JP6987559B2 - Construction method of continuous underground wall and steel pipe pile - Google Patents

Construction method of continuous underground wall and steel pipe pile Download PDF

Info

Publication number
JP6987559B2
JP6987559B2 JP2017141225A JP2017141225A JP6987559B2 JP 6987559 B2 JP6987559 B2 JP 6987559B2 JP 2017141225 A JP2017141225 A JP 2017141225A JP 2017141225 A JP2017141225 A JP 2017141225A JP 6987559 B2 JP6987559 B2 JP 6987559B2
Authority
JP
Japan
Prior art keywords
steel pipe
solidifying material
pile
filling
underground wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017141225A
Other languages
Japanese (ja)
Other versions
JP2019019633A (en
Inventor
精男 北村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GIKEN LTD.
Original Assignee
GIKEN LTD.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GIKEN LTD. filed Critical GIKEN LTD.
Priority to JP2017141225A priority Critical patent/JP6987559B2/en
Priority to PCT/JP2018/027786 priority patent/WO2019017498A1/en
Publication of JP2019019633A publication Critical patent/JP2019019633A/en
Application granted granted Critical
Publication of JP6987559B2 publication Critical patent/JP6987559B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • E02D5/285Prefabricated piles made of steel or other metals tubular, e.g. prefabricated from sheet pile elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/68Mould-pipes or other moulds for making bulkheads or elements thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/28Placing of hollow pipes or mould pipes by means arranged inside the piles or pipes

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

本発明はコンクリート等の固化材料からなる杭を地中で互いに連結して形成した連続地中壁の施工方法と、この連続地中壁の施工に用いる鋼管杭に関する。 The present invention relates to a method for constructing a continuous underground wall formed by connecting piles made of a solidifying material such as concrete to each other in the ground, and a steel pipe pile used for constructing the continuous underground wall.

従来、建築現場における構造物の施工方法として地下または地中に連続地中壁を構築することが知られている。また、止水壁として連続地中壁を構築することが知られている。
従来の連続地中壁の施工方法では、例えば掘削孔を所定間隔で地中に掘削して内部にコンクリートを充填し、これらのコンクリートが半硬化して自立できるようになると、その間に他の掘削孔を掘削してコンクリートを充填して、互いにオーバーラップさせて連続地中壁を構築している。掘削孔の崩壊防止のため、入口部分にケーシングを設置し掘削孔内にベントナイト液等を充満させている。
Conventionally, it has been known to construct a continuous underground wall underground or underground as a method of constructing a structure at a construction site. It is also known to construct a continuous underground wall as a water blocking wall.
In the conventional method of constructing a continuous underground wall, for example, excavation holes are excavated in the ground at predetermined intervals to fill the inside with concrete, and when these concretes are semi-hardened and become self-supporting, other excavations are performed during that time. Holes are excavated and filled with concrete and overlapped with each other to build a continuous underground wall. In order to prevent the excavation hole from collapsing, a casing is installed at the entrance to fill the excavation hole with bentonite liquid or the like.

また、特許文献1に記載された止水壁の構築方法では、ケーシングによって削孔を行い、ケーシング内の土砂を排土しながら地中に挿入し、ケーシング内に鋼管杭を建て込む。孔内に固化材を注入しながらケーシングを引き抜き、固化材環を形成することで、2重構造の杭を先行杭として所定間隔を開けて打設する。更に、先行杭の間に固化材環をラップさせるように後行杭を形成することで連続地中壁を形成している。 Further, in the method for constructing a waterproof wall described in Patent Document 1, a hole is drilled by a casing, earth and sand in the casing are discharged into the ground, and a steel pipe pile is built in the casing. By injecting the solidifying material into the hole and pulling out the casing to form a solidifying material ring, a pile having a double structure is used as a leading pile and placed at a predetermined interval. Further, a continuous underground wall is formed by forming a trailing pile so as to wrap the solidifying material ring between the leading piles.

特許文献2に記載された連続地中壁の構築方法では、軟弱地盤に掘削した縦孔内にケーシングを取り付けた止水用有底筒状体を挿入すると共に、有底筒状体を通して硬化性充填材を縦孔内に充填して2重構造の止水杭体を形成する。そして、隣り合う止水杭体相互が硬化性充填材の部分で重なるように連続する地中連続遮水壁を形成する。止水性有底筒状体の外周面に設けた硬化性充填材を残してケーシングを引き上げる。
しかも、止水性有底筒状体の外周面に設けた螺旋状撹拌部材で隣り合う止水杭体間の硬化性充填材を撹拌し、螺旋状撹拌部材を引き上げた後で硬化性充填材を硬化させて連続地中壁を構築している。
In the method for constructing a continuous underground wall described in Patent Document 2, a bottomed tubular body for water blocking with a casing attached is inserted into a vertical hole excavated in soft ground, and the bottomed tubular body is cured through the bottomed tubular body. The filler is filled in the vertical hole to form a double-structured waterproof pile. Then, a continuous underground impermeable wall is formed so that the adjacent waterproof piles overlap each other at the portion of the curable filler. The casing is pulled up, leaving the curable filler provided on the outer peripheral surface of the water-stopping bottomed cylinder.
Moreover, the curable filler between the adjacent waterproof piles is agitated by the spiral stirring member provided on the outer peripheral surface of the water-stopping bottomed tubular body, and after the spiral stirring member is pulled up, the curable filler is used. It is hardened to build a continuous underground wall.

特開2001−90060号公報Japanese Unexamined Patent Publication No. 2001-96060 特開2012−237138号公報Japanese Unexamined Patent Publication No. 2012-237138

ところで、ベントナイト液は連続地中壁の構築と共に汲み上げて再処理するが、再処理で生じるベントナイトは産業廃棄物として廃棄されるため環境に悪影響を与えていた。
また、特許文献1及び2に記載された連続地中壁の施工方法は鋼管以外にケーシングや螺旋状撹拌部材等が必要であり、作業工数が多いために手間がかかりコスト高になるという欠点があった。
By the way, the bentonite liquid is pumped up and reprocessed together with the construction of the continuous underground wall, but the bentonite generated by the reprocessing is discarded as industrial waste, which has an adverse effect on the environment.
Further, the method of constructing the continuous underground wall described in Patent Documents 1 and 2 requires a casing, a spiral stirring member, etc. in addition to the steel pipe, and has a drawback that it is troublesome and costly due to a large number of work man-hours. there were.

そのため、本発明は、上述した事情に鑑みてなされたものであって、処理を伴う産業廃棄物を生じず、杭体も2重構造となることが無く、少ない作業工数と低コストで施工できるようにした連続地中壁の施工方法とこの施工方法に用いる鋼管杭を提供することを目的とする。 Therefore, the present invention has been made in view of the above-mentioned circumstances, does not generate industrial waste with treatment, does not have a double structure in the pile body, and can be constructed with a small number of work man-hours and low cost. It is an object of the present invention to provide a method of constructing a continuous underground wall as described above and a steel pipe pile used in this construction method.

本発明による連続地中壁の施工方法は、第一鋼管と第二鋼管を施工方向に沿って連続して交互に打設する鋼管打設工程と、第一鋼管及び第二鋼管を打設しながらまたは打設した後に第一鋼管及び第二鋼管内を掘削する掘削工程と、一本置きに配置された第一鋼管内に固化材料を充填しながらまたは充填した後に第一鋼管を引き抜く第一固化材料充填工程と、第一鋼管の間に配設された第二鋼管内に固化材料を充填しながらまたは充填した後に第二鋼管の外側に突出する爪部によって第一固化材料充填工程で充填した固化材料を乱しつつ第二鋼管を引き抜く第二固化材料充填工程と、を備えることを特徴とする。
本発明によれば、連続して打設した第一鋼管及び第二鋼管から、第一鋼管を引き抜いた固化材料の杭の間で第二鋼管の爪部によって固化材料を乱しつつ固化材料から引き抜くことで、固化材料の杭同士を連結させた連続地中壁を形成することができる。そのため、少ない工数で固化材料の杭体同士を一体化させた連続地中壁を施工できる。しかも、施工時に固化材料の崩壊を防ぎ、ベントナイト等を使用しないため産業廃棄物を生じることを防止できる。
The method for constructing a continuous underground wall according to the present invention includes a steel pipe placing process in which the first steel pipe and the second steel pipe are continuously and alternately placed along the construction direction, and the first steel pipe and the second steel pipe are placed. The excavation process of excavating the inside of the first steel pipe and the second steel pipe while or after placing, and the first of pulling out the first steel pipe while filling or filling the solidifying material in the first steel pipe arranged every other pipe. Filling in the solidifying material filling step and the filling in the first solidifying material filling step by the claws protruding to the outside of the second steel pipe while filling or filling the solidifying material in the second steel pipe arranged between the first steel pipes. It is characterized by comprising a second solidifying material filling step of pulling out a second steel pipe while disturbing the solidified material.
According to the present invention, from the first steel pipe and the second steel pipe that are continuously cast, the solidified material is disturbed by the claws of the second steel pipe between the piles of the solidified material from which the first steel pipe is pulled out. By pulling out, it is possible to form a continuous underground wall in which piles of solidifying material are connected to each other. Therefore, it is possible to construct a continuous underground wall in which piles made of solidifying material are integrated with each other with a small number of man-hours. Moreover, it is possible to prevent the solidified material from collapsing during construction and to prevent the generation of industrial waste because bentonite or the like is not used.

本発明による連続地中壁の施工方法は、施工方向に沿って間隔を開けて第一鋼管を打設する第一鋼管打設工程と、第一鋼管を打設しながらまたは打設した後に第一鋼管内を掘削する第一掘削工程と、第一鋼管内に固化材料を充填しながらまたは充填した後に第一鋼管を引き抜く第一固化材料充填工程と、第一鋼管の間に第二鋼管を打設する第二鋼管打設工程と、第二鋼管を打設しながらまたは打設した後に第二鋼管内を掘削する第二掘削工程と、第二鋼管内に固化材料を充填しながらまたは充填した後に第二鋼管の外側に突出する爪部によって第一固化材料充填工程で充填した固化材料を乱しつつ第二鋼管を引き抜く第二固化材料充填工程と、を備えることを特徴とする。
本発明によれば、先に打設した第一鋼管を引き抜いた固化材料の杭の間で後に打設した第二鋼管の爪部によって固化材料を乱しつつ固化材料から引き抜くことで、固化材料の杭同士を連結させた連続地中壁を形成できる。
The method for constructing a continuous underground wall according to the present invention includes a first steel pipe placing step in which the first steel pipe is placed at intervals along the construction direction, and a first steel pipe placing step while or after the first steel pipe is placed. (1) The first excavation step of excavating the inside of the steel pipe, the first solidifying material filling step of pulling out the first steel pipe while filling or filling the first steel pipe with the solidifying material, and the second steel pipe between the first steel pipes. The second steel pipe placing process to be placed, the second excavation step to excavate the inside of the second steel pipe while driving or after placing the second steel pipe, and filling or filling the solidifying material in the second steel pipe. It is characterized by comprising a second solidifying material filling step of pulling out the second steel pipe while disturbing the solidifying material filled in the first solidifying material filling step by the claw portion protruding to the outside of the second steel pipe.
According to the present invention, the solidifying material is pulled out from the solidifying material while disturbing the solidifying material by the claws of the second steel pipe that is driven later between the piles of the solidifying material from which the first steel pipe was driven earlier. It is possible to form a continuous underground wall by connecting the piles of the above.

本発明による連続地中壁の施工方法は、施工方向に沿って間隔を開けて第二鋼管を打設する第二鋼管打設工程と、第二鋼管を打設しながらまたは打設した後に第二鋼管内を掘削する第二掘削工程と、第二鋼管の間に第一鋼管を打設する第一鋼管打設工程と、第一鋼管を打設しながらまたは打設した後に第一鋼管内を掘削する第一掘削工程と、第一鋼管内に固化材料を充填しながらまたは充填した後に第一鋼管を引き抜く第一固化材料充填工程と、第二鋼管内に固化材料を充填しながらまたは充填した後に第二鋼管の外側に突出する爪部によって第一固化材料充填工程で充填した固化材料を乱しつつ第二鋼管を引き抜く第二固化材料充填工程と、を備えることを特徴とする。
本発明によれば、先に打設した爪部を有する第二鋼管の間に第一鋼管を打設し、第一鋼管を引き抜いた固化材料の杭の間で第二鋼管の爪部によって固化材料を乱しつつ固化材料から引き抜くことで、固化材料の杭同士を連結させた連続地中壁を形成できる。
The method for constructing a continuous underground wall according to the present invention includes a second steel pipe placing step in which a second steel pipe is placed at intervals along the construction direction, and a second steel pipe placing step while or after placing the second steel pipe. (2) The second excavation process for excavating the inside of the steel pipe, the first steel pipe placing process for placing the first steel pipe between the second steel pipes, and the inside of the first steel pipe while or after placing the first steel pipe. The first excavation step of excavating, the first solidifying material filling step of pulling out the first steel pipe while filling or filling the first steel pipe, and filling or filling the solidifying material in the second steel pipe. It is characterized by comprising a second solidifying material filling step of pulling out the second steel pipe while disturbing the solidifying material filled in the first solidifying material filling step by the claw portion protruding to the outside of the second steel pipe.
According to the present invention, the first steel pipe is driven between the second steel pipes having the previously driven claws, and the first steel pipe is solidified by the claws of the second steel pipe between the piles of the solidifying material from which the first steel pipe is pulled out. By pulling out from the solidifying material while disturbing the material, it is possible to form a continuous underground wall in which piles of the solidifying material are connected to each other.

