JPS6120118Y2 - - Google Patents

Info

Publication number
JPS6120118Y2
JPS6120118Y2 JP13899380U JP13899380U JPS6120118Y2 JP S6120118 Y2 JPS6120118 Y2 JP S6120118Y2 JP 13899380 U JP13899380 U JP 13899380U JP 13899380 U JP13899380 U JP 13899380U JP S6120118 Y2 JPS6120118 Y2 JP S6120118Y2
Authority
JP
Japan
Prior art keywords
pull
earth retaining
column
removably
electric hoist
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP13899380U
Other languages
Japanese (ja)
Other versions
JPS5760938U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP13899380U priority Critical patent/JPS6120118Y2/ja
Publication of JPS5760938U publication Critical patent/JPS5760938U/ja
Application granted granted Critical
Publication of JPS6120118Y2 publication Critical patent/JPS6120118Y2/ja
Expired legal-status Critical Current

Links

Description

【考案の詳細な説明】 本考案は掘削溝に於ける土留構体に建込・引抜
装置に関するものである。
[Detailed Description of the Invention] The present invention relates to a device for erecting and pulling out earth retaining structures in excavated trenches.

近時、上下水道、ガス等の配管、電信電話ケー
ブル、送電線等を埋設する為の溝を掘削するに際
して、溝内の側壁の土砂くずれを防止する為に、
第1図に示す如く一部掘削した溝1の内側壁に、
左右両側面に案内溝2を有する支柱3を相対向さ
せてその正面に固設された連結部材3aにサポー
トジヤツキ4を張架して連結した2本の支柱3を
建込み、次に相対向する支柱3の一側面の案内溝
2に夫々土留板5の一側端を篏入して土中に圧入
し、次いでこの土留板5の他側端にサポートジヤ
ツキ4にて連結した次の相対向する2本の支柱3
の他側面の案内溝2を嵌合して該支柱3を建込
み、以後この組立てられた土留構体を溝1を深く
掘削するのに合せて土中に圧入し、支柱3の案内
溝2間に土留板5を嵌合して上方に延長し、更に
長手方向への溝掘削に伴い、上記手順にて土留構
体を順次組立て接続していく土留工法が施工され
ている。
Recently, when excavating trenches for burying water, sewage, gas, etc. pipes, telegraph and telephone cables, power transmission lines, etc., in order to prevent landslides on the side walls of the trench,
As shown in Fig. 1, on the inner wall of the partially excavated trench 1,
Two pillars 3 having guide grooves 2 on both left and right sides are placed facing each other, and a support jack 4 is stretched over a connecting member 3a fixed in front of the pillars 3, and the two connected pillars 3 are erected. One side end of the earth retaining plate 5 is inserted into the guide groove 2 on one side of the facing column 3 and press-fitted into the soil, and then connected to the other side end of this earth retaining plate 5 with a support jack 4. Two pillars facing each other 3
The guide groove 2 on the other side is fitted and the support column 3 is erected, and the assembled earth retaining structure is press-fitted into the soil at the same time as the groove 1 is deeply excavated, and the guide groove 2 of the support column 3 is inserted between the guide grooves 2 and 3. An earth retaining method is used in which the earth retaining plate 5 is fitted and extended upward, and the earth retaining structure is sequentially assembled and connected in accordance with the above-mentioned procedure as the trench is further excavated in the longitudinal direction.

ところで前記土留構体に於ける支柱3や土留板
5の建込み、引抜きには、クレーン車などの重機
を用いていたが、最近市街地での工事が多く、ま
た道路幅の狭い現場が多い為、重機が現場に入れ
ない。また土質によつては土留板5を引抜く際、
大きな土圧抵抗によりクレーン車でも容易に引抜
けないなどの問題がある。
By the way, heavy machinery such as a crane truck was used to erect and pull out the pillars 3 and retaining plates 5 in the earth retaining structure, but recently there has been a lot of construction work in urban areas, and there are many sites with narrow roads. Heavy machinery cannot enter the site. Also, depending on the soil quality, when pulling out the retaining plate 5,
There are problems such as the large earth pressure resistance makes it difficult to pull out even with a crane truck.

