the existing earth retaining wall on the adjacent line.
また本発明は、隣接する地盤にゆるみ、崩壊等の悪影響
を与えることがないこと。またこれにより、家屋、塀等
の建造物の傾き、不当沈下等のトラブルが発生しないよ
うにする為に、
先ず既設土留め壁を切梁又は図示しない腹おこし等を介
して既設土留め壁の崩壊を防止する一方で、崩壊された
土留め壁の部位に於いては、この崩壊土留め壁部位に於
ける隣接地の崩壊を防止する為に、この土留め壁部位に
相当する地中に、外部より土盛りする工法である。Furthermore, the present invention does not cause any adverse effects such as loosening or collapse on the adjacent ground. Additionally, in order to prevent problems such as tilting of houses, walls, and other structures and undue subsidence, the existing earth retaining walls should first be constructed with struts or with raised sides (not shown). At the same time, in the part of the collapsed earth retaining wall, in order to prevent the collapse of the adjacent land in the collapsed earth retaining wall part, underground This is a construction method in which earth is raised from the outside.
更に、本発明は、既設土留め壁部位に、確実に新設土留
め壁を構築できるようにする為に、この部位(隣接地よ
り、少なくともほぼ30正幅に相当する部位)に、外部
より良い土を充填する工法である。Furthermore, in order to be able to reliably construct a new earth retaining wall in the area of an existing earth retaining wall, the present invention provides that this area (an area equivalent to at least approximately 30 square widths from the adjacent land) has a better construction than the outside. This is a method of filling with soil.
また本発明は、新設土留め壁を前記工法を介し・て短間
間に、かつ効率よく構築する為に、根切り底部より、既
設土留め壁の崩壊並びに土盛り等の作業を成し・、かつ
その最中より底部の掘削を成す。Furthermore, in order to construct a new earth retaining wall in a short time and efficiently using the above construction method, the present invention performs work such as collapsing the existing earth retaining wall and mounding earth from the bottom of the root cut. And during this process, the bottom is excavated.
そしで、続いて次の一区画の土盛りと土留め壁の崩壊に
かかり、土砂で盛土をなし・、時的な内底面を構成し・
た後、前述の土留め壁の崩壊、瓦礫の排除並びに土盛り
をなす崩壊土盛り作業を成しで、反復一区画の土盛りと
土留め壁の崩壊が終了する。Then, the next block of earth mounds and retaining walls began to collapse, forming an embankment with earth and sand, and forming a temporary inner bottom.
After that, the above-mentioned collapse of the earth retaining wall, removal of debris, and collapse earth mounding work to form the earth mound are completed, and the repeated collapse of the earth mound and earth retaining wall of one section is completed.
その後、土留め壁の立設方向の長さに対応しで、切梁の
撤去並びに前記反復一区画の土盛りと土留め壁の崩壊を
繰り返し、既設土留め壁位置に良い土の土盛りされる。Thereafter, in accordance with the length of the earth retaining wall in the erecting direction, the removal of the struts and the repeated soil mounding and collapsing of the earth retaining wall are repeated to fill the existing earth retaining wall position with good soil.
その後、この土盛り位置に新規の土留め壁を構錆する近
接線上の既設土留め壁位置に新設土留め壁を構築する工
法である。This is a construction method in which a new earth retaining wall is then constructed at the position of the existing earth retaining wall on the adjacent line to which a new earth retaining wall is constructed.
「作用」
以下本発明の詳細な説明すると、先ず、第2図の如く、
土留め壁の崩壊を防止する為に、切梁工法により、適宜
数の切梁を装着する切梁取付は工程を成す。"Operation" A detailed explanation of the present invention will be given below. First, as shown in FIG.
In order to prevent the earth retaining wall from collapsing, installing the appropriate number of struts using the strut construction method is a process.
続いて第3図の順序で施工を成すか、先ず同図(イ)の
如く、第一に前記土留め壁の根切り底の土砂を取り除く
が、この際に、この根切り地中のほぼ最中部分の鎖線で
示す部位より、その土留め壁側の方向に向かって順次掘
削し、この掘削土砂の一部を他の部分に取り除く。Next, the construction can be carried out in the order shown in Figure 3, or first, as shown in Figure 3 (a), first remove the earth and sand at the bottom of the root cut of the earth retaining wall. Excavation is carried out sequentially from the part indicated by the chain line in the middle towards the retaining wall, and some of this excavated earth and sand is removed to other parts.
