JP7428170B2 - bridge - Google Patents

bridge Download PDF

Info

Publication number
JP7428170B2
JP7428170B2 JP2021133906A JP2021133906A JP7428170B2 JP 7428170 B2 JP7428170 B2 JP 7428170B2 JP 2021133906 A JP2021133906 A JP 2021133906A JP 2021133906 A JP2021133906 A JP 2021133906A JP 7428170 B2 JP7428170 B2 JP 7428170B2
Authority
JP
Japan
Prior art keywords
girder
bridge
concrete
section
steel material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2021133906A
Other languages
Japanese (ja)
Other versions
JP2023028291A (en
Inventor
辰雄 坪倉
誠道 大場
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2021133906A priority Critical patent/JP7428170B2/en
Publication of JP2023028291A publication Critical patent/JP2023028291A/en
Application granted granted Critical
Publication of JP7428170B2 publication Critical patent/JP7428170B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

本発明は、橋梁に関する。 The present invention relates to bridges.

橋梁をプレストレストコンクリート構造として施工することが従来から行われている(特許文献1)。 BACKGROUND ART Bridges have traditionally been constructed as prestressed concrete structures (Patent Document 1).

特開2006-348656号公報Japanese Patent Application Publication No. 2006-348656

土木学会 コンクリート委員会 超高強度繊維補強コンクリート研究小委員会編、「超高強度繊維補強コンクリートの設計・施工指針(案)」、社団法人 土木学会、平成16年9月28日発行Japan Society of Civil Engineers, Concrete Committee, Super High Strength Fiber Reinforced Concrete Research Subcommittee, ed., "Design and Construction Guidelines for Ultra High Strength Fiber Reinforced Concrete (Draft)", Japan Society of Civil Engineers, published September 28, 2004.

従来技術では、コンクートに加えた圧縮応力が、プレストレスの導入に伴う不静定力(二次力ともいう)によって減少する場合がある。この結果、コンクリートに十分な圧縮応力が与えられず、必要な性能を得られなくなる虞があった。 In the prior art, the compressive stress applied to the concrete may be reduced by an unsteady force (also referred to as a secondary force) accompanying the introduction of prestress. As a result, sufficient compressive stress may not be applied to the concrete, and there is a possibility that the required performance may not be obtained.

上記課題を解決するため、本発明は一態様として、橋軸方向に延びる、コンクリート断面を持つプレキャストコンクリート構造の桁であって、前記コンクリート断面に対してプレテンション方式で圧縮応力を与える1次鋼材と、前記コンクリート断面に対してポストテンション方式で前記圧縮応力を増加させる2次鋼材と、を有する桁を備える、橋梁を提供する。 In order to solve the above problems, one aspect of the present invention is a girder of a precast concrete structure that extends in the axial direction of a bridge and has a concrete cross section, the primary steel material applying compressive stress to the concrete cross section in a pre-tensioning manner. and a secondary steel material that increases the compressive stress in a post-tensioning manner with respect to the concrete cross section.

また、本発明は一態様として、橋軸方向に延びる、コンクリート断面を持つプレキャストコンクリート構造の桁の施工方法であって、1次鋼材を用いて前記コンクリート断面に対してプレテンション方式で圧縮応力を与える工程と、2次鋼材を用いて前記コンクリート断面に対してポストテンション方式で前記圧縮応力を増加させる工程と、を有する施工方法を提供する。 Another aspect of the present invention is a method for constructing a girder of a precast concrete structure that extends in the axial direction of a bridge and has a concrete cross section, wherein compressive stress is applied to the concrete cross section using a pretension method using a primary steel material. and a step of increasing the compressive stress on the concrete cross section using a secondary steel material in a post-tensioning manner.

本発明によれば、高い性能を持つ橋梁を提供することができる。 According to the present invention, a bridge with high performance can be provided.

実施形態における橋梁の斜視図と一部拡大図である。They are a perspective view and a partially enlarged view of a bridge in an embodiment. 実施形態による橋梁の上面図あり、桁のセグメント配置を示す。1 is a top view of a bridge according to an embodiment, showing the girder segment arrangement; FIG. 実施形態における橋梁の断面図である。なお、支間中央断面においては、配筋を図示している。It is a sectional view of the bridge in an embodiment. Note that the reinforcement arrangement is shown in the cross section at the center of the span. 実施形態による拡幅部施工工程のフローである。It is a flow of a widening part construction process according to an embodiment. 実施形態におけるプレキャスト部材の施工状態を示す図であり、(a)中央部のセグメント、(b)端部のセグメント、及び(c)床版を示す。なお、左側に側面図を、右側に断面図を示す。It is a figure showing the construction state of the precast member in an embodiment, and shows (a) a center segment, (b) an end segment, and (c) a floor slab. Note that a side view is shown on the left, and a cross-sectional view is shown on the right. 実施形態における拡幅部の施工状況を示す図であり、(a)端部のセグメント設置、(b)中央部セグメント設置、(c)床版固定、及び(d)c図におけるd枠の拡大図を示す。It is a figure which shows the construction situation of the widening part in embodiment, (a) end segment installation, (b) central part segment installation, (c) floor slab fixing, and (d) enlarged view of d frame in figure c. shows. (a)実施形態及び(b)先行文献における、桁断面にかかる圧縮応力を比較する図である。It is a figure which compares the compressive stress applied to the girder cross section in (a) embodiment and (b) prior literature. 変形例における桁の断面図であり、桁に設置されたシース及び2次鋼材の形状を示す。It is a sectional view of a girder in a modification, and shows the shape of the sheath and secondary steel material installed in the girder.

<概要>
本発明の実施形態である橋梁1を、以下に説明する。橋梁1は、少なくとも一部においてプレストレストコンクリート構造を有する。なお、以下の説明では、橋梁1が延びる方向を橋軸方向とし、これに直交する方向を橋軸直角方向とする。
<Summary>
A bridge 1 that is an embodiment of the present invention will be described below. The bridge 1 has a prestressed concrete structure at least in part. In addition, in the following description, the direction in which the bridge 1 extends is assumed to be the bridge axis direction, and the direction orthogonal to this is assumed to be the bridge axis perpendicular direction.

