JPH02104866A - Lifting of heavyweight structure in case of high banking over wide area - Google Patents
Lifting of heavyweight structure in case of high banking over wide areaInfo
- Publication number
- JPH02104866A JPH02104866A JP25478488A JP25478488A JPH02104866A JP H02104866 A JPH02104866 A JP H02104866A JP 25478488 A JP25478488 A JP 25478488A JP 25478488 A JP25478488 A JP 25478488A JP H02104866 A JPH02104866 A JP H02104866A
- Authority
- JP
- Japan
- Prior art keywords
- piles
- building
- lifting
- supported
- jacks
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000000034 method Methods 0.000 claims abstract description 9
- 238000003466 welding Methods 0.000 abstract description 2
- 238000010276 construction Methods 0.000 description 5
- 239000004744 fabric Substances 0.000 description 4
- 239000002689 soil Substances 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000007596 consolidation process Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 230000006378 damage Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
Description
【発明の詳細な説明】
(産業の利用分野)
この発明は、広域高盛り土を行うべき地盤上に建てられ
ている重量物、例えば建造物を、盛り土上にそのまま扛
上する方法に関するものである。[Detailed Description of the Invention] (Field of Industrial Application) This invention relates to a method for lifting a heavy object, such as a building, which is built on the ground where wide-area high embankment is to be performed, directly onto the embankment. .
(従来の技術)
傾斜面である地山に盛り土を行って敷地を造成し、既設
の住宅等をこの盛り土上に移動することは極めて普通に
行われており、さらに近年、河岸あるいは堤防を保護し
て流れによる破壊を防止する護岸工事として、本来の堤
防に連なる広い地域に大規模な盛り土を施し、堤防の断
面を堤防内側は在来の位置で、堤防外側に向って大幅に
拡げる旧堤増戊を行うとともに、在来の堤防に沿って低
地域に設けられていた建造物や道路などをそのまま拡張
された堤防上の対応位置に復元するスーパー堤防工法と
呼ばれる工法が開発されている。(Conventional technology) It is extremely common to create a site by mounding earth on a sloping surface and moving existing houses, etc. onto this mound. As part of the bank protection work to prevent destruction by currents, a large-scale embankment was carried out in a wide area connected to the original levee, and the cross section of the levee was widened from the original position on the inside of the levee to the outside of the old levee. In addition to expanding the area, a construction method called the super levee construction method has been developed, in which buildings and roads that were built in low-lying areas along the existing levee are restored to their corresponding positions on the expanded levee.
(発明が解決しようとする課題)
この場合、盛り土を施すべき地盤上の重量物、例えば建
造物は一旦、他の場所に移動する必要があり、次いで盛
り土上に戻すに当っても、盛り土の高さが大である場合
は容易でないから、実際には再建築が行われ、その間は
居住できないという大きな不利があった。(Problem to be solved by the invention) In this case, heavy objects on the ground to be filled with soil, such as buildings, need to be moved to another location, and then when returning to the top of the soil, it is necessary to If the height was large, it would not be easy, so in reality, the building would have to be rebuilt, which was a big disadvantage as it would be impossible to live in it during that time.
(課題を解決するための手段)
これに対して、この発明は盛り土すべき現在の地盤上の
建造物を、その基礎下面にジヤツキを介設して一定高さ
上昇するとともに、予め建造物の荷重を地盤に伝達する
ため地盤内に打ち込まれたくいの上端に、短筒状の接続
くいを継ぎ足して基礎下面を支持させ、次いで継ぎ足し
た接続くい間を充填しながら所定範囲にわたって盛り土
を行い、。(Means for Solving the Problem) In contrast, the present invention raises a building on the current ground that is to be filled with soil to a certain height by interposing a jack on the lower surface of the foundation, and In order to transfer the load to the ground, short cylindrical connecting piles are added to the upper ends of the piles driven into the ground to support the lower surface of the foundation, and then, filling in the gaps between the added connecting piles and embanking over a predetermined area. .
これを繰り返して所要高さの盛り土ならびに建造物の扛
上を完了するものである。This process is repeated to complete the embankment to the required height and the raising of the structure.
(発明の実施例)
この発明の方法を実施する順序を図面について説明する
と、第1図において1は、現在の地盤上の建造物を現わ
し、この建造物1はその布基礎2を、予め先端を地盤中
の硬い地層迄打ちこまれたくい3の上端に載架支持され
ている。(Embodiments of the Invention) The order in which the method of the present invention is carried out will be explained with reference to the drawings. In Fig. 1, 1 represents a building on the current ground, and this building 1 has its cloth foundation 2 built in advance. It is mounted and supported on the upper end of a pile 3 whose tip is driven into the hard stratum of the ground.
