JPH0649897A - Joining method for beam and pillar and precast concrete pillar applied to above method - Google Patents

Joining method for beam and pillar and precast concrete pillar applied to above method

Info

Publication number
JPH0649897A
JPH0649897A JP4222284A JP22228492A JPH0649897A JP H0649897 A JPH0649897 A JP H0649897A JP 4222284 A JP4222284 A JP 4222284A JP 22228492 A JP22228492 A JP 22228492A JP H0649897 A JPH0649897 A JP H0649897A
Authority
JP
Japan
Prior art keywords
column
joining
pillar
precast concrete
box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP4222284A
Other languages
Japanese (ja)
Inventor
Takashi Nagareda
隆 流田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toda Corp
Original Assignee
Toda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toda Corp filed Critical Toda Corp
Priority to JP4222284A priority Critical patent/JPH0649897A/en
Publication of JPH0649897A publication Critical patent/JPH0649897A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:In the case of mutually joining a steel frame beam and a reinforced concrete pillar, to secure their joining accuracy, and to easily join them to improve executing ability. CONSTITUTION:After a pillar 1 is built up by inserting a pillar main reinforcement 7 into a main reinforcement inserting hole 2 and a joining box 3 into a recessed groove 6, a beam 8 is built over between the pillars 1. The steel frames 8b of the joined ends 8d of the beams 8 mounted opposite to each other on the head parts of the pillars 1 are joined to the joining box 3, and the pillar main reinforcement 7 is inserted into the main reinforcement inserting hole 2 at the pillar head part, and concrete 10 is placed in the pillar head part.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は梁と柱との接合方法及び
それに使用するプレキャストコンクリート柱に関するも
のである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of joining a beam and a column and a precast concrete column used for the method.

【0002】[0002]

【従来の技術】一般に、鉄骨梁と鉄筋コンクリート柱と
を接合する場合は、鉄筋コンクリート柱を現場打ち工法
で構築した後、その柱頭部に鉄骨梁の接合端部を載置
し、その接合端部を柱内取付用鉄骨に接合し、この接合
部にコンクリートを打設してこれらを接合していた。
2. Description of the Related Art Generally, when joining a steel beam and a reinforced concrete column, after constructing the reinforced concrete column by the in-situ construction method, the joining end of the steel beam is placed on the column head and the joining end is It was joined to the steel frame for mounting inside the column, and concrete was placed at this joint to join them.

【0003】[0003]

【発明が解決しようとする課題】しかし、上記のように
現場打ちコンクリート柱に鉄骨梁を接合する方法は、鉄
骨梁の接合精度を確保することが困難である。また、鉄
骨梁の鉄骨と柱内取付用鉄骨を接合部内で接合する場合
は柱主筋が邪魔をして取付けが困難であり、さらにこれ
らを接合部外で接合する場合は、後打ち部の型枠工事が
必要となるため施工工程が増えるという問題があった。
本発明は上記のような問題に鑑みてなされたものであ
り、その目的は、鉄筋コンクリート柱と鉄骨コンクリー
ト梁とを接合する場合に、その接合精度を確保すること
ができると共に、容易に接合できて施工性の向上を図る
ことのできる梁と柱の接合方法及びそれに使用するプレ
キャストコンクリート柱を提供することである。
However, in the method of joining a steel beam to a cast-in-place concrete column as described above, it is difficult to secure the joining accuracy of the steel beam. In addition, when the steel frame of the steel beam and the steel frame for mounting in the column are joined inside the joint, it is difficult to install because the main bar of the column interferes. There was a problem that the construction process was increased because frame work was required.
The present invention has been made in view of the above problems, the object is to join the reinforced concrete column and the steel frame concrete beam, it is possible to ensure the joining accuracy, and can be easily joined. (EN) A method for joining a beam and a column that can improve workability, and a precast concrete column used for the method.

