JP2021188318A - Building construction method - Google Patents

Building construction method Download PDF

Info

Publication number
JP2021188318A
JP2021188318A JP2020092913A JP2020092913A JP2021188318A JP 2021188318 A JP2021188318 A JP 2021188318A JP 2020092913 A JP2020092913 A JP 2020092913A JP 2020092913 A JP2020092913 A JP 2020092913A JP 2021188318 A JP2021188318 A JP 2021188318A
Authority
JP
Japan
Prior art keywords
src
building
steel
building frame
constructed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2020092913A
Other languages
Japanese (ja)
Other versions
JP7462475B2 (en
Inventor
哲也 黒田
Tetsuya Kuroda
直樹 宮本
Naoki Miyamoto
憲之 藤田
Noriyuki Fujita
信一 井上
Shinichi Inoue
一高 小島
Kazutaka Kojima
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP2020092913A priority Critical patent/JP7462475B2/en
Publication of JP2021188318A publication Critical patent/JP2021188318A/en
Application granted granted Critical
Publication of JP7462475B2 publication Critical patent/JP7462475B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

To provide a building construction method which can effectively avoid post-construction jobs for cranes such as temporary openings and reduce the work and time for preliminary construction of the steel structure of the building frame and shorten the construction period by constructing the steel structure of the building frame in advance and installing stationary cranes on top of it.SOLUTION: A construction method of a building with a multi-story building frame 1 includes a preceding process for constructing a steel structure part 20A of an SRC part 20 which is an SRC structure from the lower floor side to the upper floor side in a part of a plan view of the building frame 1 and a follow-up process in which a stationary crane K is installed on the top of the steel structure part 20A of the SRC part 20 constructed in the preceding process to construct the remaining part of the building frame 1.SELECTED DRAWING: Figure 2

Description

本発明は、複数層の建物躯体を有する建物の構築方法に関する。 The present invention relates to a method for constructing a building having a multi-story building frame.

敷地内の建物躯体の周囲にクレーンの設置スペースを確保できない工事条件で複数層を有する建物を構築する場合には、建物躯体の平面視の一部分の下層側にクライミング式のクレーンを設置して建物躯体を構築するのが一般的である。この場合、各階のスラブを構築する際に、クライミング式のクレーンがクライミングするための仮設開口を形成してクレーンをクライミングさせながら建物躯体を下層側から上層側に向かって構築している。
しかしながら、各階のスラブに形成されるクレーン用の仮設開口が、建物躯体の上層側まで構築してクレーンを撤去するまで残ることになり、その仮設開口を鉄筋コンクリートで閉塞する閉塞部が、クレーンの撤去後に構築する後施工部となって工期が長期化する弊害がある。
When constructing a building with multiple layers under construction conditions where it is not possible to secure a space for installing a crane around the building frame on the site, a climbing crane is installed on the lower layer side of a part of the plan view of the building frame. It is common to build a skeleton. In this case, when constructing the slabs on each floor, a temporary opening for climbing is formed by the climbing type crane, and the building frame is constructed from the lower layer side to the upper layer side while climbing the crane.
However, the temporary opening for the crane formed in the slab on each floor will remain until the crane is removed by constructing it up to the upper layer side of the building frame, and the closed part that closes the temporary opening with reinforced concrete will remove the crane. It has the harmful effect of prolonging the construction period as it becomes a post-construction part to be constructed later.

この点、特許文献1には、複数層の建物躯体の平面視の全部が下層側から上層側までSRC造(鉄骨鉄筋コンクリート造)のSRC部分又はS造(鉄骨造)のS造部分とされる建物を構築する場合に、建物躯体の平面視の全部のSRC部分又はS造部分の鉄骨構造部を先行構築し、その鉄骨構造部の上部(屋上)に定置式のクレーンを設置して建物躯体の残りの部分を構築する技術が提案されている。 In this regard, in Patent Document 1, the entire plan view of the multi-story building frame is defined as an SRC portion of SRC structure (steel reinforced concrete structure) or an S structure portion of S structure (steel frame structure) from the lower layer side to the upper layer side. When constructing a building, the entire SRC part or the steel structure part of the S structure part in the plan view of the building frame is constructed in advance, and a stationary crane is installed on the upper part (rooftop) of the steel structure part to install the building frame. Techniques have been proposed to build the rest of the.