第2図は、上記建造物10床下を掘って、各くい30間
の適切な部分にジヤツキ取付穴を形成し、これらジヤツ
キ取付穴に設けた油圧ジヤツキ4を介して布基礎2をそ
のまま例えば約1.5メートル扛上せしめ、かつその状
態で各くい3の頂部と布基礎2下面との間に形成された
空間に短筒状の接続くい5を介設し、くい3の頂部に接
続しつぎ足した状態を示す。なお、この実施例において
、くい3および接続くい5は鋼管ぐいを用い、相互の接
続は溶接により行うものとする。FIG. 2 shows that the floor of the building 10 is excavated, jack mounting holes are formed at appropriate locations between the piles 30, and the cloth foundation 2 is installed as it is, for example, by using hydraulic jacks 4 provided in these jack mounting holes. 1.5 meters, and in that state, a short cylindrical connecting peg 5 is interposed in the space formed between the top of each peg 3 and the lower surface of the foundation 2, and connected to the top of the peg 3. Shows the state of addition. In this embodiment, steel pipe piles are used for the pegs 3 and the connecting pegs 5, and the mutual connection is performed by welding.
第3図は上記油圧ジヤツキ4を取りはず し、現在の地
殻」−に盛り土6を例えば約1メートルの高さに行った
状態を示す。Figure 3 shows the state in which the hydraulic jack 4 has been removed and a mound 6 has been built on the current earth's crust to a height of, for example, about 1 meter.
第4図は、この作業を数次にわたって繰返し、5回目の
盛り土を行い、かつ盛土周囲に111壁7を設けて工事
を完了した状態を示す。この場合、擁壁の代りに傾斜面
を形成してもよい。完成後の盛り土面は盛り土自体の自
重による圧縮、在来の地盤の沈下により若干下降するか
、これを予測して予め余盛りを加えておく必要がある。FIG. 4 shows the state in which this work is repeated several times, the fifth filling is performed, and the 111 wall 7 is installed around the filling to complete the construction. In this case, an inclined surface may be formed instead of the retaining wall. After completion, the surface of the embankment will drop slightly due to compression due to the weight of the embankment itself and subsidence of the existing ground, and it is necessary to anticipate this and add additional embankment in advance.
(発明の効果)
この発明は以上述べたように、ジヤツキにより上昇させ
た建造物を、本来のくい3の上端に接続くい5をつぎ足
すことにより常にくい3に支持させるとともに、つぎ足
した接続くい5を囲んで盛り土6を施すことにより、接
続くい部分に横応力が発生するのを防止し、さらに盛り
土6を数次にわたって行うことは、盛り土6がその都度
−・定量沈下、すなわち圧密沈下をして在来地盤に近い
部分から安定して行くため、前記余盛りを少くすること
ができ、このことにより盛り土高さを完成後も所定の高
さに保持することができる。1〜1,5mピッチで段階
的に扛上させてゆくので、−挙に数mも扛上する場合と
較べて、建造物の居住者は生活したままでよく、また営
業の中断をしたりする必要もなく、建造物の扛上を行う
ことができるという利点がある。(Effects of the Invention) As described above, this invention allows a building raised by a jack to be always supported by the connecting peg 5 by adding the connecting peg 5 to the upper end of the original peg 3. By applying the embankment 6 surrounding the 5, it is possible to prevent lateral stress from occurring at the connecting pile part, and furthermore, by applying the embankment 6 several times, the embankment 6 can be applied each time to cause quantitative settlement, that is, consolidation settlement. Since the embankment is stabilized starting from the part closest to the existing ground, the excess heap can be reduced, and thereby the height of the embankment can be maintained at a predetermined level even after completion. Because the building is lifted step by step at a pitch of 1 to 1.5 meters, the occupants of the building can remain living in the building, and business may have to be suspended, compared to the case where buildings are lifted several meters at a time. The advantage is that buildings can be taken over without having to do so.
なお、上記実施例にふいては予めくい3上に布基礎2を
載せた建造物が示されているが、くい3を有しない建造
物の場合は、建造物の下に鋼管杭を支持層迄圧入してか
ら本発明の方法により所定高さまで扛上させることがで
きる。−旦側方に移動し、くい3を打設してからその上
に移動して同様に実施すればよい。In addition, although the above example shows a building in which the cloth foundation 2 is placed on piles 3 in advance, in the case of a building without piles 3, steel pipe piles are placed under the building as a support layer. After being press-fitted up to this point, it can be lifted up to a predetermined height using the method of the present invention. - move to the side, drive the pile 3, move on top of it and repeat the same process.
以上のように、この発明によれば、広い地域に亙り高い
土盛りをする際に起り得る圧密沈下を非常に少なくする
ことができる。また、建造物を分解する必要もなく、か
つ作業は居住者を収容したまま続けることができて、極
めて経済的かつ効率的である。As described above, according to the present invention, it is possible to greatly reduce consolidation settlement that may occur when building a high earth mound over a wide area. Furthermore, there is no need to dismantle the building, and work can be continued with residents accommodated, making it extremely economical and efficient.
