JPH0355405A - Boiler installation working space structure - Google Patents
Boiler installation working space structureInfo
- Publication number
- JPH0355405A JPH0355405A JP19090889A JP19090889A JPH0355405A JP H0355405 A JPH0355405 A JP H0355405A JP 19090889 A JP19090889 A JP 19090889A JP 19090889 A JP19090889 A JP 19090889A JP H0355405 A JPH0355405 A JP H0355405A
- Authority
- JP
- Japan
- Prior art keywords
- boiler
- floor
- work
- temporary
- installation work
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000009434 installation Methods 0.000 title claims abstract description 37
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 9
- 239000010959 steel Substances 0.000 claims abstract description 9
- 238000005192 partition Methods 0.000 claims description 4
- 238000000034 method Methods 0.000 abstract description 3
- 238000010276 construction Methods 0.000 description 9
- 230000000694 effects Effects 0.000 description 6
- 238000010248 power generation Methods 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 230000003111 delayed effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は、ボイラの建設におけるボイラ据付作業スペー
ス構造に関する。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a boiler installation work space structure in boiler construction.
ボイラの形式には種々あるが、このうち火力発電用のボ
イラの大きさは、高さ90m1重さ15.000tにも
及ぶ。There are various types of boilers, but boilers for thermal power generation have a height of 90 m and a weight of 15,000 tons.
このような火力発電用のボイラの建設を行うには、まず
ボイラの全体を包囲する骨組構造物を鉄骨等により組み
立てる。ボイラの主要部はボイラケーシングによって被
覆されている。主要部は、火炉とボイラケージ部とに分
けられておりこれらは隣接して配置されている。ところ
で、ボイラの稼動時には、ボイラケーシングが高温とな
るため、この高温による伸びの影響を防止する手段とし
て、骨組構造物の天井部に鉄骨の大梁を配設し、この大
梁にボイラケーシングの上端を吊り下げて固定している
。従って、ボイラを組み立てながら据え付けるには、ボ
イラケーシングの上端となる部材を吊り揚げて天井大梁
に取り付けた後、順次部材、機器等を吊り揚げて上端か
ら下端へとボイラケーシング及びこれに被覆されるボイ
ラ本体の据付作業を行うことになる。To construct such a boiler for thermal power generation, first, a frame structure surrounding the entire boiler is assembled using steel frames or the like. The main part of the boiler is covered by a boiler casing. The main part is divided into a furnace and a boiler cage part, which are arranged adjacent to each other. By the way, when the boiler is in operation, the boiler casing becomes hot, so as a means to prevent the effects of elongation due to this high temperature, a large steel beam is installed on the ceiling of the frame structure, and the top end of the boiler casing is attached to this large beam. It is hung and fixed. Therefore, in order to install the boiler while assembling it, the upper end of the boiler casing is hoisted up and attached to the ceiling girder, and then the members, equipment, etc. are hoisted one after another and the boiler casing and its covering are lifted from the upper end to the lower end. Installation work will be carried out on the boiler itself.
しかしながら、ボイラケージ部側では、ボイラケージ部
における耐圧部の据付作業のみならずその水圧試験が完
了しないと、その下方に配置される下部機器の据付作業
ができない。すなわち、骨組構造物の床面は、ボイラケ
ーシングやボイラ本体の上部部材、機器等の吊り揚げ用
の作業スペースとして占有され、更に、ボイラ上部の建
設現場から部材、機器等が落下した際の措置が充分では
ない。従って、床面で据付作業を行うことができず下部
機器の据付作業が遅れ工期が長期化するという問題があ
った。However, on the boiler cage side, unless not only the installation work of the pressure-resistant part in the boiler cage part but also the water pressure test is completed, the installation work of the lower equipment disposed below the boiler cage part cannot be performed. In other words, the floor surface of the frame structure is occupied as a work space for hoisting the boiler casing, upper parts of the boiler body, equipment, etc., and also as a work space for lifting parts, equipment, etc. from the construction site above the boiler. is not enough. Therefore, there is a problem in that the installation work cannot be performed on the floor, and the installation work of the lower equipment is delayed, prolonging the construction period.
本発明は上記事実を考慮し、骨組構造物の床面での作業
を可能とすることにより、工期を短縮することができる
ボイラ据付作業スペース構造を得ることが目的である。The present invention has been made in consideration of the above-mentioned facts, and an object of the present invention is to obtain a boiler installation work space structure that can shorten the construction period by making it possible to work on the floor of a frame structure.
