JPH0223639Y2 - - Google Patents

Info

Publication number
JPH0223639Y2
JPH0223639Y2 JP15282784U JP15282784U JPH0223639Y2 JP H0223639 Y2 JPH0223639 Y2 JP H0223639Y2 JP 15282784 U JP15282784 U JP 15282784U JP 15282784 U JP15282784 U JP 15282784U JP H0223639 Y2 JPH0223639 Y2 JP H0223639Y2
Authority
JP
Japan
Prior art keywords
strut
cross
earth retaining
view
trench
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP15282784U
Other languages
Japanese (ja)
Other versions
JPS6168142U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP15282784U priority Critical patent/JPH0223639Y2/ja
Publication of JPS6168142U publication Critical patent/JPS6168142U/ja
Application granted granted Critical
Publication of JPH0223639Y2 publication Critical patent/JPH0223639Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【考案の詳細な説明】 〔産業上の利用分野〕 本考案は、地下埋設管の布設工事等において、
掘削溝の土留を行なう装置に関するものである。
[Detailed description of the invention] [Industrial application field] The present invention can be used in underground pipe installation work, etc.
This invention relates to a device for retaining earth in an excavated trench.

〔従来技術〕[Prior art]

一般に、地下埋設管を布設するには、溝を掘削
してその中に管を埋設するが、布設工事中は安全
性を確保するため掘削溝の土留を施す必要があ
る。
Generally, in order to install underground pipes, a trench is excavated and the pipe is buried in the trench, but during the installation work it is necessary to provide earth retaining for the excavated trench to ensure safety.

従来、かかる掘削溝の土留を行なうには、第1
2図ないし第13図に示すように、相対して建て
込んだ矢板3,3ごとに切梁4を掛け渡してこれ
のみで土留する方式と、第14図ないし第15図
に示すように、矢板3,3を建て込んだ後、これ
に腹起し5,5をかませ、この腹起し5,5を切
梁4で固定する方式とがある。
Conventionally, in order to retain earth in such excavated trenches, the first
As shown in Figures 2 to 13, there is a method in which struts 4 are strung across each of the sheet piles 3 and 3 that are erected facing each other, and earth retaining is carried out using this alone, and as shown in Figures 14 and 15, After the sheet piles 3, 3 have been erected, there is a method in which the uprights 5, 5 are fitted over them, and the uprights 5, 5 are fixed with struts 4.

〔考案が解決しようとする問題点〕[Problem that the invention attempts to solve]

しかしながら、前記従来技術のうち、前者は設
置が簡単で、腹起しを使用せずに矢板毎に土留す
るため、掘削溝に既設管が出現したり、また、掘
削溝が曲がつていてもきめ細かに対処できる等の
利点がある反面、部分的な土留になるために土留
の剛性が弱く、軟弱地盤や深い掘削溝には不向き
である。一方、後者は腹起しを使用するため土留
の剛性が強く、軟弱地盤や深い掘削溝にも対応で
きる等の利点がある反面、相当な長さを有する腹
起しを取扱うこととなつて設置作業が面倒であ
り、掘削溝が曲がつているような所では工事が困
難となるという難点があつた。
However, among the above-mentioned conventional techniques, the former is easy to install and retains the earth for each sheet pile without using uprights, so existing pipes may appear in the excavation groove or the excavation groove may be curved. Although it has the advantage of being able to deal with fine details, it is not suitable for soft ground or deep excavated trenches because it is a partial earth retainer and has low rigidity. On the other hand, the latter has the advantage of having strong earth retaining rigidity and being able to cope with soft ground and deep excavated trenches because it uses a raised bed. The problem was that the work was troublesome, and construction was difficult in places where the excavation trench was curved.

本考案の目的は、前記従来例の不都合を解決
し、地下埋設管の布設工事において、従来方式に
よる腹起しがない土留工法と、腹起しがある土留
工法のそれぞれの長所を採り入れ、軟弱地盤や曲
線の掘削溝等を含む各種施工条件にきめ細かに対
処でき、しかも掘削溝を安全で、かつ容易に土留
施工できる土留装置を提供することにある。
The purpose of the present invention is to solve the above-mentioned disadvantages of the conventional method, and to take advantage of the advantages of the conventional earth retaining method without raising and the earth retaining method with raising, in the installation work of underground pipes. To provide an earth retaining device that can finely deal with various construction conditions including curved excavated trenches, etc., and can safely and easily perform earth retaining work on excavated trenches.