【0004】[0004]

【課題を解決するための手段】以上の課題を達成するた
めの本発明の梁と柱の接合方法の要旨は、柱内に貫通し
た主筋挿入孔に下層階の柱主筋を挿入させてプレキャス
トコンクリート柱を建込み、その柱頭部に載置したプレ
キャストコンクリート梁の接合端部を、柱頭部に突設し
た接合用ボックスに接合すると共に、前記主筋挿入孔に
柱頭部から柱主筋を挿入し、前記柱頭部にコンクリート
を打設して接合することに存し、前記接合方法に使用す
るプレキャストコンクリート柱は、柱内に添筋に沿って
主筋挿入孔が貫通され、かつ柱頭部には接合用ボックス
を突設させたことに存する。
The gist of the method for joining a beam and a column of the present invention to achieve the above-mentioned object is to insert a column main bar of a lower floor into a main bar insertion hole penetrating into the column to make a precast concrete. Build a column, join the joint end of the precast concrete beam placed on the column head, join the box for joining protruding to the column head, and insert the column main bar from the column head to the main bar insertion hole, It consists in placing concrete on the column head and joining it, the precast concrete column used for the joining method has a main bar insertion hole penetrating along the reinforcement bar in the column, and a box for joining to the column head I'm in the project.

【0005】[0005]

【作用】このような接合方法において、プレキャストコ
ンクリート柱にプレキャストコンクリート梁を接合する
場合は、柱主筋がない状態で接合することができるため
施工性の向上を図ることができる。また、プレキャスト
コンクリート梁の接合端部を、柱頭部に突設した接合用
ボックスに接合するため、その接合精度を確保すること
ができる。さらに、柱主筋の接合が主筋挿入孔に柱頭部
から柱主筋を挿入することにより接合ができるので、施
工が簡単である。
In such a joining method, when joining a precast concrete beam to a precast concrete column, it is possible to improve the workability because the precast concrete beam can be joined without the column main bar. Moreover, since the joining end of the precast concrete beam is joined to the joining box protruding from the column head, the joining accuracy can be secured. Furthermore, since the main column reinforcement can be connected by inserting the main column reinforcement from the stigma into the main insertion hole, the construction is simple.

【0006】[0006]

【実施例】以下、本発明における梁と柱の接合方法及び
それに使用するプレキャストコンクリート柱の一実施例
ついて詳細に説明する。図1はプレキャストコンクリー
ト柱の断面図、図2は図1のAーA線断面図、図3は図
1のBーB線断面図である。
EXAMPLE An example of the method of joining a beam and a column and the precast concrete column used therefor according to the present invention will be described in detail below. 1 is a sectional view of a precast concrete column, FIG. 2 is a sectional view taken along the line AA of FIG. 1, and FIG. 3 is a sectional view taken along the line BB of FIG.

【0007】本発明の柱1はプレキャストコンクリート
柱であり、プレキャストコンクリート1a内に添筋1b
と帯筋1cとが配筋され、前記添筋1bはプレキャスト
コンクリート1aの上端面まで配筋されている。そし
て、柱1内の四隅に添筋1bに沿って上下に貫通した主
筋挿入孔2が貫通され、柱頭部には接合用ボックス3が
突設されている。この主筋挿入孔2は、柱1の隅部にお
ける添筋1bの内側に3本のシース管4が埋設されて形
成されている。
The pillar 1 of the present invention is a precast concrete pillar, and the reinforcing bar 1b is placed in the precast concrete 1a.
And the stirrup 1c are reinforced, and the reinforcement 1b is reinforced up to the upper end surface of the precast concrete 1a. Then, main bar insertion holes 2 penetrating up and down along the reinforcement bars 1b are penetrated at four corners in the pillar 1, and a box 3 for joining is provided on the pillar head in a protruding manner. The main reinforcement insertion hole 2 is formed by embedding three sheath tubes 4 inside the additional reinforcement 1b at the corner of the column 1.