本考案はかかる問題を解決すべくなされたもの
であり、重機の入れないような狭い現場でも分解
したまま搬入し組立てることができて、支柱や土
留板の建込み、引抜きを簡単に行なうことがで
き、しかも土圧抵抗が大きくてクレーン車でも容
易に引抜けない場合でも簡単に引抜くことのでき
る土留構体の建込・引抜装置を提供せんとするも
のである。
The present invention was developed to solve this problem, and it can be transported and assembled in a disassembled state even at narrow sites where heavy machinery cannot enter, and supports and retaining plates can be easily erected and pulled out. To provide a device for erecting and pulling out an earth retaining structure, which can be easily pulled out even when the earth pressure resistance is so large that even a crane truck cannot pull it out easily.

以下本考案による土留構体の建込・引抜装置の
実施例を図によつて説明すると、第2図a,b,
cに於いて、6は分解組立可能なポータブルクレ
ーンで、このクレーン6は、I形鋼7の左右両端
部の上面に固設したプレート7aの前後に、夫々
同長の車輪8付支柱9の上端が着脱可能に結合さ
れ、前後いずれか一方(図では前方)の左右の支
柱9の下部には夫々手動ウインチ10が着脱可能
に取付けられて他方(図では後方)の左右の支柱
9の下部に一端を緊縛した鋼索10aが巻取ら
れ、前記I形鋼7には電動ホイスト11が走行自
在に吊垂されている。11aは電動ホイスト11
の操作ボタンである。
Below, an embodiment of the earth retaining structure erection/extraction device according to the present invention will be explained using figures.
In c, 6 is a portable crane that can be disassembled and assembled, and this crane 6 has pillars 9 with wheels 8 of the same length attached to the front and rear of a plate 7a fixed to the upper surface of both left and right ends of an I-beam 7. The upper ends are removably connected, and a manual winch 10 is removably attached to the lower part of either the front or rear (front in the figure) left and right columns 9, and the lower part of the other (rear in the figure) left or right column 9. A steel cable 10a with one end tied tightly is wound up, and an electric hoist 11 is suspended from the I-beam 7 so as to be freely movable. 11a is an electric hoist 11
This is the operation button.

12は引抜き台車で、この引抜き台車12は、
前後端に車輪13を設けた左右一対の台枠14上
に夫々支柱15が立設され、この支柱15間に梁
16が摺動可能に張架されて、梁16の所要のピ
ン穴16aが支柱15のピン穴(図示省略)に合
せられてピン15aが挿通されて位置決め上、押
え板17を介してハンドルナツト18にて支柱1
5に締付固定されている。
12 is a pull-out truck, and this pull-out truck 12 is
Supports 15 are erected on a pair of left and right underframes 14 each having wheels 13 at the front and rear ends, and a beam 16 is slidably stretched between the supports 15, so that the required pin holes 16a of the beam 16 are inserted. The pin 15a is inserted into the pin hole (not shown) of the support post 15, and after positioning, the support plate 1 is attached to the handle nut 18 via the holding plate 17.
5 is tightened and fixed.

梁16上には支点柱19が摺動可能に且つ押え
板17を介してハンドルナツト18にて締付固定
されるようになつており、支点柱19の上端には
引抜き挺子20の一端が旋回可能に支持され且つ
上下方向に回転可能に支持されて支点Aとなつて
おり、引抜き挺子20の他端には吊索22が取付
けられてこれが前記電動ホイスト11のフツク1
1bに吊られて引抜き挺子20の他端の吊索22
の取付部が力点Bとなつており、引抜き挺子20
の支点A寄りの中間下側に土留板吊上げ金具23
又は支柱吊上げ金具23′が吊垂されてこの部分
が作用点Cとなつている。土留板吊上げ金具23
は2本の吊索23aの下端に土留板5の上縁の透
孔5aに挿入係止する突起23b付ロツド23c
を取付けたものである。支柱吊上げ金具23′は
2本の吊索23aの下端に支柱3の正面のサポー
トジヤツキ連結用部材3aの上端にピン結合する
二又の金具23dを取付けたものである。
A fulcrum column 19 is slidable on the beam 16 and is tightened and fixed with a handle nut 18 via a presser plate 17, and one end of a pull-out screw 20 is attached to the upper end of the fulcrum column 19. It is rotatably supported and rotatably supported in the vertical direction to serve as a fulcrum A, and a suspension rope 22 is attached to the other end of the extraction lever 20, which connects the hook 1 of the electric hoist 11.
The hanging cable 22 at the other end of the pull-out lever 20 is suspended from 1b.
The mounting part of is the point of emphasis B, and the pull-out screw 20
An earth retaining board lifting fitting 23 is placed on the middle lower side near the fulcrum A.
Alternatively, the support strut lifting fitting 23' is suspended, and this portion serves as the point of action C. Earth retaining board lifting fittings 23
A rod 23c with a protrusion 23b is inserted and locked into the through hole 5a on the upper edge of the retaining plate 5 at the lower end of the two hanging ropes 23a.
This is the one with the . The column lifting fitting 23' has a two-pronged metal fitting 23d attached to the lower ends of the two hanging ropes 23a, which is connected with a pin to the upper end of the support jack connecting member 3a on the front side of the column 3.

