JP6624443B2 - Freezing method - Google Patents

Freezing method Download PDF

Info

Publication number
JP6624443B2
JP6624443B2 JP2016011548A JP2016011548A JP6624443B2 JP 6624443 B2 JP6624443 B2 JP 6624443B2 JP 2016011548 A JP2016011548 A JP 2016011548A JP 2016011548 A JP2016011548 A JP 2016011548A JP 6624443 B2 JP6624443 B2 JP 6624443B2
Authority
JP
Japan
Prior art keywords
freezing
frozen soil
ground
frozen
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2016011548A
Other languages
Japanese (ja)
Other versions
JP2017133163A (en
Inventor
小林 伸司
伸司 小林
武彦 中谷
武彦 中谷
幸一 浜口
幸一 浜口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2016011548A priority Critical patent/JP6624443B2/en
Publication of JP2017133163A publication Critical patent/JP2017133163A/en
Application granted granted Critical
Publication of JP6624443B2 publication Critical patent/JP6624443B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Description

本発明は、地盤を凍結させ、地盤の止水性能及び強度性能を向上させる凍結工法に関する。   The present invention relates to a freezing method for freezing the ground and improving the water stopping performance and the strength performance of the ground.

従来、地盤の安定化、防水層の形成などを目的とした防護工として凍結工法が用いられている(例えば、特許文献1参照)。   Conventionally, a freezing method has been used as a protective method for the purpose of stabilizing the ground, forming a waterproof layer, and the like (for example, see Patent Document 1).

例えば、トンネル掘進機で地盤を掘削してトンネルを構築する際、特に、道路トンネルの分岐・合流部や鉄道トンネルの渡り線部などの大断面トンネルを構築する際の発進・到達時やセグメント切り開き時(シールドトンネルの地中拡幅時)などに、凍結工法が用いられている。  For example, when constructing a tunnel by excavating the ground with a tunnel machine, especially when constructing a large cross-section tunnel such as a branch / merge section of a road tunnel or a crossover section of a railway tunnel, or opening a segment At times (when the shield tunnel is widened underground), the freezing method is used.

ここで、大断面トンネルを構築する際などの大規模な凍土造成を行う場合や凍結対象地盤に粘性土が含まれている場合には、地盤の凍結による膨張圧が大きくなり、組み立てたセグメント(周囲の構造物など)に凍結膨張圧による過大な荷重が作用してセグメントボルトが破断したり、セグメントが破損するおそれがある。   Here, when a large-scale frozen soil is created, such as when constructing a large section tunnel, or when the ground to be frozen contains viscous soil, the expansion pressure due to the freezing of the ground increases, and the assembled segment ( Excessive load due to the freezing expansion pressure acts on the surrounding structures, etc.), so that the segment bolt may be broken or the segment may be damaged.

これに対し、凍結膨張圧対策手法としては、1)凍結管列の外側への温水管を設置し凍結領域を制御する方法、2)凍土周囲の地山を抜き取って凍結膨張圧を低減させる方法、3)凍結膨張圧に対応したセグメントの補強を講じる方法、4)凍結運転制御(間引き運転等)による凍土の成長抑制方法などが提案、実用化されている。   On the other hand, as a measure against the freezing expansion pressure, 1) a method of installing a hot water pipe outside the row of freezing pipes to control the freezing area, and 2) a method of extracting the ground around the frozen soil to reduce the freezing expansion pressure. 3) A method of reinforcing the segment corresponding to the freezing expansion pressure, 4) A method of suppressing the growth of frozen soil by freezing operation control (thinning operation or the like) has been proposed and put to practical use.

特開2005−264717号公報JP 2005-264717 A

しかしながら、1)凍結管列の外側への温水管を設置し凍結領域を制御する方法、2)凍土周囲の地山を抜き取って凍結膨張圧を低減させる方法、3)凍結膨張圧に対応したセグメントの補強を講じる方法においては、対策コストや工期の大幅な増大を招く。また、4)凍結運転制御による凍土の成長抑制方法においては抑制効果が小さいという不都合がある。   However, 1) a method of controlling the freezing area by installing a hot water pipe outside the row of freezing pipes, 2) a method of extracting the ground around the frozen soil to reduce the freezing expansion pressure, and 3) a segment corresponding to the freezing expansion pressure Reinforcement of the method leads to a significant increase in the cost of measures and the construction period. In addition, 4) In the method for suppressing the growth of frozen soil by freezing operation control, there is an inconvenience that the suppression effect is small.

