JP2003156583A - Construction method for nuclear power plant - Google Patents

Construction method for nuclear power plant

Info

Publication number
JP2003156583A
JP2003156583A JP2001355475A JP2001355475A JP2003156583A JP 2003156583 A JP2003156583 A JP 2003156583A JP 2001355475 A JP2001355475 A JP 2001355475A JP 2001355475 A JP2001355475 A JP 2001355475A JP 2003156583 A JP2003156583 A JP 2003156583A
Authority
JP
Japan
Prior art keywords
reactor
nuclear power
plant
power plant
operating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2001355475A
Other languages
Japanese (ja)
Other versions
JP4006984B2 (en
Inventor
Hiroshi Takano
高野  博
Koichi Nochida
孝一 後田
Yoshio Ishinabe
好夫 石名部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Hitachi Plant Technologies Ltd
Original Assignee
Hitachi Ltd
Hitachi Plant Technologies Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd, Hitachi Plant Technologies Ltd filed Critical Hitachi Ltd
Priority to JP2001355475A priority Critical patent/JP4006984B2/en
Publication of JP2003156583A publication Critical patent/JP2003156583A/en
Application granted granted Critical
Publication of JP4006984B2 publication Critical patent/JP4006984B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Monitoring And Testing Of Nuclear Reactors (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a construction method for twin plants sharing a reactor building operating floor. SOLUTION: In a construction method for nuclear power plants in which a following plant 3 is constructed together with a preceding plant 2 with a time difference from the construction of the preceding plant 2, partition walls 5, 8 and 9 are formed from the mat 1 to the height of roofs 12 and 13 at the boundary of the two plants, construction of two plants are proceeded on both sides of the partition walls. When the preceding plant 2 is in operation, the partition wall 9 above the operating floor 10 is removed and construction of the later plant 3 is proceeded with a state covering the operating floor 10 with a partition floor.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、二つの原子力発電
プラントの建設方法とその運用方法に関する。
TECHNICAL FIELD The present invention relates to a method for constructing two nuclear power plants and a method for operating the same.

【0002】[0002]

【従来の技術】原子炉建屋内のオペレーティングフロア
(以下、単にオペフロと略称表示する。)を二つの原子
力発電プラントで共用化したツインプラントと称せられ
る構成は特開平9−68588号公報に掲載されてい
る。
2. Description of the Related Art A structure called a twin implant in which an operating floor (hereinafter simply referred to as "opero") in a reactor building is shared by two nuclear power plants is disclosed in Japanese Patent Laid-Open No. 9-68588. ing.

【0003】又、二つの原子力発電プラントを隣接して
建設する方法として、先行して建設に着手した先行プラ
ントに時間差を置いて後続プラントの建設に着手するこ
とで、特定の建設機械や人手が特定の時期に集中するこ
とを避けることが、国際公開番号WO97/11467
号の再公表特許として公開されている。
Further, as a method of constructing two nuclear power plants adjacent to each other, the construction of a succeeding plant is started with a time lag with respect to the preceding plant which has begun construction, so that a specific construction machine or manpower can be saved. Avoiding concentration at a particular time is international publication number WO97 / 11467
Issued as a reissue patent.

【0004】[0004]

【発明が解決しようとする課題】今後、原子炉建屋内の
オペフロ等、ツインプラントで共用可能な設備を共用化
し、建設時期差を設けて建設する原子力発電所のツイン
プラントの建設においては、例えば先行プラント側のオ
ペフロでは管理区域が設定され、燃料装荷作業が実施中
であり、後続プラント側のオペフロでは非管理区域状態
での建設作業を実施するケースが当然発生する。
In the future, for example, in the construction of a twin implant of a nuclear power plant in which a facility that can be shared by the twin implants such as an operation floor in the reactor building is shared, and construction is performed with a construction time difference, In the operation plant on the preceding plant side, a controlled area is set and fuel loading work is in progress, and on the operation floor on the succeeding plant side, construction work in the non-controlled area state naturally occurs.

【0005】後続プラントの建設を急いで、共用オペフ
ロ全域を管理区域とした場合、後続プラントのオペフロ
作業は管理区域内作業時間規制等を受け、建設工程及び
建設費面での影響が発生するため、共用オペフロを管理
区域/非管理区域に区分する必要がある。
When the construction of the subsequent plant is hurried and the entire operation floor is set as the management area, the operation time of the operation plant of the succeeding plant is subject to restrictions such as working time in the management area, which may affect the construction process and the construction cost. , It is necessary to divide the common operation floor into the controlled area / non-controlled area.

【0006】また先行プラントが運転中、後続プラント
ではオペフロ管理区域内で燃料装荷作業中のケースで
は、先行プラントの原子炉格納容器内でトラブルが発生
した場合に対する、二次格納施設バウンダリの設定方法
検討が必要となる。
Further, in the case where the preceding plant is in operation and the succeeding plant is carrying out fuel loading work in the operation flow control area, a method for setting the boundary of the secondary containment facility when a trouble occurs in the reactor containment vessel of the preceding plant Consideration is required.

【0007】よって、本発明では原子力発電所のツイン
プラントの建設において最適なバウンダリを伴いながら
ツインプラントを建設する方法を提供することを主目的
とし、さらには、その建設によって造られたツインプラ
ントの運用方法を提供することを副次的目的としてい
る。
Therefore, the main object of the present invention is to provide a method for constructing a twin implant while accommodating an optimum boundary in the construction of a twin implant for a nuclear power plant, and further, for a twin implant produced by the construction. The secondary purpose is to provide an operation method.

