JP2009299346A - Construction method of building - Google Patents

Construction method of building Download PDF

Info

Publication number
JP2009299346A
JP2009299346A JP2008154905A JP2008154905A JP2009299346A JP 2009299346 A JP2009299346 A JP 2009299346A JP 2008154905 A JP2008154905 A JP 2008154905A JP 2008154905 A JP2008154905 A JP 2008154905A JP 2009299346 A JP2009299346 A JP 2009299346A
Authority
JP
Japan
Prior art keywords
slab
pillar
column
slabs
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2008154905A
Other languages
Japanese (ja)
Inventor
Norihiro Kawakami
川上憲広
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP2008154905A priority Critical patent/JP2009299346A/en
Publication of JP2009299346A publication Critical patent/JP2009299346A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction method of a building that can reduce a construction period without needing high lift work while preventing the building from becoming an unstable structure in the initial stage of construction. <P>SOLUTION: The construction method of the building includes placing the N-number of slabs 12-14 sequentially, then lifting the slabs 13, 14 other than the first slab up to predetermined positions with wires 24 through pulleys 21 mounted to the top parts of columns 2, temporarily fastening the respective slabs 13, 14 to the upper parts of the columns 2, lifting the first slab 12 with the wires 24, mounting one ends of braces 31 turnably to the lower face of the first slab 12, mounting rollable pulleys 23 with rollers to the other ends of the braces 31, pulling wires 25 wound on the pulleys 23 to push up the first slab 12 by the braces 31 to thereby lift the first slab 12 into a predetermined position, fixing the first slab 12 to the columns 2, and fixing the second to Nth slabs 13, 14 sequentially to the columns 2 in the same way. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

本発明は、建築物の施工方法に関し、より詳細には、屋根スラブや床スラブを予め打設した後、屋根スラブや床スラブを地上に近い階の床スラブから順次、該スラブを柱に剛接する建築物の施工方法に関する。   The present invention relates to a construction method for a building, and more specifically, after a roof slab and a floor slab are previously placed, the roof slab and the floor slab are sequentially fixed from a floor slab on a floor close to the ground, and the slab is rigidly attached to a column. It is related to the construction method of the building which touches.

リフトアップ工法と呼ばれる従来の工法では、屋根スラブ、床スラブを順次柱に剛接していた。まず、地上で打設した屋根スラブを吊り上げ、柱の所定の位置に該屋根スラブを剛接する。次いで、地上で打設した最上階の床スラブを吊り上げ、柱の所定の位置に該床スラブを剛接する。以下、より下の階の床スラブを吊り上げ、柱の所定の位置に該床スラブを剛接する。   In a conventional method called a lift-up method, the roof slab and the floor slab are in rigid contact with the columns in sequence. First, a roof slab placed on the ground is lifted, and the roof slab is rigidly connected to a predetermined position of a pillar. Next, the floor slab on the uppermost floor placed on the ground is lifted, and the floor slab is rigidly connected to a predetermined position of the pillar. Hereinafter, the floor slab of the lower floor is lifted, and the floor slab is rigidly connected to a predetermined position of the pillar.

かかる工法では、高所から順にスラブを吊り上げ、屋根や上階部から施工するため、施工の初期段階では建築物は揺れに対し不安定な構造となる。また、施工の初期段階では、柱とスラブとの剛接には、高所溶接作業が必要となる。したがって、施工の初期段階で建築物が不安定な構造とならず、高所での溶接作業を必要としない施工方法が求められていた。   In such a construction method, slabs are lifted in order from a high place, and construction is performed from the roof or upper floor, so that the building has an unstable structure against shaking at the initial stage of construction. In addition, at the initial stage of construction, high-place welding work is required for the rigid connection between the column and the slab. Therefore, there has been a demand for a construction method in which the building does not have an unstable structure at the initial stage of construction and does not require welding work at a high place.

また、スラブの打設後のコンクリートの養生には時間が掛かるため、工期を短縮する工法が要求されていた。   Moreover, since it takes time to cure the concrete after slab placement, a construction method that shortens the construction period has been required.