橋梁1は、最も古く施工された既設部2、次に施工された既設部3、及び、既設部2と既設部3との間に構築された拡幅部4を主に備える。既設部2、既設部3、及び拡幅部4は、いずれも橋軸方向に延びる。 The bridge 1 mainly includes an existing section 2 that was constructed the oldest, an existing section 3 that was constructed next, and a widened section 4 constructed between the existing section 2 and the existing section 3. The existing portion 2, the existing portion 3, and the widened portion 4 all extend in the bridge axis direction.

既設部2は、桁21と、桁21の上面に形成された平板状の床版22と、桁21を支持する橋脚23と、を備える。 The existing part 2 includes a girder 21, a flat slab 22 formed on the upper surface of the girder 21, and a pier 23 that supports the girder 21.

既設部3は、既設部2と同様に、桁31と、桁31の上面に形成された平板状の床版32と、桁31を支持する橋脚33と、を備える。 Like the existing part 2, the existing part 3 includes a girder 31, a flat slab 32 formed on the upper surface of the girder 31, and a pier 33 that supports the girder 31.

拡幅部4は、既設部2及び既設部3それぞれに対して接合され、既設部2及び既設部3を拡幅する橋梁として機能する。拡幅部4は、図1~4、図5、6に示すように中空断面を有する橋梁であり、U字型の断面を持つ桁41、床版42、縦接合部43、横接合部44、及び、桁41を支持する橋脚45を備える。 The widening part 4 is joined to the existing part 2 and the existing part 3, and functions as a bridge that widens the existing part 2 and the existing part 3. The widening section 4 is a bridge having a hollow cross section as shown in FIGS. 1 to 4, FIGS. It also includes a pier 45 that supports the girder 41.

桁41は、同断面形状の、プレキャストコンクリート構造を持つ複数のセグメントを橋軸方向に接合することによって形成される。桁41は、橋脚45の間、すなわち支間の中央部に位置するセグメント41Aと、支点近傍に位置するセグメント41Bとを備える。セグメント41Bは、橋脚45に支持されるセグメントであり、セグメント41Aは、2つのセグメント41Bの間に固定される(図2、図3、図6)。桁41(つまりセグメント41A、41B)の断面は、図心線41Cを規定する。 The girder 41 is formed by joining a plurality of segments having the same cross-sectional shape and a precast concrete structure in the bridge axis direction. The girder 41 includes a segment 41A located between the piers 45, that is, at the center of the span, and a segment 41B located near the fulcrum. Segment 41B is a segment supported by pier 45, and segment 41A is fixed between two segments 41B (FIGS. 2, 3, and 6). The cross section of the girder 41 (ie, segments 41A, 41B) defines a centroid line 41C.

セグメント41A、41Bは、それぞれ、コンクリート部411、シース412、1次鋼材413、2次鋼材414、及びアンカー415を備える(図3、図5)。コンクリート部411には、主筋及び用心鉄筋等の配筋が施されている。 The segments 41A and 41B each include a concrete portion 411, a sheath 412, a primary steel material 413, a secondary steel material 414, and an anchor 415 (FIGS. 3 and 5). The concrete part 411 is provided with reinforcement such as main reinforcement and safety reinforcement.

シース412は、2次鋼材414を内部に通す、略橋軸方向に延びる管であり、コンクリート部411に埋設される(図3、図5)。シース412は、セグメント41A、41Bの橋軸直角方向断面において、断面の図心位置にほぼ一致するように設置される。本実施形態では、シース412は複数箇所に設置されるが、この場合、シース412全体での図心は、桁41(つまりセグメント41A、41B)の断面における図心線41C上に位置する。 The sheath 412 is a pipe extending substantially in the axial direction of the bridge, through which the secondary steel material 414 passes, and is buried in the concrete portion 411 (FIGS. 3 and 5). The sheath 412 is installed in a cross section of the segments 41A and 41B in a direction perpendicular to the bridge axis so as to substantially coincide with the centroid position of the cross section. In this embodiment, the sheath 412 is installed at multiple locations, but in this case, the centroid of the entire sheath 412 is located on the centroid line 41C in the cross section of the girder 41 (that is, the segments 41A, 41B).

コンクリート部411の上部には、アンカー415の下部が固定される(図3)。アンカー415には様々な部材が用いられる。例えば、アンカー415として頭付きアンカーボルトが採用され得る。アンカー415の上部は、床版42に固定される。このようにアンカー415を介して、床版42と桁41は接合される。 The lower part of the anchor 415 is fixed to the upper part of the concrete part 411 (FIG. 3). Various members are used for the anchor 415. For example, a headed anchor bolt may be employed as the anchor 415. The upper part of the anchor 415 is fixed to the floor slab 42. In this way, the floor slab 42 and the girder 41 are joined via the anchors 415.

1次鋼材413は、略橋軸方向に延び、プレテンション方式によるプレストレスをコンクリート部411の断面(以下、コンクリート断面と称する)に付与する鋼材である。なお、図3においては1次鋼材413を黒丸で示す。1次鋼材413には張力が加えられており、1次鋼材413はコンクリート部411との付着を介して、コンクリート部411に圧縮応力を付加する。 The primary steel material 413 is a steel material that extends approximately in the axial direction of the bridge and applies prestress using a pretension method to a cross section of the concrete portion 411 (hereinafter referred to as a concrete cross section). In addition, in FIG. 3, the primary steel material 413 is indicated by a black circle. Tension is applied to the primary steel material 413, and the primary steel material 413 applies compressive stress to the concrete portion 411 through its adhesion to the concrete portion 411.

1次鋼材413は、セグメント41Aの下部に配置され、セグメント41Bにおいては部材の上部に配置される(図2、図3、図6)。正の曲げモーメント(部材下側に引張応力を生じさせる曲げモーメント)がかかるセグメント41Aと、その逆の負の曲げモーメントがかかるセグメント41Bとでその配置位置を変えることで、1次鋼材413は、コンクリート部411の適切な位置に圧縮応力を加えている。なお、図5では1次鋼材413を一部省略して示している。 The primary steel material 413 is placed at the bottom of the segment 41A, and at the top of the member in the segment 41B (FIGS. 2, 3, and 6). By changing the arrangement position of the segment 41A to which a positive bending moment (bending moment that produces tensile stress on the lower side of the member) is applied and the segment 41B to which a negative bending moment is applied, the primary steel material 413 is Compressive stress is applied to the concrete portion 411 at an appropriate position. In addition, in FIG. 5, the primary steel material 413 is partially omitted.