【0008】[0008]

【課題を解決するための手段】上記主目的は、先行原子
力発電プラントの建設に遅れをもって後続原子力発電プ
ラントを前記先行原子力発電プラントと一体にして建設
する原子力発電プラントの建設方法において、前記両原
子力発電プラントの境界に原子炉建屋の基礎となるマッ
トから屋根の高さに至る隔壁を形成し、前記隔壁を挟ん
で両側において前記両原子力発電プラントの建設を進
め、前記先行原子力発電プラントが運転中の場合は、オ
ペレーティングフロアより上方の前記隔壁が取り除か
れ、且つ前記先行原子力発電プラント側のオペレーティ
ングフロアを隔床で覆った状態として前記後続原子力発
電プラントの建設を進め、前記両原子力発電プラントの
建設が終えた時点で、前記両原子力発電プラントのオペ
レーティングフロアが前記両原子力発電プラントの共用
のオペレーティングフロアとされる原子力発電プラント
の建設方法によって達成される。
The main object is to provide a method for constructing a nuclear power plant in which a subsequent nuclear power plant is constructed integrally with the preceding nuclear power plant with a delay in the construction of the preceding nuclear power plant. A partition wall is formed at the boundary of the power plant from the mat that forms the basis of the reactor building to the height of the roof, and both nuclear power plants are constructed on both sides of the partition wall, and the preceding nuclear power plant is in operation. In the case of, the partition above the operating floor is removed, and the operating floor of the preceding nuclear power plant side is covered with a partition to proceed with the construction of the subsequent nuclear power plant, and the construction of the both nuclear power plants. The operating floors of both nuclear power plants will be Serial is achieved by the construction method of a nuclear power plant, which is the operating floor of the sharing of the two nuclear power plant.

【0009】上記副次的目的は、隔壁で区画された二つ
の原子炉格納施設を備え、二つの原子炉格納施設に共用
のオペレーティングフロアを備え、一方の原子炉格納施
設で原子炉圧力容器の炉開放の伴う作業を行っている間
にも、他方の原子炉格納施設では運転状態が継続される
原子力発電プラントの運用方法において、前記他方の原
子炉格納施設側のオペレーティングフロアに隔床を置い
て前記他方の原子炉格納施設での運転状態を継続する原
子力発電プラントの運用方法によって達成される。
The above secondary purpose is to provide two reactor containment facilities partitioned by bulkheads, two reactor containment facilities have a common operating floor, and one reactor containment facility to In the operation method of the nuclear power plant where the operation state is continued in the other reactor containment facility even while the work involving the opening of the reactor is being performed, a floor is placed on the operating floor of the other reactor containment facility side. This is achieved by a method of operating a nuclear power plant that continues the operating state of the other reactor containment facility.

【0010】[0010]

【発明の実施の形態】原子力発電所のツインプラントで
は、共通の原子炉建屋内に2台の原子炉圧力容器が配備
されることになるが、各原子炉圧力容器ごとに原子炉圧
力容器を格納する一次格納施設と、その一次格納施設の
外側を囲む二次格納施設とが付帯施設とし原子炉建屋内
に備わっている。このようなツインプラントでは、原子
炉建屋内の使用済燃料プールとオペフロとがツインプラ
ントで共用される合理的な設計となっている。
BEST MODE FOR CARRYING OUT THE INVENTION In a twin implant of a nuclear power plant, two reactor pressure vessels are installed in a common reactor building, but each reactor pressure vessel has a reactor pressure vessel. A primary containment facility for storage and a secondary containment facility surrounding the outside of the primary containment facility are provided as incidental facilities in the reactor building. Such a twin implant has a rational design in which the spent fuel pool in the reactor building and the operating floor are shared by the twin implant.

【0011】ツインプラントの建設に当たっては、図1
の先行原子力発電プラント2(以下、単に先行プラント
と表示する。)側の建設着手を先行させ、その着手に月
単位又は年単位の時間差を置いて、先行プラントが完成
する前に後続プラント3(以下、単に後続プラントと表
示する。)側の建設に着手する。先行と後続の各プラン
トともに建設個所を原子炉圧力容器を格納する施設であ
る原子炉建屋を図面に図示して説明を進める。そのた
め、先行プラントの建設とは、先行プラントの原子炉建
屋の建設とその原子炉建屋内の内部機器の組立て,据付
けなどを意味する。後続プラントの建設とは、同じく、
後続プラントの原子炉建屋の建設とその原子炉建屋内の
内部機器の組立て,据付けなどを意味する。そのため、
各図において先行プラント2の表示範囲は、特許請求の
範囲の欄で表現される第1の原子炉建屋の範囲を、後続
プラント3の表示範囲は、特許請求の範囲の欄で表現さ
れる第2の原子炉建屋の範囲を意味する。
In constructing the twin implant, as shown in FIG.
Of the preceding nuclear power plant 2 (hereinafter, simply referred to as a preceding plant) is started, and a time difference of a month unit or an year unit is set at the start, and the succeeding plant 3 ( In the following, it will be simply referred to as the succeeding plant.) Both the preceding and succeeding plants will be described with reference to the drawings of the reactor building which is a facility for storing the reactor pressure vessel at the construction site. Therefore, the construction of the preceding plant means the construction of the reactor building of the preceding plant and the assembling and installation of the internal equipment inside the reactor building. The construction of the subsequent plant is the same as
It means the construction of the reactor building of the subsequent plant and the assembly and installation of the internal equipment inside the reactor building. for that reason,
In each drawing, the display range of the preceding plant 2 is the range of the first reactor building expressed in the section of the claims, and the display range of the subsequent plant 3 is the range expressed in the section of the claims. It means the range of 2 reactor buildings.

【0012】以下、本発明の実施例による原子力発電所
のツインプラントの建設について、原子炉建屋とその内
部構成機器を例にあげて図面を参照しながら説明する。
図1は先行/後続プラント共用の使用済燃料プール床ま
での二次格納施設バウンダリ構成のための隔壁5の設定
状況を示すものである。先行/後続プラント共用のマッ
ト1から共用使用済燃料プール床4までの先行プラント
2の建屋工事実施に合わせ、先行プラント2と後続プラ
ント3の二次格納施設バウンダリ構成用の共用使用済燃
料プール床4までの隔壁5をマット1から共用使用済燃
料プール床4まで設定する。この時期後続プラント3は
先行プラント2に対して遅れた時期差を設けての建設と
なるため、例えば1階床6の高さまでの施工中となる。
Hereinafter, the construction of a twin implant for a nuclear power plant according to an embodiment of the present invention will be described with reference to the drawings, taking a reactor building and its internal components as an example.
FIG. 1 shows the setting status of the partition wall 5 for the boundary structure of the secondary storage facility up to the spent fuel pool floor shared by the preceding and succeeding plants. The shared spent fuel pool floor for the secondary containment facility boundary configuration of the preceding plant 2 and the succeeding plant 3 according to the building construction of the preceding plant 2 from the mat 1 for shared use of the preceding / subsequent plants to the shared spent fuel pool floor 4 Partition walls 5 up to 4 are set from the mat 1 to the shared spent fuel pool floor 4. At this time, the succeeding plant 3 is constructed with a delayed time difference with respect to the preceding plant 2, and therefore, for example, the construction is performed up to the height of the first floor 6.

