JPH01295957A - Concrete filling pipe construction and execution thereof - Google Patents

Concrete filling pipe construction and execution thereof

Info

Publication number
JPH01295957A
JPH01295957A JP12619688A JP12619688A JPH01295957A JP H01295957 A JPH01295957 A JP H01295957A JP 12619688 A JP12619688 A JP 12619688A JP 12619688 A JP12619688 A JP 12619688A JP H01295957 A JPH01295957 A JP H01295957A
Authority
JP
Japan
Prior art keywords
concrete
pipe
filled
lining
precast concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP12619688A
Other languages
Japanese (ja)
Inventor
Yutaka Saito
豊 斉藤
Koichi Nakamura
康一 中村
Yasushi Watanabe
泰志 渡辺
Takanori Sato
孝典 佐藤
Yoshihiro Orito
芳寛 下戸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP12619688A priority Critical patent/JPH01295957A/en
Publication of JPH01295957A publication Critical patent/JPH01295957A/en
Pending legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

PURPOSE:To make concrete filling compact and high-quality by setting back both ends of a lining concrete and forming a slope at least on one end in a concrete pipe. CONSTITUTION:A lining concrete 2 is formed in the internal circumferential surface of a steel pipe 1 by centrifugal force, and both ends thereof are set back. In addition, one end of the lining concrete 2 set back at least forms such a slope 6 that gradually enlarge a diameter with the approach to the end of the pipe. Such a concrete pipe (A) is connected, and after placing it on a specific location, when concrete is filled into the pipe, an impregnation work for a space made between end plates can't be necessary, and a placed concrete is filled while rising along the slope smoothly, so that a compact and high-quality concrete execution can be carried out.

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は、管等の内面にコンクリートが遠心力成形され
ることにより製作されるプレキャストコンクリート管を
、現場において、柱や抗等に組み立てた後、その内部に
コンクリートを充填することにより構築されるコンクリ
ート充填管構造及びその施工方法に関するものである。
[Detailed Description of the Invention] "Industrial Application Field" The present invention is a precast concrete pipe manufactured by centrifugally forming concrete on the inner surface of the pipe, etc., which can be assembled into columns, columns, etc. on site. The present invention also relates to a concrete-filled pipe structure constructed by filling the inside with concrete and its construction method.

「従来の技術」 従来のこの種のコンクリート充填管構造としては、第6
図、第7図に示す、プレキャストコンクリ−1・管の内
部にコンクリートを充填して構築した抗構造等が知られ
ている。
“Conventional technology” As a conventional concrete-filled pipe structure of this type, No. 6
BACKGROUND ART There is a known anti-strength structure constructed by filling the inside of a precast concrete pipe with concrete, as shown in FIGS. 1 and 7.

図中符号Aは杭として使用されるプレキャストコンクリ
ート管であり、鋼管等lの内周面に遠心力成形によって
均一な厚さのコンクリート2がライニングされている。
Reference numeral A in the figure is a precast concrete pipe used as a pile, and the inner peripheral surface of the steel pipe 1 is lined with concrete 2 of uniform thickness by centrifugal force forming.

鋼管等1の両端面には、外面側が他の鋼管等と接続され
ると共に、その内面側がライニングコンクリート2と接
触するように円盤状に形成された端板3.3が設けられ
ている。
Disc-shaped end plates 3.3 are provided on both end faces of the steel pipe etc. 1 so that the outer surface side is connected to other steel pipes etc. and the inner surface side thereof is in contact with the lining concrete 2.