また、第二鋼管の打設時に爪部は第一鋼管に干渉しない位置に設けることが好ましい。
先に打設した第一鋼管に対して第二鋼管を圧入または揺動圧入等で打設することで爪部は第一鋼管に干渉しない位置に打設できる。
Further, it is preferable that the claw portion is provided at a position where it does not interfere with the first steel pipe when the second steel pipe is placed.
By driving the second steel pipe into the first steel pipe previously driven by press-fitting or rocking press-fitting, the claw portion can be driven at a position that does not interfere with the first steel pipe.

また、第二鋼管の爪部は第一鋼管及び/または第二鋼管の一方の外接線または両側の対向する2つの外接線と隣り合う第一鋼管との間の隙間に設けることが好ましい。
連続地中壁が既設構築物に近接する位置に構築する場合でも外接線と隣の第一鋼管との間に爪部を位置させて第二鋼管を打設できる。
Further, it is preferable that the claw portion of the second steel pipe is provided in the gap between one circumscribed line of the first steel pipe and / or the second steel pipe or two opposing circumscribed lines on both sides and the adjacent first steel pipe.
Even when the continuous underground wall is constructed at a position close to the existing structure, the second steel pipe can be placed by positioning the claw portion between the circumscribed line and the adjacent first steel pipe.

また、爪部を設けた第二鋼管は圧入、回転圧入または揺動圧入で打設するようにしてもよい。
第二鋼管は地盤の固さや第一鋼管との関係で爪部が干渉しないように圧入、回転圧入または揺動圧入のいずれかを選択して打設できる。
Further, the second steel pipe provided with the claw portion may be driven by press-fitting, rotary press-fitting or rocking press-fitting.
The second steel pipe can be driven by selecting either press-fitting, rotary press-fitting, or rocking press-fitting so that the claws do not interfere with each other due to the hardness of the ground and the relationship with the first steel pipe.

また、第二鋼管を引き抜く際、第一固化材料充填工程で充填した固化材料は凝結始発時間から凝結終結時間までの状態とされていることが好ましい。
第一固化材料充填工程で充填した固化材料は、凝結開始時間から凝結終結時間までの状態であれば、第二鋼管の爪部で乱すことで流動して第二固化材料充填工程で充填した固化材料と撹拌されて一体化できる。
Further, when the second steel pipe is pulled out, it is preferable that the solidified material filled in the first solidifying material filling step is in a state from the condensation start time to the condensation end time.
If the solidified material filled in the first solidifying material filling step is in a state from the setting start time to the setting ending time, it flows by being disturbed by the claws of the second steel pipe and is solidified filled in the second solidifying material filling step. Can be integrated with the material by stirring.

また、第二鋼管は爪部が外側に拡縮可能であることが好ましい。
第二鋼管の打設時には爪部を縮径させておくことで先に打設した第一鋼管と干渉することなく圧入できてスムーズに圧入できる。また、第二鋼管の引き抜き時には爪部を拡径させることで第一鋼管の固化材料を乱して一体化できる。
Further, it is preferable that the claw portion of the second steel pipe can be expanded and contracted outward.
By reducing the diameter of the claw portion when placing the second steel pipe, it can be press-fitted smoothly without interfering with the first steel pipe that was previously placed. Further, when the second steel pipe is pulled out, the solidifying material of the first steel pipe can be disturbed and integrated by enlarging the diameter of the claw portion.

また、第二鋼管を引き抜く際に爪部によって第一固化材料充填工程で充填した固化材料を乱しつつ新たな固化材料を補充することが好ましい。
第二鋼管の爪部で乱した固化材料に新たな固化材料を補充することで固化材料同士の連結部を補強して一体化を助けることができる。
Further, when the second steel pipe is pulled out, it is preferable to replenish the new solidifying material while disturbing the solidifying material filled in the first solidifying material filling step by the claw portion.
By replenishing the solidified material disturbed by the claw portion of the second steel pipe with a new solidified material, it is possible to reinforce the connecting portion between the solidified materials and assist the integration.

また、第一鋼管及び/または第二鋼管に圧入機を設置し、圧入機により第一鋼管及び第二鋼管を打設すると共に引き抜くようにしてもよい。
圧入機を第一鋼管及び/または第二鋼管に設置することで、第一鋼管や第二鋼管に反力をとって圧入と引き抜きを行うことができ、しかも周辺地盤を足場にすることなく打設した第一鋼管や第二鋼管の上を移動できるので、傾斜地や不整地上でも施工可能である。
Further, a press-fitting machine may be installed in the first steel pipe and / or the second steel pipe, and the first steel pipe and the second steel pipe may be driven and pulled out by the press-fitting machine.
By installing the press-fitting machine in the first steel pipe and / or the second steel pipe, it is possible to perform press-fitting and pulling out by taking reaction force on the first steel pipe and the second steel pipe, and hitting without using the surrounding ground as a scaffold. Since it can move on the installed first steel pipe and second steel pipe, it can be constructed even on slopes and rough ground.

また、掘削した第一鋼管及び/または第二鋼管内にPC鋼線を設置しておき、第一鋼管に対応する第一固化材料及び/または第二鋼管に対応する第二固化材料の定着後にPC鋼線を緊張させてプレストレスを導入するようにしてもよい。
連続地中壁を構成する第一杭及び/または第二杭にポストテンション方式でプレストレスを導入することで連続地中壁にかかる引張応力を制御することができる。
In addition, after installing the PC steel wire in the excavated first steel pipe and / or the second steel pipe and fixing the first solidified material corresponding to the first steel pipe and / or the second solidified material corresponding to the second steel pipe. The PC steel wire may be strained to introduce prestress.
By introducing prestress in the first pile and / or the second pile constituting the continuous underground wall by the post-tension method, the tensile stress applied to the continuous underground wall can be controlled.

また、第一鋼管及び第二鋼管は地盤の領域では引き抜かれて第一固化材料及び第二固化材料が爪部で乱されていると共に、水中では第一鋼管及び第二鋼管を引き抜くことなく保持されていてもよい。
第一鋼管及び第二鋼管内に充填された固化材料は、直接水に接触しないので自立状態で保持できる。
また、第一鋼管及び第二鋼管は地盤の領域では引き抜かれて第一固化材料及び第二固化材料が爪部で乱されていると共に、地上では第一鋼管及び第二鋼管を引き抜くことなく保持されていてもよい。
地上では、第一鋼管及び第二鋼管内に充填された固化材料は、第一鋼管及び第二鋼管によって自立状態で保持できる。
In addition, the first steel pipe and the second steel pipe are pulled out in the ground region, and the first solidified material and the second solidified material are disturbed at the claws, and the first steel pipe and the second steel pipe are held in water without being pulled out. It may have been done.
Since the solidified material filled in the first steel pipe and the second steel pipe does not come into direct contact with water, it can be held in an independent state.
In addition, the first steel pipe and the second steel pipe are pulled out in the ground area, and the first solidified material and the second solidified material are disturbed at the claws, and the first steel pipe and the second steel pipe are held on the ground without being pulled out. It may have been done.
On the ground, the solidified material filled in the first steel pipe and the second steel pipe can be held in a self-supporting state by the first steel pipe and the second steel pipe.

本発明による鋼管杭は、鋼管と、鋼管の長手方向の適宜位置に径方向外側に突出させた爪部とを有し、地中に打設した鋼管を引き上げる際に爪部で隣接する固化材料を乱すようにしたことを特徴とする。
本発明によれば、打設した鋼管内に固化材料を充填できると共に、鋼管を引き上げる際に爪部で隣接する固化材料を乱すことで固化材料同士を一体化できる。
The steel pipe pile according to the present invention has a steel pipe and a claw portion that protrudes radially outward at an appropriate position in the longitudinal direction of the steel pipe, and is a solidified material adjacent to the claw portion when the steel pipe placed in the ground is pulled up. It is characterized by disturbing.
According to the present invention, the solidifying material can be filled in the cast steel pipe, and the solidifying materials can be integrated by disturbing the adjacent solidifying materials at the claws when the steel pipe is pulled up.

本発明による連続地中壁の施工方法によれば、第一鋼管を引き抜いた固化材料の杭体の間で第二鋼管の爪部で杭体を乱しつつ引き抜くことで杭体同士を連結させた連続地中壁を形成することができる。そのため、少ない工数で固化材料の杭体同士を一体化させた連続地中壁を確実に施工できる。
しかも、施工時に固化材料の崩壊を防ぎ、ベントナイト等を使用しないため産業廃棄物を生じることを防止できると共に部品点数と作業工数を削減できる。
According to the method for constructing a continuous underground wall according to the present invention, the pile bodies are connected to each other by pulling out the pile bodies of the solidified material from which the first steel pipe has been pulled out while disturbing the pile bodies at the claws of the second steel pipe. It is possible to form a continuous underground wall. Therefore, it is possible to reliably construct a continuous underground wall in which piles of solidifying materials are integrated with each other with a small number of man-hours.
Moreover, it is possible to prevent the solidified material from collapsing during construction and to prevent the generation of industrial waste because bentonite or the like is not used, and it is possible to reduce the number of parts and man-hours.

また、本発明による鋼管杭によれば、鋼管杭の外周面に爪部を形成したため引き抜きの際に隣接する固化材料の杭体を乱して一体化させることができる。 Further, according to the steel pipe pile according to the present invention, since the claw portion is formed on the outer peripheral surface of the steel pipe pile, the pile body of the adjacent solidifying material can be disturbed and integrated at the time of pulling out.

本発明の実施形態による連続地中壁の施工方法に用いる鋼管を示すもので、(a)は第一鋼管、(b)は第二鋼管を示す図である。It shows the steel pipe used in the construction method of the continuous underground wall by embodiment of this invention, (a) is the figure which shows the 1st steel pipe, (b) is the figure which shows the 2nd steel pipe. 第二鋼管を示すもので、(a)は平面図、(b)は部分側面図である。The second steel pipe is shown, (a) is a plan view, and (b) is a partial side view. 地中に埋設した第一鋼管及び第二鋼管の配列を示すもので、(a)は平面図、(b)は要部側面図、(c)は第二鋼管の爪部を示す説明図である。The arrangement of the first steel pipe and the second steel pipe buried in the ground is shown, (a) is a plan view, (b) is a side view of a main part, and (c) is an explanatory view showing a claw part of the second steel pipe. be. 第一実施形態による連続地中壁の施工方法を示すもので、(a)は地中の壁体から第一鋼管を引き抜く工程の説明図、(b)はその構造図である。The construction method of the continuous underground wall by 1st Embodiment is shown, (a) is the explanatory view of the process of pulling out the 1st steel pipe from the wall body in the ground, and (b) is the structural drawing. (a)、(b)は別の第一鋼管を引き抜く工程の説明図とその構造図である。(A) and (b) are explanatory views and structural views of the process of pulling out another first steel pipe. (a)、(b)は第二鋼管を引き抜く工程の説明図とその構造図である。(A) and (b) are explanatory views and structural views of the process of pulling out the second steel pipe. (a)、(b)は別の第二鋼管を引き抜く工程の説明図とその構造図である。(A) and (b) are explanatory views and structural views of the process of pulling out another second steel pipe. (a)は連続地中壁の施工工程の説明図、(b)は第一杭と第二杭の配置を示す説明図、(c)は第一杭の変形例の図である。(A) is an explanatory diagram of the construction process of the continuous underground wall, (b) is an explanatory diagram showing the arrangement of the first pile and the second pile, and (c) is a diagram of a modified example of the first pile. 第二鋼管に設けた爪部の第一変形例を示す図であり、(a)は平面図、(b)は爪部を示す同図(a)のA−A線部分断面図である。It is a figure which shows the 1st deformation example of the claw part provided in the 2nd steel pipe, (a) is a plan view, (b) is a partial cross-sectional view taken along line AA of the figure (a) which shows a claw part. 第二実施形態による連続地中壁の施工方法における壁体から第一鋼管を引き抜く工程の説明図である。It is explanatory drawing of the process of pulling out a 1st steel pipe from a wall body in the construction method of the continuous underground wall by 2nd Embodiment. 別の第一鋼管を引き抜く工程の説明図である。It is explanatory drawing of the process of pulling out another first steel pipe. 第二鋼管を引き抜く工程の説明図である。It is explanatory drawing of the process of pulling out a 2nd steel pipe. 別の第二鋼管を引き抜く工程の説明図である。It is explanatory drawing of the process of pulling out another 2nd steel pipe. 第三実施形態による連続地中壁の施工方法における第二鋼管を打設する工程の説明図である。It is explanatory drawing of the process of placing the second steel pipe in the construction method of the continuous underground wall by the third embodiment. 第一鋼管を引き抜く工程の図である。It is a figure of the process of pulling out the first steel pipe. 別の第一鋼管を引き抜く工程の図である。It is a figure of the process of pulling out another first steel pipe. 第二鋼管を引き抜く工程の図である。It is a figure of the process of pulling out the second steel pipe. 壁体と爪部の変形例を示す図である。It is a figure which shows the deformation example of a wall body and a claw part. 第二鋼管に設けた爪部の第二変形例を示す図であり,(a)は平面図、(b)は縦断面図、(c)は爪部の裏面図である。It is a figure which shows the 2nd deformation example of the claw part provided in the 2nd steel pipe, (a) is a plan view, (b) is a vertical sectional view, (c) is a back view of the claw part. 爪部の分解斜視図である。It is an exploded perspective view of a claw part. 変形例による連続地中壁を示すものであり、(a)は第一鋼管及び第二鋼管の壁体の説明図、(b)は連続地中壁の説明図である。It shows the continuous underground wall by the modification, (a) is the explanatory view of the wall body of the 1st steel pipe and the 2nd steel pipe, and (b) is the explanatory view of the continuous underground wall. 変形例による連続地中壁の一部を示すものであり、第一鋼管内にプレストレスユニットを設置した状態の説明図である。It shows a part of a continuous underground wall according to a modified example, and is an explanatory diagram of a state where a prestress unit is installed in a first steel pipe. コンクリートを充填した第一杭を示す図である。It is a figure which shows the first pile filled with concrete. プレストレスを与えた連続地中壁の第一杭を示す図である。It is a figure which shows the first pile of the continuous underground wall which gave prestress. 連続地中壁の施工方法の変形例を示す図である。It is a figure which shows the modification of the construction method of a continuous underground wall. 連続地中壁の変形例を示す要部断面図である。It is sectional drawing of the main part which shows the deformation example of a continuous underground wall.