以上の掘削を同図(イ)で仮想線で示すようにして順次
掘削し・、この掘削土砂を、既に掘削された前記最中部
分に向かって移送する。The above-mentioned excavation is carried out in sequence as shown by the imaginary lines in FIG.
容易に掘削土砂の搬送韮びに排除ができ、究極的には、
根切り底の土砂を全て掘削していき、土留め壁を露出す
る掘削盛土工程を成すと、同図(ロ)の状りとなる。The excavated soil can be easily transported and removed, and ultimately,
When all the earth and sand at the bottom of the root cut is excavated and the earth retaining wall is exposed, the result will be as shown in the same figure (b).
続いで、この根切り底盛土並ひここ掘削工程か終了した
時点で、同図(ハ)の如く、露出された鎖線で示す土留
め壁を1110次崩壊していき、同図(ニ)の如く、前
記崩壊し・た瓦礫を、盛土隙間に移送するとともに、同
図(ホ)の如く、この崩壊された既設土留め駅部情に、
1itai次良い土を充填する土盛りをなし、この崩壊
並びに充填作業を順7ケ繰り返し・で、この区画の土留
め壁の崩壊と全ての土盛りか終了す る。Subsequently, when this root cutting and bottom embankment line and excavation process is completed, the exposed earth retaining wall shown by the chain line is collapsed 1110 times as shown in the same figure (c). As shown in the figure (e), the collapsed debris was transferred to the embankment gap, and as shown in the same figure (e), the collapsed existing retaining station area was
Build an earthen mound and fill it with good soil, and repeat this collapse and filling process 7 times in order until the collapse of the retaining wall and all earth mounds in this area are complete.
これにより、前記基礎の一区画の土盛りと土留め壁の崩
壊か終了する。This completes the collapse of the earth embankment and retaining wall in one section of the foundation.
そこで、続いて同図(へ)の如く、次の一区画の土盛り
と土留め壁の崩壊にかかるか、この際先ず既設土留め壁
が露出する程度に、外部より搬入した土砂で盛土をなし
、仮想線で示すようになしで、一時的な内底面を構成す
る板肉底面盛土を成す。Therefore, as shown in the same figure (f), whether the next block of earth mounds and retaining walls collapse, or at this time, the embankment is first constructed with earth and sand brought in from outside to the extent that the existing earth retaining walls are exposed. , as shown by the phantom line, forms a plank bottom embankment that constitutes a temporary inner bottom surface.
その後同図(ト)の如く、前述と工程と同様な、土留め
壁の崩壊、瓦礫の排除並びに土盛りをなす崩壊土盛り作
業を成す。 この工程が終了し・た時点で、前記反復
一区画の土盛りと土留め壁の崩壊が終了する同図(チ)
の状態となる。After that, as shown in the same figure (g), similar to the process described above, collapse of the retaining wall, removal of debris, and collapse earth mounding work will be carried out. At the end of this process, the collapse of the earth mound and retaining wall in one section is completed (see Figure 1).
The state will be as follows.
更に、土留め壁の立設方向の長さに対応し5で、切梁の
撤去並びに前記反復一区画の土盛りと土留め壁の崩壊を
繰り返し・、既設土留め壁位置に瓦礫等が土砂が土盛り
される(同図(す)〜(ル)参照)。Furthermore, in step 5, corresponding to the length of the earth retaining wall in the erection direction, the removal of the strut and the collapse of the soil mound and earth retaining wall in one section are repeated, and debris etc. and earth and sand are deposited at the position of the existing earth retaining wall. It is piled up with earth (see (S) to (R) in the same figure).
ヲ
これにより、同図(f)で示すように、既設土留め壁部
位に良い土が充填された状態であり、いっても新設土留
め壁の工事か可能であり、また隣接地盤への悪影響もほ
とんどないものである。As a result, as shown in Figure (f), the existing earth retaining wall is filled with good soil, and it is possible to construct a new earth retaining wall, and there is no negative impact on the adjacent ground. There are also very few.
その後は、第5図の如く、第6図の掘削作業機械を介し
てi設土留め壁を構築する。Thereafter, as shown in FIG. 5, an i-set earth retaining wall is constructed using the excavating machine shown in FIG. 6.