そして、前記のように構成されたブレキャスI、コンク
リート管Aは、現場において、圧入工法等により地中に
逐次打ち込まれると共に、前記端板3を接続すべき相手
のプレキャストコンクリート管の端板3と重ね合わせた
状態で溶接等の接続手段により接続される。さらに、プ
レキャストコンクリート管A、A、・・が地中に所定の
長さに接続されて設置された後には、第4図に示すよう
に、該プレキャストコンクリート管の内部に現場打ちの
コンクリート4が打設されることによって、コンクリー
ト充填管杭構造等となる。
The Brecast I and concrete pipe A configured as described above are successively driven into the ground by a press-in method etc. at the site, and the end plate 3 of the precast concrete pipe to which the end plate 3 is to be connected is connected to the end plate 3 of the precast concrete pipe. They are connected by a connecting means such as welding in an overlapping state. Furthermore, after the precast concrete pipes A, A, etc. are connected to a predetermined length underground and installed, as shown in Fig. 4, cast-in-place concrete 4 is placed inside the precast concrete pipes. By being cast, it becomes a concrete-filled pipe pile structure, etc.

「発明が解決しようとする課題」 ところが、前記従来のコンクリート充填管構造にあって
は、プレキャストコンクリート管の端部に端板が形成さ
れてるため、該端板同士を重ね合わせて前記プレキャス
トコンクリート管を長手方向に溶接接続する際に、端番
同士の接触面に製作誤差や施工誤差のために間隙が生じ
、構造的にプレキャストコンクリート管に長手方向の応
力負担を期待しCいる杭や柱構造として、信頼性の点で
問題かあった。このため、間隙が生じないように、この
間隙に細粒子の高強度セメントペースト等を注入しなけ
らばならず、施工性に問題点が残った。
"Problems to be Solved by the Invention" However, in the conventional concrete-filled pipe structure, since end plates are formed at the ends of the precast concrete pipe, the end plates are overlapped to form the precast concrete pipe. When welding and connecting the pipes in the longitudinal direction, gaps occur at the contact surfaces between the ends due to manufacturing and construction errors, and structurally, the precast concrete pipe is expected to bear stress in the longitudinal direction. However, there were problems with reliability. For this reason, it was necessary to inject fine particles of high-strength cement paste or the like into the gaps to prevent them from forming, which left problems with workability.

また、プレキャストコンクリート管を長手方向に接続し
ていく際に、寸法調節が必要となった場合には、端板を
切削したり、コンクリートをはつったりしなけらばなら
ず、作業が繁雑となり工期遅延の原因となる虞れがあっ
た。
In addition, when connecting precast concrete pipes in the longitudinal direction, if dimensions need to be adjusted, end plates must be cut or concrete must be poured, making the work complicated. There was a risk that this would cause a delay in the construction period.

本発明は、前記課題に鑑みてなされたもので、内部にコ
ンクリートがライニングされた鋼管等(プレキャストコ
ンクリート管)を長手方向に接続する際に、プレキャス
トコンクリート管の継ぎ平部の端板間の間隙注入を不要
とし、かつまた長手方向の寸法調節を容易に行うことの
できるコンクリート充填管構造及びその施工方法を提供
することを目的としている。
The present invention has been made in view of the above-mentioned problems, and when connecting steel pipes etc. (precast concrete pipes) whose interiors are lined with concrete (precast concrete pipes) in the longitudinal direction, the gap between the end plates of the joint flat part of the precast concrete pipes is The object of the present invention is to provide a concrete-filled pipe structure that does not require pouring and can easily adjust dimensions in the longitudinal direction, and a method for constructing the same.

「課題を解決するための手段」 この発明は、管等の内周面に遠心力によって形成された
ライニングコンクリートの両端部がセットバックされ、
かつ該セットバックされたライニングコンクリートの少
なくとも一端部に管等の端部に近付くに従って漸次拡径
するような傾斜面が形成された構造とすることにより、
前記の目的を達成している。
"Means for Solving the Problems" This invention provides that both ends of lining concrete formed by centrifugal force on the inner peripheral surface of a pipe etc. are set back,
And by forming a structure in which at least one end of the setback lining concrete is formed with an inclined surface whose diameter gradually increases as it approaches the end of the pipe, etc.
The above objectives have been achieved.

