JP6588585B2 - Pile construction management method - Google Patents

Pile construction management method Download PDF

Info

Publication number
JP6588585B2
JP6588585B2 JP2018024377A JP2018024377A JP6588585B2 JP 6588585 B2 JP6588585 B2 JP 6588585B2 JP 2018024377 A JP2018024377 A JP 2018024377A JP 2018024377 A JP2018024377 A JP 2018024377A JP 6588585 B2 JP6588585 B2 JP 6588585B2
Authority
JP
Japan
Prior art keywords
pile
excavation
hole
depth
penetration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2018024377A
Other languages
Japanese (ja)
Other versions
JP2018091132A (en
Inventor
孝彦 樫本
孝彦 樫本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Oak Co Ltd
Original Assignee
Oak Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Oak Co Ltd filed Critical Oak Co Ltd
Priority to JP2018024377A priority Critical patent/JP6588585B2/en
Publication of JP2018091132A publication Critical patent/JP2018091132A/en
Application granted granted Critical
Publication of JP6588585B2 publication Critical patent/JP6588585B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、プレボーリング工法、アースドリル工法、オールケーシング工法等により、地盤に穿設した杭孔内に既製杭を建て込む杭施工管理方法に関する。   The present invention relates to a pile construction management method for building a ready-made pile in a pile hole drilled in the ground by a pre-boring method, an earth drill method, an all casing method, or the like.

従来より、プレボーリング工法による既製杭の施工では、三点式杭打機等のリーダに沿って昇降するオーガーマシンに取り付けたスクリューロッドを回転駆動しつつ下降させることにより、地盤を掘削して想定される地下深部の支持層に達する深さの杭孔を形成したのち、スクリューロッドを引き上げつつ、ソイルセメント等の根固め液を注入し、続いて孔周固定液を杭孔の上部まで注入し、該スクリューロッドを抜出したのち、オーガーマシンAに連結用ロッドを介してPHC杭やPRC杭の如き既製杭を連結し、この既製杭を杭孔に挿入して埋め込むのが一般的である。   Conventionally, in the construction of ready-made piles by the pre-boring method, it is assumed that the ground is excavated by lowering while rotating the screw rod attached to the auger machine that moves up and down along the leader such as a three-point pile driver After forming a pile hole with a depth that reaches the support layer in the deep underground, injecting a root-setting liquid such as soil cement while pulling up the screw rod, and then injecting a perimeter fixing liquid up to the top of the pile hole, After extracting a screw rod, it is common to connect a ready-made pile such as a PHC pile or a PRC pile to the auger machine A via a connecting rod, and insert the ready-made pile into a pile hole and embed it.

これら工法による建て込み完了後の杭の支持強度が充分であるか否かは一般的に載荷試験によって判定できるが、それによって支持強度不足が判明した場合は杭施工のやり直しに多大な労力と時間及びコストを費やすことになるため、掘削形成した杭孔について杭先端の支持力が充分であるか否かを杭建て込み前に判定できれば理想的である。従来、このような観点から、掘削部材の回転駆動用モータの電流値から掘削負荷の変化を捉え、この掘削負荷の増大によって杭孔が地盤深部の硬い支持層に達したことを確認する方法が提案されている(特許文献1〜3)。   In general, it is possible to determine whether or not the support strength of piles after the completion of construction by these methods is sufficient by a loading test, but if it is found that the support strength is insufficient, it takes a lot of labor and time to redo the pile construction. It would be ideal if it was possible to determine whether or not the pile bearing hole had sufficient bearing capacity at the tip of the pile before the pile was built. Conventionally, from this point of view, there has been a method of capturing changes in excavation load from the current value of the rotation drive motor of the excavation member and confirming that the pile hole has reached a hard support layer deep in the ground due to this increase in excavation load. It has been proposed (Patent Documents 1 to 3).

