JPH0310198Y2 - - Google Patents

Info

Publication number
JPH0310198Y2
JPH0310198Y2 JP11051885U JP11051885U JPH0310198Y2 JP H0310198 Y2 JPH0310198 Y2 JP H0310198Y2 JP 11051885 U JP11051885 U JP 11051885U JP 11051885 U JP11051885 U JP 11051885U JP H0310198 Y2 JPH0310198 Y2 JP H0310198Y2
Authority
JP
Japan
Prior art keywords
steel sheet
groove
trench
sheet piles
members
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP11051885U
Other languages
Japanese (ja)
Other versions
JPS6221140U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP11051885U priority Critical patent/JPH0310198Y2/ja
Publication of JPS6221140U publication Critical patent/JPS6221140U/ja
Application granted granted Critical
Publication of JPH0310198Y2 publication Critical patent/JPH0310198Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【考案の詳細な説明】 産業上の利用分野 本考案は掘削溝の土留装置に係り、特に、掘削
装置により掘削された溝壁の崩れ落ちを防止する
ために、溝壁に沿つて鋼矢板を立設し、かつ、前
記溝幅方向で鋼矢板間に腹起こし材を介し間隔保
持部材を介在固定させる作業の能率向上及び資材
の軽減化を図るとともに、これらの諸作業を掘削
溝に作業員が入ることなく、地上より全て施工で
きるようにしたものである。
[Detailed description of the invention] Industrial application field The present invention relates to an earth retaining device for an excavation trench, and in particular, to prevent the trench wall excavated by an excavation device from collapsing, steel sheet piles are erected along the trench wall. In addition, we aim to improve efficiency and reduce the amount of materials used to interpose and fix the spacing member between the steel sheet piles in the trench width direction through the raised material, and also to reduce the amount of materials required for these tasks. All construction work can be done from the ground level without entering the building.

従来の技術 一般に、電信、電話線その他上下水道、ガス管
等の管路を地中に埋設する工事においては、予め
開溝を掘削し、この開溝上方から溝底に管路を敷
設し、掘削土を埋戻して埋設する。開溝はその幅
60〜90cmで深さが150cm程度のものであるが、そ
の溝壁は土の場合が多いために崩れ易く、作業員
が溝内に入つて作業をするのは危険であるから、
溝壁の崩れ落ちを防止するために土留工事を行
う。この土留工事は、溝壁に沿つて鋼矢板又は板
材を打込んで立設し、かつ、この鋼矢板に同列方
向で腹起こし材を当てるとともに、その腹起こし
材間に溝幅方向で伸縮調節自在な管体等の間隔保
持部材(切梁)を介在固定することによつてなさ
れた。このため、溝壁の土圧に十分対抗できるよ
うに、多くの間隔保持部材を用いるので、溝内に
は溝幅方向で多数の耐力用資材が存していて、管
路を溝底に敷設する工事も極めて困難となる。
BACKGROUND TECHNOLOGY Generally, in construction work to bury telegraph, telephone lines, water, sewage, gas pipes, etc. underground, an open trench is excavated in advance, and the pipe is laid from above the trench to the bottom of the trench. Backfill the excavated soil and bury it. The width of the open groove
The trench walls are 60 to 90 cm wide and about 150 cm deep, but the walls of these trenches are often made of soil and are prone to collapse, making it dangerous for workers to work inside the trenches.
Earth retaining work will be carried out to prevent the ditch walls from collapsing. This earth retaining work involves driving and erecting steel sheet piles or planks along the trench walls, and then applying stripping materials to the steel sheet piles in the same direction, and adjusting the expansion and contraction in the trench width direction between the stripping materials. This was achieved by intervening and fixing spacing members (struts) such as flexible tubes. For this reason, many spacing members are used to sufficiently resist the earth pressure on the trench walls, so a large number of load-bearing materials exist in the trench in the trench width direction, and the conduit is laid at the bottom of the trench. Construction work to do so will also be extremely difficult.

その上、この種の工事にあつては、溝内に作業
員が入り諸作業を行うことが施工主(例えば、日
本電信電話株式会社等)の人身事故防止の見地か
ら禁止されることが多く、ケーブル埋設工事は全
て開溝の上方から行わねばならない場合が多い。
Furthermore, in this type of construction, it is often prohibited for the construction owner (for example, Nippon Telegraph and Telephone Corporation, etc.) to allow workers to enter the trench to perform various tasks in order to prevent personal injury. In many cases, all cable burying work must be done from above the open trench.