また、この発明の方法は、管等の内周面に遠心力によっ
て両端がセットバックされたライニングコンクリートを
形成してプレキャストコンクリート管とし、ついで、該
プレキャストコンクリート管を所定長に接続し、所定の
場所に設置した後、該プレキャストコンクリート管の内
部にコンクリートを充填するようにしている。
Furthermore, the method of the present invention includes forming a lining concrete with both ends set back by centrifugal force on the inner circumferential surface of a pipe, etc. to form a precast concrete pipe, and then connecting the precast concrete pipe to a predetermined length to form a precast concrete pipe. After being installed at a location, the inside of the precast concrete pipe is filled with concrete.

「作用」 本発明にあっては、プレキャストコンクリート管の管等
の両端部のコンクリートがセットバックされているため
、プレキャストコンクリート管を接続する際に端板間に
生じる間隙への注入工事を不要とする。また、寸法調節
を行う際にも、鋼管等の端部のみを切削調整するように
すれば良く、容易に寸法調節を行うことができる。
"Function" In the present invention, since the concrete at both ends of the precast concrete pipe is set back, there is no need for pouring work into the gap created between the end plates when connecting the precast concrete pipes. do. Furthermore, when adjusting the dimensions, it is sufficient to cut only the ends of the steel pipe, etc., and the dimensions can be easily adjusted.

さらに、セットバックされたライニングコンクリートの
少なくとも一端部に傾斜面が形成されているため、該傾
斜面が下側となるようにプレキャストコンクリート管を
建込んで、内部にコンクリートを打設するようにすれば
、打設コンクリートが前記傾斜面を円滑に上昇しながら
充填されるため、ライニングコンクリートのセットバッ
クされた部分に空気溜まりが形成されることなく、また
、打設後の収縮沈下の際にも、接続部付近にもス1、−
ズに上方のコンクリートが自重により沈下充填するので
密実な良質のコンクリート施工が行なわれる。
Furthermore, since a sloped surface is formed on at least one end of the setback lining concrete, it is recommended that the precast concrete pipe be built with the sloped surface facing downward and concrete poured inside. For example, since the poured concrete is filled while smoothly rising up the slope, air pockets are not formed in the setback part of the lining concrete, and even if the lining concrete shrinks and sinks after pouring, , there is also a 1, - near the connection part.
As the concrete above sinks and fills due to its own weight, dense, high-quality concrete construction is possible.

「実施例」 以下、図面を参照して本発明を説明する。第1図ないし
第5図は、本発明のコンクリート充填管構造の一実施例
を示すものである。なお、本実施例において、従来の技
術に示す構成要素と同一の要素については、同一符号を
付すこととする。
"Example" The present invention will be described below with reference to the drawings. 1 to 5 show an embodiment of the concrete-filled pipe structure of the present invention. In addition, in this embodiment, the same reference numerals are given to the same elements as those shown in the conventional technique.

第2図は本実施例のコンクリート充填管構造が建築物B
の柱及び杭として使用されている状態を示すものであり
、建築物Bの内部においては、梁5が接続されることに
よりコンクリート充填管柱構造として機能しており、建
築物Bの底盤Blの下部ではコンクリート充填管杭構造
としての機能を果たしている。
Figure 2 shows that the concrete-filled pipe structure of this example is used for building B.
This figure shows the state in which it is being used as a column and pile. Inside Building B, the beam 5 is connected to function as a concrete-filled pipe column structure, and the bottom plate Bl of Building B is functioning as a column structure. The lower part functions as a concrete-filled pipe pile structure.