かかる構造の本考案による土留構体の建込・引
抜装置の使用法について説明する。例えば市街地
の道路幅の狭い現場で下水管を布設する為に、第
1図に示す如く掘削した溝1に土留工法を施工す
べく土留構体を組立接続する場合、第3図に示す
如く溝1の左右両外側縁に鋼矢板25を平行に敷
設し、この上に分解して搬入した本考案による土
留構体の建込・引抜装置に於けるポータブルクレ
ーン6を組立てる。即ち、各鋼矢板25をレール
としてこの上に車輪8付支柱9を夫々前後に配
し、その各上端を溝1を跨いで配したI形鋼7の
左右両端部上面のプレート7aの前後に結合し、
次にI形鋼7に電動ホイスト11を走行可能に溝
1内で吊垂し、次いで前方の左右の支柱9の下部
に手動ウインチ10を取付けると共に後方の支柱
9の下部に鋼索10aの一端を緊縛する。次に各
鋼索10aの他端を手動ウインチ10に巻取つ
て、倒伏している支柱9を徐々に立上らせると共
に前後の支柱9の間隔をせばめる。I形鋼7が所
要のレベルに達したならば、手動ウインチ10の
巻取りを停止する。
The method of using the device for erecting and pulling out the earth retaining structure according to the present invention will be explained. For example, when constructing and connecting an earth retaining structure to a trench 1 that has been excavated as shown in Figure 1 in order to install a sewer pipe at a site with narrow roads in an urban area, the trench 1 as shown in Figure 3 Steel sheet piles 25 are laid in parallel on both left and right outer edges of the steel sheet piles 25, and the portable crane 6 of the earth retaining structure erecting/extracting device according to the present invention, which has been disassembled and brought in, is assembled thereon. That is, each steel sheet pile 25 is used as a rail, and struts 9 with wheels 8 are disposed on the rails, respectively, and the upper ends thereof are arranged in front and behind the plate 7a on the upper surface of both left and right ends of the I-beam 7, which is disposed across the groove 1. combine,
Next, an electric hoist 11 is suspended from the I-beam 7 in a movable manner within the groove 1, and then a manual winch 10 is attached to the lower portions of the front left and right columns 9, and one end of the steel cable 10a is attached to the lower portion of the rear column 9. To be tied up. Next, the other end of each steel cable 10a is wound around the manual winch 10 to gradually raise the prop 9 which has fallen down, and the distance between the front and rear props 9 is narrowed. When the I-beam 7 reaches the required level, the manual winch 10 stops winding.

