CN107269283B - A kind of big cross section tunneling subway station and running tunnel penetrate through construction method - Google Patents

A kind of big cross section tunneling subway station and running tunnel penetrate through construction method Download PDF

Info

Publication number
CN107269283B
CN107269283B CN201710707673.4A CN201710707673A CN107269283B CN 107269283 B CN107269283 B CN 107269283B CN 201710707673 A CN201710707673 A CN 201710707673A CN 107269283 B CN107269283 B CN 107269283B
Authority
CN
China
Prior art keywords
section
running tunnel
big cross
subway station
station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710707673.4A
Other languages
Chinese (zh)
Other versions
CN107269283A (en
Inventor
吴波
赵勇博
吴冬
李静
黄惟
王汪洋
卢福聪
刘宁
刘宗辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi University
CCCC First Highway Xiamen Engineering Co Ltd
Original Assignee
Guangxi University
CCCC First Highway Xiamen Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi University, CCCC First Highway Xiamen Engineering Co Ltd filed Critical Guangxi University
Priority to CN201710707673.4A priority Critical patent/CN107269283B/en
Publication of CN107269283A publication Critical patent/CN107269283A/en
Application granted granted Critical
Publication of CN107269283B publication Critical patent/CN107269283B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention discloses a kind of big cross section tunneling subway station and running tunnel penetrates through construction method, comprising steps of one, preparation of construction, advance geologic prediction simultaneously judges that required engineering method is excavated in big cross section subway station and running tunnel;Two, start to construct, according to required engineering method, construct simultaneously to big cross section subway station with running tunnel;Three, perforation section is reserved, big cross section subway station is excavated to station end;When running tunnel is constructed to 5~10m of station end, face stopping is tunneled forward;Four, end reinforces, and reinforces to station end, running tunnel and reserved perforation section;Five, big cross section subway station and running tunnel are penetrated through, 5 reserved~10m of running tunnel is excavated in end point AT STATION, until perforation subway station and running tunnel.Big cross section tunneling provided by the invention subway station and running tunnel penetrate through construction method, reserve safe distance in running tunnel, and to reinforcing at perforation, disturb to country rock small, reduce construction risk.