そして、第1図は第2図の2部分の拡大断面図であり、
前記コンクリート充填管柱構造及びコンクリート充填管
杭構造は、鋼管等lの内周面にライニングコンクリート
が遠心力成形されて設けられ、該ライニングコンクリー
ト2のさらに内側には現場で打設されたコンクリート4
が設けられた構成となっており、さらに、ライニングコ
ンクリート2両端部は鋼管等の端部から僅かにセットバ
ックされ、かつまたセットバックされたライニングコン
クリートの両端部には、鋼管等の端部に近付くに従って
漸次拡径するような傾斜面6が形成されたものとなって
いる。なお、鋼管等lの内部には、梁5との接続部分等
において、ライニングコンクリートを鋼管等の軸方向に
押圧するための支圧板を設けるようにしてもよい。
FIG. 1 is an enlarged sectional view of two parts in FIG.
In the concrete-filled pipe column structure and concrete-filled pipe pile structure, lining concrete is formed by centrifugal force forming on the inner peripheral surface of a steel pipe, etc., and further inside the lining concrete 2 is concrete 4 cast on site.
Furthermore, both ends of the lining concrete 2 are slightly set back from the ends of the steel pipes, etc., and both ends of the set back lining concrete are provided with the ends of the steel pipes, etc. An inclined surface 6 is formed whose diameter gradually increases as it approaches. Note that a bearing plate may be provided inside the steel pipe, etc., at the connection portion with the beam 5, etc., for pressing the lining concrete in the axial direction of the steel pipe, etc.

つぎに、前記構成の本実施例のコンクリート充填管構造
の施工方法について、その作用とともに説・明する。
Next, the construction method of the concrete-filled pipe structure of this embodiment having the above configuration will be explained and explained along with its operation.

* まず、第3図に示すように、鋼管等lを遠心機(図
示せず)にセットすると共に、鋼管等の内部にコンクリ
ート2を配した状態で、遠心機を作動させて鋼管等1を
回転させることにより、鋼管等1の内側にコンクリート
2をライニングしてプレキャストコンクリート管Aを製
作する。
* First, as shown in Figure 3, a steel pipe etc. 1 is set in a centrifuge (not shown), and with concrete 2 placed inside the steel pipe etc., the centrifuge is operated to remove the steel pipe 1. By rotating, the inside of the steel pipe etc. 1 is lined with concrete 2 to produce a precast concrete pipe A.

その際、鋼管等1の両端部付近には上端部型枠7、上端
部型枠8とを設置しておき、ライニングされるコンクリ
ート5が鋼管等!の両端部付近においてセットバックさ
れるようにする。さらに、上端部型枠7と上端部型枠8
には、鋼管等の端部に近付くに従って暫時拡径するよう
な滑らかな傾斜面6が形成されている。この傾斜面をS
カーブ状に形成すると更に望ましい。
At that time, an upper end formwork 7 and an upper end formwork 8 are installed near both ends of the steel pipe etc. 1, and the concrete 5 to be lined is the steel pipe etc.! Setback should be made near both ends of. Furthermore, the upper end formwork 7 and the upper end formwork 8
is formed with a smooth inclined surface 6 whose diameter gradually increases as it approaches the end of the steel pipe or the like. This slope is S
It is more desirable to form it into a curved shape.

* つぎに、第4図に示すように、内部に遠心力によっ
てライニングコンクリート2を形成したプレキャストコ
ンクリート管Aを所定長に接続すると共Zこ、又は接続
した後に、所定の場所に圧入工法等により設置する。
*Next, as shown in Fig. 4, the precast concrete pipe A with the lining concrete 2 formed therein by centrifugal force is connected to a predetermined length, or after the connection, the precast concrete pipe A is inserted into a predetermined place by a press-fitting method, etc. Install.

なお、プレキャストコンクリート管Aを設置する際には
、ライニングコンクリートに傾斜面6が一端のみに形成
されている場合には、必ず斜面6が形成されている方を
下端にして建て込む。
When installing the precast concrete pipe A, if the lining concrete has an inclined surface 6 formed at only one end, the precast concrete pipe A is always erected with the side where the inclined surface 6 is formed as the lower end.

* そして、プレキャストコンクリート管Aが所定の深
さまで設置されると、その内部にトレミー管9を用いて
コンクリートを充填することによりコンクリート充填管
杭構造を構築する。
* When the precast concrete pipe A is installed to a predetermined depth, the inside thereof is filled with concrete using the tremie pipe 9 to construct a concrete-filled pipe pile structure.