考案が解決しようとする問題点 しかしながら、上記従来の技術によると、鋼矢
板等は溝底近傍の溝壁の崩れ落ちを防止するため
に、少なくとも溝底に打込んで立設しなければな
らないので、鋼矢板の上端部を叩き込む作業が必
要である。しかも、打込んだ鋼矢板の倒れを防止
するとともに所定の土圧に対抗するために多数の
間隔保持部材を腹起こし材を介し、鋼矢板間に介
在固定する作業が必要である。その上、これらの
諸作業は溝の上方から、すなわち溝内に作業員が
入ることなしに行わねばならないので、作業能率
が良好でない。そして、ケーブルを挿入した管路
を溝底に敷設する場合にあつても、多数の間隔保
持部材が溝の幅方向で介在するため、溝の長手方
向に敷設される管路を溝内に挿入し溝底に載置す
べき作業が面倒で手間を要するのである。勿論、
管路の溝内挿入作業も溝の上方から行なわなけれ
ばならない。かくして、ケーブル埋設工事は、多
くの資材と繁雑な手間を要し、、作業能率が低い、
などの問題があつた。
Problems to be Solved by the Invention However, according to the above-mentioned conventional technology, steel sheet piles, etc. must be driven into at least the trench bottom to prevent the trench walls near the trench bottom from collapsing. It is necessary to hammer in the upper end of the steel sheet pile. Moreover, in order to prevent the driven steel sheet piles from collapsing and to resist a predetermined earth pressure, it is necessary to interpose and fix a large number of spacing members between the steel sheet piles via a raising member. Moreover, these operations must be performed from above the groove, that is, without a worker entering the groove, resulting in poor work efficiency. Even when a conduit with a cable inserted is laid at the bottom of the groove, many spacing members are interposed in the width direction of the groove, so the conduit laid in the longitudinal direction of the groove is inserted into the groove. However, the work of placing it on the bottom of the groove is troublesome and time-consuming. Of course,
Insertion of the pipe into the groove must also be carried out from above the groove. Therefore, cable burying work requires a lot of materials and complicated labor, and the work efficiency is low.
There were problems such as.

問題点を解決するための手段 本考案は、上記問題点の解決を図るため、掘削
溝の溝壁に沿つて立設された鋼矢板の上端部に吊
下固定される一対の側部材と、該側部材の上端部
間を結び伸縮自在な収縮部材と、該収縮部材の下
位において前記側部材の下端部間を結び伸縮自在
な間隔保持部材と、前記側部材の上端外側及び下
端内側にそれぞれ設けられ腹起こし材を着脱自在
に挿通する支架部材とからなる掘削溝の土留装置
を提供する。
Means for Solving the Problems In order to solve the above problems, the present invention includes a pair of side members that are suspended and fixed to the upper end of a steel sheet pile erected along the trench wall of an excavation trench; a retractable member that connects the upper ends of the side members, a retractable spacing member below the retractable member that connects the lower ends of the side members, and an outer upper end and an inner lower end of the side members, respectively To provide an earth retaining device for an excavated trench, which comprises a supporting member provided therein and through which a raising member is inserted in a detachable manner.

作 用 本考案の上記構成によれば、鋼矢板を溝底に打
込むことなく載置してその上端に側部材を吊支固
定するとともに、腹起こし材を装着し、間隔保持
部材を操作して鋼矢板を溝壁に当接固定し、収縮
部材を操作して側部材の上端部を互いに近接させ
ると、鋼矢板は間隔保持部材を支点として下端部
が溝壁方向へ拡幅して押圧するもので、溝底近傍
に間隔保持部材を多数介設する必要がなく溝空間
を大きくし、したがつて管路の埋設作業が容易と
なり、かつ、腹起こし材と収縮部材及び間隔保持
部材の上下2本が側部材に一体的に組付けられて
いるので、鋼矢板の倒れ防止のための補強作業を
簡便迅速かつ容易にする作用がある。
Effects According to the above configuration of the present invention, the steel sheet pile is placed without being driven into the trench bottom, the side member is suspended and fixed to the upper end of the sheet pile, the raising member is attached, and the spacing member is operated. When the steel sheet piles are fixed in contact with the groove walls and the contraction members are operated to bring the upper ends of the side members closer to each other, the lower ends of the steel sheet piles are expanded and pressed toward the groove walls using the spacing member as a fulcrum. This eliminates the need to interpose a large number of spacing members near the groove bottom, making the groove space larger, making it easier to bury the pipe, and keeping the top and bottom of the raising material, contraction member, and spacing member Since the two pieces are integrally assembled to the side member, the reinforcing work to prevent the steel sheet piles from falling down is simple, quick, and easy.

