JP2003232033A - Foundation pile structure - Google Patents
Foundation pile structureInfo
- Publication number
- JP2003232033A JP2003232033A JP2002029159A JP2002029159A JP2003232033A JP 2003232033 A JP2003232033 A JP 2003232033A JP 2002029159 A JP2002029159 A JP 2002029159A JP 2002029159 A JP2002029159 A JP 2002029159A JP 2003232033 A JP2003232033 A JP 2003232033A
- Authority
- JP
- Japan
- Prior art keywords
- pile
- piles
- foundation
- ground
- steel pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 47
- 239000010959 steel Substances 0.000 claims abstract description 47
- 238000000034 method Methods 0.000 claims abstract description 26
- 239000004567 concrete Substances 0.000 claims description 16
- 238000010276 construction Methods 0.000 abstract description 13
- 239000002184 metal Substances 0.000 description 11
- 238000003466 welding Methods 0.000 description 6
- 238000009412 basement excavation Methods 0.000 description 4
- 239000004568 cement Substances 0.000 description 4
- 238000005304 joining Methods 0.000 description 4
- 239000002689 soil Substances 0.000 description 4
- 239000011513 prestressed concrete Substances 0.000 description 3
- 238000005452 bending Methods 0.000 description 2
- 230000005540 biological transmission Effects 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 2
- 238000005553 drilling Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 230000002093 peripheral effect Effects 0.000 description 2
- 238000005260 corrosion Methods 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000008267 milk Substances 0.000 description 1
- 210000004080 milk Anatomy 0.000 description 1
- 235000013336 milk Nutrition 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 238000004080 punching Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
(57)【要約】
【課題】 安価なコストで地盤の性状に適合した基礎杭
を設置することができる基礎杭構造を提供すること。
【解決手段】 各種構造物を支える基礎杭構造におい
て、鋼管杭2を基礎杭1の所要の位置でPC杭に連結
し、これにより形成される基礎杭1を各種既製杭の打設
工法により地盤G中に設置するようにしたので、従来に
比べて安価なコストで基礎杭を構築することができる
他、施工現場の環境や地盤の性状に適合した工法により
設置することができる。
(57) [Summary] [PROBLEMS] To provide a foundation pile structure capable of installing a foundation pile adapted to the properties of the ground at low cost. SOLUTION: In a foundation pile structure supporting various structures, a steel pipe pile 2 is connected to a PC pile at a required position of the foundation pile 1, and the foundation pile 1 formed by this is grounded by a method of placing various ready-made piles. Since it is installed in G, foundation piles can be constructed at a lower cost than before, and can be installed by a construction method suitable for the environment of the construction site and the properties of the ground.
Description
【0001】[0001]
【発明の属する技術分野】本発明は、各種構造物を支え
る基礎杭構造に関する。TECHNICAL FIELD The present invention relates to a foundation pile structure for supporting various structures.
【0002】[0002]
【従来の技術】ビル建物等の建築構造物や、鉄道、港湾
等を含む土木構造物の各種構造物にあっては、例えばプ
レストレストコンクリート杭(PC杭)等の既製杭を用
い構造物の重量を強固な地盤である支持地盤まで到達さ
せることによって、構造物を支持させることが一般的に
行われている。既製杭は支持地盤の深さ位置等の地盤状
況に応じて1本又は複数本連結されて用いられており、
必要とされる強度に対してコストが安価である等の理由
から既製杭のうちPC杭が広く用いられている。2. Description of the Related Art For various structures such as building structures and civil engineering structures including railways and harbors, for example, pre-stressed concrete piles (PC piles) or other ready-made piles are used. It is common practice to support a structure by reaching the support ground, which is a solid ground. One or more ready-made piles are connected and used according to the ground condition such as the depth position of the supporting ground,
Among the ready-made piles, PC piles are widely used because the cost is low with respect to the required strength.
【0003】PC杭には、設計時に想定される地震時に
作用する水平力等の大きさに応じた適切な杭を使用でき
るよう、A種、B種、C種とこの順でプレストレス力が
大きくなる杭種が設定されており、これらの杭種のう
ち、通常条件が最も厳しくなる杭頭部において必要とさ
れる強度に合わせてB種又はC種のものが一般的に使用
されている。Prestressing force is applied to PC piles in the order of Class A, Class B, and Class C so that appropriate piles can be used according to the magnitude of horizontal force acting at the time of an earthquake that is assumed during design. Larger pile types are set, and among these pile types, those of type B or C are generally used according to the strength required in the pile head where the normal conditions are the most severe. .
