JP7005262B2 - How to build a building - Google Patents

How to build a building Download PDF

Info

Publication number
JP7005262B2
JP7005262B2 JP2017197741A JP2017197741A JP7005262B2 JP 7005262 B2 JP7005262 B2 JP 7005262B2 JP 2017197741 A JP2017197741 A JP 2017197741A JP 2017197741 A JP2017197741 A JP 2017197741A JP 7005262 B2 JP7005262 B2 JP 7005262B2
Authority
JP
Japan
Prior art keywords
girder
frame
suspended
building
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017197741A
Other languages
Japanese (ja)
Other versions
JP2019070298A (en
Inventor
弘志 井瀬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2017197741A priority Critical patent/JP7005262B2/en
Publication of JP2019070298A publication Critical patent/JP2019070298A/en
Application granted granted Critical
Publication of JP7005262B2 publication Critical patent/JP7005262B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Description

本発明は、大梁と、この大梁に吊り下げ支持された吊り架構体と、を有する建物の構築方法に関する。 The present invention relates to a method for constructing a building having a girder and a suspended frame suspended and supported by the girder.

従来より、大スパンの大梁の上に架構体を構築する場合がある。
特許文献1には、中間階に架設される大スパンの大梁の下に吹抜けが形成される構造物において、大梁より上方に構築される上部架構を施工する方法が示されている。具体的には、大梁の架設後、大梁上に立設される上部架構の柱と大梁との間にジャッキを設置し、柱をジャッキに支持させた状態で大梁上の1層分以上の架構の全体、もしくは架構の一部を構築する毎に、柱をジャッキアップする作業を繰り返す。
Conventionally, a frame may be constructed on a girder with a large span.
Patent Document 1 discloses a method of constructing an upper frame constructed above a girder in a structure in which a stairwell is formed under a girder having a large span erected on an intermediate floor. Specifically, after the girder is erected, a jack is installed between the pillar of the upper frame erected on the girder and the girder, and the frame is one layer or more on the girder with the pillar supported by the jack. Every time the whole or a part of the frame is constructed, the work of jacking up the pillars is repeated.

特許文献2には、屋根を地組みした後、壁躯体を複数に分割して、分割した区画毎に壁躯体の上にジャッキを設けて、これらジャッキの上に屋根に取り付ける工程と、1つ置きのジャッキを駆動して屋根を上昇させ、作動させなかったジャッキの下方にさらに壁躯体を構築する工程と、を備える、大スパンの屋根架構を押し上げて構築する方法が示されている。 In Patent Document 2, after the roof is grounded, the wall frame is divided into a plurality of parts, jacks are provided on the wall frame in each divided section, and the steps are attached to the roof on these jacks. A method of pushing up and constructing a large span roof frame is shown, which comprises the steps of driving a standing jack to raise the roof and further constructing a wall skeleton below the inactive jack.

特許文献3には、下部躯体の上方に主要空間を置いて上向きに湾曲した大スパン大梁を架設し、この大スパン大梁により上部躯体を支持する施工方法が示されている。具体的には、大スパン大梁の柱位置から、下部躯体の上部柱位置にPC鋼線を垂設するとともに、この上部柱位置に油圧ジャッキを設け、この油圧ジャッキによりPC鋼線を緊張して大スパン大梁に下向きの荷重を与える。上部躯体の施工段階に応じて、油圧ジャッキによりその荷重の調整を行う。 Patent Document 3 discloses a construction method in which a large span girder is erected with a main space above the lower skeleton and curved upward, and the upper skeleton is supported by the large span girder. Specifically, a PC steel wire is laid vertically from the column position of the large span girder to the upper column position of the lower skeleton, and a hydraulic jack is provided at this upper column position, and the PC steel wire is tensioned by this hydraulic jack. A downward load is applied to the large span girder. The load is adjusted with a hydraulic jack according to the construction stage of the upper frame.

特開2000-144892号公報Japanese Unexamined Patent Publication No. 2000-144892 特開1991-197736号公報Japanese Unexamined Patent Publication No. 991-197736 特開1992-044569号公報Japanese Unexamined Patent Publication No. 1992-044569

本発明は、建物の中間階または最上階に設置される大梁と、この大梁に吊り下げ支持されて複数階からなる吊り架構体と、を備える建物を、短工期で構築する方法を提供することを課題とする。 The present invention provides a method for constructing a building including a girder installed on the middle floor or the top floor of a building and a suspended frame structure having a plurality of floors suspended and supported by the girder in a short construction period. Is the subject.

第1の発明の建物の構築方法は、大梁(例えば、後述の下部大梁12、上部大梁22)と当該大梁に吊り下げ支持された吊り架構体(例えば、後述の下部吊り架構体13、上部吊り架構体23)とを有する建物(例えば、後述の建物1)の構築方法であって、仮支柱(例えば、後述の仮支柱30、32)の上に吊り架構体(例えば、後述の下部吊り架構体13、上部吊り架構体23)を構築する工程(例えば、後述のステップS1、S2)と、当該吊り架構体の上方に大梁を構築する工程(例えば、後述のステップS3)と、前記仮支柱(例えば、後述の仮支柱30)により前記吊り架構体を押し上げる、または、前記大梁に取り付けたジャッキ(例えば、後述の油圧ジャッキ34)により前記吊り架構体を引っ張り上げることにより、当該吊り架構体を上方に移動して前記大梁に接合する工程(例えば、後述のステップS4)と、前記仮支柱を撤去する工程(例えば、後述のステップS5)と、を備えることを特徴とする。 The method for constructing a building according to the first invention is to use a girder (for example, a lower girder 12 and an upper girder 22 described later) and a suspended frame suspended and supported by the girder (for example, a lower suspended frame 13 and an upper suspension described later). It is a method of constructing a building having a frame 23) (for example, the building 1 described later), and is a hanging frame structure (for example, a lower hanging frame described later) on a temporary support (for example, temporary columns 30 and 32 described later). A step of constructing the body 13 and the upper suspended frame 23) (for example, steps S1 and S2 described later), a step of constructing a girder above the suspended frame (for example, step S3 described later), and the temporary support column. (For example, the suspended frame is pushed up by the temporary support 30 described later), or the suspended frame is pulled up by a jack attached to the girder (for example, the hydraulic jack 34 described later) to lift the suspended frame. It is characterized by comprising a step of moving upward and joining to the girder (for example, step S4 described later) and a step of removing the temporary support (for example, step S5 described later).