本願発明の建築物の施工方法は、柱が立設された建築物の基礎部に、前記柱が外側になるように型枠を組み、前記型枠内に剥離部材を敷設し、更に前記剥離部材に上に補強部材を配置し、前記型枠内に生コンクリートを流し込み、フック掛け部を備える、第1スラブを打設し、
前記第1スラブ上に、前記柱が外側になるように型枠を組み、前記型枠内に剥離部材を敷設し、更に前記剥離部材に上に補強部材を配置し、前記型枠内に生コンクリートを流し込み、四隅にフック掛け部を備える、第2スラブを打設する工程を繰り返して、第1から第Nまでのスラブを打設し、
前記柱の頂部に取り付けられた滑車を介したワイヤーで前記第1スラブ以外のスラブを所定の位置まで吊り上げ、前記柱の上部に各スラブを仮止めし、更に前記ワイヤーで前記第1スラブを所定の位置まで吊り上げ、前記第1スラブを前記柱に固定し、
同様に第2から第Nスラブを順次前記柱に固定することを特徴とする。
建築物の施工方法。
In the building construction method of the present invention, a frame is assembled on the foundation of a building on which a column is erected so that the column is on the outside, and a peeling member is laid in the frame, and the peeling is further performed. Placing a reinforcing member on the member, pouring the ready-mixed concrete into the mold, and placing a first slab comprising a hook hanging portion;
A mold is assembled on the first slab so that the pillar is on the outside, a peeling member is laid in the mold, and a reinforcing member is disposed on the peeling member. Pour concrete, repeat the process of placing the second slab with hooks at the four corners, place the first to Nth slabs,
A slab other than the first slab is lifted to a predetermined position by a wire via a pulley attached to the top of the column, each slab is temporarily fixed to the upper portion of the column, and the first slab is predetermined by the wire. And lift the first slab to the column,
Similarly, the second to Nth slabs are sequentially fixed to the column.
Building construction method.

本願発明の建築物の施工方法は、柱が立設された建築物の基礎部に、前記柱が外側になるように型枠を組み、前記型枠内に剥離部材を敷設し、更に前記剥離部材に上に補強部材を配置し、前記型枠内に生コンクリートを流し込み、フック掛け部を備える、第1スラブを打設し、
前記第1スラブ上に、前記柱が外側になるように型枠を組み、前記型枠内に剥離部材を敷設し、更に前記剥離部材に上に補強部材を配置し、前記型枠内に生コンクリートを流し込み、四隅にフック掛け部を備える、第2スラブを打設する工程を繰り返して、第1から第Nまでのスラブを打設し、
前記柱の頂部に取り付けられた滑車を介したワイヤーで前記第1スラブ以外のスラブを所定の位置まで吊り上げ、前記柱の上部に各スラブを仮止めし、更に前記ワイヤーで前記第1スラブを吊り上げると共に、前記第1スラブの下面に筋違の一端を回動可能に取り付け、前記筋違の他端に転動可能なローラ付きの滑車を取り付け、前記滑車に掛けられたワイヤーを引き、前記筋違により前記第1スラブを押し上げて所定の位置に吊り上げ、前記第1スラブを前記柱に固定し、
同様に第2から第Nスラブを順次前記柱に固定することを特徴とする建築物の施工方法。
In the building construction method of the present invention, a frame is assembled on the foundation of a building on which a column is erected so that the column is on the outside, and a peeling member is laid in the frame, and the peeling is further performed. Placing a reinforcing member on the member, pouring the ready-mixed concrete into the mold, and placing a first slab comprising a hook hanging portion;
A mold is assembled on the first slab so that the pillar is on the outside, a peeling member is laid in the mold, and a reinforcing member is disposed on the peeling member. Pour concrete, repeat the process of placing the second slab with hooks at the four corners, place the first to Nth slabs,
A slab other than the first slab is lifted to a predetermined position by a wire via a pulley attached to the top of the pillar, each slab is temporarily fixed to the upper part of the pillar, and the first slab is lifted by the wire. In addition, one end of the strut is rotatably attached to the lower surface of the first slab, a pulley with a roller capable of rolling is attached to the other end of the strut, a wire hung on the pulley is pulled, and the muscle The first slab is pushed up by a mistake and lifted to a predetermined position, and the first slab is fixed to the column,
Similarly, the second to Nth slabs are sequentially fixed to the column.

まず、本願発明の施工方法によれば、屋根スラブと2階から最上位階までの床スラブとが短期間に打設できるので、施工期間を短縮できる。更に、下の階から建築物が組み立てられるので、施工の初期段階で建築物が不安定な構造とならず、高所での溶接作業を必要としない施工方法となる。   First, according to the construction method of the present invention, the roof slab and the floor slab from the second floor to the highest floor can be placed in a short time, so that the construction period can be shortened. Furthermore, since the building is assembled from the lower floor, the building does not have an unstable structure at the initial stage of construction, and the construction method does not require welding work at a high place.