尚掘削作業機械は、第6図に示す構造でも可能である。Incidentally, the excavation work machine can also have the structure shown in FIG.
「実施例」
図示する機材並びに装置は、本発明の実施に使用するに
最適な一例を示す屯のであっで、1は隣接する建造物、
2は基礎ブロック、3は基礎杭、4は既設土留め壁、5
は前記既設土留め壁で囲繞された櫂切り底、6は例えは
車庫、物置、地下室等の部屋である。``Example'' The illustrated equipment and equipment are in a tunnel, which represents an example most suitable for use in carrying out the present invention, and 1 is an adjacent building;
2 is the foundation block, 3 is the foundation pile, 4 is the existing retaining wall, 5
numeral 6 is a paddle-cut bottom surrounded by the existing retaining wall, and numeral 6 is a room such as a garage, a storeroom, or a basement.
以上のようにして構成された構造の部屋6の既設土留め
壁4を崩壊しで、新設土留め壁14する。その際の崩壊
し、た土留め壁を4aて示し、この崩壊土留め壁4aに
元通される土盛りを7で示す。The existing earth retaining wall 4 of the room 6 constructed as described above is collapsed and a new earth retaining wall 14 is constructed. The collapsed earth retaining wall at that time is shown as 4a, and the earth mound that is restored to the collapsed earth retaining wall 4a is shown as 7.
図中8は既設土留め@!14間に設けられる切条で、部
屋6の深さ寸法により適宜敷設けられ、また既設土留め
壁4の崩壊に応し・て適宜減少される。8 in the diagram is the existing earth retaining @! 14, and is laid as appropriate depending on the depth dimension of the room 6, and is appropriately reduced in accordance with the collapse of the existing earth retaining wall 4.
また9は外部より搬入した土砂で構成される盛土であっ
で、根切り底5より上方の既設土留め壁4を崩壊し・て
いく際に、一時的な内底面9aを構成する。Further, reference numeral 9 is an embankment made of earth and sand brought in from the outside, and forms a temporary inner bottom surface 9a when the existing earth retaining wall 4 above the root cut bottom 5 is collapsed.
以上の符号とか、その符号の作業又は構成は、反復して
各−区画を順次構成していく場合も同様である。The above-mentioned codes and the operations or configurations of the codes are the same even when each section is sequentially configured by repeating the code.
尚第5図、第4図に示す掘削作業機械は、前記崩壊され
た既設土留め壁部位に、新設土留め壁を構築する際に使
用される機械であり、その概要を説明すると、 21は
クレーンで、このクレーン21のlI22には、270
°旋回できる掘削作業機械24が滑車23を介し、て略
垂直状態に吊架されている。The excavation work machine shown in Figs. 5 and 4 is a machine used when constructing a new earth retaining wall at the site of the collapsed existing earth retaining wall, and its outline is as follows: In the crane, lI22 of this crane 21 has 270
An excavation work machine 24 which can be rotated is suspended in a substantially vertical state via a pulley 23.
尚この掘削作業機械24は、狭隘な間隔をもって立設し
た二枚の鋼販25.25aと、二〇鋼販25.25a間
の上、下端に軸着された鎖車26.27と、この鎖車2
6.27間に捲装された多数の爪付厖型両曲面金具28
・・ ・・ (以下単に28とする。)を設けたチェー
ン29とて構成されている。その寸法は、概ね幅が90
〜1201、鋼販25.25aの間隔が17〜30L?
II+、丈が450〜800cmが理想と考えられる。This excavation work machine 24 consists of two steel bars 25.25a set up with a narrow spacing, a chain wheel 26.27 pivoted at the upper and lower ends between the two steel bars 25.25a, and chain wheel 2
6. Numerous claw-shaped double-curved metal fittings 28 wrapped between 27
... (hereinafter simply referred to as 28). Its dimensions are approximately 90 mm wide
~1201, Hagane 25.25a spacing is 17~30L?
II+, a length of 450 to 800 cm is considered ideal.