かようにして組立てたポータブルクレーン6
は、支柱3を建込む位置まで鋼矢板25のレール
上を走行移動して停止し、ここで電動ホイスト1
1の操作ボタン11aを操作して電動ホイスト1
1を溝1の外側方に移動し、ここに搬入定置され
たサポートジヤツキ4にて連結せる相対向する2
本の支柱3を予め電動ホイスト11のフツク11
bに取付けた支柱吊上げ金具23′にて吊上げて
走行移動し、溝1の内側壁の所定位置に建込む。
次に電動ホイスト11のフツク11bから支柱吊
上げ金具23′を取外し、土留板吊上げ金具23
を取付けて再び電動ホイスト11を操作し、土留
板吊上げ金具23の2本の突起23b付ロツド2
3cを溝1の外側方に搬入定置された土留板5の
上縁の透孔5aに挿入係止して吊上げ、その一側
端のフランジを先に建込んだ一方の支柱3の一側
面の案内溝2に嵌合する。同様にして土留板5を
吊上げて他方の支柱3の一側面の案内溝2に土留
板5の一側端を嵌合する。次いでサポートジヤツ
キ4にて連結せる次の相対向する支柱3を電動ホ
イスト11にて吊上げ、各支柱3の他側面の案内
溝2を土留板5の他側端に嵌合して、該支柱3を
建込む。
Portable crane 6 assembled in this way
The electric hoist 1 moves on the rail of the steel sheet pile 25 until it reaches the position where the support 3 is to be erected, and then stops.
1 by operating the operation button 11a of the electric hoist 1.
1 is moved to the outside of the groove 1, and the opposing 2 is connected by a support jack 4 that is brought in and placed here.
The book support 3 is attached to the hook 11 of the electric hoist 11 in advance.
It is hoisted up by the prop lifting fitting 23' attached to b and moved, and is erected at a predetermined position on the inner wall of the groove 1.
Next, remove the column lifting fitting 23' from the hook 11b of the electric hoist 11, and remove the earth retaining plate lifting fitting 23'.
, and operate the electric hoist 11 again to remove the rod 2 with the two protrusions 23b of the retaining plate lifting fitting 23.
3c is inserted into the through hole 5a at the upper edge of the earth retaining plate 5 which has been carried in and placed on the outside of the groove 1, and is lifted up. Fits into the guide groove 2. Similarly, the retaining plate 5 is lifted up and one end of the retaining plate 5 is fitted into the guide groove 2 on one side of the other support column 3. Next, the next opposite column 3 to be connected by the support jack 4 is lifted up by the electric hoist 11, and the guide groove 2 on the other side of each column 3 is fitted into the other end of the retaining plate 5, and the column is Build 3.

以後この組立てられた土留構体を溝1を掘削す
るのに合せて土中に圧入し、支柱3の案内溝2間
に土留板5を嵌合して上方に延長し、更に長手方
向への溝掘削に伴いポータブルクレーン6を鋼矢
板25のレール上を走行移動しながら電動ホイス
ト11にて支柱3、土留板5を上記手順にて順次
建込んで土留構体を組立接続していく。
Thereafter, this assembled earth retaining structure is press-fitted into the soil at the same time as the groove 1 is excavated, and the earth retaining plate 5 is fitted between the guide grooves 2 of the pillars 3 to extend it upward, and the groove is further extended in the longitudinal direction. While excavating, the portable crane 6 is moved on the rails of the steel sheet piles 25, and the electric hoists 11 are used to erect the columns 3 and retaining plates 5 one after another according to the above procedure to assemble and connect the retaining structures.

