JPH11193689A - Underground cavity construction method and underground cavity construction thereby - Google Patents

Underground cavity construction method and underground cavity construction thereby

Info

Publication number
JPH11193689A
JPH11193689A JP53898A JP53898A JPH11193689A JP H11193689 A JPH11193689 A JP H11193689A JP 53898 A JP53898 A JP 53898A JP 53898 A JP53898 A JP 53898A JP H11193689 A JPH11193689 A JP H11193689A
Authority
JP
Japan
Prior art keywords
underground cavity
cavity
pit
underground
pits
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP53898A
Other languages
Japanese (ja)
Inventor
Toru Goto
徹 後藤
Tetsushi Morita
哲士 森田
Masaki Imazu
雅紀 今津
Yutaka Ishikawa
裕 石川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP53898A priority Critical patent/JPH11193689A/en
Publication of JPH11193689A publication Critical patent/JPH11193689A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide an underground cavity constructing method, capable of ensuring safe and low-cost construction in a soft ground by making working pits around an underground cavity before drilled and constructed to reinforce the ground, and provide the underground cavity. SOLUTION: In a construction method, a plurality of working pits are basically constructed outside a cavity-planed ground with a safe and reliable shield machine and a reinforcing soil zone is formed through the working pits along the vicinity of a cavity to drill a predetermined cavity by using a low-cost mountain tunnel technique. The working pits on reinforcement-necessary sides are refilled if required, the working pits are only refilled for reinforcement without forming the reinforcing soil zone or the working pits are utilized as drain pits 18 if the underground cavity should be reinforced with bolts suspended from the working pits or the underground cavity 15 should be constructed in an aquifer. The working pits are connected to the underground cavity after work is completed to construct the integrated underground cavity to be served as effective pits for ventilation 16, evacuation 17 or others.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、地下空洞の施工方
法及びその方法で施工された地下空洞に関し、特に、地
下空洞を掘削する以前に周辺を補強することで軟弱地盤
にも安全、廉価に施工できる地下空洞の施工方法及び地
下空洞に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground cavity and an underground cavity constructed by the method, and more particularly to a method for safe and inexpensive even on soft ground by reinforcing the periphery before excavating the underground cavity. The present invention relates to an underground cavity construction method and an underground cavity that can be constructed.

【0002】[0002]

【従来の技術】近年、地下の利用ニーズが高まってきて
おり、将来に備えてテスト的に構築した地下の大空洞で
各種のテストや実験も行われている。地下の利用は、特
に都市域の地下50〜100mの大深度利用に注目がな
されてきており、地下鉄、地下街及びトンネル等の構築
のために、直径20m近くの空洞を形成するのに適した
掘削法の選択や作業条件の検討も鋭意行われている。上
記のような線状構造の掘削には、一般にシールド工法や
山岳トンネル工法の適用が考えられるところである。
2. Description of the Related Art In recent years, underground utilization needs have been increasing, and various tests and experiments have been conducted in large underground cavities constructed for testing in preparation for the future. The use of underground has been attracting attention, especially for the use of a deep area of 50 to 100 m underground in an urban area, and excavation suitable for forming a cavity having a diameter of about 20 m for construction of a subway, an underground mall, a tunnel, and the like. Efforts are being made to select a law and to consider working conditions. For excavation of the above-mentioned linear structure, application of a shield method or a mountain tunnel method is generally considered.

【0003】しかしながら、シールド工法は、安全確実
であっても工費の高い点が問題であり、特に、前述のよ
うな大空洞になるとこれに合わせたシールド機の製作は
現実的でない。即ち、シールド機はその掘削径が大径に
なると、径の大きさに応じて重量が大幅に増加すると言
われており、その他にも製作、仮組、運搬、現場組立、
現場設備等の面で人手やコストが急激に嵩んでしまうか
らである。又、山岳トンネル工法は、安価であるものの
地山崩壊、湧水等の問題があり、補助工法を併用すると
工期と工費がかかり過ぎるという問題点もあった。
[0003] However, the shield method has a problem in that the cost is high even if it is safe and secure. Particularly, when the above-mentioned large cavity is formed, it is not practical to manufacture a shield machine in accordance with the large cavity. That is, it is said that when the excavation diameter of the shield machine becomes large, the weight increases greatly according to the size of the diameter. In addition, production, temporary assembly, transportation, on-site assembly,
This is because manpower and costs increase rapidly in terms of on-site facilities and the like. In addition, although the mountain tunnel method is inexpensive, it has problems such as collapse of the ground and spring water, and there is also a problem that if the auxiliary method is used together, the construction period and construction cost are excessively required.