また前記鎖車26.27間に捲装されたチェーン29は
鋼販25.25a間に設けたモータ30で正逆転駆動さ
れ、もって爪付箆型両曲面金具28が正逆転するととも
に、この正逆転の周回移行により、前記新設土留め壁1
4位置の穴を順次地中方向に掘進していき、究極的には
、その掘進深さの穴をスプライン方式で掘削するもので
ある。The chain 29 wound between the chain wheels 26 and 27 is driven forward and backward by a motor 30 installed between the chain wheels 25 and 25a, and as a result, the claw-shaped double-curved metal fitting 28 is rotated forward and backward, and this Due to the reversal of the rotation, the new earth retaining wall 1
Holes at four positions are sequentially dug underground, and ultimately a hole of the same depth is drilled using the spline method.
このスプライン穴には、掘削作業機械24の持ち上けら
れ分の隙間に、生コンクリートが充填されで、型鋼入り
新設土留め壁14か構築されるか、又はモルタル、セメ
ントミルク等が圧入されで、型鋼入すソイルセメントf
JT段土留めu14が構娶される。In this spline hole, the gap created by the lifting of the excavating machine 24 is filled with ready-mixed concrete, and a new earth retaining wall 14 containing molded steel is constructed, or mortar, cement milk, etc. are press-fitted. , Soil cement f
JT tiered retaining u14 is constructed.
図中31は掘削作業機械24を吊架する滑車で、32は
ローブで、33は前記滑車31を支持する掘削作業機械
24の一面側に設けた架承部材である。し、たかっで、
掘削作業機械24はこの架承部材33及び滑車31、ロ
ーブ32並びに滑車23を介しで、櫓22に対して27
0 旋回可能なように吊架されてい る。In the figure, 31 is a pulley for suspending the excavating machine 24, 32 is a lobe, and 33 is a supporting member provided on one side of the excavating machine 24 for supporting the pulley 31. Takade,
The excavation work machine 24 is attached to the tower 22 via the support member 33, the pulley 31, the lobe 32, and the pulley 23.
0 It is suspended so that it can rotate.
尚、前記爪付箆型両曲面金具28の主体をなす箆本体2
8aの除土曲面の全部と、この箆本体28aに設けた爪
28bの全部が、両鋼販25.25aの前後方向並びに
下方の端面より完全に突出し、かつ幅方向にもかなり突
出する構成であり、かつ除土曲面の両側面並びに爪28
bの両側面が、両鋼販25.25aの幅方向の端面より
かなり突出する構成である。Incidentally, the spatula main body 2 forming the main body of the clawed spatula type double-curved metal fitting 28
The entire earth removal curved surface 8a and the claw 28b provided on the spatula main body 28a completely protrude from the front and rear direction and the lower end surface of the two steel plates 25.25a, and also protrude considerably in the width direction. Yes, and both sides of the earth removal curved surface and the claw 28
Both side surfaces of b protrude considerably from the end surfaces in the width direction of both steel sheets 25.25a.
これによっで、掘削作業機械24て掘削されるラスプラ
イン穴の形状は、この掘削作業機械24の本体より一回
り大きく掘削される。As a result, the shape of the raspline hole excavated by the excavating machine 24 is one size larger than the main body of the excavating machine 24.
したかっで、掘削作業機械24の本体に対する土圧抵抗
をほぼ無くすことかできるので、この掘削作業機械24
の自重沈下が可能となる。Therefore, the earth pressure resistance against the main body of the excavating machine 24 can be almost eliminated, so this excavating machine 24
It becomes possible to sink under its own weight.
また第6図は、−軸〜五軸等の多軸掘削作業機械44を
示しており(図示の例では、三軸掘削作業機械を示す)
、41はその回転駆動装置、42は多軸装置、 43a
〜43cはオーカースクリユーを有するオーカーマンン
である。Further, FIG. 6 shows a multi-axis excavating machine 44, such as a -axis to five axes (the illustrated example shows a three-axis excavating machine).
, 41 is its rotational drive device, 42 is a multi-axis device, 43a
~43c is an oakermann with an ocher screw.
尚本発明の工法は、既設土留め壁4の一部の場合にも利
用できることは勿論であり、またこのような工法も、本
発明の範鴫に含まれる。It goes without saying that the construction method of the present invention can also be used for a part of the existing earth retaining wall 4, and such construction method is also included in the scope of the present invention.