その際、打設されたコンクリート4はライニングコンク
リート2のセットパック位置においても、傾斜面6に沿
って滑らかに上昇し、また打設後にはスムーズに収縮沈
下することとなり、ライニングコンクリート2の端部付
近(継手部付近)に空気溜まりや、骨材分離か発生した
りすることがない。
At this time, the poured concrete 4 rises smoothly along the slope 6 even at the set pack position of the lining concrete 2, and also smoothly shrinks and sinks after being poured, so that the end of the lining concrete 2 There are no air pockets or aggregate separation in the vicinity (near the joint).

* モして、コンクリート充填管杭構造が構築された後
には、さらに、その上部に順次プレキャストコンクリー
ト管Aを接続していくと共に、仕口部分に粱5を接続し
た後、前記プレキャストコンクリート管A、A、・・内
にコンクリートを打設することにより、コンクリート充
填管柱構造を構築する。
*After the concrete-filled pipe pile structure is constructed, the precast concrete pipes A are successively connected to the upper part of the pile structure, and the precast concrete pipes A are connected to the joint part. A concrete-filled pipe column structure is constructed by pouring concrete into , A, .

このように、本実施例のコンクリート充填管構造にあっ
ては、プレキャストコンクリート管Aの鋼管等lの両端
部のコンクリート2がセットバックされているため、プ
レキャストコンクリート管Aを継ぎ足して接続する際に
も、端板間に生じる間隙への注入工事を不要とすること
ができる。また、高さ方向の寸法調節を行う際にも、プ
レキャストコンクリート管Aの鋼管等の端部のみを切削
調整するようにすれば良く、容易にかつ高精度に長手方
向の寸法調節を行うことができ、工期の短縮及び高品質
で信頼性の高い施工をすることができる。
In this way, in the concrete-filled pipe structure of this embodiment, since the concrete 2 at both ends of the steel pipe etc. l of the precast concrete pipe A is set back, when adding and connecting the precast concrete pipe A, Also, it is possible to eliminate the need for injection work into the gap created between the end plates. Also, when adjusting dimensions in the height direction, it is only necessary to cut and adjust the ends of the steel pipes, etc. of precast concrete pipe A, making it possible to easily and accurately adjust dimensions in the longitudinal direction. It is possible to shorten the construction period and perform high quality and reliable construction.

さら1こ、セットバックされノこライニングコンクリー
ト2の端部に傾斜面6が形成されているため、打設コン
クリート4が傾斜面6に沿って円滑に上昇しながら充填
されるため、また、打設後にはスムーズに収縮沈下する
ためライニングコンクリート2のセットバックされた股
部分(接続部付近)に空気溜まりや骨材分離が形成され
ることなく、密実な高品質のコンクリート施工が行える
Furthermore, since the sloped surface 6 is formed at the end of the saw lining concrete 2 that has been set back, the poured concrete 4 is filled while rising smoothly along the sloped surface 6. After installation, the lining concrete 2 shrinks and settles smoothly, so that no air pockets or aggregate separation are formed in the setback crotch part (near the connection part) of the lining concrete 2, allowing dense, high-quality concrete construction.

尚、以上述べた実施例において、鋼管等の内側にアンボ
ンド処理を施した鋼管等を用いれば、アンボンドコンク
リート充填管構造として実施できる。
Incidentally, in the embodiments described above, if a steel pipe or the like which has been subjected to an unbonding treatment on the inside thereof is used, it can be implemented as an unbonded concrete-filled pipe structure.