【0004】[0004]

【発明が解決しようとする課題】本発明は、従来のシー
ルド工法や山岳トンネル工法が抱えていた問題点を考慮
しながら、それぞれの良さを有効に生かして問題の解決
を図ろうとするもので、最初に安全確実で製作費の安い
シールド機を用いて、地下空洞掘削作業用の坑及び補強
土ゾーンを形成してから、安価な山岳トンネル工法を用
いて所望の地下空洞を掘削しようとするものである。
SUMMARY OF THE INVENTION The present invention seeks to solve the problems by effectively utilizing the respective advantages while taking into account the problems of the conventional shield method and mountain tunnel method. First, use a shield machine that is safe and inexpensive to create a pit and a reinforced soil zone for underground cavity excavation work, and then try to excavate the desired underground cavity using an inexpensive mountain tunnel method It is.

【0005】[0005]

【課題を解決するための手段】本発明は、基本的に空洞
形成予定地盤の外側に複数個の作業坑を安全確実なシー
ルドマシンで築造し、その作業坑から空洞周辺に沿って
補強土ゾーンを形成してから安価な山岳トンネル工法を
用いて所定の空洞を掘削する地下空洞の施工方法であ
る。そして、必要に応じて補強を要する側の作業坑を埋
め込んだり、補強が作業坑の埋め込みのみで補強土ゾー
ンを形成しないで済ますことも考慮している。又、作業
坑からの吊り下げボルトで地下空洞を補強することや帯
水層に地下空洞を構築する必要がある場合には作業坑を
水抜き坑として活用することも配慮している。さらに、
上記施工方法での工事完了後に作業坑を地下空洞に連結
して、換気、避難等の有効坑として一体化した地下空洞
も本発明の範囲に含まれる。
According to the present invention, a plurality of working pits are basically constructed outside a ground where a cavity is to be formed by a safe and secure shield machine, and a reinforcing soil zone is formed along the periphery of the cavity from the working pit. Is a method of constructing an underground cavity in which a predetermined cavity is excavated by using an inexpensive mountain tunnel method after the formation of the tunnel. Further, it is also considered that the work pit on the side requiring reinforcement is buried as necessary, and that the reinforcement is performed only by burying the work pit without forming a reinforced soil zone. Consideration is also given to reinforcing the underground cavities with suspension bolts from the work pit, and utilizing the work pit as a drainage pit when it is necessary to construct an underground cavity in the aquifer. further,
An underground cavity in which the working pit is connected to the underground cavity after the completion of the construction by the above-described construction method and integrated as an effective pit for ventilation, evacuation, etc. is also included in the scope of the present invention.

【0006】[0006]

【発明の実施の形態】本発明による地下空洞の施工方法
及びその方法で施工された地下空洞について図面に基づ
いて説明する。図1〜3に示す施工方法は、本発明によ
る地下空洞の施工方法の基本的な方法を示すものであ
り、以下図面に従って順次説明する。図1は、本発明に
よる施工方法で地下空洞の本工事の事前に行う工事であ
る作業坑の掘削状況を示すものである。作業坑は、都市
部の地下空洞を構築する予定の地盤1の周辺部2に所定
の間隔で複数のシールド3を掘削する。掘削用のシール
ドマシンの内径は工事の作業性等を考慮して、3〜3.
5m程度のものが望ましい。掘削するシールドのピッチ
と個数は、構築する地下空洞の規模と地盤の強弱状況を
FEM解析等で分析した結果に応じて決められるもので
あり、上部のみの場合もあり得るもので特定できないも
のである。
DESCRIPTION OF THE PREFERRED EMBODIMENTS A method for constructing an underground cavity according to the present invention and an underground cavity constructed by the method will be described with reference to the drawings. The construction method shown in FIGS. 1 to 3 shows a basic method of constructing an underground cavity according to the present invention, and will be sequentially described below with reference to the drawings. FIG. 1 shows an excavation situation of a work pit which is a construction to be performed before the main construction of an underground cavity by the construction method according to the present invention. The work pit excavates a plurality of shields 3 at predetermined intervals in a peripheral portion 2 of a ground 1 where an underground cavity in an urban area is to be constructed. The inner diameter of the excavating shield machine is 3 to 3 in consideration of the workability of the construction.
About 5 m is desirable. The pitch and the number of shields to be excavated are determined according to the result of analyzing the scale of the underground cavity to be constructed and the strength of the ground by FEM analysis etc., and may not be specified because it may be only the upper part. is there.