2次鋼材414は、1本ずつシース412に挿入され、張力が掛けられた状態で桁41に固定される。それぞれの2次鋼材414は、2つの橋脚45にまたがって、すなわち1つの支間に亘って連続して設置される。2次鋼材414の両端部は、セグメント41Bの端部に固定される。2次鋼材414の配置は、シース412とほぼ同じである。つまり、2次鋼材414は、それぞれ略橋軸方向に延びるように直線状に配置される。また、断面で見たとき、2次鋼材414全体での図心は、セグメント41A、41Bの図心線41C上に位置する(図3、図5)。換言すれば、2次鋼材414は、セグメント41A、41Bの断面図心線41Cに対して略対称となるように配置される。このため、2次鋼材414全体での張力中心は、概して図心線41C上に位置する。 The secondary steel materials 414 are inserted into the sheath 412 one by one and fixed to the girder 41 under tension. Each secondary steel material 414 is installed continuously across two piers 45, that is, over one span. Both ends of the secondary steel material 414 are fixed to the ends of the segment 41B. The arrangement of the secondary steel material 414 is almost the same as that of the sheath 412. In other words, the secondary steel materials 414 are arranged linearly so as to extend substantially in the bridge axis direction. Furthermore, when viewed in cross section, the centroid of the entire secondary steel material 414 is located on the centroid line 41C of the segments 41A and 41B (FIGS. 3 and 5). In other words, the secondary steel material 414 is arranged so as to be substantially symmetrical with respect to the cross-sectional center line 41C of the segments 41A and 41B. Therefore, the center of tension in the entire secondary steel material 414 is generally located on the centroid line 41C.

加えて、セグメント41A、41Bのそれぞれの端部には、接合キー416が設けられる(図5)。接合キー416は、セグメント41A及びセグメント41Bを接合し、せん断力及び橋軸方向圧縮力を両セグメント間に伝達する。接合キー416の構造は、設計条件に応じて適宜選択される。したがって、接合キー416は鋼製であってもよいが、本実施形態ではコンクリート製接合キーが用いられるものとする。セグメント41A、41Bの間(すなわち対向する接合キー416の間)は、必要に応じて無収縮モルタルによって間詰めされる。 In addition, a joining key 416 is provided at each end of segments 41A, 41B (FIG. 5). Joining key 416 joins segment 41A and segment 41B, and transmits shear force and bridge axial direction compressive force between both segments. The structure of the joining key 416 is appropriately selected depending on design conditions. Therefore, the joint key 416 may be made of steel, but in this embodiment, a concrete joint key is used. The space between the segments 41A and 41B (that is, between the opposing joint keys 416) is filled with non-shrinkage mortar as necessary.

床版42は、平板状に形成されたプレキャストコンクリート部材であり、桁41の上面にアンカー415を介して固定される(図3、図5、図6)。床版42は、プレテンション方式によるプレストレストコンクリート構造を有する。床版42の部材断面には、PC鋼材である鋼材421によって、圧縮応力が加えられている。鋼材421は、床版42の断面に対してほぼ一様な圧縮応力を付与できるように配置される。なお、図5では1次鋼材413の位置、本数などを簡略に示している。 The floor slab 42 is a precast concrete member formed into a flat plate shape, and is fixed to the upper surface of the girder 41 via anchors 415 (FIGS. 3, 5, and 6). The floor slab 42 has a prestressed concrete structure using a pretension method. A compressive stress is applied to the cross section of the floor slab 42 by a steel material 421 that is a prestressing steel material. The steel material 421 is arranged so as to be able to apply substantially uniform compressive stress to the cross section of the deck slab 42. In addition, in FIG. 5, the position, number, etc. of the primary steel materials 413 are simply shown.

縦接合部43は、床版22と床版42との間、及び床版32と床版42との間において、橋軸方向に延びるように形成される。図1及び図2に示すように、縦接合部43は、床版22と床版42の橋軸直角方向端部とを接合し、また、床版32と床版42の橋軸直角方向端部とを接合する。縦接合部43は、配筋431及びコンクリート部432によって形成された鉄筋コンクリート部材である。 The vertical joint portion 43 is formed between the floor slab 22 and the floor slab 42 and between the floor slab 32 and the floor slab 42 so as to extend in the bridge axis direction. As shown in FIGS. 1 and 2, the vertical joint portion 43 joins the ends of the deck slab 22 and the deck slab 42 in the direction perpendicular to the bridge axis, and also connects the ends of the deck slab 32 and the deck slab 42 in the direction perpendicular to the bridge axis. join the parts. The vertical joint portion 43 is a reinforced concrete member formed by reinforcement 431 and a concrete portion 432.

配筋431は、少なくとも、床版22の端部及び床版42の端部それぞれから、橋軸直角方向に突出して定着を取る鉄筋を複数本備える(図3)。 The reinforcement arrangement 431 includes a plurality of reinforcing bars that protrude from at least the ends of the deck slab 22 and the ends of the deck slab 42 in the direction perpendicular to the bridge axis to provide anchorage (FIG. 3).

コンクリート部432は、繊維補強コンクリート、特に超高強度繊維補強コンクリート(UFC)造とすることが望ましい。UFCは様々な特性を持つ材料であるが、非特許文献1では、UFCの引張強度を5N/mm2以上と規定している。 The concrete portion 432 is preferably made of fiber-reinforced concrete, particularly ultra-high strength fiber-reinforced concrete (UFC). Although UFC is a material with various properties, Non-Patent Document 1 specifies that the tensile strength of UFC is 5 N/mm 2 or more.

このように高い引張強度を有する材料であるため、コンクリート部432にUFCを用いる場合、他のコンクリート材料に比較して、配筋431の定着長さを短くすることが可能である。定着長さを短くすることで、縦接合部43の幅を短くし、工事の施工範囲を小さくすることができる。 Because it is a material with such high tensile strength, when UFC is used for the concrete portion 432, it is possible to shorten the anchorage length of the reinforcement 431 compared to other concrete materials. By shortening the anchoring length, the width of the vertical joint portion 43 can be shortened, and the construction range of the construction work can be reduced.