本願発明の施工方法によれば、軽微な装置と少人数の作業で施工でき、更に、仮設材を使用することなく建築物が施工可能となる。   According to the construction method of the present invention, construction can be performed with a light device and a small number of people, and a building can be constructed without using temporary materials.

以下、図面を用いて、3階建ての建築物(N=3)を例にして、本発明に係る施工方法を説明する。図1aはスラブを打設する前の建築物を上から見た図であり、図1bは建築物の一部を拡大した図、図1cは図1aのA−A線断面図である。建築物の基礎部1の四隅には柱2が立設されている。柱2の立設方法は公知の方法で構わない。例えば、図1cに示すように再生砕石を敷いた土台100に柱2を立設させた後コンクリートを打設して柱2を立設固定し、基礎部1を形成することができる。また、柱2の一例として、トラス柱と呼ばれる斜材2aで補強された柱2を使用することができ、必要に応じて複数のトラス柱を溶接などの方法で順次接続して所定の高さの柱を立設する。なお、後述するが柱2の頂部には滑車が取り付けられている。   Hereinafter, the construction method according to the present invention will be described with reference to the drawings, taking a three-story building (N = 3) as an example. FIG. 1a is a top view of a building before placing a slab, FIG. 1b is an enlarged view of a part of the building, and FIG. 1c is a cross-sectional view taken along line AA of FIG. 1a. Pillars 2 are erected at the four corners of the foundation 1 of the building. A well-known method may be used as a method of standing the pillar 2. For example, as shown in FIG. 1 c, the foundation 2 can be formed by placing the pillar 2 on the base 100 laid with recycled crushed stone and then placing concrete to stand and fix the pillar 2. Further, as an example of the pillar 2, a pillar 2 reinforced with a diagonal member 2a called a truss pillar can be used, and a plurality of truss pillars are sequentially connected by a method such as welding as required to have a predetermined height. Stand up the pillar. As will be described later, a pulley is attached to the top of the pillar 2.

次に、2階床スラブ(第1スラブ)、3階床スラブ(第2スラブ)、屋根スラブ(第3スラブ)に相当するスラブの打設について説明するが、以下に述べる構造でなくても所定の強度を有していればよい。図1dにおいて、基礎部1には、スラブを打設するために柱2の内側に型枠3(コンパネとも呼ばれるベニヤ板)を立設し、次に剥離部材としてコンパネ4を敷設する。剥離部材としてビニールシートなどを使用してもよい。   Next, the placement of slabs corresponding to the second floor slab (first slab), the third floor slab (second slab), and the roof slab (third slab) will be described. What is necessary is just to have predetermined intensity | strength. In FIG. 1d, in order to place a slab, a formwork 3 (a veneer plate also called a panel) is erected on the inside of a pillar 2 and then a panel 4 is laid as a peeling member. A vinyl sheet or the like may be used as the peeling member.

そして、補強部材として、トラス梁5を格子状に型枠3内に配置し、トラス梁5が交差している箇所を溶接する。更に補強部材として格子のマス目内に鉄筋6を配置してもよく、所定の強度を確保しつつスラブの軽量化を図るため、発泡スチロールのなどの軽量ブロック(図示しない)を配置してもよい。鉄筋6を軽量ブロックの上下に配置して軽量ブロックを挟む構造としてもよい。   Then, as the reinforcing member, the truss beams 5 are arranged in a lattice shape in the mold 3 and the places where the truss beams 5 intersect are welded. Further, reinforcing bars 6 may be arranged in the grid cells as reinforcing members, and lightweight blocks (not shown) such as polystyrene foam may be arranged to reduce the weight of the slab while ensuring a predetermined strength. . It is good also as a structure which arrange | positions the reinforcing bar 6 on the upper and lower sides of a lightweight block, and pinches | interposes a lightweight block.

また、後述するワイヤーによる吊り上げのための中空部とフック掛け部との形成のため、小枠7と小枠7に予め貫通させたフック掛け部8(例えば鉄の棒)をスラブの四隅に配置する。また、スラブの四隅の側面に、後述する仮止めのための凹部を形成するためのブロック(図示しない)を配置しておく。   In addition, a small frame 7 and hook hooks 8 (for example, iron bars) that have been penetrated in advance through the small frame 7 are arranged at the four corners of the slab in order to form a hollow portion and a hook hook portion for lifting with a wire, which will be described later. To do. In addition, blocks (not shown) for forming concave portions for temporary fixing, which will be described later, are arranged on the side surfaces of the four corners of the slab.