本発明は、上記事情に鑑み、確実且つ簡便に凍結膨張圧を制御でき、工期短縮、コストダウンを可能にする凍結工法を提供することを目的とする。   The present invention has been made in view of the above circumstances, and has as its object to provide a freezing method capable of reliably and easily controlling the freezing and inflation pressure, shortening the construction period, and reducing costs.

上記の目的を達するために、この発明は以下の手段を提供している。   In order to achieve the above object, the present invention provides the following means.

本発明の凍結工法は、地盤を凍結させ、地盤の止水性能及び強度性能を向上させる凍結工法において、凍結運転開始から所定領域の凍土が連続的に繋がって止水性能が確保された段階と、必要な凍土厚の凍土壁が造成されて強度性能が確保された段階との間の任意のタイミングで、前記凍土壁に対して内側の領域の一部の地盤を先行掘削することを特徴とする。   The freezing method of the present invention freezes the ground, and in the freezing method of improving the water stopping performance and strength performance of the ground, at the stage where the frozen water in a predetermined area is continuously connected from the start of the freezing operation and the water stopping performance is secured. At an arbitrary timing between the stage where the permafrost wall of the required permafrost thickness is created and the strength performance is ensured, a preliminary excavation of a part of the ground in an area inside with respect to the permafrost wall is characterized in that I do.

本発明の凍結工法においては、止水性能が確保される段階から強度性能が確保される段階までの間の任意のタイミングで、凍土壁の内側の領域の一部の地盤を先行掘削することによって、凍結膨張圧の一部を開放させることができ、凍結膨張圧の低減を図ることが可能になる。  In the freezing method of the present invention, at an arbitrary timing between the stage at which the water stopping performance is secured and the stage at which the strength performance is secured, by excavating part of the ground inside the area of the frozen soil wall in advance. In addition, a part of the freezing expansion pressure can be released, and the freezing expansion pressure can be reduced.

また、このように止水性能が確保される段階から強度性能が確保される段階までの間の任意のタイミングで凍結膨張圧の一部を開放させることにより、強度的に十分な凍土壁が形成された段階における凍結膨張圧(最終的に凍土が必要(最大)凍土厚に達した時点の凍結膨張圧)も低減させることが可能になる。   In addition, by releasing a part of the freezing and expanding pressure at an arbitrary timing between the stage where the water stopping performance is secured and the stage where the strength performance is secured, a sufficiently strong frozen soil wall is formed. It is also possible to reduce the freezing expansion pressure at the specified stage (the freezing expansion pressure when the frozen soil finally reaches the required (maximum) frozen soil thickness).

凍結工法を用いて構築するトンネルの施工方法の一例を示す図である。It is a figure showing an example of the construction method of the tunnel constructed using the freezing method. 凍結工法を用いて構築するトンネルの一例を示す図である。It is a figure showing an example of a tunnel constructed using a freezing method. 凍結工法を用いて構築する分岐・合流部のトンネルの一例を示す図である。It is a figure which shows an example of the tunnel of the branching / merging part constructed using the freezing method. 凍結工法を用いて構築するトンネルの施工方法の一例を示す図である。It is a figure showing an example of the construction method of the tunnel constructed using the freezing method. 凍結工法を用いた際の凍土の造成段階の説明に用いた図である。It is the figure used for description of the creation stage of the frozen soil at the time of using a freezing method. 本発明の一実施形態の凍結工法において、止水性能と確保した段階と強度性能を確保した段階の間の任意のタイミングで、凍土壁の内側の一部の地盤を掘削することを示す図である。In the freezing method of one embodiment of the present invention, at an arbitrary timing between the stage of securing the water stopping performance and the stage of securing the strength performance, it is a diagram showing that a part of the ground inside the frozen soil wall is excavated. is there.

