JPH1037180A - Construction method of continuous underground wall - Google Patents

Construction method of continuous underground wall

Info

Publication number
JPH1037180A
JPH1037180A JP20918996A JP20918996A JPH1037180A JP H1037180 A JPH1037180 A JP H1037180A JP 20918996 A JP20918996 A JP 20918996A JP 20918996 A JP20918996 A JP 20918996A JP H1037180 A JPH1037180 A JP H1037180A
Authority
JP
Japan
Prior art keywords
underground wall
casing
continuous
drilling machine
piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP20918996A
Other languages
Japanese (ja)
Inventor
Takashi Nishimoto
孝史 西本
Yasuhiro Arai
康博 荒井
Kiyoshi Onozawa
潔 小野沢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP20918996A priority Critical patent/JPH1037180A/en
Publication of JPH1037180A publication Critical patent/JPH1037180A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve the efficiency of the construction work by lapping following piles between preceding piles constructed at an interval for construction and carrying out a hole drilling process at the time by removing an underground obstacle by using a hole drilling machine having a rock drilling function. SOLUTION: A casing 2 is mounted on a hole drilling machine 1 externally to drill holes over the whole length in the horizontal direction of a continuous underground wall across a predetermined interval. At this time, the hole drilling machine 1 having a rock drilling function is used to crush and remove an underground obstacle such as rock. Next, the hole drilling machine 1 is pulled up, a steel pipe 3 is built in a remaining casing, and then the casing 2 is pulled out while filling solidifying material 4 such as cement milk in holes digged in the inside and outside of the steel pipe 3 to construct a group of preceding piles. Then, a following pile is constructed by lapping with adjacent preceding piles on both sides between the group of preceding piles in the same process to construct the underground wall like a row of continuous columns. Moreover, an underground wall like a row of many step type continuous columns is constructed as required. Consequently, it is possible to remove an underground obstacle and construct the continuous underground wall simultaneously.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は連続地中壁の構築方
法に関するものである。
TECHNICAL FIELD The present invention relates to a method for constructing a continuous underground wall.

【0002】[0002]

【発明が解決しようとする課題】従来の連続地中壁の構
築方法としては、SMW工法と呼ばれる工法等が存在す
るが、この工法は、地中の障害物(コンクリ−ト塊や石
塊等)への適応性が乏しい。そこで、地中障害物の除去
と連続地中壁の構築を同時に行える方法が希求されてい
る。
As a conventional method of constructing a continuous underground wall, there is a construction method called an SMW construction method. However, this construction method employs an underground obstacle (such as a concrete block or a stone block). Poor adaptability to). Therefore, there is a need for a method that can simultaneously remove an underground obstacle and construct a continuous underground wall.

【0003】[0003]

【発明の目的】本発明は、上記のような問題点を解決す
るためになされたもので、地中障害物の除去と連続地中
壁の構築を同時に行うことができる連続地中壁の構築方
法を提供することを目的とする。
SUMMARY OF THE INVENTION An object of the present invention is to solve the above-mentioned problems and to construct a continuous underground wall capable of simultaneously removing an underground obstacle and constructing a continuous underground wall. The aim is to provide a method.

【0004】[0004]

【課題を解決するための手段】上記課題を解決するため
の手段として、本発明は、ケ−シングを取り付けた削孔
機により所定の間隔をおいて削孔を行う工程と、ケ−シ
ングを残して削孔機を引き上げた後にケ−シング内に鋼
管を建て込む工程と、削孔内に固化材を充填しながらケ
−シングを引き抜く工程と、固化材の固化工程とにより
先行杭を構築した後、先行杭の間に、両隣の先行杭とラ
ップさせて上記工程を繰り返して後行杭を構築すること
によって、連続柱列状の地中壁を構築することを特徴と
した、連続地中壁の構築方法を提供する。
As a means for solving the above-mentioned problems, the present invention provides a step of drilling holes at predetermined intervals by a drilling machine equipped with a casing, and the steps of: Construction of the leading pile by the process of erecting the steel pipe in the casing after raising the drilling machine while leaving it, the process of extracting the casing while filling the drilling hole with the solidified material, and the process of solidifying the solidified material Then, between the preceding piles, by wrapping with the preceding piles on both sides and repeating the above process to construct the succeeding piles, a continuous pillar-column-shaped underground wall was constructed, Provide a method of constructing the inner wall.

【0005】また、前記削孔機には、油圧ハンマ−ドリ
ル等の削岩機能を有するものを用いて、地中障害物の除
去と連続地中壁の構築とを同時に行えるよう構成したこ
とを特徴とする、連続地中壁の構築方法を提供する。以
下、図を参照しながら、本発明の一実施の形態について
説明する。
[0005] Further, the drilling machine having a rock drilling function such as a hydraulic hammer drill is used to remove underground obstacles and construct a continuous underground wall at the same time. A method for constructing a continuous underground wall is provided. Hereinafter, an embodiment of the present invention will be described with reference to the drawings.

