JPH0381457A - Work scaffold in deep foundation method - Google Patents

Work scaffold in deep foundation method

Info

Publication number
JPH0381457A
JPH0381457A JP21604089A JP21604089A JPH0381457A JP H0381457 A JPH0381457 A JP H0381457A JP 21604089 A JP21604089 A JP 21604089A JP 21604089 A JP21604089 A JP 21604089A JP H0381457 A JPH0381457 A JP H0381457A
Authority
JP
Japan
Prior art keywords
scaffold
work
scaffolding
legs
deep foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP21604089A
Other languages
Japanese (ja)
Other versions
JP2681219B2 (en
Inventor
Ryoichi Okimoto
沖本 良一
Masayuki Yano
正行 矢野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP21604089A priority Critical patent/JP2681219B2/en
Publication of JPH0381457A publication Critical patent/JPH0381457A/en
Application granted granted Critical
Publication of JP2681219B2 publication Critical patent/JP2681219B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

PURPOSE:To enable work scaffolds to be set up and removed quickly and safely by piling up scaffold units in order wherein each unit is made up out of a work stand which is smaller in outer diameter than the inner diameter of a vertical shaft and is furnished with a center hole opened for workers to pass through, support legs and of a ladder. CONSTITUTION:Each scaffold unit 1 and 1 is made up out of a work stand 2 which is smaller in outer diameter than the inner diameter of a vertical shaft and is furnished with a center hole 6 opened for workers to pass through, a plurality of legs 3 supporting said stand, and of a ladder 5 provided in the vicinity of the center hole 6. In the second place, the lowermost scaffold unit 1 and 1 is hanged down in order to be set up on the base concrete placed on the bottom of the hole. Following which, the upper scaffold units 1 and 1 are piled up in order so that the respective legs 3 are connected in the vertical direction so as to be fixed. In addition, a crane mast 7 is set up at the uppermost section of the group of the piled-up scaffolds.

Description

【発明の詳細な説明】 〈産業上の利用分野〉 本発明は、深礎工法における簡易な作業足場に関するも
のである。
DETAILED DESCRIPTION OF THE INVENTION <Industrial Application Field> The present invention relates to a simple work scaffold for deep foundation construction.

〈従来の技術〉 直径の大きい杭を構築する場合に、深礎工法が採用され
ている。
<Conventional technology> When constructing piles with a large diameter, the deep foundation method is used.

この工法は、周囲の土砂の崩壊を防護しつつ、作業者が
内部に降りて掘削、排土を行う工法であり、大口径の杭
を、大型の機械を使用せずに構築できるという特徴を備
えている。
This construction method involves workers descending into the interior to excavate and remove soil while protecting the surrounding soil from collapsing.It is characterized by the ability to construct large-diameter piles without the use of large machinery. We are prepared.

〈本発明が解決しようとする問題点〉 しかし掘削完了後の鉄筋組立には、作業性、安全性に問
題があった。
<Problems to be Solved by the Present Invention> However, there are problems in workability and safety when assembling reinforcing bars after excavation is completed.

すなわち、掘削が完了した後には鉄筋を組立なければな
らないが、深さ10メートル以上の坑内で、その周囲に
100kgを越す重量の縦筋やフープ筋を組み立てる作
業は容易ではない。
That is, after excavation is completed, reinforcing bars must be assembled, but it is not easy to assemble vertical bars or hoop bars that weigh more than 100 kg around the reinforcing bars in a mine that is 10 meters or more deep.

そのため、円盤状の足場を上から吊ってその上で作業を
する方法、上下方向に配置したロープに安全帯を取り付
けて作業する方法、などが採用されている。
For this reason, methods such as suspending a disk-shaped scaffold from above and working on it, or attaching safety belts to ropes placed vertically, and so on, have been adopted.

しかし、竪坑の内部に円盤状の足場を水平に吊りさげる
方法では足場を周囲に固定することが困難である。した
がって空中に吊った足場は不安定であって作用性が悪か
った。
However, with the method of horizontally suspending a disc-shaped scaffold inside a shaft, it is difficult to secure the scaffold to the surrounding area. Therefore, scaffolds suspended in the air were unstable and had poor functionality.

また足場が不安定あることから、その下方の孔t+ 底での作業は不可能であった。Also, since the footing is unstable, the hole t+ below it It was impossible to work at the bottom.