【0004】杭頭部に想定される水平力や曲げモーメン
トがC種のPC杭でも耐えられない程大きい場合には、
鋼管杭内部に遠心力コンクリートを打設した高い水平耐
力と曲げ耐力とを保有する外殻鋼管付コンクリート杭
(SC杭)をPC杭に連結して基礎杭の杭頭部に使用す
ることにより対応する場合が多い。If the horizontal force and bending moment expected on the pile head are too large for a C type PC pile to withstand,
Corresponding by connecting the concrete pile with steel pipe with outer shell (SC pile), which has high horizontal and bending strength in which centrifugal concrete is placed inside the steel pile, to the pile head of the foundation pile by connecting it to the PC pile Often.
【0005】上述の如く、先ず基礎杭の下杭としてPC
杭を打設し、PC杭にSC杭を杭頭部として継ぎ足して
打設する場合、PC杭とSC杭とは、一般的に、それぞ
れの杭の端部に予め設けられている端部金物同士を突き
合わせ、溶接して接合するほか、ネジ継手や圧着金物を
用いる等の方法により接合が行われている。As described above, first, the PC is used as the lower pile of the foundation pile.
When piles are piled up, and when piles are piled up by adding SC piles to PC piles as pile heads, PC piles and SC piles are generally end hardware provided in advance at the ends of the piles. In addition to joining them by welding, they are joined by a method such as using a screw joint or a crimp metal fitting.
【0006】[0006]
【発明が解決しようとする課題】ところで、SC杭は、
例えば、端部金物と型枠とを取り付けて用意しておいた
鋼管内部にコンクリートを注入し、成型、養生した後型
枠を取り外す等の工程を経て製造されるため、その製作
に非常に手間がかかる等の理由により高価なものとなっ
ている。このようにコストの高いSC杭をPC杭に継ぎ
足して使用する従来技術にあっては、安価なPC杭によ
りコストのかからない杭基礎を構築しようとしても、高
価なSC杭を採用することによりコストのかかる杭基礎
となってしまうという問題点を有している。By the way, the SC pile is
For example, since it is manufactured through the steps of pouring concrete into the steel pipe prepared by attaching the end metal fittings and the mold, molding and curing, and then removing the mold, it is very troublesome to manufacture. It is expensive because of the cost. In the conventional technology in which the high-priced SC piles are added to the PC piles in this way, even if an inexpensive PC pile is used to construct a pile foundation that does not cost much, the cost is increased by adopting the expensive SC piles. It has a problem that it becomes such a pile foundation.
【0007】また、周辺環境や地盤の性状、施工コスト
等の理由により、PC杭をハンマーで打撃する打ち込み
工法により設置する場合には、PC杭を打ち込んで支持
地盤に到達することにより地盤中でのその実際の深さが
分かるが、このとき支持地盤が不陸している等の理由に
より設計時の想定より早い段階で打ち込みを終了させる
必要が生じることが多々ある。この場合には施工現場に
おいて杭頭部を適宜の位置で切断して杭長を調節するこ
とが一般的に行われる。しかしながら、SC杭を杭頭部
に用いている場合、SC杭は剛性が非常に大きく施工現
場で切断することは基本的に困難であるため、SC杭を
杭頭部に用いる場合には打ち込み工法を採用しにくいと
いう別の問題点を有している。Further, when the PC pile is installed by a hammering driving method due to the surrounding environment, the property of the ground, construction cost, etc., the PC pile is driven into the supporting ground to reach the supporting ground. Although its actual depth can be known, it is often necessary to finish the driving at an earlier stage than expected at the time of design due to the fact that the supporting ground is unplanned. In this case, the pile head is generally cut at an appropriate position to adjust the pile length at the construction site. However, when the SC pile is used for the pile head, the rigidity of the SC pile is very large and it is basically difficult to cut it at the construction site. Therefore, when the SC pile is used for the pile head, the driving method is used. It has another problem that it is difficult to adopt.
【0008】本発明の目的は、上述した従来技術の問題
点を解決することができる基礎杭構造を提供することに
ある。An object of the present invention is to provide a foundation pile structure which can solve the above-mentioned problems of the prior art.
【0009】[0009]
【課題を解決するための手段】上記課題を解決するた
め、請求項1の発明によれば、各種構造物を支える基礎
杭構造であって、鋼管杭と既製コンクリート杭とから基
礎杭を形成し、前記鋼管杭を前記基礎杭の所要の位置に
用いたことを特徴とする基礎杭構造が提案される。To solve the above problems, according to the invention of claim 1, there is provided a foundation pile structure for supporting various structures, wherein the foundation pile is formed from steel pipe piles and ready-made concrete piles. There is proposed a foundation pile structure characterized by using the steel pipe pile at a required position of the foundation pile.
【0010】請求項2の発明によれば、請求項1の発明
において、前記基礎杭は各種既製杭の設置工法により設
置される基礎杭構造が提案される。According to the invention of claim 2, in the invention of claim 1, there is proposed a foundation pile structure in which the foundation pile is installed by a method of installing various ready-made piles.