しかしながら、回転駆動用モータの電流値から掘削負荷の変化を捉える方法では、掘孔が深くなるに伴い、掘削部材と孔壁との摩擦抵抗が大きくなることで、支持層に達していなくとも掘削負荷が著しく増大したり、掘削部位で滑りが発生することで、逆に支持層に達していても掘削負荷が減少したり、更には作業者の掘削作業の巧拙によっても掘削負荷は大きく変動するから、支持層への到達を確認する指標として信頼性に乏しい。従って、一般的には、専ら施工予定地での試験ボーリングにて得られた地質試料のデータに基づき、所定の深度まで掘孔することで支持層に届いたものとみなすのが普通であるが、施工予定地全体の地下深部が一様な層序で均質であるとは限らず、地歴によっては局所的に支持層の深さが異なったり、支持層自体の硬さの違いが大きかったりすることも多々あるため、個々の杭孔の底部が実際に充分な杭先端の支持力を有するとは言えない。   However, in the method of detecting the change in the excavation load from the current value of the rotation drive motor, the frictional resistance between the excavation member and the hole wall increases as the digging hole becomes deeper, so that the excavation can be performed even if it does not reach the support layer. Excessive increase in load, slippage at the excavation site, conversely, even if the support layer is reached, the excavation load decreases, and the excavation load varies greatly depending on the skill of the operator's excavation work. Therefore, it is poor in reliability as an index for confirming the arrival at the support layer. Therefore, in general, based on the data of the geological sample obtained exclusively by the test boring at the planned construction site, it is usually considered that the material reached the support layer by drilling to a predetermined depth. The underground depth of the entire construction site is not always uniform with a uniform stratigraphy. Depending on the geological history, the depth of the support layer may vary locally, or the difference in hardness of the support layer itself may be large. Since there are many cases, it cannot be said that the bottom of each pile hole actually has a sufficient support force of the pile tip.

そこで、本発明者は先に、杭施工管理方法として、地盤に設定深度の杭孔を形成後、該杭孔内への杭の建て込み前に、杭孔内に貫入試験機を配置して貫入試験を行い、その結果から孔底の支持強度を判定し、その支持強度が所定値以上である場合に該杭孔に杭を建て込むようにすることを提案している(特許文献4)。その貫入試験機は、縦筒状のケーシング内に、該ケーシングの下端から下方突出する貫入軸を一体化したノッキングブロックと、該ノッキングブロックを自由落下によって打撃するドライブハンマーと、落下後のドライブハンマーを吊り上げて所定高さで下放する吊上げ機構とを備えており、着底させた貫入軸が孔底から所定深さまで貫入するのに要する打撃回数(N値)から孔底の支持強度を判定するものであり、国際標準のN値での管理を行えるので測定値の高い信頼評価が得られる。また、本発明者は、このような貫入試験機として、クレーンのワイヤで吊下げて杭孔に出入させる吊下げ式のもの(特許文献5)、アースオーガのスクリューロッドやアースドリルのケリーバ等の掘削ロッドに、その杭孔を掘削後の掘削先部材に代えて連結する掘削ロッド連結式のもの(特許文献6)、アースオーガにおけるスクリューロッドの先端側中空ロッド内やアースドリルにおける軸堀りバケット又は拡底バケットの中空ロッド内に組み込んだ掘削部材の中空ロッド内蔵型のもの(特許文献7)を提案している。   Therefore, the inventor previously arranged a penetration tester in the pile hole as a pile construction management method after forming a pile hole of a set depth in the ground and before laying the pile in the pile hole. It is proposed that a penetration test is performed, the support strength of the hole bottom is determined from the result, and the pile is built in the pile hole when the support strength is a predetermined value or more (Patent Document 4). . The penetration tester includes a knocking block in which a penetration shaft that protrudes downward from the lower end of the casing is integrated in a vertical cylindrical casing, a drive hammer that strikes the knocking block by free fall, and a drive hammer after the fall And a lifting mechanism that lifts and lowers at a predetermined height, and determines the support strength of the hole bottom from the number of impacts (N value) required for the bottomed penetration shaft to penetrate from the hole bottom to a predetermined depth. Therefore, it is possible to manage with the international standard N value, and a high reliability evaluation of the measured value can be obtained. In addition, the present inventor, as such a penetration tester, is a suspended type (Patent Document 5) that is hung with a crane wire to enter and exit a pile hole, a screw rod of an earth auger, a kelly bar of an earth drill, and the like. An excavating rod connection type in which the pile hole is connected to the excavation rod in place of the excavation target member after excavation (Patent Document 6), the inside of the hollow rod on the tip side of the screw rod in the earth auger, or the shaft excavation bucket in the earth drill Alternatively, a hollow rod built-in type drilling member incorporated in a hollow rod of a bottomed bucket (Patent Document 7) has been proposed.