ローブと安全帯との組み合わせでは作業者は自分の体を
固定して作業を行う方式である。
The combination of a robe and a safety belt allows the worker to work while securing his or her body.

したがって作業位置を変更する場合にその移動がスムー
ズではなく、作業性がきわめて悪いものであった。
Therefore, when changing the working position, the movement is not smooth, resulting in extremely poor workability.

〈本発明の目的〉 本発明は以上のような問題を解決するためになされたも
ので、作業者も周囲も安全で作業性の良好な、深礎工法
における作業足場を提供することを目的とする。
<Purpose of the present invention> The present invention was made to solve the above-mentioned problems, and its purpose is to provide a work scaffold for the deep foundation construction method that is safe for workers and the surrounding area and has good workability. do.

〈問題点を解決するための手段〉 すなわち本発明は、周囲土砂の崩壊を防止しつつ、垂直
方向に竪坑の掘削を行う深礎工法において使用する足場
であって、1単位の足場単体は、竪坑の内径よりも小さ
い外径を有し、中央に作業者の通過孔を開口した作業板
と、この作業板を支゛持する複数の脚と、中央孔近傍に
設けた梯子とより構成し、この1単位の足場単体を、脚
を上下方向に接続することによって順次積み上げ、積み
上げた足場群の最上部には、クレーンを配置して構成し
た、深礎工法における作業足場である。
<Means for solving the problem> In other words, the present invention is a scaffold used in a deep foundation construction method in which a shaft is excavated in the vertical direction while preventing the collapse of surrounding earth and sand, and one unit of the scaffold is: It consists of a work plate that has an outer diameter smaller than the inner diameter of the shaft and has a passage hole for workers in the center, a plurality of legs that support this work plate, and a ladder installed near the center hole. , this single unit of scaffolding is stacked one by one by connecting the legs in the vertical direction, and a crane is placed at the top of the stacked scaffold group, making it a working scaffold for the deep foundation construction method.

〈本発明の説明〉 以下本発明の詳細な説明する。<Description of the present invention> The present invention will be explained in detail below.

〈イ〉深礎工法 fIIIi工法は、竪坑の掘削に平行してその周囲にラ
イナープレートPを張り付けて周囲の土砂の崩壊を阻止
しつつその孔底を掘削して行く工法である。
<A> Deep foundation construction method The fIIIi construction method is a construction method in which a liner plate P is pasted around the shaft in parallel with the excavation of the shaft, and the bottom of the shaft is excavated while preventing the surrounding earth and sand from collapsing.

〈口〉足場単体 足場単体1は、作業台2と、脚3とより構成する。〈Mouth〉Single scaffolding The scaffolding unit 1 is composed of a workbench 2 and legs 3.

作業台2は金網その他の部材で構成した円盤であり、作
業者がその上で重量物を扱っても破損しないだけの強度
を有する。
The workbench 2 is a disk made of wire mesh and other materials, and has enough strength to not be damaged even when a worker handles a heavy object on it.

この作業台2の外径は、竪坑のライナープレート内径よ
りも小さく形成する。
The outer diameter of this workbench 2 is formed smaller than the inner diameter of the liner plate of the shaft.

作業台2の中央には中央孔6を開口する。A central hole 6 is opened in the center of the workbench 2.

この中央孔6の内径は、作業者が容易に出入りできる寸
法に構成する。
The inner diameter of this central hole 6 is configured to a size that allows an operator to easily enter and exit.

一方、脚3は作業台2の下面に固定した複数の棒状体よ
りなる。
On the other hand, the legs 3 are composed of a plurality of rod-shaped bodies fixed to the lower surface of the workbench 2.

この#3の高さは、作業者の身長よりも多少高く形成す
る。
The height of #3 is formed to be somewhat higher than the height of the worker.

脚3の上端と、その下端とは、順次積み重ねた場合に接
続可能な構造に形成する。
The upper end of the leg 3 and its lower end are formed in a structure that can be connected when stacked one after another.

脚3の一部には複数の横材4を配置し、脚3間の補強を
行う。
A plurality of cross members 4 are arranged on a part of the legs 3 to provide reinforcement between the legs 3.

〈ハ〉梯子 脚3の間には梯子5を設置する。<C> Ladder A ladder 5 is installed between the legs 3.