請求項(1)記載の発明は、ボイラ本体の上部に配置さ
れるボイラケージ部の耐圧部を鉄骨梁へ吊り下げ、前記
耐圧部へ順次前記ボイラケージ部の下方に配設される下
部機器を吊り下げながら据え付けるためのボイラ据付作
業スペース構造であって、前記ボイラ本体の高さ方向中
間部に前記作業スペースを上下方向に仕切る仮設作業床
を設けたことを特徴としている。The invention described in claim (1) suspends a pressure-resistant part of a boiler cage part disposed in an upper part of a boiler main body from a steel beam, and suspends lower equipment arranged below the boiler cage part in sequence from the pressure-resistant part. This is a boiler installation work space structure for installing the boiler while the boiler is being installed, and is characterized in that a temporary work floor is provided in the middle part of the boiler body in the height direction to partition the work space in the vertical direction.
請求項(2)記載の発明は、請求項(1)記載の前記仮
設作業床において、前記ボイラケージ部の耐圧部と下部
機器との間に配設され、前記ボイラケージ部の耐圧部の
据付作業と前記下部機器の据付作業とを分離して作業可
能としたことを特徴としている。The invention set forth in claim (2) is arranged between the pressure-resistant part of the boiler cage part and the lower equipment in the temporary work floor set forth in claim (1), and includes an installation work of the pressure-resistant part of the boiler cage part. The present invention is characterized in that the work for installing the lower equipment can be performed separately.
請求項(1)記載の発明では、ボイラ本体の高さ方向中
間部に作業スペースを上下方向に仕切る仮設作業床が設
けられるので、上方作業スペースの据付作業と下方作業
スペースの据付作業とは別個に行うことができる。上方
作業スペースでは仮設作業床に部材、機器等を載せた後
吊り揚げて鉄骨梁に順次据え付けられる。下方作業スペ
ースではボイラ本体の下端、例えば床に部材、機器等を
そのまま搬入して順次積み上げることにより据え付けら
れる。この時、下方作業スペースの上部には仮設作業床
が存在しているので、上方作業スペースから落下物が落
下する場合にも安全に作業を行える。In the invention described in claim (1), a temporary work floor is provided in the middle part of the boiler body in the height direction to partition the work space vertically, so the installation work for the upper work space and the installation work for the lower work space are performed separately. can be done. In the upper work space, parts and equipment are placed on a temporary work floor and then lifted and installed on the steel beams one after another. In the lower working space, members, equipment, etc. are brought in as they are and stacked one after another on the lower end of the boiler main body, for example on the floor, for installation. At this time, since there is a temporary work floor above the lower work space, work can be carried out safely even if objects fall from the upper work space.
また、請求項(2)記載の発明では、前記仮設作業床が
ボイラケージ部の耐圧部と下部機器との間に配設される
ので、特に工期が長期化する前記ボイラケージ部の耐圧
部の据付作業及び水圧試験等と前記下部機器の据付作業
とを分離して同時に行うことができる。これにより、工
期は大幅に短縮されることになる。Further, in the invention as set forth in claim (2), since the temporary working floor is disposed between the pressure-resistant part of the boiler cage part and the lower equipment, the installation work of the pressure-resistant part of the boiler cage part, which requires a particularly long construction period, can be carried out. Also, the water pressure test, etc. and the installation work of the lower equipment can be performed separately and at the same time. This will significantly shorten the construction period.
第1図には、本実施例に係るボイラ据付作業スペース構
造を用いて建設されるボイラ10が示されている。この
ボイラ10の外周は、骨組構造物12とされており、ボ
イラケーシング14を包囲するように配設されている。FIG. 1 shows a boiler 10 constructed using the boiler installation work space structure according to this embodiment. The outer periphery of this boiler 10 is made into a frame structure 12, which is arranged so as to surround a boiler casing 14.
なお、第l図中外壁は省略されている。骨組構造物12
は、鉄骨柱16、鉄骨梁18、床20を主要部材として
構或されている。また、骨組構造物12の天井部には、
4本の天井大粱22が配設されている。この4本の天井
大粱22に、ボイラ本体を収容したボイラケーシングl
4の上端が吊り下げられた状態で固定されている。Note that the outer wall is omitted in Figure 1. Frame structure 12
is constructed with steel columns 16, steel beams 18, and a floor 20 as main members. In addition, on the ceiling of the frame structure 12,
Four ceiling slats 22 are arranged. The boiler casing l that houses the boiler body is placed in these four ceiling casings 22.