施工範囲を小さくすることによって、工事の中断及び復旧、また、交通の開放が容易となる。例えば工期が複数日にまたがる場合などにおいて、工事休止中の交通を可能とする場合がある。この場合、施工範囲に仮舗装を実施し、または施工範囲を敷鉄板で覆うことによって、工事休止中における車両等の通行を可能とすることが一般的である。施工範囲が小さければ、仮舗装または鉄板敷設を行う範囲も小さくすることができ、工事休止のための準備、工事復旧にかかる作業も少なくすることができる。そのため、工期の短縮やコストの削減が可能となる。 By reducing the construction area, it will be easier to suspend and restore the construction work, and to open it to traffic. For example, in cases where the construction period spans multiple days, traffic may be allowed during the suspension of construction. In this case, it is common to temporarily pave the construction area or cover the construction area with iron plates to allow vehicles and the like to pass during the suspension of construction. If the construction area is small, the area for temporary paving or laying of iron plates can be made smaller, and the work required for preparation for construction suspension and construction restoration can also be reduced. Therefore, it is possible to shorten the construction period and reduce costs.

横接合部44は、床版42の間において、略橋軸直角方向に延びるように形成される。横接合部44は、図1に示すように、床版42同士を橋軸方向に接合する機能を有する。横接合部44は、配筋441及びコンクリート部442によって形成された鉄筋コンクリート部材である(図6(d))。 The lateral joint portion 44 is formed between the deck slabs 42 so as to extend approximately in a direction perpendicular to the bridge axis. As shown in FIG. 1, the lateral joint portion 44 has a function of joining the deck slabs 42 together in the bridge axis direction. The horizontal joint portion 44 is a reinforced concrete member formed by reinforcement 441 and a concrete portion 442 (FIG. 6(d)).

横接合部44は、図1及び図6(c)に示すように、セグメント41A、41Bの接合位置とは異なる位置に設けられる。横接合部44の位置をセグメント41A、41Bの接合位置から橋軸方向にずらすことにより、横接合部44に過大なひずみが発生することが回避される。これは、横接合部44にひびが発生するなどの不具合を防止し、橋梁1の品質維持に貢献する。 As shown in FIGS. 1 and 6(c), the horizontal joint portion 44 is provided at a position different from the joint position of the segments 41A and 41B. By shifting the position of the lateral joint 44 in the bridge axis direction from the joining position of the segments 41A, 41B, excessive strain can be avoided from occurring in the lateral joint 44. This prevents problems such as cracks occurring in the lateral joints 44 and contributes to maintaining the quality of the bridge 1.

配筋441は、少なくとも、床版42から橋軸方向に突出して定着を取る鉄筋またはアンカーを複数本備える。 The reinforcing bars 441 include at least a plurality of reinforcing bars or anchors that protrude from the deck slab 42 in the bridge axis direction to take anchor.

コンクリート部442は、繊維補強コンクリート、特にUFC造とすることが望ましい。UFCを用いることにより、縦接合部43と同様、配筋441の定着長さを短くし、横接合部44の幅及び施工範囲を小さくすることができる。その結果、縦接合部43の説明として上述したように、工期短縮等の様々な効果が得られる。 The concrete portion 442 is preferably made of fiber-reinforced concrete, particularly UFC construction. By using UFC, the anchoring length of the reinforcement 441 can be shortened, and the width and construction range of the horizontal joint 44 can be reduced, similarly to the vertical joint 43. As a result, as described above for the vertical joint portion 43, various effects such as shortening the construction period can be obtained.

橋脚45は、桁41を支持する部材である。橋脚45は、図2に示すように、橋脚23、33とは独立して設置されており、設置位置及び橋脚間距離のいずれについても、橋脚23、33とは必ずしも一致しない。橋脚45による桁41の支持方法及び支点の形状は、例えば剛接合や、支承を介したピン、ローラー、ヒンジ支持など、条件に応じて適宜選択される。 The pier 45 is a member that supports the girder 41. As shown in FIG. 2, the piers 45 are installed independently of the piers 23 and 33, and do not necessarily match the piers 23 and 33 both in installation position and distance between the piers. The method of supporting the girder 41 by the pier 45 and the shape of the fulcrum are appropriately selected depending on the conditions, such as rigid connection, pin, roller, or hinge support via a support, for example.

<工程>
上記のように構成される拡幅部4について、施工手順を以下に説明する。施工手順は、図4に示すように、S1からS7の工程によって構成される。
<Process>
The construction procedure for the widened portion 4 configured as described above will be explained below. The construction procedure is comprised of steps S1 to S7, as shown in FIG.

〔桁、床版製作〕
まず、セグメント41A、41B、及び床版42が製作される(S1)。製作は、製造設備の整った工場、または、これと同等の施工条件を持ったヤードで実行される。セグメント41A、41B、及び床版42は、図5に示すように、いずれもプレテンション方式によるプレキャストコンクリート部材として製作される。
[Girder, floor slab production]
First, the segments 41A, 41B and the floor slab 42 are manufactured (S1). Fabrication is carried out in a factory equipped with manufacturing equipment or in a yard with equivalent construction conditions. As shown in FIG. 5, the segments 41A, 41B and the floor slab 42 are all manufactured as precast concrete members using a pretension method.

セグメント41A、41Bの製作では、1次鋼材413及びシース412が設計上の位置に配置され、さらに1次鋼材413にジャッキ等の装置を用いて張力を掛けた状態のまま、コンクリートが打設される(図5(a)、図5(b))。床版42の製作においても同様に、鋼材421に張力を掛けた状態で、コンクリートが打設される(図5(c))。 In manufacturing the segments 41A and 41B, the primary steel material 413 and sheath 412 are placed at the designed positions, and concrete is poured while the primary steel material 413 is kept under tension using a device such as a jack. (Fig. 5(a), Fig. 5(b)). Similarly, in manufacturing the floor slab 42, concrete is poured while tension is applied to the steel material 421 (FIG. 5(c)).

コンクリートの強度発現後、1次鋼材413に掛けられた張力が解放されるが、その後も3~6か月程度の養生期間が設けられる(S2)。養生期間を設けることにより、コンクリートのクリープまたは乾燥収縮によるひずみの進展が収束する。 After the concrete develops strength, the tension applied to the primary steel material 413 is released, but a curing period of approximately 3 to 6 months is provided thereafter (S2). By providing a curing period, the development of strain due to concrete creep or drying shrinkage is brought to an end.

〔現場での施工〕
セグメント41A、41B及び床版42の製作後、または製作と並行して、現場での拡幅部4の施工が進められる。
[Construction on site]
After or in parallel with the fabrication of the segments 41A, 41B and the floor slab 42, the construction of the widened portion 4 is proceeded on-site.