なお、図1dの鎖線円で示したスラブの隅部の概略を図1eに示す。中空部9がスラブを貫通し、フック掛け部8がスラブに埋め込まれている。またスラブの側面には凹部10が段違いで形成されている。   In addition, the outline of the corner part of the slab shown by the chain line circle in FIG. 1d is shown in FIG. 1e. The hollow portion 9 penetrates the slab, and the hook hanging portion 8 is embedded in the slab. Moreover, the recessed part 10 is formed in the step in the side surface of the slab.

この状態で生コンクリートを流し込み、スラブ(2階床スラブ12)を打設する。生コンクリートがある程度固まったら(例えば、24時間)、2階床スラブ12の上に型枠3を立設し、コンパネ4などを敷設する。以下同様に、トラス梁5などを配置し、生コンクリートを流し込み、スラブ(3階床スラブ13)を打設する。この作業を繰り返し、必要なスラブを打設する。例えば、3階建ての建築物を施工する場合、2階床スラブ、3階床スラブ、屋根スラブの計3枚のスラブを順次打設する。   In this state, ready-mixed concrete is poured and a slab (second floor slab 12) is placed. When the ready-mixed concrete is hardened to some extent (for example, 24 hours), the formwork 3 is erected on the second floor slab 12, and the panel 4 and the like are laid. In the same manner, the truss beam 5 and the like are arranged, the ready-mixed concrete is poured, and a slab (third floor slab 13) is placed. Repeat this work to place the necessary slabs. For example, when constructing a three-story building, a total of three slabs, a second-story floor slab, a third-story floor slab, and a roof slab, are sequentially placed.

スラブの打設後は十分な強度を得るためにコンクリートの養生時間(約4週間)が必要である。従来工法では、スラブ毎にコンクリートを養生する必要があり、大幅に長い工期を必要となる。しかし、最初のスラブが十分な強度を得る前に、次のスラブの打設が可能となり、順次スラブの打設が可能となるため、工期を大幅に短縮できる。すなわち、従来の工法では、スラブの枚数×約4週間の時間を必要としていたが、本発明の方法では実質的に約4週間程度の時間で済むことになる。   After placing the slab, concrete curing time (about 4 weeks) is required to obtain sufficient strength. In the conventional construction method, it is necessary to cure concrete for each slab, which requires a significantly long construction period. However, since the next slab can be placed before the first slab has sufficient strength, and the slab can be placed sequentially, the construction period can be greatly shortened. That is, in the conventional method, the time of the number of slabs × about 4 weeks is required, but in the method of the present invention, the time of about 4 weeks is substantially required.

次に、スラブの取り付けについて説明する。図2aに示すように、最も上部にある屋根スラブ14のフック掛け部にフック(図示しない)を介してワイヤー24が取り付けられる。ワイヤー24は、柱2の頂部に取り付けられた滑車21と、基礎部1に取り付けられた滑車22に掛けられている。例えばウインチ(図示しない)でワイヤー24を引くことで屋根スラブ14が吊り上げられる。   Next, attachment of the slab will be described. As shown in FIG. 2a, a wire 24 is attached to a hook hook portion of the roof slab 14 at the uppermost portion via a hook (not shown). The wire 24 is hung on a pulley 21 attached to the top of the pillar 2 and a pulley 22 attached to the foundation 1. For example, the roof slab 14 is lifted by pulling the wire 24 with a winch (not shown).

屋根スラブ14が適切な位置まで吊り上げられると、屋根スラブ14は柱2に仮止めされる。図2bに示すように、屋根スラブ14の凹部10に仮止め具41(例えば鉄製の金属片)を挿入し、柱2の水平部材2bと仮止め具41とが係止することにより、屋根スラブ14に仮止めが行なわれる。凹部10が段違いで形成されているため、2方向から仮止め具41を挿入できる。なお、図2bでは柱2を簡略して図示している。   When the roof slab 14 is lifted to an appropriate position, the roof slab 14 is temporarily fixed to the column 2. As shown in FIG. 2b, a temporary stopper 41 (for example, a metal piece made of iron) is inserted into the recess 10 of the roof slab 14, and the horizontal member 2b of the pillar 2 and the temporary stopper 41 are locked, thereby the roof slab. 14 is temporarily fixed. Since the recessed part 10 is formed in steps, the temporary stopper 41 can be inserted from two directions. In FIG. 2b, the pillar 2 is illustrated in a simplified manner.

同様に、3階床スラブ13も吊り上げられ、柱2に仮止めされる。ワイヤー24は各スラブの中空部9を貫通するので、スラブの吊り上げにおいて支障はない。   Similarly, the third floor slab 13 is also lifted and temporarily fixed to the pillar 2. Since the wire 24 penetrates the hollow portion 9 of each slab, there is no problem in lifting the slab.