4 is fixed in a suspended state.
ボイラ本体は、第2図に示される如く、その左側床面2
OA上方には火炉Aが据え付けられている。この火炉A
と隣り合うように第2図右側床面2OB上方には、ボイ
ラケージ部24及び下部機器Cが配設されている。ボイ
ラケージ部24には、再熱器、1次加熱器、節炭器等の
耐圧部が据え付けられている。また、下部機器Cには、
1次空気予熱器等が据え付けられている。ここで、火炉
Aの据付作業とボイラケージ部24側の据付作業とは、
別個に行われるようになっている。As shown in Fig. 2, the boiler body is located on the left floor surface 2.
Furnace A is installed above the OA. This furnace A
A boiler cage section 24 and lower equipment C are arranged above the floor surface 2OB on the right side of FIG. 2 so as to be adjacent to each other. The boiler cage section 24 is equipped with pressure-resistant sections such as a reheater, a primary heater, and a energy saver. In addition, in the lower device C,
A primary air preheater etc. are installed. Here, the installation work of the furnace A and the installation work on the boiler cage part 24 side are as follows:
It is supposed to be done separately.
前記ボイラケージ部24と下部機器Cとの間には、仮設
作業床26が配設されている。第4図に示される如く、
この仮設作業床26は、複数のプレート28が鉄骨梁3
0の上面に仮接合されることにより形或されている。前
記仮設作業床26が配設される範囲は、平面視で下部機
器C及び下部機器Cに取り付けられている2次空気予熱
器32を隠す範囲となっている。また、第3図に示され
る如く、仮設作業床26が配設される高さH2は、本実
施例では骨組構造物l2の全体の高さHl(81m)の
ほぼ中間である約37mとされており、これにより作業
スペースは上下方向に仕切られている。以下、上方作業
スペース、下方作業スペースという。A temporary work floor 26 is provided between the boiler cage section 24 and the lower equipment C. As shown in Figure 4,
This temporary work floor 26 has a plurality of plates 28 attached to the steel beams 3.
The shape is formed by temporarily joining the top surface of 0. The range in which the temporary work floor 26 is arranged is a range that hides the lower equipment C and the secondary air preheater 32 attached to the lower equipment C in a plan view. Further, as shown in FIG. 3, the height H2 at which the temporary work floor 26 is installed is approximately 37 m, which is approximately the middle of the entire height Hl (81 m) of the frame structure l2 in this embodiment. This allows the work space to be partitioned vertically. Hereinafter, they will be referred to as the upper work space and the lower work space.
仮設作業床26により仕切られた上方作業スペースでポ
イラケージ部24の耐圧部の据付作業を行う場合の作業
手順の一例を、第5図を用いて説明する。トラッククレ
ーン34で部材、機器等を台車36に載せた状態で第5
図矢印A方向に吊り揚げた後、仮設作業床26の上に載
せる。次に、第5図矢印B方向に横引した後、ボイラ1
0の建設時に骨組構造物12上に設置される揚重機38
で第5図矢印C方向に吊り揚げながら所定の位置に順次
部材、機器等を据え付けていく。An example of the work procedure when installing the pressure-resistant part of the poiler cage part 24 in the upper work space partitioned off by the temporary work floor 26 will be described with reference to FIG. With the truck crane 34 loading parts, equipment, etc. onto the truck 36, the fifth
After lifting it in the direction of arrow A in the figure, it is placed on the temporary work floor 26. Next, after pulling horizontally in the direction of arrow B in Fig. 5, boiler 1
Lifting machine 38 installed on frame structure 12 during construction of 0
While hoisting it up in the direction of arrow C in Fig. 5, parts, equipment, etc. are successively installed at predetermined positions.
一方、仮設作業床26により仕切られた下方作業スペー
スで下部機器Cの据付作業を行う場合は、床面2OB上
の所定の位置に部材、機器等をそのまま搬入して据え付
ければよい。On the other hand, when installing the lower equipment C in the lower work space partitioned by the temporary work floor 26, the members, equipment, etc. may be carried in and installed as they are at predetermined positions on the floor surface 2OB.