まずセグメント41Bが橋脚45上に設置され(S3、図6(a))、次にセグメント41Aが、セグメント41Bの間に設置される(S4、図6(b))。 First, the segments 41B are installed on the pier 45 (S3, FIG. 6(a)), and then the segments 41A are installed between the segments 41B (S4, FIG. 6(b)).

次に2次鋼材の緊張が実施される(S5)。支保工などに支持させることにより、セグメント41Aが設計上定められた位置に配置された後、シース412の中に2次鋼材414が挿入される。2次鋼材414は、複数のセグメント41A、41Bにまたがって、1つの支間で連続するように配置される(図6(b))。挿入完了後、ジャッキ等の装置により2次鋼材414に対して張力が掛けられ、2次鋼材414端部のセグメント41Bへの固定と、シース412へのグラウト注入が実施される。さらに必要に応じて、セグメント41A、41Bの間に間詰めが実施される。セグメント41Aの設置が完了すると、セグメント41Aを支持していた支保工が取り外される。 Next, tensioning of the secondary steel material is performed (S5). After the segment 41A is placed in a designed position by supporting it with a support or the like, the secondary steel material 414 is inserted into the sheath 412. The secondary steel material 414 is arranged so as to span the plurality of segments 41A and 41B and to be continuous in one span (FIG. 6(b)). After the insertion is completed, tension is applied to the secondary steel material 414 by a device such as a jack, and the end of the secondary steel material 414 is fixed to the segment 41B and grout is injected into the sheath 412. Furthermore, if necessary, spacing is performed between the segments 41A and 41B. When the installation of the segment 41A is completed, the shoring that supported the segment 41A is removed.

次に床版42が桁41に接合される(S6)。床版42は、アンカー415を介して桁41の上部に固定される。さらに、床版42の間にUFCが打設されることにより、横接合部44が形成される(図6(c)、(d))。横接合部44により、橋軸方向に隣接する床版42が互いに接合される。 Next, the floor slab 42 is joined to the girder 41 (S6). The floor slab 42 is fixed to the upper part of the girder 41 via anchors 415. Further, by placing UFC between the floor slabs 42, a lateral joint 44 is formed (FIGS. 6(c) and 6(d)). The horizontal joints 44 join the deck slabs 42 adjacent in the bridge axis direction to each other.

さらに、床版42の橋軸直角方向端部と、床版22、32との間にUFCが打設され、縦接合部43が形成される(S7)。縦接合部43により、床版42と床版22、及び、床版42と床版32がそれぞれ剛接合される。 Further, a UFC is placed between the end of the deck slab 42 in the direction perpendicular to the bridge axis and the deck slabs 22, 32, and a vertical joint 43 is formed (S7). The vertical joint portion 43 rigidly connects the floor slab 42 and the floor slab 22, and the floor slab 42 and the floor slab 32, respectively.

上記の工程S1~S7を各支間で実行することにより、拡幅部4の施工が進捗する。 By executing the above steps S1 to S7 for each span, the construction of the widened portion 4 progresses.

<効果>
上記実施形態における桁41は、コンクリート断面を持つプレキャストコンクリート構造の桁であり、コンクリート断面に対してプレテンション方式によって圧縮応力を与える1次鋼材413と、コンクリート断面に対してポストテンション方式によって圧縮応力を増加させる2次鋼材414とを有する。
<Effect>
The girder 41 in the above embodiment is a girder of a precast concrete structure with a concrete cross section, and includes a primary steel member 413 that applies compressive stress to the concrete cross section by a pre-tension method, and a compressive stress to the concrete cross section by a post-tension method. It has a secondary steel material 414 that increases.

このような施工方法、構造が採用されることにより、桁41のコンクリート断面には、図7(a)に示すように、1次鋼材413と2次鋼材414によって圧縮応力が二段階で増加される。 By adopting such a construction method and structure, compressive stress is increased in two stages in the concrete cross section of the girder 41 by the primary steel material 413 and the secondary steel material 414, as shown in FIG. 7(a). Ru.

拡幅部4は周囲を拘束され、拡幅部4自身のクリープと乾燥収縮による収縮ひずみの拘束により(反作用的に)大きな引張力が発生する。そのため、桁41と床版42に付与された圧縮応力は、上記の引張力により大きく減少する。 The widened portion 4 is constrained around its periphery, and a large tensile force is generated (reactively) due to the constraint of shrinkage strain caused by creep and drying shrinkage of the widened portion 4 itself. Therefore, the compressive stress applied to the girder 41 and the deck slab 42 is greatly reduced by the above-mentioned tensile force.

本実施形態では、桁41において圧縮応力の減少が発生しても、2次鋼材414によって圧縮応力が付加される。そのため、圧縮応力の減少を補い、設計上の性能を満たした桁41が得られる。 In this embodiment, even if a decrease in compressive stress occurs in the girder 41, the compressive stress is applied by the secondary steel material 414. Therefore, a girder 41 that compensates for the decrease in compressive stress and satisfies the designed performance can be obtained.

また、圧縮応力の一部が施工前に1次鋼材413によって付与されるため、2次鋼材414にかかる張力は一般的な橋梁に比較して少ない。加えて、1次鋼材413による応力付与はプレテンション方式によるものであり、十分な養生期間を設けることで、クリープ及び乾燥収縮によるひずみの進展を現場搬入前に一定程度収束させておくことができる。したがって、既設部2及び既設部3の拘束によって生じる引張力を抑制することができる。 Further, since a part of the compressive stress is applied by the primary steel material 413 before construction, the tension applied to the secondary steel material 414 is less than that of a general bridge. In addition, the stress applied by the primary steel material 413 is based on the pre-tension method, and by providing a sufficient curing period, the development of strain due to creep and drying shrinkage can be brought to a certain level before delivery to the site. . Therefore, the tensile force generated by restraining the existing portions 2 and 3 can be suppressed.

一方、従来技術(特許文献1)では、桁断面に対する圧縮応力の付与は1回の作業だけで実施され、床版の圧縮応力も桁部材には寄与しない(図7(b))。この施工方法及び構造では、1回の緊張作業だけで必要な圧縮応力の全てを導入する必要があるため、鋼材に導入される張力を大きくする必要がある。このため、プレストレスの導入によって桁に発生する不静定力も大きい。加えて、鋼材のリラクゼーションやコンクリートのクリープに起因する圧縮応力の低下も大きなものとなるため、設計上要求される圧縮応力を桁に与えることは容易ではない。 On the other hand, in the conventional technology (Patent Document 1), compressive stress is applied to the girder cross section in only one operation, and the compressive stress of the deck does not contribute to the girder member (FIG. 7(b)). In this construction method and structure, it is necessary to introduce all the necessary compressive stress in just one tensioning operation, so it is necessary to increase the tension introduced into the steel material. For this reason, the introduction of prestress also generates a large unsteady force on the girder. In addition, the reduction in compressive stress due to relaxation of the steel and creep of concrete is also significant, so it is not easy to provide the girder with the compressive stress required in the design.