図面はこの発明の方法を実施する順序を示j7、第1図
は施工前の状態、第2図は上昇させた状態第3図は第1
回目の盛り土を施した状態、第4図は施工完了後の状態
を示す説明図である。
1・・建造物、 2・・布基礎、
3・・くい 4・・油圧ジヤツキ、5・・接続
くい 6・・盛り土。The drawings show the order in which the method of the present invention is carried out. Figure 1 shows the state before construction, Figure 2 shows the elevated state, and Figure 3 shows the first stage.
FIG. 4 is an explanatory diagram showing the state after the second filling has been applied, and FIG. 4 is an explanatory diagram showing the state after the construction is completed. 1. Building, 2. Cloth foundation, 3. Pile 4. Hydraulic jack, 5. Connecting pile 6. Embankment.
Claims (1)
にジャッキを介設して所望高さに扛上し、次いで上記建
造物を支持するくいの上端に接続くいを継ぎ足して建造
物を支持させ、これら接続くい間を充填して盛り土を行
い、上記扛上・土盛り作業を数次にわたり繰り返し行っ
て所要高さとすることを特徴とする広域高盛り土の際の
重量物扛上方法。A building built on the ground to be filled is raised to the desired height by installing a jack under the foundation, and then a connecting peg is added to the top of the peg that supports the structure to support the structure. A method for lifting heavy objects in wide-area high earth embankment, characterized in that the connecting piles are filled with earth to form a mound, and the above-mentioned lifting and earth mounding operations are repeated several times to obtain the required height.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP25478488A JPH02104866A (en) | 1988-10-12 | 1988-10-12 | Lifting of heavyweight structure in case of high banking over wide area |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP25478488A JPH02104866A (en) | 1988-10-12 | 1988-10-12 | Lifting of heavyweight structure in case of high banking over wide area |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH02104866A true JPH02104866A (en) | 1990-04-17 |
Family
ID=17269833
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP25478488A Expired - Lifetime JPH02104866A (en) | 1988-10-12 | 1988-10-12 | Lifting of heavyweight structure in case of high banking over wide area |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH02104866A (en) |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5935655U (en) * | 1982-08-30 | 1984-03-06 | 日産ディーゼル工業株式会社 | Engine auxiliary drive control device |
-
1988
- 1988-10-12 JP JP25478488A patent/JPH02104866A/en not_active Expired - Lifetime
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5935655U (en) * | 1982-08-30 | 1984-03-06 | 日産ディーゼル工業株式会社 | Engine auxiliary drive control device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106522242A (en) | Foundation pit supporting system for subsurface structure close to soft ground stratum and construction method of foundation pit supporting system | |
CN106522241A (en) | Deep foundation pit supporting method of ultrahigh floor height type basement structure | |
CN105350527A (en) | Prestressed pipe pile construction method based on building information modeling (BIM) and prestressed pipe pile | |
CN110878562B (en) | Method for in-situ excavation of foundation pit and new addition of underground structure under existing reserved building | |
CN109024662A (en) | Method of the anchor pile underpinning without basement building underground space increasing layer | |
CN113356219A (en) | Synchronous excavation construction method for foundation pits at different depths on two sides of operation subway | |
CN110439025B (en) | Portal type building pile foundation underpinning structure in narrow space and construction method | |
JP3126896B2 (en) | Restoration method for uneven settlement structures | |
CN208517810U (en) | A kind of temporary trestle bridge for deep big foundation pit excavation construction | |
JP2596798B2 (en) | Existing building seismic isolation method | |
CN208763446U (en) | Increase the supporting construction for building the underground space under a kind of existing building group | |
CN217027018U (en) | A downthehole dynamic compaction gravel pile foundation structure for large tracts of land weak soil is consolidated | |
JPH02104866A (en) | Lifting of heavyweight structure in case of high banking over wide area | |
JPS62288269A (en) | Method for extending underground stair of building | |
CN211395691U (en) | Structure for improving vertical supporting node | |
CN114215106A (en) | Multi-pile support column structure adopting upper steel structure full-reverse construction method and construction method | |
JPH0559728A (en) | Sheathing work above underground structure | |
CN107023012A (en) | Multiple tracks annular concrete support Deep Foundation Pit Excavation outward transport construction method | |
CN216999743U (en) | Foundation pit enclosure structure capable of constructing inclined support before excavation of foundation pit | |
CN215669660U (en) | But reuse's retaining wall | |
Jovanović et al. | Excavation support system with piles—Case study | |
CN212452682U (en) | Deep foundation pit supporting structure | |
JPH0548820B2 (en) | ||
Huber et al. | Supporting Community Health: Foundations and Excavation Support for Brooklyn Methodist Hospital’s Center for Community Healthcare | |
CN206956730U (en) | Multiple tracks annular concrete support pit earthwork outward transport constructing structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090506 Year of fee payment: 16 |
|
EXPY | Cancellation because of completion of term | ||
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090506 Year of fee payment: 16 |