JP4006984B2 - Nuclear power plant construction method - Google Patents

Nuclear power plant construction method Download PDF

Info

Publication number
JP4006984B2
JP4006984B2 JP2001355475A JP2001355475A JP4006984B2 JP 4006984 B2 JP4006984 B2 JP 4006984B2 JP 2001355475 A JP2001355475 A JP 2001355475A JP 2001355475 A JP2001355475 A JP 2001355475A JP 4006984 B2 JP4006984 B2 JP 4006984B2
Authority
JP
Japan
Prior art keywords
nuclear power
reactor
plant
power plant
reactor building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001355475A
Other languages
Japanese (ja)
Other versions
JP2003156583A (en
Inventor
博 高野
孝一 後田
好夫 石名部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP2001355475A priority Critical patent/JP4006984B2/en
Publication of JP2003156583A publication Critical patent/JP2003156583A/en
Application granted granted Critical
Publication of JP4006984B2 publication Critical patent/JP4006984B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Monitoring And Testing Of Nuclear Reactors (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、二つの原子力発電プラントの建設方法に関する
【0002】
【従来の技術】
原子炉建屋内のオペレーティングフロア(以下、単にオペフロと略称表示する。)を二つの原子力発電プラントで共用化したツインプラントと称せられる構成は特開平9−68588号公報に掲載されている。
【0003】
又、二つの原子力発電プラントを隣接して建設する方法として、先行して建設に着手した先行プラントに時間差を置いて後続プラントの建設に着手することで、特定の建設機械や人手が特定の時期に集中することを避けることが、国際公開番号WO97/11467号の再公表特許として公開されている。
【0004】
【発明が解決しようとする課題】
今後、原子炉建屋内のオペフロ等、ツインプラントで共用可能な設備を共用化し、建設時期差を設けて建設する原子力発電所のツインプラントの建設においては、例えば先行プラント側のオペフロでは管理区域が設定され、燃料装荷作業が実施中であり、後続プラント側のオペフロでは非管理区域状態での建設作業を実施するケースが当然発生する。
【0005】
後続プラントの建設を急いで、共用オペフロ全域を管理区域とした場合、後続プラントのオペフロ作業は管理区域内作業時間規制等を受け、建設工程及び建設費面での影響が発生するため、共用オペフロを管理区域/非管理区域に区分する必要がある。
【0006】
また先行プラントが運転中、後続プラントではオペフロ管理区域内で燃料装荷作業中のケースでは、先行プラントの原子炉格納容器内でトラブルが発生した場合に対する、二次格納施設バウンダリの設定方法検討が必要となる。
【0007】
よって、本発明では原子力発電所のツインプラントの建設において最適なバウンダリを伴いながらツインプラントを建設する方法を提供することを主目的とし、さらには、その建設によって造られたツインプラントの運用方法を提供することを副次的目的としている。
【0008】
【課題を解決するための手段】
上記主目的は、先行原子力発電プラントの建設に遅れをもって後続原子力発電プラントを前記先行原子力発電プラントと一体にして建設する原子力発電プラントの建設方法において、前記両原子力発電プラントの境界に原子炉建屋の基礎となるマットから屋根の高さに至る隔壁を形成し、前記隔壁を挟んで両側において前記両原子力発電プラントの建設を進め、前記先行原子力発電プラントが運転中の場合は、オペレーティングフロアより上方の前記隔壁が取り除かれ、且つ前記先行原子力発電プラント側のオペレーティングフロアを隔床で覆った状態として前記後続原子力発電プラントの建設を進め、前記両原子力発電プラントの建設が終えた時点で、前記両原子力発電プラントのオペレーティングフロアが前記両原子力発電プラントの共用のオペレーティングフロアとされる原子力発電プラントの建設方法によって達成される。
【0010】
【発明の実施の形態】
原子力発電所のツインプラントでは、共通の原子炉建屋内に2台の原子炉圧力容器が配備されることになるが、各原子炉圧力容器ごとに原子炉圧力容器を格納する一次格納施設と、その一次格納施設の外側を囲む二次格納施設とが付帯施設とし原子炉建屋内に備わっている。このようなツインプラントでは、原子炉建屋内の使用済燃料プールとオペフロとがツインプラントで共用される合理的な設計となっている。
【0011】
ツインプラントの建設に当たっては、図1の先行原子力発電プラント2(以下、単に先行プラントと表示する。)側の建設着手を先行させ、その着手に月単位又は年単位の時間差を置いて、先行プラントが完成する前に後続プラント3(以下、単に後続プラントと表示する。)側の建設に着手する。先行と後続の各プラントともに建設個所を原子炉圧力容器を格納する施設である原子炉建屋を図面に図示して説明を進める。そのため、先行プラントの建設とは、先行プラントの原子炉建屋の建設とその原子炉建屋内の内部機器の組立て,据付けなどを意味する。後続プラントの建設とは、同じく、後続プラントの原子炉建屋の建設とその原子炉建屋内の内部機器の組立て,据付けなどを意味する。そのため、各図において先行プラント2の表示範囲は、特許請求の範囲の欄で表現される第1の原子炉建屋の範囲を、後続プラント3の表示範囲は、特許請求の範囲の欄で表現される第2の原子炉建屋の範囲を意味する。
【0012】
以下、本発明の実施例による原子力発電所のツインプラントの建設について、原子炉建屋とその内部構成機器を例にあげて図面を参照しながら説明する。図1は先行/後続プラント共用の使用済燃料プール床までの二次格納施設バウンダリ構成のための隔壁5の設定状況を示すものである。先行/後続プラント共用のマット1から共用使用済燃料プール床4までの先行プラント2の建屋工事実施に合わせ、先行プラント2と後続プラント3の二次格納施設バウンダリ構成用の共用使用済燃料プール床4までの隔壁5をマット1から共用使用済燃料プール床4まで設定する。この時期後続プラント3は先行プラント2に対して遅れた時期差を設けての建設となるため、例えば1階床6の高さまでの施工中となる。
【0013】
図2は先行/後続プラントの共用使用済燃料プール床4以上の二次格納施設バウンダリ構成の隔壁設定状況を示すものである。先行プラント2の共用使用済燃料プール床4以上の躯体7から屋根12までの建屋工事施工に合わせ、先行プラント側のオペフロ10と後続プラント3側のオペフロ11の境を通る垂直方向に、共用使用済燃料プール内隔壁8とオペフロ以上の隔壁9を設定する。
【0014】
尚、共用使用済燃料プール内隔壁8と、オペフロ以上の隔壁9は分離可能な構造とする。共用使用済燃料プール内隔壁8とオペフロ以上の隔壁9により先行プラント2のオペフロと後続プラント3との間は遮断され、後続プラント3からの先行プラント2のオペフロへの粉塵侵入等を防止する。尚、後続プラント3は先行プラントに対して時期差を設けての建設となるため、共用使用済燃料プール内隔壁8とオペフロ以上の隔壁9を設定する時期においては後続プラント3側のオペフロ11までの施工中となる。
【0015】
図3は先行プラント2が管理区域設定前のオペフロ機械・電気作業中で、後続プラント3がオペフロ壁から屋根12までの建屋工事実施中の状況を示すものである。先行プラント2の屋根12施工完了前に天井クレーンレール15を搬入・据付け、及び2台の天井クレーン14を搬入して天井クレーンレール15に据付けを完了させ、先行プラント2の屋根12を完成後に天井クレーン14の試験を実施し、また並行してオペフロ以上の隔壁9により後続プラント3側のオペフロ11と先行プラント2のオペフロ10とを仕切り、後続プラントでの建設作業で生じた粉塵の先行プラント2側のオペフロ10への侵入防止を図った上で、2台の天井クレーン14を用い管理区域設定前の炉内工事等のオペフロ機械・電気作業を実施する。後続プラントの建設は先行プラントの建設に対して遅れた時期差を設けての建設となるため、この時期では、後続プラント3ではオペフロ壁17から屋根13までの躯体工事中となる。
【0016】
このようにして、原子炉建屋の基礎となるマット1から屋根12,13の高さにまで各隔壁5,8,9を構築した後に、いずれの隔壁も撤去せずにその隔壁で隔てられた両区画側で建設を個々に進め、両区画側での建設が終了してから、隔壁9を撤去して両プラントのオペフロ11とオペフロ10とを連通して、両プラントで共用するオペフロとする。この隔壁5,8,9は隙間無く上下方向に連続して放射線の透過と放射性物質の往来を防止する機能を有する。
【0017】
建設作業途中でも、両プラントのオペフロ11とオペフロ10とを連通して、両プラントで共用するオペフロとすることで、作業環境を広く確保したり、二台の天井クレーン14を片側のプラントの建設に集中して用いたい場合には、既述の図3の状態から図4−図8の状態に作業を順次進めてゆく。以下に、その順次進める作業について図4−図8に従って説明する。
【0018】
図3の状態から図4の状態へと作業が進むが、図4の状態は先行及び後続プラント共、管理区域設定前のオペフロ機械・電気作業中の状態を示すものである。先行プラント2及び後続プラント3のオペフロで天井クレーン14を2台使用しての作業となるため、まずオペフロ以上の隔壁9を一時撤去し、次に先行プラント2で稼動していた天井クレーン14を後続プラント3でも使用可能とするため、先行プラント2側と後続プラント3側の天井クレーンレール15を連続的につなぐ。このようにして天井クレーン14は先行プラント2と後続プラント3との間をお互いに往来できる状態にして2台の天井クレーン14を先行プラント2側と後続プラント3側とのどちらでも共用できるようにして建設作業を促進する。
【0019】