【0011】[0011]
【発明の実施の形態】以下、図面を参照して本発明の実
施の形態の一例につき詳細に説明する。BEST MODE FOR CARRYING OUT THE INVENTION An example of an embodiment of the present invention will be described in detail below with reference to the drawings.
【0012】図1は本発明の実施の形態の一例を示す断
面図であり、本発明の構造による基礎杭1は、構造物の
重量を支持地盤G1まで到達させて地盤Gにおいて構造
物を支持するため、地盤G中に形成された掘削孔A内に
設置されている。符号2で示されるのは地盤G中の地上
付近に用いられている鋼管杭であり、符号3、4で示さ
れるのは鋼管杭2より下方部に用いられている既製コン
クリート杭のプレストレストコンクリート杭(PC杭)
である。ここでは、1本の鋼管杭2と2本のPC杭3、
4とが連結され基礎杭1が構築されて構造物のフーチン
グBに連結されている。FIG. 1 is a sectional view showing an example of an embodiment of the present invention. A foundation pile 1 according to the structure of the present invention supports the structure on the ground G by allowing the weight of the structure to reach the supporting ground G1. Therefore, it is installed in the excavation hole A formed in the ground G. Reference numeral 2 is a steel pipe pile used near the ground in the ground G, and reference numerals 3 and 4 are prestressed concrete piles of ready-made concrete piles used below the steel pipe pile 2. (PC pile)
Is. Here, one steel pipe pile 2 and two PC piles 3,
4 and the foundation pile 1 is constructed and connected to the footing B of the structure.
【0013】鋼管杭2とPC杭3、4との径はそれぞれ
略同じ大きさとなっており、鋼管杭2とPC杭3とは、
図1に示される如く鋼材から成る端部金物2A、3Aが
それぞれの端部に固着されており、鋼管杭2とPC杭3
とは、これらの端部金物2A、3A同士を溶接する等の
適宜の方法により接合されている。また、PC杭3とP
C杭4とは、それぞれの端部に予め設けられている端部
金物3B、4AによりPC杭を継ぎ足して基礎杭を構築
する従来の場合と同様の方法により接合されている。The diameters of the steel pipe pile 2 and the PC piles 3 and 4 are substantially the same, and the steel pipe pile 2 and the PC pile 3 are
As shown in FIG. 1, end metal parts 2A and 3A made of steel are fixed to the respective ends, and a steel pipe pile 2 and a PC pile 3 are provided.
Are joined by an appropriate method such as welding these end metal parts 2A, 3A to each other. Also, PC pile 3 and P
The C pile 4 is joined by a method similar to the conventional method of constructing a foundation pile by adding PC piles by the end metal fittings 3B and 4A provided in advance at the respective ends.
【0014】鋼管杭2は、腐食代も考慮に入れ必要とさ
れる耐力に見合った径寸法と厚さ寸法とを有するもので
あることが必要であることは勿論である。また、鋼管杭
2は、従来杭頭部に用いられている外殻鋼管付コンクリ
ート杭(SC杭)と異なり鋼板のみから形成されている
ため現場で切断することができるほか、SC杭と比べて
安価な部材である。It is needless to say that the steel pipe pile 2 needs to have a diameter dimension and a thickness dimension corresponding to the required yield strength in consideration of the corrosion allowance. Further, the steel pipe pile 2 can be cut at the site because it is made of only steel plates unlike the concrete pile with outer shell steel pipe (SC pile) that has been conventionally used for the pile head, and in comparison with SC piles. It is an inexpensive member.
【0015】基礎杭においては、一般的に、地上付近の
杭頭部に大きな水平力等が作用するため杭頭部には大き
な水平耐力等が要求されるが、基礎杭1においてはPC
杭3、4より許容応力の大きい鋼管杭2を杭頭部に用い
たため、地震時等に発生する地盤からの水平力等に対し
て強固な杭を構築することができる。In the foundation pile, generally, a large horizontal force or the like is applied to the pile head near the ground, so that the pile head is required to have a large horizontal proof strength.
Since the steel pipe pile 2 having a larger allowable stress than the piles 3 and 4 is used for the pile head, it is possible to construct a pile that is strong against horizontal force from the ground generated during an earthquake or the like.
【0016】また、鋼管杭2は施工現場において切断す
ることができるため、基礎杭1を打ち込み工法により打
ち込んでいき、PC杭4が設計時の想定より浅い深さ位
置で支持地盤G1に到達し、予定より早い段階で打ち込
みを終了させて杭頭部の切断を行う必要が生じても、施
工現場において杭頭部に用いた鋼管杭2を適宜の位置で
切断して基礎杭1を構造物を支えるのに最適な杭長とな
るよう調節することができる。Further, since the steel pipe pile 2 can be cut at the construction site, the foundation pile 1 is driven by the driving method, and the PC pile 4 reaches the supporting ground G1 at a depth position shallower than expected at the time of design. , Even if it is necessary to finish the driving at an earlier stage to cut the pile head, the steel pile 2 used for the pile head is cut at an appropriate position at the construction site to construct the foundation pile 1 as a structure. It can be adjusted to have the optimum pile length to support.