また不静定力や既設部の拘束に対向するために桁断面を大きくしてプレストレス量を増大させる方法を採用すると、既設部と拡幅部のたわみ剛性の差が大きくなり、既設桁にねじりなどの影響が生じてしまう。この問題を避けるためには、既設桁と同様な桁高(小さな断面)とする必要があるが、こうするとPC鋼材の配置に自由度がなくなり、構造を成立させることができない。本実施形態ではこのような問題点を解決している。 In addition, if a method is adopted in which the girder cross section is enlarged to increase the amount of prestress in order to cope with unsteady force and restraint of the existing section, the difference in flexural rigidity between the existing section and the expanded section increases, causing torsion in the existing section. Such effects will occur. In order to avoid this problem, it is necessary to make the girder height similar to the existing girder (small cross section), but if this is done, there will be no degree of freedom in the arrangement of the PC steel materials, and the structure will not be able to be established. This embodiment solves these problems.

加えて、従来技術では、橋梁拡幅工事は既設部を供用した上で交通規制(車線規制等)を実施しながらの施工となることが多い。従来の橋梁拡幅において、拡幅部は現場打ちで施工されるため、施工位置で3~6か月程度の養生期間が必要になり、この養生期間中交通規制を継続する必要がある。本実施形態ではプレキャストコンクリート構造を採用することで、現場以外の仮置きヤードで養生を実施することが可能となり、交通規制期間の短縮効果がある。また、養生期間を3~6か月に限定せず、それ以上の長期養生の実施が交通規制によらず可能になり、プレキャストコンクリート構造の採用だけでも通常以上にクリープ及び乾燥収縮による影響を低減する効果が期待できる。 In addition, with conventional technology, bridge widening work is often carried out while using the existing section and implementing traffic regulations (lane regulations, etc.). In conventional bridge widening, the widening section is cast in place, which requires a curing period of about 3 to 6 months at the construction site, and traffic control must continue during this curing period. By adopting a precast concrete structure in this embodiment, it becomes possible to carry out curing in a temporary storage yard other than the site, which has the effect of shortening the traffic regulation period. In addition, the curing period is not limited to 3 to 6 months, but longer curing can be carried out without traffic restrictions, and the effects of creep and drying shrinkage are reduced more than usual by simply adopting a precast concrete structure. You can expect the effect of

上記実施形態において橋梁1は、桁41を支持する橋脚45(本発明の支持部に相当)を備える。橋脚45の近傍において、1次鋼材413は、桁41の上部に配置される。 In the embodiment described above, the bridge 1 includes piers 45 (corresponding to the support section of the present invention) that support the girders 41. In the vicinity of the pier 45, the primary steel material 413 is placed on top of the girder 41.

上記構成とすることにより、桁41に発生する曲げモーメントの向き及びその大きさに対応して効果的に1次鋼材を配置し、適切な量、分布の圧縮応力をコンクリート断面に対して与えることが可能となる。 実施形態において、2次鋼材414は、桁41の断面図心線41Cに対して対称に配置される。 By having the above configuration, the primary steel members can be effectively arranged in accordance with the direction and magnitude of the bending moment generated in the girder 41, and compressive stress with an appropriate amount and distribution can be applied to the concrete cross section. becomes possible. In the embodiment, the secondary steel material 414 is arranged symmetrically with respect to the cross-sectional center line 41C of the girder 41.

上記構成では、2次鋼材414の張力の中心がコンクリート断面の図心線41C上または近傍に位置する。2次鋼材414は、コンクリート断面に一様な圧縮応力を付与し、プレストレスによる不静定力の影響を低減することができる。 In the above configuration, the center of tension of the secondary steel material 414 is located on or near the centroid line 41C of the concrete cross section. The secondary steel material 414 can apply uniform compressive stress to the concrete cross section and reduce the influence of unsteady force due to prestress.

実施形態において縦接合部43(第1接合部に相当)は、橋軸直角方向における床版42の端部を、超高強度繊維補強コンクリートを用いて床版22、32(周辺構造物に相当)と接合する。 In the embodiment, the vertical joint part 43 (corresponding to the first joint part) connects the end of the deck slab 42 in the direction perpendicular to the bridge axis to the deck slabs 22, 32 (corresponding to surrounding structures) using ultra-high strength fiber reinforced concrete. ) to join.

上記のようにUFCを用いて床版42の端部を接合することにより、プレストレスの導入できない縦接合部43においても強度または耐久性を向上させることができる。また上述の通り、縦接合部43の幅及び施工範囲を小さくし、工期短縮などの効果を得ることができる。 By joining the ends of the floor slabs 42 using UFC as described above, the strength or durability can be improved even in the vertical joints 43 where prestress cannot be introduced. Further, as described above, the width of the vertical joint portion 43 and the construction range can be reduced, thereby achieving effects such as shortening the construction period.

実施形態において横接合部44(第2接合部に相当)は、橋軸方向に隣り合う前記床版を、超高強度繊維補強コンクリートを用いて接合する。 In the embodiment, the horizontal joint portion 44 (corresponding to the second joint portion) joins the deck slabs adjacent in the bridge axis direction using ultra-high strength fiber reinforced concrete.

上記のようにUFCを用いて床版42同士を接合することにより、プレストレスの導入できない横接合部44においても強度または耐久性を向上させることができる。また上述の通り、横接合部44の幅及び施工範囲を小さくし、工期短縮などの効果を得ることができる。 By joining the floor slabs 42 together using UFC as described above, the strength or durability can be improved even in the lateral joint parts 44 where prestress cannot be introduced. Further, as described above, the width of the horizontal joint portion 44 and the construction range can be reduced, thereby achieving effects such as shortening the construction period.

実施形態において横接合部44は、セグメント41A、41Bの接合部に対して橋軸方向にずれた位置に設けられる。 In the embodiment, the lateral joint 44 is provided at a position shifted in the bridge axis direction with respect to the joint between the segments 41A and 41B.