この発明によれば、複数階からなる吊り架構体を仮支柱で仮支持して構築し、その後、仮支柱または油圧ジャッキによりこの吊り架構体を上方に移動して、大梁から吊り下げ支持する。よって、大梁に吊り下げ支持された吊り架構体を備える建物を、短工期で構築できる。
また、吊り架構体を大梁から吊り下げ支持する構造であるため、この吊り架構体には上載荷重が作用しない。よって、吊り上げられる吊り架構体の梁や床にむくりを設ける必要がなく、吊り架構体に早期に外装材を取り付けることができる。
According to the present invention, a suspended frame structure having a plurality of floors is temporarily supported by temporary columns and then constructed, and then the suspended frame is moved upward by temporary columns or hydraulic jacks to be suspended and supported from a girder. Therefore, it is possible to construct a building having a suspended frame suspended and supported by a girder in a short construction period.
Further, since the suspended frame is suspended and supported from the girder, no load is applied to the suspended frame. Therefore, it is not necessary to provide the beams or the floor of the suspended frame to be lifted, and the exterior material can be attached to the suspended frame at an early stage.

第2の発明の建物の構築方法は、前記大梁を構築する工程では、当該大梁のスパン中央部を上方に湾曲させることを特徴とする。 The method for constructing a building according to the second invention is characterized in that, in the step of constructing the girder, the central portion of the span of the girder is curved upward.

吊り架構体を建物の複数階で構成した場合、吊り架構体の重量が大きいため、吊り架構体を大梁から吊り下げ支持すると、大梁が変形して下方に撓んでしまう。
そこで、本発明によれば、予め吊り架構体の重量による撓みを考慮して、大梁のスパン中央を上方に湾曲させてむくりを設けておいたので、吊り架構体を吊り上げた際、大梁を略水平にできる。
When the suspended frame is composed of multiple floors of the building, the weight of the suspended frame is large, so when the suspended frame is suspended and supported from the girder, the girder is deformed and bends downward.
Therefore, according to the present invention, in consideration of the bending due to the weight of the suspended frame, the center of the span of the girder is curved upward to provide a peeling. Therefore, when the suspended frame is lifted, the girder is lifted. Can be made almost horizontal.

第3の発明の建物の構築方法は、前記建物は、前記吊り架構体に隣接して設けられて前記大梁を支持する大梁支持架構体(例えば、後述の上部大梁支持架構体21)をさらに備え、前記吊り架構体と当該大梁とを接合する工程では、前記吊り架構体の少なくとも一部を、前記大梁支持架構体から仮支持部材(例えば、後述の仮支持部材33)で仮支持することを特徴とする。 In the method for constructing a building according to the third invention, the building further includes a girder support frame (for example, an upper girder support frame 21 described later) which is provided adjacent to the suspended frame and supports the girder. In the step of joining the suspended frame and the girder, at least a part of the suspended frame is temporarily supported by a temporary support member (for example, a temporary support member 33 described later) from the girder support frame. It is a feature.

ここで、仮支持部材は、圧縮力が作用する圧縮材でもよいし、引張力が作用する引張材でもよい。また、仮支持部材に油圧ジャッキ等を内蔵して、仮支持部材の長さや軸力を調整可能としてもよい。
この発明によれば、吊り架構体の少なくとも一部を、仮支持部材で大梁支持架構体から仮支持した。よって、吊り架構体の重量の一部を大梁支持架構体が負担するので、吊り架構体の下方への撓み量を低減しつつ、仮支柱に加わる鉛直荷重を低減できる。また、仮支持部材を介して大梁支持架構体が吊り架構体の水平方向の揺れを拘束するので、建物の構築過程において、大梁と吊り架構体が接合されていない状態であっても、吊り架構体の耐震性能を確保できる。
Here, the temporary support member may be a compressive material on which a compressive force acts, or a tensile material on which a tensile force acts. Further, a hydraulic jack or the like may be built in the temporary support member so that the length and axial force of the temporary support member can be adjusted.
According to the present invention, at least a part of the suspended frame is temporarily supported from the girder support frame by a temporary support member. Therefore, since the girder support frame bears a part of the weight of the suspended frame, the vertical load applied to the temporary support can be reduced while reducing the amount of downward bending of the suspended frame. In addition, since the girder support frame restrains the horizontal swing of the suspended frame via the temporary support member, the suspended frame is not joined even if the girder and the suspended frame are not joined in the building construction process. The seismic performance of the body can be ensured.

本発明によれば、建物の中間階または最上階に設置される大梁と、この大梁に吊り下げ支持されて複数階からなる吊り架構体と、を備える建物を、短工期で構築できる。 According to the present invention, it is possible to construct a building including a girder installed on the middle floor or the top floor of a building and a suspended frame structure having a plurality of floors suspended and supported by the girder in a short construction period.