以下、本発明の実施形態による連続地中壁の施工方法と施工方法で用いる第二鋼管2について添付図面による説明する。
図1乃至図8は本発明の第一実施形態による連続地中壁Rの施工方法を示す図である。
本第一実施形態では、第一鋼管1と第二鋼管2を用いて連続地中壁Rを構築する。第一鋼管1は図1(a)に示す通常の鋼管であり、第二鋼管2は図1(b)に示すように管体の長手方向下部に外周面の対向する位置から径方向外側に突出する一対の爪部3を設けている。第一鋼管1と第二鋼管2は鋼管杭を構成する。
Hereinafter, the construction method of the continuous underground wall according to the embodiment of the present invention and the second steel pipe 2 used in the construction method will be described with reference to the attached drawings.
1 to 8 are views showing a method of constructing a continuous underground wall R according to the first embodiment of the present invention.
In the first embodiment, the continuous underground wall R is constructed by using the first steel pipe 1 and the second steel pipe 2. The first steel pipe 1 is a normal steel pipe shown in FIG. 1 (a), and the second steel pipe 2 is radially outward from a position facing the outer peripheral surface at the lower portion in the longitudinal direction of the pipe body as shown in FIG. 1 (b). A pair of protruding claw portions 3 are provided. The first steel pipe 1 and the second steel pipe 2 form a steel pipe pile.

第二鋼管2の爪部3は図2(a)、(b)に示すように例えばスチール製であり、略円弧板状で先端部3aが円弧状に形成されている。爪部3の両側部3bには高硬度材料製、例えば超硬合金製の刃部4が溶接等で連結され、爪部3の先端部3aと周方向両端部の刃部4が例えば断面略三角形状に形成されている。
そのため、第二鋼管2の地中への圧入時に直線的な圧入、回転圧入または揺動圧入することで爪部3の先端部3aと両側の刃部4で地盤を掘削できる。第二鋼管2を地中から引き抜く際には爪部3の先端部3aと刃部4とで隣接する硬化前のコンクリート製の第一杭を乱して一体化できる。なお、爪部3は必要に応じて第二鋼管2の長手方向適宜位置に設置できる。
As shown in FIGS. 2A and 2B, the claw portion 3 of the second steel pipe 2 is made of, for example, steel, and has a substantially arcuate plate shape and the tip portion 3a is formed in an arcuate shape. A blade portion 4 made of a high hardness material, for example, a cemented carbide is connected to both side portions 3b of the claw portion 3 by welding or the like, and the tip portion 3a of the claw portion 3 and the blade portions 4 at both ends in the circumferential direction, for example, have a substantially cross section. It is formed in a triangular shape.
Therefore, when the second steel pipe 2 is press-fitted into the ground, the ground can be excavated by the tip portion 3a of the claw portion 3 and the blade portions 4 on both sides by linear press-fitting, rotary press-fitting, or rocking press-fitting. When the second steel pipe 2 is pulled out from the ground, the first pile made of concrete before hardening, which is adjacent to the tip portion 3a of the claw portion 3 and the blade portion 4, can be disturbed and integrated. The claw portion 3 can be installed at an appropriate position in the longitudinal direction of the second steel pipe 2 as needed.

つぎに本第一実施形態による連続地中壁Rの施工方法について、図3から図7に示す各工程に基づいて説明する。
まず、圧入及び引き抜き装置として例えば図4に示す圧入機6を用い、第一鋼管1と第二鋼管2を交互に圧入して順次打設する(鋼管打設工程)。図3(a)〜(c)は連続して地中に圧入された第一鋼管1及び第二鋼管2の壁体7を示すものであり、第二鋼管2は第一鋼管1の間に打設されている。
鋼管打設工程において、第二鋼管2は先に圧入された第一鋼管1に爪部3が干渉しない範囲で揺動させて揺動圧入するか、揺動させずに直線的に圧入する。
Next, the construction method of the continuous underground wall R according to the first embodiment will be described based on each step shown in FIGS. 3 to 7.
First, for example, a press-fitting machine 6 shown in FIG. 4 is used as a press-fitting and pulling-out device, and the first steel pipe 1 and the second steel pipe 2 are alternately press-fitted and sequentially driven (steel pipe driving step). 3 (a) to 3 (c) show the wall body 7 of the first steel pipe 1 and the second steel pipe 2 continuously pressed into the ground, and the second steel pipe 2 is between the first steel pipe 1. It has been cast.
In the steel pipe placing step, the second steel pipe 2 is oscillated and press-fitted into the first steel pipe 1 previously press-fitted within a range in which the claw portion 3 does not interfere with each other, or is linearly press-fitted without oscillating.

次に図4〜図7により壁体7から第一及び第二鋼管1,2の引き抜きによる連続地中壁の構築方法を説明するが、各図の(a)は施工工程を示し、(b)は各工程における壁体7の構成を示している。
図4において、圧入機6は台車8のロック部を既設の第一鋼管1及び第二鋼管2(または反力ウェイト)に設置して反力をとり、各鋼管1,2を把持部9で把持してコンクリートを充填しながらまたは充填した後で地盤から引き抜きを行うものである。
圧入機6は壁体7をなす複数の第一鋼管1及び第二鋼管2を地盤のGL面からロック部のクランプのための高さだけ突出させておくことが好ましい。これにより、圧入機6は第一鋼管1及び第二鋼管2上で移動させながら第一鋼管1及び第二鋼管2の圧入と引き抜きの作業を行える。
Next, a method of constructing a continuous underground wall by pulling out the first and second steel pipes 1 and 2 from the wall body 7 will be described with reference to FIGS. 4 to 7, and FIG. ) Shows the configuration of the wall body 7 in each step.
In FIG. 4, the press-fitting machine 6 installs the lock portion of the carriage 8 on the existing first steel pipe 1 and second steel pipe 2 (or reaction force weight) to take reaction force, and each steel pipe 1 and 2 is held by the grip portion 9. It is pulled out from the ground while being gripped and filled with concrete or after filling.
It is preferable that the press-fitting machine 6 projects a plurality of first steel pipes 1 and second steel pipes 2 forming the wall body 7 from the GL surface of the ground by a height for clamping the lock portion. As a result, the press-fitting machine 6 can perform press-fitting and pulling-out operations of the first steel pipe 1 and the second steel pipe 2 while moving on the first steel pipe 1 and the second steel pipe 2.

図4(a)において、各鋼管1,2内を圧入機6で圧入した後で(または圧入しながら)各鋼管1,2内から掘削機(図示せず)で土砂を排出する(掘削工程)。つぎに、壁体7の端部に圧入された第一鋼管1にコンクリートを充填しながらまたは充填した後で、圧入機6で他の打設済み第一鋼管1に反力をとりながら引き抜く(第一固化材料充填工程)。これによりコンクリート製で略円柱状の第一杭1Aが地中に埋設される。第一杭1Aは未硬化であるが周囲の地盤に支持されている。
第一鋼管1はコンクリートを充填しながら引き抜いていくので地盤の穴の崩壊を生じない。図4では地盤のGL面を第一杭1Aa(1A)の上面とした。
In FIG. 4A, after the inside of each steel pipe 1 and 2 is press-fitted by the press-fitting machine 6 (or while press-fitting), earth and sand are discharged from the inside of each of the steel pipes 1 and 2 by an excavator (not shown) (excavation step). ). Next, after filling or filling the first steel pipe 1 press-fitted into the end of the wall body 7 with concrete, the press-fitting machine 6 pulls out the first steel pipe 1 already cast while taking a reaction force ( First solidification material filling process). As a result, the first pile 1A, which is made of concrete and has a substantially columnar shape, is buried in the ground. The first pile 1A is uncured but is supported by the surrounding ground.
Since the first steel pipe 1 is pulled out while filling concrete, the holes in the ground do not collapse. In FIG. 4, the GL surface of the ground is the upper surface of the first pile 1Aa (1A).

次に、圧入機6を1本開けた別の第一鋼管1上で移動させる。第一杭1Aaに対して第二鋼管2を挟んだ隣の第一鋼管1にコンクリートを充填しながらまたは充填した後で、圧入機6でこの第一鋼管1を引き抜く(第二固化材料充填工程)。圧入機6では他の第一鋼管1に反力をとりながら引き抜く。
この第一鋼管1を引き抜く際、図5(a)に示すように、第二鋼管2の間の第一鋼管1は把持しにくいので、圧入機6の把持部9に打ち下げ装置11を把持してその先端部を第一鋼管1内に嵌合させて互いに係合させた状態で引き抜く。こうしてコンクリート製で略円柱状の第一杭1Abが地中に埋設されている。
Next, the press-fitting machine 6 is moved on another first steel pipe 1 opened. While filling or filling the first steel pipe 1 adjacent to the first pile 1Aa sandwiching the second steel pipe 2, the first steel pipe 1 is pulled out by the press-fitting machine 6 (second solidifying material filling step). ). In the press-fitting machine 6, the other first steel pipe 1 is pulled out while taking a reaction force.
As shown in FIG. 5A, when the first steel pipe 1 is pulled out, the first steel pipe 1 between the second steel pipes 2 is difficult to grip, so the downing device 11 is gripped by the grip portion 9 of the press-fitting machine 6. Then, the tip portion thereof is fitted into the first steel pipe 1 and pulled out in a state of being engaged with each other. In this way, the first pile 1Ab, which is made of concrete and has a substantially columnar shape, is buried in the ground.

次に、図6において、第一杭1Aa、1Abの間の第二鋼管2内にコンクリートを充填しながらまたは充填した後で、圧入機6で他の第二鋼管2に反力をとりながら引き抜く。その際、第一杭1Aaと1Abは未硬化状態であり、第二鋼管2を回動させて第一杭1Aa、1Abに重ねた状態で揺動させながらまたは揺動させずに直線的に引き抜く。
これにより、コンクリート製で略円柱状の第二杭2Aaが未硬化状態で地中に埋設される。しかも、未硬化状態の第一杭1Aaと1Abは第二鋼管2の対向する爪部3で乱され、第二杭2Aa(2A)と一体化される。
Next, in FIG. 6, while filling or filling the second steel pipe 2 between the first piles 1Aa and 1Ab with concrete, the press-fitting machine 6 pulls out the second steel pipe 2 while taking a reaction force. .. At that time, the first piles 1Aa and 1Ab are in an uncured state, and the second steel pipe 2 is rotated and pulled out linearly with or without swinging while being overlapped with the first piles 1Aa and 1Ab. ..
As a result, the second pile 2Aa, which is made of concrete and has a substantially columnar shape, is buried in the ground in an uncured state. Moreover, the uncured first piles 1Aa and 1Ab are disturbed by the facing claws 3 of the second steel pipe 2 and integrated with the second pile 2Aa (2A).