図5は先行プラント2側で放射線管理区域設定後のオペフロ機械・電気作業中、後続プラント3側では放射線管理区域設定前のオペフロ機械・電気作業中の状態を示すものである。後続プラント3のオペフロを非管理区域に保つため、まず天井クレーンレール15のうち、オペフロ以上の隔壁9の上端部分に設定されていた天井クレーンレール部分を一時撤去する。
【0020】
その後一時撤去しておいたオペフロ以上の隔壁9をオペフロ中央部で共用使用済燃料プール内隔壁8上に再設定する。このことにより、先行プラント2側のオペフロと後続プラントのオペフロとの間を遮断する。尚、天井クレーン14は先行プラント2オペフロ作業用として1台、後続プラント3オペフロ作業用として1台の使用区分として設定する。
【0021】
図6は先行プラント2が運転中、後続プラント3は放射線管理区域設定前のオペフロ機械・電気作業中の状態を示すものである。先行プラント2の原子炉格納容器内トラブル時に対する二次格納施設バウンダリ構成方法として、オペフロ以上の隔壁9を撤去し、先行プラント2側と後続プラント3側との天井クレーンレール15を接続して後続プラント3側の作業を2台の天井クレーン14で推進できるようにする。
【0022】
次に先行プラント2側のオペフロ10上にオペフロ隔床16を設定し、共用使用済燃料プール床4までの隔壁5と、共用使用済燃料プール内隔壁8と、オペフロ隔床16とにより先行プラント2とオペフロ上方の空間及び後続プラント3への境界を遮断するバウンダリを構成する。
【0023】
オペフロ隔床16は、コンクリート製の板を金属板で被覆した板を複数枚並べて構成される。そのオペフロ隔床16の板一枚一枚は、天井クレーン14で取り扱うことができる重さと大きさを有する。そして、並べた板の間にはシールが施される。オペフロ隔床16はそのオペフロ隔床16の下部に漏れ出た放射線や放射性物質がオペフロ隔床16の上部に漏れ出ないようにする機能がある。この実施例では、オペフロ隔床16は共用使用済燃料プールの上も覆っている。
【0024】
オペフロ隔床16を構成する板は天井クレーン14で吊って移動させることができる。その移動によってオペフロから撤去させたりオペフロに敷き詰めたりすることができる。
【0025】
原子力発電プラントのプラント運転を開始した後には、原子炉圧力容器の上蓋を開けて原子炉圧力容器内の核燃料を配置換えしたり新燃料と取り替えたり、あるいは原子炉圧力容器内内部点検を行う時期が到来する。その時期には、原子炉圧力容器の上蓋を開けるという炉開放状態が発生する。炉開放状態では、放射線や放射性物質がオペフロ空間に飛散する可能性があるので、そのオペフロ空間は厳重な放射線管理区域とされる。
【0026】
図7は先行プラント2の運転後の原子炉圧力容器の炉開放、後続プラント3の放射線管理区域設定後のオペフロ機械・電気作業中の状態を示す。後続プラント3の放射線管理区域設定後のオペフロでの機械・電気作業に際し、先行プラント2と後続プラント3のオペフロを分離しない場合、先行プラント2の運転後の原子炉圧力容器の炉開放により、後続プラント3オペフロの放射線量が増加し、規定線量到達時間が早期化し、後続プラント3の管理区域内作業効率が低下する。その低下を抑制するため、まず天井クレーンレール15のうち、オペフロ以上の隔壁9設定範囲部のレールを取り外し、次に一時撤去しておいたオペフロ以上の隔壁9を元の状態に再設定することにより、先行プラント2側のオペフロと後続プラント側のオペフロとを分離区分して、その後に先行プラント2側ではオペフロ隔床16を撤去し、炉開放状態での作業を行い、後続プラント3側では放射線管理区域設定下での機械・電気作業を実施する。
【0027】
炉開放状態は先行プラントと後続プラントとが完成した後に両プラントを運用しているさなかにあっても発生する。例えば、図8の状態である。即ち、図8は先行プラント2の運転後の原子炉圧力容器の炉開放状態,後続プラント3の運転中の状態を示すものである。
【0028】
先行プラント2側で炉開放状態を伴う作業を行っているさなかに運転中の後続プラント3でのトラブルで後続プラント3から放射線や放射性物質がオペフロ上空間に漏れると深刻な状況となることが懸念される。
【0029】
そこで、運転中の後続プラント3の原子炉格納容器内のトラブル時に対する二次格納施設バウンダリの構成方法として、後続プラント3側のオペフロ上にオペフロ隔床16を敷き詰めて各隔壁5,8及びオペフロ隔床16で後続プラント3をオペフロや先行プラント2側から隔離する。このように、共用使用済燃料プール床までの隔壁5と、共用使用済燃料プール内隔壁8と、後続プラント3のオペフロ隔床16により、後続プラント3のバウンダリを構成する。これにより後続プラント3側の原子炉格納容器内のトラブルによる先行プラント2側への放射能漏れを防止する。このように両プラントを運用すれば、両プラント間でオペフロが共用化されオペフロ上空間が両プラント間でつながっていても安全且つ広くオペフロを利用して運転後の保守や核燃料取り扱い作業が実施できる。
【0030】
このようにして、隔壁5,8,9のうち、隔壁5,8はツインプラントの建設終了後も残存して放射線の透過や放射性物質の往来を抑制している。しかし、共用使用済燃料プールを完全に共用するために、隔壁5,8の一部である隔壁5を残存させ、隔壁8を共用使用済燃料プールから撤去する様にしても良い。
【0031】
【発明の効果】
以上のように、本発明の建設方法によれば、オペフロを共用化とする原子力発電所のツインプラントを各プラント間で時期差を設けて建設する際に、建設進捗に応じて隔壁や隔床を用いて放射線や放射性物質や塵埃の拡散をコントロールしながら合理的且つ安全にそのツインプラントを建設できる。
【図面の簡単な説明】
【図1】本発明の実施例による建設初期の原子炉建屋の説明図である。
【図2】本発明の実施例による隔壁設定状況を示す原子炉建屋の説明図である。
【図3】本発明の実施例による先発プラントが管理区域設定前のオペフロ機械・電気作業中で、後続プラントがオペフロ壁から屋根までの建屋工事実施中の状況を示す原子炉建屋の説明図である。
【図4】本発明の実施例による先行及び後続プラント共、管理区域設定前のオペフロ機械・電気作業中の状態を示す原子炉建屋の説明図である。
【図5】本発明の実施例による先行プラントが管理区域設定後のオペフロ機械・電気作業中、後続プラントは管理区域設定前のオペフロ機械・電気作業中の状態を示す原子炉建屋の説明図である。
【図6】本発明の実施例による先行プラントが運転中、後続プラントは管理区域設定前のオペフロ機械・電気作業中の状態を示す原子炉建屋の説明図である。
【図7】本発明の実施例による先行プラントが運転後の原子炉圧力容器の炉開放、後続プラントが管理区域設定後のオペフロ機械・電気作業中の状態を示す原子炉建屋の説明図である。
【図8】本発明の実施例による先行プラントが運転後の原子炉圧力容器の炉開放、後続プラント運転中の状態を示す原子炉建屋の説明図である。
【符号の説明】
1…マット、2…先行プラント、3…後続プラント、4…共用使用済燃料プール床、5…共用使用済燃料プール床までの隔壁、6…後続プラント1階床、7…共用使用済燃料プール床以上の躯体、8…共用使用済燃料プール内隔壁、9…オペフロ以上の隔壁、10…先行プラントのオペフロ、11…後続プラントのオペフロ、12…先行プラント屋根、13…後続プラント屋根、14…天井クレーン、15…天井クレーンレール、16…オペフロ隔床、17…後続プラントオペフロ壁。
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for constructing two nuclear power plants.
[0002]
[Prior art]
Japanese Patent Laid-Open No. 9-68588 discloses a configuration called a twin implant in which an operating floor (hereinafter simply abbreviated as “operation floor”) in a reactor building is shared by two nuclear power plants.
[0003]
In addition, as a method of constructing two nuclear power plants adjacent to each other, a specific construction machine or manpower can be placed at a specific time by starting the construction of the succeeding plant with a time difference from the preceding plant that has begun construction in advance. It has been published as a republished patent of International Publication No. WO97 / 11467.
[0004]
[Problems to be solved by the invention]
In the future, in the construction of nuclear power plant twin implants that will be constructed with a difference in construction time, such as the operation floor inside the reactor building, the facilities that can be shared by the two implants will be shared. Of course, there are cases where fuel loading work is being carried out and construction work is being carried out in an unmanaged area in the operation floor on the subsequent plant side.
[0005]
When the construction of the succeeding plant is rushed and the entire common operation floor is set as the management area, the operation work of the subsequent plant is subject to restrictions on the working time in the management area, and the construction process and construction costs are affected. Need to be divided into managed / unmanaged areas.