Description

A kind of big cross section tunneling subway station and running tunnel penetrate through construction method
Technical field
The present invention relates to subway work technical fields, more particularly to a kind of big cross section tunneling subway station and running tunnel Penetrate through construction method.
Background technique
In Urban Metro Construction, Underground Subway Station generally can all construct simultaneously with running tunnel, but tunneling big cross section Since section is big, difficulty of construction is big when subway station, construction speed can lag behind running tunnel.Therefore, when running tunnel and vehicle When section of standing friendship is passed through, suitable perforation technology and perforation opportunity is selected to become critical issue.
Currently, construction method is at tunnel big cross section connect perforation with light section with light section gradual transition to big cross section side Based on formula.Although this method construction period is shorter, narrow-bore tunnel digs large cross-section tunnel and disturbs big, difficulty of construction to country rock Greatly, it easily collapses and causes calamity, construction risk is big.
Summary of the invention
The object of the present invention is to provide a kind of big cross section tunneling subway stations and running tunnel to penetrate through construction method, to solve The above-mentioned problems of the prior art reserves safe distance in running tunnel, and is effectively reinforced at perforation, to country rock It disturbs small, reduces construction risk, ensure that construction safety.
To achieve the above object, the present invention provides the following technical scheme that
The present invention provides a kind of big cross section tunneling subway station and running tunnel penetrates through construction method, includes the following steps:
One, preparation of construction carries out advance geologic prediction and judges that institute is excavated in big cross section subway station and running tunnel accordingly Need engineering method;
Two, start to construct, according to required engineering method, construct simultaneously excavation to big cross section subway station and running tunnel;
Three, perforation section is reserved, big cross section subway station is excavated to station end by required engineering method;Running tunnel is pressed into institute When engineering method being needed to be excavated to 5~10m of station end, the face stopping of running tunnel is tunneled forward;
Four, end reinforces, and reinforces to the station end, running tunnel and reserved perforation section;
Five, big cross section subway station and running tunnel are penetrated through, 5 reserved~10m of running tunnel is excavated in end point AT STATION, Until perforation subway station and running tunnel.
Optionally, the construction of running tunnel described in step 2 specifically comprises the following steps:
A, according to the actual situation by the reasonable subregion piecemeal of running tunnel, and arch advance support is applied;
B, subregion piecemeal tunneling, and system radial direction anchor pole and interim steel arch-shelf are applied in time;
C, when face is pushed ahead away from the first Pin steel arch-shelf about 30m, a Pin steel arch-shelf is removed, and in time in corresponding positions It sets and applies secondary lining arch wall and inverted arch;
D, circulation step A, B, C is until position of the face away from 5~10m of station end, face stopping are tunneled forward.
Optionally, big cross section metro station construction described in step 2 specifically comprises the following steps:
A, according to the actual situation by the reasonable subregion piecemeal in big cross section subway station, and arch advance support is applied;
B, subregion piecemeal excavates big cross section subway station, and applies system radial direction anchor pole and interim steel arch-shelf in time;
C, when face is pushed ahead away from the first Pin steel arch-shelf about 30m, a Pin steel arch-shelf is removed, and in time in corresponding positions It sets and applies secondary lining arch wall and inverted arch;
D, circulation step A, B, C until face is tunneled to station tip position, tunnel forward by face stopping.
Optionally, the running tunnel and big cross section metro station construction respectively further comprise step E, remove opened in order All interim steel arch-shelfs in region are dug, and apply lock foot anchoring stock, secondary lining arch wall and inverted arch in time, until it is secondary to have excavated region Lining cutting all applies completion.
Optionally, step 5 described above specifically includes:
1) the section preliminary bracing of big cross section subway station end, is applied, steel mesh and gunite concrete are hung;
2), in big cross section subway station end section part along running tunnel design profile line, and within the scope of contour line 3m Apply two rows of arch advance supports;
3), subregion piecemeal excavates reserved perforation section, and applies system radial direction anchor pole and interim steel arch-shelf in time;
4) perforation of big cross section tunneling subway station and running tunnel, is completed.
Optionally, the arch advance support is uniformly arranged on country rock using advance anchor bolt or steel pipe, and with The country rock radial direction cross section perpendicular.