この梯子5の設置位置は作業台2の中央孔6がら昇降す
る場合に使用できる位置である。
This ladder 5 is installed at a position where it can be used when going up and down through the central hole 6 of the workbench 2.

〈本発明の作用〉 以下、本発明の作用を詳細に説明する。<Action of the present invention> Hereinafter, the operation of the present invention will be explained in detail.

〈イ〉掘削時 竪坑の孔底を掘削、排土し、その進捗にしたがって周囲
の壁面にライナープレートPを組み立てて土砂の崩壊を
防止する。
<B> During excavation, the bottom of the shaft is excavated and earth is removed, and as the work progresses, liner plates P are assembled on the surrounding walls to prevent earth and sand from collapsing.

〈口〉足場単体の組み立て 孔底が所定の深さに達したら、基礎のコンクリートを打
設する。
<Entrance> When the bottom of the scaffold assembly hole reaches the specified depth, concrete for the foundation is poured.

そして基礎コンクリートの上に第1段の足場単体1を設
置する。
Then, the first stage scaffolding unit 1 is installed on the foundation concrete.

この設置の作業は、竪坑の上部がら足場単体1を吊り降
ろして行う。
This installation work is carried out by suspending the scaffolding unit 1 from the upper part of the shaft.

第1段の足場単体1の据え付けが終わったら、その上に
第2段の足場車体lを吊りおろす。
After the installation of the first-stage scaffold unit 1 is completed, the second-stage scaffolding vehicle body l is lowered onto it.

そして下段の足場単体1の脚3の頭部に、上段の足場単
体1の脚の下端を嵌合し、両者を一体に固定する。
Then, the lower end of the leg of the upper scaffold 1 is fitted into the head of the leg 3 of the lower scaffold 1, and the two are fixed together.

こうして順次脚を上下方向に接続して上方に向けて組み
立てて行く。
In this way, the legs are sequentially connected in the vertical direction and assembled upward.

そして数段ごとに周辺のライナープレートPなどに埋め
込んだアンカーとワイヤーなどで連結して安定を図る。
Then, every few stages are connected to anchors embedded in the surrounding liner plate P etc. using wires, etc. to ensure stability.

〈ハ〉クレーンの組み立て 足場単体10組み立ては、その作業台2が地表に近付い
た位置で完了する。
<C> Crane assembly The assembly of the single scaffold 10 is completed when the work platform 2 approaches the ground surface.

最上部の作業台2は、1まぼ地表と同一の高さに設定す
る。
The topmost workbench 2 is set at the same height as the ground surface.

そして最上部の作業台2よりも上には、クレーンマスト
7を設置する。
A crane mast 7 is installed above the topmost workbench 2.

このクレーンマスト7は、足場単体1の脚3のみで形成
した枠体によって構成することができる。
This crane mast 7 can be constituted by a frame body formed only from the legs 3 of the single scaffold 1.

このクレーンマスト7の上端には、垂直軸を取り付け、
この垂直軸を中心に水平面で回転可能なアーム9を水平
に取り付ける。
A vertical shaft is attached to the upper end of this crane mast 7,
An arm 9 rotatable in a horizontal plane about this vertical axis is mounted horizontally.

このアーム9の一端にはカウンターウェイトを登載し、
他方には移動可能な状態で、ホイストなどの巻き上げ機
を取り付ける。
A counterweight is mounted on one end of this arm 9,
A hoist or other hoist is attached to the other side so that it can be moved.

〈ハ〉鉄筋の組み立て 以上の作業によって、足場単体1の積み上げによる全体
足場が、竪坑内に完了すれば、各段の作業台2上に作業
者を配置し、上方から鉄筋を順次吊りおろす。
<C> After the entire scaffolding by stacking the scaffolding units 1 is completed in the shaft by the work beyond assembling the reinforcing bars, workers are placed on the work benches 2 at each stage and the reinforcing bars are successively lowered from above.

この場合の鉄筋の扱いは、クレーンマスト7上のアーム
9によって行うことができるから、作業は安全で迅速で
ある。
In this case, the reinforcing bars can be handled by the arm 9 on the crane mast 7, so the work is safe and quick.