ここで、第二鋼管2の爪部3で両側の第一杭1Aa、1Abを乱して第二鋼管2の第二杭2Aaと一体化する際、引き抜く第二鋼管2を通して増加分のコンクリートが供給されるため、第一杭1Aa、1Abとの連結部における第二杭2Aaの断面積が増大する。これによって、第二杭2Aaと両側の第一杭1Aa、1Abとは連結部にコンクリートが補充されて高強度な連続地中壁Rが形成される。図7に示す例では、第二杭2Aaが両側の第一杭1Aa、1Abとの連結部で幅広に形成されている。 Here, when the first piles 1Aa and 1Ab on both sides are disturbed by the claw portion 3 of the second steel pipe 2 and integrated with the second pile 2Aa of the second steel pipe 2, the increased amount of concrete is removed through the second steel pipe 2 to be pulled out. Since it is supplied, the cross-sectional area of the second pile 2Aa at the connecting portion with the first pile 1Aa and 1Ab increases. As a result, concrete is replenished at the connecting portion between the second pile 2Aa and the first piles 1Aa and 1Ab on both sides to form a high-strength continuous underground wall R. In the example shown in FIG. 7, the second pile 2Aa is formed wide at the connecting portion with the first piles 1Aa and 1Ab on both sides.

次に、圧入機6を第一杭1Abから埋設状態の第二鋼管2を1本飛ばした第一鋼管1に移動させる。この第一鋼管1にコンクリートを充填しながらまたは充填した後で、圧入機6で第一鋼管1を引き抜く。圧入機6は他の第一鋼管1に反力をとりながら引き抜き、コンクリート製の第一杭1Acを埋設状態に保持する。
この状態で、図7(a)に示すように、第一杭1Ab、1Acの間の第二鋼管2内にコンクリートを充填しながらまたは充填した後で、圧入機6で第二鋼管2を引き抜く。その際、第一杭1Abと1Acは未硬化状態であり、第二鋼管2を回動させて爪部3を第一杭1Ab、1Acに重ねた状態で揺動させながらまたは揺動させずに直線的に引き抜く。これによって、コンクリート製で略円柱状の第二杭2Abが未硬化状態で地中に埋設される。しかも、未硬化状態の第一杭1Abと1Acは第二鋼管2の対向する爪部3で乱され、互いに未硬化状態であるため、補充されるコンクリートによって第二杭2Abとの連結部が補強されて一体化される。しかも、図7(a)、(b)に示すように第二杭2Abの幅が増大する。
Next, the press-fitting machine 6 is moved from the first pile 1Ab to the first steel pipe 1 in which one buried second steel pipe 2 is skipped. While or after filling the first steel pipe 1 with concrete, the first steel pipe 1 is pulled out by the press-fitting machine 6. The press-fitting machine 6 pulls out the other first steel pipe 1 while taking a reaction force, and holds the concrete first pile 1Ac in the buried state.
In this state, as shown in FIG. 7A, the second steel pipe 2 is pulled out by the press-fitting machine 6 while filling or after filling the second steel pipe 2 between the first piles 1Ab and 1Ac with concrete. .. At that time, the first piles 1Ab and 1Ac are in an uncured state, and the second steel pipe 2 is rotated so that the claw portion 3 is overlapped with the first piles 1Ab and 1Ac and is shaken or not shaken. Pull out in a straight line. As a result, the second pile 2Ab, which is made of concrete and has a substantially columnar shape, is buried in the ground in an uncured state. Moreover, since the uncured first piles 1Ab and 1Ac are disturbed by the facing claws 3 of the second steel pipe 2 and are in an uncured state with each other, the connecting portion with the second pile 2Ab is reinforced by the replenished concrete. And integrated. Moreover, as shown in FIGS. 7A and 7B, the width of the second pile 2Ab increases.

このような作業を繰り返すことで、壁体7はコンクリート製の第一杭1Aと第二杭2Aが交互に配列される。しかも第一杭1A(=1Aa、1Ab、1Ac、…)は第二鋼管2の爪部3に乱されるため、図8(a)、(b)に示すように第一杭1Aと第二杭2A(=2Aa、2Ab、…)は地中で一体化され、第二杭2Aの第一杭1Aとの連結部が拡径された連続地中壁Rが形成される。
なお、連続地中壁Rの必要な壁強度に応じて第一杭1Aや第二杭2A内にH鋼を施工してもよい(図8(c)参照)。
By repeating such work, the concrete first pile 1A and the second pile 2A are alternately arranged in the wall body 7. Moreover, since the first pile 1A (= 1Aa, 1Ab, 1Ac, ...) Is disturbed by the claw portion 3 of the second steel pipe 2, the first pile 1A and the second pile are as shown in FIGS. 8A and 8B. The piles 2A (= 2Aa, 2Ab, ...) Are integrated in the ground to form a continuous underground wall R in which the connecting portion of the second pile 2A with the first pile 1A has an enlarged diameter.
In addition, H steel may be constructed in the first pile 1A and the second pile 2A depending on the required wall strength of the continuous underground wall R (see FIG. 8C).

上述したように、本第一実施形態による連続地中壁Rの施工方法によれば、第一鋼管1の間に圧入された第二鋼管2に対向する爪部3を設けたため、コンクリート製の第一杭1A、1Aの間でコンクリートを充填した第二鋼管2を引き抜く工程を順次繰り返すことで、第一杭1Aと第二杭2Aとが一体化された連続地中壁Rを形成できる。そのため、施工が簡単で低コストである。
しかも、第二鋼管2の引き抜き時に内部にコンクリートを補充することで、両側の第一杭1Aと第二杭2Aとの連結部のコンクリートを補強して高強度な連続地中壁Rを形成でき、止水性も向上する。
As described above, according to the method of constructing the continuous underground wall R according to the first embodiment, since the claw portion 3 facing the second steel pipe 2 press-fitted between the first steel pipes 1 is provided, the concrete is made of concrete. By sequentially repeating the process of pulling out the second steel pipe 2 filled with concrete between the first piles 1A and 1A, a continuous underground wall R in which the first pile 1A and the second pile 2A are integrated can be formed. Therefore, construction is easy and low cost.
Moreover, by replenishing concrete inside when the second steel pipe 2 is pulled out, the concrete at the joint between the first pile 1A and the second pile 2A on both sides can be reinforced to form a high-strength continuous underground wall R. , Water stoppage is also improved.

なお、本発明による連続地中壁Rの施工方法とこれに用いる第二鋼管2は、上述の実施形態に限定されるものではなく、その要旨を逸脱しない範囲で種々の変更や置換等が可能であり、これらの場合も本発明の技術的範囲に含まれる。以下に本発明の他の実施形態や変形例について上述した実施形態と同一または同様な部分、部材には同一の符号を用いて説明する。 The method for constructing the continuous underground wall R according to the present invention and the second steel pipe 2 used therein are not limited to the above-described embodiment, and various changes and replacements can be made without departing from the gist thereof. These cases are also included in the technical scope of the present invention. Hereinafter, other embodiments and modifications of the present invention will be described with reference to the same or similar parts and members as those described above.

図9は第二鋼管2に設置した爪部3の第一変形例を示すものである。
本変形例による爪部13は同図(a)に示すように先端部13aに所定間隔で例えば超硬合金製の刃部14を固定してもよい。刃部14は同図(b)に示すように上側に鋭角の刃14aが突出して形成されている。これによって、第二鋼管2を引き抜く際、両側の第一杭1Aを切削してかき乱すことができる。
また、別の変形例として、図2に示す爪部3の先端部3aに図9に示す爪部13の刃部14を加えた構成を採用してもよい。このような構成を採用すれば爪部3の強度と切削能力が一層高強度となり、未硬化または半硬化状態の第一杭1Aの乱し効果が向上する。また、刃部4、14は超硬合金に限定されることなく、cBN等の適宜の高強度合金を採用できる。
FIG. 9 shows a first modification example of the claw portion 3 installed in the second steel pipe 2.
As shown in FIG. 3A, the claw portion 13 according to the present modification may have a blade portion 14 made of, for example, a cemented carbide fixed to the tip portion 13a at predetermined intervals. As shown in FIG. 3B, the blade portion 14 is formed with an acute-angled blade 14a protruding upward. As a result, when the second steel pipe 2 is pulled out, the first piles 1A on both sides can be cut and disturbed.
Further, as another modification, a configuration in which the blade portion 14 of the claw portion 13 shown in FIG. 9 is added to the tip portion 3a of the claw portion 3 shown in FIG. 2 may be adopted. If such a configuration is adopted, the strength and cutting ability of the claw portion 3 become higher, and the disturbing effect of the uncured or semi-cured first pile 1A is improved. Further, the blade portions 4 and 14 are not limited to cemented carbide, and an appropriate high-strength alloy such as cBN can be adopted.

次に、本発明の第二実施形態による連続地中壁Rの施工方法について、図10〜図13により説明する。
図10において、第一鋼管打設工程として、壁体7の施工方向に沿って第二鋼管2の1本の間隔を開けて第一鋼管1を圧入機6で圧入する。第一鋼管1の打設は、圧入、回転圧入、揺動圧入のいずれでもよい。次に第一掘削工程として、第一鋼管1を打設しながらまたは打設した後に第一鋼管1内を図示しない掘削機で掘削する。
そして、第一固化材料充填工程において、第一鋼管1内にコンクリート等の固化材料を充填しながらまたは充填した後に第一鋼管1を引き抜く。第一鋼管1を引き抜くことで、コンクリート製で略円柱状の第一杭1Aaが未硬化状態で地中に埋設される。
Next, the construction method of the continuous underground wall R according to the second embodiment of the present invention will be described with reference to FIGS. 10 to 13.
In FIG. 10, as a step of placing the first steel pipe, the first steel pipe 1 is press-fitted by the press-fitting machine 6 at intervals of one of the second steel pipes 2 along the construction direction of the wall body 7. The casting of the first steel pipe 1 may be press-fitting, rotary press-fitting, or rocking press-fitting. Next, as the first excavation step, the inside of the first steel pipe 1 is excavated by an excavator (not shown) while or after the first steel pipe 1 is driven.
Then, in the first solidifying material filling step, the first steel pipe 1 is pulled out while or after the solidifying material such as concrete is filled in the first steel pipe 1. By pulling out the first steel pipe 1, a concrete, substantially columnar first pile 1Aa is buried in the ground in an uncured state.

また、図11に示すように、第一杭1Aaから間隔を開けた隣の位置で、第一鋼管1内にコンクリート等の固化材料を充填しながらまたは充填した後に第一鋼管1を引き抜く。第一鋼管1を引き抜くことで、コンクリート製で略円柱状の第一杭1Abが未硬化状態で地中に埋設される。
次に、第二鋼管打設工程として、第一杭1Aa、1Abの間に第二鋼管2を圧入機6で圧入する。第二鋼管2は下端部の対向する位置に一対の爪部3(または爪部13)が固定されているため、第一杭1Aa,1Abと干渉しないように圧入または揺動圧入によって打設する。第二掘削工程として、第二鋼管2を打設しながらまたは打設した後に第二鋼管2内を図示しない掘削機で掘削して排土する。
Further, as shown in FIG. 11, the first steel pipe 1 is pulled out while or after the solidifying material such as concrete is filled in the first steel pipe 1 at a position adjacent to the first pile 1Aa at a distance. By pulling out the first steel pipe 1, a concrete, substantially columnar first pile 1Ab is buried in the ground in an uncured state.
Next, as a second steel pipe placing process, the second steel pipe 2 is press-fitted between the first piles 1Aa and 1Ab by the press-fitting machine 6. Since the pair of claws 3 (or claws 13) are fixed to the opposite positions of the lower end of the second steel pipe 2, the second steel pipe 2 is driven by press-fitting or rocking press-fitting so as not to interfere with the first piles 1Aa and 1Ab. .. As the second excavation step, the inside of the second steel pipe 2 is excavated by an excavator (not shown) while or after the second steel pipe 2 is driven, and soil is discharged.

次に第二固化材料充填工程として、図12に示すように、地中に埋設した第二鋼管2内にコンクリートを充填しながらまたは充填した後に第二鋼管2を圧入機6で引き抜く。これによってコンクリート製の第二杭2Aaが地中に埋設される。第二鋼管2の引き抜き時に、第二鋼管2の外側に突出する爪部3によって両側の第一杭1Aa、1Abを乱しながら第二鋼管2を引き抜く。しかも、第二鋼管2の引き抜き時に第二鋼管2を通して追加のコンクリートを補充する。
その際、第一杭1Aaと1Abは未硬化状態であり、第二鋼管2を回動させて爪部3を第一杭1Ab、1Acに重ねた状態で揺動させながらまたは揺動させずに直線的に引き抜く。これによって、コンクリート製で略円柱状の第二杭2Aaが未硬化状態で地中に埋設される。しかも、未硬化状態の第一杭1Aaと1Abは第二鋼管2の対向する爪部3で乱されるため第二杭2Aaと一体化され、追加のコンクリートによって第二杭2Aaの連結部が拡径される。
Next, as a second solidifying material filling step, as shown in FIG. 12, the second steel pipe 2 is pulled out by the press-fitting machine 6 while filling or after filling the second steel pipe 2 buried in the ground with concrete. As a result, the second concrete pile 2Aa is buried in the ground. When the second steel pipe 2 is pulled out, the second steel pipe 2 is pulled out while disturbing the first piles 1Aa and 1Ab on both sides by the claws 3 protruding to the outside of the second steel pipe 2. Moreover, when the second steel pipe 2 is pulled out, additional concrete is replenished through the second steel pipe 2.
At that time, the first piles 1Aa and 1Ab are in an uncured state, and the second steel pipe 2 is rotated so that the claw portion 3 is overlapped with the first piles 1Ab and 1Ac and is shaken or not shaken. Pull out in a straight line. As a result, the second pile 2Aa, which is made of concrete and has a substantially columnar shape, is buried in the ground in an uncured state. Moreover, since the uncured first piles 1Aa and 1Ab are disturbed by the facing claws 3 of the second steel pipe 2, they are integrated with the second pile 2Aa, and the connecting portion of the second pile 2Aa is expanded by the additional concrete. Be stakeout.