特開2000−226187号公報Japanese Unexamined Patent Publication No. 2000-226187

特許文献1に記載の建物の構築方法によれば、先行構築した建物躯体の鉄骨構造部の上部に定置式のクレーンを設置するので、クライミング式のクレーン用の仮設開口を各階のスラブに形成する必要がなく、クレーン用の仮設開口の閉塞部のような後施工部の発生は回避することができる。
ところが、クレーンの設置前のタイミングで、複数層の建物躯体の平面視の全部において下層側から上層側まで亘って鉄骨構造部を構築するので、その鉄骨構造部の構築に手間や時間がかかることになり、工期の短縮を効果的に図ることができないという問題がある。
According to the building construction method described in Patent Document 1, since a stationary crane is installed on the upper part of the steel structure portion of the building frame previously constructed, a temporary opening for a climbing crane is formed in the slab of each floor. It is not necessary, and it is possible to avoid the occurrence of a post-construction part such as a closed part of a temporary opening for a crane.
However, at the timing before the installation of the crane, the steel structure part is constructed from the lower layer side to the upper layer side in the entire plan view of the multi-story building frame, so it takes time and effort to construct the steel frame structure part. Therefore, there is a problem that the construction period cannot be effectively shortened.

この実情に鑑み、本発明の主たる課題は、建物躯体の鉄骨構造部を先行構築し、その上部に定置式のクレーンを設置することで、仮設開口のようなクレーンのための後施工部の発生を回避しながら、建物躯体の鉄骨構造部の先行構築の手間と時間も削減して工期の短縮を効果的に図ることのできる建物の構築方法を提供する点にある。 In view of this situation, the main problem of the present invention is to construct the steel structure part of the building frame in advance and install a stationary crane on the upper part to generate a post-construction part for the crane such as a temporary opening. The point is to provide a building construction method that can effectively shorten the construction period by reducing the labor and time for the advance construction of the steel structure part of the building frame while avoiding the above.

本発明の第1特徴構成は、複数層の建物躯体を有する建物の構築方法であって、
前記建物躯体の平面視の一部分で下層側から上層側までSRC造とされるSRC部分の鉄骨構造部を構築する先行工程と、
前記先行工程で構築した前記SRC部分の鉄骨構造部の上部に定置式のクレーンを設置して前記建物躯体における平面視で前記SRC部分の周囲に位置する部分を構築する後行工程と、を備える点にある。
The first characteristic configuration of the present invention is a method for constructing a building having a multi-story building frame.
The preceding process of constructing the steel structure part of the SRC part, which is an SRC structure from the lower layer side to the upper layer side in a part of the plan view of the building frame,
A subsequent step of installing a stationary crane on the upper part of the steel structure portion of the SRC portion constructed in the preceding step and constructing a portion located around the SRC portion in a plan view of the building frame is provided. At the point.