【0013】図2は先行/後続プラントの共用使用済燃
料プール床4以上の二次格納施設バウンダリ構成の隔壁
設定状況を示すものである。先行プラント2の共用使用
済燃料プール床4以上の躯体7から屋根12までの建屋
工事施工に合わせ、先行プラント側のオペフロ10と後
続プラント3側のオペフロ11の境を通る垂直方向に、
共用使用済燃料プール内隔壁8とオペフロ以上の隔壁9
を設定する。
FIG. 2 shows a partition wall setting situation of a secondary containment facility boundary structure having four or more shared spent fuel pool floors of preceding and succeeding plants. In line with the construction work from the skeleton 7 of the shared spent fuel pool floor 4 or more of the preceding plant 2 to the roof 12, in the vertical direction passing through the boundary between the operation plant 10 on the preceding plant side and the operation flow 11 on the succeeding plant 3 side,
Shared spent fuel pool bulkhead 8 and bulkhead 9 above operation floor
To set.

【0014】尚、共用使用済燃料プール内隔壁8と、オ
ペフロ以上の隔壁9は分離可能な構造とする。共用使用
済燃料プール内隔壁8とオペフロ以上の隔壁9により先
行プラント2のオペフロと後続プラント3との間は遮断
され、後続プラント3からの先行プラント2のオペフロ
への粉塵侵入等を防止する。尚、後続プラント3は先行
プラントに対して時期差を設けての建設となるため、共
用使用済燃料プール内隔壁8とオペフロ以上の隔壁9を
設定する時期においては後続プラント3側のオペフロ1
1までの施工中となる。
The partition wall 8 in the shared spent fuel pool and the partition wall 9 above the operating floor are separable from each other. The partition wall 8 in the shared spent fuel pool and the partition wall 9 above the operating floor block the operation floor of the preceding plant 2 from the succeeding plant 3 to prevent dust from entering the operating floor of the preceding plant 2 from the succeeding plant 3. Since the succeeding plant 3 is constructed with a time lag with respect to the preceding plant, at the time of setting the shared spent fuel pool partition 8 and the partition 9 above the operating floor, the operating plant 1 on the side of the succeeding plant 3
It is under construction up to 1.

【0015】図3は先行プラント2が管理区域設定前の
オペフロ機械・電気作業中で、後続プラント3がオペフ
ロ壁から屋根12までの建屋工事実施中の状況を示すも
のである。先行プラント2の屋根12施工完了前に天井
クレーンレール15を搬入・据付け、及び2台の天井ク
レーン14を搬入して天井クレーンレール15に据付け
を完了させ、先行プラント2の屋根12を完成後に天井
クレーン14の試験を実施し、また並行してオペフロ以
上の隔壁9により後続プラント3側のオペフロ11と先
行プラント2のオペフロ10とを仕切り、後続プラント
での建設作業で生じた粉塵の先行プラント2側のオペフ
ロ10への侵入防止を図った上で、2台の天井クレーン
14を用い管理区域設定前の炉内工事等のオペフロ機械
・電気作業を実施する。後続プラントの建設は先行プラ
ントの建設に対して遅れた時期差を設けての建設となる
ため、この時期では、後続プラント3ではオペフロ壁1
7から屋根13までの躯体工事中となる。
FIG. 3 shows a situation in which the preceding plant 2 is operating mechanical and electrical work before setting the control area, and the succeeding plant 3 is performing building work from the operating floor wall to the roof 12. Before the roof 12 of the preceding plant 2 is completed, the overhead crane rail 15 is loaded and installed, and the two overhead cranes 14 are loaded to complete the installation on the overhead crane rail 15, and the roof 12 of the preceding plant 2 is completed. The crane 14 is tested, and in parallel, the operation flow 11 on the succeeding plant 3 side and the operation flow 10 of the preceding plant 2 are separated by the partition 9 over the operation flow, and the preceding plant 2 of dust generated in the construction work in the succeeding plant is separated. After preventing intrusion into the operating floor 10 on the side, the operating floor mechanical and electrical work such as in-furnace construction before setting the control area is carried out by using two overhead cranes 14. Since the construction of the succeeding plant will be delayed in time relative to the construction of the preceding plant, at this time, the operating plant 1
The frame construction from 7 to roof 13 is under construction.

【0016】このようにして、原子炉建屋の基礎となる
マット1から屋根12,13の高さにまで各隔壁5,
8,9を構築した後に、いずれの隔壁も撤去せずにその
隔壁で隔てられた両区画側で建設を個々に進め、両区画
側での建設が終了してから、隔壁9を撤去して両プラン
トのオペフロ11とオペフロ10とを連通して、両プラ
ントで共用するオペフロとする。この隔壁5,8,9は
隙間無く上下方向に連続して放射線の透過と放射性物質
の往来を防止する機能を有する。
In this way, each partition wall 5, from the mat 1 which is the basis of the reactor building, to the height of the roofs 12 and 13.
After building 8 and 9, proceed with the construction individually on both partition sides separated by the partition without removing any partition, and remove the partition 9 after the construction on both partition sides is completed. The operation flow 11 and the operation flow 10 of both plants are communicated with each other to form an operation flow shared by both plants. The partition walls 5, 8 and 9 have a function of preventing the transmission of radiation and the movement of radioactive substances continuously in the vertical direction without a gap.