このような作業を繰り返すことで、第一鋼管1を引き抜いた第一杭1A、1Aの間に第二鋼管2を引き抜いた第二杭2Aが連結される。しかも、未硬化状態の第一杭1Aは第二鋼管2の爪部3に乱され且つ追加のコンクリートが補充されるため、図13に示すように、第二杭2Aの両側の第一杭1Aとの連結部が拡径された連続地中壁Rが形成される。なお、第二鋼管2の第二固化材料充填工程は、先に打設した第一杭1A、1Aが未硬化の段階で行うものである。そのため、第二固化材料充填工程に至るまでの第一杭1Aの打設可能本数は制限され、これらの施工を繰り返して行う。
本第二実施形態においても、高強度な連続地中壁Rを構築できる上に施工工数とコストを削減できる。
By repeating such work, the second pile 2A from which the second steel pipe 2 is pulled out is connected between the first piles 1A and 1A from which the first steel pipe 1 is pulled out. Moreover, since the uncured first pile 1A is disturbed by the claw portion 3 of the second steel pipe 2 and is replenished with additional concrete, as shown in FIG. 13, the first pile 1A on both sides of the second pile 2A A continuous underground wall R is formed in which the diameter of the connecting portion with the pile is expanded. The second solidifying material filling step of the second steel pipe 2 is performed at the stage where the first piles 1A and 1A placed earlier are uncured. Therefore, the number of piles 1A that can be driven up to the second solidifying material filling step is limited, and these constructions are repeated.
Also in the second embodiment, it is possible to construct a high-strength continuous underground wall R and reduce the construction man-hours and costs.

次に、本発明の第三実施形態による連続地中壁Rの施工方法について、図14〜図17に示す各工程により説明する。本実施形態では硬質地盤に連続地中壁Rを構築するものであり、爪部3を設置した第二鋼管2を回転圧入によって硬質地盤に埋設する。そのため、第二鋼管2を先に圧入し、その後に第一鋼管1を圧入する。
図14に示す第二鋼管打設工程において、圧入機6を用いて壁体7の施工方向に沿って間隔を開けて第二鋼管2を回転圧入によって地中に埋設する。第二掘削工程として第二鋼管2を打設しながらまたは打設した後で、掘削機によって第二鋼管2内を掘削して排土する。
次に、図15において、第一鋼管打設工程として、埋設した第二鋼管2の間に第一鋼管1を圧入する。第一鋼管1の圧入は、圧入、回転圧入、揺動圧入のいずれを用いてもよい。第一鋼管1の打設をしながらまたは打設後に第一鋼管1内を掘削する。
Next, the construction method of the continuous underground wall R according to the third embodiment of the present invention will be described by each step shown in FIGS. 14 to 17. In the present embodiment, a continuous underground wall R is constructed on the hard ground, and the second steel pipe 2 on which the claw portion 3 is installed is buried in the hard ground by rotary press-fitting. Therefore, the second steel pipe 2 is press-fitted first, and then the first steel pipe 1 is press-fitted.
In the second steel pipe driving step shown in FIG. 14, the second steel pipe 2 is buried in the ground by rotary press-fitting at intervals along the construction direction of the wall body 7 using the press-fitting machine 6. As the second excavation step, the inside of the second steel pipe 2 is excavated by an excavator and the soil is discharged while or after the second steel pipe 2 is driven.
Next, in FIG. 15, as the first steel pipe placing step, the first steel pipe 1 is press-fitted between the buried second steel pipe 2. As the press-fitting of the first steel pipe 1, any of press-fitting, rotary press-fitting, and rocking press-fitting may be used. The inside of the first steel pipe 1 is excavated while or after the driving of the first steel pipe 1.

そして、図15の第一固化材料充填工程において、第一鋼管1内にコンクリートを充填しながらまたは充填した後に第一鋼管1を圧入機6で引き抜く。第一鋼管1の引き抜きによってコンクリート製で略円柱状の第一杭1Aaが地中に埋設される。また、図16において、第一杭1Aaから第二鋼管2を飛ばした第一鋼管1内にコンクリートを充填しながらまたは充填した後に第一鋼管1を圧入機6で引き抜く。この第一鋼管1の引き抜きによってコンクリート製で略円柱状の第一杭1Abが地中に埋設される。
そして、図17に示す第二固化材料充填工程において、第一杭1Aa、1Abの間に圧入された第二鋼管2内にコンクリートを充填しながらまたは充填した後に第二鋼管2を圧入機6で引き抜く。これによってコンクリート製の第二杭2Aaが地中に埋設される。
Then, in the first solidifying material filling step of FIG. 15, the first steel pipe 1 is pulled out by the press-fitting machine 6 while or after the concrete is filled in the first steel pipe 1. By pulling out the first steel pipe 1, a concrete, substantially columnar first pile 1Aa is buried in the ground. Further, in FIG. 16, the first steel pipe 1 is pulled out by the press-fitting machine 6 while filling or after filling the first steel pipe 1 from which the second steel pipe 2 is skipped from the first pile 1Aa. By pulling out the first steel pipe 1, a concrete, substantially columnar first pile 1Ab is buried in the ground.
Then, in the second solidifying material filling step shown in FIG. 17, the second steel pipe 2 is press-fitted with the press-fitting machine 6 while filling or after filling the second steel pipe 2 press-fitted between the first piles 1Aa and 1Ab with concrete. Pull out. As a result, the second concrete pile 2Aa is buried in the ground.

第二鋼管2の引き抜き時に、第二鋼管2の外側に突出する爪部3によって両側の第一杭1Aa、1Abをかき乱しながら第二鋼管2を引き抜く。第二鋼管2の引き抜きは爪部3を第一杭1Aa,1Abに重ねて揺動させずに、或いは第二鋼管2を揺動させながら行う。これによって、コンクリート製で略円柱状の第二杭2Aaが未硬化状態で地中に埋設される。
しかも、未硬化状態の第一杭1Aaと1Abは第二鋼管2の爪部3で乱されて未硬化状態の第二杭2Aaと一体化され、しかも補充コンクリートによって第二杭2Aaの連結部が拡径される。
When the second steel pipe 2 is pulled out, the second steel pipe 2 is pulled out while disturbing the first piles 1Aa and 1Ab on both sides by the claws 3 protruding to the outside of the second steel pipe 2. The second steel pipe 2 is pulled out by overlapping the claws 3 on the first piles 1Aa and 1Ab without swinging, or swinging the second steel pipe 2. As a result, the second pile 2Aa, which is made of concrete and has a substantially columnar shape, is buried in the ground in an uncured state.
Moreover, the uncured first piles 1Aa and 1Ab are disturbed by the claw portion 3 of the second steel pipe 2 and integrated with the uncured second pile 2Aa, and the connecting portion of the second pile 2Aa is formed by the supplementary concrete. The diameter is expanded.

このような作業を繰り返すことで、第一鋼管1を引き抜いた第一杭1A、1Aの間で第二鋼管2を引き抜いた第二杭2Aが埋設されてコンクリート製の第一杭1Aと第二杭2Aが交互に配列される。未硬化状態の第一杭1Aは第二鋼管2の爪部3に乱されるため地中で一体化され、しかも補充コンクリートが加わって図17に示すように第二杭2Aの両側の第一杭1Aとの連結部が拡径された連続地中壁Rが形成される。
本第三実施形態においても、高強度な連続地中壁Rを構築でき、施工工数とコストを削減できる。
By repeating such work, the second pile 2A from which the second steel pipe 2 is pulled out is buried between the first pile 1A and 1A from which the first steel pipe 1 is pulled out, and the first pile 1A and the second pile made of concrete are buried. The piles 2A are arranged alternately. Since the uncured first pile 1A is disturbed by the claw portion 3 of the second steel pipe 2, it is integrated in the ground, and supplementary concrete is added to the first pile 2A on both sides as shown in FIG. A continuous underground wall R is formed in which the diameter of the connecting portion with the pile 1A is expanded.
Also in the third embodiment, a high-strength continuous underground wall R can be constructed, and the construction man-hours and costs can be reduced.

また、連続地中壁Rを施工する際、近接箇所に他の既設構造物が設置されている場合がある。この場合には、図18に示すように施工方向に配列された第一鋼管1及び第二鋼管2(第一杭1A及び第二杭2A)からなる壁体7の一方の外側の接線である外接線Lより第二鋼管2の爪部3が飛び出さないように施工する必要がある。この場合には、第二鋼管2を圧入施工するか、外接線Lと隣の第一鋼管1との隙間の範囲内で揺動圧入することで、爪部3が外接線Lより飛び出さないように施工することができる。この場合、爪部3を例えば各辺が凸曲線をなす略三角形板状等に形成すればよい。
また、既設構造物は壁体7の一方だけでなく対向する他方にも構築されていてもよい。両方の外接線L,Laに挟まれた領域で第二鋼管2を圧入施工するか、両側の外接線L、Laと隣の第一鋼管1との隙間の範囲内で揺動圧入することで、爪部3が外接線L、Laより飛び出さないように施工することができる。
In addition, when constructing the continuous underground wall R, other existing structures may be installed in the vicinity. In this case, it is an outer tangent line of one of the wall body 7 composed of the first steel pipe 1 and the second steel pipe 2 (first pile 1A and second pile 2A) arranged in the construction direction as shown in FIG. It is necessary to construct so that the claw portion 3 of the second steel pipe 2 does not protrude from the tangent line L. In this case, the claw portion 3 does not protrude from the circumscribed line L by press-fitting the second steel pipe 2 or swinging and press-fitting within the gap between the circumscribed line L and the adjacent first steel pipe 1. It can be constructed as follows. In this case, the claw portion 3 may be formed, for example, in the shape of a substantially triangular plate having a convex curve on each side.
Further, the existing structure may be constructed not only on one side of the wall body 7 but also on the other side facing the wall body 7. By press-fitting the second steel pipe 2 in the region sandwiched between both circumscribed lines L and La, or by rocking and press-fitting within the gap between the circumscribed lines L and La on both sides and the adjacent first steel pipe 1. , The claw portion 3 can be constructed so as not to protrude from the circumscribed lines L and La.

なお、上述した各実施形態や変形例では、第二鋼管2に爪部3を対向して固定配置したが、この場合、第二鋼管2を地中に圧入する際に爪部3が抵抗になるため回転圧入か揺動圧入で行われることがある。
これに対して、本第二変形例では爪部16を拡縮可能または進退可能に設置した。以下に、拡縮可能な爪部16の一例を図19及び図20により説明する。図19に示す第二鋼管2の下端部において、対向する位置に第二変形例による拡縮可能な爪部16が対向して設置されている。爪部16は、第二鋼管2の外周面に固定された軸受部17と、軸受部17の貫通孔に挿通された支軸18と、支軸18の両端部を嵌合させていて支軸18を中心に上下方向に回動可能な爪部本体19とを備えている。
In each of the above-described embodiments and modifications, the claw portion 3 is fixedly arranged to face the second steel pipe 2, but in this case, the claw portion 3 becomes a resistance when the second steel pipe 2 is press-fitted into the ground. Therefore, it may be performed by rotary press-fitting or rocking press-fitting.
On the other hand, in this second modification, the claw portion 16 is installed so that it can be expanded / contracted or moved forward / backward. Hereinafter, an example of the expandable claw portion 16 will be described with reference to FIGS. 19 and 20. At the lower end of the second steel pipe 2 shown in FIG. 19, the expandable and contractible claws 16 according to the second modification are installed facing each other at opposite positions. The claw portion 16 fits the bearing portion 17 fixed to the outer peripheral surface of the second steel pipe 2, the support shaft 18 inserted through the through hole of the bearing portion 17, and both ends of the support shaft 18. A claw portion main body 19 that can rotate in the vertical direction around the 18 is provided.

爪部本体19は図20に示すように第二鋼管2の外周面に沿った凹曲面をなす板状とされ、その基部には軸受部17を嵌入可能な凹部19aが形成され、刃部をなす先端部19bは厚み方向に傾斜する凸曲面または傾斜面とされている。凹部19a内の両側面には支軸18を嵌入させる穴部が形成されている。また、凹部19aの両側の端部はストッパ部19cであり、爪部本体19が水平位置に開いた際に第二鋼管2の外周面に当接して引き抜き時のかき乱し荷重を受けることができる。 As shown in FIG. 20, the claw portion main body 19 has a plate shape having a concave curved surface along the outer peripheral surface of the second steel pipe 2, and a recess 19a into which the bearing portion 17 can be fitted is formed at the base thereof, and the blade portion is formed. The tip portion 19b of the eggplant is a convex curved surface or an inclined surface that is inclined in the thickness direction. Holes for fitting the support shaft 18 are formed on both side surfaces in the recess 19a. Further, both end portions of the recess 19a are stopper portions 19c, and when the claw portion main body 19 is opened in a horizontal position, it comes into contact with the outer peripheral surface of the second steel pipe 2 and can receive a disturbing load at the time of pulling out.