本構成によれば、先行工程において、建物躯体の平面視の一部分で下層側から上層側までSRC造のSRC部分の鉄骨建方工事を実施してSRC部分の鉄骨構造部を構築する。この下層側から上層側まで亘るSRC部分は、建物躯体の平面視の一部分であるので、少ない手間と時間で構築することができる。また、敷地内における当該SRC部分の周囲の空間を利用して構築作業を行うことも可能となる。
次いで、後行工程において、下層側から上層側まで亘るSRC部分の鉄骨構造部の上部に定置式のクレーンを設置することで、建物躯体における平面視でSRC部分の周囲に位置する部分よりも高い位置にクレーンを設置する。
そして、その高い位置に設置したクレーンを使用し、建物躯体における平面視でSRC部分の周囲に位置する部分を構築することができる。
よって、仮設開口のようなクレーンのための後施工部の発生を回避しながら、建物躯体の鉄骨構造部の先行構築の手間と時間も削減して工期の短縮を効果的に図ることができる。
According to this configuration, in the preceding process, the steel frame construction work of the SRC part of the SRC structure is carried out from the lower layer side to the upper layer side in a part of the plan view of the building frame to construct the steel frame structure part of the SRC part. Since the SRC portion extending from the lower layer side to the upper layer side is a part of the plan view of the building frame, it can be constructed with less effort and time. In addition, it is possible to carry out the construction work using the space around the SRC portion in the site.
Next, in the subsequent process, by installing a stationary crane on the upper part of the steel structure part of the SRC part extending from the lower layer side to the upper layer side, it is higher than the part located around the SRC part in the plan view of the building frame. Install a crane at the position.
Then, using the crane installed at the high position, it is possible to construct a portion located around the SRC portion in a plan view of the building frame.
Therefore, it is possible to effectively shorten the construction period by reducing the labor and time for pre-construction of the steel structure part of the building frame while avoiding the occurrence of the post-construction part for the crane such as the temporary opening.

本発明の第2特徴構成は、前記SRC部分が、前記建物躯体を構築するのに先立ってRC造からSRC造に設計変更されたものである点にある。 The second characteristic configuration of the present invention is that the SRC portion is redesigned from an RC structure to an SRC structure prior to constructing the building frame.

本構成によれば、原設計でRC造とされる建物躯体の平面視の一部分を耐震性等の面で安全サイドのSRC造に設計変更することによって、定置式のクレーンを設置するためのSRC部分を創出することができ、定置式のクレーンを設置するためのSRC部分が原設計に存在しない場合でも、先行工程と後行工程を実施して工期の短縮を効果的に図ることができる。 According to this configuration, SRC for installing a stationary crane by changing the design of a part of the plan view of the building frame, which is the RC structure in the original design, to the SRC structure on the safety side in terms of earthquake resistance, etc. A part can be created, and even if the SRC part for installing a stationary crane does not exist in the original design, the preceding process and the following process can be carried out to effectively shorten the construction period.

本発明の第3特徴構成は、前記SRC部分が本設鉄骨階段を含み、
前記先行工程にて前記本設鉄骨階段を構築する点にある。
In the third characteristic configuration of the present invention, the SRC portion includes a main steel frame staircase.
The point is to construct the main steel staircase in the preceding process.

本構成によれば、先行工程でSRC部分に含まれる本設鉄骨階段を構築するので、仮設階段を設置することなく、本設鉄骨階段を使用して後行工程にて建物躯体の残りの部分を構築することができ、後行工程を効率良く実施することができる。 According to this configuration, since the main steel stairs included in the SRC part are constructed in the preceding process, the rest of the building frame is constructed in the subsequent process using the main steel stairs without installing temporary stairs. Can be constructed, and the subsequent process can be carried out efficiently.

本発明の第4特徴構成は、前記SRC部分が本設エレベータシャフトを含み、
前記先行工程にて前記本設エレベータシャフトを構築し、
前記本設エレベータシャフトに本設エレベータを設置して前記後行工程を実施する点にある。
In the fourth characteristic configuration of the present invention, the SRC portion includes a main elevator shaft.
The main elevator shaft is constructed in the preceding process, and the main elevator shaft is constructed.
The point is that the main elevator is installed on the main elevator shaft to carry out the subsequent process.

本構成によれば、先行工程でSRC部分に含まれる本設エレベータシャフトを構築し、その本設エレベータシャフトに本設エレベータを設置して後行工程を実施するので、仮設エレベータシャフトや仮設エレベータを設置することなく、本設エレベータを使用して後行工程にて建物躯体の残りの部分を構築することができ、後行工程を効率良く実施することができる。 According to this configuration, the main elevator shaft included in the SRC part is constructed in the preceding process, and the main elevator is installed on the main elevator shaft to carry out the subsequent process. Therefore, the temporary elevator shaft and the temporary elevator can be used. The remaining part of the building skeleton can be constructed in the follow-up process using the main elevator without installation, and the follow-up process can be carried out efficiently.