【0017】建設作業途中でも、両プラントのオペフロ
11とオペフロ10とを連通して、両プラントで共用す
るオペフロとすることで、作業環境を広く確保したり、
二台の天井クレーン14を片側のプラントの建設に集中
して用いたい場合には、既述の図3の状態から図4−図
8の状態に作業を順次進めてゆく。以下に、その順次進
める作業について図4−図8に従って説明する。
Even during the construction work, the operation environment can be secured widely by connecting the operation flow 11 and the operation flow 10 of both plants so that the operation flow is shared by both plants.
When it is desired to concentrate the use of the two overhead cranes 14 on the construction of the plant on one side, the work is sequentially advanced from the state shown in FIG. 3 to the state shown in FIGS. Hereinafter, the work to be sequentially performed will be described with reference to FIGS.

【0018】図3の状態から図4の状態へと作業が進む
が、図4の状態は先行及び後続プラント共、管理区域設
定前のオペフロ機械・電気作業中の状態を示すものであ
る。先行プラント2及び後続プラント3のオペフロで天
井クレーン14を2台使用しての作業となるため、まず
オペフロ以上の隔壁9を一時撤去し、次に先行プラント
2で稼動していた天井クレーン14を後続プラント3で
も使用可能とするため、先行プラント2側と後続プラン
ト3側の天井クレーンレール15を連続的につなぐ。こ
のようにして天井クレーン14は先行プラント2と後続
プラント3との間をお互いに往来できる状態にして2台
の天井クレーン14を先行プラント2側と後続プラント
3側とのどちらでも共用できるようにして建設作業を促
進する。
Although the work progresses from the state of FIG. 3 to the state of FIG. 4, the state of FIG. 4 shows a state in which the operation machine and electric work are being performed before the control area is set in both the preceding and succeeding plants. Since the operation of the preceding plant 2 and the succeeding plant 3 uses two overhead cranes 14, first, the partition 9 above the operating floor is temporarily removed, and then the overhead crane 14 operating in the preceding plant 2 is removed. Since it can be used in the succeeding plant 3, the overhead crane rails 15 on the preceding plant 2 side and the succeeding plant 3 side are continuously connected. In this way, the overhead crane 14 is allowed to come and go between the preceding plant 2 and the succeeding plant 3 so that the two overhead cranes 14 can be shared by both the preceding plant 2 side and the succeeding plant 3 side. Promote construction work.

【0019】図5は先行プラント2側で放射線管理区域
設定後のオペフロ機械・電気作業中、後続プラント3側
では放射線管理区域設定前のオペフロ機械・電気作業中
の状態を示すものである。後続プラント3のオペフロを
非管理区域に保つため、まず天井クレーンレール15の
うち、オペフロ以上の隔壁9の上端部分に設定されてい
た天井クレーンレール部分を一時撤去する。
FIG. 5 shows a state in which the preceding plant 2 side is operating mechanical / electrical work after setting the radiation control area and the subsequent plant 3 side is operating mechanical / electrical work before setting the radiation control area. In order to keep the operation floor of the succeeding plant 3 in the non-controlled area, first, of the overhead crane rails 15, the ceiling crane rail portion set at the upper end portion of the partition wall 9 above the operation floor is temporarily removed.

【0020】その後一時撤去しておいたオペフロ以上の
隔壁9をオペフロ中央部で共用使用済燃料プール内隔壁
8上に再設定する。このことにより、先行プラント2側
のオペフロと後続プラントのオペフロとの間を遮断す
る。尚、天井クレーン14は先行プラント2オペフロ作
業用として1台、後続プラント3オペフロ作業用として
1台の使用区分として設定する。
After that, the partition 9 over the operation floor which has been temporarily removed is reset on the partition wall 8 in the common spent fuel pool at the center of the operation floor. As a result, the operation flow on the side of the preceding plant 2 and the operation flow on the following plant are cut off. It should be noted that the overhead crane 14 is set as a usage group of one for the operation of the preceding plant and two for the operation of the succeeding plant.

【0021】図6は先行プラント2が運転中、後続プラ
ント3は放射線管理区域設定前のオペフロ機械・電気作
業中の状態を示すものである。先行プラント2の原子炉
格納容器内トラブル時に対する二次格納施設バウンダリ
構成方法として、オペフロ以上の隔壁9を撤去し、先行
プラント2側と後続プラント3側との天井クレーンレー
ル15を接続して後続プラント3側の作業を2台の天井
クレーン14で推進できるようにする。
FIG. 6 shows a state in which the preceding plant 2 is in operation, and the succeeding plant 3 is in operation for mechanical and electrical operation before setting the radiation control area. As a secondary containment facility boundary configuration method in case of a trouble in the reactor containment vessel of the preceding plant 2, the partition 9 above the operation floor is removed, and the overhead crane rails 15 of the preceding plant 2 side and the succeeding plant 3 side are connected to follow The work on the plant 3 side can be promoted by two overhead cranes 14.

【0022】次に先行プラント2側のオペフロ10上に
オペフロ隔床16を設定し、共用使用済燃料プール床4
までの隔壁5と、共用使用済燃料プール内隔壁8と、オ
ペフロ隔床16とにより先行プラント2とオペフロ上方
の空間及び後続プラント3への境界を遮断するバウンダ
リを構成する。
Next, an operation floor partition 16 is set on the operation floor 10 on the side of the preceding plant 2, and the shared spent fuel pool floor 4 is set.
The partition wall 5 up to, the shared spent fuel pool partition wall 8, and the operation floor partition 16 form a boundary that blocks the boundary between the preceding plant 2, the space above the operation floor, and the succeeding plant 3.