爪部本体19は常態において凹曲面が第二鋼管2の外周面に当接した起立位置に保持され、この状態で先端部19bは第二鋼管2の外周面から厚み方向に離間するに従って上方に湾曲または傾斜するポケットPを形成する。地中に埋設した第二鋼管2を引き抜くと先端部19bのポケットPに第一杭1Aのコンクリート等が流入するため、爪部本体19が支軸18回りに外側に開いて略水平位置に拡径され、第一杭1Aを掘削してかき乱すことができる。
一方、第二鋼管2の圧入に際して爪部本体19は起立して外周面に当接した縮径状態に保持され、圧入の邪魔にならない。そのため第二鋼管2は回転圧入や揺動圧入だけでなく、直線的に圧入できる。
The claw portion main body 19 is normally held in an upright position where the concave curved surface is in contact with the outer peripheral surface of the second steel pipe 2, and in this state, the tip portion 19b is moved upward as it is separated from the outer peripheral surface of the second steel pipe 2 in the thickness direction. Form a curved or sloping pocket P. When the second steel pipe 2 buried in the ground is pulled out, the concrete or the like of the first pile 1A flows into the pocket P of the tip portion 19b, so that the claw portion main body 19 opens outward around the support shaft 18 and expands to a substantially horizontal position. The diameter is increased and the first pile 1A can be excavated and disturbed.
On the other hand, when the second steel pipe 2 is press-fitted, the claw portion main body 19 stands up and is held in a reduced diameter state in contact with the outer peripheral surface, and does not interfere with the press-fitting. Therefore, the second steel pipe 2 can be press-fitted linearly as well as rotary press-fitting and rocking press-fitting.

また、上述した各実施形態では、爪部3、13、16を第二鋼管2の下端部近傍に設置してほぼ全長に亘って止水可能で壁体強度を備えた連続地中壁Rを施工するようにした。しかしながら、例えば連続地中壁Rが壁体強度よりも止水に目的であるなら、止水範囲に爪部3や爪部16を設置すればよい。このような変形例による連続地中壁Rの施工方法について図21により説明する。
図21(a)において、例えば地中に粘土層あり、その上側に地下水が流れている場合、この地下水を止水するためには粘土層の上側に連続壁体R1が施工されていればよい。そのため、粘土層に対応する第二鋼管2の長手方向中間位置に爪部3を設置する。
Further, in each of the above-described embodiments, the claw portions 3, 13 and 16 are installed near the lower end portion of the second steel pipe 2 to provide a continuous underground wall R capable of stopping water over almost the entire length and having wall strength. I tried to construct it. However, for example, if the continuous underground wall R is intended for water stoppage rather than wall strength, the claw portion 3 or the claw portion 16 may be installed in the water stop range. A method of constructing the continuous underground wall R according to such a modification will be described with reference to FIG.
In FIG. 21A, for example, when there is a clay layer in the ground and groundwater is flowing above the clay layer, a continuous wall body R1 may be constructed on the upper side of the clay layer in order to stop the groundwater. .. Therefore, the claw portion 3 is installed at an intermediate position in the longitudinal direction of the second steel pipe 2 corresponding to the clay layer.

本変形例では、例えば打設された第一鋼管1内にコンクリートを充填しながらまたは充填した後に第一鋼管1を引き抜いて第一杭1Aa、1Abを順次施工する。次に、第一杭1Aa、1Abの間の第二鋼管2内にコンクリートを充填しながらまたは充填した後に第二鋼管2を引き抜くことで、爪部3を設けた部分から上側で第一杭1Aa,1Abのコンクリートをかき乱し、更に補充コンクリートを加えて第二杭2Aaの両側を拡幅して第一杭1Aa,1Abと一体化させる。このような作業を順次行うことで図21(b)に示す連続壁体R1が止水範囲に形成される。
この場合、連続壁体R1の下側の第一杭1Aと第二杭2Aが互いに連結されていなくても土圧は第一杭1Aと第二杭2A自身の曲げ強度で支持できて、連続地中壁Rの壁体強度を確保できる。しかも、爪部3の下側で第一杭1Aの掘削によるかき乱しをしなくてもよく、施工がより迅速でコンクリート等の材料コストを削減できる。
In this modification, for example, the first steel pipe 1 is pulled out while filling or after filling the first steel pipe 1 that has been cast, and the first piles 1Aa and 1Ab are sequentially constructed. Next, by pulling out the second steel pipe 2 while filling or after filling the second steel pipe 2 between the first piles 1Aa and 1Ab, the first pile 1Aa is on the upper side from the portion where the claw portion 3 is provided. , 1Ab of concrete is disturbed, and supplementary concrete is added to widen both sides of the second pile 2Aa and integrated with the first piles 1Aa and 1Ab. By sequentially performing such operations, the continuous wall body R1 shown in FIG. 21B is formed in the water stop range.
In this case, even if the first pile 1A and the second pile 2A on the lower side of the continuous wall body R1 are not connected to each other, the earth pressure can be supported by the bending strength of the first pile 1A and the second pile 2A themselves and is continuous. The wall strength of the underground wall R can be secured. Moreover, it is not necessary to disturb the lower side of the claw portion 3 by excavating the first pile 1A, the construction is quicker, and the cost of materials such as concrete can be reduced.

また、連続地中壁Rの第一杭1Aと第二杭2Aにポストテンション方式でプレストレスを導入してもよい。この変形例について図22〜図24により説明するが、図では第一鋼管1とこれに対応する第一杭1Aのみを示し、他の第一鋼管1と第二鋼管2に対応する第一杭1A,第二杭2Aは省略する。
上述した各実施形態と同様に第一鋼管1及び第二鋼管2を地中に打設して第一鋼管1及び第二鋼管2の内部を掘削して排土する。図22に示す第一鋼管1内にプレストレスユニット21を設置する。プレストレスユニット21は、端板22の一方の面にPC鋼線23を内蔵したシース管24を設置し、端板22の他方の面にPC鋼線23を貫通させて定着具25で定着させる。プレストレスユニット21は端板22を排土した第一鋼管1の下端部に設置し、PC鋼線23及びシース管24を第一鋼管1の内部を通して上部開口から外部に延ばしておく。
Further, prestress may be introduced into the first pile 1A and the second pile 2A of the continuous underground wall R by a post-tension method. This modification will be described with reference to FIGS. 22 to 24, but in the figure, only the first steel pipe 1 and the corresponding first pile 1A are shown, and the first pile corresponding to the other first steel pipe 1 and the second steel pipe 2 is shown. 1A and the second pile 2A are omitted.
Similar to each of the above-described embodiments, the first steel pipe 1 and the second steel pipe 2 are driven into the ground, and the inside of the first steel pipe 1 and the second steel pipe 2 is excavated to remove soil. The prestress unit 21 is installed in the first steel pipe 1 shown in FIG. 22. In the prestress unit 21, a sheath tube 24 having a built-in PC steel wire 23 is installed on one surface of the end plate 22, and the PC steel wire 23 is passed through the other surface of the end plate 22 and fixed by the fixing tool 25. .. The prestress unit 21 is installed at the lower end of the first steel pipe 1 from which the end plate 22 is discharged, and the PC steel wire 23 and the sheath pipe 24 are extended from the upper opening to the outside through the inside of the first steel pipe 1.

そして、上述した各実施形態と同様の工程により、図23に示すように第一鋼管1内にコンクリートを充填しながらまたは充填した後で圧入機6によって第一鋼管1を地中から引き抜き、第一杭1Aを生成する。コンクリートを充填しながらまたは充填した後で第二鋼管2を引き抜く際に爪部3によってその両側に設けた第一杭1Aを乱して第二杭2Aと一体化する。次に第一杭1Aを養生させて所定の強度を発現した後に、コンクリート製の第一杭1Aの上面に蓋26を設置してシース管24内のPC鋼線23を貫通させて引っ張り、定着具25で第一杭1Aを緊張させて保持する。第二鋼管2に対応する第二杭2Aについても同様の工程によりプレストレス(圧縮力)を付与する。
これによって、全ての第一鋼管1及び第二鋼管2に対応する第一杭1A及び第二杭2Aの連続地中壁Rについてプレストレスがかかった状態になり、荷重を受けても引張応力を制御してひび割れ等を防ぐことができる。
Then, by the same process as each of the above-described embodiments, the first steel pipe 1 is pulled out from the ground by the press-fitting machine 6 while or after the concrete is filled in the first steel pipe 1 as shown in FIG. Generate one pile 1A. When the second steel pipe 2 is pulled out while filling or after filling the concrete, the first pile 1A provided on both sides of the second steel pipe 2 is disturbed by the claw portion 3 and integrated with the second pile 2A. Next, after the first pile 1A is cured to develop a predetermined strength, a lid 26 is installed on the upper surface of the concrete first pile 1A, and the PC steel wire 23 in the sheath pipe 24 is pulled through and fixed. The tool 25 tensions and holds the first pile 1A. Prestress (compressive force) is applied to the second pile 2A corresponding to the second steel pipe 2 by the same process.
As a result, prestress is applied to the continuous underground wall R of the first pile 1A and the second pile 2A corresponding to all the first steel pipe 1 and the second steel pipe 2, and the tensile stress is applied even if a load is applied. It can be controlled to prevent cracks and the like.

なお、全ての第一鋼管1及び第二鋼管2に対応する第一杭1A及び第二杭2Aにプレストレスをかけなくてもよい。例えば第一杭1Aのみ、または第二杭2Aのみにプレストレスをかけてもよい。或いは、一部の第一杭1Aや第二杭2Aのみ、或いは曲げ荷重がかかる部分のコンクリートのみプレストレスを導入してもよい。 It is not necessary to apply prestress to the first pile 1A and the second pile 2A corresponding to all the first steel pipe 1 and the second steel pipe 2. For example, prestress may be applied only to the first pile 1A or only the second pile 2A. Alternatively, prestress may be introduced only in a part of the first pile 1A and the second pile 2A, or only in the concrete of the part where the bending load is applied.

上述した各実施形態や変形例等による連続地中壁Rの施工方法において、第二鋼管2の引き抜き時に爪部3,13、16でコンクリート製の第一杭1Aを掘削してかき乱す際、第一杭1Aは未硬化状態であるとした。爪部3,13、16による第一杭1Aのかき乱しはコンクリートの凝結始発時間から凝結終結時間の範囲で行うことが好ましい。また、凝結終結時間後であっても半硬化状態または硬化状態で第一杭1Aを削ってかき乱してもよい。この場合でも追加の補充コンクリートで第二杭2Aと一体化できる。 In the construction method of the continuous underground wall R according to each of the above-described embodiments and deformation examples, when the first pile 1A made of concrete is excavated and disturbed by the claws 3, 13 and 16 when the second steel pipe 2 is pulled out, the first It is assumed that one pile 1A is in an uncured state. It is preferable that the first pile 1A is disturbed by the claw portions 3, 13 and 16 within the range from the condensation start time to the condensation end time of the concrete. Further, even after the condensation completion time, the first pile 1A may be scraped and disturbed in a semi-cured state or a cured state. Even in this case, it can be integrated with the second pile 2A with additional supplementary concrete.

また、上述した各実施形態や変形例等の連続地中壁Rの施工方法では、第一鋼管1及び第二鋼管2の圧入と引き抜きを圧入機6によって行うようにしたが、本発明はこのような構成に限定されない。圧入機6に代えて、公知の圧入引き抜き装置を採用できる。 Further, in the method of constructing the continuous underground wall R such as each of the above-described embodiments and modifications, the press-fitting machine 6 is used to press-fit and pull out the first steel pipe 1 and the second steel pipe 2. It is not limited to such a configuration. Instead of the press-fitting machine 6, a known press-fitting / pulling-out device can be adopted.

また、第二鋼管2の爪部3、13、16は円弧板状に形成したが、第二鋼管2の全周にリング状に形成されていてもよい。この構成を採用すれば、第二鋼管2の引き抜き時に爪部3を第一杭1Aと重なるように位置合わせする必要がなく、また爪部3を揺動または回転させる必要もない。
この場合には第三実施形態のように第二鋼管2を第一鋼管1より先に打設することが好ましい。また、上述した各実施形態や変形例等の連続地中壁Rの施工方法において、一部の第一鋼管1を他の第一鋼管1や第二鋼管2より長く設定して第一杭1Aや第二杭2Aを形成してもよい。
Further, although the claw portions 3, 13 and 16 of the second steel pipe 2 are formed in the shape of an arc plate, they may be formed in the shape of a ring all around the second steel pipe 2. If this configuration is adopted, it is not necessary to align the claw portion 3 so as to overlap with the first pile 1A when the second steel pipe 2 is pulled out, and it is not necessary to swing or rotate the claw portion 3.
In this case, it is preferable to drive the second steel pipe 2 before the first steel pipe 1 as in the third embodiment. Further, in the construction method of the continuous underground wall R such as each of the above-described embodiments and deformation examples, a part of the first steel pipe 1 is set longer than the other first steel pipe 1 and the second steel pipe 2, and the first pile 1A is set. Or the second pile 2A may be formed.