【0008】前記接合用ボックス3はボックス3aの下
部にスタッドボルト3bを、また上部には四方に接合プ
レート3cをそれぞれ突設し、前記スタッドボルト3b
を突設した下部が柱頭部内に埋設されており、その突出
長さを上端が床スラブ5の上面から適宜高さ突出した長
さとする。また、柱1の下端には接合用ボックス3の上
端が挿入される凹溝6が形成されている。
The joining box 3 is provided with stud bolts 3b at the lower portion of the box 3a and joining plates 3c at the upper portion of the box 3a so as to project in four directions.
The projecting lower part is embedded in the pillar head, and the projecting length of the projecting part is such that the upper end thereof appropriately projects from the upper surface of the floor slab 5 by a height. Further, a concave groove 6 into which the upper end of the joining box 3 is inserted is formed at the lower end of the column 1.

【0009】このような柱1は工場で予め製作され、現
場に運搬して組み立てられて梁を接合するものであり、
その接合方法を図4〜図8に基づいて説明する。図4は
下層階のコンクリートが打設され、柱1の柱主筋7及び
接合用ボックス3の上端が床スラブ5の上面から突出し
ている。そして図5に示すように、柱主筋7を主筋挿入
孔2に、また接合用ボックス3を凹溝6に挿入して柱1
を建込むと、柱1は接合用ボックス3により自立する。
このような方法により適宜箇所に柱1を複数本建込むも
のとする。
Such a pillar 1 is prefabricated in a factory, transported to a site and assembled to join beams.
The joining method will be described with reference to FIGS. In FIG. 4, the concrete of the lower floor is cast, and the pillar main bars 7 of the pillar 1 and the upper ends of the joining boxes 3 project from the upper surface of the floor slab 5. Then, as shown in FIG. 5, the column main bar 7 is inserted into the main bar insertion hole 2 and the joining box 3 is inserted into the groove 6, and the column 1 is inserted.
When the column is installed, the pillar 1 becomes independent by the joining box 3.
A plurality of pillars 1 are to be built in appropriate places by such a method.

【0010】次に、図6に示すように、これらの柱1間
に渡って梁8を架設し、その柱頭部に対向載置された接
合端部8aの鉄骨8bを接合用ボックス3の接合プレー
ト3cにボルト接合すると共に、鉄骨8bの上下端をボ
ックス3aに溶接接合する。この梁8はプレキャストコ
ンクリート梁であり、プレキャストコンクリート8dに
鉄骨8bが埋設され、この鉄骨8bに巻きか掛けられた
あばら筋8cの上部がプレキャストコンクリート8dの
上面から突出されている。また、この接合作業は、柱主
筋7が柱頭部から突設されていないため容易に行うこと
ができる。
Next, as shown in FIG. 6, a beam 8 is laid across these columns 1, and a steel frame 8b of a joint end 8a placed opposite to the column head is joined to the box 3 for joining. The plate 3c is bolted, and the upper and lower ends of the steel frame 8b are welded to the box 3a. This beam 8 is a precast concrete beam, and a steel frame 8b is embedded in the precast concrete 8d, and the upper part of the stirrup 8c wound around the steel frame 8b is projected from the upper surface of the precast concrete 8d. Further, this joining work can be easily performed because the column main bars 7 are not projected from the column head.

【0011】そしてこれらの梁8が接合用ボックス3に
より柱1に接合された後、図7に示すように、主筋挿入
孔2に柱頭部から柱主筋7を挿入すると共に、主筋挿入
孔2に注入孔2aからグラウトを充填することにより、
下層階の柱主筋7と上層階の柱主筋7とが柱1内で接合
される。
After these beams 8 are joined to the pillar 1 by the joining box 3, as shown in FIG. 7, the pillar main bar 7 is inserted into the main bar insertion hole 2 from the pillar head and the main bar insertion hole 2 is inserted. By filling the grout through the injection hole 2a,
The column main bars 7 on the lower floor and the column main bars 7 on the upper floor are joined in the column 1.