【0023】オペフロ隔床16は、コンクリート製の板
を金属板で被覆した板を複数枚並べて構成される。その
オペフロ隔床16の板一枚一枚は、天井クレーン14で
取り扱うことができる重さと大きさを有する。そして、
並べた板の間にはシールが施される。オペフロ隔床16
はそのオペフロ隔床16の下部に漏れ出た放射線や放射
性物質がオペフロ隔床16の上部に漏れ出ないようにす
る機能がある。この実施例では、オペフロ隔床16は共
用使用済燃料プールの上も覆っている。
The operation floor partition 16 is formed by arranging a plurality of concrete plates covered with a metal plate. Each plate of the operation floor partition 16 has a weight and a size that can be handled by the overhead crane 14. And
A seal is applied between the arranged plates. Operation floor partition 16
Has a function of preventing radiation and radioactive substances leaking to the lower part of the operation floor partition 16 from leaking to the upper part of the operation floor partition 16. In this embodiment, the operation floor 16 also covers the shared spent fuel pool.

【0024】オペフロ隔床16を構成する板は天井クレ
ーン14で吊って移動させることができる。その移動に
よってオペフロから撤去させたりオペフロに敷き詰めた
りすることができる。
The plates constituting the operation floor partition 16 can be hung and moved by the overhead crane 14. By the movement, it can be removed from the operation floor or spread on the operation floor.

【0025】原子力発電プラントのプラント運転を開始
した後には、原子炉圧力容器の上蓋を開けて原子炉圧力
容器内の核燃料を配置換えしたり新燃料と取り替えた
り、あるいは原子炉圧力容器内内部点検を行う時期が到
来する。その時期には、原子炉圧力容器の上蓋を開ける
という炉開放状態が発生する。炉開放状態では、放射線
や放射性物質がオペフロ空間に飛散する可能性があるの
で、そのオペフロ空間は厳重な放射線管理区域とされ
る。
After the plant operation of the nuclear power plant is started, the upper lid of the reactor pressure vessel is opened and the nuclear fuel in the reactor pressure vessel is rearranged or replaced with new fuel, or the inside of the reactor pressure vessel is inspected. It's time to do. At that time, a reactor open state occurs in which the upper lid of the reactor pressure vessel is opened. When the furnace is open, radiation and radioactive substances may be scattered in the operating space, so the operating space is a strict radiation control area.

【0026】図7は先行プラント2の運転後の原子炉圧
力容器の炉開放、後続プラント3の放射線管理区域設定
後のオペフロ機械・電気作業中の状態を示す。後続プラ
ント3の放射線管理区域設定後のオペフロでの機械・電
気作業に際し、先行プラント2と後続プラント3のオペ
フロを分離しない場合、先行プラント2の運転後の原子
炉圧力容器の炉開放により、後続プラント3オペフロの
放射線量が増加し、規定線量到達時間が早期化し、後続
プラント3の管理区域内作業効率が低下する。その低下
を抑制するため、まず天井クレーンレール15のうち、
オペフロ以上の隔壁9設定範囲部のレールを取り外し、
次に一時撤去しておいたオペフロ以上の隔壁9を元の状
態に再設定することにより、先行プラント2側のオペフ
ロと後続プラント側のオペフロとを分離区分して、その
後に先行プラント2側ではオペフロ隔床16を撤去し、
炉開放状態での作業を行い、後続プラント3側では放射
線管理区域設定下での機械・電気作業を実施する。
FIG. 7 shows a state in which the reactor pressure vessel is opened after the operation of the preceding plant 2 and the radiation control area of the succeeding plant 3 is set, and the operation and mechanical operations are performed. In the mechanical / electrical work in the operation plant after the radiation control area of the succeeding plant 3 is set, if the operation plants of the preceding plant 2 and the succeeding plant 3 are not separated, the reactor pressure vessel after the operation of the preceding plant 2 is opened, The radiation dose of the plant 3 operation increases, the prescribed dose arrival time is shortened, and the work efficiency in the controlled area of the subsequent plant 3 is reduced. In order to suppress the decrease, first of all, among the overhead crane rails 15,
Remove the rail in the partition 9 setting range above the operation floor,
Next, by resetting the partition 9 over the operation flow that has been temporarily removed to the original state, the operation flow on the side of the preceding plant 2 and the operation flow on the side of the succeeding plant are separated and separated, and then the operation side of the preceding plant 2 is separated. Remove the operation floor partition 16,
The work is performed with the furnace open, and the mechanical / electrical work is performed on the subsequent plant 3 side under the radiation control area setting.

【0027】炉開放状態は先行プラントと後続プラント
とが完成した後に両プラントを運用しているさなかにあ
っても発生する。例えば、図8の状態である。即ち、図
8は先行プラント2の運転後の原子炉圧力容器の炉開放
状態,後続プラント3の運転中の状態を示すものであ
る。
The open furnace state occurs even while the preceding plant and the succeeding plant are completed and both plants are in operation. For example, the state shown in FIG. That is, FIG. 8 shows the reactor open state of the reactor pressure vessel after the operation of the preceding plant 2 and the operating state of the subsequent plant 3.

【0028】先行プラント2側で炉開放状態を伴う作業
を行っているさなかに運転中の後続プラント3でのトラ
ブルで後続プラント3から放射線や放射性物質がオペフ
ロ上空間に漏れると深刻な状況となることが懸念され
る。
A serious situation occurs when radiation or radioactive material leaks from the succeeding plant 3 into the space above the operating floor due to a trouble in the succeeding plant 3 while the preceding plant 2 is working with the furnace open. Is concerned.