「発明の効果−ノ 以上説明したように本発明のコンクリート充填管構造及
びその施工方法は、プレキャストコンクリート管の鋼管
等の両端部のコンクリートがセットバーツクされている
ため、プレキャストコンクリート管を接続する際に、端
板間に生じる間隙への注入工事を不要とすることかでき
るので、複雑な施工をしなけらばならないという、従来
の構造や施工方法の問題点を解決することができる。さ
らに、接続部での、寸法調節を行う際にも、鋼管等のみ
を切削するようにすれば良く、容易に精度良く寸法調節
を行うことができる。したがって、構造上の信頼性が極
めて高い高品質のコンクリート充填管構造と、その施工
方法を提供するものとなり、建設産業の発展に極めて多
大な寄与をする。
"Effects of the Invention - As explained above, the concrete-filled pipe structure and its construction method of the present invention have concrete at both ends of the steel pipe, etc. of the precast concrete pipe being set bard, so that it is difficult to connect the precast concrete pipes. In this case, it is possible to eliminate the need for injection work into the gap that occurs between the end plates, which solves the problem of conventional structures and construction methods that require complicated construction. , when adjusting the dimensions at the connection part, it is only necessary to cut the steel pipe, etc., and the dimensions can be easily and accurately adjusted.Therefore, high quality with extremely high structural reliability. This will provide a concrete-filled pipe structure and its construction method, making an extremely large contribution to the development of the construction industry.

また、セットバックされたライニングコンクリートの少
なくとも一端部に傾斜面が形成されているため、該傾斜
面が下側となるようにプレキャストコンクリート管を建
込んで、内部にコンクリートを打設するようにすれば、
打設コンクリートが前記傾斜面を円滑に上昇しながら充
填されるため、また、コンクリート打設後の収縮沈下も
スムーズに行なわれるので、ライニングコンクリートの
セットバックされた部分に空気溜まりが形成されたり、
骨材分離減少が生じることなく、密実な高品質のコンク
リートを施工することができる効果を奏する。
In addition, since a sloped surface is formed at least at one end of the setback lining concrete, it is recommended to build a precast concrete pipe with the sloped surface facing downward and pour concrete inside. Ba,
Because the poured concrete is filled while smoothly rising up the slope, and because the concrete shrinks and sinks smoothly after being poured, air pockets are not formed in the setback part of the lining concrete.
This has the effect of making it possible to construct dense, high-quality concrete without reducing aggregate separation.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図ないし第5図は本発明の第1実施例を示すもので
あり、第1図は第2図の2部分を拡大したものであり、
本発明のコンクリート充填管構造の側断面図、第2図は
本発明のコンクリート充填管構造が建物の柱や杭として
使用されている状態を説明するための説明図、第3図は
遠心力成形されたプレキャストコンクリート管柱の側断
面図、第4図は地盤中に建込んだ状態のプレキャストコ
ンクリート管柱の側断面図、第5図は接続されたプレキ
ャストコンクリート管の内部にコンクリートを打設して
いるところを示す側断面図、第6図。 第7図は従来の技術を示すものであり、第6図はプレキ
ャストコンクリート管の接続前の側断面図、第7図は従
来のプレキャストコンクリート管を接続して内部にコン
クリートを打設することにより構築されたコンクリート
充填管構造の側断面図である。 A・・・・・・プレキャストコンクリート管、l・・・
・・・鋼管等、2・・・・・・ライニングコンクリート
(コンクリート)、4・・・・・・打設コンクリート(
コンクリート)、6・・・・・・傾斜面。
1 to 5 show a first embodiment of the present invention, and FIG. 1 is an enlarged view of two parts of FIG.
A side sectional view of the concrete-filled pipe structure of the present invention, Fig. 2 is an explanatory diagram for explaining the state in which the concrete-filled pipe structure of the present invention is used as a pillar or pile of a building, and Fig. 3 is centrifugal force forming. Fig. 4 is a side sectional view of the precast concrete pipe column installed in the ground, and Fig. 5 is a side sectional view of the precast concrete pipe column installed in the ground. FIG. 6 is a side sectional view showing the location where the Fig. 7 shows the conventional technology, Fig. 6 is a side sectional view of precast concrete pipes before connection, and Fig. 7 shows the conventional technology by connecting precast concrete pipes and pouring concrete inside. FIG. 2 is a side sectional view of the constructed concrete-filled pipe structure. A... Precast concrete pipe, l...
... Steel pipes, etc., 2 ... Lining concrete (concrete), 4 ... Pouring concrete (
concrete), 6... Slope surface.