本発明の一実施形態に係る建物の構築方法により構築される建物の縦断面図である。It is a vertical sectional view of a building constructed by the building construction method which concerns on one Embodiment of this invention. 吊り架構体を有する建物の主要な構築手順のフローチャートである。It is a flowchart of the main construction procedure of a building having a suspended frame. 吊り架構体を有する建物の詳細な構築手順のフローチャートである。It is a flowchart of the detailed construction procedure of a building having a suspended frame. 建物の構築手順の説明図(その1、下部吊り架構体の構築工程)である。It is explanatory drawing of the building construction procedure (the first, the construction process of the lower suspension frame). 建物の構築手順の説明図(その2、下部大梁の構築工程)である。It is explanatory drawing (2, construction process of a lower girder) of a building construction procedure. 建物の構築手順の説明図(その3、下部大梁と下部吊り架構体との接合工程)である。It is explanatory drawing (3, the process of joining a lower girder and a lower suspension frame) of a building construction procedure. 建物の構築手順の説明図(その4、仮支柱の撤去工程)である。It is explanatory drawing (4, removal process of a temporary support) of a building construction procedure. 建物の構築手順の説明図(その5、上部吊り架構体の構築工程)である。It is explanatory drawing (5, construction process of the upper suspension frame) of the building construction procedure. 建物の構築手順の説明図(その6、上部大梁と上部吊り架構体との接合工程)である。It is explanatory drawing (6, the process of joining the upper girder and the upper suspension frame) of the building construction procedure.

本発明は、建物の中間階または最上階に設置されるメガトラス(大梁)から吊り架構体を吊り下げ支持させる方法であって、大梁支持架構体と吊り架構体とを分離して同時に構築し、その後、大梁支持架構体上に大梁を架設して、この大梁に吊り架構体を接合する建物の構築方法である。
本発明では、建物の下部を構成する下部架構体を構築する際、床スラブの上に設置した仮支柱上に吊り架構体を構築し、その後、この仮支柱により吊り架構体を下から押し上げて、大梁に接合する(図4~図7)。一方、建物の上部を構成する上部架構体を構築する際、仮支持部材により大梁支持架構体から仮支持しながら吊り架構体を構築することで、吊り架構体の下方への撓み量を低減させておき、その後、最上段の油圧ジャッキによりこの吊り架構体を引っ張り上げて、大梁に接合する(図8および図9)。
The present invention is a method of suspending and supporting a suspended frame from a mega truss (girder) installed on the middle floor or the top floor of a building, in which the girder support frame and the suspended frame are separately constructed and simultaneously constructed. After that, it is a method of constructing a building in which a girder is erected on a girder support frame and a suspended frame is joined to the girder.
In the present invention, when constructing the lower frame structure constituting the lower part of the building, the suspended frame is constructed on the temporary support placed on the floor slab, and then the suspended frame is pushed up from below by the temporary support. , Join to the girder (Figs. 4-7). On the other hand, when constructing the upper frame that constitutes the upper part of the building, the amount of downward deflection of the suspended frame is reduced by constructing the suspended frame while temporarily supporting it from the girder support frame with temporary support members. After that, the suspended frame is pulled up by the uppermost hydraulic jack and joined to the girder (FIGS. 8 and 9).

以下、本発明の一実施形態を図面に基づいて説明する。
図1は、本発明の一実施形態に係る建物の構築方法により構築される建物1の縦断面図である。
建物1は、下部架構体10と、下部架構体10の上に設けられた上部架構体20と、を備える。
Hereinafter, an embodiment of the present invention will be described with reference to the drawings.
FIG. 1 is a vertical sectional view of a building 1 constructed by the method for constructing a building according to an embodiment of the present invention.
The building 1 includes a lower frame 10 and an upper frame 20 provided on the lower frame 10.

下部架構体10は、複数階からなる下部大梁支持架構体11と、下部大梁支持架構体11の上に構築されてこの下部大梁支持架構体11に支持されたトラス構造の下部大梁12と、下部大梁支持架構体11に隣接して設けられて下部大梁12に吊り下げ支持された複数階からなる下部吊り架構体13と、を備える。
下部大梁支持架構体11と下部大梁12との間には、免震装置14が設けられて、免震層15が形成されている。
The lower frame 10 has a lower girder support frame 11 composed of a plurality of floors, a truss structure lower girder 12 constructed on the lower girder support frame 11 and supported by the lower girder support frame 11, and a lower portion. A lower suspension frame 13 composed of a plurality of floors provided adjacent to the girder support frame 11 and suspended and supported by the lower girder 12 is provided.
A seismic isolation device 14 is provided between the lower girder support frame 11 and the lower girder 12, and a seismic isolation layer 15 is formed.

上部架構体20は、複数階からなる上部大梁支持架構体21と、上部大梁支持架構体21の上に構築されてこの上部大梁支持架構体21に支持されたトラス構造の上部大梁22と、上部大梁支持架構体21に隣接して設けられて上部大梁22に吊り下げ支持された複数階からなる上部吊り架構体23と、を備える。
上部大梁支持架構体21は、下部大梁支持架構体11の直上に位置しており、下部大梁12の上に設けられている。この上部大梁支持架構体21の柱のうち、最も上部吊り架構体23に近いものを柱24とし、次に近いものを柱25とする。
The upper frame 20 has an upper frame 21 composed of a plurality of floors, a truss structure upper frame 22 constructed on the upper frame 21 and supported by the upper frame 21, and an upper portion. It is provided with an upper suspension frame 23 composed of a plurality of floors, which is provided adjacent to the girder support frame 21 and is suspended and supported by the upper girder 22.
The upper girder support frame 21 is located directly above the lower girder support frame 11 and is provided on the lower girder 12. Among the columns of the upper girder support frame 21, the column closest to the upper suspension frame 23 is the column 24, and the column closest to the column 25 is the column 25.