【0029】そこで、運転中の後続プラント3の原子炉
格納容器内のトラブル時に対する二次格納施設バウンダ
リの構成方法として、後続プラント3側のオペフロ上に
オペフロ隔床16を敷き詰めて各隔壁5,8及びオペフ
ロ隔床16で後続プラント3をオペフロや先行プラント
2側から隔離する。このように、共用使用済燃料プール
床までの隔壁5と、共用使用済燃料プール内隔壁8と、
後続プラント3のオペフロ隔床16により、後続プラン
ト3のバウンダリを構成する。これにより後続プラント
3側の原子炉格納容器内のトラブルによる先行プラント
2側への放射能漏れを防止する。このように両プラント
を運用すれば、両プラント間でオペフロが共用化されオ
ペフロ上空間が両プラント間でつながっていても安全且
つ広くオペフロを利用して運転後の保守や核燃料取り扱
い作業が実施できる。
Therefore, as a method of constructing the secondary containment facility boundary in the case of a trouble in the reactor containment vessel of the operating subsequent plant 3, the operating floors 16 are spread over the operating plant on the side of the subsequent plant 3 and each partition wall 5, 5. 8 and the operation floor partition 16 isolate the succeeding plant 3 from the operation floor and the preceding plant 2 side. In this way, the partition wall 5 up to the shared spent fuel pool floor, the shared spent fuel pool internal partition wall 8,
The operation floor partition 16 of the succeeding plant 3 constitutes a boundary of the succeeding plant 3. This prevents the leakage of radioactivity to the preceding plant 2 side due to a trouble in the reactor containment vessel on the succeeding plant 3 side. By operating both plants in this way, it is possible to perform post-operation maintenance and nuclear fuel handling work safely and widely using the operation floor even if the operation floor is shared between both plants and the space above the operation floor is connected between both plants. .

【0030】このようにして、隔壁5,8,9のうち、
隔壁5,8はツインプラントの建設終了後も残存して放
射線の透過や放射性物質の往来を抑制している。しか
し、共用使用済燃料プールを完全に共用するために、隔
壁5,8の一部である隔壁5を残存させ、隔壁8を共用
使用済燃料プールから撤去する様にしても良い。
In this way, of the partition walls 5, 8, 9
The partition walls 5 and 8 remain after the construction of the twin implants to suppress the transmission of radiation and the passage of radioactive substances. However, in order to completely share the shared spent fuel pool, the partition wall 5, which is a part of the partition walls 5 and 8, may be left and the partition wall 8 may be removed from the shared spent fuel pool.

【0031】[0031]

【発明の効果】以上のように、本発明の建設方法によれ
ば、オペフロを共用化とする原子力発電所のツインプラ
ントを各プラント間で時期差を設けて建設する際に、建
設進捗に応じて隔壁や隔床を用いて放射線や放射性物質
や塵埃の拡散をコントロールしながら合理的且つ安全に
そのツインプラントを建設できる。
As described above, according to the construction method of the present invention, when constructing a twin implant of a nuclear power plant which shares an operating floor with a time lag between the plants, the construction progress can be adjusted according to the construction progress. It is possible to construct the twin implant rationally and safely while controlling the diffusion of radiation, radioactive substances and dust by using partition walls and floors.

【0032】本発明の運用方法によれば、前記両プラン
ト間でオペフロが共用化されオペフロ上空間が両プラン
ト間でつながっていても安全且つ広くオペフロを利用し
て運転後の必要な作業が実施できる。
According to the operation method of the present invention, even if the operating floor is shared between both plants and the space above the operating floor is connected between both plants, the necessary work after operation is performed safely and widely using the operating floor. it can.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施例による建設初期の原子炉建屋の
説明図である。
FIG. 1 is an explanatory diagram of a reactor building at an early stage of construction according to an embodiment of the present invention.

【図2】本発明の実施例による隔壁設定状況を示す原子
炉建屋の説明図である。
FIG. 2 is an explanatory diagram of a reactor building showing a partition wall setting state according to an embodiment of the present invention.

【図3】本発明の実施例による先発プラントが管理区域
設定前のオペフロ機械・電気作業中で、後続プラントが
オペフロ壁から屋根までの建屋工事実施中の状況を示す
原子炉建屋の説明図である。
FIG. 3 is an explanatory diagram of a reactor building showing a situation in which a starting plant according to an embodiment of the present invention is operating mechanical / electrical work before setting a control area, and a succeeding plant is performing a building construction from an operating floor wall to a roof. is there.

【図4】本発明の実施例による先行及び後続プラント
共、管理区域設定前のオペフロ機械・電気作業中の状態
を示す原子炉建屋の説明図である。
FIG. 4 is an explanatory diagram of a reactor building showing a state during operation of an operation / electrical machine before setting a control area in both preceding and succeeding plants according to an embodiment of the present invention.

【図5】本発明の実施例による先行プラントが管理区域
設定後のオペフロ機械・電気作業中、後続プラントは管
理区域設定前のオペフロ機械・電気作業中の状態を示す
原子炉建屋の説明図である。
FIG. 5 is an explanatory diagram of the reactor building showing a state in which the preceding plant according to the embodiment of the present invention is in the operation machine / electrical work after setting the control area, and the succeeding plant is in the operation machine / electric work before setting the control area. is there.

【図6】本発明の実施例による先行プラントが運転中、
後続プラントは管理区域設定前のオペフロ機械・電気作
業中の状態を示す原子炉建屋の説明図である。
FIG. 6 shows that the preceding plant according to the embodiment of the present invention is in operation,
The subsequent plant is an explanatory view of the reactor building showing a state in which the operation floor is under mechanical and electrical work before the management area is set.

【図7】本発明の実施例による先行プラントが運転後の
原子炉圧力容器の炉開放、後続プラントが管理区域設定
後のオペフロ機械・電気作業中の状態を示す原子炉建屋
の説明図である。
FIG. 7 is an explanatory view of the reactor building showing a state in which the preceding plant according to the embodiment of the present invention opens the reactor pressure vessel after the operation, and the succeeding plant performs the operation and mechanical operation of the operation after setting the control area. .

【図8】本発明の実施例による先行プラントが運転後の
原子炉圧力容器の炉開放、後続プラント運転中の状態を
示す原子炉建屋の説明図である。
FIG. 8 is an explanatory diagram of the reactor building showing a state in which the preceding plant according to the embodiment of the present invention is in operation while the reactor pressure vessel is open, and the subsequent plant is in operation.