作業者は作業台2の上で、アーム9から吊り降ろされた
鉄筋を、安定した状態や姿勢で取り扱い、目前に位置す
る縦横の鉄筋群の結束を行うことができる。
On the workbench 2, the worker can handle the reinforcing bars suspended from the arm 9 in a stable state and posture, and can bind the vertical and horizontal reinforcing bars located in front of him.

同じ貰さでの作業は、作業台2上を壁面に沿って移動す
るだけで処理することができる。
Work on the same item can be done by simply moving on the workbench 2 along the wall surface.

高さが相違する場所での結束作業は、梯子5を使用して
中央孔6から他の段の足場単体1に昇降して作業を継続
する。
Binding work at locations with different heights is continued by using a ladder 5 to go up and down from the central hole 6 to the scaffolding unit 1 at another level.

〈二〉足場の解体 鉄筋群の組み立てが完了すれば、コンクリートを打設す
るために足場を撤去する。
(2) Dismantling the scaffolding Once the reinforcing bars have been assembled, the scaffolding will be removed to allow concrete to be poured.

その場合にも全体足場は複数段の足場単体lによって構
成しであるから、きわめて容易に上方へ釣り上げて解体
することができる。
Even in that case, since the entire scaffold is composed of multiple stages of single scaffolds 1, it can be lifted upward and dismantled very easily.

〈実施例〉 以上の足場は、たとえば内径3メートル、深さ20メ一
トル程度の深礎において使用できる。
<Example> The scaffold described above can be used, for example, in a deep foundation with an inner diameter of 3 meters and a depth of about 20 meters.

ライナープレートの内側に一段に鉄筋を組むとすると、
作業台2縁端とライナープレートPの内側には30セン
チ程度の間隔を設けておけば作業上で問題はない。
If you install reinforcing bars in one step inside the liner plate,
As long as there is a gap of about 30 cm between the edge of the workbench 2 and the inside of the liner plate P, there will be no problem in working.

脚3の長さ、すなわち上段の作業台2と下段の作業台2
との距離は、1.8〜2.0メ一トル程度に構成するこ
とができる。
The length of the legs 3, that is, the upper workbench 2 and the lower workbench 2
The distance can be set to about 1.8 to 2.0 meters.

く本発明の効果〉 本発明は以上のような構成からなるから、次のような効
果を得ることができる。
Effects of the Present Invention Since the present invention has the above configuration, the following effects can be obtained.

〈イ〉孔底の掘削が完了したら、足場単体を順次吊りお
ろして一度に全体の足場を組み立てることができる。
(a) Once the bottom of the hole has been excavated, the entire scaffold can be assembled at once by lowering the individual scaffolds one by one.

したがって、竪坑内で部材を組み立てる方法に比較して
作業が迅速で確実である。
Therefore, compared to the method of assembling parts in a shaft, the work is faster and more reliable.

〈口〉足場単体は工場で製造した既威品である。<Mouth> The scaffold itself is an existing item manufactured in a factory.

したがって現場で組み立する方法に比較して足場の信頼
性が高く、安全に作業を行うことができる。
Therefore, compared to on-site assembly methods, the scaffolding is more reliable and allows for safer work.

〈ハ〉足場は壁面に沿って配置してあり、竪坑の中心は
中央孔による空間が確保しである。
<C> Scaffolding is placed along the wall, and a space is secured in the center of the shaft by a central hole.

したがって孔底の中心部分の作業は安全に行うことがで
きる。
Therefore, work on the central part of the hole bottom can be carried out safely.

〈二〉足場の組み立てが完了したらその上方にクレーン
のマストを組み立てることができる。
(2) Once the scaffolding is completed, the crane mast can be assembled above it.

したがって、狭い作業空間の中で、重量の大きな鉄筋群
を安全、迅速に扱って結束作業を行うことができる。
Therefore, it is possible to safely and quickly handle and bundle a group of heavy reinforcing bars in a narrow work space.

〈ホ〉鉄筋の組み立てが完了したら足場を解体する必要
がある。
<E> Once the reinforcing bars have been assembled, the scaffolding will need to be dismantled.

その場合にも足場単体を順次引き揚げれば簡単に解体で
きるから作業は安全で簡単である。
Even in that case, the work is safe and easy because the scaffolding can be easily dismantled by pulling it up one by one.