実施例 以下に本考案を図示の実施例に基づき説明す
る。
Embodiments The present invention will be explained below based on illustrated embodiments.

第1図は正面図、第2図は平面図、第3図は側
面図、第4図及び第5図は間隔保持部材の平面図
及び側面図、第6図は第2図A−A断面図、第7
図及び第8図は使用例を示す掘削溝の平面図及び
第7図B−B断面図である。
Fig. 1 is a front view, Fig. 2 is a plan view, Fig. 3 is a side view, Figs. 4 and 5 are a plan view and side view of the spacing member, and Fig. 6 is a cross section taken along line A-A in Fig. 2. Figure, 7th
The figure and FIG. 8 are a plan view of an excavated trench and a sectional view taken along the line B-B in FIG. 7, showing an example of use.

第1図から第6図において、1は左右一対の側
部材、2は側部材1,1の上端部近傍に軸支連結
されて伸縮可能な収縮部材、3は側部材1,1の
下端部に軸支連結されて伸縮可能な間隔保持部材
で、これらが四辺形の構体を形成している。
In FIGS. 1 to 6, 1 is a pair of left and right side members, 2 is a retractable member that is pivotally connected to the upper end of the side members 1 and 1, and 3 is the lower end of the side members 1 and 1. The spacing member is pivotably connected to and expandable and retractable, and these form a quadrilateral structure.

側部材1は、鋼矢板4よりも小幅で約80cm程度
の高さを有する金属板の上下端部を、それぞれ外
方及び内方へ曲成し、上端部には鋼矢板4の上端
に吊下する引掛部1a及びその引掛部1aと連結
して鋼矢板4を包囲できる枠部5を有するととも
に、その枠部5の外側には腹起こし材36を挿通
固定する支架部6を有し、かつ、下端部に他の腹
起こし材37を載置固定する支架部7を有する。
支架部6は枠部5の外側方向へ突出する上下一対
の張出部6a,6aとその張出部6a,6aの端
部において上方から挿抜可能な逆U字形の止めピ
ン6bとからなる。支架部7は支架部6が側部材
1の外側に設けられるに反し、側部材1の内側に
設けられ、したがつて腹起こし材36,37は鋼
矢板4を挾んで位置する。
The side member 1 is a metal plate having a width smaller than the steel sheet pile 4 and a height of about 80 cm. The upper and lower ends of the metal plate are bent outward and inward, respectively, and the upper end is suspended from the upper end of the steel sheet pile 4. It has a hook part 1a to be lowered and a frame part 5 that can be connected to the hook part 1a to surround the steel sheet pile 4, and has a support part 6 on the outside of the frame part 5 through which a raising material 36 is inserted and fixed, Moreover, it has a support part 7 on the lower end on which another belly raising material 37 is placed and fixed.
The support portion 6 includes a pair of upper and lower overhang portions 6a, 6a that protrude outward from the frame portion 5, and an inverted U-shaped stop pin 6b that can be inserted and removed from above at the ends of the overhang portions 6a, 6a. The support portion 7 is provided on the inside of the side member 1, whereas the support portion 6 is provided on the outside of the side member 1, and therefore the raised members 36 and 37 are positioned to sandwich the steel sheet pile 4.