【0017】また、鋼管杭2とPC杭3、4とは略同径
のものとなっているため、鋼管杭2とPC杭3、及びP
C杭3とPC杭4との間で水平力の伝達に大きな段差が
生じずスムーズな伝達が行われ、基礎杭1全体として大
きな水平耐力を保持することができる。Further, since the steel pipe pile 2 and the PC piles 3 and 4 have substantially the same diameter, the steel pipe pile 2 and the PC pile 3 and P pile.
A large level difference does not occur in the transmission of the horizontal force between the C pile 3 and the PC pile 4, and smooth transmission is performed, and a large horizontal proof strength can be maintained as the entire foundation pile 1.
【0018】次に、基礎杭1を地盤に設置する場合の施
工手順の一例を説明する。基本的には従来の打ち込み工
法と同様に行うことができる。Next, an example of a construction procedure for installing the foundation pile 1 on the ground will be described. Basically, it can be performed in the same manner as the conventional driving method.
【0019】まず、PC杭4を地盤G上の所定の位置に
建て込み、ハンマー等でPC杭4に打撃を与えて地盤G
中に打ち込み、次いで端部金物4Aと、PC杭3の端部
金物3Bとを溶接又はネジ継手や圧着金物による接合等
という公知の方法により接合してPC杭3をPC杭4に
継ぎ足し、同様に打ち込む。次に鋼管杭2を端部金物2
A、3Aを用いて溶接等適宜の手段によりPC杭3に継
ぎ足して打ち込み、PC杭4の先端部を地盤G中の支持
地盤G1に到達させる。First, the PC pile 4 is built in a predetermined position on the ground G, and the PC pile 4 is hit with a hammer etc.
Then, the end metal fittings 4A and the end metal fittings 3B of the PC pile 3 are joined by a known method such as welding or joining with a screw joint or a crimp metal fitting to join the PC pile 3 to the PC pile 4 and the same. Drive into. Next, attach the steel pipe pile 2 to the end hardware 2
A and 3A are added to the PC pile 3 by an appropriate means such as welding and driven, and the tip end of the PC pile 4 reaches the support ground G1 in the ground G.
【0020】以上により、地盤Gの地上付近には鋼管杭
2を用い、それより下方部にはPC杭3、4を用いた基
礎杭1が地盤G中に構築される。As described above, the foundation pile 1 using the steel pipe pile 2 in the vicinity of the ground of the ground G and the PC piles 3 and 4 in the lower portion is constructed in the ground G.
【0021】上述の如く構築された基礎杭1は、全体的
に鋼管杭のみを用いた基礎杭を打設する場合と異なり、
先端支持力と周辺摩擦力とにより基礎杭1に大きな支持
力の発生を期待することができるため、市街地における
杭の設置工法として適しているプレボーリング工法によ
り地盤Gに設置することができる。なお、近年静的に杭
をねじ込む回転圧入工法が考案されてきているが、この
工法によれば、杭先端に羽状部材を設けて地盤を掘削し
ながら杭をねじ込んでいくため、羽状部材を取り付ける
等のための手間とコストがかかってしまう。The foundation pile 1 constructed as described above is different from the case where a foundation pile using only steel pipe piles is placed as a whole.
Since a large supporting force can be expected to be generated in the foundation pile 1 due to the tip supporting force and the peripheral frictional force, the foundation pile 1 can be installed on the ground G by a pre-boring method suitable as a method for installing the pile in the city area. A rotary press-fitting method of statically screwing the pile has been devised in recent years. According to this method, a wing-shaped member is provided at the tip of the pile and the pile is screwed while excavating the ground. It takes a lot of time and money to attach the parts.
【0022】次に、基礎杭1をプレボーリング工法によ
り地盤G中に設置する場合の施工手順の一例について説
明する。基本的には従来のプレボーリング工法により設
置する場合と同様に行うことができる。Next, an example of a construction procedure for installing the foundation pile 1 in the ground G by the preboring method will be described. Basically, it can be performed in the same manner as the case of installing by the conventional preboring method.