このような構成とすることにより、横接合部44に過大な変位またはひずみが発生することが回避される。横接合部44にひびが発生するなどの不具合を防止し、橋梁1における耐久性などの品質を向上させることができる。 Such a configuration prevents excessive displacement or strain from occurring in the lateral joint portion 44. It is possible to prevent defects such as the occurrence of cracks in the lateral joints 44, and improve the quality of the bridge 1, such as its durability.

<変形例>
上記構成では、2次鋼材414は、コンクリート断面の図心線41Cに沿って直線状に設置された。本発明はこの構成に限定されず、図8に示すように、2次鋼材414を桁41に発生する曲げモーメントの大きさ及び向きに対応させて、曲線状に配置してもよい。
<Modified example>
In the above configuration, the secondary steel material 414 was installed linearly along the centroid line 41C of the concrete cross section. The present invention is not limited to this configuration, and as shown in FIG. 8, the secondary steel materials 414 may be arranged in a curved shape corresponding to the magnitude and direction of the bending moment generated in the girder 41.

実施形態において桁41はU字型の断面を持っていたが、本発明は桁の断面形状及び構造を限定するものではない。桁の構造はT桁、箱桁、合成桁など設計条件に合わせて適宜設定し得る。また、実施形態では桁41が連続桁である場合について説明したが、桁41は単純桁であってもよい。この場合、支間全長に亘って1次鋼材413を桁41の下部に配置するなど、1次鋼材413及び2次鋼材414の形状及び位置は、曲げモーメントの向き及び大きさに合わせて適切に設計される。図心線についても、桁の形状に合わせて設定される。 Although the girder 41 had a U-shaped cross section in the embodiment, the present invention does not limit the cross-sectional shape and structure of the girder. The structure of the girder can be appropriately set according to the design conditions, such as a T-girder, a box girder, or a composite girder. Further, in the embodiment, the case where the digits 41 are continuous digits has been described, but the digits 41 may be simple digits. In this case, the shape and position of the primary steel material 413 and the secondary steel material 414 are appropriately designed to match the direction and magnitude of the bending moment, such as by arranging the primary steel material 413 at the bottom of the girder 41 over the entire span length. be done. The centroid line is also set according to the shape of the girder.

実施形態では、桁41はセグメント41A、41Bを接合することによって施工された。この施工方法に代えて、桁41は1つのプレキャスト部材として製作されてもよい。 In the embodiment, the girder 41 was constructed by joining segments 41A, 41B. Alternatively to this construction method, the girder 41 may be manufactured as a single precast member.

実施形態において橋梁1は、既設部2、既設部3、及び拡幅部4を備えていたが、既設部3は必須の構成ではない。すなわち、橋梁1が既設部3を備えず、既設部2と、既設部2を拡幅する拡幅部4とによって構成されてもよい。 In the embodiment, the bridge 1 includes an existing portion 2, an existing portion 3, and an expanded portion 4, but the existing portion 3 is not an essential configuration. That is, the bridge 1 may not include the existing portion 3 but may be configured by the existing portion 2 and the widening portion 4 that widens the existing portion 2.

橋梁1
既設部2
既設部3
拡幅部4
桁41
セグメント41A、41B
床版42
縦接合部43
横接合部44
橋脚45
Bridge 1
Existing part 2
Existing part 3
Widened part 4
Digit 41
Segments 41A, 41B
Floor slab 42
Vertical joint 43
Lateral joint 44
Pier 45

Claims (8)

橋軸方向に延びる、コンクリート断面を持つプレキャストコンクリート構造の桁であって、
前記コンクリート断面に対してプレテンション方式で圧縮応力を与える1次鋼材と、
前記コンクリート断面に対してポストテンション方式で前記圧縮応力を増加させる2次鋼材と、を有する桁を備え、
前記2次鋼材は、前記桁の断面図心線に対して対称に配置される、橋梁。
A girder of precast concrete structure with a concrete cross section extending in the axial direction of the bridge,
a primary steel material that applies compressive stress to the concrete cross section in a pretensioning manner;
a girder having a secondary steel material that increases the compressive stress in a post-tensioning manner with respect to the concrete cross section,
The said secondary steel material is a bridge arrange|positioned symmetrically with respect to the cross-sectional center line of the said girder .
前記桁を支持する支持部をさらに備え、
前記1次鋼材は、前記支持部近傍において前記桁の上部に配置される、請求項1に記載の橋梁。
further comprising a support part that supports the girder,
The bridge according to claim 1, wherein the primary steel material is arranged above the girder near the support portion.
前記桁に固定された、プレストレストコンクリート構造のプレキャスト造床版をさらに備える、請求項1または2に記載の橋梁。 The bridge according to claim 1 or 2 , further comprising a precast deck slab of prestressed concrete structure fixed to the girder. 前記橋軸方向に直交する方向における前記床版の端部を、超高強度繊維補強コンクリートを用いて周辺構造物と接合する第1接合部をさらに備える、請求項3に記載の橋梁。 The bridge according to claim 3 , further comprising a first joint part that joins an end of the deck in a direction perpendicular to the bridge axis direction to a surrounding structure using ultra-high strength fiber-reinforced concrete. 前記橋軸方向に隣り合う前記床版を、超高強度繊維補強コンクリートを用いて接合する第2接合部をさらに備える、請求項3または4に記載の橋梁。 The bridge according to claim 3 or 4 , further comprising a second joint portion that joins the deck slabs adjacent in the bridge axis direction using ultra-high strength fiber reinforced concrete. 橋軸方向に延びる、コンクリート断面を持つプレキャストコンクリート構造の桁であって、
前記コンクリート断面に対してプレテンション方式で圧縮応力を与える1次鋼材と、
前記コンクリート断面に対してポストテンション方式で前記圧縮応力を増加させる2次鋼材と、を有する桁と、
前記桁に固定された、プレストレストコンクリート構造のプレキャスト造床版と、
前記橋軸方向に隣り合う前記床版を接合する第2接合部と、を備え、
前記桁は、複数のセグメントを有し、
前記第2接合部は、前記複数のセグメントの接合位置に対して前記橋軸方向にずれた位置に設けられる、橋梁。
A girder of precast concrete structure with a concrete cross section extending in the axial direction of the bridge,
a primary steel material that applies compressive stress to the concrete cross section in a pretensioning manner;
a girder having a secondary steel material that increases the compressive stress with respect to the concrete cross section in a post-tensioning manner;
a precast deck slab of prestressed concrete structure fixed to the girder;
a second joint part that joins the deck slabs adjacent in the bridge axis direction,
the girder has a plurality of segments;
The second joint portion is a bridge provided at a position shifted in the bridge axis direction with respect to a joint position of the plurality of segments.
前記第2接合部において、超高強度繊維補強コンクリートを用いて前記橋軸方向に隣り合う前記床版を接合する、請求項6に記載の橋梁。7. The bridge according to claim 6, wherein the deck slabs adjacent in the bridge axis direction are joined at the second joint using ultra-high strength fiber-reinforced concrete. 橋軸方向に延びる、コンクリート断面を持つプレキャストコンクリート構造の桁を有する橋梁の施工方法であって、
1次鋼材を用いて前記コンクリート断面に対してプレテンション方式で圧縮応力を与える工程と、
前記桁の断面図心線に対して対称に配置した2次鋼材を用いて前記コンクリート断面に対してポストテンション方式で前記圧縮応力を増加させる工程と、を有する施工方法。
A method of constructing a bridge having a girder of precast concrete structure with a concrete cross section extending in the direction of the bridge axis, the method comprising:
applying compressive stress to the concrete cross section using a pretension method using primary steel;
A construction method comprising the step of increasing the compressive stress in the concrete cross section using a post-tension method using secondary steel materials arranged symmetrically with respect to the cross-sectional center line of the girder .
JP2021133906A 2021-08-19 2021-08-19 bridge Active JP7428170B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021133906A JP7428170B2 (en) 2021-08-19 2021-08-19 bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021133906A JP7428170B2 (en) 2021-08-19 2021-08-19 bridge