上部吊り架構体23には、下端から上端まで連続する2本の柱26が設けられている。上部吊り架構体23は、下部吊り架構体13の直上に位置しているが、上部大梁22によって上から吊り下げ支持されているため、上部吊り架構体23の荷重は下部大梁12に作用していない。つまり、上部吊り架構体23の最下段の柱26Aには、上載荷重が作用していない状態である。 The upper suspension frame 23 is provided with two pillars 26 that are continuous from the lower end to the upper end. The upper suspension frame 23 is located directly above the lower suspension structure 13, but since it is suspended and supported from above by the upper girder 22, the load of the upper suspension structure 23 acts on the lower girder 12. do not have. That is, no load is applied to the lowermost column 26A of the upper suspension frame 23.

以上の建物1では、免震装置14により、下部大梁支持架構体11に対し、下部大梁12、下部吊り架構体13、上部架構体20が一体となって水平方向に相対移動可能となっている。 In the above building 1, the seismic isolation device 14 allows the lower girder 12, the lower suspension frame 13, and the upper frame 20 to move relative to the lower girder support frame 11 in the horizontal direction. ..

以上の建物1を構築する手順について、図2および図3のフローチャートを参照しながら説明する。図2は、建物1の主要な構築手順であり、図3は、建物1の詳細な構築手順である。
建物1の構築手順は、仮支柱30、32の上に吊り架構体13、23を構築する工程(後述のステップS1、S2、S11、S15)と、吊り架構体13、23の上方に大梁12、22を構築する工程(後述のステップS3、S12、S16)と、仮支柱30により吊り架構体13を押し上げる、または、大梁22に取り付けたジャッキ(例えば、後述の最上段の油圧ジャッキ34)により吊り架構体23を引っ張り上げることにより、吊り架構体13、23を上方に移動して大梁12、22に接合する工程(例えば、後述のステップS4、S13、S17)と、仮支柱30、32を撤去する工程(例えば、後述のステップS5、S14、S18)と、を備える。
The procedure for constructing the above building 1 will be described with reference to the flowcharts of FIGS. 2 and 3. FIG. 2 shows the main construction procedure of the building 1, and FIG. 3 shows the detailed construction procedure of the building 1.
The procedure for constructing the building 1 includes a step of constructing the suspended frames 13 and 23 on the temporary columns 30 and 32 (steps S1, S2, S11 and S15 described later) and a girder 12 above the suspended frames 13 and 23. , 22 (steps S3, S12, S16 described later) and a jack (for example, the uppermost hydraulic jack 34 described later) that pushes up the suspension frame 13 by the temporary support column 30 or is attached to the girder 22. The steps of moving the suspended frames 13 and 23 upward and joining them to the girders 12 and 22 by pulling up the suspended frame 23 (for example, steps S4, S13 and S17 described later) and the temporary columns 30 and 32 are performed. A step of removing (for example, steps S5, S14, and S18 described later) is provided.

まず、ステップS1では、大梁支持架構体11の床スラブまたは大梁12の上に仮支柱30を設置する(図4および図8参照)。
ステップS2では、大梁支持架構体11、21を構築するとともに、仮支柱30の上に吊り架構体13、23を構築する(図4および図8参照)。
ステップS3では、大梁支持架構体11、21の上に大梁12、22を構築する(図5および図9参照)。
ステップS4では、仮支柱30により吊り架構体13を押し上げる、または、大梁22に取り付けた油圧ジャッキ34により吊り架構体23を引っ張り上げることにより、吊り架構体13、23を上方に移動して、この吊り架構体13、23を大梁12、22に接合して、大梁12、22から吊り下げ支持する(図6参照)。
ステップS5では、油圧ジャッキ31および仮支柱30を撤去する(図6参照)。
First, in step S1, the temporary support column 30 is installed on the floor slab of the girder support frame 11 or the girder 12 (see FIGS. 4 and 8).
In step S2, the girder support frames 11 and 21 are constructed, and the suspended frames 13 and 23 are constructed on the temporary columns 30 (see FIGS. 4 and 8).
In step S3, the girders 12 and 22 are constructed on the girder support frames 11 and 21 (see FIGS. 5 and 9).
In step S4, the suspension frame 13 is moved upward by pushing up the suspension frame 13 by the temporary support column 30 or by pulling up the suspension frame 23 by the hydraulic jack 34 attached to the girder 22. The suspension frames 13 and 23 are joined to the girders 12 and 22 and suspended and supported from the girders 12 and 22 (see FIG. 6).
In step S5, the hydraulic jack 31 and the temporary support column 30 are removed (see FIG. 6).