【0023】まずスイパイラルオーガー等の掘削装置を
使用して掘削孔Aを穿孔する。このとき、掘削装置の先
端よりセメントミルクを注入し掘削土砂と攪拌混合して
ソイルセメントとする。硬化材としてのソイルセメント
中にPC杭4を沈設していき、その上にPC杭3を接合
する。PC杭4とPC杭3とは、上述した打ち込み工法
の場合と同様、溶接等の公知の方法により連結されるの
で、ここでのこれ以上の詳しい説明は省略する。接合し
たPC杭3も掘削孔A中に沈設していき、その上に鋼管
杭2を接合する。PC杭3と鋼管杭2との接合は、それ
ぞれの端部に予め設けられている端部金物3A、2Aと
を用い、上述した打ち込み工法の場合と同様に溶接等適
宜の手段により接合される。鋼管杭2を所定の深さまで
沈設した後、ソイルセメントの硬化により、基礎杭1が
設置される。First, the excavation hole A is bored using an excavation device such as a swipe auger. At this time, cement milk is injected from the tip of the excavator and mixed with excavated earth and sand to obtain soil cement. The PC pile 4 is submerged in the soil cement as a hardening material, and the PC pile 3 is joined on it. Since the PC pile 4 and the PC pile 3 are connected by a known method such as welding as in the case of the driving method described above, further detailed description will be omitted here. The joined PC pile 3 is also sunk in the excavation hole A, and the steel pipe pile 2 is joined thereon. The PC pile 3 and the steel pipe pile 2 are joined to each other by appropriate means such as welding in the same manner as in the case of the driving method described above, using the end metal parts 3A and 2A provided in advance at the respective end portions. . After the steel pipe pile 2 is sunk to a predetermined depth, the foundation pile 1 is installed by hardening the soil cement.
【0024】なお、穿孔のための掘削装置や硬化材は一
例を挙げたものであり、上記のものに限定されない。It should be noted that the drilling device for punching and the hardening material are only examples and are not limited to the above.
【0025】本実施の形態では、既製コンクリート杭と
してPC杭を用いた場合について説明したが、これに限
定されることなく、地盤、水平支持力、鉛直支持力等に
応じてPC杭よりもコンクリート強度の小さい鉄筋コン
クリート杭(RC杭)や、PC杭よりもコンクリート強
度の大きい高強度プレストレストコンクリート杭(PH
C杭)を用いてもよい。In the present embodiment, the case where PC piles are used as ready-made concrete piles has been described, but the present invention is not limited to this, and concrete piles are more suitable than PC piles depending on the ground, horizontal bearing capacity, vertical bearing capacity, and the like. Reinforced concrete piles with low strength (RC piles) and high-strength prestressed concrete piles with greater concrete strength than PC piles (PH
C pile) may be used.
【0026】また、本実施の形態では、基礎杭1は2本
のPC杭3、4に1本の鋼管杭2を連結して形成されて
いるが、地盤G中の支持地盤G1の深さ位置等の地盤性
状や杭の各長さ位置において要求される支持力等に応じ
てPC杭と鋼管杭とをそれぞれ所要本数ずつ継ぎ足して
連結し打設してもよい。Further, in the present embodiment, the foundation pile 1 is formed by connecting one steel pipe pile 2 to two PC piles 3 and 4, but the depth of the supporting ground G1 in the ground G is reduced. Depending on the ground properties such as the position and the supporting force required at each length position of the pile, the required number of PC piles and steel pipe piles may be added and connected to each other.
【0027】図2は本発明の他の実施の形態を示す断面
図である。図2では、基礎杭1’がPC杭3’とPC杭
4’との間に鋼管杭2’を挟んで構成されている点と、
地盤G’が軟弱層GAと軟弱層GBとの間に硬質層GC
を挟むようにして構成されている点とにおいて、図1に
示した場合と異なっている。基礎杭1’は、構造物のフ
ーチングB’に連結されて構造物を支えている。FIG. 2 is a sectional view showing another embodiment of the present invention. In FIG. 2, the foundation pile 1'is configured by sandwiching the steel pipe pile 2'between the PC pile 3'and the PC pile 4 ', and
Ground G'is a hard layer GC between the soft layer GA and the soft layer GB.
It is different from the case shown in FIG. 1 in that it is configured so as to sandwich. The foundation pile 1'is connected to the footing B'of the structure to support the structure.
【0028】PC杭3’と鋼管杭2’、及び鋼管杭2’
とPC杭4’とは、それぞれの端部に予め設けられた端
部金物3A’と2A’、端部金物2B’と4A’とを図
1に示した鋼管杭2とPC杭3とを接合する場合と同様
の方法により継ぎ足して連結し、接合されている。PC pile 3'and steel pipe pile 2'and steel pipe pile 2 '
The PC pile 4'and the steel pile 2 and the PC pile 3 shown in FIG. 1 are the end metal fittings 3A 'and 2A' and the end metal fittings 2B 'and 4A' which are provided in advance at the respective ends. In the same manner as in the case of joining, they are joined and joined by joining.