「発明の効果」
以上で詳述したように、本発明は、切梁取付けをした後
、先ず最初に、根切り底の土砂を取り除く。この際に、
この根切り地中のほぼ最中部分よりその土留め壁側の方
向に向かって順次掘削し、順次繰り返して根切り底の土
砂を全て掘削(1)つつ、一部を残して盛土作業を順次
なし、かつ土留め壁を露出する掘削盛土を成す。"Effects of the Invention" As detailed above, in the present invention, after installing the strut, first of all, the earth and sand at the bottom of the root cut are removed. At this time,
Excavation is carried out sequentially from approximately the middle of the root cut in the direction of the earth retaining wall, and the earth and sand at the bottom of the root cut are excavated (1) in sequence, while embankment work is carried out in sequence, leaving a portion of the soil. None, and consists of an excavated embankment that exposes the retaining wall.
そしで、この根切り底盛土並びに掘削工程か終了した時
点で、露出された土留め壁を順次崩壊し・つつ、この崩
壊瓦礫を盛土隙間に移送し、かつこの崩壊された既設土
留め壁部位に、順次良い土を充填する土盛りをなす崩壊
土盛りを一区画全部に成すと、ここに、基礎の一区画の
土盛りと土留め壁の崩壊か終了する。Then, when the root cutting and bottom embankment and excavation processes are completed, the exposed earth retaining walls are sequentially collapsed and the collapsed debris is transferred to the embankment gap, and the collapsed existing earth retaining wall parts are removed. Then, if a collapsed earth mound, which is a mound of earth filled with good soil, is made for the entire area, the collapse of the earth mound of one area of the foundation and the earth retaining wall will be completed.
そこで、続いて次の一区画の土盛りと土留め壁の崩壊に
かかり、先ず既設土留め壁が露出する程度に、土砂で盛
土をなし、一時的な内底面を構成する板肉底面盛土をす
る。Therefore, the next step was to collapse the earth embankment and earth retaining wall. First, we made an embankment with earth and sand to the extent that the existing earth retaining wall was exposed, and then we built a plank bottom embankment to form a temporary inner bottom surface. .
その後前述と工程と同様な、土留め壁の崩壊、瓦礫の排
除並びに土盛りをなす崩壊土盛り作業を成すことにより
、ここに、前記反復一区画の土盛りと土留め壁の崩壊が
終了する。Thereafter, the collapse of the earth retaining wall, the removal of debris, and the collapsing earth embankment work are carried out in the same manner as in the process described above, thereby completing the collapse of the earth embankment and earth retaining wall of the repeated section.
更に、土留め壁の立設方向の長さに対応しで、切梁の撤
去並びに前記反復一区画の土盛りと土留め壁の崩壊を縁
り返し、既設土留め壁位置に良い土の土盛りされる。Furthermore, in accordance with the length of the earth-retaining wall in the erection direction, the sills are removed, the soil mound of one section is repeated, and the collapse of the earth-retaining wall is reversed, and a good earth mound is placed at the position of the existing earth-retaining wall. Ru.
その後、この土盛り(良い土)位置に新規の土留め壁を
構築する近接線上の既設土留め壁位置に新設土留め壁を
構築する工法である。This is a construction method in which a new earth retaining wall is then constructed at the position of this earth mound (good soil), and a new earth retaining wall is constructed at the position of the existing earth retaining wall on the adjacent line.
したかっで、近接線上に構築された既設土留め壁位置に
、新設土留め壁を確実、かつ簡易に構築することができ
る効果と、土地の賂駄かなくなり、土地の有効利用が図
れる卓効かある。Therefore, the effect of being able to reliably and easily construct a new earth retaining wall at the location of an existing earth retaining wall built on the adjacent line, and the great effect of eliminating the waste of land and making effective use of land. be.
また本発明は、先ず既設土留め壁を切梁又は図示しない
腹おこし・等を介して既設土留め壁の崩壊を防止する一
方で、崩壊された土留め壁の部位に於いては、この崩壊
土留め壁部位に於ける隣接地の崩壊を防止する為に、こ
の土留め壁部位に相当する地中に、外部より土盛りする
工法である。In addition, the present invention first prevents the existing earth retaining wall from collapsing by using struts or erectors (not shown), etc., and at the same time prevents the collapsed earth retaining wall from collapsing. In order to prevent the adjacent land from collapsing in the area of the earth retaining wall, this is a construction method in which earth is piled up from outside into the ground corresponding to the earth retaining wall area.