然して掘削溝1に第4図に示す如く下水管26
を布設し、溝1内に土砂27を埋戻した後、支柱
3や土留板5を引抜く際には、電動ホイスト11
では土圧抵抗により引抜けないので、現場に分解
して搬入した本考案による土留構体の建込・引抜
装置に於ける引抜き台車12を組立てる。即ち、
ポータブルクレーン6の後方にて各鋼矢板25の
レール上に、前後端に車輪13を有する台枠14
を配し、この両台枠14上の支柱15間に梁16
を張架し、所要のピン穴16aを支柱15のピン
穴(図示省略)に合せてピン15aを挿通して位
置決めの上、押え板17を介してハンドルナツト
18にて締付固定する。次に梁16上の所要位置
に支点柱19を配し、押え板17を介してハンド
ルナツト18にて締付固定する。次いで支点柱1
9の上端に引抜き挺子20の一端を旋回可能に支
持し且つ上下方向に回転可能に支持して支点Aと
なし、他端の吊索22を電動ホイスト11のフツ
ク11bに吊つて引抜き挺子の他端を力点Bとな
し、支点A寄りの中間下側に土留板吊上げ金具2
3を吊垂して作用点Cとなす。
However, a sewer pipe 26 is installed in the excavated trench 1 as shown in FIG.
After laying the soil and backfilling the trench 1 with earth and sand 27, when pulling out the pillars 3 and retaining plates 5, use the electric hoist 11.
Since it cannot be pulled out due to earth pressure resistance, the pull-out cart 12 of the earth retaining structure erecting and extracting device according to the present invention, which has been disassembled and brought to the site, is assembled. That is,
An underframe 14 having wheels 13 at the front and rear ends is placed on the rail of each steel sheet pile 25 at the rear of the portable crane 6.
A beam 16 is placed between the supports 15 on both underframes 14.
is stretched, the required pin holes 16a are aligned with the pin holes (not shown) in the support column 15, the pins 15a are inserted and positioned, and the handle nuts 18 are tightened and fixed via the holding plate 17. Next, a fulcrum column 19 is placed at a required position on the beam 16, and is tightened and fixed with a handle nut 18 via a presser plate 17. Next, fulcrum pillar 1
One end of the extraction lever 20 is rotatably supported at the upper end of 9 and rotatably supported in the vertical direction to serve as a fulcrum A, and the suspension rope 22 at the other end is suspended from the hook 11b of the electric hoist 11 to form the extraction lever. The other end is the point of effort B, and the earth retaining plate lifting fitting 2 is placed on the middle lower side near the fulcrum A.
3 is suspended to form the point of action C.

かようにして組立てた引抜き台車12と先に組
立てたポータブルクレーン6とより成る本考案に
よる土留構体の建込・引抜装置により土留板5を
引抜くには、先ず土砂27を埋戻したた位置に本
装置を走行移動して停止し、次に土留板吊上げ金
具23の2本の突起23b付ロツド23cを土砂
27に埋め込まれている土留板5の上縁の透孔5
aに挿入係止する。次いで第5図に示す如く電動
ホイスト11の操作ボタン11aを操作して、フ
ツク11bに吊つた吊索22を介して引抜き挺子
20の他端の力点Bを引上げ、引抜き挺子20の
中間下側に於ける作用点Cの土留板吊上げ金具2
3に結合した土留板5を土中より引抜く。数10セ
ンチ引抜かれたならば、引抜き挺子20を取外し
て引抜き台車13を後方に移動し、ポータブルク
レーン13を所要の位置まで後退させると共に電
動ホイスト11を土留板5の上方に移動し、フツ
ク11bに土留板吊上げ金具23を掛けて、動動
ホイスト11により土留板5を土中より完全に引
抜く。
In order to pull out the earth retaining plate 5 using the earth retaining structure erection/extracting device according to the present invention, which is comprised of the pull-out cart 12 assembled in this way and the portable crane 6 assembled previously, the earth retaining plate 5 is to be pulled out at the position where earth and sand 27 has been backfilled. Then, the device is moved and stopped, and then the rod 23c with the two protrusions 23b of the retaining plate lifting fitting 23 is inserted into the through hole 5 at the upper edge of the retaining plate 5 embedded in the earth and sand 27.
Insert and lock into a. Next, as shown in FIG. 5, the operation button 11a of the electric hoist 11 is operated to pull up the force point B at the other end of the extraction lever 20 via the hanging rope 22 suspended from the hook 11b, and Earth retaining plate lifting fitting 2 at the point of action C on the side
The earth retaining board 5 connected to 3 is pulled out from the soil. Once it has been pulled out several tens of centimeters, remove the pull-out lever 20, move the pull-out trolley 13 backwards, move the portable crane 13 back to the required position, and move the electric hoist 11 above the retaining plate 5 to remove the hook. 11b with the retaining plate lifting fitting 23, and the movable hoist 11 completely pulls out the retaining plate 5 from the soil.