【0029】地盤G’内において、軟弱層GAと硬質層
GCとの境界面10、及び硬質層GCと軟弱層GBとの
境界面11では、それぞれの面の上下におけるその土質
の違いにより地盤の剛性が大きく変化している。このた
め地震時等に各境界面10、11の上下では地盤の状態
が異なると想定され、この場合境界面10、11に接し
ている位置において基礎杭1’には非常に大きな水平力
等が発生する。水平耐力が大きく靱性が高い鋼管杭2’
をこのような2つの境界面10、11を通って接するよ
う基礎杭1’内に設置することにより構造物をしっかり
と支えることができるようにすることができる。In the ground G ′, the boundary surface 10 between the soft layer GA and the hard layer GC and the boundary surface 11 between the hard layer GC and the soft layer GB are different from each other due to the difference in the soil properties above and below each surface. The rigidity has changed significantly. Therefore, it is assumed that the ground condition is different between the upper and lower sides of the boundary surfaces 10 and 11 in the event of an earthquake, etc. In this case, a very large horizontal force is applied to the foundation pile 1'at a position in contact with the boundary surfaces 10 and 11. Occur. Steel pipe pile 2'with high horizontal yield strength and high toughness
Can be installed in the foundation pile 1 ′ so as to be in contact with each other through the two boundary surfaces 10 and 11 so that the structure can be firmly supported.
【0030】上述の如く、基礎杭1’によれば、地盤性
状に合わせて基礎杭1’のうちの所要の位置において鋼
管杭2’を既製コンクリート杭のPC杭3’、4’に連
結し、地盤の剛性が異なり基礎杭1’に大きな水平力等
がかかる部分に鋼管杭2’を対応させて使用することが
でき、図1で示した杭頭部に用いた場合と同様の効果を
期待することができる。As described above, according to the foundation pile 1 ', the steel pipe pile 2'is connected to the PC piles 3', 4'of ready-made concrete piles at the required positions of the foundation pile 1'according to the ground property. It is possible to use the steel pipe pile 2'corresponding to the part where the rigidity of the ground is different and a large horizontal force is applied to the foundation pile 1 ', and the same effect as when used for the pile head shown in Fig. 1 is obtained. Can be expected.
【0031】[0031]
【発明の効果】本発明によれば、上述の如く、基礎杭構
造において鋼管杭を基礎杭の所要の位置で既製コンクリ
ート杭に連結させ、これにより形成された基礎杭を各種
既製杭の設置工法により地盤に設置するようにしたの
で、既製コンクリート杭では耐えるのが困難な大きな応
力を要求される部分において、高価なSC杭ではなく、
SC杭より安価な鋼管杭を用いるため、基礎構築にかか
るコストを大幅に低減させることができる。According to the present invention, as described above, in the foundation pile structure, the steel pipe pile is connected to the ready-made concrete pile at the required position of the foundation pile, and the foundation pile thus formed is installed by various ready-made piles. Since it was installed on the ground by using, it is not an expensive SC pile in a part requiring a large stress that is difficult to withstand with ready-made concrete piles,
Since steel pipe piles, which are cheaper than SC piles, are used, the cost for foundation construction can be significantly reduced.
【0032】また、鋼管杭及び既製コンクリート杭は基
礎杭の施工現場において切断することができるので、杭
頭部にSC杭を用いる従来方法とは異なり、本発明の基
礎杭構造によれば打ち込み工法を採用することができ
る。Further, since steel pipe piles and ready-made concrete piles can be cut at the construction site of foundation piles, unlike the conventional method of using SC piles at the pile heads, the foundation pile structure of the present invention has a driving method. Can be adopted.
【0033】さらに、全体的に鋼管杭のみを用いた基礎
杭を打設する場合と異なり、本発明の構造による基礎杭
によれば先端支持力と周辺摩擦力とにより杭への大きな
支持力の発生を期待することができるため、市街地にお
ける基礎杭の設置工法として適しているプレボーリング
工法を用いて基礎杭の設置を行うことができる。すなわ
ち、本発明の構造による基礎杭は、鋼管杭でも既製コン
クリート杭でも既製杭の打設工法を用いて設置すること
ができ、その施工現場の環境や地盤の性状に適合した工
法により設置することができる。Further, unlike the case of placing a foundation pile using only steel pipe piles as a whole, according to the foundation pile having the structure of the present invention, a large bearing force is exerted on the pile due to the tip supporting force and the peripheral frictional force. Since it can be expected to occur, it is possible to install the foundation piles using the pre-boring method, which is suitable as the method for installing foundation piles in urban areas. That is, the foundation pile according to the structure of the present invention can be installed by using a construction method of a ready-made pile, whether it is a steel pipe pile or a ready-made concrete pile, and be installed by a method suitable for the environment of the construction site and the properties of the ground. You can
【0034】また、本発明の構造による基礎杭は、鋼管
杭を製造する鉄鋼メーカーと既製コンクリート杭を製造
する杭メーカーとの両メーカーが関わる領域の隙間を埋
めて利用するようにしたものということができる。Further, the foundation pile according to the structure of the present invention is designed to fill the gap in the region in which both the steel manufacturer producing steel pipe piles and the pile manufacturer producing ready-made concrete piles are used. You can
【図1】本発明の実施の形態の一例を示す断面図。FIG. 1 is a sectional view showing an example of an embodiment of the present invention.