【符号の説明】[Explanation of symbols]

1…マット、2…先行プラント、3…後続プラント、4
…共用使用済燃料プール床、5…共用使用済燃料プール
床までの隔壁、6…後続プラント1階床、7…共用使用
済燃料プール床以上の躯体、8…共用使用済燃料プール
内隔壁、9…オペフロ以上の隔壁、10…先行プラント
のオペフロ、11…後続プラントのオペフロ、12…先
行プラント屋根、13…後続プラント屋根、14…天井
クレーン、15…天井クレーンレール、16…オペフロ
隔床、17…後続プラントオペフロ壁。
1 ... Matt, 2 ... Preceding plant, 3 ... Subsequent plant, 4
… Shared spent fuel pool floor, 5… Bulkhead to shared spent fuel pool floor, 6… Floor of the subsequent plant, 7… Bridge above shared spent fuel pool floor, 8… Shared spent fuel pool internal bulkhead, 9 ... Partition wall above or above operating floor, 10 ... Operating floor of preceding plant, 11 ... Operating floor of succeeding plant, 12 ... Preceding plant roof, 13 ... Subsequent plant roof, 14 ... Overhead crane, 15 ... Overhead crane rail, 16 ... Operating floor partition, 17 ... Subsequent plant operation wall.

フロントページの続き (72)発明者 後田 孝一 茨城県日立市幸町三丁目1番1号 株式会 社日立製作所原子力事業部内 (72)発明者 石名部 好夫 東京都千代田区内神田一丁目1番14号 日 立プラント建設株式会社内Continued front page    (72) Inventor Koichi Gota             3-1-1 Sachimachi, Hitachi City, Ibaraki Prefecture Stock Association             Hitachi, Ltd. Nuclear Business Division (72) Inventor Yoshio Ishinabe             1-14-1 Kanda, Uchida, Chiyoda-ku, Tokyo             Stand Plant Construction Co., Ltd.

Claims (10)

【特許請求の範囲】[Claims] 【請求項1】第1の原子炉圧力容器を格納する第1の原
子炉建屋を有する先行原子力発電プラントと、前記先行
原子力発電プラントの建設開始後であってその完成前に
建設が開始されて第2の原子炉圧力容器を格納する第2
の原子炉建屋を有する後続原子力発電プラントとにおけ
る両方の原子炉建屋を一体にして建設する原子力発電プ
ラントの建設方法において、 前記両原子炉建屋の境界に前記両原子炉建屋を区画する
隔壁を形成し、 前記隔壁を挟んで両側の前記区画において前記両原子力
発電プラントの建設を進め、 前記両原子力発電プラントの完成前に、前記オペレーテ
ィングフロアから上の前記隔壁を撤去して、前記第1の
原子炉建屋と前記第2の原子炉建屋の各オペレーティン
グフロアを共用のオペレーティングフロアとした原子力
発電プラントの建設方法。
1. A preceding nuclear power plant having a first nuclear reactor building for housing a first nuclear reactor pressure vessel, and construction of the preceding nuclear power plant after starting construction but before completion thereof. Second to store the second reactor pressure vessel
In the method for constructing a nuclear power plant in which both the reactor buildings in the subsequent nuclear power plant having the reactor building are integrally constructed, a partition wall for partitioning the reactor buildings is formed at a boundary between the reactor buildings. Then, proceed with the construction of the both nuclear power plants in the compartments on both sides of the partition wall, and before the completion of the both nuclear power plants, remove the partition wall above the operating floor, the first atom A method for constructing a nuclear power plant, wherein the operating floors of the reactor building and the second reactor building are shared.
【請求項2】請求項1において、前記両原子力発電プラ
ントの完成後においても前記オペレーティングフロアか
ら下側の全部又は一部の隔壁を残存させて、前記残存し
た隔壁を前記第1の原子炉建屋と前記第2の原子炉建屋
とで共有する壁とした原子力発電プラントの建設方法。
2. The structure according to claim 1, wherein even after the completion of the both nuclear power plants, all or a part of the partition walls on the lower side of the operating floor are left, and the remaining partition walls are connected to the first reactor building. And a method for constructing a nuclear power plant having a wall shared by the second reactor building.
【請求項3】請求項1又は請求項2において、前記後続
原子力発電プラントの建設途中に前記先行原子力発電プ
ラントが運転中の状態では、オペレーティングフロアよ
り上方の前記隔壁が取り除かれ、且つ前記隔壁で区画さ
れたうちの前記第1の原子炉建屋側の使用済燃料プール
を隔床で覆った状態として前記後続発電プラントの建設
を進めることを特徴とする原子力発電プラントの建設方
法。
3. The partition wall above the operating floor according to claim 1 or 2, wherein the partition wall above the operating floor is removed while the preceding nuclear power plant is in operation while the subsequent nuclear power plant is being constructed. A method for constructing a nuclear power plant, wherein construction of the subsequent power generation plant is proceeded with the spent fuel pool on the side of the first reactor building among the partitioned areas being covered with a partition.
【請求項4】請求項1又は請求項2又は請求項3におい
て、前記隔壁は、第1の原子炉建屋の建設に合わせて施
工することを特徴とする原子力発電プラントの建設方
法。
4. The method of constructing a nuclear power plant according to claim 1, 2 or 3, wherein the partition wall is constructed in accordance with the construction of the first reactor building.
【請求項5】請求項1又は請求項2又は請求項3におい
て、第1の原子炉建屋側のオペレーティングフロアが放
射線管理区域となった時点で、両原子炉建屋間に隔壁を
設けて両原子炉建屋間を遮断した状態で両原子力発電プ
ラントの建設作業を進めることを特徴とする原子力発電
プラントの建設方法。
5. The nuclear reactor according to claim 1, 2 or 3, wherein a partition wall is provided between the reactor buildings when the operating floor on the side of the first reactor building becomes a radiation controlled area. A method for constructing a nuclear power plant, characterized in that construction work for both nuclear power plants is carried out with the reactor buildings being cut off.
【請求項6】請求項1又は請求項2又は請求項3におい
て、第1の原子炉建屋側のオペレーティングフロアが放
射線管理区域となる前に、第2の原子炉建屋側から第1
の原子炉建屋側へ粉塵侵入を防止する必要のある間、両
原子炉建屋の境界に隔壁を設けて粉塵侵入の防止を図る
ことを特徴とする原子力発電プラントの建設方法。
6. The method according to claim 1, 2 or 3, wherein the operating floor on the first reactor building side becomes the first reactor building side before the operating floor becomes the radiation controlled area.
A method for constructing a nuclear power plant, characterized in that a partition is provided at the boundary between both reactor buildings to prevent dust intrusion while it is necessary to prevent dust intrusion to the reactor building side.
【請求項7】請求項1又は請求項2又は請求項3におい
て、第1の原子炉建屋内及び第2の原子炉建屋内共に放
射線管理区域が設定される前のオペレーティングフロア
機械・電気作業は、オペレーティングフロアから上方の
隔壁を取り除いて、両原子炉建屋のオペレーティングフ
ロア間の遮断を解除した状態で行うことを特徴とする原
子力発電プラントの建設方法。
7. The operating floor mechanical / electrical work before the radiation controlled area is set in both the first reactor building and the second reactor building according to claim 1, 2 or 3. A method for constructing a nuclear power plant, characterized in that the upper partition is removed from the operating floor, and the operation is performed in a state where the interruption between the operating floors of both reactor buildings is released.
【請求項8】請求項3において、先行原子力発電プラン
トが運転中で、後続プラントではオペレーティングフロ
アにおいて機械・電気作業が行われている場合、隔壁で
分割されたうちの第1の原子炉建屋側の使用済燃料プー
ル隔床で覆うことを特徴とする原子力発電プラントの建
設方法。
8. The nuclear reactor power plant according to claim 3, wherein when the preceding nuclear power plant is in operation and the succeeding plant is performing mechanical / electrical work on the operating floor, the first reactor building side among the partitions A method for constructing a nuclear power plant, which is characterized by covering the spent fuel pool with a partition.
【請求項9】請求項1又は請求項2又は請求項3におい
て、第1の原子炉建屋内では原子炉圧力容器の炉開放が
行われ、第2の原子炉建屋内では放射線管理区域が設定
されている場合のオペレーティングフロア機械・電気作
業中は、両原子炉建屋間を隔壁で遮断しておくことを特
徴とする原子力発電プラントの建設方法。
9. The reactor according to claim 1, 2 or 3, wherein the reactor pressure vessel is opened in the first reactor building, and the radiation control area is set in the second reactor building. A method for constructing a nuclear power plant characterized in that a partition wall is used to block the space between the two reactor buildings during mechanical and electrical work.
【請求項10】同一建屋内で隔壁で区画された二つの原
子炉格納施設を備え、二つの原子炉格納施設に共用のオ
ペレーティングフロアを備え、一方の原子炉格納施設で
原子炉圧力容器の炉開放の伴う作業を行っている間に
も、他方の原子炉格納施設では運転状態が継続される原
子力発電プラントの運用方法において、 前記他方の原子炉格納施設側のオペレーティングフロア
に隔床を置いて前記他方の原子炉格納施設での運転状態
を継続する原子力発電プラントの運用方法。
10. A reactor pressure vessel reactor provided with two reactor containment facilities partitioned by bulkheads in the same building, two operating facilities shared by the two reactor containment facilities, and one of the reactor containment facilities having a reactor pressure vessel. In the method of operating a nuclear power plant in which the operating state of the other reactor containment facility is maintained even while performing work involving opening, a floor is placed on the operating floor of the other reactor containment facility side. A method of operating a nuclear power plant that continues the operating state of the other nuclear reactor containment facility.
JP2001355475A 2001-11-21 2001-11-21 Nuclear power plant construction method Expired - Fee Related JP4006984B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001355475A JP4006984B2 (en) 2001-11-21 2001-11-21 Nuclear power plant construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001355475A JP4006984B2 (en) 2001-11-21 2001-11-21 Nuclear power plant construction method