[0006]
Also, in cases where the preceding plant is in operation and the subsequent plant is fuel-loaded in the operation control area, it is necessary to study how to set the secondary containment facility boundary in the event of a trouble in the reactor containment vessel of the preceding plant. It becomes.
[0007]
Therefore, the main object of the present invention is to provide a method for constructing a twin implant with an optimum boundary in the construction of the twin implant of a nuclear power plant, and further, an operation method for the twin implant constructed by the construction is provided. It is a secondary purpose to provide.
[0008]
[Means for Solving the Problems]
The main purpose is to provide a nuclear power plant construction method in which a subsequent nuclear power plant is constructed integrally with the preceding nuclear power plant with a delay in the construction of the preceding nuclear power plant. Form a partition from the base mat to the height of the roof, and proceed with the construction of both nuclear power plants on both sides of the partition, and if the preceding nuclear power plant is in operation, When the bulkhead is removed and the operating floor of the preceding nuclear power plant side is covered with a floor, the construction of the subsequent nuclear power plant is proceeded. The operating floor of the power plant is the same for both nuclear power plants. It is of the operating floor is achieved by the construction method of a nuclear power plant.
[0010]
DETAILED DESCRIPTION OF THE INVENTION
In the nuclear power plant twin implant, two reactor pressure vessels will be deployed in a common reactor building, and a primary containment facility for storing a reactor pressure vessel for each reactor pressure vessel, A secondary containment facility that surrounds the primary containment facility is an ancillary facility and is provided inside the reactor building. Such a implant has a rational design in which the spent fuel pool and the operation floor in the reactor building are shared by the implant.
[0011]
In the construction of the two implants, the construction start on the preceding nuclear power plant 2 (hereinafter simply referred to as the preceding plant) in FIG. 1 is preceded, and a time difference in units of months or years is placed at the beginning, and the preceding plant is The construction of the succeeding plant 3 (hereinafter simply referred to as the succeeding plant) is started before the completion of the process. In the preceding and succeeding plants, the reactor building, which is a facility for storing the reactor pressure vessel, will be described with reference to the drawings. Therefore, the construction of the preceding plant means the construction of the reactor building of the preceding plant and the assembly and installation of internal equipment in the reactor building. The construction of the succeeding plant also means the construction of the reactor building of the succeeding plant and the assembly and installation of the internal equipment in the reactor building. Therefore, in each figure, the display range of the preceding plant 2 is expressed by the range of the first reactor building expressed in the column of claims, and the display range of the subsequent plant 3 is expressed by the column of claims. Means the range of the second reactor building.
[0012]
Hereinafter, construction of a nuclear power plant twin implant according to an embodiment of the present invention will be described with reference to the drawings, taking a reactor building and its internal components as examples. FIG. 1 shows the setting state of the partition wall 5 for the secondary containment facility boundary structure up to the spent fuel pool floor shared by the preceding / following plant. The shared spent fuel pool floor for the secondary containment facility boundary construction of the preceding plant 2 and the succeeding plant 3 in accordance with the building construction of the preceding plant 2 from the mat 1 common to the preceding / following plant to the shared spent fuel pool floor 4 The partition walls 5 up to 4 are set from the mat 1 to the shared spent fuel pool floor 4. Since this time subsequent plant 3 is constructed with a delayed time difference with respect to the preceding plant 2, for example, the construction up to the height of the first floor 6 is in progress.
[0013]
FIG. 2 shows the partition setting situation of the secondary containment facility boundary structure of the shared spent fuel pool floor 4 or more of the preceding / following plant. Shared use in the vertical direction passing through the boundary between the operating plant 10 on the preceding plant side and the operating floor 11 on the succeeding plant 3 side, in accordance with the construction work of the building 7 from the common spent spent fuel pool floor 4 of the preceding plant 2 to the roof 12 A partition 8 inside the spent fuel pool and a partition 9 above the operation floor are set.