建物の構築方法を示す立面図Elevation showing how to build a building 建物の構築方法を示す立面図Elevation showing how to build a building 建物の構築方法を示す立面図Elevation showing how to build a building コア部分の配置を示す平面図Plan view showing the arrangement of the core part

本発明に係る建物の構築方法の実施形態を図面に基づいて説明する。
本建物の構築方法(以下、単に本工法と称する場合がある)で構築される建物は、図3に示すように、複数層の建物躯体1を有する建物として構成される。建物躯体1は、基礎2、及び、それに支持される柱3や梁4、スラブ(図示省略)等から構成される。
An embodiment of a building construction method according to the present invention will be described with reference to the drawings.
As shown in FIG. 3, the building constructed by the construction method of the present building (hereinafter, may be simply referred to as the present construction method) is configured as a building having a multi-story building frame 1. The building frame 1 is composed of a foundation 2, columns 3 and beams 4 supported by the foundation 2, slabs (not shown), and the like.

建物躯体1は、主にはRC造(鉄筋コンクリート造)とされており、低層階部分10(図示例では2階床構造以下の部分)の全部、及び、図3及び図4に示すように、平面視の一部分で下層側の最下階から上層側の最上階に亘るコア部分20(SRC部分に相当する)がSRC造とされ、その他の部分30がRC造とされる。 The building frame 1 is mainly made of RC structure (reinforced concrete structure), and the entire lower floor portion 10 (the portion below the second floor structure in the illustrated example) and, as shown in FIGS. 3 and 4, are shown. The core portion 20 (corresponding to the SRC portion) extending from the lowest floor on the lower layer side to the uppermost floor on the upper layer side in a part of the plan view is made of SRC structure, and the other part 30 is made of RC structure.

コア部分20は、設備スペースや耐震要素などが集中的に配置されるもので、その内部には、下層側の最下階から上層側の最上階に亘る本設鉄骨階段5や本設エレベータシャフト6等が含まれる。本設エレベータシャフト6は、コア部分20において各階のスラブを貫通して下層側の最下階から上層側の最上階に亘って延びる空間である。 The core portion 20 is where equipment space, seismic elements, etc. are centrally arranged, and inside it, a main steel staircase 5 and a main elevator shaft extending from the lowest floor on the lower layer side to the uppermost floor on the upper layer side. 6 etc. are included. The main elevator shaft 6 is a space that penetrates the slabs of each floor in the core portion 20 and extends from the lowermost floor on the lower layer side to the uppermost floor on the upper layer side.

SRC造の低層階部分10及びコア部分20は、当初の原設計ではRC造とされていたが、建物躯体1を構築するのに先立って実施される施工計画の際に本工法を実施するためにRC造からSRC造に設計変更されたものである。そして、本工法は、当該設計変更を活かして後述する先行工程と後行工程とを順番に実施することで、敷地S内で建物躯体1の周囲にクレーン設置スペースや資材搬入経路を確保できない工事条件であっても、建物躯体1の構築を短工期で効率良く行うことができる。以下、本工法の各工程について順番に説明する。 The lower floor part 10 and core part 20 of the SRC structure were originally made of RC structure in the original design, but in order to implement this method in the construction plan to be carried out prior to the construction of the building frame 1. The design was changed from RC structure to SRC structure. In this construction method, by utilizing the design change and carrying out the preceding process and the following process, which will be described later, in order, it is not possible to secure a crane installation space and a material carry-in route around the building frame 1 in the site S. Even under the conditions, the building frame 1 can be efficiently constructed in a short construction period. Hereinafter, each step of this method will be described in order.