〔問題点を解決するための手段〕[Means for solving problems]

本考案の土留装置は、前記目的を達成するた
め、所定の長さを有する縦材に適宜長さの短尺な
腹起しを直交させて取付けて十字型枠を形成し、
該腹起しの上面または下面に切梁用ブラケツトを
固着し、該ブラケツトを介して腹起し間に切梁を
着脱自在に取付けることを要旨とするものであ
る。
In order to achieve the above-mentioned object, the earth retaining device of the present invention is provided by forming a cross-shaped frame by attaching short ribs of an appropriate length orthogonally to a vertical member having a predetermined length;
The gist of the present invention is to fix a strut bracket to the upper or lower surface of the rib, and to detachably attach the strut between the ribs via the bracket.

〔作用〕[Effect]

本考案によれば、予め十字に組まれた切梁ブラ
ケツト付きの型枠を用いて矢板と切梁を簡単にセ
ツトすることができるものである。
According to the present invention, sheet piles and struts can be easily set using a formwork with strut brackets assembled in a cross shape in advance.

〔実施例〕〔Example〕

以下、図面について本考案の実施例を詳細に説
明する。
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.

第1図は本考案の土留装置の実施例を示す正面
図、第2図は同上側面図、第3図は同上平面図
で、図中10は十字型枠であり、この十字型枠1
0は〓字型鋼またはコ字型鋼で、所定の長さを有
する縦材11に、角パイプ鋼などで成形され1.0
〜1.5mの長さに切断された横材である短尺な腹
起し12を直交させて溶接又はボルト止め等で取
付けたものである。該十字型枠10の前記水平な
腹起し12の上面または下面に、切梁用ブラケツ
ト13を溶接等で予め固着しておく。縦材11の
上端部には、仮組みされた十字型枠10を掘削溝
1内に建て込んだり、引き抜いたりする際の取扱
い性を良くするために把手16を溶接等により固
着しておくとよい。図中、14は切梁で、これは
端部をブラケツト13に結合できるものであり、
また固定用の油圧ジヤキ(図示せず)なども取付
け可能なものである。
Fig. 1 is a front view showing an embodiment of the earth retaining device of the present invention, Fig. 2 is a side view of the same, and Fig. 3 is a plan view of the same.
0 is 〓-shaped steel or U-shaped steel, which is formed from square pipe steel or the like into a vertical member 11 having a predetermined length.
Short ribs 12, which are cross members cut to a length of ~1.5 m, are orthogonally arranged and attached by welding or bolting. A strut bracket 13 is fixed in advance to the upper or lower surface of the horizontal upright 12 of the cross-shaped frame 10 by welding or the like. A handle 16 is fixed to the upper end of the vertical member 11 by welding or the like to improve handling when the temporarily assembled cross-shaped frame 10 is inserted into or pulled out of the excavation groove 1. good. In the figure, 14 is a strut whose end can be connected to the bracket 13.
It is also possible to attach a fixing hydraulic jack (not shown).

次に本考案の装置を用いた土留め工法について
説明すると、掘削溝1の土留を施工する場合は、
まず予め地上で縦材11と腹起し12を十字型に
仮組みして十字型枠10を形成し、この十字型枠
10を左右一対で1組とし、該一対の十字型枠1
0,10の切梁用ブラケツト13と13の間に切
梁14を取付ける。このとき、十字型枠10,1
0間の腹起し12間に掛け渡される切梁14の長
さは、掘削溝1内に円滑に建て込まれるような長
さに調整しておく。
Next, to explain the earth retaining method using the device of the present invention, when constructing earth retaining for excavated trench 1,
First, a cross-shaped frame 10 is formed by temporarily assembling the vertical members 11 and the uprights 12 in a cross shape on the ground, and a pair of left and right cross-shaped frames 10 is formed, and the pair of cross-shaped frames 1
Install the strut 14 between the brackets 13 and 13 for struts 0 and 10. At this time, the cross-shaped frame 10,1
The length of the strut 14 that spans between the 0-space uprights 12 is adjusted to such a length that it can be built smoothly into the excavated trench 1.

つぎに、縦材11の把手16を持つて切梁14
で結合された十字型枠10,10を掘削溝1内に
建て込み、矢板15を腹起し12の背面に建て込
む。その際、地盤の状態に応じて矢板15の間隔
は第6図に示すように間隔をあけたり、または第
7図に示すように密接させて選定する。つづいて
第8図に示すように切梁14のジヤツキを伸ばし
て矢板15が地山に密着するようにする。
Next, hold the handle 16 of the vertical member 11 and hold the strut 14.
The cross-shaped frames 10, 10 connected together are built into the excavation trench 1, and the sheet piles 15 are built into the back of the upright 12. At this time, depending on the condition of the ground, the sheet piles 15 are selected to be spaced apart as shown in FIG. 6 or closely spaced as shown in FIG. 7. Next, as shown in FIG. 8, the struts 14 are straightened so that the sheet piles 15 come into close contact with the ground.