また支柱3を引抜くには、引抜き挺子20の中
間下側の土留板吊上げ金具23を取外して第2図
に示される支柱吊上げ金具23′を取付ける。そ
してポータブルクレーン6及び引抜き台車12を
所要の位置まで走行移動して停止し、引抜き挺子
20の支点柱19のハンドルナツト18を緩めて
梁16上を摺動させ、所要位置でハンドルナツト
18の締付けにより固定する。次いで第6図に示
す如く支柱吊上げ金具23′の二又の金具23d
を相対向する支柱3の正面のサポートジヤツキ連
結用部材3aの上端にピン結合する。然る後電動
ホイスト11の操作ボタン11aを操作して、フ
ツク11bに吊索22にて吊つた引抜き挺子20
の他端の力点Bを引上げ、引抜き挺子20の中間
下側に於ける作用点Cの支柱吊上げ金具23′に
結合した相対向する支柱3をサポートジヤツキ4
にて連結されたままの状態で土中より引抜く。数
10センチ引抜かれたならば、引抜き挺子20を取
外して、引抜き台車13を後方に移動し、ポータ
ブルクレーン6を所要の位置まで後退させて電動
ホイスト11のフツク11bに支柱吊上げ金具2
3′を掛けて、電動ホイスト11により相対向す
る支柱3を土中より完全に引抜く。
In order to pull out the support column 3, the earth retaining board lifting fitting 23 located at the middle lower side of the pull-out lever 20 is removed and a support lifting fitting 23' shown in FIG. 2 is attached. Then, the portable crane 6 and the pull-out cart 12 are moved to a required position and stopped, the handle nut 18 of the fulcrum column 19 of the pull-out screw 20 is loosened, and the handle nut 18 is slid on the beam 16, and the handle nut 18 is tightened at the required position. Secure by tightening. Next, as shown in FIG.
is pin-coupled to the upper end of the support jack connecting member 3a on the front side of the opposing support column 3. After that, the operation button 11a of the electric hoist 11 is operated to remove the extraction lever 20 suspended from the hook 11b by the hanging rope 22.
The force point B at the other end is pulled up, and the support jack 4 is attached to the opposing column 3 connected to the column lifting fitting 23' at the point of application C at the middle lower side of the pull-out lever 20.
Pull it out of the soil while still connected. number
Once it has been pulled out by 10 cm, remove the pull-out lever 20, move the pull-out trolley 13 backward, move the portable crane 6 back to the required position, and attach the support bracket 2 to the hook 11b of the electric hoist 11.
3', and the electric hoist 11 completely pulls out the opposing support columns 3 from the soil.

以上の説明で判るように本考案の掘削溝に於け
る土留構体の建込・引抜装置は、分解して現場に
搬入し、また現場で掘削溝の溝幅に合せて簡単組
立てることができるのであるから、重機が入れな
いような狭い現場でも掘削溝への土留構体建込、
下水管布設後の埋戻し土砂からの引抜きを簡単に
行なうことができる。
As can be seen from the above explanation, the device for erecting and pulling out earth retaining structures in excavated trenches according to the present invention can be disassembled and transported to the site, and can be easily assembled on site to match the width of the excavated trench. Because of this, it is possible to erect earth retaining structures in excavated trenches even on narrow sites where heavy machinery cannot enter.
It can be easily pulled out from the backfilled earth and sand after installing the sewer pipe.

また本考案の土留構体の建込・引抜装置は、土
中から土留構体の支柱や土留板を引抜く際、左右
前後に移動できる引抜き挺子を利用して電動ホイ
ストにて引抜くのであるから、土圧抵抗が大きく
てクレーン車でも容易に引抜けないような場合で
も簡単に引抜くことができる。
In addition, the earth retaining structure erection/extracting device of the present invention uses an electric hoist to pull out the earth retaining structure columns and retaining plates from the soil using a pull-out lever that can move left, right, front, and back. , it can be easily pulled out even in cases where the earth pressure resistance is so great that even a crane truck cannot pull it out easily.