Publications (2)

Publication Number Publication Date
JP2023028291A JP2023028291A (en) 2023-03-03
JP7428170B2 true JP7428170B2 (en) 2024-02-06

Family

ID=85331646

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021133906A Active JP7428170B2 (en) 2021-08-19 2021-08-19 bridge

Country Status (1)

Country Link
JP (1) JP7428170B2 (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006138064A (en) 2004-11-10 2006-06-01 Taisei Corp Girder structure and construction method therefor
JP2014062403A (en) 2012-09-21 2014-04-10 Kitagawa Kogyo Co Ltd Bridge girder and construction method of bridge girder
JP2015113589A (en) 2013-12-10 2015-06-22 黒沢建設株式会社 Ps post-introduction method of rc building and structure thereof
JP2016008441A (en) 2014-06-25 2016-01-18 株式会社日本ピーエス Structure and manufacturing method for prestressed concrete member
JP6158616B2 (en) 2013-07-09 2017-07-05 株式会社パイオラックスメディカルデバイス Foreign body capture device in body cavity
JP2017172143A (en) 2016-03-22 2017-09-28 株式会社高速道路総合技術研究所 Junction structure of precast concrete floor slab for rapid construction work, and construction method of the same

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61113908A (en) * 1984-11-06 1986-05-31 住友建設株式会社 Production of prestressed concrete beam

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006138064A (en) 2004-11-10 2006-06-01 Taisei Corp Girder structure and construction method therefor
JP2014062403A (en) 2012-09-21 2014-04-10 Kitagawa Kogyo Co Ltd Bridge girder and construction method of bridge girder
JP6158616B2 (en) 2013-07-09 2017-07-05 株式会社パイオラックスメディカルデバイス Foreign body capture device in body cavity
JP2015113589A (en) 2013-12-10 2015-06-22 黒沢建設株式会社 Ps post-introduction method of rc building and structure thereof
JP2016008441A (en) 2014-06-25 2016-01-18 株式会社日本ピーエス Structure and manufacturing method for prestressed concrete member
JP2017172143A (en) 2016-03-22 2017-09-28 株式会社高速道路総合技術研究所 Junction structure of precast concrete floor slab for rapid construction work, and construction method of the same

Also Published As

Publication number Publication date
JP2023028291A (en) 2023-03-03

Similar Documents

Publication Publication Date Title
KR100941066B1 (en) Prestressed-precast-segmental open spendral concrete arch bridge and its constructing method
JP5945418B2 (en) How to build a box girder bridge
KR100991869B1 (en) Single and continuous prestressed concrete girder bridge and the construction method
KR100703134B1 (en) Prefabricated prestressed concrete beam bridge and its construction method
JP2007077630A (en) Continuous girder using precast main-girder segment, and its erection method
KR101107826B1 (en) Slab-type box girder made by precast concrete and method constructing the bridge therewith
JP3844743B2 (en) Box girder bridge structure and its construction method
KR100952623B1 (en) Bridge having deck slab concrete structure on plural beams, constructing method thereof and precast partial-depth deck slab concrete structure used in constructing same
KR100823448B1 (en) The improved seismic resistant continuation structure of prestressed concrete composite beam bridge and method thereof
JP5802519B2 (en) Bridge
JP2003253621A (en) Continuous beam structure for continuing existing simple beam bridge
KR101771911B1 (en) Costruction method of presressed segment streel composite girder with load-locking structure
KR20000055053A (en) Reinforcing Method Of PC Beam Bridge With Box Structure And PC Beam Bridge Having Box Reinforced Structure
US20120222375A1 (en) Method to Compress Prefabricated Deck Units by Tensioning Elements at Intermediate Supports
JP3877995B2 (en) How to build a string string bridge
KR101688517B1 (en) Continuous bridge construction method using support pier girder and continuous tendon of pier
JP7428170B2 (en) bridge
KR101067717B1 (en) Process for producing prestressed concrete girder and concrete girder structure
KR100785634B1 (en) Continuation structure of prestressed concrete composite beam bridge and method thereof
JP2021011778A (en) Road structure
CN215484065U (en) Subregion expansion concrete beam
KR100724739B1 (en) Construction method of PSC Girder bridge using Retensionable and Detensionable anchorage with unbonded tendon
KR102207785B1 (en) PSC Decked bulb tee girder and construction method thereof
JP4493245B2 (en) Suspended floor slab bridge and method for reinforcing suspended floor slab
KR100899713B1 (en) Bridge structure of steel composite girder using precast arch-deck, and constructing method thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230725

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20230725

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20231003

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20231101

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20231226

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240108

R150 Certificate of patent or registration of utility model

Ref document number: 7428170

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150