収縮部材2は、左右の側部材1,1に枠部5の
高さで固着したブラケツト8,8に短管9と内管
10をそれぞれ軸ピン11,11で軸支連結し、
この短管9と内管10を両端部に挿入した外管1
2とを有し、短管9と外管12とはピン13で連
結固定する一方、内管10と外管12とは軸方向
移動可能に係合させる。すなわち、第4図及び第
5図に示すように、内管10と外管12とはそれ
ぞれ直径方向に穿設されたピン穴14,15を一
定の間で有し、また外管12にはピン穴14と同
列の長穴16を有する。ピン穴15はピン穴14
の約1.5ピツチで穿設されていて、いずれか一方
のピン穴15が内管10のスライドによつて位置
の変るピン穴14のいずれかと合致し、ピン17
を挿通可能である。そして、前記長穴16にはコ
形をした金具18が外管12を挾んで位置し、か
つピン19がこの金具18から長穴16を経て内
管10のピン穴14に挿通される。この金具18
には側方へ張出す突出部18aが設けられてお
り、また、少なくともこの突出部18aと同列で
対面し水平な油圧駆動装置固定部20,20aが
外管12の側部に翼状に固着されている。油圧駆
動装置固定部20,20aは簡便な手押し操作型
の油圧発生装置と圧油管で結ばれる小型のジヤツ
キを載置固定する凹部21を有する。11a,1
7a,19aはピン連結用のチエーンである。
The shrinkable member 2 has a short tube 9 and an inner tube 10 pivotally connected to brackets 8, 8 fixed to the left and right side members 1, 1 at the height of the frame portion 5 by shaft pins 11, 11, respectively.
Outer tube 1 with this short tube 9 and inner tube 10 inserted into both ends
2, the short tube 9 and the outer tube 12 are connected and fixed by a pin 13, while the inner tube 10 and the outer tube 12 are engaged so as to be movable in the axial direction. That is, as shown in FIGS. 4 and 5, the inner tube 10 and the outer tube 12 each have pin holes 14 and 15 drilled in the diametrical direction at a certain distance, and the outer tube 12 has pin holes 14 and 15 formed in the diametrical direction. It has a long hole 16 in the same row as the pin hole 14. Pin hole 15 is pin hole 14
The pin holes 15 on either side match with any of the pin holes 14 whose position changes as the inner tube 10 slides, and the pin holes 17
can be inserted. A U-shaped metal fitting 18 is positioned in the elongated hole 16, sandwiching the outer tube 12, and a pin 19 is inserted through the elongated hole 16 from the metal fitting 18 into the pin hole 14 of the inner tube 10. This metal fitting 18
is provided with a protrusion 18a that protrudes laterally, and horizontal hydraulic drive device fixing parts 20, 20a that face at least the same line as the protrusion 18a are fixed to the side of the outer tube 12 in the form of wings. ing. The hydraulic drive device fixing portions 20, 20a have a recess 21 in which a simple hand-operated hydraulic pressure generating device and a small jack connected by a pressure oil pipe are placed and fixed. 11a,1
7a and 19a are chains for connecting pins.

間隔保持部材3は、左右の側部材1,1に固着
したブラケツト22,22に、支架部7を構成す
べきアングル材からなる蓋部23,23が軸ピン
24,24を介し軸支連結され、かつ、これらの
蓋部23,23間には既製の挺子型ジヤツキ25
がピン26,27で連結されてなる。この挺子型
ジヤツキ25は、第6図に示す如く、ケース28
と、ケース28に挿通されて軸方向へ進退可能な
シヤフト29と、シヤフト29を貫通してケース
28にロツクばね30を介し固定したロツク板3
1と、ロツク板31との間に駆動用ばね32を介
在しシヤフト29を貫通し傾動可能な駆動板33
と、駆動板33を傾動させる駆動レバー34とか
らなり、駆動レバー34を前後へ倒すことを繰り
返すと駆動板33が傾動してシヤフト29をケー
ス28から押し出す一方、駆動レバー34を図示
とは反対方向へ倒しシヤフト29に圧力を加えれ
ばシヤフト29はケース28側へ引込まれるとい
うものである。
In the spacing member 3, lid portions 23, 23 made of angle material, which constitute the support portion 7, are pivotally connected via shaft pins 24, 24 to brackets 22, 22 fixed to the left and right side members 1, 1. , and there is a ready-made screw-type jack 25 between these lid parts 23, 23.
are connected by pins 26 and 27. This screw type jack 25 is attached to the case 28 as shown in FIG.
, a shaft 29 that is inserted through the case 28 and can move back and forth in the axial direction, and a lock plate 3 that passes through the shaft 29 and is fixed to the case 28 via a lock spring 30.
1 and the lock plate 31, a drive spring 32 is interposed between the drive plate 33, which passes through the shaft 29 and is tiltable.
and a drive lever 34 that tilts the drive plate 33. When the drive lever 34 is repeatedly tilted back and forth, the drive plate 33 tilts and pushes the shaft 29 out of the case 28, while the drive lever 34 is tilted in the opposite direction as shown in the figure. If the shaft 29 is tilted in the direction and pressure is applied to the shaft 29, the shaft 29 will be pulled toward the case 28 side.