次に、建物1を構築する詳細な手順について、図3のフローチャートを参照しながら説明する。
ステップS11では、図4に示すように、下部大梁支持架構体11を構築するとともに、この下部大梁支持架構体11の下部の床スラブの上に仮支柱30を設置する。この仮支柱30には、油圧ジャッキが内蔵されている。次に、下部大梁支持架構体11の上部に隣接して、仮支柱30の上に下部吊り架構体13を下層から上層に向かって構築する。このとき、下部吊り架構体13の所定の2フロアの柱16には、油圧ジャッキ31を設ける。つまり、下部吊り架構体13の各柱16は、下端部が仮支柱30で支持されるとともに、中間の2箇所に油圧ジャッキ31が介装される。
Next, a detailed procedure for constructing the building 1 will be described with reference to the flowchart of FIG.
In step S11, as shown in FIG. 4, the lower girder support frame 11 is constructed, and the temporary support column 30 is installed on the floor slab below the lower girder support frame 11. A hydraulic jack is built in the temporary support column 30. Next, the lower suspension frame 13 is constructed on the temporary support column 30 from the lower layer to the upper layer adjacent to the upper part of the lower girder support frame 11. At this time, a hydraulic jack 31 is provided on the pillar 16 on the predetermined two floors of the lower suspension frame 13. That is, each column 16 of the lower suspension frame 13 is supported by a temporary column 30 at the lower end thereof, and hydraulic jacks 31 are interposed at two intermediate positions.

ステップS12では、図5に示すように、下部大梁支持架構体11の上方に下部大梁12を構築する。具体的には、下部大梁支持架構体11の上に免震装置14を取り付けて、この免震装置14の上に下部大梁12を構築する。
このとき、下部大梁12のスパン中央部を上方に湾曲させて、むくりを付けておく。これにより、下部大梁12が下部吊り架構体13の上方に所定間隔離れて配置される。
In step S12, as shown in FIG. 5, the lower girder 12 is constructed above the lower girder support frame 11. Specifically, the seismic isolation device 14 is mounted on the lower girder support frame 11, and the lower girder 12 is constructed on the seismic isolation device 14.
At this time, the central portion of the span of the lower girder 12 is curved upward to form a peel. As a result, the lower girders 12 are arranged above the lower suspension frame 13 at predetermined intervals.

ステップS13では、図6に示すように、仮支柱30のジャッキを駆動して下部吊り架構体13を下部大梁12に向かって上方に押し上げることにより、下部吊り架構体13を上方に移動し、下部大梁12に接合する。
その後、図7に示すように、仮支柱30のジャッキをジャッキダウンする。これにより、下部吊り架構体13が下部大梁12に吊り下げ支持されるとともに、下部大梁12のむくりが解消されて、下部大梁12が略水平となる。
In step S13, as shown in FIG. 6, by driving the jack of the temporary support column 30 and pushing the lower suspension frame 13 upward toward the lower girder 12, the lower suspension structure 13 is moved upward and the lower part is moved. Join to the girder 12.
After that, as shown in FIG. 7, the jack of the temporary support column 30 is jacked down. As a result, the lower suspension frame 13 is suspended and supported by the lower girder 12, and the peeling of the lower girder 12 is eliminated, so that the lower girder 12 becomes substantially horizontal.

なお、仮支柱30のジャッキをジャッキダウンすると、下部吊り架構体13の柱16に作用する荷重が大きくなり、柱16が軸方向に延びて長くなる。よって、下部吊り架構体13の所定フロアの柱16に設けた油圧ジャッキ31を駆動することで、下部吊り架構体13の柱16の長さを適宜調整する。
ステップS14では、図7に示すように、油圧ジャッキ31および仮支柱30を撤去する。
When the jack of the temporary support column 30 is jacked down, the load acting on the column 16 of the lower suspension structure 13 becomes large, and the column 16 extends in the axial direction and becomes long. Therefore, by driving the hydraulic jack 31 provided on the pillar 16 on the predetermined floor of the lower suspension frame 13, the length of the pillar 16 of the lower suspension structure 13 is appropriately adjusted.
In step S14, as shown in FIG. 7, the hydraulic jack 31 and the temporary support column 30 are removed.

ステップS15では、図8示すように、下部大梁12の上に、上部大梁支持架構体21および上部吊り架構体23を下層から上層に向かって構築する。
ここで、下部大梁12の上に、上部吊り架構体23の最下段の柱26Aの代わりに仮支柱32を設置し、上部吊り架構体23をこの仮支柱32の上に構築する。
また、上部吊り架構体23の3フロア毎に、柱26の柱頭部と直上階の床躯体27との間に、油圧ジャッキ31を設ける。また、油圧ジャッキ31を設けた階の直下階の柱26の柱頭部と3フロア下の上部大梁支持架構体21の柱24の柱脚部との間に、仮支持部材33を設ける。この仮支持部材33は、圧縮力が作用する棒状の圧縮材であり、この仮支持部材33により、上部吊り架構体23が上部大梁支持架構体21から仮支持される。
In step S15, as shown in FIG. 8, the upper girder support frame 21 and the upper suspension frame 23 are constructed on the lower girder 12 from the lower layer to the upper layer.
Here, a temporary support column 32 is installed on the lower girder 12 instead of the lowermost column 26A of the upper suspension frame structure 23, and the upper suspension frame structure 23 is constructed on the temporary support column 32.
Further, a hydraulic jack 31 is provided between the stigma of the pillar 26 and the floor skeleton 27 on the immediately above floor for each of the three floors of the upper suspension frame 23. Further, a temporary support member 33 is provided between the stigma of the column 26 on the floor directly below the floor where the hydraulic jack 31 is provided and the column base of the column 24 of the upper girder support frame 21 under the three floors. The temporary support member 33 is a rod-shaped compression material on which a compressive force acts, and the upper suspension frame 23 is temporarily supported from the upper girder support frame 21 by the temporary support member 33.