以下、図1から図6を参照し、本発明の一実施形態に係る凍結工法について説明する。   Hereinafter, a freezing method according to an embodiment of the present invention will be described with reference to FIGS. 1 to 6.

ここで、本実施形態では、例えば、道路トンネルの分岐・合流部や鉄道トンネルの渡り線部などの大断面トンネルを構築する際の発進・到達時やセグメント切り開き時(シールドトンネルの地中拡幅時)などに対し凍結工法を用いるものとして説明を行う。
但し、本発明の凍結工法は、土木建築分野において、地盤を凍結させて凍土壁(凍結領域)等を形成するあらゆるケースに適用可能である。
Here, in the present embodiment, for example, at the time of starting and reaching when constructing a large-section tunnel such as a branching / merging portion of a road tunnel or a crossover portion of a railway tunnel, or at the time of segment opening (during underground widening of a shield tunnel, ) Etc. will be described as using the freezing method.
However, the freezing method of the present invention can be applied to any case where the ground is frozen to form a frozen soil wall (freezing region) in the field of civil engineering and construction.

はじめに、図1から図4に示すように、道路トンネルの分岐・合流部などの大断面トンネルを構築する際には、例えば、本線シールド1、ランプシールド2(2本の導坑)を横方向に間隔をあけて先行構築するとともに、本線シールド1を通じ、凍結工法で環状や門型の凍土壁5を形成して地盤の安定化を図りつつ地中発進基地3を構築し、この地中発進基地3から本線シールド1、ランプシールド2を囲繞するように小径のトンネル掘進機で複数の外殻シールド4を構築する。   First, as shown in FIGS. 1 to 4, when constructing a large-section tunnel such as a branch or a junction of a road tunnel, for example, the main shield 1 and the lamp shield 2 (two pits) are placed in a horizontal direction. At the same time, the underground starting base 3 is constructed while the stabilization of the ground is achieved by forming a ring-shaped or gate-shaped frozen soil wall 5 by the freezing method through the main line shield 1 while maintaining an interval. A plurality of outer shell shields 4 are constructed with a small diameter tunnel excavator so as to surround the main line shield 1 and the lamp shield 2 from the base 3.

さらに、凍結工法を用いて凍土壁5を形成しつつ隣り合う外殻シールド4を切り開いて連通させ、本線シールド1、ランプシールド2を囲繞する本設覆工6を構築する。そして、本線シールド1から本設覆工6で囲まれた地盤を掘削して連通させ、分岐・合流部となる大断面トンネルを構築する。   Further, the adjacent outer shell shields 4 are cut open to communicate with each other while the frozen soil wall 5 is formed by using the freezing method, and a permanent lining 6 surrounding the main line shield 1 and the lamp shield 2 is constructed. Then, the ground surrounded by the permanent lining 6 is excavated from the main line shield 1 to communicate with each other, and a large-section tunnel serving as a branching / merging portion is constructed.

また、凍結工法で凍土壁5を形成する際には、凍結管7と測温管を地盤内に設置し、凍結管7にブラインを循環供給するための配管設備、冷凍機設備を設置し、測温管に計装設備等を設置する。そして、凍結管5にブラインを循環させて凍土造成を開始する。このとき、測温管で地中温度をリアルタイムで計測し、凍土造成の進行状況や凍土の維持状況を捉え、施工管理を行う。   When the frozen soil wall 5 is formed by the freezing method, the freezing pipe 7 and the temperature measuring pipe are installed in the ground, and piping equipment and a refrigerator for circulating and supplying the brine to the freezing pipe 7 are installed. Install instrumentation equipment, etc. in the temperature measuring tube. Then, brine is circulated through the freezing tube 5 to start freezing soil formation. At this time, the underground temperature is measured in real time with a temperature measuring tube, and the progress of the formation of the frozen soil and the maintenance of the frozen soil are grasped, and construction management is performed.