さらに本考案の土留構体の建込・引抜装置に於
ける引抜き台車は、クレーン車が使用できる現場
でも土圧抵抗が大きくて土留構体の支柱や土留板
を容易に引抜けない場合に、クレーン車と一諸に
使用することにより簡単に支柱や土留板を引抜く
ことができる。
Furthermore, the pull-out trolley in the earth retaining structure erection/removal device of the present invention can be used even at sites where crane trucks can be used, when the earth pressure resistance is large and the supports and retaining plates of the earth retaining structure cannot be easily pulled out. By using both together, you can easily pull out the pillars and retaining plates.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は溝掘削用土留構体による土留工法を示
す斜視図、第2図a,b,cは本考案による土留
構体の建込・引抜装置の正面図、側面図、平面
図、第3図は掘削溝を跨いて組立てた本考案によ
る土留構体の建込・引抜装置に於けるポータブル
クレーンの斜視図、第4図はそのポータブルクレ
ーンの後方で引抜き台車を組立ててポータブルク
レーンの電動ウインチに連繋した本考案による土
留構体の建込・引抜装置の斜視図、第5図は本装
置により土留板を引抜く次態を示す正面図、第6
図は本装置により支柱を引抜く状態を示す正面図
である。 1……掘削溝、2……支柱の案内溝、3……支
柱、3a……サポートジヤツキ連結用部材、4…
…サポートジヤツキ、5……土留板、5a……透
孔、6……ポータブルクレーン、7……I形鋼、
8……車輪、9……支柱、10……手動ウイン
チ、10a……鋼索、11……電動ホイスト、1
1a……電動ホイストの操作ボタン、11b……
フツク、12……引抜き台車、13……車輪、1
4……台枠、15……支柱、16……梁、17…
…押え板、18……ハンドルナツト、19……支
点柱、20……引抜き挺子、22……吊索、23
……土留板吊上げ金具、23′……支柱吊上げ金
具、23a……吊索、23b……突起、23c…
…ロツド、23d……二又の金具、25……鋼矢
板、26……下水管、27……土砂、A……支
点、B……力点、C……作用点。
Fig. 1 is a perspective view showing the earth retaining method using an earth retaining structure for trench excavation; Fig. 2 a, b, and c are front views, side views, and plan views of the earth retaining structure erecting/extracting device according to the present invention; Fig. 3; Figure 4 is a perspective view of a portable crane in the erecting/extracting device for an earth retaining structure according to the present invention, which is assembled across an excavation trench, and Figure 4 shows a pull-out cart assembled behind the portable crane and connected to the electric winch of the portable crane. FIG. 5 is a perspective view of the device for erecting and pulling out earth retaining structures according to the present invention; FIG.
The figure is a front view showing a state in which the support column is pulled out by this device. 1... Excavation groove, 2... Support guide groove, 3... Support column, 3a... Support jack connection member, 4...
...Support jack, 5...Earth retaining plate, 5a...Through hole, 6...Portable crane, 7...I-shaped steel,
8...Wheel, 9...Strut, 10...Manual winch, 10a...Steel cable, 11...Electric hoist, 1
1a...Electric hoist operation button, 11b...
Hook, 12... Pull-out trolley, 13... Wheels, 1
4... Underframe, 15... Support, 16... Beam, 17...
... Pressing plate, 18 ... Handle nut, 19 ... Fulcrum column, 20 ... Pulling lever, 22 ... Suspension rope, 23
...Earth retaining board lifting metal fitting, 23'... Prop lifting metal fitting, 23a... Suspension rope, 23b... Protrusion, 23c...
...rod, 23d...two-pronged metal fitting, 25...steel sheet pile, 26...sewer pipe, 27...earth and sand, A...fulcrum, B...point of force, C...point of action.

Claims (1)

【実用新案登録請求の範囲】 前後左右の4本の車輪付支柱の上端がI形鋼の
左右両端部上縁に着脱可能に結合され、I形鋼に
は電動ホイストが走行可能に吊垂され、左右の前
後いずれか一方の支柱の下部には手動ウインチが
着脱可能に取付けられ、他方の支柱の下部には鋼
索の一端が着脱可能に取付けられて、その他端が
手動ウインチに巻取られたポータブルクレーン
と、 前後端に車輪を設けた左右一対の台枠上に夫々
支柱が立設され、その左右の支柱間に梁が着脱可
能に且つ摺動可能に張架固定され、梁上には支点
柱が摺動可能に取付けられて締付固定され、支点
柱の上端には引抜き挺子の一端が着脱可能に枢支
され、引抜き挺子の他端は着脱可能に電動ホイス
トに吊垂され、引抜き挺子の一端寄りの中間下側
には所要の吊上げ金具が着脱可能に吊垂された引
抜き台車と、 より成る掘削溝に於ける土留構体の建込・引抜装
置。
[Scope of Claim for Utility Model Registration] The upper ends of four wheeled columns on the front, rear, left and right sides are removably connected to the upper edges of both left and right ends of the I-beam, and an electric hoist is suspended from the I-beam so that it can run. A manual winch was removably attached to the bottom of one of the left and right front and rear columns, one end of the steel cable was detachably attached to the bottom of the other column, and the other end was wound around the manual winch. A portable crane and supports are erected on a pair of left and right underframes with wheels at the front and rear ends, and a beam is removably and slidably stretched between the left and right supports. A fulcrum column is slidably attached and tightened, one end of a pull-out screw is removably pivoted to the upper end of the fulcrum column, and the other end of the pull-out screw is detachably suspended from an electric hoist. A device for erecting and extracting an earth retaining structure in an excavated trench, consisting of a pull-out cart with the necessary lifting fittings removably suspended from the intermediate lower side near one end of the pull-out screw.
JP13899380U 1980-09-30 1980-09-30 Expired JPS6120118Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13899380U JPS6120118Y2 (en) 1980-09-30 1980-09-30