よっで、隣接する地盤にゆるみ、崩壊等の悪影響を与え
ることがないこと。またこれにより、家屋、塀等の建造
物の傾き、不当沈下等のトラブルが発生しないようにす
る為に、更に、本発明は、既設土留め壁の部位に、外部
より良い土を充填する工法である。Therefore, there shall be no adverse effects such as loosening or collapse on the adjacent ground. In addition, in order to prevent troubles such as tilting of buildings such as houses and fences and undue subsidence from occurring, the present invention further provides a construction method in which the existing earth retaining wall is filled with soil better than the outside. It is.
したがっで、既設土留め壁の部位に、確実、かつ簡易に
新設土留め壁を構築できる効果があ る。Therefore, it has the effect of allowing a new earth retaining wall to be constructed reliably and easily at the site of an existing earth retaining wall.
また本発明は、先ず相切り底部より、既設土留め壁の崩
M並びに土盛り等の作業を成し、かつその最中より底部
の掘削を成す。Further, in the present invention, work such as demolishing the existing earth retaining wall and earth embankment is first performed from the bottom of the phase cut, and the bottom is excavated during this work.
そし・で、続いて次の一区画の土盛りと土留め壁の崩壊
にかかり、土砂で盛土をなし・、時的な内底面を構成し
た後、前述の土留め壁の崩壊、瓦礫の排除並びに土盛り
をなす崩壊土盛り作業を成しで、反復一区画の土盛りと
土留め壁の崩壊が終了する。Then, the next block of earth mounds and retaining walls will collapse, and after forming the embankment with earth and sand and forming a temporary inner bottom, the aforementioned earth retaining walls will collapse, debris will be removed, and debris will be removed. Collapse to form an earth mound The earth mound work is completed, and the repeated collapse of one area of earth mound and retaining wall is completed.
その後、土留め壁の立設方向の長さに対のし・で、切梁
の撤去並びに前記反復一区画の土盛りと土留め壁の崩壊
を繰り返し・、既設土留め壁位置に良い土の土盛りされ
る。After that, the length of the earth retaining wall is paralleled in the erection direction, and the struts are removed, and the above-mentioned repeated earth mounding and collapse of the earth retaining wall are repeated. be done.
その後、この土盛り位置に新規の土留め壁を構築する近
接線上の既設土留め壁位置に新設土留め壁を構築する工
法である。This is a construction method in which a new earth retaining wall is then constructed at the position of the existing earth retaining wall on the adjacent line to a new earth retaining wall at this earth mound position.
したがっで、既設土留め壁の取り壊し・と、この部位に
新設土留め壁を構築するに際しで、誠に短期間に、かつ
効率よく構築し得る効果を有する。Therefore, when demolishing the existing earth retaining wall and constructing a new earth retaining wall in this area, it has the effect of being able to construct it efficiently and in a very short period of time.
図面は本工法の一実施例を示すものであり、第1図は工
事前の断面図、第2図は切梁を装置
着した状態の断面図、第3図(イ)〜(t)は施工順序
の一例を示した模式図、第4図はfJi設土留め壁を構
築する状態の断面図、第5図並ひここ第6図は、それぞ
れ掘削作業機械の一例を示した概略図である。
25.25a:4111鈑
26.27: 鎖車
28: 爪付箆型両曲面金具
28a:i%本体 28b: 爪
29: チェーン 30: モータ32:
ローフ 33: 架承部材44; 多軸掘削
作業機織
42: 多軸装置
43a〜43c: オーカーマンン
1: 建造物 2: 基礎フロック3: 基礎
杭 4: 既設土留め壁4a: 崩壊した土
留め壁
5: 根切り8!6: 部屋
7: 土盛り 9: 盛土
9a: 内底面 14: 新設土留め壁21
: クレーン 22: 櫓23.31; 滑