一方、図5に示すように、凍結工法では、凍結管7にブラインを循環させるとともに凍結管7の周囲に凍土が造成されて膨張が生じる(凍土領域10)。ブライン流通方向上流側の凍土が先行して造成され(凍土領域11)、次第に下流側の凍土が造成され(凍土領域12)、凍土が繋がり、止水性能をもつ凍土壁が形成される。さらに、必要凍土厚まで凍土造成され、所望の強度性能をもつ凍土壁5が形成される。凍土の維持を図ることにより、さらに凍土が内側、外側に造成され(凍土領域13、凍土領域14)、凍土壁5が増厚してゆく。   On the other hand, as shown in FIG. 5, in the freezing method, brine is circulated through the freezing tube 7, and frozen soil is formed around the freezing tube 7 to expand (the frozen soil region 10). The frozen soil on the upstream side in the brine distribution direction is formed first (frozen soil area 11), and the frozen soil on the downstream side is gradually formed (frozen soil area 12), and the frozen soil is connected to form a frozen soil wall having water stopping performance. Further, the frozen soil is formed to a required frozen soil thickness, and the frozen soil wall 5 having a desired strength performance is formed. By maintaining the frozen soil, the frozen soil is further formed inside and outside (the frozen soil area 13 and the frozen soil area 14), and the thickness of the frozen soil wall 5 is increased.

なお、測温管による温度計測によって、例えば平均温度−5℃の領域が連続的に形成されれば止水性能を有する(止水性能を確保した)凍土領域11、12が形成されたことを検知することができる。また、例えば平均温度−10°の領域が連続的に形成されれば、強度性能を有する(所望の強度性能を確保した)凍土壁5が形成されたことを検知することができる。   In addition, the temperature measurement by the temperature measuring tube indicates that the frozen ground regions 11 and 12 having the water stopping performance (securing the water stopping performance) are formed if the region of, for example, the average temperature of −5 ° C. is continuously formed. Can be detected. Further, for example, if the region of the average temperature of −10 ° is continuously formed, it can be detected that the frozen soil wall 5 having the strength performance (securing the desired strength performance) is formed.

ここで、凍土の強度に期待し、耐力壁としての凍土壁5を施工する場合には、一般に、構造計算により決定した必要凍土厚まで凍土を造成した後にトンネル掘削を行う。また、凍結膨張圧は凍土の成長に応じて大きくなるため、トンネル掘削前には必要凍土厚に応じた凍結膨張圧が発生する。   Here, when the frozen soil wall 5 as a bearing wall is constructed in consideration of the strength of the frozen soil, tunnel excavation is generally performed after the frozen soil is formed to a required frozen soil thickness determined by structural calculation. Further, since the freezing expansion pressure increases in accordance with the growth of the frozen soil, the freezing expansion pressure according to the required frozen soil thickness is generated before tunnel excavation.

一方、凍土の遮水性(止水性)に期待し、遮水壁として凍土壁5を施工する場合には、連続性を保った凍土壁が形成されていればよく、その凍土厚は施工誤差を考慮しても耐力壁で必要となるものよりも小さい。   On the other hand, in the case where the frozen soil wall 5 is constructed as a water impervious wall in anticipation of the water shielding (water blocking) of the frozen soil, it is sufficient that the frozen soil wall maintaining the continuity is formed, and the thickness of the frozen soil may cause a construction error. Even if you consider it, it is smaller than what is needed for load-bearing walls.

本実施形態の凍結工法においては、この点に着目し、図凍土の成長過程を、運転開始から凍土が繋がって止水性能が確保されるまでの第一段階、凍土が繋がって必要な凍土厚が造成されて強度性能が確保されるまでの第二段階、凍結維持期間の第三段階に区分する。   Focusing on this point, the freezing method of the present embodiment focuses on this point, and illustrates the growth process of the frozen soil in the first stage from the start of operation to the connection of the frozen soil and the water stopping performance, the required frozen soil thickness by the connection of the frozen soil. Is divided into a second stage until the strength performance is ensured and a third stage of the freezing maintenance period.

そして、止水性能が確保されるまでの第一段階から強度性能が確保される第二段階までの任意のタイミングで、地盤先行掘削工程によって凍土壁5の内側の一部の地盤を先行掘削(一次掘削)する。   Then, at an arbitrary timing from the first stage until the water stopping performance is secured to the second stage where the strength performance is secured, a partial ground inside the frozen soil wall 5 is preliminarily excavated by the ground preliminary excavation process ( Primary excavation).