(先行工程)
図1に示すように、先行工程では、基礎2を構築した後、SRC造のコア部分20の鉄骨建方工事を実施し、基礎2の上にコア部分20の鉄骨構造部20Aを構築する。コア部分20の鉄骨構造部20Aは、最下階から最上階に亘るもので、多数の柱鉄骨3aと多数の梁鉄骨4aとを組み付けて構成される。
SRC造のコア部分20は、図4に示すように、建物躯体1の平面視の一部分であるので、少ない手間と時間で構築することができる。また、敷地S内におけるコア部分20の周囲の空間を利用してコア部分20の鉄骨構造部20Aの構築作業を行うことができる。
(Preceding process)
As shown in FIG. 1, in the preceding process, after the foundation 2 is constructed, the steel frame construction work of the core portion 20 of the SRC structure is carried out, and the steel structure portion 20A of the core portion 20 is constructed on the foundation 2. The steel structure portion 20A of the core portion 20 extends from the lowest floor to the top floor, and is configured by assembling a large number of column steel frames 3a and a large number of beam steel frames 4a.
As shown in FIG. 4, the core portion 20 of the SRC structure is a part of the plan view of the building frame 1, so that it can be constructed with less effort and time. Further, the construction work of the steel frame structure portion 20A of the core portion 20 can be performed by utilizing the space around the core portion 20 in the site S.

また、このとき、コア部分20に含まれる本設鉄骨階段5と本設エレベータシャフト6も併せて構築する。このような早いタイミングで本設鉄骨階段5を設置することで、仮設階段を設置することなく、本設鉄骨階段5を使用して以降の工事を行うことができる。 At this time, the main steel frame stairs 5 and the main elevator shaft 6 included in the core portion 20 are also constructed. By installing the main steel frame stairs 5 at such an early timing, it is possible to carry out the subsequent construction using the main steel frame stairs 5 without installing the temporary stairs.

更に、本実施形態では、図1に示すように、SRC造の低層階部分10の鉄骨建方工事を実施し、基礎2の上に低層階部分10の鉄骨構造部10Aを構築する。低層階部分10の鉄骨構造部10Aも柱鉄骨3aと梁鉄骨4aとを組み付けて構成される。
SRC造の低層階部分10の鉄骨構造部10Aを構築することで、複数階分の高さを有するコア部分20の鉄骨構造部20Aの足元側を頑丈に固定することができ、コア部分20の鉄骨構造部20Aを一層安定させることができる。
なお、この低層階部分10の鉄骨構造部10Aは、後述する後行工程にてコア部分20の鉄骨構造部20Aの上部に定置式のクレーンKを設置した後、当該クレーンKを使用して構築してもよい。
Further, in the present embodiment, as shown in FIG. 1, the steel frame construction work of the lower floor portion 10 of the SRC structure is carried out, and the steel structure portion 10A of the lower floor portion 10 is constructed on the foundation 2. The steel structure portion 10A of the lower floor portion 10 is also configured by assembling the column steel frame 3a and the beam steel frame 4a.
By constructing the steel structure portion 10A of the lower floor portion 10 of the SRC structure, the foot side of the steel structure portion 20A of the core portion 20 having the heights of a plurality of floors can be firmly fixed, and the core portion 20 can be firmly fixed. The steel structure portion 20A can be further stabilized.
The steel frame structure portion 10A of the lower floor portion 10 is constructed by using the crane K after installing a stationary crane K on the steel frame structure portion 20A of the core portion 20 in a subsequent process described later. You may.

(後行工程)
この後行工程では、図2に示すように、まず、先行工程にて構築したコア部分20の鉄骨構造部20Aの上部に定置式のクレーンKを設置する。
定置式のクレーンKは、例えば、コア部分20の鉄骨構造部20Aの最上階の梁鉄骨4aの間に複数本の受け梁k1を亘らせ、その複数本の受け梁k1の上に設置する等の方法でコア部分20の鉄骨構造部20Aの上部に設置することができる。
ちなみに、コア部分20は、図4に示すように、平面視L字状等の倒れ難い形状とすることができ、定置式のクレーンKは、コア部分20の鉄骨構造部20Aの上面における重心位置等に配置される。
(Following process)
In this subsequent step, as shown in FIG. 2, first, a stationary crane K is installed on the upper part of the steel structure portion 20A of the core portion 20 constructed in the preceding step.
The stationary crane K is installed on, for example, a plurality of receiving beams k1 extending between the beam steel frames 4a on the uppermost floor of the steel frame structure portion 20A of the core portion 20 and the plurality of receiving beams k1. It can be installed on the upper part of the steel frame structure portion 20A of the core portion 20 by such a method.
By the way, as shown in FIG. 4, the core portion 20 can have a shape that does not easily fall, such as an L-shape in a plan view, and the stationary crane K has a center of gravity position on the upper surface of the steel frame structure portion 20A of the core portion 20. Etc. are placed.