【0007】図2は、掘削した作業坑3からの地盤補強
の施工状態を示すものである。シールド内からの補強工
事は、図示のように各作業坑3からの補強用部材4を地
下空洞構築地盤周辺2にこれを補強するように施工する
ことで補強土ゾーン5を形成する。隣接する作業坑3か
らの補強用部材4とは互いに補完し合うように交互に交
差させて施工するのも1つの方法である。補強用部材4
としては、モルタル杭、鋼製パイプ、ロックボルト等を
挙げることができるが、使用目的を確立できる機能を有
しているものであれば、これを採用することに制限はな
い。
FIG. 2 shows a construction state of ground reinforcement from the excavated work pit 3. In the reinforcement work from inside the shield, as shown in the figure, the reinforcing member 4 from each work pit 3 is constructed around the underground cavity construction ground 2 so as to reinforce it, thereby forming the reinforcing soil zone 5. One method is to alternately intersect with the reinforcing member 4 from the adjacent work pit 3 so as to complement each other. Reinforcing member 4
Examples thereof include mortar piles, steel pipes, lock bolts, and the like, but there is no limitation on adopting these as long as they have a function of establishing the purpose of use.

【0008】地下空洞構築地盤1の周辺に補強土ゾーン
5を形成すると、図3に示すように地下空洞を構築する
ための本工事を実施する。地下空洞構築地盤1は、上述
のように地盤に補強土ゾーン5を形成してあるので、N
ATM工法や機械掘削のような安価な工法を採用するこ
とが可能になる。NATM工法の場合には、所定の空間
6を通常の方法で数段階に分けて分割掘削してから掘削
面にコンクリート7を吹き付け、これをロックボルト8
で補強してから2次覆工して工事を完了する。また、バ
ックホー等の機械掘削の場合にも機械によって所定の掘
削をしてから覆工を行う通常の工法を適用することで工
事を完了させることができる。
When the reinforced soil zone 5 is formed around the underground cavity construction ground 1, as shown in FIG. 3, the main work for constructing the underground cavity is performed. The underground cavity construction ground 1 has the reinforcing soil zone 5 formed in the ground as described above.
It becomes possible to adopt an inexpensive construction method such as the ATM construction method or mechanical excavation. In the case of the NATM method, a predetermined space 6 is divided and excavated in several steps by an ordinary method, and then concrete 7 is sprayed on the excavation surface, and the concrete 7 is
After completing the construction, complete the secondary lining. Also, in the case of mechanical excavation of a backhoe or the like, the construction can be completed by applying a normal construction method in which a predetermined excavation is performed by a machine and then lining is performed.

【0009】図4は、上述の図2で示した地盤補強の他の
例を紹介するためのものである。図4(イ)に示す例
は、図示のように作業坑3からの補強用部材4を特定方
向の隣接作業坑3の上部9に亙って地盤を補強するため
に施工するもので作業効率の向上を図れる実施の形態で
ある。図4(ロ)に示す他の例は、作業坑の31つから両
側に補強用部材4を伸長させて施工し、これに隣接する
作業坑からは補強用部材を伸長施工させずに、上記補強
用部材を隣接する作業坑3の上部9に亙って地盤を補強
するために施工する作業効率の向上を図れるさらに他の
実施の形態である。
FIG. 4 is for introducing another example of the ground reinforcement shown in FIG. 2 described above. In the example shown in FIG. 4 (a), as shown in the figure, the reinforcing member 4 from the work pit 3 is constructed to reinforce the ground over the upper part 9 of the adjacent work pit 3 in a specific direction. This is an embodiment that can improve the performance. In another example shown in FIG. 4 (b), the reinforcing member 4 is extended from 31 of the working pits on both sides and constructed, and the reinforcing member 4 is not extended and constructed from the working pit adjacent thereto. This is still another embodiment in which the efficiency of work for reinforcing the ground over the upper part 9 of the adjacent work pit 3 with the reinforcing member can be improved.