Optionally, grouting and reinforcing is carried out at the country rock around the big cross section subway station and the running tunnel.
Optionally, the radial anchor pole is uniformly distributed in country rock surrounding, and is respectively perpendicular to country rock axial direction section.
Big cross section tunneling provided by the invention subway station and running tunnel penetrate through construction method, have compared with prior art There is following technical effect:
1, adaptable;The present invention can adapt to various complex geological conditions, especially in the various complexity such as weak surrounding rock Under geological conditions, effect is especially pronounced.
2, highly-safe;It is traditional in a manner of light section gradual transition to big cross section based on construction method country rock is disturbed Greatly, difficulty of construction is big, easily collapses and causes calamity, and construction risk is big.The present invention reserves safe distance in running tunnel first, and to passing through Logical place is effectively reinforced, and is then constructed in such a way that big cross section is transitioned into small end face.The traditional perforation construction of effective solution The problems such as method disturbs greatly country rock, and construction risk is high, ensure that construction safety.
3, at low cost;Difficulty of construction of the present invention is low, reduces the triviality of personnel, machinery and construction method adjustment, drop Low construction cost.
4 flexibilities are good;The present invention can according to country rock actual conditions, flexibly adjustment station end section with remain to penetrate through in advance The support pattern in area.
Detailed description of the invention
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, for those of ordinary skill in the art, without any creative labor, can also be according to these attached drawings Obtain other attached drawings;
Fig. 1 is that big cross section tunneling of the present invention subway station and running tunnel penetrate through construction process schematic diagram;
Fig. 2 is big cross section tunneling of the present invention subway station end schematic cross-sectional view;
Fig. 3 is running tunnel of the present invention construction schematic cross-sectional view;
Fig. 4 is big cross section tunneling of the present invention subway station and running tunnel perforation construction vertical section schematic diagram;
Description of symbols: 1 it is system radial direction anchor pole, 2 is arch advance support, 3 is arch wall, 4 is inverted arch, 5 is interim Steel arch-shelf, 6 be Station end section, 7 be face, 8 be country rock, 9 be running tunnel design profile line, 10 be lock foot anchor Bar, 11 are the section preliminary bracing of station end.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
The object of the present invention is to provide a kind of big cross section tunneling subway stations and running tunnel to penetrate through construction method, to solve The above-mentioned problems of the prior art reserves safe distance in running tunnel, and is effectively reinforced at perforation, to country rock It disturbs small, reduces construction risk, ensure that construction safety.
Big cross section tunneling provided by the invention subway station and running tunnel penetrate through construction method, include the following steps:
One, preparation of construction carries out advance geologic prediction and judges that institute is excavated in big cross section subway station and running tunnel accordingly Need engineering method;
Two, start to construct, according to required engineering method, construct simultaneously excavation to big cross section subway station and running tunnel;
Three, perforation section is reserved, big cross section subway station is excavated to station end by required engineering method;Running tunnel is constructed When to 5~10m of station end, face stopping is tunneled forward;
Four, end reinforces, and reinforces to the station end, running tunnel and reserved perforation section;
Five, big cross section subway station and running tunnel are penetrated through, 5 reserved~10m of running tunnel is excavated in end point AT STATION, Until perforation subway station and running tunnel.
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, with reference to the accompanying drawing and specific real Applying mode, the present invention is described in further detail.
The Specific construction process of big cross section tunneling provided by the invention subway station and running tunnel perforation construction method is such as Shown in Fig. 1;Firstly, carrying out preparation of construction, advance geologic prediction, and judge operating condition, determines big cross section subway station and area according to this Between tunnel respectively excavate needed for engineering method;Big cross section subway station is excavated simultaneously with running tunnel, excavate before respectively to place to be dug into Row leading pre-supporting, Rapid Excavation, the part dug carry out primary supporting and secondary lining in time step by step later.Wherein, area Between tunnel excavation to away from 5~10m of station end locate, face stop tunnel;And big cross section subway station section is excavated arrive vehicle always Stand end, later Closed station end, and AT STATION end to reinforcing leading pre-supporting around running tunnel design profile line, it Running tunnel is excavated along running tunnel design profile line until running tunnel is reserved at face afterwards;At this point, completing construction, realize The perforation of big cross section tunneling subway station and running tunnel.