【0006】[0006]

【発明の実施の形態】BEST MODE FOR CARRYING OUT THE INVENTION

<イ>削孔 スクリュ−オ−ガ等の削孔機1にケ−シング2を外装し
て削孔を行う。ケ−シング2は削孔とほぼ等しい長さの
ものを使用する。削孔は、所定の間隔をおいて連続地中
壁の水平方向の全長に亘って行う。このようにケ−シン
グ2を外装して削孔を行うことにより、孔壁の崩壊を防
止できると共に、削孔作業を迅速かつ簡便に行うことが
できる。
<A> Drilling The drilling is performed by mounting the casing 2 on a drilling machine 1 such as a screw auger. The casing 2 has a length substantially equal to the length of the hole. Drilling is performed at predetermined intervals over the entire horizontal length of the continuous underground wall. By drilling the exterior of the casing 2 in this way, the collapse of the hole wall can be prevented, and the drilling operation can be performed quickly and easily.

【0007】削孔機1に、低騒音、低振動の油圧ハンマ
−ドリル等の削岩機能を有するものを用いれば、地中障
害物(コンクリ−ト塊や石塊等)を破砕除去しながら連
続地中壁の構築を行うことができる。
If a drilling machine 1 having a rock drilling function such as a low-noise, low-vibration hydraulic hammer drill is used as the drilling machine 1, an underground obstacle (such as a concrete block or a stone block) is crushed and removed. A continuous underground wall can be constructed.

【0008】<ロ>鋼管の建て込み ケ−シング2を残して削孔機1を引き上げた後に、ケ−
シング2内に、小孔径かつ極厚の鋼管3を建て込む。鋼
管3は削孔とほぼ等しい長さを有し、かつケ−シング2
の内径より小さい外径を有するものを使用する。
<B> Installation of steel pipe After drilling the drilling machine 1 while leaving the casing 2, the casing
A steel pipe 3 having a small hole diameter and an extremely thick diameter is built in the thing 2. The steel pipe 3 has a length substantially equal to the drilled hole and the casing 2
Use an outer diameter smaller than the inner diameter.

【0009】<ハ>固化材の充填 各ケ−シング2内に鋼管3を建て込んだ後に、鋼管3の
内外の削孔内全体にセメントミルク等の固化材4を充填
しながらケ−シング2を引き抜く。他の削孔内にも同様
に固化材4を充填し、固化させて、図2に示すような先
行杭5群を構築する。
<C> Filling of the solidified material After the steel pipes 3 are built in the respective casings 2, the solidified material 4 such as cement milk is filled into the entire inside and outside of the drilled holes of the steel pipes 3. Pull out. The solidification material 4 is similarly filled in other drilled holes and solidified to construct a group of preceding piles 5 as shown in FIG.

【0010】<ニ>後行杭の構築 先行杭5群を構築した後、図2に示すように、先行杭5
群の間に、両隣の先行杭5とラップさせて後行杭6を構
築する。後行杭6の構築は、上記の先行杭5の構築工程
と同様に行う。そして、図2に示すように、先行杭5と
後行杭6が連続して構築されることによって、連続柱列
状の地中壁を構築することができる。また、図3に示す
ような多段式連続柱列状の地中壁を構築することもでき
る。
<D> Construction of trailing stake After the group of leading stakes 5 has been constructed, as shown in FIG.
Between the groups, a trailing pile 6 is constructed by wrapping the leading pile 5 on both sides. The construction of the trailing pile 6 is performed in the same manner as the construction step of the preceding pile 5 described above. Then, as shown in FIG. 2, by continuously constructing the leading pile 5 and the trailing pile 6, it is possible to construct a continuous pillar-shaped underground wall. Also, a multi-stage continuous column-shaped underground wall as shown in FIG. 3 can be constructed.

【0011】[0011]

【発明の効果】本発明は以上説明したように、削孔機に
油圧ハンマ−ドリル等の削岩機能を有するものを用いる
ことによって、地中障害物の除去と連続地中壁の構築と
を同時に行うことができるため、施工能率の向上を図る
ことができる。
As described above, according to the present invention, by using a drilling machine having a rock drilling function such as a hydraulic hammer drill, the removal of underground obstacles and the construction of a continuous underground wall can be achieved. Since they can be performed at the same time, the construction efficiency can be improved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明の施工手順の説明図FIG. 1 is an explanatory view of a construction procedure of the present invention.