【0010】図5〜7に示す例は、作業坑の掘削後の活
用展開について種々の実施の形態を紹介するものであ
る。図5に示す例は、図2で紹介した補強例の場合で掘
削する地盤1が軟弱層の場合に作業坑3を地下空洞6の
上部保護に活用する例で、地下空洞構築後に地下空洞6
の上部10に埋め戻すことで剛性を持たせた補強用シー
ルド10を形成する例である。本例は、地下空洞掘削時
の覆工厚を減少させる目的で採用できるものである。
The examples shown in FIGS. 5 to 7 introduce various embodiments of utilization development after excavation of a work pit. The example shown in FIG. 5 is an example in which the working pit 3 is used to protect the upper part of the underground cavity 6 when the ground 1 to be excavated is a soft layer in the case of the reinforcement example introduced in FIG.
This is an example in which a reinforcing shield 10 having rigidity is formed by being buried in the upper part 10 of the base member. This example can be adopted for the purpose of reducing the lining thickness when excavating an underground cavity.

【0011】図6に示す例も掘削する地盤1が軟弱層の
場合に採用できる例であり、補強用部材4は施工せずに
作業坑3のみを地下空洞の補強にに活用する例で、地下
空洞構築後に埋め戻すことで剛性を持たせた補強用シー
ルド10を地下空洞6の上部に形成している。本例も地
下空洞掘削時の覆工厚を減少させるための目的で採用で
きる。
The example shown in FIG. 6 is also an example in which the ground 1 to be excavated is a soft layer, and is an example in which only the work pit 3 is used to reinforce an underground cavity without constructing the reinforcing member 4. A reinforcing shield 10 having rigidity by being buried back after the construction of the underground cavity is formed above the underground cavity 6. This example can also be adopted for the purpose of reducing the lining thickness when excavating an underground cavity.

【0012】図7の例は、補強方式を他の例と異にする
ものである。即ち、地下空洞の上部に該当する作業坑3
の1つから地下空洞の覆工コンクリート11に対して吊
り下げボルト12を通して地盤支持をするもので、該当
作業坑は埋め戻すことなくその両サイドの作業坑3のみ
を埋め戻しておくものである。
The example of FIG. 7 differs from the other examples in the reinforcing method. That is, the work pit 3 corresponding to the upper part of the underground cavity
The ground support is provided from one of the above to the lining concrete 11 of the underground cavity through the suspension bolts 12, and the work pit is not backfilled but only the work pits 3 on both sides thereof are backfilled. .

【0013】図8で示す作業坑の活用例は、掘削地盤を
補強するために活用するものでなく、地下空洞を構築す
る地盤が帯水層13である場合に採用する例である。こ
の場合は、地下空洞の掘削施行を推進する際に作業区間
に湧水等が発生しないように帯水層13からの水を作業
坑14に集めてから外部に放水してしまうのに活用して
いるものである。
FIG. 8 shows an example in which the working pit is not used to reinforce the excavated ground, but is used when the ground for constructing the underground cavity is the aquifer 13. In this case, it is used to collect water from the aquifer 13 into the work pit 14 and then discharge the water to the outside so that no spring water is generated in the work section when promoting the excavation of the underground cavity. Is what it is.