なお、本実施形態では、圧縮材である仮支持部材33を用いたが、これに限らず、図8中破線で示すように、引張材である仮支持部材33Aを用いてもよい。この仮支持部材33Aは、上部吊り架構体23の3フロア毎に、油圧ジャッキ31を設けた階の柱24の柱頭部と2フロア下の柱26の柱脚部との間、および、油圧ジャッキ31を設けた階の柱25の柱頭部と2フロア下の柱24の柱脚部との間に設けられる。これら仮支持部材33Aは、引張力が作用する棒状の引張材であり、この仮支持部材33Aにより、上部吊り架構体23が上部大梁支持架構体21から仮支持される。 In the present embodiment, the temporary support member 33 which is a compression material is used, but the present invention is not limited to this, and as shown by the broken line in FIG. 8, the temporary support member 33A which is a tension material may be used. The temporary support member 33A is provided between the stigma of the pillar 24 on the floor where the hydraulic jack 31 is provided and the pillar base of the pillar 26 two floors below, and the hydraulic jack on each of the three floors of the upper suspension structure 23. It is provided between the stigma of the pillar 25 on the floor where 31 is provided and the pillar base of the pillar 24 two floors below. These temporary support members 33A are rod-shaped tensile members on which a tensile force acts, and the upper suspension frame 23 is temporarily supported from the upper girder support frame 21 by the temporary support member 33A.

ステップS16では、図9示すように、上部大梁支持架構体21および上部吊り架構体23の上に上部大梁22を構築する。
このとき、上部大梁22のスパン中央部を上方に湾曲させて、むくりを付けておく。これにより、上部大梁22が上部吊り架構体23の上方に所定間隔離れて配置されるので、この上部吊り架構体23の柱24の頂部と上部大梁22との間に、油圧ジャッキ34を取り付ける。
In step S16, as shown in FIG. 9, the upper girder 22 is constructed on the upper girder support frame 21 and the upper suspension frame 23.
At this time, the central portion of the span of the upper girder 22 is curved upward to form a peel. As a result, the upper girder 22 is arranged above the upper suspension frame 23 at predetermined intervals, so that the hydraulic jack 34 is attached between the top of the pillar 24 of the upper suspension structure 23 and the upper girder 22.

ステップS17では、最上段の油圧ジャッキ34を駆動して上部吊り架構体23を上部大梁22に向かって上方に引っ張り上げることにより、下部吊り架構体13を上方に移動して、上部大梁22に接合する。これにより、上部吊り架構体23が上部大梁22に吊り下げ支持されるとともに、上部大梁22のむくりが解消されて、上部大梁22が略水平となる。
また、最上段の油圧ジャッキ34を駆動して上部吊り架構体23を上方に引っ張り上げることにより、最上段の仮支持部材33に作用する圧縮力が解除されるので、この仮支持部材33を撤去する。この作業を上層から下層に向かって繰り返す。
なお、上部吊り架構体23を上方に引っ張り上げると、上部吊り架構体23の柱26に作用する荷重が大きくなり、柱26が軸方向に延びて長くなる。よって、油圧ジャッキ31を駆動することで、この上部吊り架構体23の柱の長さを適宜調整する。
ステップS18では、油圧ジャッキ31および仮支柱32を撤去する。この仮支柱32を撤去した箇所には、上部吊り架構体23の最下段の柱26Aを構築する(図1参照)。
In step S17, the lower suspension frame 13 is moved upward and joined to the upper girder 22 by driving the uppermost hydraulic jack 34 and pulling the upper suspension structure 23 upward toward the upper girder 22. do. As a result, the upper suspension frame 23 is suspended and supported by the upper girder 22, and the peeling of the upper girder 22 is eliminated, so that the upper girder 22 becomes substantially horizontal.
Further, by driving the hydraulic jack 34 on the uppermost stage and pulling the upper suspension structure 23 upward, the compressive force acting on the temporary support member 33 on the uppermost stage is released, so that the temporary support member 33 is removed. do. This work is repeated from the upper layer to the lower layer.
When the upper suspension frame 23 is pulled upward, the load acting on the pillar 26 of the upper suspension structure 23 becomes large, and the pillar 26 extends in the axial direction and becomes long. Therefore, by driving the hydraulic jack 31, the length of the pillar of the upper suspension frame 23 is appropriately adjusted.
In step S18, the hydraulic jack 31 and the temporary support column 32 are removed. At the location where the temporary column 32 is removed, the lowermost column 26A of the upper suspension frame 23 is constructed (see FIG. 1).

本実施形態によれば、以下のような効果がある。
(1)複数階からなる吊り架構体13、23を仮支柱30、32で仮支持して構築し、その後、仮支柱30または油圧ジャッキ34により吊り架構体13、23を上方に移動して、大梁12、22から吊り下げ支持する。よって、大梁支持架構体11、21と吊り架構体13、23とを分離して同時期に構築することで、吊り架構体13、23を備える建物1を、短工期で構築できる。
また、吊り架構体13、23を大梁12、22から吊り下げ支持する構造であるため、これら吊り架構体13、23には上載荷重が作用しない。よって、吊り架構体13、23の梁や床にむくりを設ける必要がなく、吊り架構体13、23に早期に外装材を取り付けることができる。
According to this embodiment, there are the following effects.
(1) The suspension frames 13 and 23 composed of a plurality of floors are temporarily supported by the temporary columns 30 and 32, and then the suspension structures 13 and 23 are moved upward by the temporary columns 30 or the hydraulic jack 34. It is suspended and supported from the girders 12 and 22. Therefore, by separating the girder support frames 11 and 21 and the suspended frames 13 and 23 and constructing them at the same time, the building 1 provided with the suspended frames 13 and 23 can be constructed in a short construction period.
Further, since the suspended frame structures 13 and 23 are suspended and supported from the girders 12 and 22, no overload is applied to these suspended frame structures 13 and 23. Therefore, it is not necessary to provide the beams and floors of the suspended frames 13 and 23 with peeling, and the exterior material can be attached to the suspended frames 13 and 23 at an early stage.