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13899380U JPS6120118Y2 (en) 1980-09-30 1980-09-30

Publications (2)

Publication Number Publication Date
JPS5760938U JPS5760938U (en) 1982-04-10
JPS6120118Y2 true JPS6120118Y2 (en) 1986-06-17

Family

ID=29498982

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13899380U Expired JPS6120118Y2 (en) 1980-09-30 1980-09-30

Country Status (1)

Country Link
JP (1) JPS6120118Y2 (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62276792A (en) * 1986-05-26 1987-12-01 松下電工株式会社 Discharge lamp lighter
JPS62276794A (en) * 1986-05-26 1987-12-01 松下電工株式会社 Discharge lamp lighter
JPH0439957Y2 (en) * 1986-08-06 1992-09-18
JPH0439956Y2 (en) * 1986-08-06 1992-09-18
JPH0724206Y2 (en) * 1988-06-27 1995-06-05 三幸商事株式会社 Bolt tightening device
JPH0572373U (en) * 1992-03-13 1993-10-05 関東自動車工業株式会社 Engine drive plate rotating device
JPH1044052A (en) * 1996-08-01 1998-02-17 Maeda Kinzoku Kogyo Kk Tightening machine
JP2003221184A (en) * 2002-01-31 2003-08-05 Haneda Concrete Industrial Co Ltd Block setting base
JP2018118649A (en) * 2017-01-26 2018-08-02 大成建設株式会社 Transporting device, transporting system and transporting method of long member

Also Published As

Publication number Publication date
JPS5760938U (en) 1982-04-10

Similar Documents

Publication Publication Date Title
JPS6120118Y2 (en)
CN108203981B (en) System and method for installing steel support in cover and excavation method
US3362168A (en) Trench wall retainer
CN107794945A (en) A kind of removable assembled template peace tears operating system and its construction method open
CN207469303U (en) A kind of removable assembled template peace tears operating system open
JPS62288269A (en) Method for extending underground stair of building
CN206457831U (en) The overall punching block suspension device of pipe trench with water-proof function
JP2966765B2 (en) Underground construction members burying method
JP2006070437A (en) Earth retaining method and device for excavated ditch
JPS6027157Y2 (en) Equipment for pulling out earth retaining structures, etc. in excavated trenches
JPH0310198Y2 (en)
CN212001163U (en) Combined temporary groove side slope supporting device
JP2000257069A (en) Earth retaining and earth retaining construction method
CN117003118A (en) Pipelined protection system and method for controlling deformation of existing pipeline
JP2000351600A (en) Traction type gate shape jack
JPH07300856A (en) Earth retaining device
JP2583830B2 (en) Construction method of concrete deep foundation pile
JPH08109634A (en) Earth retaining method and earth retaining timbering device
JPH0529248Y2 (en)
JP3054071B2 (en) Method and apparatus for erecting steel for underground continuous wall
KR19990023523A (en) File drawing machine
JP3252365B2 (en) Pillar structure of sheet pile type support for excavation trench
JPH06336723A (en) Earth retaining device
JPS5845323Y2 (en) Tensioning device for earth retaining sheet piles for trench excavation
CN115787660A (en) Modularized detachable elevator foundation pit support and construction method thereof