次に、第7図及び第8図に基づき、上記実施例
の使用例を説明する。予めバツクフオー等の掘削
装置で所定幅及び深さに掘削された溝35の両溝
壁35a,35aに沿つて鋼矢板4,4を挿入
し、その鋼矢板4,4の上端部は溝35から所定
の高さで突出させ、かつ、下端部を溝底35bに
打込むことなく溝底35bに載置して立設する。
溝35の長手方向に沿い密接し、又は所定の間隔
で溝壁35a,35aに沿つて所定の長さ、例え
ば3〜4mで鋼矢板4,4を立設すると、その両
端側に位置する鋼矢板4の一対間に土留装置をそ
れぞれ入れ、側部材1,1の枠部5,5をそれぞ
れ鋼矢板4,4の上端部に嵌合し、かつ鋼矢板
4,4の上端部にそれぞれ引掛部1a,1aを吊
下固定させる。こうして3〜4m間隔で一対の土
留装置が溝35内に吊下されると、溝35の長手
方向で相対する支架部6,7には腹起こし材3
6,37をそれぞれ装着する。この作業は溝35
の上方から行なう。腹起こし部材36,37によ
り中間部の鋼矢板4aは鋼矢板4と一体化され倒
れ難くなる。ついで、間隔保持部材3を操作して
両側の鋼矢板4,4を溝壁35a,35aに押し
付け、間隔を固定する。この操作は駆動レバー3
4を前後へ倒す作業を繰り返し、シヤフト29を
ケース28から側部材1側へ突出させて行う。こ
うして間隔保持部材3が鋼矢板4,4間に固定さ
れた後、つぎには、収縮部材2を操作することに
よつて鋼矢板4,4の上端部を互いに近接すべく
引寄せる。この操作は、収縮部材2の油圧装置固
定部20にジヤツキ38を載置固定する一方、そ
の作動ロツド39を突出部19に当接させ、その
ジヤツキ38に圧油を供給する。この場合におい
て、内管10と外管12とを連結するピン17は
外しておく。そこでジヤツキ38の作動ロツド3
9が動くと突出部19は金具17がピン19で内
管10と連結されている為、長穴16に沿つて第
6図の左方へ内管10を引寄せるので、収縮部材
2の長さが縮小し、引掛部1a,1a間の間隔は
狭くなる。そこで、前記取外したピン17をピン
穴14,15に挿入し外管12と内管10とを伸
縮不能に固定する。つまり、鋼矢板4,4の上端
部間隔が短縮されると、間隔保持部材3を支点と
して鋼矢板4,4の下端部の間隔は拡大する。そ
の結果、鋼矢板4,4の下端部は溝底35b近傍
の溝壁35aに圧接するから、溝底35b近傍に
間隔保持部材3を介在することなく、溝35内空
間部を広く保有できる。
Next, an example of use of the above embodiment will be explained based on FIGS. 7 and 8. Steel sheet piles 4, 4 are inserted along both groove walls 35a, 35a of the groove 35, which has been excavated in advance to a predetermined width and depth with an excavator such as a backup, and the upper ends of the steel sheet piles 4, 4 are inserted from the groove 35. It is made to protrude at a predetermined height and is placed upright on the groove bottom 35b without driving the lower end into the groove bottom 35b.
When the steel sheet piles 4, 4 are erected for a predetermined length, for example, 3 to 4 m, closely spaced along the longitudinal direction of the groove 35 or along the groove walls 35a, 35a at a predetermined interval, the steel sheet piles 4, 4 located at both ends thereof are A retaining device is inserted between each pair of sheet piles 4, and the frame portions 5, 5 of the side members 1, 1 are fitted to the upper ends of the steel sheet piles 4, 4, respectively, and are hooked to the upper ends of the steel sheet piles 4, 4, respectively. The parts 1a, 1a are suspended and fixed. When the pair of earth retaining devices are suspended in the groove 35 at intervals of 3 to 4 m, the support members 6 and 7 facing each other in the longitudinal direction of the groove 35 are
6 and 37 respectively. This work is done in groove 35.
Do it from above. The steel sheet piles 4a in the intermediate portion are integrated with the steel sheet piles 4 by the raising members 36 and 37, making them difficult to fall down. Next, the spacing member 3 is operated to press the steel sheet piles 4, 4 on both sides against the groove walls 35a, 35a, thereby fixing the spacing. This operation is performed using drive lever 3.
4 is repeated back and forth, and the shaft 29 is made to protrude from the case 28 toward the side member 1 side. After the spacing member 3 is thus fixed between the steel sheet piles 4, 4, the upper end portions of the steel sheet piles 4, 4 are drawn closer to each other by operating the contraction member 2. In this operation, the jack 38 is placed and fixed on the hydraulic device fixing part 20 of the contraction member 2, and the operating rod 39 is brought into contact with the protrusion 19, so that pressure oil is supplied to the jack 38. In this case, the pin 17 connecting the inner tube 10 and the outer tube 12 is removed. Therefore, the operating rod 3 of the jack 38
9 moves, the protrusion 19 pulls the inner tube 10 along the elongated hole 16 to the left in FIG. The distance between the hooks 1a and 1a becomes narrower. Therefore, the removed pins 17 are inserted into the pin holes 14 and 15 to fix the outer tube 12 and the inner tube 10 in a non-expandable manner. That is, when the interval between the upper ends of the steel sheet piles 4, 4 is shortened, the interval between the lower ends of the steel sheet piles 4, 4 is expanded using the interval retaining member 3 as a fulcrum. As a result, the lower end portions of the steel sheet piles 4, 4 come into pressure contact with the groove wall 35a near the groove bottom 35b, so that a wide space inside the groove 35 can be maintained without intervening the spacing member 3 near the groove bottom 35b.