In above-mentioned work progress, running tunnel is excavated along running tunnel design profile line until running tunnel reserves area At face, first reinforces leading pre-supporting before excavating, substep Rapid Excavation later, when digging to the region dug carry out primary supporting and Secondary lining.
Specifically, as shown in Fig. 2, big cross section tunneling of the present invention subway station Specific construction process are as follows: A, according to practical feelings The reasonable subregion piecemeal of running tunnel is applied arch advance support 2 by condition;B, it is excavated with reasonable working procedure subregion piecemeal Subway station, and system radial direction anchor pole 1 and interim steel arch-shelf 5 are applied in time;C, it is pushed ahead to face interim away from the first Pin When the about 30m of steel arch-shelf 5, the interim steel arch-shelf 5 of a Pin is removed, and apply secondary lining arch wall 3 and inverted arch 4 in corresponding position in time; D, tri- circulation A, B, C steps form big cross section tunneling subway station end section 6 up to the driving of face 7 to station end, Interim steel arch-shelf 5 is removed in order, and applies lock foot anchoring stock 10 and secondary lining arch wall 3, inverted arch 4 in time, until subway station Secondary lining all applies completion.
As shown in figure 3, running tunnel of the present invention excavates construction process are as follows: A, according to the actual situation that running tunnel is reasonable Subregion piecemeal applies arch advance support 2;B, it is excavated with reasonable working procedure subregion piecemeal, and applies system diameter in time To anchor pole 1 and interim steel arch-shelf 5;C, it when face pushes ahead steel arch-shelf 5 about 30m interim away from the first Pin, removes a Pin and faces When steel arch-shelf 5, and apply secondary lining arch wall 3 and inverted arch 4 in corresponding position in time;D, tri- circulation A, B, C steps are until the palm Son driving removes interim steel arch-shelf 5, and apply lock foot anchoring stock 10 and secondary lining arch wall 3 in time, face upward to station end in order Arch 4, until subway station secondary lining all applies completion.
As shown in figure 4, big cross section tunneling of the present invention subway station and running tunnel penetrate through construction process are as follows: A, apply station End section preliminary bracing 11, hangs steel mesh and gunite concrete should also carry out grouting and reinforcing if 8 condition of country rock is poor;B, exist Station end section part applies two rows of arch advance supports 2 along running tunnel design profile line 9 within the scope of its 3m, if country rock 8 Condition is poor, Ying Jinhang grouting and reinforcing or use other reinforcing modes;C, according to the actual situation by the reasonable subregion of running tunnel Piecemeal;D, with reasonable working procedure, subregion piecemeal excavates running tunnel region to be penetrated through, and applies system radial direction anchor in time Bar 1 and interim steel arch-shelf 5;E, in digging process, reinforce the Real-Time Measuring and timely feedback, adjust support pattern in time, really Protect safe construction at perforation.F, it is excavated to face 7, completes the perforation of big cross section tunneling subway station and running tunnel.
Big cross section tunneling provided by the invention subway station and running tunnel penetrate through construction method, adaptable;It can fit Various complex geological conditions and environmental condition are answered, especially under the various complex geological conditions such as weak surrounding rock, effect is especially aobvious It writes.It is highly-safe;It is traditional in a manner of light section gradual transition to big cross section based on construction method big, construction is disturbed to country rock Difficulty is big, easily collapses and causes calamity, and construction risk is big.The present invention reserves safe distance in running tunnel first, and at perforation into Row effectively reinforce, then by big cross section be transitioned into it is light-gauge in a manner of construct.The traditional perforation construction method pair of effective solution The problems such as country rock disturbance is big, and construction risk is high, ensure that construction safety.It is at low cost;Difficulty of construction of the present invention is low, reduces people The triviality that member, mechanical and construction method adjust, reduces construction cost.Flexibility is good;The present invention can be according to country rock reality Situation, flexibly adjustment Station end section and the support pattern for remaining perforation area in advance.
Apply that a specific example illustrates the principle and implementation of the invention in this specification, above embodiments Explanation be merely used to help understand method and its core concept of the invention;At the same time, for those skilled in the art, According to the thought of the present invention, there will be changes in the specific implementation manner and application range.In conclusion in this specification Appearance should not be construed as limiting the invention.