【図面の簡単な説明】[Brief explanation of drawings]

第1図:本発明の足場を構成する単体の斜視図第2図:
その使用状態の説明図 第3図:作業状態の説明図
Fig. 1: Perspective view of a single unit constituting the scaffold of the present invention Fig. 2:
An explanatory diagram of its usage condition Figure 3: An explanatory diagram of its working condition

Claims (1)

【特許請求の範囲】[Claims] (1)周囲土砂の崩壊を防止しつつ、垂直方向に竪坑の
掘削を行う深礎工法において使用する足場であって、 1単位の足場単体は、竪坑の内径よりも小さい外径を有
し、 中央に作業者の通過孔を開口した作業板と、この作業板
を支持する複数の脚と、 中央孔近傍からほぼ垂直に設けた梯子とより構成し、 この1単位の足場単体を、脚を上下方向に接続すること
によって順次積み上げ、 積み上げた足場群の最上部には、クレーンを配置して構
成した、 深礎工法における作業足場
(1) Scaffolding used in the deep foundation method of vertically excavating a shaft while preventing the collapse of surrounding earth and sand, where one unit of scaffolding has an outer diameter smaller than the inner diameter of the shaft, It consists of a work plate with a hole for workers to pass through in the center, multiple legs to support this work plate, and a ladder installed almost perpendicularly from near the center hole. Work scaffolding used in the deep foundation construction method, in which scaffolds are connected vertically and stacked one after another, and a crane is placed at the top of the stacked scaffolding group.
JP21604089A 1989-08-24 1989-08-24 Working scaffolding in the deep foundation method Expired - Lifetime JP2681219B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21604089A JP2681219B2 (en) 1989-08-24 1989-08-24 Working scaffolding in the deep foundation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21604089A JP2681219B2 (en) 1989-08-24 1989-08-24 Working scaffolding in the deep foundation method

Publications (2)

Publication Number Publication Date
JPH0381457A true JPH0381457A (en) 1991-04-05
JP2681219B2 JP2681219B2 (en) 1997-11-26

Family

ID=16682339

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21604089A Expired - Lifetime JP2681219B2 (en) 1989-08-24 1989-08-24 Working scaffolding in the deep foundation method

Country Status (1)

Country Link
JP (1) JP2681219B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH061599U (en) * 1992-06-11 1994-01-14 日立造船エンジニアリング株式会社 Temporary scaffolding device inside the tank
JP2006307506A (en) * 2005-04-27 2006-11-09 Gifu Kogyo Co Ltd Scaffolding

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH061599U (en) * 1992-06-11 1994-01-14 日立造船エンジニアリング株式会社 Temporary scaffolding device inside the tank
JP2006307506A (en) * 2005-04-27 2006-11-09 Gifu Kogyo Co Ltd Scaffolding

Also Published As

Publication number Publication date
JP2681219B2 (en) 1997-11-26

Similar Documents

Publication Publication Date Title
JP2021514437A (en) Shaft slip foam device and method
JPH0381457A (en) Work scaffold in deep foundation method
JP2681218B2 (en) Working scaffolding in the deep foundation method
CN211171941U (en) Manual hole digging operation frame based on full-sleeve full-slewing drilling machine
JP2855210B2 (en) Work scaffolding in the deep foundation method
JP3220397B2 (en) Elevating scaffold
JPH09177070A (en) Method and device for placing of steel bar cage for deep foundation
JP2002038475A (en) Construction method of caisson type pile
JPH0730564B2 (en) Construction method of underground structure
JP2000120367A (en) External fastening liner plate and method for using it
JP3532161B2 (en) Tower construction machine and tower construction method
JPH0687557U (en) Scaffolding for deep foundation work
JP3243539B2 (en) Equipment for setting up piles
CN215167838U (en) Movable overhung suspension type operating platform
JP2013011119A (en) Construction method of multi-layer building and lifting device for continuous layer foothold used therefor
JPH11287040A (en) Hanging stairs
JP2843042B2 (en) Steel framing unit scaffolding method
JPH10140839A (en) Device for vertically hoisting form material and pipe support
JPH028106B2 (en)
JP2817208B2 (en) Construction method of rack steel frame
JPS6152305B2 (en)
JPH04153460A (en) Constructing method for building, and its equipment
JPS6322192Y2 (en)
JPH0715187B2 (en) Building construction method
JP2761528B2 (en) How to build structures