次に、上述した第二実施形態による連続地中壁Rの施工方法の変形例について、図25により説明する。
本変形例の施工方法では、図25において、第一鋼管1を間隔を開けて打設しながらまたは打設後に掘削機で第一鋼管内を掘削するが、第二鋼管2は第一鋼管1の間に順次打設することはしない。例えば、適宜の隣り合う2本の第一鋼管1の間に第二鋼管2を打設する。第二鋼管2を打設しながらまたは打設後に第二鋼管2内を掘削する。
そして、両側の第一鋼管1内に固化材料を充填しながらまたは充填した後に、第一鋼管1を順次引き抜く。得られた第一杭1Aa,1Abの間に打設した第二鋼管2内に固化材料を充填しながらまたは充填した後に第二鋼管2を引き抜く。その際、第二鋼管2の爪部3によって未硬化の第一杭1Aa及び第一杭1Abを掻き乱しながら引き抜く。
次に、図25に示すように、第一杭1Abと第一鋼管1の間に第二鋼管2を打設して同様に施工してもよい。或いは離れた位置で、隣り合う第一鋼管1の間に第二鋼管2を打設して同様に施工してもよい。このように、必ずしも打設した第一鋼管1の間に順次第二鋼管2を打設しなくてもよく、結果的に第一杭1Aと第二杭2Aとで連続する連続壁Rが構築できればよい。
Next, a modified example of the construction method of the continuous underground wall R according to the second embodiment described above will be described with reference to FIG. 25.
In the construction method of this modification, in FIG. 25, the inside of the first steel pipe is excavated with an excavator while or after the first steel pipe 1 is driven at intervals, but the second steel pipe 2 is the first steel pipe 1. It is not placed in sequence between. For example, the second steel pipe 2 is placed between two adjacent first steel pipes 1 as appropriate. The inside of the second steel pipe 2 is excavated while or after the second steel pipe 2 is driven.
Then, the first steel pipe 1 is sequentially pulled out while or after the solidifying material is filled in the first steel pipe 1 on both sides. The second steel pipe 2 is pulled out while or after the solidifying material is filled in the second steel pipe 2 placed between the obtained first piles 1Aa and 1Ab. At that time, the uncured first pile 1Aa and the first pile 1Ab are pulled out while being disturbed by the claw portion 3 of the second steel pipe 2.
Next, as shown in FIG. 25, the second steel pipe 2 may be placed between the first pile 1Ab and the first steel pipe 1 and constructed in the same manner. Alternatively, the second steel pipe 2 may be placed between the adjacent first steel pipes 1 at a distant position and constructed in the same manner. In this way, it is not always necessary to sequentially drive the second steel pipe 2 between the first steel pipes 1 that have been driven, and as a result, a continuous wall R that is continuous between the first pile 1A and the second pile 2A is constructed. I hope I can.

図26は他の変形例による連続地中壁Rを示すものである。
河川や沼H等に連続地中壁Rを施工する場合、水中でコンクリート等の固化材料は硬化前には自立できない。そのため、連続地中壁Rを構成する第一杭1Aの第一鋼管1及び第二杭2Aの第二鋼管2を完全に引き抜かないで、第一杭1A、第二杭2Aの上部の水中に一部残して覆ってもよい。
本変形例による連続地中壁Rでは、河川や沼H等の水底の地盤内では、第一鋼管1と第二鋼管2を途中まで引き抜いて第一杭1Aa,1Abと第二杭2Aaとを第二鋼管2の爪部3で掻き乱した一体化する。この部分の連続地中壁Rは地盤に接触している。
その上部から河川や沼等の水中では、第一杭1Aa,1Abの上部に第一鋼管1を残して、水に接触させている。しかも、第一鋼管1の水面より上方は必要に応じてカットしている。地盤中の第二杭2Aaの上部にも第二鋼管2を残しており、河川や沼等の水中で水に接触させている。しかも、第二鋼管2の下端部の爪部3は地中に埋設されている。第二鋼管2の水面より上方は必要に応じてカットしている。第一鋼管1、第二鋼管2の上端部に継手28を設けて鋼管を接続して延ばしてもよいし、継手28で分離除去してもよい。
水底から地盤中の第一杭1Aa,1Ab及び第二杭2Aaの上部までの根入れ部Pは第一鋼管1及び第二鋼管2を残すことで連続地中壁Rの強度を増している。
FIG. 26 shows a continuous underground wall R according to another modification.
When a continuous underground wall R is constructed in a river, swamp H, etc., the solidified material such as concrete cannot stand on its own before hardening in water. Therefore, the first steel pipe 1 of the first pile 1A and the second steel pipe 2 of the second pile 2A constituting the continuous underground wall R are not completely pulled out, but are submerged in the water above the first pile 1A and the second pile 2A. You may leave a part and cover it.
In the continuous underground wall R according to this modification, the first steel pipe 1 and the second steel pipe 2 are pulled out halfway to form the first pile 1Aa, 1Ab and the second pile 2Aa in the ground of the bottom of the water such as a river or a swamp H. The claw portion 3 of the second steel pipe 2 is disturbed and integrated. The continuous underground wall R in this portion is in contact with the ground.
In water such as rivers and swamps from above, the first steel pipe 1 is left above the first piles 1Aa and 1Ab and is in contact with water. Moreover, the area above the water surface of the first steel pipe 1 is cut as necessary. The second steel pipe 2 is also left above the second pile 2Aa in the ground, and is in contact with water in water such as rivers and swamps. Moreover, the claw portion 3 at the lower end of the second steel pipe 2 is buried in the ground. The area above the water surface of the second steel pipe 2 is cut as necessary. A joint 28 may be provided at the upper ends of the first steel pipe 1 and the second steel pipe 2 to connect and extend the steel pipe, or the joint 28 may separate and remove the pipe.
The rooting portion P from the bottom of the water to the upper part of the first pile 1Aa, 1Ab and the second pile 2Aa in the ground increases the strength of the continuous underground wall R by leaving the first steel pipe 1 and the second steel pipe 2.

また、第一杭1Aや第二杭2Aの長手方向の上部等の一部に第一鋼管1や第二鋼管2を残す構成は、水中に限らず高天端等、地上に壁部が突出しているような領域に連続壁を形成する場合にも適用できる。これによって、地上の壁部で例えば土圧がかかるような連続壁面に固化材料の第一杭1Aや第二杭2Aを第一鋼管1や第二鋼管2で保護して当接させ、連続壁の一部に連結することができる。第一杭1Aや第二杭2Aに続く地上の第一鋼管1や第二鋼管2はわずかな間隙を開けて起立している。本明細書では、このような地上に延びる連続壁も連続地中壁Rに含めるものとする。
また、本実施形態による連続地中壁Rの他の変形例として、第一杭1Aや第二杭2Aの上部に残した第一鋼管1及び第二鋼管2の配列の一方の片側に土壁や固化材料が接触し他方の片側が空間に接触していてもよい。或いは、第一鋼管1及び第二鋼管2の両側に空間が接触している場合や、第一鋼管1及び第二鋼管2の一方の片側に土壁や固化材料が接触し、他方の片側に水面が接触している場合等、各種の場合も含めることができる。
Further, in the configuration in which the first steel pipe 1 and the second steel pipe 2 are left in a part of the upper portion of the first pile 1A and the second pile 2A in the longitudinal direction, the wall portion protrudes above the ground such as the high top end as well as underwater. It can also be applied when forming a continuous wall in such a region. As a result, the first pile 1A and the second pile 2A of the solidifying material are protected by the first steel pipe 1 and the second steel pipe 2 and brought into contact with the continuous wall surface where earth pressure is applied, for example, on the wall above the ground, and the continuous wall is formed. Can be linked to a part of. The first steel pipe 1 and the second steel pipe 2 on the ground following the first pile 1A and the second pile 2A stand up with a slight gap. In the present specification, such a continuous wall extending above the ground is also included in the continuous underground wall R.
Further, as another modification of the continuous underground wall R according to the present embodiment, there is a soil wall on one side of the arrangement of the first steel pipe 1 and the second steel pipe 2 left above the first pile 1A and the second pile 2A. Or the solidifying material may be in contact and the other side may be in contact with the space. Alternatively, when the space is in contact with both sides of the first steel pipe 1 and the second steel pipe 2, or when the earthen wall or the solidifying material is in contact with one side of the first steel pipe 1 and the second steel pipe 2, the other side is in contact with the earthen wall or the solidifying material. Various cases such as when the water surface is in contact can also be included.

1 第一鋼管
1A、1Aa、1Ab、1Ac 第一杭
2 第二鋼管
2A、2Aa、2Ab 第二杭
3、16 爪部
6 圧入機
21 プレストレスユニット
23 PC鋼線
24 シース管
R 連続地中壁
1 1st steel pipe 1A, 1Aa, 1Ab, 1Ac 1st pile 2 2nd steel pipe 2A, 2Aa, 2Ab 2nd pile 3, 16 Claws 6 Press-fitting machine 21 Prestress unit 23 PC steel wire 24 Sheath pipe R Continuous underground wall

Claims (16)