(2)予め、吊り架構体13、23の重量による撓みを考慮して、大梁12、22のスパン中央を上方に湾曲させてむくりを設けておいたので、吊り架構体13、23を吊り上げた際、大梁12、22を略水平にできる。 (2) In consideration of the bending due to the weight of the suspended frames 13 and 23, the center of the span of the girders 12 and 22 is curved upward in advance to provide a peeling, so that the suspended frames 13 and 23 are lifted. At that time, the girders 12 and 22 can be made substantially horizontal.

(3)上部吊り架構体23を仮支持部材33で上部大梁支持架構体21から仮支持した。よって、上部吊り架構体23の重量の一部を上部大梁支持架構体21が負担するので、上部吊り架構体23の下方への撓み量を低減しつつ、仮支柱32に加わる鉛直荷重を低減できる。また、仮支持部材33を介して上部大梁支持架構体21が上部吊り架構体23の水平方向の揺れを拘束するので、建物1の構築過程において、上部大梁22と上部吊り架構体23が接合されていない状態であっても、上部吊り架構体23の耐震性能を確保できる。 (3) The upper suspension frame 23 was temporarily supported from the upper girder support frame 21 by the temporary support member 33. Therefore, since the upper girder support frame 21 bears a part of the weight of the upper suspension frame 23, the vertical load applied to the temporary support column 32 can be reduced while reducing the amount of downward bending of the upper suspension frame 23. .. Further, since the upper girder support frame 21 restrains the horizontal shaking of the upper suspension frame 23 via the temporary support member 33, the upper girder 22 and the upper suspension frame 23 are joined in the construction process of the building 1. Even if it is not in the state, the seismic performance of the upper suspension frame 23 can be ensured.

なお、本発明は前記実施形態に限定されるものではなく、本発明の目的を達成できる範囲での変形、改良等は本発明に含まれるものである。
例えば、本実施形態では、建物1の上部架構体20を構築する場合のみ、仮支持部材33により上部吊り架構体23を上部大梁支持架構体21から仮支持しながら、上部吊り架構体23を構築したが、これに限らない。例えば、建物1の下部架構体10を構築する際にも、仮支持部材を用いてもよいし、建物1の上部架構体20を構築する際に、仮支持部材を用いなくてもよい。
また、本実施形態では、建物1を、下部吊り架構体13を有する下部架構体10と、上部吊り架構体23を有する上部架構体20と、を上下二段に配置して構成したが、これに限らない。例えば、建物の下部架構体あるいは上部架構体のみを一段に配置して構成してもよい。
The present invention is not limited to the above-described embodiment, and modifications, improvements, and the like to the extent that the object of the present invention can be achieved are included in the present invention.
For example, in the present embodiment, only when constructing the upper frame 20 of the building 1, the upper suspension frame 23 is constructed while temporarily supporting the upper suspension frame 23 from the upper girder support frame 21 by the temporary support member 33. However, it is not limited to this. For example, the temporary support member may be used when constructing the lower frame 10 of the building 1, or the temporary support member may not be used when constructing the upper frame 20 of the building 1.
Further, in the present embodiment, the building 1 is configured by arranging the lower frame 10 having the lower frame 13 and the upper frame 20 having the upper frame 23 in two upper and lower stages. Not limited to. For example, only the lower frame structure or the upper frame structure of the building may be arranged and configured in one stage.

1…建物 10…下部架構体 11…下部大梁支持架構体(大梁支持架構体)
12…下部大梁(大梁) 13…下部吊り架構体(吊り架構体)
14…免震装置 15…免震層 16…下部吊り架構体の柱
20…上部架構体 21…上部大梁支持架構体(大梁支持架構体)
22…上部大梁(大梁) 23…上部吊り架構体(吊り架構体)
24、25…上部大梁支持架構体の柱 26…上部吊り架構体の柱
26A…上部吊り架構体の最下段の柱 27…床躯体
30…油圧ジャッキが内蔵された仮支柱 31…油圧ジャッキ
32…仮支柱 33、33A…仮支持部材 34…最上段の油圧ジャッキ
1 ... Building 10 ... Lower frame 11 ... Lower girder support frame (girder support frame)
12 ... Lower girder (girder) 13 ... Lower hanging frame (suspended frame)
14 ... Seismic isolation device 15 ... Seismic isolation layer 16 ... Pillars of lower suspended frame 20 ... Upper frame 21 ... Upper girder support frame (girder support frame)
22 ... Upper girder (girder) 23 ... Upper suspended frame (suspended frame)
24, 25 ... Pillars of the upper girder support frame 26 ... Pillars of the upper suspension frame 26A ... Pillars at the bottom of the upper suspension frame 27 ... Floor skeleton 30 ... Temporary columns with built-in hydraulic jacks 31 ... Hydraulic jacks 32 ... Temporary columns 33, 33A ... Temporary support member 34 ... Top hydraulic jack

Claims (3)