更に、図3aに示すように、2階床スラブ12にワイヤー24を取り付けて、2階床スラブ12を所定の位置に吊り上げる。ここで、2階床スラブ12をある程度吊り上げた状態で、基礎部1と2階床スラブ12との間に筋違31を挿入する。   Further, as shown in FIG. 3a, a wire 24 is attached to the second floor slab 12, and the second floor slab 12 is lifted to a predetermined position. Here, the strut 31 is inserted between the foundation 1 and the second floor slab 12 in a state where the second floor slab 12 is lifted to some extent.

筋違31の一端は回動可能に2階床スラブ12の下面に取り付けられている。例えば、打設時にフック掛け部8と同様の方法でリンク軸32を設けておき、リンク軸32に筋違31の一端を回動可能に取り付けておく。   One end of the strut 31 is attached to the lower surface of the second floor slab 12 so as to be rotatable. For example, the link shaft 32 is provided in the same manner as the hook hooking portion 8 at the time of placing, and one end of the strut 31 is attached to the link shaft 32 so as to be rotatable.

筋違31の他端には、基礎部1上を転動可能なローラ付きの滑車23が取り付けられている。滑車23にはワイヤー25が掛けられ、ワイヤー24とワイヤー25が同時に引かれる。したがって、2階床スラブ12は、ワイヤー24で吊り上げられると共に、筋違31により押し上げられ、所定の位置に持ち上げられる。   A pulley 23 with a roller that can roll on the base 1 is attached to the other end of the strut 31. A wire 25 is hung on the pulley 23, and the wire 24 and the wire 25 are pulled simultaneously. Therefore, the second floor slab 12 is lifted by the wire 24 and is pushed up by the strut 31 and lifted to a predetermined position.

筋違31による押し上げがなくてもよいが、筋違31により2階床スラブ12が支持されているとワイヤー24の張力が軽減されるので、ワイヤー24の破損などが防止できる。また、吊り上げ作業中に地震などによる揺れがあっても、スラブが落下するなどの事故を防ぐことができる。   Although there is no need to push up due to the strut 31, if the second floor slab 12 is supported by the strut 31, the tension of the wire 24 is reduced, so that the breakage of the wire 24 can be prevented. In addition, accidents such as falling of the slab can be prevented even if there is shaking due to an earthquake during the lifting work.

柱とスラブの固定について説明する。図3bに示すように、まず2階床スラブ12の補強部材(例えばトラス梁5)に結合部材42を柱2に貫通した状態で溶接する。図3cに結合部材42の一例を示す。図では鉄製円板と鉄製棒が溶接された構造を有する。   Explain how to fix the column and slab. As shown in FIG. 3 b, first, the connecting member 42 is welded to the reinforcing member (for example, the truss beam 5) of the second floor slab 12 while penetrating the column 2. An example of the coupling member 42 is shown in FIG. 3c. In the figure, it has a structure in which an iron disk and an iron bar are welded.

図3dに示すように、その後、柱2の周囲を型枠43に囲い、型枠43内に生コンクリートを流し込む。生コンクリートは柱2の内部や周囲に行き渡り、2階床スラブ12と柱2との隙間にも充填されるので、2階床スラブ12と柱2とが固定される。   As shown in FIG. 3 d, the periphery of the pillar 2 is then surrounded by a mold frame 43, and ready-mixed concrete is poured into the mold frame 43. The ready-mixed concrete spreads inside and around the pillar 2 and is filled in the gap between the second-floor floor slab 12 and the pillar 2, so that the second-floor slab 12 and the pillar 2 are fixed.

別の方法では、柱2が貫通可能な接合部材を用いてもよい。図3eでは、予め2階床スラブ12の補強部材(例えばトラス梁5)に結合部材44が接合されている。結合部材44はスラブの打設前に柱2に貫通させておき、スラブの吊り上げまでに補強部材に接合(例えば溶接やボルト止め)しておけばよい。したがって、高所での溶接作業が不要となる。   In another method, a joining member through which the pillar 2 can penetrate may be used. In FIG. 3e, the coupling member 44 is joined to the reinforcing member (for example, the truss beam 5) of the second floor slab 12 in advance. The connecting member 44 may be passed through the column 2 before the slab is placed and joined to the reinforcing member (for example, welding or bolting) before the slab is lifted. Therefore, welding work at a high place becomes unnecessary.