【0014】図9は、これまで紹介してきた上記の施工
方法で構築した地下空洞15の完成状態を示している。
地下空洞15の周辺に事前に施工された作業坑3は、1
部を埋め戻すことで地盤の補強用シールド10として活
用しており、いくつかの作業坑についてはこれを埋め戻
さずに地下空洞と掘削連結することで、一体の地下空洞
として構築している。この場合の埋め戻さない作業坑
は、図示のように、換気坑16、避難坑17及び排水坑
18として形成して地下空洞6と斜坑19等で一帯に関
連付けており、それぞれが地下構築物として完成してい
る。以上詳細に説明したように、本発明による地下空洞
の施工方法は、地下空洞を掘削する本工事の前に製造が
容易で安価で取り扱いの簡単なシールドマシンを使用し
て作業坑を構築して周辺地盤の補強をしておき、その後
に安価な山岳トンネル工法を採用していることで地下空
洞を構築する本工事を行い、全体として安全確実にして
安価に地下空洞の構築を完成する方法である。
FIG. 9 shows a completed state of the underground cavity 15 constructed by the above-described construction method introduced so far.
The working pit 3 constructed in advance around the underground cavity 15 is 1
By refilling the part, it is used as a ground reinforcement shield 10, and some working pits are constructed as an integrated underground cavity by excavating and connecting to some underground cavities without backfilling. In this case, the working pit which is not backfilled is formed as a ventilation pit 16, an evacuation pit 17 and a drain pit 18 as shown in the figure, and is associated with the underground cavity 6 and the inclined pit 19, etc., each of which is completed as an underground construction. doing. As described in detail above, the method of constructing an underground cavity according to the present invention uses a shield machine that is easy to manufacture, inexpensive, and easy to handle before constructing the underground cavity. The construction of the underground cavity is carried out by reinforcing the surrounding ground and then using the inexpensive mountain tunnel construction method. is there.

【0015】[0015]

【発明の効果】本発明は、基本的に空洞形成予定地盤の
外側に複数個の作業坑を安全確実なシールドマシンで築
造し、その作業坑から空洞周辺に沿って補強土ゾーンを
形成してから安価な山岳トンネル工法を用いて所定の空
洞を掘削する地下空洞の施工方法である。そして、必要
に応じて補強を要する側の作業坑を埋め込んだり、
補強が作業坑の埋め込みのみで補強土ゾーンを形成しな
いで済ましているものであり、作業坑からの吊り下げボ
ルトで地下空洞を補強することや帯水層に地下空洞を構
築する必要がある場合には作業坑を水抜き坑として活用
しており、さらに、上記施工方法での工事完了後に作業
坑を地下空洞に連結して、換気、避難等の有効坑として
一体化した地下空洞であるから、以下の各種効果を奏す
るものである。 (1)補強土ゾーンの事前形成で地下空洞が安価にかつ
安全に施工することができ、断面変化にも追従できる。 (2)都市域でも無理なく適用することが可能である。 (3)補強土ゾーンは、地盤状況、地下空洞の大きさ、
地下水状況などに応じて自由に選択することができる。 (4)作業坑を、避難、排水及び換気等坑として活用で
き地下空洞に余分な空間を必要としない。
According to the present invention, basically, a plurality of working pits are constructed outside the ground where the cavity is to be formed with a safe and secure shield machine, and a reinforcing soil zone is formed from the working pit along the periphery of the cavity. This is a method of constructing an underground cavity for excavating a predetermined cavity using a cheap mountain tunnel method. And if necessary, bury work pits on the side that needs reinforcement,
Reinforcement is only for embedding work pits and does not form a reinforced soil zone, and it is necessary to reinforce underground cavities with suspension bolts from work pits or to build underground cavities in aquifers The work pit is used as a drain pit, and after the completion of the above construction method, the work pit is connected to the underground cavity, and it is an underground cavity integrated as an effective pit for ventilation, evacuation, etc. The following various effects can be obtained. (1) The underground cavity can be constructed inexpensively and safely by the pre-formation of the reinforcing soil zone, and it can follow the cross section change. (2) It can be applied without difficulty in urban areas. (3) Reinforcement soil zone is ground condition, underground cavity size,
It can be freely selected according to groundwater conditions. (4) The working pit can be used as a pit for evacuation, drainage, ventilation, etc., and no extra space is required in the underground cavity.

【図面の簡単な説明】[Brief description of the drawings]

【図1】作業坑の施工状況図Fig. 1 Construction situation diagram of working pit

【図2】補強土ゾーンの形成図FIG. 2 is a diagram showing formation of a reinforcing soil zone.