なお、上記の如く装着した土留装置を取り外す
には、収縮部材2のジヤツキ38を上記操作と同
じ油圧装置固定部20に載置し、ピン17が容易
に抜けるように収縮部材2を収縮動作させた後、
ピン17を抜き取れば、間隔保持部材3の拡幅力
によつて収縮部材2は伸長し元の長さに戻る。一
方、収縮部材2を伸長させることもでき、この場
合にはジヤツキ38を油圧装置固定部20とは反
対側の油圧装置固定部20a上に前記とは逆向き
にして載置固定するとともに、突出部18aを有
する金具18をピン19を抜いて取り外し、その
金具18を内管10にピン穴14を介し挾持固定
し、その突出部19にジヤツキ38の作動ロツド
39を当てる。そこでジヤツキ38に圧油を供給
すると作動ロツド39が金具18を第6図の右方
へ押すので収縮部材2の長さが拡大し元の長さに
なることができる。ついで、、間隔保持部材3の
駆動レバー34を倒してシヤフト29をケース2
8内に収縮させ、腹起こし材36,37を抜去す
れば、土留装置は全体として溝35内から上方へ
抜取ることができるのである。このような諸作業
は、側部材1,1の高さが約80cm程度であるか
ら、、溝35の上方から作業員が身を屈して手を
差し込めば行うことができ、溝35内に作業員が
入らずともよい。
In order to remove the earth retaining device installed as described above, place the jack 38 of the retractable member 2 on the hydraulic device fixing part 20 in the same manner as in the above operation, and retract the retractable member 2 so that the pin 17 can be easily removed. After
When the pin 17 is removed, the contraction member 2 is expanded by the width-expanding force of the spacing member 3 and returns to its original length. On the other hand, the contraction member 2 can also be extended, and in this case, the jack 38 is placed and fixed on the hydraulic device fixing part 20a on the opposite side from the hydraulic device fixing part 20 in the opposite direction, and the jack 38 is The metal fitting 18 having the portion 18a is removed by removing the pin 19, the metal fitting 18 is clamped and fixed to the inner tube 10 through the pin hole 14, and the operating rod 39 of the jack 38 is applied to the protruding portion 19. Then, when pressure oil is supplied to the jack 38, the actuating rod 39 pushes the metal fitting 18 to the right in FIG. 6, so that the length of the contraction member 2 is expanded and can return to its original length. Next, push down the drive lever 34 of the spacing member 3 and move the shaft 29 to the case 2.
8 and remove the raising members 36 and 37, the entire earth retaining device can be removed upward from within the groove 35. Since the height of the side members 1, 1 is approximately 80 cm, such operations can be performed by the worker bending down and inserting his/her hand from above the groove 35. There is no need for staff to enter.