【図2】 本発明の連続地中壁の完成状態の平面図FIG. 2 is a plan view showing a completed underground wall according to the present invention;

【図3】 本発明の連続地中壁の完成状態の平面図FIG. 3 is a plan view showing a completed underground wall according to the present invention;

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 ケ−シングを取り付けた削孔機により所
定の間隔をおいて削孔を行う工程と、 ケ−シングを残して削孔機を引き上げた後にケ−シング
内に鋼管を建て込む工程と、 削孔内に固化材を充填しながらケ−シングを引き抜く工
程と、 固化材の固化工程とにより先行杭を構築した後、 先行杭の間に、両隣の先行杭とラップさせて上記工程を
繰り返して後行杭を構築することによって、 連続柱列状の地中壁を構築することを特徴とした、 連続地中壁の構築方法。
1. A step of drilling holes at predetermined intervals by a drilling machine with a casing, and after elevating the drilling machine while leaving the casing, a steel pipe is built in the casing. After constructing the leading pile by the process, the step of extracting the casing while filling the drilling with the solidified material, and the step of solidifying the solidified material, wrap the preceding piles on both sides between the preceding piles and A method of constructing a continuous underground wall, comprising constructing a continuous pillar-shaped underground wall by repeating a process to construct a trailing pile.
【請求項2】 請求項1に記載の連続地中壁の構築方法
において、前記削孔機には、油圧ハンマ−ドリル等の削
岩機能を有するものを用いて、地中障害物の除去と連続
地中壁の構築とを同時に行えるよう構成したことを特徴
とする、連続地中壁の構築方法。
2. The method for constructing a continuous underground wall according to claim 1, wherein said drilling machine has a rock drilling function such as a hydraulic hammer drill to remove underground obstacles. A method for constructing a continuous underground wall, wherein the method is configured to be able to simultaneously construct a continuous underground wall.
JP20918996A 1996-07-19 1996-07-19 Construction method of continuous underground wall Pending JPH1037180A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20918996A JPH1037180A (en) 1996-07-19 1996-07-19 Construction method of continuous underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20918996A JPH1037180A (en) 1996-07-19 1996-07-19 Construction method of continuous underground wall

Publications (1)

Publication Number Publication Date
JPH1037180A true JPH1037180A (en) 1998-02-10

Family

ID=16568831

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20918996A Pending JPH1037180A (en) 1996-07-19 1996-07-19 Construction method of continuous underground wall

Country Status (1)

Country Link
JP (1) JPH1037180A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7776415B2 (en) 2003-10-03 2010-08-17 Kureha Corporation Stretch-formed multilayer container and production process for the same
JP2019019633A (en) * 2017-07-20 2019-02-07 株式会社技研製作所 Construction method of continuous underground wall and steel pipe pile
KR20190062809A (en) * 2017-11-29 2019-06-07 한요섭 Cantilever Earth Retaining Wal1 Construction Method Using PHC Pile And Key Block

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7776415B2 (en) 2003-10-03 2010-08-17 Kureha Corporation Stretch-formed multilayer container and production process for the same
JP2019019633A (en) * 2017-07-20 2019-02-07 株式会社技研製作所 Construction method of continuous underground wall and steel pipe pile
KR20190062809A (en) * 2017-11-29 2019-06-07 한요섭 Cantilever Earth Retaining Wal1 Construction Method Using PHC Pile And Key Block

Similar Documents

Publication Publication Date Title
KR102521610B1 (en) Multi casing perforation device
JPH1037180A (en) Construction method of continuous underground wall
JPH07331998A (en) Constructing method of rock cavern
JP2004060266A (en) Non-open-cut construction method for underground structure
JPH05287745A (en) Mounting method for wale in column aligning method
JP2001182477A (en) Device of partition iron plate
JPS6332930B2 (en)
JP2604622B2 (en) Tunnel construction method
JPS61186623A (en) Method of building foundation of building
KR20100117826A (en) Construction method of earth retaining wall
JP2603414B2 (en) True pipe large diameter cast-in-place pile method
JP6019689B2 (en) Tunnel widening method
JP2001090060A (en) Driving method for pile and constructing method for cut- off wall using the method
JPH0230890A (en) Method and apparatus for replacing of underground buried pipe
JP3424117B2 (en) Construction method of continuous underground wall
JP2569991B2 (en) Concrete removal method for reinforced concrete joints
JPH0617590A (en) Excavating method for tunnel
JP2668109B2 (en) Construction method for underground structures
JP2003293681A (en) Tunnel construction method
JPH0360972B2 (en)
JPH0568599B2 (en)
JPH031479B2 (en)
JPH0328463A (en) Method for breaking and removing wall of concrete building
JP2009057804A (en) Tunnel boring method
JPH0317314A (en) Execution of underground continuous wall

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050909

A131 Notification of reasons for refusal

Effective date: 20050913

Free format text: JAPANESE INTERMEDIATE CODE: A131

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20060207