この方法でも図3fに示すように、柱2の周囲を型枠43に囲い、型枠43内に生コンクリートを流し込む。生コンクリートは柱2の内部や周囲に行き渡り、2階床スラブ12と柱2との隙間にも充填されるので、2階床スラブ12と柱2とが固定される。そして、柱2の間に壁部材を取り付ける。   Also in this method, as shown in FIG. 3 f, the periphery of the pillar 2 is surrounded by a mold frame 43, and ready-mixed concrete is poured into the mold frame 43. The ready-mixed concrete spreads inside and around the pillar 2 and is filled in the gap between the second-floor floor slab 12 and the pillar 2, so that the second-floor slab 12 and the pillar 2 are fixed. And a wall member is attached between the pillars 2.

壁部材の取り付けは公知の方法で構わないが、図4に示すように、壁部材33を取り付けて、柱2、2階床スラブ12、柱2に接する壁部材33とをコンクリートで打設することもできる。また、筋違31が壁部材33を補強する役目も果たす。なお、打設前に筋違31の端部は基礎部1に固定されたリンク軸34に固定される。したがって、下の階から建築物が組み立てられるので、施工の初期段階で建築物が不安定な構造とならない。   The wall member may be attached by a known method. However, as shown in FIG. 4, the wall member 33 is attached, and the pillar 2, the second floor slab 12, and the wall member 33 in contact with the pillar 2 are cast with concrete. You can also. Further, the strut 31 also serves to reinforce the wall member 33. Note that the end of the strut 31 is fixed to the link shaft 34 fixed to the base portion 1 before placing. Therefore, since the building is assembled from the lower floor, the building does not have an unstable structure at the initial stage of construction.

以下同様に、順次下位の階のスラブが取り付けられ、最後に屋根スラブ14が柱2に取り付けられる。例えば、図5に示すように、2階床スラブ12と3階床スラブ13との間に筋違31を挿入する。ワイヤー24で吊り上げられると共に、筋違31により押し上げられ、3階床スラブ13が所定の位置に持ち上げられる。   Similarly, the slabs of the lower floors are sequentially attached, and finally the roof slab 14 is attached to the pillar 2. For example, as shown in FIG. 5, a strut 31 is inserted between the second floor slab 12 and the third floor slab 13. The third floor slab 13 is lifted to a predetermined position by being lifted by the wire 24 and pushed up by the strut 31.

スラブを打設する前の建築物を上から見た図である。It is the figure which looked at the building before placing the slab from the top. スラブを打設する前の建築物の一部を示す図である。It is a figure which shows a part of building before slab placement. 図1aのA−A線断面図である。It is the sectional view on the AA line of FIG. スラブを打設する前の建築物を上から見た図である。It is the figure which looked at the building before placing the slab from the top. 図1dの円で囲んだスラブの隅部を示す概略図である。FIG. 2 is a schematic view showing a corner of a slab surrounded by a circle in FIG. 1d. スラブの取り付けの過程を示す図である。It is a figure which shows the process of attachment of a slab. スラブの仮止めを示す図である。It is a figure which shows the temporary stop of a slab. スラブの取り付けの過程を示す図である。It is a figure which shows the process of attachment of a slab. スラブと柱との固定を示す図である。It is a figure which shows fixation of a slab and a pillar. 結合部材の一例を示す図である。It is a figure which shows an example of a coupling member. スラブと柱との固定を示す図である。It is a figure which shows fixation of a slab and a pillar. スラブと柱との固定を示す図である。It is a figure which shows fixation of a slab and a pillar. スラブと柱との固定を示す図である。It is a figure which shows fixation of a slab and a pillar. スラブの取り付けの過程を示す図である。It is a figure which shows the process of attachment of a slab. スラブの取り付けの過程を示す図である。It is a figure which shows the process of attachment of a slab.

符号の説明Explanation of symbols

1 基礎部
2 柱
3 型枠
4 コンパネ
5 トラス梁
6 鉄筋
12 2階床スラブ
13 3階床スラブ
14 屋根スラブ
21、22 滑車
23 滑車
24、25 ワイヤー
31 筋違
32 リンク軸
33 壁部材
34 リンク軸
41 仮止め具
42 結合部材
43 型枠
44 結合部材
DESCRIPTION OF SYMBOLS 1 Base part 2 Column 3 Formwork 4 Companion panel 5 Truss beam 6 Reinforcement 12 Second floor slab 13 Third floor slab 14 Roof slab 21, 22 Pulley 23 Pulley 24, 25 Wire 31 Stitch 32 Link shaft 33 Wall member 34 Link shaft 41 Temporary fastener 42 Coupling member 43 Form frame 44 Coupling member