【0012】次に、図8に示すように、梁8間にプレキ
ャストコンクリート床版9を架設し、その上及び柱頭部
の接合部内にコンクリート10を打設して床スラブ5を
構築して柱1と梁8とを接合する。この状態で前記床ス
ラブ5からは次層階の柱の接合用として柱主筋7及び接
合用ボックス3の上端が突設されている。そしてこのよ
うな作業を順次繰り返すことにより、容易に柱1と梁8
とを接合してプレキャストコンクリート構造物を構築す
ることができる。
Next, as shown in FIG. 8, a precast concrete floor slab 9 is erected between the beams 8 and concrete 10 is placed on the precast concrete floor slab 9 and at the joints of the pillar heads to construct the floor slab 5 and the pillars. 1 and the beam 8 are joined. In this state, the column main bars 7 and the upper ends of the joining boxes 3 project from the floor slab 5 for joining columns on the next floor. Then, by repeating such work in sequence, the pillar 1 and the beam 8 can be easily
And can be joined to construct a precast concrete structure.

【0013】[0013]

【発明の効果】梁の接合端部を柱頭部の接続用ボックス
に接合するので接合精度の向上を図ることができる。
Since the joint end of the beam is joined to the connecting box of the column head, the joint accuracy can be improved.

【0014】梁の接合端部をプレキャストコンクリート
柱に接合する際に、柱主筋がないのでその接合作業を容
易に行うことできる。
When the joining end portion of the beam is joined to the precast concrete column, since there is no column main bar, the joining work can be easily performed.

【0015】主筋挿入孔に挿入した主筋と接合用ボック
スとにより、プレキャストコンクリート柱を建込む際に
これを自立させることができる。
The main reinforcement inserted into the main reinforcement insertion hole and the joining box allow the precast concrete column to be self-supporting when it is erected.

【0016】柱主筋の継手がプレキャストコンクリート
柱に埋設された添筋による添筋継手なので施工を容易に
行うことができる。
Since the joint of the main reinforcement of the column is a joint of reinforcing bars embedded in a precast concrete column, the construction can be easily carried out.

【0017】柱の柱頭部に接続用ボックスを突設したこ
とにより、梁の応力の柱に対する伝達性能の向上を図る
ことができる。
By projecting the connecting box on the column head of the column, it is possible to improve the transmission performance of the stress of the beam to the column.

【図面の簡単な説明】[Brief description of drawings]

【図1】柱の断面図である。FIG. 1 is a cross-sectional view of a column.

【図2】図1のA−A線断面図である。FIG. 2 is a sectional view taken along the line AA of FIG.

【図3】図1のB−B線断面図である。FIG. 3 is a sectional view taken along line BB of FIG.

【図4】柱主筋及び接続ボックスが突出した下層階の床
スラブの断面図である。
FIG. 4 is a cross-sectional view of a floor slab on a lower floor in which a pillar main bar and a connection box are projected.

【図5】下層階の柱建込み位置に建込んだ柱の断面図で
ある。
FIG. 5 is a cross-sectional view of a pillar installed at a pillar-installed position on a lower floor.

【図6】柱に梁を架設した断面図である。FIG. 6 is a cross-sectional view in which a beam is installed on a column.

【図7】柱主筋を主筋挿入孔に挿入した柱と梁の断面図
である。
FIG. 7 is a cross-sectional view of a column and a beam in which a column main reinforcement is inserted into a main reinforcement insertion hole.

【図8】梁上に床スラブを構築した断面図である。FIG. 8 is a sectional view of a floor slab constructed on a beam.

【符号の説明】[Explanation of symbols]

1 柱 2 主筋挿入孔 3 接合用ボックス 5 床スラブ 6 凹溝 7 柱主筋 8 梁 1 Column 2 Main Reinforcement Insertion Hole 3 Joining Box 5 Floor Slab 6 Recessed Groove 7 Column Main Reinforcement 8 Beam

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 柱内に貫通した主筋挿入孔に下層階の柱
主筋を挿入させてプレキャストコンクリート柱を建込
み、その柱頭部に載置したプレキャストコンクリート梁
の接合端部を、柱頭部に突設した接合用ボックスに接合
すると共に、前記主筋挿入孔に柱頭部から柱主筋を挿入
し、前記柱頭部にコンクリートを打設して接合すること
を特徴とする梁と柱の接合方法。
1. A precast concrete column is constructed by inserting a column main reinforcement of a lower floor into a main reinforcement insertion hole penetrating into the column, and a joint end portion of a precast concrete beam placed on the column head is projected to the column head. A method for joining a beam and a column, which comprises joining to the provided joining box, inserting a column main bar from a column head into the main bar insertion hole, and placing concrete into the column head to join the columns.
【請求項2】 柱内に添筋に沿って主筋挿入孔が貫通さ
れ、かつ柱頭部には接合用ボックスを突設させたことを
特徴とするプレキャストコンクリート柱。
2. A precast concrete column characterized in that a main bar insertion hole is penetrated into the column along the reinforcement bar, and a box for joining is projected on the column head.
JP4222284A 1992-07-30 1992-07-30 Joining method for beam and pillar and precast concrete pillar applied to above method Pending JPH0649897A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4222284A JPH0649897A (en) 1992-07-30 1992-07-30 Joining method for beam and pillar and precast concrete pillar applied to above method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4222284A JPH0649897A (en) 1992-07-30 1992-07-30 Joining method for beam and pillar and precast concrete pillar applied to above method

Publications (1)

Publication Number Publication Date
JPH0649897A true JPH0649897A (en) 1994-02-22

Family

ID=16779964

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4222284A Pending JPH0649897A (en) 1992-07-30 1992-07-30 Joining method for beam and pillar and precast concrete pillar applied to above method

Country Status (1)

Country Link
JP (1) JPH0649897A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103953124A (en) * 2014-05-15 2014-07-30 苏州工业园区设计研究院股份有限公司 Section-steel concrete beam and ordinary concrete column nodal region structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103953124A (en) * 2014-05-15 2014-07-30 苏州工业园区设计研究院股份有限公司 Section-steel concrete beam and ordinary concrete column nodal region structure

Similar Documents

Publication Publication Date Title
JP2535722B2 (en) Reinforcement concrete column and steel beam connection structure and building construction method
JPH0649897A (en) Joining method for beam and pillar and precast concrete pillar applied to above method
JPH0480444A (en) Connection unit of reinforced concrete pole and steel framed beam
JPH06185111A (en) Precast concrete beam and column and construction method of earthquake-proof wall using them
JPS6157732A (en) Construction of multilayered building skeletal by precast reinforced concrete unit
JP2003034997A (en) Earthquake-resistant steel plate wall and its construction method
JP2635872B2 (en) How to build a composite structure
JPH03275839A (en) Connection construction of reinforced concrete column and steel beam
JP2972956B2 (en) Column and beam joining method and its structure
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPH0762740A (en) Joint method for precast steel framed reinforced concrete construction pillar and beam
JPH02140339A (en) Structure of composite pc member
JPH0420639A (en) Pc small beam
JP2741849B2 (en) Construction method of L-shaped retaining wall corner
JPH11172689A (en) Anchoring method of leg section of steel-framed column
JPH116162A (en) Construction method for reinforced concrete underground external wall
JPH06306935A (en) Connection structure of column and beam of rc structure and its construction
JP2003176696A (en) Prefabricated tunnel and construction method therefor
JPH08246587A (en) Successive concrete placing formwork and wall jointing construction method
JPH0588331B2 (en)
JP2002115402A (en) Earthquake-resistant reinforcing wall and its construction method
JPS62170640A (en) Outer wall structure of building
JPH1113015A (en) Arch slab type viaduct, and its execution method
JP2000045521A (en) Execution for placing joint of concrete
JPH0725102U (en) Frame joint structure

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees