JPH03247818A - Construction of concrete foundation - Google Patents

Construction of concrete foundation

Info

Publication number
JPH03247818A
JPH03247818A JP4639690A JP4639690A JPH03247818A JP H03247818 A JPH03247818 A JP H03247818A JP 4639690 A JP4639690 A JP 4639690A JP 4639690 A JP4639690 A JP 4639690A JP H03247818 A JPH03247818 A JP H03247818A
Authority
JP
Japan
Prior art keywords
foundation
construction
concrete
reinforced concrete
bundle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP4639690A
Other languages
Japanese (ja)
Inventor
Futoshi Isshiki
太 一色
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
National House Industrial Co Ltd
Original Assignee
National House Industrial Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by National House Industrial Co Ltd filed Critical National House Industrial Co Ltd
Priority to JP4639690A priority Critical patent/JPH03247818A/en
Publication of JPH03247818A publication Critical patent/JPH03247818A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To reduce construction manpower at site by forming reinforced concrete to the lower part of the foundation post together as a unit, and joining the foundation beam to the foundation post with bolts. CONSTITUTION:Reinforced concrete 1 is formed to the lower part of the foundation post 2 together as a unit in a factory. Bolt holes 4 are made on the side of the foundation beam 3 as a lattice beam, and female screw holes 5 are made on the foundation post 2 respectively. In a construction site, bolts are screwed into the female screw holes 5 from the bolt holes 4 to build the foundation beam 3.

Description

【発明の詳細な説明】[Detailed description of the invention] 【産業上の利用分野】[Industrial application field]

本発明は施工工数が大幅に削減されたコンクリート基礎
構造に関する。
The present invention relates to a concrete foundation structure in which the number of construction steps is significantly reduced.

【従来技術】[Prior art]

従来より、第2図に示すように、ラチス梁である基礎梁
3を基礎束2を介して組立てた後、下部で鉄筋6を組み
、この後コンクリート7を打設してコンクリート基礎が
構築されている。 [発明が解決しようとする課題] 従来にあっては、全て現場での施工となり、しかも湿式
施工でもあり、施工に手間を要するものになってしまっ
ていた。 本発明は上記事情に鑑みて為されたものであり、その目
的とするところは、現場での施工工数が削減され、しか
も乾式施工ともなり施工性に優れるコンクリート基礎構
造を提供することにある。 El1題を解決するための手Fi1 本発明のコンクリート基礎構造は、下部に鉄筋コンクリ
ート1を一体成形した基礎束2に基礎梁3を架設させて
成るものであり、この構成により上記課題が解決された
ものである。 [作用] 現場において基礎梁3を基礎束2に架設するだけで施工
でき、乾式施工で施工性に優れるものである。 [実施例] 基礎束2の下部には鉄筋コンクリート1が一体成形され
ている。この成形は工場において行なわれる。ラチス梁
である基礎梁3の1部のボルト孔4からボルトを基礎束
2の雌ねし孔5に螺入して基礎梁3が架設されてコンク
リート基礎構造が構築されている。而して、現場におい
では、基i!梁3を基礎束2にボルト接合するだけで施
工でき、施工工数を大幅に削減できるだけでなく、乾式
施工ともなる。
Conventionally, as shown in Fig. 2, after a foundation beam 3, which is a lattice beam, is assembled via a foundation bundle 2, reinforcing bars 6 are erected at the bottom, and then concrete 7 is poured to construct a concrete foundation. ing. [Problems to be Solved by the Invention] Conventionally, all construction was done on-site, and it was also wet construction, making the construction time-consuming. The present invention has been made in view of the above-mentioned circumstances, and its purpose is to provide a concrete foundation structure that reduces the number of construction steps at the site, and can be dry constructed and has excellent workability. A method for solving the problem El1Fi1 The concrete foundation structure of the present invention is constructed by constructing a foundation beam 3 on a foundation bundle 2 whose lower part is integrally formed with reinforced concrete 1, and with this configuration, the above problem has been solved. It is something. [Function] Construction can be carried out by simply erecting the foundation beam 3 on the foundation bundle 2 at the site, and the construction is excellent in dry construction. [Example] Reinforced concrete 1 is integrally molded at the lower part of the foundation bundle 2. This molding is done in a factory. A concrete foundation structure is constructed by screwing a bolt from a bolt hole 4 of a part of a foundation beam 3, which is a lattice beam, into a female threaded hole 5 of a foundation bundle 2 to erect the foundation beam 3. Then, at the scene, Kii! Construction can be done by simply bolting the beam 3 to the foundation bundle 2, which not only greatly reduces the number of construction steps, but also enables dry construction.