【図3】地下空洞本体の掘削施工図Fig. 3 Excavation drawing of the underground cavity body

【図4】補強土ゾーンの他の形成図FIG. 4 is another formation diagram of the reinforcing soil zone.

【図5】作業坑の補強活用図FIG. 5: Reinforcement diagram of work pit

【図6】作業坑の他の補強活用図FIG. 6 is a diagram showing another use of the work pit for reinforcement.

【図7】作業坑の地下空洞補強図FIG. 7: Underground cavity reinforcement diagram of working pit

【図8】作業坑の水抜き坑としての活用図FIG. 8: Utilization diagram of working pit as drainage pit

【図9】地下空洞完成図Fig. 9 Underground cavity completed

【符号の説明】[Explanation of symbols]

1 地盤 2 地下空洞構築地盤周辺 3 作業坑 4 補強用部材 5 補強土ゾーン 6 空間 7 吹き付けコンクリート 8 ロックボルト 10 補強用シールド 11 覆工コンクリート 12 吊り下げボルト 13 帯水層 14 作業坑 15 地下空洞 16 換気坑 17 避難坑 18 排水坑 19 斜坑 DESCRIPTION OF SYMBOLS 1 Ground 2 Underground cavity construction ground 3 Working pit 4 Reinforcement member 5 Reinforced soil zone 6 Space 7 Shotcrete 8 Rock bolt 10 Reinforcement shield 11 Lining concrete 12 Hanging bolt 13 Aquifer 14 Working pit 15 Underground cavity 16 Ventilation pit 17 Evacuation pit 18 Drain pit 19 Shaft pit

───────────────────────────────────────────────────── フロントページの続き (72)発明者 石川 裕 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 ────────────────────────────────────────────────── ─── Continued on front page (72) Inventor Hiroshi Ishikawa 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Corporation

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 空洞形成予定地盤の外側に複数個の作業
坑をシールドマシンで築造し、該作業坑から空洞周辺に
沿って補強土ゾーンを形成した後に山岳トンネル工法を
用いて所定の空洞を掘削する地下空洞の施工方法。
1. A plurality of working pits are constructed outside a ground formation scheduled ground by a shield machine, a reinforcing soil zone is formed from the working pits along the periphery of the cavities, and a predetermined cavity is formed by using a mountain tunnel method. How to construct the underground cavity to be excavated.
【請求項2】 要補強側の作業坑を埋め込むことを特徴
とする請求項1に記載の地下空洞の施工方法。
2. The method for constructing an underground cavity according to claim 1, wherein a work pit on the side requiring reinforcement is buried.
【請求項3】 要補強側の補強土ゾーンの形成が、作業
坑の埋め込みのみであることを特徴とする請求項1に記
載の地下空洞の施工方法。
3. The method for constructing an underground cavity according to claim 1, wherein the formation of the reinforcing soil zone on the side requiring reinforcement is performed only by embedding a working pit.
【請求項4】 作業坑からの吊り下げボルトで地下空洞
を補強することを特徴とする請求項1〜3のいずれかに
記載の地下空洞の施工方法。
4. The method for constructing an underground cavity according to claim 1, wherein the underground cavity is reinforced with a suspension bolt from a work pit.
【請求項5】 作業坑を帯水層の水抜き坑として活用す
ることを特徴とする請求項1〜4のいずれかに記載の地
下空洞の施工方法。
5. The method for constructing an underground cavity according to claim 1, wherein the work pit is used as a drainage pit for an aquifer.
【請求項6】 作業坑の一部を地下空洞と連結して換
気、避難等の有効坑とすることを特徴とする請求項1〜
5のいずれかに記載の地下空洞の施工方法で施工された
地下空洞。
6. An effective pit for ventilation, evacuation, etc. by connecting a part of a work pit to an underground cavity.
5. An underground cavity constructed by the method for constructing an underground cavity according to any one of 5.
JP53898A 1998-01-05 1998-01-05 Underground cavity construction method and underground cavity construction thereby Pending JPH11193689A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP53898A JPH11193689A (en) 1998-01-05 1998-01-05 Underground cavity construction method and underground cavity construction thereby

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP53898A JPH11193689A (en) 1998-01-05 1998-01-05 Underground cavity construction method and underground cavity construction thereby

Publications (1)