特開平5−280031号公報JP-A-5-280031 特開2000−245058号公報JP 2000-245058 A 特開2003−74045号公報JP 2003-74045 A 特許第5948435号公報Japanese Patent No. 5948435 特願2016−071845号Japanese Patent Application No. 2006-071845 特願2016−078302号Japanese Patent Application No. 2006-07832 特許第5932178号公報Japanese Patent No. 5932178

前記の杭施工管理方法において、杭の建て込み前の貫入試験機による判定で孔底の支持強度が所定値に満たなかった場合、場所を代えて新たに杭孔を形成するか、あるいは杭孔を更に深く掘削し、再度の貫入試験を行うことを、支持強度が所定値以上になるまで繰り返すことになる。しかるに、場所を代えて新たに杭孔を形成することは、建造物の設計変更を要したり、大幅な施工コスト増大や工期延長を招くことから、極めて困難である。従って、支持強度が所定値以上になるまで杭孔を更に深く掘削する方法が現実的であるが、施工現場に搬入されている既製杭は最初の設定した杭孔深度に対応する長さであるため、再掘削で深度が増した杭孔には適用できない。また、これら既製杭として予め長さの種々異なるものを用意することは、コスト面及び作業効率面より無駄が大き過ぎて到底無理である。   In the above-mentioned pile construction management method, if the support strength of the hole bottom does not satisfy the predetermined value as judged by the penetration tester before the pile is built, a new pile hole is formed at a different location, or the pile hole The drilling is further deepened and the re-penetration test is repeated until the support strength becomes a predetermined value or more. However, it is extremely difficult to form a new pile hole at a different location because it requires a change in the design of the building and causes a significant increase in construction cost and construction period. Therefore, it is realistic to excavate the pile hole deeper until the support strength becomes a predetermined value or more, but the ready-made pile carried into the construction site has a length corresponding to the initially set pile hole depth. Therefore, it cannot be applied to pile holes whose depth has been increased by re-digging. In addition, it is impossible to prepare various ready-made piles with different lengths in advance because the cost is too high and the work efficiency is high.

本発明は上述の事情に鑑みて、杭の建て込み前の貫入試験機による判定で孔底の支持強度が所定値に満たなかった場合に、その杭孔の再掘削及び再判定を行い、該支持強度が所定値以上になった段階で杭を建て込むが、深度が増した杭孔に対して再掘削前の深度に対応する既製杭を利用して低コストで能率よく杭施工を行うことを可能とする杭施工管理方法を提供することを目的としている。   In view of the above circumstances, the present invention performs re-excavation and re-determination of the pile hole when the support strength of the hole bottom is less than a predetermined value as determined by the penetration tester before the pile is built, Pile is built when the support strength reaches the specified value or higher, but piles with increased depth should be efficiently built at low cost using ready-made piles corresponding to the depth before re-excavation. The purpose is to provide a pile construction management method that makes it possible.