Claims (1)

【特許請求の範囲】 1、柱や杭等に使用されるコンクリート充填管構造であ
って、管等の内周面に遠心力によって形成されたライニ
ングコンクリートの両端部がセットバックされ、かつ該
セットバックされたライニングコンクリートの少なくと
も一端部に管等の端面に近付くに従って漸次拡径するよ
うな傾斜面が形成されていることを特徴とするコンクリ
ート充填管構造。 2、管等の内周面に遠心力によって両端がセットバック
されたライニングコンクリートを形成してプレキャスト
コンクリート管とし、ついで、該プレキャストコンクリ
ート管を所定長に接続し、所定の場所に設置した後、該
プレキャストコンクリート管の内部にコンクリートを充
填することを特徴とするコンクリート充填管構造の施工
方法。
[Claims] 1. A concrete-filled pipe structure used for columns, piles, etc., in which both ends of the lining concrete formed by centrifugal force on the inner peripheral surface of the pipe, etc. are set back, and the set A concrete-filled pipe structure characterized in that at least one end of the backed lining concrete is formed with an inclined surface whose diameter gradually increases as it approaches the end face of the pipe or the like. 2. Form a lining concrete on the inner peripheral surface of the pipe etc. with both ends set back by centrifugal force to form a precast concrete pipe, then connect the precast concrete pipe to a predetermined length and install it at a predetermined location, A method for constructing a concrete-filled pipe structure, comprising filling the inside of the precast concrete pipe with concrete.
JP12619688A 1988-05-24 1988-05-24 Concrete filling pipe construction and execution thereof Pending JPH01295957A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12619688A JPH01295957A (en) 1988-05-24 1988-05-24 Concrete filling pipe construction and execution thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12619688A JPH01295957A (en) 1988-05-24 1988-05-24 Concrete filling pipe construction and execution thereof

Publications (1)

Publication Number Publication Date
JPH01295957A true JPH01295957A (en) 1989-11-29

Family

ID=14929080

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12619688A Pending JPH01295957A (en) 1988-05-24 1988-05-24 Concrete filling pipe construction and execution thereof

Country Status (1)

Country Link
JP (1) JPH01295957A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6332030A (en) * 1986-07-28 1988-02-10 日本鋼管株式会社 Method for bonding pillar

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6332030A (en) * 1986-07-28 1988-02-10 日本鋼管株式会社 Method for bonding pillar

Similar Documents

Publication Publication Date Title
CN105421222B (en) Bridge prefabrication pier column and cushion cap socket type connecting structure and its assembling method
JPH01256651A (en) Steel pipe concrete pillar structure and construction thereof
JP2003232033A (en) Foundation pile structure
KR20210012525A (en) Steel structures and top-down method using it
JPH01295957A (en) Concrete filling pipe construction and execution thereof
JPH02161043A (en) Joint structure of steel pipe concrete column, steel pipe concrete column, and construction thereof
JP2010196441A (en) Core material of soil cement continuous underground wall
JPS62194319A (en) Construction of in-situ concrete pile
JPH0315605Y2 (en)
KR102644085B1 (en) Steel outer casing molding jig coated with lining for drilling clearance
JPH10331155A (en) Soil cement embedding pile
JPS6026724A (en) Integration work of steel-framed building structure and composite underground beam
JPH09170338A (en) Base isolation method for existing building
JPS59116090A (en) Wall structure in reactor building and the like
JPS62244923A (en) Anchor bolt-driven precast concrete block and driving of anchor bolt
JP2973334B2 (en) Manufacturing method of steel pipe concrete column
JP2651607B2 (en) Joint structure of steel tube concrete column, steel tube concrete column and construction method
JPH0219251B2 (en)
JPS63147009A (en) Construction of continuous underground wall
JPH0448137B2 (en)
JPS61229067A (en) Underground construction method of building
KR20220147295A (en) Seismic foundation pile and method of manufacturing the same
JPS5850218A (en) Connecting structure system for head of cast-in-place concrete pile and footing
SU831894A1 (en) Collar for securing upper part of trench
JPH02132228A (en) Process of building heavy-duty working floor using existing basement structure