【図2】本発明の他の実施の形態を示す断面図。FIG. 2 is a sectional view showing another embodiment of the present invention.
1、1’ 基礎杭 2、2’ 鋼管杭 3、3’、4、4’ PC杭 A 掘削孔 G 地盤 G1 支持地盤 GA 軟弱層 GB 軟弱層 GC 硬質層 1,1 'foundation pile 2,2 'steel pipe pile 3,3 ', 4,4' PC pile A drilling hole G ground G1 support ground GA soft layer GB Soft layer GC hard layer
Claims (2)
て、 鋼管杭と既製コンクリート杭とから基礎杭を形成し、前
記鋼管杭を前記基礎杭の所要の位置に用いたことを特徴
とする基礎杭構造。1. A foundation pile structure for supporting various structures, wherein a foundation pile is formed from steel pipe piles and ready-made concrete piles, and the steel pipe piles are used at required positions of the foundation piles. Foundation pile structure.
り設置される請求項1記載の基礎杭構造。2. The foundation pile structure according to claim 1, wherein the foundation pile is installed by a method of installing various ready-made piles.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002029159A JP2003232033A (en) | 2002-02-06 | 2002-02-06 | Foundation pile structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002029159A JP2003232033A (en) | 2002-02-06 | 2002-02-06 | Foundation pile structure |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2003232033A true JP2003232033A (en) | 2003-08-19 |
Family
ID=27773584
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002029159A Pending JP2003232033A (en) | 2002-02-06 | 2002-02-06 | Foundation pile structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2003232033A (en) |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007107200A (en) * | 2005-10-11 | 2007-04-26 | Kanto Gakuin | How to install ready-made piles for heat exchange, how to build ready-made piles for heat exchange, and ready-made piles for bottom |
JP2009097261A (en) * | 2007-10-18 | 2009-05-07 | Sumitomo Metal Ind Ltd | Foundation pile structure, prefabricated concrete pile, and joint hardware for prefabricated concrete pile and steel pipe pile |
WO2014115235A1 (en) * | 2013-01-22 | 2014-07-31 | 株式会社オーク | Method for inhibiting propagation of vibration |
CN105220714A (en) * | 2015-09-09 | 2016-01-06 | 杭州江润科技有限公司 | Core compound prestress pile tube float Structure construction method filled with by built-in anchor cable |
JP2016041893A (en) * | 2014-08-19 | 2016-03-31 | 株式会社Ihi | Pile foundation and pile foundation construction method |
CN106801428A (en) * | 2017-01-16 | 2017-06-06 | 青岛中天斯壮科技有限公司 | Reinforced tensile-shear PHC pipe pile foundation structure and construction method thereof |
JP2017106214A (en) * | 2015-12-09 | 2017-06-15 | 前田建設工業株式会社 | Existing pile |
JP2017223066A (en) * | 2016-06-16 | 2017-12-21 | 株式会社オーク | Pile construction management method |
JP2018091132A (en) * | 2018-02-14 | 2018-06-14 | 株式会社オーク | Pile construction management method |
CN110700103A (en) * | 2019-10-16 | 2020-01-17 | 中铁工程服务有限公司 | Construction method of continuous composite beam |
JP2020020262A (en) * | 2019-11-11 | 2020-02-06 | 前田建設工業株式会社 | Existing pile |
CN114809027A (en) * | 2022-04-20 | 2022-07-29 | 中国建筑土木建设有限公司 | Construction method of volcanic ash underground pile foundation |
KR20220135437A (en) * | 2021-03-30 | 2022-10-07 | 송성민 | Compoisite phc pile and construction method thereof |
CN115369867A (en) * | 2022-08-18 | 2022-11-22 | 广州市第二建筑工程有限公司 | BIM-based lead hole pile sinking construction method |
KR20230168118A (en) * | 2022-06-03 | 2023-12-12 | 대영스틸산업주식회사 | Precast Composite Pile Structure and its Construction Method |
-
2002
- 2002-02-06 JP JP2002029159A patent/JP2003232033A/en active Pending
Cited By (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007107200A (en) * | 2005-10-11 | 2007-04-26 | Kanto Gakuin | How to install ready-made piles for heat exchange, how to build ready-made piles for heat exchange, and ready-made piles for bottom |
JP2009097261A (en) * | 2007-10-18 | 2009-05-07 | Sumitomo Metal Ind Ltd | Foundation pile structure, prefabricated concrete pile, and joint hardware for prefabricated concrete pile and steel pipe pile |
WO2014115235A1 (en) * | 2013-01-22 | 2014-07-31 | 株式会社オーク | Method for inhibiting propagation of vibration |
JPWO2014115235A1 (en) * | 2013-01-22 | 2017-01-19 | 株式会社オーク | Vibration propagation prevention method |
JP2016041893A (en) * | 2014-08-19 | 2016-03-31 | 株式会社Ihi | Pile foundation and pile foundation construction method |