この際、掘削溝1の地盤が特に軟弱な場合や比
較的長期間掘り置きの必要がある場合は、第9図
に示すように横材である腹起し12の隣接するも
のを相互に連結することも可能であり、かかる腹
起し12の連結は第10図、第11図に示すよう
に腹起し12の端面に溶着したフランジ19を突
き合わせてボルト締めしたり、腹起し12の一端
を膨出したソケツト12aに形成し、このソケツ
ト12aに他方の端部を挿入するようにしたソケ
ツト式接合等が適用される。
At this time, if the ground of the excavation trench 1 is particularly soft or if it is necessary to leave the excavation for a relatively long period of time, as shown in FIG. As shown in FIGS. 10 and 11, the flange 19 welded to the end surface of the tuck 12 can be butted together and bolted, or the tuck 12 can be connected by bolts. A socket type joint or the like is applied in which one end is formed into a bulged socket 12a and the other end is inserted into this socket 12a.

なお、上記腹起し12は縦材11に対して前記
のごとく溶接等により固定してもよいが、一般的
には溝1の掘削深度に合わせて腹起し12の高さ
を調節したり、必要に応じて腹起し12と切梁1
4とは複数段に設置できるよう、第2実施例とし
て、第4図ないし第5図に示すように腹起し12
は縦材11に対して取付金具17、ボトル18、
あるいはコツタ等を用いて上下方向にスライド可
能に装着してもよい。この場合は、掘削溝の深度
に合せて腹起し12の上下位置が設定され、腹起
し12に一体に固着された切梁用ブラケツト13
を介して切梁14による張り位置が決る。
Incidentally, the above-mentioned riser 12 may be fixed to the vertical member 11 by welding or the like as described above, but generally the height of the riser 12 is adjusted according to the excavation depth of the groove 1. , if necessary, stand up 12 and cross beam 1
4 is a second embodiment of the invention, so that it can be installed in multiple stages, as shown in Figures 4 and 5.
is a mounting bracket 17, a bottle 18,
Alternatively, it may be attached so as to be slidable in the vertical direction using a kotsuta or the like. In this case, the upper and lower positions of the riser 12 are set according to the depth of the excavation groove, and the strut bracket 13 is integrally fixed to the riser 12.
The tension position by the strut 14 is determined through the.

また、切梁14は、その都度所定の長さに切断
して使用される木材等を使用することもできる
が、通常のネジ式、または油圧式のジヤツキ等を
使用する方が取扱いが簡単で、確実に取付けられ
る。
Furthermore, the strut 14 can be made of wood or the like, which is cut to a predetermined length each time, but it is easier to handle if a regular screw type or hydraulic jack is used. , reliably mounted.

さらに、十字型枠10は縦材11を幅広に形成
すれば、矢板と兼用できるので地盤のよい掘削溝
ではその分だけ矢板15の建て込み間隔を広くと
ることができる。
Furthermore, if the vertical members 11 of the cross-shaped frame 10 are made wide, they can also be used as sheet piles, so that the pitch between the sheet piles 15 can be increased correspondingly in excavated trenches with good ground.

なお、他の使用法として十字型枠10のみを先
に掘削溝1内に建込み、該溝1内で切梁14をセ
ツトすることも可能である。
In addition, as another method of use, it is also possible to first erect only the cross-shaped frame 10 into the excavated trench 1, and then set the struts 14 within the trench 1.

〔考案の効果〕[Effect of idea]

以上述べたように本考案の土留装置は、構造が
簡単で軽量であるから、取扱いが容易で、作業人
員の削減と作業工程数の低減を図ることができる
ものである。
As described above, the earth retaining device of the present invention has a simple structure and is lightweight, so it is easy to handle, and it is possible to reduce the number of workers and the number of work steps.