すなわち、本実施形態の凍結工法においては、地盤先行掘削工程を備え、例えばトンネル掘削の一部(止水性能を担保した凍土壁5の内側のセグメント近傍)を構造安定性に影響を及ぼさない範囲で先行掘削することにより、凍結膨張圧の一部を開放し、凍結膨張圧を低減することができる。  That is, the freezing method according to the present embodiment includes a ground excavation step, for example, a part of the tunnel excavation (in the vicinity of the inner segment of the frozen soil wall 5 that secures the water stopping performance) in a range that does not affect the structural stability. By excavating in advance, a part of the freezing expansion pressure can be released and the freezing expansion pressure can be reduced.

また、この止水性能を担保した内側の一部の地盤を先行掘削することによって、凍土を造成して増厚させ、強度的に十分な凍土壁を形成した段階の凍結膨張圧、すなわち、最終的に凍土が必要(最大)凍土厚に達した時点の凍結膨張圧も低減させることができる。   In addition, by excavating a part of the inner ground which secured the water stopping performance in advance, the frozen expansion pressure at the stage where the frozen soil was formed and thickened to form a frozen soil wall having sufficient strength, that is, the final expansion pressure, The freezing expansion pressure at the time when the frozen soil reaches the necessary (maximum) frozen soil thickness can also be reduced.

なお、実際の検討事例において、最大凍土厚6.6mを施工した時点における一次掘削を行わない場合の最大凍結膨張圧668kN/mに対し、一次掘削を行うことで最大凍結膨張圧が369kN/mに低減できることが実証されている。 Incidentally, in an actual study cases, with respect to the maximum freezing inflation pressure 668kN / m 2 in the case of not performing primary drilling at the time of the construction of the maximum frozen soil thickness 6.6 m, the maximum freezing inflation pressure by performing primary drilling 369KN / it has been demonstrated that can be reduced to m 2.

よって、本実施形態の凍結工法によれば、従来の凍結管列の外側への温水管を設置し凍結領域を制御する方法、凍土周囲の地山を抜き取って凍結膨張圧を低減させる方法、凍結膨張圧に対応したセグメントの補強を講じる方法、凍結運転制御(間引き運転等)による凍土の成長抑制方法と比較し、確実且つ簡便に凍結膨張圧を制御でき、工期短縮、コストダウンを実現することが可能になる。   Therefore, according to the freezing method of the present embodiment, a conventional method of installing a hot water pipe outside the row of freezing pipes to control the freezing area, a method of extracting the ground around the frozen soil to reduce the freezing expansion pressure, Compared with the method of reinforcing the segments corresponding to the expansion pressure and the method of controlling the growth of frozen soil by freezing operation control (thinning operation, etc.), it is possible to control the freezing expansion pressure more reliably and easily, and to shorten the construction period and reduce costs. Becomes possible.

以上、本発明による凍結工法の一実施形態について説明したが、本発明は上記の一実施形態に限定されるものではなく、その趣旨を逸脱しない範囲で適宜変更可能である。   As described above, one embodiment of the freezing method according to the present invention has been described, but the present invention is not limited to the above-described embodiment, and can be appropriately changed without departing from the gist thereof.

1 本線シールド
2 ランプシールド
3 地中発進基地
4 外殻シールド
5 凍土壁
6 本設覆工
7 凍結管
10 凍土領域
11 凍土領域
12 凍土領域
13 凍土領域
14 凍土領域
DESCRIPTION OF SYMBOLS 1 Main line shield 2 Lamp shield 3 Underground starting base 4 Outer shell shield 5 Frozen soil wall 6 Main lining 7 Freezing tube 10 Frozen area 11 Frozen area 12 Frozen area 13 Frozen area 14 Frozen area

Claims (1)