Claims (5)

柱が立設された建築物の基礎部に、前記柱が外側になるように型枠を組み、前記型枠内に剥離部材を敷設し、更に前記剥離部材に上に補強部材を配置し、前記型枠内に生コンクリートを流し込み、フック掛け部を備える、第1スラブを打設し、
前記第1スラブ上に、前記柱が外側になるように型枠を組み、前記型枠内に剥離部材を敷設し、更に前記剥離部材に上に補強部材を配置し、前記型枠内に生コンクリートを流し込み、四隅にフック掛け部を備える、第2スラブを打設する工程を繰り返して、第1から第Nまでのスラブを打設し、
前記柱の頂部に取り付けられた滑車を介したワイヤーで前記第1スラブ以外のスラブを所定の位置まで吊り上げ、前記柱の上部に各スラブを仮止めし、更に前記ワイヤーで前記第1スラブを所定の位置まで吊り上げ、前記第1スラブを前記柱に固定し、
同様に第2から第Nスラブを順次前記柱に固定することを特徴とする建築物の施工方法。
Assembling the formwork so that the pillar is on the outside of the foundation of the building where the pillar is erected, laying a peeling member in the formwork, and further placing a reinforcing member on the peeling member, Pour the ready-mixed concrete into the mold, and provide a first slab with a hook hanging portion,
A mold is assembled on the first slab so that the pillar is on the outside, a peeling member is laid in the mold, and a reinforcing member is disposed on the peeling member. Pour concrete, repeat the process of placing the second slab with hooks at the four corners, place the first to Nth slabs,
A slab other than the first slab is lifted to a predetermined position by a wire via a pulley attached to the top of the column, each slab is temporarily fixed to the upper portion of the column, and the first slab is predetermined by the wire. And lift the first slab to the column,
Similarly, the second to Nth slabs are sequentially fixed to the column.
柱が立設された建築物の基礎部に、前記柱が外側になるように型枠を組み、前記型枠内に剥離部材を敷設し、更に前記剥離部材に上に補強部材を配置し、前記型枠内に生コンクリートを流し込み、フック掛け部を備える、第1スラブを打設し、
前記第1スラブ上に、前記柱が外側になるように型枠を組み、前記型枠内に剥離部材を敷設し、更に前記剥離部材に上に補強部材を配置し、前記型枠内に生コンクリートを流し込み、四隅にフック掛け部を備える、第2スラブを打設する工程を繰り返して、第1から第Nまでのスラブを打設し、
前記柱の頂部に取り付けられた滑車を介したワイヤーで前記第1スラブ以外のスラブを所定の位置まで吊り上げ、前記柱の上部に各スラブを仮止めし、更に前記ワイヤーで前記第1スラブを吊り上げると共に、前記第1スラブの下面に筋違の一端を回動可能に取り付け、前記筋違の他端に転動可能なローラ付きの滑車を取り付け、前記滑車に掛けられたワイヤーを引き、前記筋違により前記第1スラブを押し上げて所定の位置に吊り上げ、前記第1スラブを前記柱に固定し、
同様に第2から第Nスラブを順次前記柱に固定することを特徴とする建築物の施工方法。
Assembling the formwork so that the pillar is on the outside of the foundation of the building where the pillar is erected, laying a peeling member in the formwork, and further placing a reinforcing member on the peeling member, Pour the ready-mixed concrete into the mold, and provide a first slab with a hook hanging portion,
A mold is assembled on the first slab so that the pillar is on the outside, a peeling member is laid in the mold, and a reinforcing member is disposed on the peeling member. Pour concrete, repeat the process of placing the second slab with hooks at the four corners, place the first to Nth slabs,
A slab other than the first slab is lifted to a predetermined position by a wire via a pulley attached to the top of the pillar, each slab is temporarily fixed to the upper part of the pillar, and the first slab is lifted by the wire. In addition, one end of the strut is rotatably attached to the lower surface of the first slab, a pulley with a roller capable of rolling is attached to the other end of the strut, a wire hung on the pulley is pulled, and the muscle The first slab is pushed up by a mistake and lifted to a predetermined position, and the first slab is fixed to the column,
Similarly, the second to Nth slabs are sequentially fixed to the column.
前記各スラブは四隅に仮止めのための凹部を備え、前記柱は所定の位置に水平部材を備えた、
前記各スラブの仮止め方法は、前記凹部に挿入された仮止め具と前記柱の水平部材との係止によりなされる方法である請求項1又は2に記載の建築物の施工方法。
Each of the slabs has recesses for temporary fixing at the four corners, and the pillar has a horizontal member at a predetermined position.
The method for constructing a building according to claim 1 or 2, wherein the temporary fixing method for each slab is a method of locking the temporary fixing tool inserted into the recess and the horizontal member of the pillar.
前記各スラブの固定の方法は、各スラブに接合され、前記柱を貫通した又は前記柱に貫通された接合部材と、前記柱とをコンクリートで打設して各スラブを前記柱に固定する方法である請求項1〜3のいずれかに記載の建築物の施工方法。   The method of fixing each slab is a method of fixing each slab to the column by joining the column with a joining member that is bonded to each slab and penetrates the column or penetrates the column. The construction method for a building according to any one of claims 1 to 3. 前記各スラブの固定の方法は、各スラブに接合され、前記柱を貫通した又は前記柱に貫通された接合部材と、前記柱と、前記柱に接する壁部材とをコンクリートで打設して各スラブを前記柱に固定する方法である請求項1〜4のいずれかに記載の建築物の施工方法。   The fixing method of each slab is as follows. Each of the slabs is bonded to each slab, and a joining member penetrating the column or penetrating the column, the column, and a wall member in contact with the column are cast with concrete. It is a method of fixing a slab to the said pillar, The construction method of the building in any one of Claims 1-4.
JP2008154905A 2008-06-13 2008-06-13 Construction method of building Pending JP2009299346A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008154905A JP2009299346A (en) 2008-06-13 2008-06-13 Construction method of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008154905A JP2009299346A (en) 2008-06-13 2008-06-13 Construction method of building

