CN202866828U - Seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel - Google Patents

Seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel Download PDF

Info

Publication number
CN202866828U
CN202866828U CN 201220525760 CN201220525760U CN202866828U CN 202866828 U CN202866828 U CN 202866828U CN 201220525760 CN201220525760 CN 201220525760 CN 201220525760 U CN201220525760 U CN 201220525760U CN 202866828 U CN202866828 U CN 202866828U
Authority
CN
China
Prior art keywords
tunnel
high pressure
seepage
buried
lining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220525760
Other languages
Chinese (zh)
Inventor
张伟
罗前进
沈明
赵瑞存
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hydrochina East China Engineering Corp
Original Assignee
Hydrochina East China Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina East China Engineering Corp filed Critical Hydrochina East China Engineering Corp
Priority to CN 201220525760 priority Critical patent/CN202866828U/en
Application granted granted Critical
Publication of CN202866828U publication Critical patent/CN202866828U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to a seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel. And the utility model aims at providing the seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel which is simple in structure and convenient to construct and completely. Solving the leakage problem of the high pressure tunnel, thus leakage damage prevented from happening and the seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel ensures that the tunnel operates safely and permanently. The technical scheme of the seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel is that the seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel comprises the tunnel, wherein a concrete lining is poured on the inner surface of the tunnel. The seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel is characterized in that pipe-shaped steel lining is sleeved in the tunnel, wherein concrete layers are refilled in the reserved gap between the steel lining and the concrete lining. The seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel is suitable for a water resources and hydropower project.