また、この後行工程の途中等の適宜のタイミングでコア部分20の鉄骨構造部20Aに本設エレベータ7を設置する。このような早いタイミングで本設エレベータ7を設置することで、仮設エレベータを設置することなく、本設エレベータ7を使用して以降の工事を行うことができる。本設エレベータ7は、本設エレベータシャフト6内に配置されるエレベータ籠7Aと、当該エレベータ籠をロープ等を用いて昇降させる昇降装置(図示省略)等から構成される。 Further, the main elevator 7 is installed in the steel structure portion 20A of the core portion 20 at an appropriate timing such as in the middle of the subsequent process. By installing the main elevator 7 at such an early timing, it is possible to carry out the subsequent construction using the main elevator 7 without installing the temporary elevator. The main elevator 7 is composed of an elevator cage 7A arranged in the main elevator shaft 6, an elevating device (not shown) for raising and lowering the elevator cage using a rope or the like.

そして、図2、図3に示すように、コア部分20の鉄骨構造部20Aの上部に設置された定置式のクレーンK、コア部分20の鉄骨構造部20Aに設置された本設鉄骨階段5、本設エレベータ7を使用して、配筋工事、型枠工事、コンクリート打設工事を順に実施し、建物躯体1における平面視でコア部分20の周囲に位置する部分を含む建物躯体1の残りの部分を下層側から上層側に向かって順番に構築する。 Then, as shown in FIGS. 2 and 3, a stationary crane K installed on the upper part of the steel structure portion 20A of the core portion 20, and a main steel staircase 5 installed on the steel structure portion 20A of the core portion 20. Reinforcing work, formwork work, and concrete placing work are carried out in order using the main elevator 7, and the rest of the building skeleton 1 including the part located around the core part 20 in the plan view of the building skeleton 1 The parts are constructed in order from the lower layer side to the upper layer side.

具体的には、SRC造のコア部分20は、定置式のクレーンKで建築資材等を揚重し、鉄骨構造部20Aの柱鉄骨3aや梁鉄骨4aの周囲やスラブの構築箇所に鉄筋及び型枠を配置した上でコンクリートを打設することにより、コア部分20のSRC造の柱3や梁4やスラブ等を構築する。 Specifically, in the core portion 20 of the SRC structure, building materials and the like are lifted by a stationary crane K, and reinforcing bars and molds are placed around the pillar steel frame 3a and the beam steel frame 4a of the steel structure portion 20A and at the construction location of the slab. By placing concrete after arranging the frame, the SRC pillar 3, beam 4, slab, etc. of the core portion 20 are constructed.

SRC造の低層階部分10は、定置式のクレーンKで建築資材等を揚重し、鉄骨構造部10Aの柱鉄骨3aや梁鉄骨4aの周囲やスラブの構築箇所に鉄筋及び型枠を配置した上でコンクリートを打設することにより、低層階部分10のSRC造の柱3や梁4やスラブ等を構築する。
このとき、低層階部分10のSRC造の梁4やスラブ等を構成するための型枠には、梁鉄骨4aから吊り下げ状態で支持される吊り型枠を使用する。このようにすることで、資材搬入の邪魔になる下階床から型枠を支えるパイプサポート等の支保工を無くすことができ、低層階部分10の内部に資材搬入経路を適切に確保することができる。
In the lower floor portion 10 of the SRC structure, building materials and the like are lifted by a stationary crane K, and reinforcing bars and formwork are arranged around the pillar steel frame 3a and the beam steel frame 4a of the steel structure portion 10A and at the construction location of the slab. By placing concrete on the top, SRC pillars 3, beams 4, slabs, etc. of the lower floor portion 10 are constructed.
At this time, a suspended formwork supported from the beam steel frame 4a in a suspended state is used as the formwork for forming the SRC beam 4 or the slab of the lower floor portion 10. By doing so, it is possible to eliminate the support work such as the pipe support that supports the formwork from the lower floor that interferes with the material import, and it is possible to appropriately secure the material import route inside the lower floor portion 10. can.