車 24: 掘削作業機械寮4図The drawings show an example of this construction method. Figure 1 is a cross-sectional view before construction, Figure 2 is a cross-sectional view with the struts installed, and Figures 3 (a) to (t) are cross-sectional views. Fig. 4 is a schematic diagram showing an example of the construction order, Fig. 4 is a cross-sectional view of the fJi earth retaining wall being constructed, and Fig. 5 and Fig. 6 are schematic diagrams showing an example of the excavation work machine. be. 25.25a: 4111 plate 26.27: Chain wheel 28: Plough type double curved metal fitting with claw 28a: i% body 28b: claw 29: Chain 30: Motor 32:
Loaf 33: Supporting member 44; Multi-axis excavation machine 42: Multi-axis devices 43a to 43c: Oakermann 1: Building 2: Foundation block 3: Foundation pile 4: Existing retaining wall 4a: Collapsed retaining wall 5: Root cutting 8! 6: Room 7: Earth mound 9: Embankment 9a: Inner bottom surface 14: New earth retaining wall 21
: Crane 22: Tower 23.31; Pulley 24: Excavation machine dormitory diagram 4
Claims (1)
、適宜数の切梁を装着する切梁取付け工程と、 前記土留め壁の根切り底の土砂を取り除く為に、この根
切り地中のほぼ最中部分よりその土留め壁側の方向に向
かって順次掘削し、この掘削土砂の一部を他の部分に取
り除き、その他の掘削土砂を最中部分に向かって移送す
る盛土作業を、順次繰り返して根切り底の土砂を全て掘
削しつつ、一部を残して盛土作業を順次なし、かつ土留
め壁を露出する掘削盛土工程と、 この根切り底盛土並びに掘削工程が終了した時点で、露
出された土留め壁を順次崩壊しつつ、この崩壊瓦礫を盛
土隙間に移送し、かつこの崩壊された既土留め壁部位に
、順次瓦礫、石等の混じりもののない土砂を充填する土
盛りをなし、この崩壊並びに充填作業を順次繰り返して
、この一区画の土留め壁の崩壊と全ての土盛りをなす崩
壊土盛り工程と、 この工程が終了した時点で、前記基礎の一区画の土盛り
と土留め壁の崩壊が終了する。 そこで、続いて次の一区画の土盛りと土留め壁の崩壊に
かかるが、この際先ず既設土留め壁が露出する程度に、
外部より搬入する土砂で盛土をなし、一時的な内底面を
構成する仮内底面盛土工程と、 その後前述と工程と同様な、土留め壁の崩壊、瓦礫の排
除並びに土盛りをなす崩壊土盛り工程と、 この工程が終了した時点で、前記反復一区画の土盛りと
土留め壁の崩壊が終了する。 更に、土留め壁の立設方向の長さに対応して、切梁の撤
去並びに前記反復一区画の土盛りと土留め壁の崩壊を繰
り返し、既設土留め壁位置に瓦礫等が土砂が土盛りされ
る。 その後、この土盛り位置に新規の土留め壁を構築する近
接線上の既設土留め壁位置に新設土留め壁を構築する工
法。(1) In order to prevent the earth retaining wall from collapsing, there is a beam installation process in which an appropriate number of struts are installed using the beam construction method, and the roots of the earth retaining wall are removed to remove earth and sand at the bottom of the cut. An embankment in which excavation is carried out sequentially from approximately the middle part of the cut land toward the retaining wall side, part of this excavated soil is removed to another part, and the remaining excavated soil is transferred toward the middle part. The excavation and filling process involves repeating the work in sequence to excavate all of the earth and sand at the bottom of the root cut, leaving a portion behind, and then carrying out the embankment work in order to expose the retaining wall. At that point, the exposed earth retaining walls are sequentially collapsed, the collapsed debris is transferred to the embankment gap, and the collapsed existing earth retaining walls are sequentially filled with pure earth and sand such as debris and stones. This collapse and filling process is repeated sequentially to collapse the earth retaining wall of this one section and form the entire earth mound, and when this process is completed, the earth mound of one section of the foundation is completed. The collapse of the earth retaining wall ends. Therefore, the next section of earth mound and earth retaining wall will collapse, but first, the existing earth retaining wall will be exposed.