Description

The leakage preventing structure that water conservancy project high pressure, buried, inclination tunnel seepage are processed
Technical field
The utility model relates to the leakage preventing structure of leakage preventing structure, particularly a kind of water conservancy project high pressure that a kind of tunnel seepage processes, buried, inclination tunnel (vertical shaft, inclined shaft) seepage treatment, mainly is applicable in the Hydraulic and Hydro-Power Engineering.
Background technology
In recent years, China's Hydraulic and Hydro-Power Engineering development is rapid, and large quantities of large, medium and small type power stations are constructed and put into operation successively.For the power station (perhaps pumped storage power plant) of adopting longer tunnel development scheme, because landform, condition of technology and economy, the reasons such as duration, long, large buried depth tunnel is with respect to surface buildingses such as dams, the engineering preliminary stage is difficult to carry out fairly large ground and surveys work, also can't carry out extensive supplementary investigation owing to all condition restriction after the engineering practice of construction, so that adopt the hydropower tunnel of reinforced concrete lining layer pattern behind power generation, to have leakage greatly or the risk of seepage failure, and then affect the normal operation in power station, cause the loss on the economic benefit of power station, also may cause certain social influence.Hinge according to the water delivery electricity generation system is arranged, often needs to arrange that the tunnel (vertical shaft, inclined shaft) of inclination reduces diversion tunnel length in the diversion system, reduces cost.If tunnel seepage occurs in vertical shaft (or inclined shaft) hole section, then with respect to adit, intractability will further strengthen.
Seepage treatment for high pressure, buried, (vertical shaft, the inclined shaft) tunnel that tilts, process seepage if adopt grouting method, because of reasons such as seepage section stratum geological conditions, structural plane proterties, perhaps reasons such as difficulty of construction, construction technology level, grouting agent, consolidation grouting does not often reach expected effect, even reached Expected Results, from satisfying the angle of the permanent service requirement of engineering, this method also is difficult to obtain each side's approval.
Adopt the processing mode of spraying seepage prevention material on the tunnel lining surface, then be not suitable for the outer higher engineering characteristic of hydraulic pressure of buried hydraulic tunnel.
Summary of the invention
The technical problems to be solved in the utility model is: provide a kind of water conservancy project high pressure of simple in structure, easy construction, buried, leakage preventing structure that the inclination tunnel seepage is processed for the problem of above-mentioned existence, thoroughly solve the leakage problems of heavy-duty pressure tunnel, prevent seepage failure, to guarantee the permanent security of operation of tunnel.
The technical scheme that the utility model adopts is: the leakage preventing structure that water conservancy project high pressure, buried, inclination tunnel seepage are processed, comprise tunnel, its inner surface has been built concrete lining, it is characterized in that: described tunnel inner sleeve tubulose steel lining, backfill has layer of concrete in the space of reserving between this steel lining and the concrete lining.
Gap between described concrete lining and the steel lining external surface is not less than 25cm.
Described steel lining external surface coaxial rings is to arranging one group of stiffening ring.
The height of described stiffening ring is not less than 10cm.
The spacing of adjacent two stiffening rings does not occur in the external pressure situation to be controlled at that stress is overlapping to be as the criterion, and its minimum value is 40cm.
Described steel lining is welded successively by the some sections identical steel pipes of diameter.
Described steel lining adopts Q345R or Q235R steel to make.
The beneficial effects of the utility model are: the utility model is when the water conservancy project high pressure, buried, (vertical shaft tilts, when inclined shaft) having occurred in the tunnel exceeding the seepage of design limiting, be the control leakage, prevent seepage failure, by the tunnel seepage analysis, take the mode of inner sleeve steel lining to carry out seepage treatment to the certain hole section that produces tunnel seepage, and backfill high fluid self dense concrete in the space of between inner sleeve steel lining and concrete lining, reserving, thereby once and for all has solved the problem of high pressure deep-lying tunnel seepage, prevent seepage failure, do not stay future trouble, guaranteed the permanent Operation safety of tunnel.For occuring, remedying equally of seepage failure tunnel corresponding site can adopt said method.
Description of drawings
Fig. 1 is sectional view of the present utility model.
Fig. 2 is the profile of Fig. 1.
Fig. 3 is steel pipe single-sided welding weld groove drawing in the utility model.
Fig. 4 is steel lining transportation scheme of installation in the utility model.
The specific embodiment
As shown in Figure 1 and Figure 2, present embodiment comprises inclination tunnel 1(vertical shaft or inclined shaft, be inclined shaft in this example), it is 50cm that tunnel 1 inner surface has been built this routine thickness of concrete lining 2(), and the tubulose steel lining 3 of inner sleeve coaxial arrangement, one group of stiffening ring 5 of steel lining 3 external surface coaxial arrangement wherein, and wherein part stiffening ring 5 welds with the support system dowel, simultaneously between concrete lining 2 and steel lining 3, reserve construction gap, and good this example of the layer of concrete 4(employing strength grade of backfill self-compacting ability is the concrete of C20).
In the specific implementation process, at first according to the site operation data of early stage, the geologic information of construction period and tunnel concrete liner 2, grouting, fill the draining data and the earth's surface is surveyed etc. in conjunction with tunnel 1, hydraulic tunnel 1 seepage is analyzed, determine inclination tunnel 1 concrete seepage place, and determine the layout scope of inner sleeve steel lining 3 according to the principle of seepage stability.
Secondly, according to aspects such as the calculating of power station transient process, the variation of water delivery electricity generation system damage by water, steel lining 3 installations, welding procedure needs and construction investments, comprehensively determine the caliber of inner sleeve steel lining 3.For reducing as much as possible head loss, reduce the intensity of variation of channel system fringe conditions, the diameter of inner sleeve steel lining 3 should be larger, but for construction and installation need, be convenient to the transportation of steel lining 3, and consider steel lining 3 outer stiffening rings 5 highly, should reserve certain space between inner sleeve steel lining 3 and the concrete lining 2, its minimum value is 25cm, in this example, gap between described concrete lining 2 and steel lining 3 external surfaces is 35cm, and namely the thickness of layer of concrete 4 is 35cm.
Present embodiment is according to the wall thickness of external water pressure and steel lining 3, stiffening ring 5 adopts the arrangement highly low, that spacing is close, the highly general desirable 10cm~15cm of stiffening ring 5, overlapping or the overlapping stress that do not cause of stress of stress does not occur and significantly increases to standard to be controlled in the spacing between adjacent two stiffening rings 5 in the external pressure situation, minimum can be got 40cm~50cm.
Described steel lining 3 is formed by the identical steel pipe of some sections diameters successively continued access, according to present welding procedure level, the steel pipe circular seam that wall thickness 30mm is following, Site Welding adopts single-side welding double-side forming technique or peripheral hardware backing plate technique welding quality can reach requirement, therefore, steel pipe adopts Q345R or the Q235R steel of good welding performance in this example, and adopts single face (inwall of steel pipe) welding manner as shown in Figure 3 to realize that the continued access of steel lining 3 prolongs.
As shown in Figure 4, in the practical application, the transport channel of steel pipe generally is selected in needs to arrange tunnel plug position, steel lining section upstream and downstream, with the former plug demolition blasting of tunnel, utilize former construction to prop up the hole and form transport channel, steel pipe props up in the hole or the construction operations such as unload, stand up in a construction hole and intersection, main hole, skate welding in former construction; Simultaneously, according to the Against Sliding Stability needs of newly-increased inner sleeve steel lining 3 and fill concrete layer 4, carry out surperficial dabbing on concrete lining 2 surfaces of tunnel 1 and process (process range, length are decided according to the Against Sliding Stability needs).Steel pipe is at tunnel 1(inclined shaft) in when transportation, need to be at the default rail 6 of 1 end of tunnel arch, simultaneously at steel pipe welding skate 7, the rail 6 that utilization is complementary and skate 7 carry out steel pipe transmission, then utilize operation platform 8 in the steel pipe realize steel linings 3 location fixing (comprise utilize operation platform 8 steel pipe nozzle hoop construction dowel and and steel-pipe welding fix) and adjacent two steel pipes between welding, backfill high fluid self dense concrete gets final product outside managing at last.
Steel pipe is comparatively convenient at shaft transport, need not weld skate, and directly lifting is fixing gets final product; In addition, the utility model also can be used for the antiseepage processing of water conservancy project high pressure, buried adit.