[0014]
The partition wall 8 in the shared spent fuel pool and the partition wall 9 above the operation floor are separable. The common spent fuel pool partition wall 8 and the partition wall 9 above the operation floor cut off the operation flow of the preceding plant 2 and the subsequent plant 3 to prevent dust from entering the operation floor of the preceding plant 2 from the subsequent plant 3. Since the succeeding plant 3 is constructed with a time difference from the preceding plant, when the common spent fuel pool partition wall 8 and the partition wall 9 above the operation floor are set, the operation plant 11 on the subsequent plant 3 side is reached. Is under construction.
[0015]
FIG. 3 shows a situation in which the preceding plant 2 is in operation and mechanical work before the management area is set, and the subsequent plant 3 is in the process of building construction from the operation floor to the roof 12. Prior to the completion of the construction of the roof 12 of the preceding plant 2, the overhead crane rail 15 is carried in and installed, and the two overhead cranes 14 are carried in to complete the installation on the overhead crane rail 15. The crane 14 was tested, and in parallel, the operation floor 11 on the succeeding plant 3 side and the operation floor 10 on the preceding plant 2 were partitioned by the partition wall 9 above the operation floor, and the preceding plant 2 of the dust generated by the construction work in the succeeding plant. In order to prevent intrusion into the operation floor 10 on the side, operation machines and electrical work such as in-furnace construction before setting the management area are performed using two overhead cranes 14. Since the construction of the succeeding plant is a construction that is delayed with respect to the construction of the preceding plant, at this time, the succeeding plant 3 is under the construction of the casing from the operation floor wall 17 to the roof 13.
[0016]
Thus, after each partition 5, 8, and 9 was constructed from the mat 1 as the foundation of the reactor building to the height of the roofs 12 and 13, each partition was separated by the partition without being removed. Construction is proceeded individually on both compartments, and after the construction on both compartments is completed, the bulkhead 9 is removed, and the operation floor 11 and the operation floor 10 of both plants are communicated to form an operation floor shared by both plants. . The partition walls 5, 8 and 9 have a function of preventing the transmission of radiation and the passage of radioactive substances continuously in the vertical direction without any gap.
[0017]
Even during the construction work, the operation floor 11 and the operation floor 10 of both plants communicate with each other so that the operation floor can be shared by both plants, so that a wide working environment can be secured, or two overhead cranes 14 can be constructed on one side of the plant. If the user wants to concentrate on the operation, the operation is sequentially advanced from the state shown in FIG. 3 to the state shown in FIGS. In the following, the work proceeding in sequence will be described with reference to FIGS.
[0018]
The work progresses from the state of FIG. 3 to the state of FIG. 4, and the state of FIG. 4 shows the state of the operating and electrical work before setting the management area for both the preceding and subsequent plants. Since the operation is performed using two overhead cranes 14 at the operation of the preceding plant 2 and the subsequent plant 3, first, the bulkhead 9 above the operation floor is temporarily removed, and then the overhead crane 14 operating at the preceding plant 2 is replaced. In order to enable use in the succeeding plant 3, the overhead crane rail 15 on the preceding plant 2 side and the succeeding plant 3 side are continuously connected. In this way, the overhead crane 14 can move between the preceding plant 2 and the succeeding plant 3 so that the two overhead cranes 14 can be shared by both the preceding plant 2 side and the succeeding plant 3 side. To promote construction work.
[0019]
FIG. 5 shows a state in which the operating plant / electrical work after setting the radiation control area is performed on the preceding plant 2 side and the operating plant / electrical work is set on the succeeding plant 3 side before setting the radiation management area. In order to keep the operation floor of the succeeding plant 3 in the unmanaged area, first, the overhead crane rail portion set at the upper end portion of the partition wall 9 above the operation floor is temporarily removed from the overhead crane rail 15.