また、腹起しの長さを短く形成できるので、曲
がりのある掘削溝にも十分に適用でき、さらに、
縦材に腹起しが予め十字型に固定され、この腹起
しに切梁を取付けるブラケツトが固着されている
ので、地上での組上げ部分が多く、作業員が溝内
に入ることを少なくして工事が施工できる等、軟
弱地盤でも安全に作業ができるものである。
In addition, since the length of the upright can be shortened, it can be fully applied to curved excavation trenches.
Since a cross-shaped upright is fixed to the vertical members in advance, and the bracket for attaching the strut is fixed to the upright, much of the assembly is done on the ground, reducing the chance of workers entering the trench. The construction work can be carried out safely even on soft ground.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本考案の土留装置の実施例を示す正面
図、第2図は同上側面図、第3図は同上平面図、
第4図は第2実施例の要部を示す側面図、第5図
は同上平面図、第6図ないし第7図は本考案によ
る土留装置の施工状態を示す正面図、第8図は第
6図の断面図、第9図は本考案による他の施工状
態を示す正面図、第10図、第11図は同上要部
の横断面図、第12図は従来の施工方法を示す縦
断側面図、第13図は同上平面図、第14図は従
来の他の施工方法を示す縦断側面図、第15図は
同上平面図である。 1……掘削溝、10……十字型枠、11……縦
材、12……腹起し、12a……ソケツト、13
……切梁用ブラケツト、14……切梁、15……
矢板、16……把手、17……取付金具、18…
…ボルト、19……フランジ。
Figure 1 is a front view showing an embodiment of the earth retaining device of the present invention, Figure 2 is a side view of the same, Figure 3 is a plan view of the same,
FIG. 4 is a side view showing the main parts of the second embodiment, FIG. 5 is a plan view of the same as above, FIGS. 6 and 7 are front views showing the construction state of the earth retaining device according to the present invention, and FIG. Fig. 6 is a sectional view, Fig. 9 is a front view showing another construction state according to the present invention, Figs. 10 and 11 are cross-sectional views of the main parts of the above, and Fig. 12 is a vertical sectional view showing the conventional construction method. 13 is a plan view of the same as above, FIG. 14 is a longitudinal side view showing another conventional construction method, and FIG. 15 is a plan view of same as above. 1... Excavation groove, 10... Cruciform frame, 11... Vertical member, 12... Ribbon, 12a... Socket, 13
...Bracket for strut beam, 14...Strut beam, 15...
Sheet pile, 16...Handle, 17...Mounting bracket, 18...
...Bolt, 19...Flange.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 所定の長さを有する縦材に適宜長さの短尺な腹
起しを直交させて取付けて十字型枠を形成し、該
腹起しの上面または下面に切梁用ブラケツトを固
着し、該ブラケツトを介して腹起し間に切梁を着
脱自在に取付けることを特徴とした土留装置。
A cross-shaped frame is formed by attaching short ribs of appropriate length orthogonally to a vertical member having a predetermined length, and a strut bracket is fixed to the upper or lower surface of the rib. An earth retaining device characterized in that a strut is removably attached between the sills via.
JP15282784U 1984-10-09 1984-10-09 Expired JPH0223639Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15282784U JPH0223639Y2 (en) 1984-10-09 1984-10-09

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15282784U JPH0223639Y2 (en) 1984-10-09 1984-10-09

Publications (2)

Publication Number Publication Date
JPS6168142U JPS6168142U (en) 1986-05-10
JPH0223639Y2 true JPH0223639Y2 (en) 1990-06-27

Family

ID=30710875

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15282784U Expired JPH0223639Y2 (en) 1984-10-09 1984-10-09

Country Status (1)

Country Link
JP (1) JPH0223639Y2 (en)

Also Published As

Publication number Publication date
JPS6168142U (en) 1986-05-10

Similar Documents

Publication Publication Date Title
JPH0223639Y2 (en)
JPH08144284A (en) Landslide protection wall timbering
JP2852173B2 (en) Seawall construction using steel sheet piles
JP3078412B2 (en) Groove excavation method and stand for temporary assembly of retaining panels
JP2966765B2 (en) Underground construction members burying method
JP3053296B2 (en) Pillar hanging jig
JPS6137689Y2 (en)
JP3049585B2 (en) Driving floor beam-to-column connection and driving floor final joining method in the driving floor advance ascending construction method
JPH0738555Y2 (en) Beam formwork support frame
JP2886376B2 (en) Anchor structure of pile head
JP3456572B2 (en) Tower and paper drain machine
JP3325156B2 (en) Soil support method and structure in excavation trench
JPS5833154Y2 (en) Basic anchor member insertion positioning device
CN211171634U (en) Novel assembled bracket bearing structure
JPH0632989Y2 (en) Work table of pile press-in / pull-out machine
JP3106302B2 (en) How to build underground structures
JPS624132Y2 (en)
JPS5911016B2 (en) Earth retaining construction method and raised structure used in the same construction method
JPH05140937A (en) Mounting of strut with underground reverse driving method
JP2649682B2 (en) Underground structure
JPH0342111Y2 (en)
JP3054071B2 (en) Method and apparatus for erecting steel for underground continuous wall
JP3567387B2 (en) How to build an underground skeleton
JPH0529248Y2 (en)
JP3682504B2 (en) Building foundations and construction methods