Publications (1)

Publication Number Publication Date
JP2009299346A true JP2009299346A (en) 2009-12-24

Family

ID=41546516

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008154905A Pending JP2009299346A (en) 2008-06-13 2008-06-13 Construction method of building

Country Status (1)

Country Link
JP (1) JP2009299346A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864841A (en) * 2010-05-28 2010-10-20 武汉一冶机电工程有限责任公司 Integral mounting method of steel-structure factory building wall skin
CN115045271A (en) * 2022-06-28 2022-09-13 中交四公局第三工程有限公司 Pile foundation steel pile casing transportation construction trolley and pile foundation steel pile casing positioning construction process
CN115492310A (en) * 2022-10-31 2022-12-20 中国十九冶集团有限公司 Steel reinforcement cage expansion device and construction method for installing box steel column in steel reinforcement cage

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864841A (en) * 2010-05-28 2010-10-20 武汉一冶机电工程有限责任公司 Integral mounting method of steel-structure factory building wall skin
CN115045271A (en) * 2022-06-28 2022-09-13 中交四公局第三工程有限公司 Pile foundation steel pile casing transportation construction trolley and pile foundation steel pile casing positioning construction process
CN115492310A (en) * 2022-10-31 2022-12-20 中国十九冶集团有限公司 Steel reinforcement cage expansion device and construction method for installing box steel column in steel reinforcement cage

Similar Documents

Publication Publication Date Title
US7219474B2 (en) Load bearing building panel
JP6474151B2 (en) Dismantling system and dismantling method
JP3196043B2 (en) Construction method of stairs and staircase, construction method of stairs, and stair members
US10829927B2 (en) Vertical slip form construction system with multi-function platform, and method of constructing a building therewith
KR101116254B1 (en) High-rise structure construction method by lifting up table-form
JP2009299346A (en) Construction method of building
JP7220044B2 (en) Building construction method
JPH05287901A (en) Construction of stairs
JP5003253B2 (en) RC beam construction method
JP4191235B1 (en) Temporary support joint, temporary structure, and multi-story slab construction method
JPH10331272A (en) Construction method of building frame constituted of reinforced concrete column, core wall, uppermost wall beam, and slab
JP6391134B2 (en) Dismantling method and dismantling system
JP4027170B2 (en) External scaffold device and construction method of external scaffold device
US3435583A (en) Method of forming buildings
JPH08239906A (en) Construction of building
JP4445366B2 (en) Reinforcement method for tower crane mount
JP5972113B2 (en) Construction method of multistory parking lot
CN114263349B (en) Construction method of wall-attached-free combined scaffold
KR20130009225A (en) Rail-stopper for lifting-rail assembly
JP4897095B1 (en) Gradient concrete roof construction method
JP3187618B2 (en) How to assemble beam reinforcement
JP2010138601A (en) Temporary structure and construction method of multistory slab
JP2002194892A (en) Construction method of building
JP2000154595A (en) Execution method of domed construction
JP2761527B2 (en) How to build structures