考案の効果 以上に説明した本考案によれば、掘削溝の溝壁
に沿つて立設した鋼矢板に吊下固定する側部材
と、側部材間に軸支連結されて伸縮可能な収縮部
材と間隔保持部材とからなる四辺形の構体により
鋼矢板に掛かる土圧に対処する土留装置を得るこ
とができ、しかも、収縮部材を作動して鋼矢板の
上端部間隔を縮小することにより鋼矢板の下端部
間隔を拡大し、溝壁に圧接することができ、溝内
底部に間隔保持部材を設けずして溝内空間に余裕
をもたせ、管路の埋込み作業の能率を図ることが
できるほか、土留用資材の軽減を図ることができ
る。その上、土留装置として一体的に構成されて
いるので使用に際して組立てることもなく、また
必要により分解することもできて軽便で、取扱い
上に支障もない。更には、側部材の高さを小さく
することにより溝の上方から作業員が手を溝内に
入れて間隔保持部材又は収縮部材を操作し、若し
くは腹起こし材を装架できて、構内に作業員が入
ることなく土留工事を施工できる。しかも、鋼矢
板を溝底に打込むことなく載置して立設すればよ
いので、鋼矢板の立設作業が簡略化され、土留工
事の作業能率の向上は勿論のこと、ケーブル埋設
工事等の作業能率を向上させる、等の効果を奏す
る。
Effects of the invention According to the invention described above, there are provided a side member that is suspended and fixed to a steel sheet pile erected along the trench wall of an excavation trench, and a retractable member that is pivotally connected between the side members and is expandable and retractable. It is possible to obtain an earth retaining device that copes with the earth pressure applied to the steel sheet piles by using a quadrilateral structure consisting of a spacing member, and furthermore, by operating the contraction member to reduce the spacing between the upper ends of the steel sheet piles, the steel sheet piles can be The gap between the lower ends can be expanded and the pipe can be pressed against the groove wall, and there is no need to provide a spacing member at the bottom of the groove, allowing for extra space within the groove, making it possible to improve the efficiency of conduit embedding work. It is possible to reduce the amount of earth retaining materials. Moreover, since it is integrally constructed as an earth retaining device, there is no need to assemble it before use, and it can also be disassembled if necessary, making it convenient and easy to handle. Furthermore, by reducing the height of the side members, workers can put their hands into the groove from above the groove to operate the spacing member or contraction member, or install the lifting member, making it easier to carry out work within the premises. Earth retaining work can be carried out without the need for personnel to enter. Moreover, since the steel sheet piles can be placed and erected without driving them into the trench bottom, the work of erecting the steel sheet piles is simplified, which not only improves the work efficiency of earth retaining work, but also improves cable burying work, etc. This has the effect of improving work efficiency, etc.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は正面図、第2図は平面図、第3図は側
面図、第4図及び第5図は間隔保持部材の平面図
及び側面図、第6図は第2図A−A断面図、第7
図及第8図は使用例を示す掘削溝の平面図及び第
7図B−B断面図である。 1……側部材、1a……引掛部、2……収縮部
材、3……間隔保持部材、4……鋼矢板、5……
枠部、6,7……支架部、10……内管、12…
…外管、14,15……ピン穴、16……長穴、
18……金具、20,20a……油圧装置固定
部、21……凹部、25……挺子型ジヤツキ、2
8……ケース、29……シヤフト、30……ロツ
クばね、31……ロツク板、32……駆動用ば
ね、33……駆動板、34……駆動レバー、35
……溝、36,37……腹起こし材、38……油
圧装置。
Fig. 1 is a front view, Fig. 2 is a plan view, Fig. 3 is a side view, Figs. 4 and 5 are a plan view and side view of the spacing member, and Fig. 6 is a cross section taken along line A-A in Fig. 2. Figure, 7th
The figures and FIG. 8 are a plan view of an excavated groove and a sectional view taken along the line B-B in FIG. 7, showing an example of use. DESCRIPTION OF SYMBOLS 1... Side member, 1a... Hook part, 2... Contraction member, 3... Spacing member, 4... Steel sheet pile, 5...
Frame portion, 6, 7... Support portion, 10... Inner pipe, 12...
...outer tube, 14, 15... pin hole, 16... oblong hole,
18...Metal fitting, 20, 20a...Hydraulic device fixing part, 21...Recess, 25...Screw type jack, 2
8... Case, 29... Shaft, 30... Lock spring, 31... Lock plate, 32... Drive spring, 33... Drive plate, 34... Drive lever, 35
... Groove, 36, 37 ... Raising material, 38 ... Hydraulic device.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 掘削溝の溝壁に沿つて立設された鋼矢板の上端
部に吊下固定される一対の側部材と、該側部材の
上端部間を結び伸縮自在な収縮部材と、該収縮部
材の下位において前記側部材の下端部間を結び伸
縮自在な間隔保持部材と、前記側部材の上端外側
及び下端内側にそれぞれ設けられ腹起こし材を着
脱自在に挿通する支架部とからなることを特徴と
する掘削溝の土留装置。
A pair of side members that are suspended and fixed to the upper ends of steel sheet piles erected along the trench walls of an excavation trench, a contractable member that connects the upper ends of the side members and is expandable and contractible, and a lower part of the contractible members. The method is characterized in that it is comprised of an elastic spacing member that connects the lower ends of the side members, and support parts that are provided on the outer side of the upper end and the inner side of the lower end of the side member, and through which the belly-raising material is inserted in a detachable manner. Earth retaining device for excavated trenches.
JP11051885U 1985-07-19 1985-07-19 Expired JPH0310198Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11051885U JPH0310198Y2 (en) 1985-07-19 1985-07-19