大梁と当該大梁に吊り下げ支持された吊り架構体と、当該吊り架構体に隣接して設けられて前記大梁を支持する大梁支持架構体と、を有する建物の構築方法であって、
仮支柱の上に前記吊り架構体を構築する工程と、
当該吊り架構体の上方に前記大梁を構築する工程と、
前記仮支柱により前記吊り架構体を下から押し上げる、または、前記大梁に取り付けたジャッキにより前記吊り架構体を引っ張り上げることにより、当該吊り架構体を上方に移動して、前記大梁に接合する工程と、
前記仮支柱を撤去する工程と、を備え
前記吊り架構体と当該大梁とを接合する工程では、前記吊り架構体の少なくとも一部を、前記大梁支持架構体から仮支持部材で仮支持することを特徴とする建物の構築方法。
It is a method of constructing a building having a girder , a suspended frame suspended and supported by the girder, and a girder supporting frame provided adjacent to the suspended frame and supporting the girder .
The process of constructing the suspended frame on the temporary support and
The process of constructing the girder above the suspended frame and
A step of moving the suspended frame upward by pushing up the suspended frame from below by the temporary support or pulling up the suspended frame by a jack attached to the girder to join the suspended frame to the girder. ,
The process of removing the temporary support is provided .
A method for constructing a building, characterized in that , in a step of joining the suspended frame and the girder, at least a part of the suspended frame is temporarily supported by a temporary support member from the girder support frame .
大梁と当該大梁に吊り下げ支持された吊り架構体と、当該吊り架構体に隣接して設けられて前記大梁を支持する大梁支持架構体と、を有する建物の構築方法であって、
仮支柱の上に前記吊り架構体を下層から上層に向かって構築するとともに、前記大梁支持架構体を下層から上層に向かって構築する工程と、
前記大梁支持架構体の上でかつ当該吊り架構体の上方に前記大梁を構築する工程と、
前記仮支柱により前記吊り架構体を下から押し上げることにより、当該吊り架構体を上方に移動して、前記大梁に接合する工程と、
前記仮支柱を撤去する工程と、を備えることを特徴とする建物の構築方法。
It is a method of constructing a building having a girder , a suspended frame suspended and supported by the girder, and a girder supporting frame provided adjacent to the suspended frame and supporting the girder .
A process of constructing the suspended frame from the lower layer to the upper layer on the temporary support and a process of constructing the girder support frame from the lower layer to the upper layer .
The process of constructing the girder on the girder support frame and above the suspended frame, and
A step of moving the suspended frame upward by pushing up the suspended frame from below by the temporary support and joining the suspended frame to the girder.
A method for constructing a building, which comprises a step of removing the temporary support.
前記大梁を構築する工程では、当該大梁のスパン中央部を上方に湾曲させることを特徴とする請求項1または2に記載の建物の構築方法。 The method for constructing a building according to claim 1 or 2 , wherein in the step of constructing the girder, the central portion of the span of the girder is curved upward.
JP2017197741A 2017-10-11 2017-10-11 How to build a building Active JP7005262B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017197741A JP7005262B2 (en) 2017-10-11 2017-10-11 How to build a building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017197741A JP7005262B2 (en) 2017-10-11 2017-10-11 How to build a building

Publications (2)

Publication Number Publication Date
JP2019070298A JP2019070298A (en) 2019-05-09
JP7005262B2 true JP7005262B2 (en) 2022-02-10

Family

ID=66441027

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017197741A Active JP7005262B2 (en) 2017-10-11 2017-10-11 How to build a building

Country Status (1)

Country Link
JP (1) JP7005262B2 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2974025B1 (en) 1998-11-10 1999-11-08 鹿島建設株式会社 Construction method of large span large beam upper frame

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2984700B2 (en) * 1990-11-07 1999-11-29 東急建設株式会社 Control method of installation distance in lift-up method of beam string
JPH0693663A (en) * 1992-09-11 1994-04-05 Maeda Corp Dome type roof structure and execution method thereof

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2974025B1 (en) 1998-11-10 1999-11-08 鹿島建設株式会社 Construction method of large span large beam upper frame

Also Published As

Publication number Publication date
JP2019070298A (en) 2019-05-09

Similar Documents

Publication Publication Date Title
JP6503716B2 (en) Demolition system and demolition method
JP2009073599A (en) Supporting structure of tower crane and climbing method
JP6474151B2 (en) Dismantling system and dismantling method
JP7005262B2 (en) How to build a building
JP5528311B2 (en) Demolition method for multi-story buildings
JPH08270232A (en) Demolishing method for steel structural building
JP5953186B2 (en) Simultaneous dismantling method of boiler and boiler building
JP7041463B2 (en) How to build a building
JP5003253B2 (en) RC beam construction method
JP2010255374A (en) Demolition method for skyscraper building
JP6879613B1 (en) Curing system at the time of building demolition and demolition method of the building to be demolished
JP6391134B2 (en) Dismantling method and dismantling system
JP6655936B2 (en) Construction method of structure
JP5737578B2 (en) Construction method of suspended structure
JP6418825B2 (en) Jack reaction force support member and building dismantling method using the reaction force support member
JP6751311B2 (en) Building construction method
JPH08270081A (en) Construction method of frame structure
JP2019190073A (en) Construction method of structure
JP5200416B2 (en) Construction method of suspended structure building, suspended structure building
JP2890341B2 (en) Method and apparatus for lifting up top-level frame for structure construction
JP6411832B2 (en) Temporary beam connecting member and structure construction method
JP5255914B2 (en) Dismantling method of boiler and boiler building
JP2021188318A (en) Building construction method
JP2009108476A (en) Building demolition method
JP2704447B2 (en) Lift-up method using permanent columns

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200929

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210712

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210830

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20211214

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220105

R150 Certificate of patent or registration of utility model

Ref document number: 7005262

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150