Claims (7)

1. a water conservancy project high pressure, buried, leakage preventing structure that the inclination tunnel seepage is processed, comprise tunnel (1), its inner surface has been built concrete lining (2), it is characterized in that: described tunnel (1) inner sleeve tubulose steel lining (3), backfill has layer of concrete (4) in the space of reserving between this steel lining and the concrete lining (2).
2. the leakage preventing structure processed of water conservancy project high pressure according to claim 1, buried, inclination tunnel seepage, it is characterized in that: the gap between described concrete lining (2) and steel lining (3) external surface is not less than 25cm.
3. the leakage preventing structure processed of water conservancy project high pressure according to claim 1 and 2, buried, inclination tunnel seepage, it is characterized in that: described steel lining (3) external surface coaxial rings is to arranging one group of stiffening ring (5).
4. the leakage preventing structure processed of water conservancy project high pressure according to claim 3, buried, inclination tunnel seepage, it is characterized in that: the height of described stiffening ring (5) is not less than 10cm.
5. the leakage preventing structure processed of water conservancy project high pressure according to claim 3, buried, inclination tunnel seepage is characterized in that: the spacing of adjacent two stiffening rings (5) does not occur in the external pressure situation to be controlled at that stress is overlapping to be as the criterion, and its minimum value is 40cm.
6. the leakage preventing structure processed of water conservancy project high pressure according to claim 1 and 2, buried, inclination tunnel seepage, it is characterized in that: described steel lining (3) is welded successively by the some sections identical steel pipes of diameter.
7. the leakage preventing structure processed of water conservancy project high pressure according to claim 1 and 2, buried, inclination tunnel seepage, it is characterized in that: described steel lining (3) adopts Q345R or Q235R steel to make.
CN 201220525760 2012-10-15 2012-10-15 Seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel Expired - Lifetime CN202866828U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220525760 CN202866828U (en) 2012-10-15 2012-10-15 Seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220525760 CN202866828U (en) 2012-10-15 2012-10-15 Seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel

Publications (1)

Publication Number Publication Date
CN202866828U true CN202866828U (en) 2013-04-10

Family

ID=48033553

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220525760 Expired - Lifetime CN202866828U (en) 2012-10-15 2012-10-15 Seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel

Country Status (1)

Country Link
CN (1) CN202866828U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105257318A (en) * 2015-10-22 2016-01-20 上海交通大学 Safety protection method for tunnel structural deformation caused by lining local leakage
CN111697481A (en) * 2020-06-30 2020-09-22 上海宝冶集团有限公司 Manufacturing and using method of cable well

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105257318A (en) * 2015-10-22 2016-01-20 上海交通大学 Safety protection method for tunnel structural deformation caused by lining local leakage
CN111697481A (en) * 2020-06-30 2020-09-22 上海宝冶集团有限公司 Manufacturing and using method of cable well

Similar Documents

Publication Publication Date Title
CN100554646C (en) Shield method combines the job practices of building the subway station with shallow burial hidden digging
CN110005439B (en) Construction method for shield near-distance over-advanced tunnel
CN101915105B (en) United method for tunneling super-strong or strong rock burst hole section of TBM construction tunnel
CN110924978B (en) Construction method for preventing instability of shield tunnel under high-sensitivity stratum condition
CN103469802A (en) Combined lattice steel frame spray anchoring supporting method and combined lattice steel frame spray anchoring supporting structure
CN109779653B (en) Construction method for crossing of soft rock large-section tunnel
CN104018846B (en) A kind of hydraulic tunnel structure of crossing over large-scale activity fault zone
CN203547753U (en) Profile steel concrete shaft wall base
CN109779651A (en) A kind of sand ginger cohesive soil stratum low coverage Slurry Balanced Pipe Jacking Construction method
CN203583493U (en) Combined lattice steel frame spray anchoring foundation pit supporting structure
CN202866828U (en) Seepage-proofing structure of hydraulic high pressure, deeply buried and leakage processing of inclined tunnel
CN204716253U (en) Circular major diameter diversion tunnel structure
Wu et al. Rock mechanical problems and optimization for the long and deep diversion tunnels at Jinping II hydropower station
CN109695457A (en) The enlarging large section tunnel in situ and step construction method of hard rock
CN203429600U (en) Impervious structure for seepage treatment of high-pressure deeply-buried inclined tunnel in water conservancy project
CN205206847U (en) Shield constructs business turn over hole portal annular and freezes sealed sealing device
CN202181907U (en) Tenon-free pipe curtain structure
CN108915723B (en) Shield tunnel segment structure crossing vertical dislocation movable fault
CN204370417U (en) A kind of for base pit engineering external corner or the road place of going along with sb. to guard him to drawing cable bolting structure
CN102444408A (en) Secondary lining split mounting type blocking head device for metro underground excavation tunnel
CN210238512U (en) Concrete high dam full dam storehouse surface-free consolidation grouting structure
CN104047273B (en) Power station dissipation and scouring wall and construction method thereof
CN210152658U (en) Mutual independent many cabins of structure utility tunnel side by side
CN208441866U (en) Diversion Tunnel excavation liner structure
Zhang et al. Construction applicability of mechanical methods for connecting aisle in the bohai mudstone stratum with high water pressure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20130410

CX01 Expiry of patent term