Publications (2)

Publication Number Publication Date
JP2003156583A true JP2003156583A (en) 2003-05-30
JP4006984B2 JP4006984B2 (en) 2007-11-14

Family

ID=19167169

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001355475A Expired - Fee Related JP4006984B2 (en) 2001-11-21 2001-11-21 Nuclear power plant construction method

Country Status (1)

Country Link
JP (1) JP4006984B2 (en)

Also Published As

Publication number Publication date
JP4006984B2 (en) 2007-11-14

Similar Documents

Publication Publication Date Title
US7684535B2 (en) Reactor containment vessel
EP1258889A1 (en) Method of handling reactor vessel
JP2003156583A (en) Construction method for nuclear power plant
JP3027430B2 (en) Construction method of nuclear power plant building, building module and nuclear power plant building
JP2001281387A (en) Handling method of large-sized structure within reactor building
JPH11337675A (en) Reactor-containment vessel and its building method
US20020176529A1 (en) Reactor vessel handling method
JP4014748B2 (en) Spent fuel storage building
JP3462911B2 (en) Reactor building
KR100959886B1 (en) Cavity Wall Liner Construction Method For Nuclear Reactor Containment Building
JPS63274897A (en) Cask cleaning pit in common use as depot for head of nuclear reactor pressure vessel
Ijichi et al. Development of advanced concept for shortening construction period of ABWR plant
JPH09166684A (en) Structure of pool in reactor building
JPH0513225B2 (en)
JP2000346993A (en) Method for handling large structure in reactor building
JPH10206586A (en) Remodeling method for increasing internal volume of pressurized water reactor containment
JPH0355405A (en) Boiler installation working space structure
JP3273668B2 (en) How to construct a containment vessel
JPH10239477A (en) Nuclear power plant
JPS63284493A (en) Frame for supporting reactor pressure vessel
JPH07209478A (en) Reactor internal equipment temporary setting pool
JP2020187039A (en) Shielding facilities, methods of installing the same, and shielding blocks
JP2003207588A (en) Construction method of nuclear reactor building
JP2003041661A (en) Building construction method and building
JPH10132980A (en) Construction work process for reactor housing container made of concrete

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20040512

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040519

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20040512

RD01 Notification of change of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7421

Effective date: 20060419

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070522

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070612

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070807

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070820

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100907

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100907

Year of fee payment: 3

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100907

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100907

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110907

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120907

Year of fee payment: 5

LAPS Cancellation because of no payment of annual fees