地盤を凍結させ、地盤の止水性能及び強度性能を向上させる凍結工法において、
凍結運転開始から所定領域の凍土が連続的に繋がって止水性能が確保された段階と、必要な凍土厚の凍土壁が造成されて強度性能が確保された段階との間の任意のタイミングで、前記凍土壁に対して内側の領域の一部の地盤を先行掘削することを特徴とする凍結工法。
In the freezing method to freeze the ground and improve the water stopping performance and strength performance of the ground,
At any time between the stage where the frozen soil in the predetermined area is continuously connected from the start of the freezing operation and the water stopping performance is secured, and the stage where the frozen soil wall of the required frozen soil thickness is created and the strength performance is secured, A freezing method characterized by excavating a part of the ground in an area inside the frozen soil wall in advance.
JP2016011548A 2016-01-25 2016-01-25 Freezing method Active JP6624443B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016011548A JP6624443B2 (en) 2016-01-25 2016-01-25 Freezing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016011548A JP6624443B2 (en) 2016-01-25 2016-01-25 Freezing method

Publications (2)

Publication Number Publication Date
JP2017133163A JP2017133163A (en) 2017-08-03
JP6624443B2 true JP6624443B2 (en) 2019-12-25

Family

ID=59502401

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016011548A Active JP6624443B2 (en) 2016-01-25 2016-01-25 Freezing method

Country Status (1)

Country Link
JP (1) JP6624443B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107829747B (en) * 2017-11-02 2019-08-02 安徽建筑大学 Construction method suitable for shallow-buried underground excavation tunnel in expansive soil area
JP6997614B2 (en) * 2017-12-20 2022-01-17 東京電力ホールディングス株式会社 How to maintain frozen soil and how to create frozen soil
CN108589706B (en) * 2018-05-11 2020-01-03 佳琳 Composite frozen soil steel pipe pile construction method
JP7498154B2 (en) 2021-06-30 2024-06-11 大成建設株式会社 Frozen soil expansion pressure absorber and frozen soil formation method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005264717A (en) * 2004-02-19 2005-09-29 Kajima Corp Ground freezing method
JP4771170B2 (en) * 2006-12-25 2011-09-14 清水建設株式会社 Construction method of underground cavity
KR20080079090A (en) * 2007-02-26 2008-08-29 김상록 Ground freezing process of underground structure outblock
JP5688244B2 (en) * 2010-07-28 2015-03-25 鹿島建設株式会社 Construction method for underground structures

Also Published As

Publication number Publication date
JP2017133163A (en) 2017-08-03

Similar Documents

Publication Publication Date Title
JP6624443B2 (en) Freezing method
JP6733862B2 (en) Construction method of the underground widening part
JP6252850B2 (en) Method of suppressing frost heave pressure in freezing method
JP2016160717A (en) Freezing method and freezing device of shield tunnel construction
CN104989421A (en) Support structure for preventing settlement deformation of tunnels and construction method thereof
CN104314585A (en) Pre-reinforcement method and pre-reinforcement structure for full section of tunnel
JP2010043440A (en) Method of increasing width of shield tunnel
CN109026012A (en) Vertical shaft surrounding rock supporting structure and its excavation supporting method
JP6624444B2 (en) Freezing method
CN105937397A (en) Segmented excavation freezing method reinforcing construction method for deep tunnel
JP2017172280A (en) Body lining wall and construction method thereof
JP2017122354A (en) Construction method of freezing pipe
CN110608047A (en) Underpass subway supporting structure and manufacturing method thereof
CN103924980A (en) Obstacle removing construction method
CN211008655U (en) Underpass subway supporting structure
CN104612113A (en) Karst water treatment method for diversion tunnel
JP6675637B2 (en) Freezing method
CN107387092A (en) A kind of multiple rectangular top pipes are connected in parallel on the engineering method that the underground space is formed under complex environment
CN113431587B (en) Construction method of shield tunnel connecting channel
JP2011080241A (en) Construction method of tunnel
JP6624441B2 (en) Construction method of the wall
JP2007277954A (en) Connecting structure between segment rings
CN107269283B (en) A kind of big cross section tunneling subway station and running tunnel penetrate through construction method
CN202866828U (en) Seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel
JP7019360B2 (en) Freezing method

Legal Events

Date Code Title Description
A80 Written request to apply exceptions to lack of novelty of invention

Free format text: JAPANESE INTERMEDIATE CODE: A80

Effective date: 20160217

RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20181005

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190111

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20191018

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20191029

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20191113

R150 Certificate of patent or registration of utility model

Ref document number: 6624443

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150