Publication Number Publication Date
JPH11193689A true JPH11193689A (en) 1999-07-21

Family

ID=11476536

Family Applications (1)

Application Number Title Priority Date Filing Date
JP53898A Pending JPH11193689A (en) 1998-01-05 1998-01-05 Underground cavity construction method and underground cavity construction thereby

Country Status (1)

Country Link
JP (1) JPH11193689A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015203193A (en) * 2014-04-11 2015-11-16 大成建設株式会社 tunnel construction method
CN106640117A (en) * 2017-03-08 2017-05-10 中国电建集团中南勘测设计研究院有限公司 Underground cavern top arc structure, underground cavern and construction method of underground cavern
CN106640118A (en) * 2017-03-08 2017-05-10 中国电建集团中南勘测设计研究院有限公司 Underground cavity arch crown structure, underground cavity and underground cavity construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015203193A (en) * 2014-04-11 2015-11-16 大成建設株式会社 tunnel construction method
CN106640117A (en) * 2017-03-08 2017-05-10 中国电建集团中南勘测设计研究院有限公司 Underground cavern top arc structure, underground cavern and construction method of underground cavern
CN106640118A (en) * 2017-03-08 2017-05-10 中国电建集团中南勘测设计研究院有限公司 Underground cavity arch crown structure, underground cavity and underground cavity construction method
CN106640117B (en) * 2017-03-08 2019-02-19 中国电建集团中南勘测设计研究院有限公司 A kind of underground cavern crown structure, underground chamber and Cavity Construction method
CN106640118B (en) * 2017-03-08 2019-02-19 中国电建集团中南勘测设计研究院有限公司 A kind of underground cavern crown structure, underground chamber and Cavity Construction method

Similar Documents

Publication Publication Date Title
CN210598987U (en) Subway station based on single-layer four-guide-hole and middle-guide-hole inner pile foundation
CN111456773A (en) Close-fitting open-and-underground excavation combined subway station structure and construction method thereof
CN108797618A (en) One kind being used for Urban Underground pipe gallery drainage of foundation pit structure and its construction method
JP4132442B2 (en) Tunnel construction method
KR101065458B1 (en) Rock Shed Tunnel Structure as Retaining Wall and Contructing Method for Such Rock Shed Tunnel Structure
CN104895111A (en) Construction method of integrated pipe trench in soft soil
CN113482021A (en) Half-pile supporting structure for excavating shallow foundation pit above underground structure floor and construction method
CN101161947A (en) Integration method of lagging pile and dewatering well for foundation ditch support
JP4493936B2 (en) Method for constructing tunnel junction and tunnel junction
JP2000352296A (en) Method o constructing passage just under underground structure
KR100313721B1 (en) Method for designing synthetic underground retaining wall by temporary soil protection structure and working process of underground retaining wall of structure
JPH11193689A (en) Underground cavity construction method and underground cavity construction thereby
JPH03202599A (en) Reinforced structure of twin tunnels
JP2000179299A (en) Large-section tunnel construction method
CN103046556A (en) Inside-support-free ring-shaped enclosure structure and manufacturing method thereof
CN108643195A (en) The main body of foundation pit and the integral system of supporting construction and method
JP2893349B2 (en) Large section tunnel structure and its construction method.
CN111441794B (en) Underground excavation construction method and structure for rebuilding existing tunnel into double-layer tunnel
CN114411781A (en) Construction method of rock geological sheet pile cofferdam
CN210459300U (en) Enclosure structure for covering and digging station
CN106988337A (en) A kind of reinforcement means for being used to reduce bar shaped shallow foundation house differential settlement
CN106498951A (en) A kind of shaft excavation construction method
JP3772915B2 (en) Foundation pile construction method and foundation pile
CN214939276U (en) Suspension bridge major diameter secant pile gravity type anchorage foundation envelope
CN212202085U (en) Close-adhesion type open-and-underground excavation combined subway station structure

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040611

A131 Notification of reasons for refusal

Effective date: 20040706

Free format text: JAPANESE INTERMEDIATE CODE: A131

RD02 Notification of acceptance of power of attorney

Effective date: 20040712

Free format text: JAPANESE INTERMEDIATE CODE: A7422

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20041109