CN105220714A (en) * | 2015-09-09 | 2016-01-06 | 杭州江润科技有限公司 | Core compound prestress pile tube float Structure construction method filled with by built-in anchor cable |
JP2017106214A (en) * | 2015-12-09 | 2017-06-15 | 前田建設工業株式会社 | Existing pile |
JP2017223066A (en) * | 2016-06-16 | 2017-12-21 | 株式会社オーク | Pile construction management method |
CN106801428A (en) * | 2017-01-16 | 2017-06-06 | 青岛中天斯壮科技有限公司 | Reinforced tensile-shear PHC pipe pile foundation structure and construction method thereof |
CN106801428B (en) * | 2017-01-16 | 2018-11-20 | 青岛中天斯壮科技有限公司 | Reinforced tensile-shear PHC pipe pile foundation structure and construction method thereof |
JP2018091132A (en) * | 2018-02-14 | 2018-06-14 | 株式会社オーク | Pile construction management method |
CN110700103A (en) * | 2019-10-16 | 2020-01-17 | 中铁工程服务有限公司 | Construction method of continuous composite beam |
JP2020020262A (en) * | 2019-11-11 | 2020-02-06 | 前田建設工業株式会社 | Existing pile |
KR20220135437A (en) * | 2021-03-30 | 2022-10-07 | 송성민 | Compoisite phc pile and construction method thereof |
KR102574831B1 (en) * | 2021-03-30 | 2023-09-06 | 송성민 | Compoisite phc pile and construction method thereof |
CN114809027A (en) * | 2022-04-20 | 2022-07-29 | 中国建筑土木建设有限公司 | Construction method of volcanic ash underground pile foundation |
KR20230168118A (en) * | 2022-06-03 | 2023-12-12 | 대영스틸산업주식회사 | Precast Composite Pile Structure and its Construction Method |
KR102629212B1 (en) * | 2022-06-03 | 2024-01-25 | 대영스틸산업주식회사 | Precast Composite Pile Structure and its Construction Method |
CN115369867A (en) * | 2022-08-18 | 2022-11-22 | 广州市第二建筑工程有限公司 | BIM-based lead hole pile sinking construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20060185279A1 (en) | Foundations for constructions | |
KR100788623B1 (en) | Top-down method using precast-concrete colum | |
JP2003232033A (en) | Foundation pile structure | |
JP2018024982A (en) | Reinforcement method and reinforcement structure of existing pile foundation | |
JP3071402B2 (en) | Lifting method of structure, jack engaging structure and bracket used in the method | |
JP4771244B2 (en) | Connection joint between steel pipe pile and concrete pile, connection pile structure between steel pipe pile and concrete pile, construction method of connection pile between steel pipe pile and concrete pile | |
KR20060092552A (en) | The non-strut down framework construction method of having used cast in place concrete pile | |
JP6847899B2 (en) | Ring-shaped tip hardware | |
KR101144312B1 (en) | Steel pipe pile equipped with base enlargement device and the construction method | |
JP4373824B2 (en) | Joining method of cast-in-place pile and steel pipe column | |
JP5456627B2 (en) | Connection structure and method of connection between pile and steel column | |
JP2002004271A (en) | Composite pile and its construction method | |
KR101124203B1 (en) | Pile structure | |
JP5077865B2 (en) | Ready-made pile and foundation pile structure | |
JP4329068B2 (en) | Yamauchi composite wall and method for constructing Yamauchi composite wall | |
CN114482071A (en) | Device for improving rock-socketed depth of large-diameter cast-in-place pile | |
JP2009162034A (en) | Method of constructing foundation of structure | |
JP4475116B2 (en) | Vertical shaft structure and its construction method | |
JP2001182053A (en) | Underground aseismatic reinforcing pile and foundation aseismatic structure | |
CN219280687U (en) | Device for repairing broken damage of pile foundation of wharf and pile foundation structure of high-pile wharf | |
JP6093458B1 (en) | Construction method of subsidence structure | |
JP3681990B2 (en) | Propulsion shaft structure | |
JP5267242B2 (en) | Pier foundation structure and bridge pier foundation construction method | |
JP2005083149A (en) | Reinforcement method for foundation and reinforcement structure of foundation | |
JP5439918B2 (en) | Pier foundation structure and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20041105 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20061201 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20061212 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070213 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070410 |
|
A02 | Decision of refusal |
Effective date: 20071002 Free format text: JAPANESE INTERMEDIATE CODE: A02 |