Claims (8)

1. a kind of big cross section tunneling subway station and running tunnel penetrate through construction method, characterized by the following steps:
One, preparation of construction carries out advance geologic prediction and judges big cross section subway station and running tunnel according to advance geologic prediction Engineering method needed for excavating;
Two, start to construct, according to required engineering method, construct simultaneously excavation to big cross section subway station and running tunnel;
Three, perforation section is reserved, big cross section subway station is excavated to station end by required engineering method;Running tunnel is pressed into required work When method is excavated to 5~10m of station end, the face stopping of running tunnel is tunneled forward;
Four, end reinforces, and reinforces to the station end, running tunnel and reserved perforation section;
Five, big cross section subway station and running tunnel are penetrated through, 5 reserved~10m of running tunnel is excavated in end point AT STATION, until Penetrate through subway station and running tunnel.
2. big cross section tunneling according to claim 1 subway station and running tunnel penetrate through construction method, it is characterised in that: The construction of running tunnel described in step 2 specifically comprises the following steps:
A, according to the actual situation by the reasonable subregion piecemeal of running tunnel, and arch advance support is applied;
B, subregion piecemeal tunneling, and system radial direction anchor pole and interim steel arch-shelf are applied in time;
C, when face is pushed ahead away from the first Pin steel arch-shelf about 30m, a Pin steel arch-shelf is removed, and apply in time in corresponding position Make secondary lining arch wall and inverted arch;
D, circulation step A, B, C is until position of the face away from 5~10m of station end, face stopping are tunneled forward.
3. big cross section tunneling according to claim 1 subway station and running tunnel penetrate through construction method, it is characterised in that: Big cross section metro station construction described in step 2 specifically comprises the following steps:
A, according to the actual situation by the reasonable subregion piecemeal in big cross section subway station, and arch advance support is applied;
B, subregion piecemeal excavates big cross section subway station, and applies system radial direction anchor pole and interim steel arch-shelf in time;
C, when face is pushed ahead away from the first Pin steel arch-shelf about 30m, a Pin steel arch-shelf is removed, and apply in time in corresponding position Make secondary lining arch wall and inverted arch;
D, circulation step A, B, C until face is tunneled to station tip position, tunnel forward by face stopping.
4. big cross section tunneling according to claim 2 or 3 subway station and running tunnel penetrate through construction method, feature exists Step E is respectively further comprised in: the running tunnel and big cross section metro station construction, removes excavated that region is all to be faced in order When steel arch-shelf, and apply lock foot anchoring stock, secondary lining arch wall and inverted arch in time, all applied until having excavated region secondary lining It completes.
5. big cross section tunneling according to claim 1 subway station and running tunnel penetrate through construction method, it is characterised in that: The step 5 specifically includes:
1) the section preliminary bracing of big cross section subway station end, is applied, steel mesh and gunite concrete are hung;
2) it, is applied in big cross section subway station end section part along running tunnel design profile line, and within the scope of contour line 3m Two rows of arch advance supports;
3), subregion piecemeal excavates reserved perforation section, and applies system radial direction anchor pole and interim steel arch-shelf in time;
4) perforation of big cross section tunneling subway station and running tunnel, is completed.
6. big cross section tunneling according to claim 5 subway station and running tunnel penetrate through construction method, it is characterised in that: The arch advance support is uniformly arranged on country rock using advance anchor bolt or steel pipe, and with the country rock radial direction section Vertically.
7. big cross section tunneling according to claim 5 subway station and running tunnel penetrate through construction method, it is characterised in that: Grouting and reinforcing is carried out at the country rock around the big cross section subway station and the running tunnel.
8. big cross section tunneling according to claim 5 subway station and running tunnel penetrate through construction method, it is characterised in that: The system radial direction anchor pole is the system radial direction anchor pole of big cross section subway station, running tunnel and reserved perforation section, and it is uniformly It is distributed in country rock surrounding, and is respectively perpendicular to country rock axial direction section.
CN201710707673.4A 2017-08-17 2017-08-17 A kind of big cross section tunneling subway station and running tunnel penetrate through construction method Active CN107269283B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710707673.4A CN107269283B (en) 2017-08-17 2017-08-17 A kind of big cross section tunneling subway station and running tunnel penetrate through construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710707673.4A CN107269283B (en) 2017-08-17 2017-08-17 A kind of big cross section tunneling subway station and running tunnel penetrate through construction method

Publications (2)

Publication Number Publication Date
CN107269283A CN107269283A (en) 2017-10-20
CN107269283B true CN107269283B (en) 2019-07-12

Family

ID=60080454

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710707673.4A Active CN107269283B (en) 2017-08-17 2017-08-17 A kind of big cross section tunneling subway station and running tunnel penetrate through construction method

Country Status (1)

Country Link
CN (1) CN107269283B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107965328B (en) * 2017-12-29 2019-09-06 中车建设工程有限公司 Underground station whole dark digging construction method
CN108457658B (en) * 2018-03-14 2019-12-06 济南城建集团有限公司 Construction method for single-hole bidirectional construction intersection section of tunnel with soil layer