第一鋼管と第二鋼管を施工方向に沿って連続して交互に打設する鋼管打設工程と、
前記第一鋼管及び第二鋼管を打設しながらまたは打設した後に前記第一鋼管及び第二鋼管内を掘削する掘削工程と、
一本置きに配置された前記第一鋼管内に固化材料を充填しながらまたは充填した後に前記第一鋼管を引き抜く第一固化材料充填工程と、
前記第一鋼管の間に配設された前記第二鋼管内に固化材料を充填しながらまたは充填した後に前記第二鋼管の外側に突出する爪部によって前記第一固化材料充填工程で充填した固化材料を乱しつつ前記第二鋼管を引き抜く第二固化材料充填工程と、
を備えることを特徴とする連続地中壁の施工方法。
A steel pipe placing process in which the first steel pipe and the second steel pipe are continuously and alternately placed along the construction direction,
An excavation step of excavating the inside of the first steel pipe and the second steel pipe while or after driving the first steel pipe and the second steel pipe.
The first solidifying material filling step of pulling out the first steel pipe while filling or filling the first steel pipe arranged every other pipe with the solidifying material.
Solidification filled in the first solidifying material filling step by a claw portion protruding to the outside of the second steel pipe while filling or filling the second steel pipe arranged between the first steel pipes. The second solidifying material filling process of pulling out the second steel pipe while disturbing the material,
A method of constructing a continuous underground wall, which is characterized by being provided with.
施工方向に沿って間隔を開けて第一鋼管を打設する第一鋼管打設工程と、
前記第一鋼管を打設しながらまたは打設した後に前記第一鋼管内を掘削する第一掘削工程と、
前記第一鋼管内に固化材料を充填しながらまたは充填した後に前記第一鋼管を引き抜く第一固化材料充填工程と、
前記第一鋼管の間に第二鋼管を打設する第二鋼管打設工程と、
前記第二鋼管を打設しながらまたは打設した後に前記第二鋼管内を掘削する第二掘削工程と、
前記第二鋼管内に固化材料を充填しながらまたは充填した後に前記第二鋼管の外側に突出する爪部によって前記第一固化材料充填工程で充填した固化材料を乱しつつ前記第二鋼管を引き抜く第二固化材料充填工程と、
を備えることを特徴とする連続地中壁の施工方法。
The first steel pipe placing process in which the first steel pipe is placed at intervals along the construction direction,
The first excavation step of excavating the inside of the first steel pipe while or after driving the first steel pipe.
The first solidifying material filling step of pulling out the first steel pipe while filling or after filling the first steel pipe with the solidifying material.
The second steel pipe driving process in which the second steel pipe is placed between the first steel pipes,
A second excavation step of excavating the inside of the second steel pipe while or after driving the second steel pipe.
The second steel pipe is pulled out while filling the solidifying material in the second steel pipe or after filling the second steel pipe while disturbing the solidifying material filled in the first solidifying material filling step by the claws protruding to the outside of the second steel pipe. The second solidifying material filling process and
A method of constructing a continuous underground wall, which is characterized by being provided with.
施工方向に沿って間隔を開けて第二鋼管を打設する第二鋼管打設工程と、
前記第二鋼管を打設しながらまたは打設した後に前記第二鋼管内を掘削する第二掘削工程と、
前記第二鋼管の間に第一鋼管を打設する第一鋼管打設工程と、
前記第一鋼管を打設しながらまたは打設した後に前記第一鋼管内を掘削する第一掘削工程と、
前記第一鋼管内に固化材料を充填しながらまたは充填した後に前記第一鋼管を引き抜く第一固化材料充填工程と、
前記第二鋼管内に固化材料を充填しながらまたは充填した後に前記第二鋼管の外側に突出する爪部によって前記第一固化材料充填工程で充填した固化材料を乱しつつ前記第二鋼管を引き抜く第二固化材料充填工程と、
を備えることを特徴とする連続地中壁の施工方法。
The second steel pipe placing process, in which the second steel pipe is placed at intervals along the construction direction,
A second excavation step of excavating the inside of the second steel pipe while or after driving the second steel pipe.
The first steel pipe driving process in which the first steel pipe is placed between the second steel pipes,
The first excavation step of excavating the inside of the first steel pipe while or after driving the first steel pipe.
The first solidifying material filling step of pulling out the first steel pipe while filling or after filling the first steel pipe with the solidifying material.
The second steel pipe is pulled out while filling the solidifying material in the second steel pipe or after filling the second steel pipe while disturbing the solidifying material filled in the first solidifying material filling step by the claws protruding to the outside of the second steel pipe. The second solidifying material filling process and
A method of constructing a continuous underground wall, which is characterized by being provided with.
前記第二鋼管の打設時に前記爪部は前記第一鋼管に干渉しない位置に設けた請求項1または2に記載された連続地中壁の施工方法。 The method for constructing a continuous underground wall according to claim 1 or 2, wherein the claw portion is provided at a position where the claw portion does not interfere with the first steel pipe when the second steel pipe is placed. 前記第二鋼管の爪部は前記第一鋼管及び/または第二鋼管の一方の外接線または両側の対向する2つの外接線と隣り合う前記第一鋼管との間の隙間に設けた請求項1から4のいずれか1項に記載された連続地中壁の施工方法。 The claw portion of the second steel pipe is provided in a gap between one circumscribed line of the first steel pipe and / or the second steel pipe or two opposing circumscribed lines on both sides and the adjacent first steel pipe. The method for constructing a continuous underground wall according to any one of 4 to 4. 前記爪部を設けた前記第二鋼管は圧入、回転圧入または揺動圧入で打設するようにした請求項1から5のいずれか1項に記載された連続地中壁の施工方法。 The method for constructing a continuous underground wall according to any one of claims 1 to 5, wherein the second steel pipe provided with the claw portion is driven by press-fitting, rotary press-fitting, or rocking press-fitting. 前記第二鋼管を引き抜く際、前記第一固化材料充填工程で充填した固化材料は凝結始発時間から凝結終結時間までの状態とされている請求項1から6のいずれか1項に記載された連続地中壁の施工方法。 The continuous according to any one of claims 1 to 6, wherein when the second steel pipe is pulled out, the solidified material filled in the first solidifying material filling step is in a state from the condensation start time to the condensation end time. Construction method of underground wall. 前記第二鋼管は前記爪部が外側に拡縮可能である請求項1から7のいずれか1項に記載された連続地中壁の施工方法。 The method for constructing a continuous underground wall according to any one of claims 1 to 7, wherein the second steel pipe has a claw portion that can be expanded and contracted outward. 前記第二鋼管を引き抜く際に前記爪部によって前記第一固化材料充填工程で充填した固化材料を乱しつつ新たな固化材料を補充するようにした請求項1から8のいずれか1項に記載された連続地中壁の施工方法。 The invention according to any one of claims 1 to 8, wherein when the second steel pipe is pulled out, a new solidifying material is replenished while disturbing the solidifying material filled in the first solidifying material filling step by the claw portion. Construction method of the continuous underground wall. 前記第一鋼管及び/または前記第二鋼管に圧入機を設置し、前記圧入機により前記第一鋼管及び第二鋼管を打設すると共に引き抜くようにした請求項1から9のいずれか1項に記載された連続地中壁の施工方法。 According to any one of claims 1 to 9, a press-fitting machine is installed in the first steel pipe and / or the second steel pipe, and the first steel pipe and the second steel pipe are driven and pulled out by the press-fitting machine. The described method of constructing a continuous underground wall. 掘削した前記第一鋼管及び/または第二鋼管内にPC鋼線を設置しておき、
前記第一鋼管に対応する第一固化材料及び/または前記第二鋼管に対応する第二固化材料の定着後に前記PC鋼線を緊張させてプレストレスを導入するようにした請求項1から10のいずれか1項に記載された連続地中壁の施工方法。
A PC steel wire is installed in the excavated first steel pipe and / or second steel pipe.
Claims 1 to 10 in which the PC steel wire is tensioned to introduce prestress after fixing the first solidifying material corresponding to the first steel pipe and / or the second solidifying material corresponding to the second steel pipe. The method for constructing a continuous underground wall according to any one of the items.
前記第一鋼管及び第二鋼管は地盤の領域では引き抜かれて第一固化材料及び第二固化材料が前記爪部で乱されていると共に、水中では前記第一鋼管及び第二鋼管を引き抜くことなく保持されている請求項1から11のいずれか1項に記載された連続地中壁の施工方法。 The first steel pipe and the second steel pipe are pulled out in the area of the ground, and the first solidifying material and the second solidifying material are disturbed at the claw portion, and the first steel pipe and the second steel pipe are not pulled out in water. The method for constructing a continuous underground wall according to any one of claims 1 to 11. 前記第一鋼管及び第二鋼管は地盤の領域では引き抜かれて第一固化材料及び第二固化材料が前記爪部で乱されていると共に、地上では前記第一鋼管及び第二鋼管を引き抜くことなく保持されている請求項1から11のいずれか1項に記載された連続地中壁の施工方法。 The first steel pipe and the second steel pipe are pulled out in the area of the ground, and the first solidifying material and the second solidifying material are disturbed at the claw portion, and the first steel pipe and the second steel pipe are not pulled out on the ground. The method for constructing a continuous underground wall according to any one of claims 1 to 11. 鋼管と、
前記鋼管の長手方向の適宜位置に径方向外側に突出させた爪部とを有し、
地中に打設した前記鋼管を引き上げる際に、前記爪部は前記鋼管とともに引き上げられ、前記鋼管に隣接する固化材料からなる第一杭を、前記爪部で乱すことで、前記鋼管を通して地中に埋設された固化材料からなる第二杭と一体化させて連続地中壁を形成するようにしたことを特徴とする鋼管杭。
With steel pipe,
It has a claw portion protruding outward in the radial direction at an appropriate position in the longitudinal direction of the steel pipe.
When the steel pipe placed in the ground is pulled up, the claw portion is pulled up together with the steel pipe, and the first pile made of a solidifying material adjacent to the steel pipe is disturbed by the claw portion, thereby passing through the steel pipe to the ground. A steel pipe pile characterized by being integrated with a second pile made of solidified material buried in the pile to form a continuous underground wall.
一対の前記爪部を有し、It has a pair of the claws and
前記一対の爪部は、前記鋼管の外周面の対向する位置から径方向外側に突出している請求項14に記載の鋼管杭。The steel pipe pile according to claim 14, wherein the pair of claws protrudes radially outward from a position facing the outer peripheral surface of the steel pipe.
前記爪部は外側に拡縮可能である請求項14に記載の鋼管杭。The steel pipe pile according to claim 14, wherein the claw portion can be expanded and contracted outward.
JP2017141225A 2017-07-20 2017-07-20 Construction method of continuous underground wall and steel pipe pile Active JP6987559B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2017141225A JP6987559B2 (en) 2017-07-20 2017-07-20 Construction method of continuous underground wall and steel pipe pile
PCT/JP2018/027786 WO2019017498A1 (en) 2017-07-20 2018-07-18 Method for constructing continuous underground wall and steel pipe pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017141225A JP6987559B2 (en) 2017-07-20 2017-07-20 Construction method of continuous underground wall and steel pipe pile

Publications (2)

Publication Number Publication Date
JP2019019633A JP2019019633A (en) 2019-02-07
JP6987559B2 true JP6987559B2 (en) 2022-01-05

Family

ID=63312432

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017141225A Active JP6987559B2 (en) 2017-07-20 2017-07-20 Construction method of continuous underground wall and steel pipe pile

Country Status (2)

Country Link
JP (1) JP6987559B2 (en)
WO (1) WO2019017498A1 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022200692A1 (en) * 2021-03-25 2022-09-29 Pirkan Laatupalvelu Oy Method for forming a wall structure in the ground by drilling and wall structure formed by drilling
CN111236262A (en) * 2020-03-16 2020-06-05 中铁建设集团有限公司 CSM + TRD underground continuous wall comprehensive construction method
CN112281873A (en) * 2020-10-19 2021-01-29 中铁六局集团有限公司 Construction method of anchoring pile
CN112459045A (en) * 2020-12-01 2021-03-09 南京深地智能建造技术研究院有限公司 Construction process of rotary digging hole-forming construction method pile

Family Cites Families (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS601451B2 (en) * 1979-06-04 1985-01-14 株式会社竹中工務店 Water stop mountain stop wall construction method using Benoto pile excavator
DE3428297C3 (en) * 1984-08-01 1994-02-24 Zueblin Ag Method of connecting membranes serving as additional flow and / or diffusion barrier and connecting tube for use in this method
JPH0733657B2 (en) * 1992-06-08 1995-04-12 株式会社武東工務店 Column-type underground continuous wall construction method
JPH06228947A (en) * 1993-02-01 1994-08-16 Taisei Corp Construction of landslide protection wall in ground filled up with wastes
US5758993A (en) * 1996-06-11 1998-06-02 Slurry Systems, Inc. Method and apparatus for forming successive overlapping voids in the ground along a predetermined course of travel and for producing a subterranean wall therein
JPH1037180A (en) * 1996-07-19 1998-02-10 Taisei Corp Construction method of continuous underground wall
JPH09119131A (en) * 1996-08-02 1997-05-06 Kengi Kaihatsu Kk Construction method of column row type underground continuous wall and guide plate structure of multishaft auger machine used therefor
JP3909510B2 (en) * 1999-04-12 2007-04-25 株式会社テノックス Synthetic pile construction method
JP2001090060A (en) 1999-09-17 2001-04-03 Shoowa Kensho:Kk Driving method for pile and constructing method for cut- off wall using the method
NL1021310C2 (en) * 2002-08-20 2004-02-24 Kandt Special Crane Equipment Sheet piling jack for constructing sheet pile walls, has pile clamping devices independently movable in jack length and transverse directions
JP2006077388A (en) * 2004-08-12 2006-03-23 Norihiro Watanabe Pile burying method
KR101126131B1 (en) * 2010-04-20 2012-03-29 최성희 Structure for reinforcing head of a steel pipe pile for a construction
JP5749070B2 (en) * 2011-05-11 2015-07-15 株式会社グラテクセンターシモダ Method for constructing continuous underground impermeable wall and casing provided with separable spiral stirring member
JP5981792B2 (en) * 2012-07-20 2016-08-31 株式会社技研製作所 Construction method of press-fit continuous wall
JP5762511B2 (en) * 2013-11-11 2015-08-12 藤井 俊彦 Ground improvement wall construction method
JP6218762B2 (en) * 2015-01-23 2017-10-25 株式会社フジタ Casing segment joint member used in the micropile method

Also Published As

Publication number Publication date
WO2019017498A1 (en) 2019-01-24
JP2019019633A (en) 2019-02-07

Similar Documents

Publication Publication Date Title
JP6987559B2 (en) Construction method of continuous underground wall and steel pipe pile
JP6762800B2 (en) Reinforcement method and structure of existing pile foundation
JP5274145B2 (en) Cast-in-place pile and its construction method
JP4693423B2 (en) Pile head reinforcement method
KR101045625B1 (en) Construction method of retaining wall using cast-in-place pile
JP2011179220A (en) Method of stabilizing slope and landslide control steel pipe pile
JP2008014000A (en) Construction method of cast-in-place concrete pile
JP2007009505A (en) Foundation reinforcing method
JP6460712B2 (en) Construction method of underground continuous wall
JP4811176B2 (en) Construction method of ready-made piles
JP5480744B2 (en) Foundation for structure and its construction method
KR20190109890A (en) Composite phc pile for soil retaining wall
KR20210009502A (en) Cast-in-place pile using Pressurized grouting and construction method
JP6006004B2 (en) Pile head space formation auxiliary tool, hollow ready-made pile provided with the same, pile head processing method using the hollow ready-made pile, and pile head space forming method
JP2005282063A (en) Composite field preparation pile, its construction method and device for preparing composite field preparation pile
JP2019173278A (en) Cutoff wall construction method
JP2004232436A (en) Pier foundation reinforcing method and pier foundation reinforcing structure
JP2007162323A (en) Wall body forming method and wall body
JP4341029B2 (en) Pile foundation method
JP2007297865A (en) Steel pipe pile structure and construction method therefor
KR20130002797A (en) Reinforced concrete pile construction method for which steel pipe casing structure for steel pipe casing recovery this were used
JP2007308951A (en) Method of constructing outer peripheral column by inverted construction method
KR101047257B1 (en) Construction method of earth wall using composite sheet pile
JP3919852B2 (en) Method for construction of cast-in-place pile
JP3881961B2 (en) Pile embedding method and excavator used for the method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200618

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210629

A601 Written request for extension of time

Free format text: JAPANESE INTERMEDIATE CODE: A601

Effective date: 20210826

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20211027

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20211116

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20211201

R150 Certificate of patent or registration of utility model

Ref document number: 6987559

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150