ボイラ10の据付時、火炉Aとボイラケージ部24とは
、高さ方向位置で互いに干渉されないので、同時に据付
作業を行うことができる。一方、ボイラケージ部24と
下部機器Cとは、高さ方向位置が同一となるため、本実
施例ではこれらの間を仮設作業床26で仕切り、上方作
業スペースと下方作業スペースとを確保した。この仮設
作業床26は、平面視で下部機器C及び2次空気予熱器
32等が据え付けられるスペースを隠している。When installing the boiler 10, the furnace A and the boiler cage part 24 do not interfere with each other in the height direction, so that the installation work can be performed at the same time. On the other hand, since the boiler cage section 24 and the lower equipment C are at the same height, in this embodiment, a temporary work floor 26 is used to partition them, thereby securing an upper work space and a lower work space. This temporary work floor 26 hides the space where the lower equipment C, the secondary air preheater 32, etc. are installed in plan view.
このため、上方作業スペースでの作業中に誤って部材、
機器等を落下させても、下方作業スペースへは至らず、
仮設作業床26上で受け止めることができる。これによ
り、下方作業スペースの作業の安全性が確保される。For this reason, parts may be accidentally removed while working in the upper work space.
Even if equipment is dropped, it will not reach the work space below.
It can be received on the temporary work floor 26. This ensures the safety of work in the lower work space.
また、仮設作業床26を配設することによりボイラケー
ジ部24の耐圧部の据付作業はトラ・ンククレーン34
、揚重機38等を用いて行われ、下部機器Cの据付作業
はそのまま床面2OBに搬入して据付作業が行われるの
で、ボイラケージ部24の耐圧部の据付作業と下部機器
Cの据付作業とを分離して同時に行うことができる。従
って、必要とされる工期も半減され、各々の工程も圧迫
されずに作業を進めることができる。In addition, by providing a temporary work floor 26, installation work of the pressure-resistant part of the boiler cage part 24 can be carried out using a truck crane 34.
, using a lifting machine 38, etc., and the lower equipment C is carried directly onto the floor 2OB and the installation work is performed, so the installation work of the pressure-resistant part of the boiler cage section 24 and the installation work of the lower equipment C are performed. can be done separately and at the same time. Therefore, the required construction period is halved, and each process can be carried out without stress.
なお、仮設作業床26の上方作業スペース及び下方作業
スペースでの据付作業が大概終了した時点で、前記仮設
作業床26を撤去しながらボイラケージ部24の耐圧部
及び下部機器Cを接続して、これらの据付作業は完了す
る。When the installation work in the upper and lower working spaces of the temporary working floor 26 is almost completed, the pressure-resistant part of the boiler cage part 24 and the lower equipment C are connected while removing the temporary working floor 26. The installation work has been completed.
以上説明した如く本発明に係るボイラ据付作業スペース
構造は、ボイラ本体の高さ方向中間部に仮設作業床を設
けることにより、作業スペースを上下方向に分離するこ
とができ、下方作業スペースで据付作業を安全に行うこ
とができるという優れた効果を有する。As explained above, the boiler installation work space structure according to the present invention can separate the work space vertically by providing a temporary work floor in the middle part of the boiler body in the height direction, and the installation work can be carried out in the lower work space. It has the excellent effect of being able to be carried out safely.
また、上記効果に加え、前記仮設作業床をボイラケージ
部の耐圧部と下部機器との間に配設すれば、ボイラケー
ジ部の耐圧部の据付作業と下部機器の据付作業とを分離
して上下同時に行うことができ、工期を大幅に短縮する
ことができるという優れた効果を有する。In addition to the above effects, if the temporary work floor is installed between the pressure-resistant section of the boiler cage section and the lower equipment, the installation work of the pressure-resistant section of the boiler cage section and the installation work of the lower equipment can be separated, allowing both the upper and lower parts to be installed simultaneously. It has the excellent effect of significantly shortening the construction period.
第1図は本実施例に係るボイラ据付作業スペース構造を
用いて建設されるボイラを示す概略斜視図、第2図は第
1図の■一■線断面図、第3図はボイラケージ部及び下
部機器の拡大正面図、第4図は第1図IV−rV線断面
図、第5図は第1図に係る作業スペース構造を用いて同
時作業をする場合の一例を示す説明図である。
10・・・ボイラ、
20、2OA,20B・・・床、
24・・・ボイラケージ部、
26・・・仮設作業床、
28・・・プレート。Fig. 1 is a schematic perspective view showing a boiler constructed using the boiler installation work space structure according to this embodiment, Fig. 2 is a sectional view taken along the line ■■ in Fig. 1, and Fig. 3 is a boiler cage section and lower part. FIG. 4 is an enlarged front view of the equipment, FIG. 4 is a sectional view taken along the line IV-rV in FIG. 1, and FIG. 5 is an explanatory diagram showing an example of simultaneous work using the work space structure according to FIG. DESCRIPTION OF SYMBOLS 10... Boiler, 20, 2OA, 20B... Floor, 24... Boiler cage part, 26... Temporary work floor, 28... Plate.