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11051885U JPH0310198Y2 (en) 1985-07-19 1985-07-19

Publications (2)

Publication Number Publication Date
JPS6221140U JPS6221140U (en) 1987-02-07
JPH0310198Y2 true JPH0310198Y2 (en) 1991-03-13

Family

ID=30989591

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11051885U Expired JPH0310198Y2 (en) 1985-07-19 1985-07-19

Country Status (1)

Country Link
JP (1) JPH0310198Y2 (en)

Also Published As

Publication number Publication date
JPS6221140U (en) 1987-02-07

Similar Documents

Publication Publication Date Title
JPS6120118Y2 (en)
JPH0310198Y2 (en)
KR200389267Y1 (en) Box type trench shoring apparatus
JP3018921B2 (en) Earth retaining method and earth retaining device
JP3824384B2 (en) Construction method of shaft and apparatus used in the method
JP3011093U (en) Sheet pile connecting device
JP4889993B2 (en) Construction method of widening shaft
JP2000257069A (en) Earth retaining and earth retaining construction method
JPH0745628Y2 (en) Expandable steel sheet pile
JPS6120121Y2 (en)
JP3252365B2 (en) Pillar structure of sheet pile type support for excavation trench
JPH08120676A (en) Earth retaining timbering detaching method and device therefor
JP2618796B2 (en) How to build a wall
JPH0469681B2 (en)
JPS5847091Y2 (en) Earth retention shoring device for excavated trenches
JPS5845323Y2 (en) Tensioning device for earth retaining sheet piles for trench excavation
JPS6027157Y2 (en) Equipment for pulling out earth retaining structures, etc. in excavated trenches
JPS5842508Y2 (en) Crosspiece support device for earthworks
JP2002013382A (en) Square shaft excavation device and work execution method thereof
JPS6310249B2 (en)
JPH082178Y2 (en) Earth retaining plate support device for excavation trench
JPH0874257A (en) Earth retaining device for excavated groove
JPS6310250B2 (en)
JPH0711649A (en) Earth retaining method and earth retaining box
JPH08246459A (en) Excavated ditch earth retaining shoring device