[0020]
Thereafter, the partition wall 9 that has been temporarily removed is reset on the shared spent fuel pool partition wall 8 in the center of the operation floor. As a result, the operation flow on the preceding plant 2 side and the operation flow on the subsequent plant are blocked. In addition, the overhead crane 14 is set as one usage category for the preceding plant 2 operation work and one for the subsequent plant 3 operation work.
[0021]
FIG. 6 shows a state in which the preceding plant 2 is in operation and the succeeding plant 3 is in an operating machine / electrical work before setting the radiation control area. As a secondary containment facility boundary configuration method in case of trouble in the containment vessel of the preceding plant 2, the bulkhead 9 above the operating floor is removed, and the overhead crane rails 15 on the preceding plant 2 side and the succeeding plant 3 side are connected to follow. The work on the plant 3 side can be propelled by two overhead cranes 14.
[0022]
Next, the operation floor 16 is set on the operation floor 10 on the preceding plant 2 side, and the preceding plant is constituted by the partition wall 5 up to the shared spent fuel pool floor 4, the shared spent fuel pool partition wall 8, and the operation floor 16. 2 and the boundary above the operating floor and the boundary to the succeeding plant 3 are configured.
[0023]
The operating floor 16 is configured by arranging a plurality of plates made of a concrete plate covered with a metal plate. Each plate of the operating floor 16 has a weight and a size that can be handled by the overhead crane 14. A seal is applied between the arranged plates. The operating floor 16 has a function of preventing radiation or radioactive material leaking into the lower portion of the operating floor 16 from leaking into the upper portion of the operating floor 16. In this embodiment, the operating floor 16 also covers the shared spent fuel pool.
[0024]
The plates constituting the operating floor 16 can be suspended and moved by the overhead crane 14. By the movement, it can be removed from the operation floor or spread on the operation floor.
[0025]
After starting the nuclear power plant operation, it is time to open the top of the reactor pressure vessel and replace the nuclear fuel in the reactor pressure vessel, replace it with new fuel, or perform an internal inspection of the reactor pressure vessel Will arrive. At that time, a reactor open state occurs in which the top cover of the reactor pressure vessel is opened. When the furnace is open, radiation and radioactive materials may be scattered in the operating space, so that the operating space is a strict radiation control area.
[0026]
FIG. 7 shows a state in which the reactor pressure vessel is opened after the operation of the preceding plant 2 and the operating machine / electric work is being performed after the radiation control area of the succeeding plant 3 is set. If the operation flow of the preceding plant 2 and the succeeding plant 3 is not separated during the mechanical / electrical work in the operation flow after setting the radiation control area of the succeeding plant 3, the reactor pressure vessel is opened after the operation of the preceding plant 2 and the subsequent operation is performed. The radiation dose of the plant 3 operation floor increases, the specified dose arrival time is advanced, and the work efficiency in the management area of the succeeding plant 3 decreases. In order to suppress the decrease, first, remove the rails in the setting range portion of the bulkhead 9 above the operating floor from the overhead crane rail 15, and then reset the bulkhead 9 above the operating floor that has been temporarily removed to the original state. Thus, the operation floor on the preceding plant 2 side and the operation floor on the subsequent plant side are separated and separated, and then the operation floor floor 16 is removed on the preceding plant 2 side, and the operation is performed in the furnace open state. Carry out mechanical and electrical work under the setting of radiation control areas.
[0027]
The furnace open state occurs even when both plants are operating after the preceding plant and the succeeding plant are completed. For example, this is the state of FIG. That is, FIG. 8 shows the reactor open state of the reactor pressure vessel after the operation of the preceding plant 2 and the operation state of the subsequent plant 3.
[0028]
There is concern that radiation or radioactive material leaks from the subsequent plant 3 into the space above the operating floor due to a trouble in the subsequent plant 3 that is in operation while the operation is performed with the furnace open on the preceding plant 2 side. Is done.