Claims (2)
耐圧部を鉄骨梁へ吊り下げ、前記耐圧部へ順次前記ボイ
ラケージ部の下方に配設される下部機器を吊り下げなが
ら据え付けるためのボイラ据付作業スペース構造であっ
て、 前記ボイラ本体の高さ方向中間部に前記作業スペースを
上下方向に仕切る仮設作業床を設けたことを特徴とする
ボイラ据付作業スペース構造。(1) Boiler installation work in which the pressure-resistant section of the boiler cage section located at the top of the boiler body is suspended from a steel beam, and the lower equipment arranged below the boiler cage section is successively suspended and installed onto the pressure-resistant section. What is claimed is: 1. A boiler installation work space structure, characterized in that a temporary work floor is provided at a heightwise intermediate portion of the boiler main body to partition the work space in the vertical direction.
と下部機器との間に配設され、前記ボイラケージ部の耐
圧部の据付作業と前記下部機器の据付作業とを分離して
作業可能としたことを特徴とする請求項(1)記載のボ
イラ据付作業スペース構造。(2) The temporary work floor is arranged between the pressure-resistant section of the boiler cage section and the lower equipment, and is capable of separating the installation work of the pressure-resistant section of the boiler cage section and the installation work of the lower equipment. The boiler installation work space structure according to claim 1, characterized in that:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19090889A JPH086896B2 (en) | 1989-07-24 | 1989-07-24 | Boiler installation work space structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19090889A JPH086896B2 (en) | 1989-07-24 | 1989-07-24 | Boiler installation work space structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0355405A true JPH0355405A (en) | 1991-03-11 |
JPH086896B2 JPH086896B2 (en) | 1996-01-29 |
Family
ID=16265719
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP19090889A Expired - Fee Related JPH086896B2 (en) | 1989-07-24 | 1989-07-24 | Boiler installation work space structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH086896B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008218418A (en) * | 2008-03-31 | 2008-09-18 | Mitsubishi Rayon Co Ltd | Surface light source and light guide used for same |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106287645A (en) * | 2016-08-30 | 2017-01-04 | 中国能源建设集团安徽电力建设第工程有限公司 | Tower-type furnace buckstay integral installation method |
-
1989
- 1989-07-24 JP JP19090889A patent/JPH086896B2/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008218418A (en) * | 2008-03-31 | 2008-09-18 | Mitsubishi Rayon Co Ltd | Surface light source and light guide used for same |
Also Published As
Publication number | Publication date |
---|---|
JPH086896B2 (en) | 1996-01-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5059357B2 (en) | Construction method of boiler cage section floor | |
JP2007315732A (en) | Installation method of boiler furnace wall | |
US5119598A (en) | Method of construction of top slab for a nuclear containment building | |
JPH0355405A (en) | Boiler installation working space structure | |
JPH11337675A (en) | Reactor-containment vessel and its building method | |
CN208815048U (en) | A kind of State of Blast Furnace is interior to protect canopy support device | |
JPH06323503A (en) | Assembling method for large size suspension type boiler | |
KR100959886B1 (en) | Cavity Wall Liner Construction Method For Nuclear Reactor Containment Building | |
JP3419252B2 (en) | Method of constructing substructure inside PCV | |
JP3462911B2 (en) | Reactor building | |
JP7543088B2 (en) | How to Install Piping | |
JP2927423B2 (en) | Rear transmission block construction method for a suspended boiler | |
JP4006984B2 (en) | Nuclear power plant construction method | |
JPH08194085A (en) | Shroud suspending method for nuclear reactor and shroud structure | |
JP3044822U (en) | Lightweight auxiliary scaffold for boiler furnace hopper | |
SU724669A1 (en) | Method of erecting a vertical structure | |
JPH0513225B2 (en) | ||
JPH0791603A (en) | Assembly parallel progressing method for large suspension type boiler | |
JPH1089858A (en) | Method for installing upper structure of condenser | |
JPH01237493A (en) | Reactor container made of concrete and construction thereof | |
JPH11131811A (en) | Method for constructing building | |
JPS6365398A (en) | Method of assembly construction of nuclear-reactor container | |
JPS6197591A (en) | Container for nuclear reactor | |
JPS6325313B2 (en) | ||
JP2018071161A (en) | Building open-ceiling part construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |