JPH03224999A - Construction of underground cavity having large section and tunnel - Google Patents
Construction of underground cavity having large section and tunnelInfo
- Publication number
- JPH03224999A JPH03224999A JP2019486A JP1948690A JPH03224999A JP H03224999 A JPH03224999 A JP H03224999A JP 2019486 A JP2019486 A JP 2019486A JP 1948690 A JP1948690 A JP 1948690A JP H03224999 A JPH03224999 A JP H03224999A
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- constructed
- wall
- ceiling
- section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title abstract description 17
- 238000000034 method Methods 0.000 claims abstract description 16
- 238000009412 basement excavation Methods 0.000 abstract description 13
- 238000005192 partition Methods 0.000 description 3
- 238000004804 winding Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
Abstract
Description
【発明の詳細な説明】
[産業上の利用分野コ
本発明は、軟岩、土砂地山等の地山強度の弱い都市部で
計画されている、地下高速道路の分岐部の施工や地下変
電所の施工に利用できる大断面地下空洞およびトンネル
の構築方法に関する。[Detailed Description of the Invention] [Industrial Application Fields] The present invention is applicable to the construction of branch sections of underground expressways and underground substations planned in urban areas where the ground strength is weak, such as soft rocks and earthy mountains. This paper relates to a method for constructing large-section underground cavities and tunnels that can be used for construction.
[従来の技術]
近年、地下掘削工法の1つとしてNATM(New A
u5trian Tunnellng Method
)が注目されている。在来のトンネル工法が、掘削後の
地山緩み荷重を鋼製支保工と矢板の支持力で支持すると
いう考え方に対して、NATMは、掘削にともなう土庄
を、吹付はコンクリート等のトンネル支保と地山リング
で分担し、地山の持つ強度を有効に利用してトンネルの
安定を保つという考え方のもとに、地山と一体化したト
ンネル構造物を構築する。[Conventional technology] In recent years, NATM (New A
u5trian Tunneling Method
) is attracting attention. In contrast to the conventional tunnel construction method, which supports the loosening load of the ground after excavation with steel shoring and the supporting capacity of sheet piles, NATM supports the soil shogi that accompanies excavation, and spraying supports the tunnel support with concrete, etc. Based on the idea of keeping tunnel stability by effectively utilizing the strength of the ground, we construct a tunnel structure that is integrated with the ground.
[発明が解決しようとする課題]
しかしながら、従来のNATMによる工法では、掘削に
ともなう土圧を、吹付はコンクリート等のトンネル支保
と地山リングで分担するので、軟岩、土砂地山等の地山
強度が弱い場合には、地中の変位が大きくなったり、切
羽が崩落したりして施工ができなくなるという問題を有
している。例えば一般のトンネルでは、−軸圧縮強度が
0.5kgf/c112、変形係数が50kgf/cm
2がNATMの限界であると言われている。これがさら
に大きな断面のトンネルである場合には、さらに大きな
地山強度が必要となり、都市部での施工はほとんど難し
くなる。[Problem to be solved by the invention] However, in the conventional NATM construction method, the earth pressure caused by excavation is shared between the tunnel support such as concrete and the ground ring, so it If the strength is weak, there are problems in that underground displacement increases or the face collapses, making construction impossible. For example, in a general tunnel, the -axial compressive strength is 0.5 kgf/c112, and the deformation coefficient is 50 kgf/cm.
2 is said to be the limit of NATM. If this were to be a tunnel with a larger cross-section, even greater ground strength would be required, making construction in urban areas almost impossible.
本発明は、上記問題を解決するものであって、地山強度
の弱い地域に大断面のトンネルを施工することができる
大断面地下空洞およびトンネルの構築方法を提供するこ
とを目的とする。The present invention solves the above-mentioned problems, and aims to provide a large-section underground cavity and a method for constructing a tunnel, which can construct a large-section tunnel in an area with weak ground strength.
[課題を解決するための手段]
そのために本発明の大断面地下空洞およびトンネルの構
築方法は、トンネルの安定が確保できる程度の大きさの
断面の先行トンネル12を先行して施工し、この先行ト
ンネル12からトンネル軸線に横断方向に、先行トンネ
ル12と同様又は小さい断面の天井トンネル13、壁面
トンネル14を施工し、この内部に天井又は壁面を施工
しその後に内部を掘削するものである。[Means for Solving the Problems] To this end, the method for constructing large cross-section underground cavities and tunnels of the present invention involves first constructing a preceding tunnel 12 having a cross section large enough to ensure stability of the tunnel; A ceiling tunnel 13 and a wall tunnel 14 having the same or smaller cross section as the preceding tunnel 12 are constructed in a direction transverse to the tunnel axis from the tunnel 12, a ceiling or a wall is constructed inside the tunnel, and then the interior is excavated.
なお、天井トンネル13、壁面トンネル14は連続して
(側壁と側壁が接して並べる)施工する必要があるが、
これは、先行した天井トンネル13等の構築の後にすぐ
となりの天井トンネル13の施工を実施することで並設
する。また、壁面トンネル14の施工は、地下連続壁1
1を使用したり深礎工を使用したりしてもよい。Note that the ceiling tunnel 13 and wall tunnel 14 need to be constructed continuously (side walls are in contact with each other).
This is done by constructing the ceiling tunnel 13 immediately next to the ceiling tunnel 13 after constructing the ceiling tunnel 13 and the like. In addition, the construction of the wall tunnel 14 involves the underground continuous wall 1
1 or deep foundation work may be used.
なお、上記構成に付加した番号は、理解を容易にするた
めに図面と対比させるためのもので、これにより本発明
の構成が限定されるものではない。Note that the numbers added to the above configurations are for comparison with the drawings to facilitate understanding, and the configurations of the present invention are not limited thereby.
[作用]
本発明においては、トンネルの外壁(天井、壁面)を先
施工してから内部掘削を実施すると、掘削にともなう解
放地中応力が主にトンネル外壁に導入されるので、地山
強度の弱い地域に大断面のトンネルを施工することがで
きる。[Function] In the present invention, if internal excavation is carried out after the outer walls (ceiling, wall surface) of the tunnel are constructed first, the released underground stress caused by the excavation is mainly introduced into the tunnel outer wall, which reduces the strength of the ground. It is possible to construct large-section tunnels in weak areas.
以下、本発明の実施例を図面を参照しつつ説明する。 Embodiments of the present invention will be described below with reference to the drawings.
第1図は本発明の地下空洞および大断面トンネルの構築
方法の1実施例を示す断面図、第2図は第1図における
■−■線に沿う断面図、第3図は第1図における■−■
線に沿う断面図、第4図は先行トンネル内から地下連続
壁を使用して壁面トンネルを施工する例を示す断面図で
ある。FIG. 1 is a cross-sectional view showing one embodiment of the method for constructing an underground cavity and large-section tunnel according to the present invention, FIG. 2 is a cross-sectional view taken along the line ■-■ in FIG. 1, and FIG. ■−■
FIG. 4 is a cross-sectional view along the line showing an example of constructing a wall tunnel using an underground continuous wall from inside the preceding tunnel.
図において、11は地下連続壁、12は先行トンネル、
13は天井トンネル、14は壁面トンネル、15は隔壁
、16は補強壁面を示す。In the figure, 11 is an underground continuous wall, 12 is a preceding tunnel,
13 is a ceiling tunnel, 14 is a wall tunnel, 15 is a partition wall, and 16 is a reinforced wall surface.
先ず、先行トンネル12をNATMまたはシールド等の
トンネル工法で施工する。NATMを使用する場合は、
地山の強度と先行トンネルの大きさに応じて、薬液注入
やRodinjet等の特殊工法を採用することもでき
る。First, the preceding tunnel 12 is constructed using a tunnel construction method such as NATM or shield. When using NATM,
Depending on the strength of the ground and the size of the preceding tunnel, special construction methods such as chemical injection or Rodinjet may also be employed.
次に、先行トンネル12から、天井トンネル1引および
壁面トンネル14をトンネル横断方向に施工し、この内
部に第2図、第3図に示すようにRC又はPCの壁体1
3aを施工する。これらトンネルの施工は、壁体13a
構築後にその側部のトンネルを施工するという方法をと
る。なお、天井トンネル13の掘削は、NATM等の山
岳トンネル工法またはシールド等の推進による。また、
天井トンネル13断面形状をアーチ形状とせず水平また
は下に凸形状に施工してもよい。Next, from the preceding tunnel 12, a ceiling tunnel 1 and a wall tunnel 14 are constructed in the cross-tunnel direction, and inside this, as shown in FIGS. 2 and 3, an RC or PC wall 1 is constructed.
Construct 3a. Construction of these tunnels is carried out by wall 13a
The method is to construct a tunnel on the side after construction. Note that the ceiling tunnel 13 is excavated by a mountain tunnel construction method such as NATM or by a shield method. Also,
The cross-sectional shape of the ceiling tunnel 13 may not be arched but may be constructed horizontally or downwardly convex.
また、壁面トンネル14の掘削には、立坑NATMを応
用する方法や深礎や、第4図に示すように、先行トンネ
ル12内から地下連続壁11を使用して掘削機17によ
り掘削する方法等が考えられる。In addition, for excavating the wall tunnel 14, there are methods such as applying a vertical shaft NATM, using a deep foundation, and using an excavator 17 to excavate from inside the preceding tunnel 12 using the underground continuous wall 11, as shown in FIG. is possible.
天井トンネル13、壁面トンネル14構築後に、内部掘
削を実施する。内部掘削はベンチ方式による方法が一般
的であるが、壁面11.14を補強する必要がある場合
には、CD工法を実施して逆巻工法等で強度壁面16を
施工する。After constructing the ceiling tunnel 13 and wall tunnel 14, internal excavation is carried out. The bench method is generally used for internal excavation, but if it is necessary to reinforce the wall surface 11.14, the CD method is implemented and a strong wall surface 16 is constructed using a reverse winding method or the like.
トンネル外壁内部の掘削は、第1図左側の断面に示した
ように、逆巻工法等で壁面を補強する必要がある場合は
、隔壁15を設けながら壁面付近を先行掘削(■、■、
■)し逆巻工法等で補強しながら掘り下り、その後、内
部掘削(■、■、■)を行う。なお、■、■、■部分の
掘削は、CD工法やCRD工法をを応用して施工するこ
ともできる。When excavating the inside of the tunnel outer wall, as shown in the cross section on the left side of Figure 1, if it is necessary to reinforce the wall surface using the reverse winding method, etc., advance excavation near the wall surface while installing the partition wall 15 (■, ■,
■) and dig down while reinforcing it using the reverse winding method, etc., and then perform internal excavation (■, ■, ■). Note that the excavation of portions ■, ■, and ■ can also be carried out by applying the CD construction method or the CRD construction method.
以上のように本発明によれば、先行した先行トンネルか
ら天井トンネルおよび壁面トンネルをトンネル軸線に横
断方向に施工して、天井および壁面を構築した後に空洞
内部を掘削するため、トンネルの外壁を先施工してから
内部掘削を実施すると、掘削にともなう解放地中応力が
主にトンネル外壁に導入されるので、地山強度の弱い地
域に大断面のトンネルを施工することができる。As described above, according to the present invention, a ceiling tunnel and a wall tunnel are constructed from a preceding tunnel in a direction transverse to the tunnel axis, and the interior of the cavity is excavated after the ceiling and walls are constructed, so the outer wall of the tunnel is first constructed. If internal excavation is carried out after construction, the released underground stress caused by excavation will be mainly introduced into the tunnel outer wall, making it possible to construct large-section tunnels in areas where the ground strength is weak.
第1図は本発明の地下空洞および大断面トンネルの構築
方法の1実施例を示す断面図、第2図は第1図における
■−■線に沿う断面図、第3図は第1図における■−■
線に沿う断面図、第4図は先行トンネル内から地下連続
壁を使用して壁面トンネルを施工する例を示す断面図で
ある。
11・・・地下連続壁、12・・・先行トンネル、13
・・・天井トンネル、14・・・壁面トンネル、15・
・・隔壁、16・・・は補強壁面。
出 願 人 清水建設株式会社FIG. 1 is a cross-sectional view showing one embodiment of the method for constructing an underground cavity and large-section tunnel according to the present invention, FIG. 2 is a cross-sectional view taken along the line ■-■ in FIG. 1, and FIG. ■−■
FIG. 4 is a cross-sectional view along the line showing an example of constructing a wall tunnel using an underground continuous wall from inside the preceding tunnel. 11... Underground continuous wall, 12... Leading tunnel, 13
... Ceiling tunnel, 14... Wall tunnel, 15.
...Partition wall, 16... is a reinforced wall surface. Applicant: Shimizu Corporation
Claims (1)
面トンネルをトンネル軸線に横断方向に施工して、天井
および壁面を構築した後に空洞内部を掘削することを特
徴とする大断面地下空洞およびトンネルの構築方法。(1) A method for constructing large cross-section underground cavities and tunnels, which is characterized by constructing a ceiling tunnel and a wall tunnel from a preceding tunnel in a direction transverse to the tunnel axis, and excavating the inside of the cavity after constructing the ceiling and walls. .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2019486A JP2520036B2 (en) | 1990-01-29 | 1990-01-29 | Construction method of large section underground cavity and large section tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2019486A JP2520036B2 (en) | 1990-01-29 | 1990-01-29 | Construction method of large section underground cavity and large section tunnel |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH03224999A true JPH03224999A (en) | 1991-10-03 |
JP2520036B2 JP2520036B2 (en) | 1996-07-31 |
Family
ID=12000687
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2019486A Expired - Lifetime JP2520036B2 (en) | 1990-01-29 | 1990-01-29 | Construction method of large section underground cavity and large section tunnel |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2520036B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0726877A (en) * | 1993-07-07 | 1995-01-27 | Kajima Corp | Construction method of underground structure |
JP2009062682A (en) * | 2007-09-04 | 2009-03-26 | Kajima Corp | Tunnel junction structure and construction method for tunnel junction structure |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0384200A (en) * | 1989-08-28 | 1991-04-09 | Kajima Corp | Construction of underground structure |
JPH03122400A (en) * | 1989-10-04 | 1991-05-24 | Takenaka Komuten Co Ltd | Method for constructing architectural big space in great depth underground |
-
1990
- 1990-01-29 JP JP2019486A patent/JP2520036B2/en not_active Expired - Lifetime
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0384200A (en) * | 1989-08-28 | 1991-04-09 | Kajima Corp | Construction of underground structure |
JPH03122400A (en) * | 1989-10-04 | 1991-05-24 | Takenaka Komuten Co Ltd | Method for constructing architectural big space in great depth underground |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0726877A (en) * | 1993-07-07 | 1995-01-27 | Kajima Corp | Construction method of underground structure |
JP2009062682A (en) * | 2007-09-04 | 2009-03-26 | Kajima Corp | Tunnel junction structure and construction method for tunnel junction structure |
Also Published As
Publication number | Publication date |
---|---|
JP2520036B2 (en) | 1996-07-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4647544B2 (en) | Underpass construction method and underpass | |
JP4132442B2 (en) | Tunnel construction method | |
JP2004124489A (en) | Underground structure and its construction method | |
JP2000352296A (en) | Method o constructing passage just under underground structure | |
JPH03202599A (en) | Reinforced structure of twin tunnels | |
JPH03224999A (en) | Construction of underground cavity having large section and tunnel | |
JPH03279600A (en) | Construction method of large cavity | |
JPS6117696A (en) | Construction of underground head | |
JP3026134B2 (en) | How to build underground structures under roads | |
JPH03122400A (en) | Method for constructing architectural big space in great depth underground | |
JPS62220616A (en) | Construction work for underground space | |
JPH062329A (en) | Shoring and cut-off method by underground continuous wall | |
JP2675858B2 (en) | Vertical shaft excavation method | |
KR102477671B1 (en) | Non excavation type constructed tunnel constructing method | |
JPS61186623A (en) | Method of building foundation of building | |
JP2667350B2 (en) | Underground structures and construction methods | |
JP4031284B2 (en) | Construction method for underground structures | |
JP2544829B2 (en) | How to build an underground cavity | |
JPH03279598A (en) | Construction method of large section or superlarge section of tunnel | |
JPH08165899A (en) | Tunnel lining method using timbering concurrently serving as reinforcing bar | |
JPH0414594A (en) | Construction method of tunnel | |
JPH066878B2 (en) | Tunnel or underground cavity lining structure | |
JPH11193689A (en) | Underground cavity construction method and underground cavity construction thereby | |
JPH03206213A (en) | Construction method of earth support | |
JPH0396600A (en) | Constructing method for building large space in large-depth underground section |