[0029]
Therefore, as a method of configuring the secondary containment facility boundary in the event of a trouble in the reactor containment vessel of the subsequent plant 3 that is in operation, the operation floors 16 are spread over the operation floor on the subsequent plant 3 side, and the bulkheads 5 and 8 and the operation floor are arranged. The subsequent plant 3 is isolated from the operation floor and the preceding plant 2 side by the partition 16. Thus, the boundary of the subsequent plant 3 is constituted by the partition wall 5 up to the shared spent fuel pool floor, the shared spent fuel pool inner partition wall 8, and the operation floor 16 of the subsequent plant 3. This prevents leakage of radioactivity to the preceding plant 2 due to a trouble in the reactor containment vessel on the succeeding plant 3 side. If both plants are operated in this way, maintenance after operation and handling of nuclear fuel can be carried out safely and widely using the operating floor even if the operating floor is shared between both plants and the space above the operating floor is connected between the two plants. .
[0030]
In this way, of the partition walls 5, 8, 9, the partition walls 5, 8 remain even after the construction of the implant is completed, thereby suppressing the transmission of radiation and the passage of radioactive materials. However, in order to completely share the shared spent fuel pool, the partition wall 5 which is a part of the partition walls 5 and 8 may be left and the partition wall 8 may be removed from the shared spent fuel pool.
[0031]
【The invention's effect】
As described above, according to the construction method of the present invention, when the nuclear power plant twin implants that share the operation floor are constructed with a time difference between the plants, the partition walls and the floors are used in accordance with the construction progress. The screw implant can be constructed reasonably and safely while controlling the diffusion of radiation, radioactive material and dust.
[Brief description of the drawings]
FIG. 1 is an explanatory diagram of a reactor building at an early stage of construction according to an embodiment of the present invention.
FIG. 2 is an explanatory diagram of a reactor building showing a partition setting state according to an embodiment of the present invention.
FIG. 3 is an explanatory diagram of a reactor building showing a situation in which a starting plant according to an embodiment of the present invention is in operation and electrical work before setting a management area, and a subsequent plant is under construction from the operation floor to the roof. is there.
FIG. 4 is an explanatory diagram of a reactor building showing a state during operation of an operating machine and electrical work before setting a management area for both the preceding and succeeding plants according to the embodiment of the present invention.
FIG. 5 is an explanatory diagram of a reactor building showing a state in which the preceding plant according to the embodiment of the present invention is in the operation machine / electric work after setting the management area, and the subsequent plant is in the operation machine / electric work before setting the management area. is there.
FIG. 6 is an explanatory diagram of a reactor building showing a state in which the preceding plant according to the embodiment of the present invention is in operation and the succeeding plant is in an operation machine / electrical work before setting a management area.
FIG. 7 is an explanatory diagram of a reactor building showing a state in which an operating plant and an electric work are being performed after a preceding plant has been operated and a succeeding plant has been set in a management area according to an embodiment of the present invention. .
FIG. 8 is an explanatory diagram of a reactor building showing a state in which the reactor pressure vessel is opened after the operation of the preceding plant according to the embodiment of the present invention and the subsequent plant is operating.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 ... Mat, 2 ... Predecessor plant, 3 ... Subsequent plant, 4 ... Shared spent fuel pool floor, 5 ... Bulkhead to shared spent fuel pool floor, 6 ... Subsequent plant 1st floor, 7 ... Shared spent fuel pool Body above floor, 8 ... partition wall in shared spent fuel pool, 9 ... partition above operation floor, 10 ... operation floor of preceding plant, 11 ... operation floor of subsequent plant, 12 ... roof of preceding plant, 13 ... roof of subsequent plant, 14 ... Overhead crane, 15 ... overhead crane rail, 16 ... operating floor, 17 ... following plant operating floor.

Claims (9)

第1の原子炉圧力容器を格納する第1の原子炉建屋を有する先行原子力発電プラントと、前記先行原子力発電プラントの建設開始後であってその完成前に建設が開始されて第2の原子炉圧力容器を格納する第2の原子炉建屋を有する後続原子力発電プラントとにおける両方の原子炉建屋を一体にして建設する原子力発電プラントの建設方法において、
前記両原子炉建屋の境界に前記両原子炉建屋を区画する隔壁を形成し、
前記隔壁を挟んで両側の前記区画において前記両原子力発電プラントの建設を進め、
前記両原子力発電プラントの完成前に、前記オペレーティングフロアから上の前記隔壁を撤去して、前記第1の原子炉建屋と前記第2の原子炉建屋の各オペレーティングフロアを共用のオペレーティングフロアとした原子力発電プラントの建設方法。
A first nuclear power plant having a first nuclear reactor building for storing a first nuclear reactor pressure vessel, and a second nuclear reactor after the construction of the preceding nuclear power plant is started and before the completion thereof In a method for constructing a nuclear power plant in which both reactor buildings in a subsequent nuclear power plant having a second reactor building for storing a pressure vessel are integrally constructed,
Forming a partition wall that partitions both reactor buildings at the boundary between both reactor buildings,
Proceed with the construction of both nuclear power plants in the compartments on both sides across the bulkhead,
Before the completion of the two nuclear power plants, the bulkhead is removed from the operating floor, and each operating floor of the first reactor building and the second reactor building is used as a common operating floor. Power plant construction method.
請求項1において、前記両原子力発電プラントの完成後においても前記オペレーティングフロアから下側の全部又は一部の隔壁を残存させて、前記残存した隔壁を前記第1の原子炉建屋と前記第2の原子炉建屋とで共有する壁とした原子力発電プラントの建設方法。  In Claim 1, even after the completion of the two nuclear power plants, all or a part of the partition walls on the lower side from the operating floor are left, and the remaining partitions are separated from the first reactor building and the second reactor building. A method of constructing a nuclear power plant with walls shared by the reactor building. 請求項1又は請求項2において、前記後続原子力発電プラントの建設途中に前記先行原子力発電プラントが運転中の状態では、オペレーティングフロアより上方の前記隔壁が取り除かれ、且つ前記隔壁で区画されたうちの前記第1の原子炉建屋側の使用済燃料プールを隔床で覆った状態として前記後続発電プラントの建設を進めることを特徴とする原子力発電プラントの建設方法。  In Claim 1 or Claim 2, in a state where the preceding nuclear power plant is in operation during the construction of the subsequent nuclear power plant, the bulkhead above the operating floor is removed and the bulkhead is partitioned by the bulkhead A construction method of a nuclear power plant, wherein the construction of the subsequent power plant is advanced with the spent fuel pool on the first reactor building side covered with a floor. 請求項1又は請求項2又は請求項3において、前記隔壁は、第1の原子炉建屋の建設に合わせて施工することを特徴とする原子力発電プラントの建設方法。  4. The nuclear power plant construction method according to claim 1, wherein the partition wall is constructed in accordance with construction of the first reactor building. 請求項1又は請求項2又は請求項3において、第1の原子炉建屋側のオペレーティングフロアが放射線管理区域となった時点で、両原子炉建屋間に隔壁を設けて両原子炉建屋間を遮断した状態で両原子力発電プラントの建設作業を進めることを特徴とする原子力発電プラントの建設方法。  In Claim 1 or Claim 2 or Claim 3, when the operating floor on the first reactor building side becomes a radiation control area, a partition wall is provided between the two reactor buildings to shut off the two reactor buildings. A construction method of a nuclear power plant characterized in that the construction work of both nuclear power plants is proceeded in a state in which it has been completed. 請求項1又は請求項2又は請求項3において、第1の原子炉建屋側のオペレーティングフロアが放射線管理区域となる前に、第2の原子炉建屋側から第1の原子炉建屋側へ粉塵侵入を防止する必要のある間、両原子炉建屋の境界に隔壁を設けて粉塵侵入の防止を図ることを特徴とする原子力発電プラントの建設方法。  4. Dust intrusion from the second reactor building side to the first reactor building side before the operating floor on the first reactor building side becomes a radiation control area in claim 1, 2 or 3 A construction method of a nuclear power plant characterized in that a partition wall is provided at the boundary between both reactor buildings to prevent dust intrusion while it is necessary to prevent dust. 請求項1又は請求項2又は請求項3において、第1の原子炉建屋内及び第2の原子炉建屋内共に放射線管理区域が設定される前のオペレーティングフロア機械・電気作業は、オペレーティングフロアから上方の隔壁を取り除いて、両原子炉建屋のオペレーティングフロア間の遮断を解除した状態で行うことを特徴とする原子力発電プラントの建設方法。  In Claim 1 or Claim 2 or Claim 3, before the radiation control area is set in both the first reactor building and the second reactor building, the operating floor mechanical and electrical work is performed upward from the operating floor. A method for constructing a nuclear power plant, which is performed in a state in which the partition between the operating floors of both reactor buildings is released by removing the bulkhead. 請求項3において、先行原子力発電プラントが運転中で、後続プラントではオペレーティングフロアにおいて機械・電気作業が行われている場合、隔壁で分割されたうちの第1の原子炉建屋側の使用済燃料プールを隔床で覆うことを特徴とする原子力発電プラントの建設方法。In Claim 3, when the preceding nuclear power plant is in operation and the subsequent plant is performing mechanical and electrical work on the operating floor, the spent fuel pour on the first reactor building side divided by the partition wall is used. construction method for a nuclear power plant, characterized in that covering the Le in intervals bed. 請求項1又は請求項2又は請求項3において、第1の原子炉建屋内では原子炉圧力容器の炉開放が行われ、第2の原子炉建屋内では放射線管理区域が設定されている場合のオペレーティングフロア機械・電気作業中は、両原子炉建屋間を隔壁で遮断しておくことを特徴とする原子力発電プラントの建設方法。  In claim 1, 2 or 3, the reactor pressure vessel is opened in the first reactor building, and the radiation control area is set in the second reactor building. A construction method of a nuclear power plant characterized in that the partition between both reactor buildings is cut off by a partition wall during operating floor machine / electrical work.
JP2001355475A 2001-11-21 2001-11-21 Nuclear power plant construction method Expired - Fee Related JP4006984B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001355475A JP4006984B2 (en) 2001-11-21 2001-11-21 Nuclear power plant construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001355475A JP4006984B2 (en) 2001-11-21 2001-11-21 Nuclear power plant construction method