SRC造のコア部分20及び低層階部分10以外のRC造の部分30は、定置式のクレーンKを使用し、鉄筋及び型枠を配置した上でコンクリートを打設することにより、RC造の柱3や梁4やスラブ等を構築する。そして、全ての工事が完了したら定置式のクレーンKを撤去する。 For the RC part 30 other than the core part 20 and the lower floor part 10 of the SRC structure, a stationary crane K is used, and concrete is cast after arranging the reinforcing bars and formwork to form the columns of the RC structure. Build 3, beam 4, slab, etc. Then, when all the construction work is completed, the stationary crane K is removed.

〔別実施形態〕
本発明の他の実施形態について説明する。
なお、以下に説明する各実施形態の構成は、夫々単独で適用することに限らず、他の実施形態の構成と組み合わせて適用することも可能である。
[Another Embodiment]
Other embodiments of the present invention will be described.
It should be noted that the configurations of the respective embodiments described below are not limited to being applied independently, but can also be applied in combination with the configurations of other embodiments.

(1)上記実施形態では、設備スペースや耐震要素などが集中的に配置されるコア部分20を、定置式のクレーンKを上部に設置するためのSRC部分とする場合を例に示したが、建物躯体1におけるコア部分20以外の部分を定置式のクレーンKを上部に設置するためのSRC部分としてもよい。 (1) In the above embodiment, the case where the core portion 20 in which the equipment space and the seismic elements are intensively arranged is used as the SRC portion for installing the stationary crane K at the upper part is shown as an example. A portion of the building frame 1 other than the core portion 20 may be used as an SRC portion for installing the stationary crane K at the upper part.

(2)建物躯体1における定置式のクレーンKを上部に設置するためのSRC部分(コア部分20)以外の部分10、30は、前述の実施形態で示したSRC造やRC造に限らず、各種の構造を採用することができる。 (2) The parts 10 and 30 other than the SRC part (core part 20) for installing the stationary crane K in the building frame 1 are not limited to the SRC structure and the RC structure shown in the above-described embodiment. Various structures can be adopted.

(3)前述の実施形態では、建物躯体1における定置式のクレーンKを上部に設置するためのSRC部分(コア部分20)以外の部分10、30は、前述の実施形態で示したSRC造やRC造に限らず、各種の構造を採用することができる。 (3) In the above-described embodiment, the portions 10 and 30 other than the SRC portion (core portion 20) for installing the stationary crane K in the building frame 1 are the SRC structure shown in the above-described embodiment. Not limited to RC construction, various structures can be adopted.

(4)本発明は、高層、中層、低層の各種の建物の構築に適用することができ、特に、中層や低層の建物の構築に好適に適用することができる。 (4) The present invention can be applied to the construction of various high-rise, middle-rise, and low-rise buildings, and in particular, can be suitably applied to the construction of middle-rise and low-rise buildings.

1 建物躯体
5 本設鉄骨階段
6 本設エレベータシャフト
7 本設エレベータ
20 コア部分(SRC部分)
20A 鉄骨構造部
K 定置式のクレーン

1 Building frame 5 Main steel stairs 6 Main elevator shaft 7 Main elevator 20 Core part (SRC part)
20A Steel structure K Stationary crane

Claims (4)