上記目的を達成するための手段を図面の参照符号を付して示せば、請求項1の発明に係る杭施工管理方法は、地盤Gに設定深度の杭孔H1を形成後、該杭孔H1内への設定深度に相当する杭長さの杭の建て込み前に、縦筒状のケーシング(外側ケーシング)3内に、該ケーシング3の下端から下方突出する貫入軸4を一体化したノッキングブロック51と、該ノッキングブロック51を自由落下によって打撃するドライブハンマー52と、落下後のドライブハンマー52を吊り上げて所定高さで下放する吊上げ機構8とを備えてなる貫入試験機M1〜M3を用い、杭孔H1内に配置させた貫入試験機M1〜M3の貫入軸4を孔底Hb1に着底させ、該貫入軸4が孔底Hb1から所定深さまで貫入するのに要する打撃回数から孔底Hb1の支持強度を判定し、その支持強度が所定値に満たない場合に、該杭孔Hを更に深く再掘削して、再掘削後の孔底Hb2の支持強度を貫入試験機M1〜M3によって同様にして判定し、この際、再掘削の掘削深さを一律とし、且つ、その一律の再掘削深さに対応する長さの同じ杭の複数本を予め用意しておき、一律の掘削深さの再掘削により、該支持強度が所定値以上に達した場合に、元の設定深度に相当する杭長さに対して再掘削による一律の掘削深さの深度増加分の予め用意した長さの杭を継ぎ足し調整した杭を該杭孔H2に建て込む杭施工管理方法であって、
元の設定深度に相当する杭長さの杭本体P1がコンクリート杭であり、前記再掘削による一律の掘削深さの深度増加分に対応する短尺杭部材P2が鋼管杭P2A、P2B又はP2Cあり、
該鋼管杭P2A、P2B又はP2Cは、再掘削による一律の掘削深さに対応する同じ長さの予め容易した複数本の鋼管20と、該鋼管20の上端部に固着され、前記コンクリート杭P1の下端部に固着された鋼製端板12に溶接又は/及びボルト止めされる連結リング部材21とからなり、
コンクリート杭P1の下端部の鋼製端板12に鋼管20の上端部の連結リング部材21を溶接又は/及びボルト止めすることによって、再掘削による一律の掘削深さの深度増加分の予め用意した長さの杭を継ぎ足し調整した杭として、この継ぎ足し調整した杭を再掘削後の杭孔に建て込むことを特徴とする。
If the means for achieving the above-mentioned object is shown with reference numerals in the drawings, the pile construction management method according to the invention of claim 1 will form the pile hole H1 in the ground G after forming the pile hole H1 of the set depth. A knocking block in which a penetrating shaft 4 that protrudes downward from the lower end of the casing 3 is integrated into a longitudinal cylindrical casing (outer casing) 3 before the pile having a pile length corresponding to the set depth is built. 51, a penetration hammer 52 comprising a drive hammer 52 that strikes the knocking block 51 by free fall, and a lifting mechanism 8 that lifts the dropped drive hammer 52 and releases it at a predetermined height. The penetration shaft 4 of the penetration testing machines M1 to M3 arranged in the pile hole H1 is settled on the hole bottom Hb1, and the hole bottom Hb1 is calculated from the number of hits required for the penetration shaft 4 to penetrate from the hole bottom Hb1 to a predetermined depth. Support When the support strength is less than the predetermined value, the pile hole H is re-excavated further deeply, and the support strength of the hole bottom Hb2 after the re-excavation is similarly set by the penetration test machines M1 to M3. In this case, the digging depth of the re-digging is made uniform, and a plurality of piles having the same length corresponding to the uniform digging depth are prepared in advance, and the uniform digging depth is restored. When the support strength reaches a predetermined value or more by excavation, a pile having a length prepared in advance corresponding to the depth increase of the uniform excavation depth by re-excavation with respect to the pile length corresponding to the original set depth is used. A pile construction management method for building a pile that has been added and adjusted in the pile hole H2 ,
The pile body P1 having a pile length corresponding to the original set depth is a concrete pile, and the short pile member P2 corresponding to the depth increase of the uniform excavation depth by the re-excavation is a steel pipe pile P2A, P2B or P2C,
The steel pipe piles P2A, P2B, or P2C are fixed to a plurality of steel pipes 20 having the same length corresponding to a uniform excavation depth by re-excavation and the upper end of the steel pipe 20, and the concrete piles P1 A connecting ring member 21 welded and / or bolted to the steel end plate 12 fixed to the lower end portion;
By welding or / and bolting the connection ring member 21 at the upper end of the steel pipe 20 to the steel end plate 12 at the lower end of the concrete pile P1, a uniform increase in the depth of excavation by re-excavation was prepared in advance. As a pile adjusted by adding a pile of length, the pile adjusted by adding the pile is built in a pile hole after re-excavation .