Publications (2)

Publication Number Publication Date
JP2003156583A JP2003156583A (en) 2003-05-30
JP4006984B2 true JP4006984B2 (en) 2007-11-14

Family

ID=19167169

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001355475A Expired - Fee Related JP4006984B2 (en) 2001-11-21 2001-11-21 Nuclear power plant construction method

Country Status (1)

Country Link
JP (1) JP4006984B2 (en)

Also Published As

Publication number Publication date
JP2003156583A (en) 2003-05-30

Similar Documents

Publication Publication Date Title
US6625245B1 (en) Method of handling reactor vessel
JP4006984B2 (en) Nuclear power plant construction method
JP2519896B2 (en) Reactor dismantling method
JP7467250B2 (en) Method and device for dismantling nuclear reactor equipment
JP3152125B2 (en) Radioactive material storage facility
JPH11337675A (en) Reactor-containment vessel and its building method
US20030043953A1 (en) Reactor vessel handling method
JP3787808B2 (en) How to dismantle the shielding wall
JP2011127906A (en) Method of uncovering apparatus temporary storage pool and method of transporting reactor internal
JP5358516B2 (en) Construction method of reactor containment vessel
JP3462911B2 (en) Reactor building
JPS63274897A (en) Cask cleaning pit in common use as depot for head of nuclear reactor pressure vessel
KR100959886B1 (en) Cavity Wall Liner Construction Method For Nuclear Reactor Containment Building
JPH0768776B2 (en) Cutting and demolition equipment for cylindrical structures
JP7353065B2 (en) shielding equipment
JP2000193786A (en) Spent fuel storage building
JP2011027665A (en) Method for laydown in reactor building of abwr plant and for replacing annular seal member of reactor pressure vessel of abwr plant
JP2001042076A (en) Construction method for reactor power facility
JPH0355405A (en) Boiler installation working space structure
JPH09166684A (en) Structure of pool in reactor building
Ijichi et al. Development of advanced concept for shortening construction period of ABWR plant
JPH0513225B2 (en)
JPH07209478A (en) Reactor internal equipment temporary setting pool
JP4096911B2 (en) Reactor pressure vessel replacement method
JP4055156B2 (en) Reactor pressure vessel replacement method

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20040512

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040519

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20040512

RD01 Notification of change of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7421

Effective date: 20060419

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070522

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070612

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070807

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070820

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100907

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100907

Year of fee payment: 3

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100907

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100907

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110907

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120907

Year of fee payment: 5

LAPS Cancellation because of no payment of annual fees