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19617199A1 (en) * 1996-04-29 1997-10-30 Hochtief Ag Hoch Tiefbauten Station-formation method in Tubbing-lined railway tunnel
CN101289938A (en) * 2008-06-12 2008-10-22 北京城建设计研究总院有限责任公司 Subway shield tunnel enlarging station special area and station structure connecting method
CN101864959A (en) * 2009-04-17 2010-10-20 中铁工程设计咨询集团有限公司 Method for tunneling construction of main structure of underground station
CN105041349A (en) * 2015-07-26 2015-11-11 北京工业大学 Underground excavation construction method for expanded excavation of station on basis of metro regional shield tunnel

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19617199A1 (en) * 1996-04-29 1997-10-30 Hochtief Ag Hoch Tiefbauten Station-formation method in Tubbing-lined railway tunnel
CN101289938A (en) * 2008-06-12 2008-10-22 北京城建设计研究总院有限责任公司 Subway shield tunnel enlarging station special area and station structure connecting method
CN101864959A (en) * 2009-04-17 2010-10-20 中铁工程设计咨询集团有限公司 Method for tunneling construction of main structure of underground station
CN105041349A (en) * 2015-07-26 2015-11-11 北京工业大学 Underground excavation construction method for expanded excavation of station on basis of metro regional shield tunnel

Also Published As

Publication number Publication date
CN107269283A (en) 2017-10-20

Similar Documents

Publication Publication Date Title
CN104612698B (en) A kind of shallow-depth-excavation tunnel top bar interval wall construction method
CN101775988B (en) Method for constructing from inclined shaft to main tunnel in weak surrounding rock
CN108035733B (en) A kind of perpendicular support partial excavation method of rock matter large section tunnel steelframe dike combination
CN109707399B (en) Tunnel exit supporting structure and construction method thereof
CN104653187B (en) Water-rich sand layer geology large cross-section tunnel excavation method
CN105443132A (en) Construction method of shallow-buried subsurface-excavated cross-shaped cross-strut tunnel
CN108442943A (en) A kind of branch-cut bridge section tunnel and Double side heading method construction method
CN104632235A (en) Method for expanding excavation of large-diameter shield tunnel for subway station construction through pile arch wall support
CN102644467A (en) Tunnel connecting passage construction method for directly cutting segment rings through pipe jacking machine
CN103899318B (en) The milling of medium ground tunnel is dug and supporting machinery construction
CN103939105B (en) A kind of construction method and structure laying construction shaft above underground construction
CN102373930A (en) Rapid construction method of weak surrounding rock large-section multi-arc tunnel
CN103306680A (en) Construction method for extending single-track tunnel to multi-track tunnel
CN102312672A (en) Fast large-cross-section tunnel construction method adapting to complicated and variable geological conditions
CN106869969A (en) A kind of excavation supporting construction method of soft rock large section tunnel
CN107575237A (en) A kind of subsurface excavation method is combined the construction method of construction subway station with shield method
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN104533428B (en) A kind of steep cliffs tunnel outlet engineering method
CN110242305A (en) A kind of inclined shaft applies the construction technique in main hole into single side heading method
CN105507908A (en) Three-arch construction process for connecting tunnel of large cross-section tunnel
CN105909256A (en) Large-span weak surrounding rock tunnel construction method adopting face pre-reinforcement core soil reserving three-step temporary inverted arch technology
CN109184700A (en) The construction method of rock is pressed from both sides during a kind of weak surrounding rock small-clear-distance tunnel is stable
CN107620600A (en) A kind of MJS engineering methods and pipe-roof method combined supporting big cross section small interval tunneling engineering method
CN104632227A (en) Subway station excavation technology of single-layer beam arch structure
CN107269283B (en) A kind of big cross section tunneling subway station and running tunnel penetrate through construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190617

Address after: 530004 100 East University Road, XiXiangTang District, Nanning, the Guangxi Zhuang Autonomous Region

Applicant after: Guangxi University

Applicant after: CCCC First Highway Xiamen Engineering Co., Ltd.

Address before: 530000 100 East University Road, XiXiangTang District, Nanning, the Guangxi Zhuang Autonomous Region

Applicant before: Guangxi University

GR01 Patent grant
GR01 Patent grant