A temporary inner bottom embankment process in which earth and sand brought in from outside are used to form a temporary inner bottom surface, and then a collapse earth embankment process in which retaining walls collapse, debris is removed, and a soil embankment is created, which is similar to the process described above. , When this step is completed, the collapse of the earth embankment and earth retaining wall of the repeated section is completed. Furthermore, in accordance with the length of the earth retaining wall in the erection direction, the removal of the struts and the repeated earth mounding and collapse of the earth retaining wall were repeated, and debris, etc., and earth were piled up at the existing earth retaining wall position. Ru. A construction method in which a new earth retaining wall is then constructed at the position of the existing earth retaining wall on the adjacent line to construct a new earth retaining wall at this earth mound location.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11652090A JPH0414518A (en) | 1990-05-02 | 1990-05-02 | Method for constructing new retaining wall at old retaining wall position on neighboring line |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11652090A JPH0414518A (en) | 1990-05-02 | 1990-05-02 | Method for constructing new retaining wall at old retaining wall position on neighboring line |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0414518A true JPH0414518A (en) | 1992-01-20 |
JPH0547710B2 JPH0547710B2 (en) | 1993-07-19 |
Family
ID=14689172
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP11652090A Granted JPH0414518A (en) | 1990-05-02 | 1990-05-02 | Method for constructing new retaining wall at old retaining wall position on neighboring line |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0414518A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013155592A (en) * | 2012-01-27 | 2013-08-15 | Takuzo Hanada | Demolition method for border proximity underground concrete construction body |
CN104164879A (en) * | 2013-05-16 | 2014-11-26 | 辛鹏 | Wall footing and foundation pit support dismantling device |
CN110259182A (en) * | 2019-04-26 | 2019-09-20 | 安徽省公路桥梁工程有限公司 | The construction method of retaining wall ecology dismounting structure |
JP2019206860A (en) * | 2018-05-30 | 2019-12-05 | 花田 卓蔵 | Demolition method of underground structure |
JP2020037777A (en) * | 2018-09-03 | 2020-03-12 | 花田 卓蔵 | Method for demolishing underground structure in contact with building |
CN111139838A (en) * | 2020-01-04 | 2020-05-12 | 中亿丰建设集团股份有限公司 | Treatment method for long-standing ultra-deep foundation pit in soft soil area |
-
1990
- 1990-05-02 JP JP11652090A patent/JPH0414518A/en active Granted
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013155592A (en) * | 2012-01-27 | 2013-08-15 | Takuzo Hanada | Demolition method for border proximity underground concrete construction body |
CN104164879A (en) * | 2013-05-16 | 2014-11-26 | 辛鹏 | Wall footing and foundation pit support dismantling device |
JP2019206860A (en) * | 2018-05-30 | 2019-12-05 | 花田 卓蔵 | Demolition method of underground structure |
JP2020037777A (en) * | 2018-09-03 | 2020-03-12 | 花田 卓蔵 | Method for demolishing underground structure in contact with building |
CN110259182A (en) * | 2019-04-26 | 2019-09-20 | 安徽省公路桥梁工程有限公司 | The construction method of retaining wall ecology dismounting structure |
CN110259182B (en) * | 2019-04-26 | 2021-03-19 | 安徽省公路桥梁工程有限公司 | Construction method of ecological demolition structure of retaining wall |
CN111139838A (en) * | 2020-01-04 | 2020-05-12 | 中亿丰建设集团股份有限公司 | Treatment method for long-standing ultra-deep foundation pit in soft soil area |
Also Published As
Publication number | Publication date |
---|---|
JPH0547710B2 (en) | 1993-07-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111119904A (en) | Construction Method of Tunnel in Karst Section of Weak Surrounding Rock | |
EP0136355A1 (en) | Method and apparatus for constructing reinforced concrete walls in the earth | |
KR100289256B1 (en) | Tunnel construction method in shallow toffee area | |
JPH0414518A (en) | Method for constructing new retaining wall at old retaining wall position on neighboring line | |
JP2000291398A (en) | Underground structure and its construction method | |
JP2004060266A5 (en) | ||
CN112813996A (en) | Construction method of deepwater cast-in-place concrete cofferdam | |
JPS60119816A (en) | Formation of continuous pile | |
JPH03257215A (en) | Pile constructing method | |
JP2004218378A (en) | Removing method for existing pile | |
JPS6018769B2 (en) | Construction method of underground structure | |
JP3076827B2 (en) | Seismic support pile | |
JPH0584773B2 (en) | ||
JPS6062327A (en) | Construction of underwater continuous wall | |
JP3238390U (en) | shelter | |
JPS62220616A (en) | Construction work for underground space | |
JPH05125891A (en) | Large-diameter underground wall, construction method thereof, and pipe digging device | |
JPH0434209Y2 (en) | ||
JPH04194277A (en) | Building demolition method | |
JP3646698B2 (en) | Construction method for underground structures | |
JPH04309694A (en) | Underground space construction method | |
JPH0442493B2 (en) | ||
JP2000110158A (en) | Retaining wall construction method using diagonal walls | |
JPH11256604A (en) | Burying method | |
JPH0442356Y2 (en) |