請求項の発明は、上記請求項の杭施工管理方法において、貫入試験機M1が吊下げ式であり、該貫入試験機M1をクレーンのワイヤWで吊下げて杭孔H1,H2に出入させる構成としている。
The invention according to claim 2 is the pile construction management method according to claim 1 , wherein the penetration testing machine M1 is a suspension type, and the penetration testing machine M1 is suspended by the wire W of the crane to enter and exit the pile holes H1, H2. The configuration is to let

請求項の発明は、上記請求項1又は2の杭施工管理方法において、貫入試験機M2が掘削ロッド連結式であり、杭孔H1,H2を掘削後の掘削先部材(先端ロッド部材Rh,軸堀りバケットB1,拡底バケットB2)に代えて該貫入試験機M2を連結して杭孔H1,H2に出入させる構成としている。
The invention of claim 3 is the pile construction management method according to claim 1 or 2 , wherein the penetration testing machine M2 is a drilling rod connection type, and the drilling tip member (tip rod member Rh, Instead of the shaft-drilling bucket B1 and the widened bucket B2), the penetration testing machine M2 is connected to enter and exit the pile holes H1 and H2.

請求項の発明は、上記請求項1〜3のいずれかの杭施工管理方法において、貫入試験機M3が掘削部材の中空ロッド内蔵型であり、掘削後の杭孔H1,H2内に掘削先部材(先端ロッド部材Rh)を挿入した状態で該貫入試験機M3を作動させて貫入試験を行う構成としている。
According to a fourth aspect of the present invention, in the pile construction management method according to any one of the first to third aspects, the penetration testing machine M3 is a hollow rod built-in type excavation member, and the excavation destination is placed in the pile holes H1 and H2 after excavation. The penetration tester M3 is operated in a state where the member (the tip rod member Rh) is inserted to perform a penetration test.

次に、本発明の効果について、図面の参照符号を付して説明する。まず、請求項1の発明に係る杭施工管理方法では、地盤Gに前記設定深度の杭孔H1を形成後、該杭孔H1内への設定深度に相当する杭長さの杭の建て込み前に、杭孔H1内に配置させた特定の貫入試験機M1〜M3の貫入軸4を孔底Hb1に着底させて孔底Hb1の支持強度を判定するが、その支持強度が所定値に満たない場合に、該杭孔H1を更に深く再掘削し、再掘削後の孔底Hb2の支持強度を貫入試験機M1〜M3で同様にして判定し、該支持強度が所定値以上に達した場合に、元の設定深度に相当する杭長さに対して再掘削による深度増加分の長さを継ぎ足し調整した杭を該杭孔H2に建て込むようにしている。従って、この杭施工管理方法によれば、掘削した設定深度の杭孔H1の孔底Hb1の支持強度が不足しても、場所を代えて新たに杭孔を形成する必要はなく、同じ杭孔H1の再掘削と再判定を行うことで対応できるから、建造物の設計変更、大幅な施工コスト増大や工期延長等を回避できる上、設定深度の杭孔H1用として予め準備している既製杭Pを杭本体P1として長さ不足分だけ簡単に継ぎ足す形で利用できるから、資材コストが嵩まず、且つ能率よく杭の建て込み作業を行える。なお、再掘削と再判定は、所定値以上の支持強度が得られるまで繰り返し行える。
この際、再掘削の掘削深さを一律とし、且つ、その掘削深さに対応する長さの同じ杭の複数本を予め用意しているため、再掘削が必要になった時に迅速に対応できる。
Next, effects of the present invention will be described with reference numerals in the drawings. First, in the pile construction management method according to the invention of claim 1, after the pile hole H1 having the set depth is formed in the ground G, before the pile having a pile length corresponding to the set depth in the pile hole H1 is built. In addition, the penetration shaft 4 of a specific penetration testing machine M1 to M3 arranged in the pile hole H1 is grounded to the hole bottom Hb1 to determine the support strength of the hole bottom Hb1, but the support strength satisfies a predetermined value. When the pile hole H1 is re-excavated further deeply, the support strength of the hole bottom Hb2 after the re-excavation is similarly determined by the penetration test machines M1 to M3, and the support strength reaches a predetermined value or more. In addition, a pile that is adjusted by adding the length of the depth increase by re-excavation to the pile length corresponding to the original set depth is built in the pile hole H2. Therefore, according to this pile construction management method, even if the supporting strength of the hole bottom Hb1 of the excavated set depth of the pile hole H1 is insufficient, it is not necessary to form a new pile hole by changing the place, and the same pile hole Since it can respond by performing re-excavation and re-determination of H1, it is possible to avoid design changes of buildings, significant construction cost increase, construction period extension, etc., and ready-made piles prepared in advance for pile holes H1 with a set depth Since P can be used as a pile body P1 by simply adding only the shortage of the length, the material cost is low and the pile can be built efficiently. The re-digging and re-determination can be repeated until a support strength of a predetermined value or more is obtained.
At this time, since the excavation depth of the re-excavation is uniform and a plurality of piles having the same length corresponding to the excavation depth are prepared in advance, it is possible to respond quickly when re-excavation becomes necessary. .