複数層の建物躯体を有する建物の構築方法であって、
前記建物躯体の平面視の一部分で下層側から上層側までSRC造とされるSRC部分の鉄骨構造部を構築する先行工程と、
前記先行工程で構築した前記SRC部分の鉄骨構造部の上部に定置式のクレーンを設置して前記建物躯体における平面視で前記SRC部分の周囲に位置する部分を構築する後行工程と、を備える建物の構築方法。
It is a method of constructing a building with a multi-story building frame.
The preceding process of constructing the steel structure part of the SRC part, which is an SRC structure from the lower layer side to the upper layer side in a part of the plan view of the building frame,
A subsequent step of installing a stationary crane on the upper part of the steel structure portion of the SRC portion constructed in the preceding step and constructing a portion located around the SRC portion in a plan view of the building frame is provided. How to build a building.
前記SRC部分が、前記建物躯体を構築するのに先立ってRC造からSRC造に設計変更されたものである請求項1記載の建物の構築方法。 The building construction method according to claim 1, wherein the SRC portion is redesigned from an RC structure to an SRC structure prior to constructing the building frame. 前記SRC部分が本設鉄骨階段を含み、
前記先行工程にて前記本設鉄骨階段を構築する請求項1又は2記載の建物の構築方法。
The SRC portion includes the main steel staircase
The building construction method according to claim 1 or 2, wherein the main steel frame staircase is constructed in the preceding step.
前記SRC部分が本設エレベータシャフトを含み、
前記先行工程にて前記本設エレベータシャフトを構築し、
前記本設エレベータシャフトに本設エレベータを設置して前記後行工程を実施する請求項1〜3のいずれか1項に記載の建物の構築方法。

The SRC portion includes the main elevator shaft.
The main elevator shaft is constructed in the preceding process, and the main elevator shaft is constructed.
The method for constructing a building according to any one of claims 1 to 3, wherein the main elevator is installed on the main elevator shaft and the subsequent process is carried out.

JP2020092913A 2020-05-28 2020-05-28 How to build a building Active JP7462475B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020092913A JP7462475B2 (en) 2020-05-28 2020-05-28 How to build a building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020092913A JP7462475B2 (en) 2020-05-28 2020-05-28 How to build a building

Publications (2)

Publication Number Publication Date
JP2021188318A true JP2021188318A (en) 2021-12-13
JP7462475B2 JP7462475B2 (en) 2024-04-05

Family

ID=78848340

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020092913A Active JP7462475B2 (en) 2020-05-28 2020-05-28 How to build a building

Country Status (1)

Country Link
JP (1) JP7462475B2 (en)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000226187A (en) 1999-02-04 2000-08-15 Kumagai Gumi Co Ltd Installation method of tower crane

Also Published As

Publication number Publication date
JP7462475B2 (en) 2024-04-05

Similar Documents

Publication Publication Date Title
KR100968068B1 (en) Multi-Horizontal Structure Member Forming Method
JP2014227651A (en) Building demolition system
JP5977412B2 (en) Basement of new building using existing building
JPH09317183A (en) Construction method of building
JP2021188318A (en) Building construction method
JP2010255374A (en) Demolition method for skyscraper building
JP2017214738A (en) Demolition system and demolition method for high-rise building
JP6391134B2 (en) Dismantling method and dismantling system
JP6991625B1 (en) Anti-scattering curing system and structure dismantling method using it
JP5003253B2 (en) RC beam construction method
JP6449637B2 (en) Building construction method
JP5925231B2 (en) Building construction method and underground building of new building
JP6088926B2 (en) Structure reconstruction method
JP6093665B2 (en) Structure reconstruction method
JP7012486B2 (en) Bridge construction method
JP6418825B2 (en) Jack reaction force support member and building dismantling method using the reaction force support member
JPH08239906A (en) Construction of building
KR102394812B1 (en) Method for constructing precast flat slab
JP2023004557A (en) Building demolition method
JP2024000601A (en) Construction method of building
KR101219466B1 (en) Method for constructing framework and outer window simultaneously
JP6814717B2 (en) How to install horizontal members and how to build a building frame
JP3328790B2 (en) High-rise building assembly method
JP7034630B2 (en) Dismantling method
JP2009299346A (en) Construction method of building

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230330

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20231227

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20240105

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240221

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240313

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240326

R150 Certificate of patent or registration of utility model

Ref document number: 7462475

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150