【発明の効果】【Effect of the invention】

本発明にあっては、下部に鉄筋コンクリートを一体成形
した基礎束に基礎梁を架設させているので、現場におい
て基礎梁を基礎束に架設するだけで施工でき、施工工数
を大幅に削減でき、しかも乾式施工となり施工性に優れ
るものである。
In the present invention, since the foundation beam is installed on the foundation bundle whose lower part is integrally formed with reinforced concrete, construction can be carried out by simply installing the foundation beam on the foundation bundle at the site, which can significantly reduce the number of construction steps. It is dry construction and has excellent workability.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の一実施例を示す一部省略斜視図、第2
図(a)(b)は従来における施工を示す説明図であっ
て、1は鉄筋コンクリート、2は基礎束、3は基礎梁で
ある。
FIG. 1 is a partially omitted perspective view showing one embodiment of the present invention, and FIG.
Figures (a) and (b) are explanatory diagrams showing conventional construction, in which 1 is reinforced concrete, 2 is a foundation bundle, and 3 is a foundation beam.

Claims (1)

【特許請求の範囲】[Claims] (1)下部に鉄筋コンクリートを一体成形した基礎束に
基礎梁を架設させて成ることを特徴とするコンクリート
基礎構造。
(1) A concrete foundation structure characterized by having a foundation beam erected on a foundation bundle whose lower part is integrally formed with reinforced concrete.
JP4639690A 1990-02-26 1990-02-26 Construction of concrete foundation Pending JPH03247818A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4639690A JPH03247818A (en) 1990-02-26 1990-02-26 Construction of concrete foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4639690A JPH03247818A (en) 1990-02-26 1990-02-26 Construction of concrete foundation

Publications (1)

Publication Number Publication Date
JPH03247818A true JPH03247818A (en) 1991-11-06

Family

ID=12745988

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4639690A Pending JPH03247818A (en) 1990-02-26 1990-02-26 Construction of concrete foundation

Country Status (1)

Country Link
JP (1) JPH03247818A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108999427A (en) * 2018-10-15 2018-12-14 北京建工四建工程建设有限公司 The support construction and its construction method of traveling load when a kind of building moving is in place

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5431903A (en) * 1977-08-16 1979-03-09 Kentarou Kawai Foundation of reinforced concrete cloth produced in factory assembled by using fittings and adhesives while laying emphasis on foundation unit under post

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5431903A (en) * 1977-08-16 1979-03-09 Kentarou Kawai Foundation of reinforced concrete cloth produced in factory assembled by using fittings and adhesives while laying emphasis on foundation unit under post

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108999427A (en) * 2018-10-15 2018-12-14 北京建工四建工程建设有限公司 The support construction and its construction method of traveling load when a kind of building moving is in place
CN108999427B (en) * 2018-10-15 2023-10-24 北京建工四建工程建设有限公司 Support structure for moving load during building migration in place and construction method thereof

Similar Documents

Publication Publication Date Title
KR20190027230A (en) Joint for Precast Beam and Columns
US5540020A (en) Building panel
JPH03247818A (en) Construction of concrete foundation
JPH0280747A (en) Girder structure
JPH03247819A (en) Construction of concrete foundation
JP2001311247A (en) Construction method for concrete structure
KR200303783Y1 (en) Apparatus for a Mold of Precast Box Culvert
JP2000212930A (en) Joint structure of prefabricated caisson and prefabricated caisson
CN220285156U (en) Environment-friendly energy-saving concrete member
JPH0473381A (en) Independent electric pole and its pole erecting construction
KR200187741Y1 (en) A molding frame for formwork
JPH04215Y2 (en)
JPH0427018A (en) Construction of concrete assembly-type basement
JPH0833016B2 (en) Concrete assembling basement skeleton structure
JP2862771B2 (en) Construction method of precast concrete foundation
JP2881585B2 (en) Integral foundation formwork components
JPH04265315A (en) Junction structure of block structure for foundation
JPH0427077A (en) House with concrete built-up type basement
KR100361318B1 (en) The manufacturing method of a panel of fence with compounded materials
JPH0376932A (en) Construction of housing foundation formed in different level
JPH0352820Y2 (en)
JPH0649897A (en) Joining method for beam and pillar and precast concrete pillar applied to above method
JP2781640B2 (en) Construction method of concrete basement
JP2965950B2 (en) Joint structure between precast concrete cloth foundations
JPH09100655A (en) Fence