又、本発明によれば、既製杭の施工において、再掘削で深くなった杭孔H2に対し、元の設定深度の杭孔H1に対応する長さの杭本体P1に短尺杭部材P2を継ぎ足し連結した杭PAを建て込むから、再掘削の一律の掘削深さを短尺杭部材P2の長さに対応させることにより、同じ寸法形状の短尺杭部材P2を利用して一律な杭施工管理を行える。
In addition, according to the present invention , the short pile member P2 is added to the pile body P1 having a length corresponding to the pile hole H1 having the original set depth with respect to the pile hole H2 deepened by re-excavation in the construction of the ready-made pile. Since the connected pile PA is built, by making the uniform excavation depth of re-excavation correspond to the length of the short pile member P2, uniform pile construction management can be performed using the short pile member P2 of the same size and shape. .

更に、本発明によれば、コンクリート杭からなる杭本体P1に対し、その下端に短尺杭部材P2としての鋼管20を継ぎ足し連結するから、その継ぎ足し連結の作業を容易に迅速に行える。また、該鋼管20の鋼管原材として長尺のものを用意しておけば、この鋼管原材から杭孔H1の再掘削による深度増加に対応する長さ分を切り取って該鋼管杭P2A、P2B又はP2C2に利用できる。
Furthermore, according to the present invention , since the steel pipe 20 as the short pile member P2 is added and connected to the lower end of the pile main body P1 made of concrete piles, the connecting and connecting work can be easily and quickly performed. Further, by preparing those long as steel raw material of the steel pipe 20, steel pipe piles P2A cut lengths fraction corresponding from the steel raw material in the depth increases by re-drilling Kuiana H1, P2B Or it can be used for P2C2 .

請求項の発明によれば、貫入試験機M1が吊下げ式であるから、クレーンのワイヤWで吊下げて杭孔H1,H2に能率よく出入操作できると共に、該貫入試験機Mを容易に製作できるという利点がある。
According to the invention of claim 2 , since the penetration testing machine M1 is a suspension type, it can be efficiently moved in and out of the pile holes H1, H2 by being suspended by the crane wire W, and the penetration testing machine M can be easily operated. There is an advantage that it can be manufactured.

請求項の発明によれば、貫入試験機M2が掘削ロッド連結式であるから、杭孔H1,H2の掘削に用いたアースオーガAAのスクリューロッドRsやアースドリル機ADのケリーバK等を利用して、その掘削先部材(先端ロッド部材Rh,軸堀りバケットB1,拡底バケットB2)に代えて該貫入試験機M2を連結することで、杭孔H1,H2に能率よく出入操作できると共に、該貫入試験機M2を容易に製作できるという利点がある。
According to the invention of claim 3 , since the penetration testing machine M2 is of the excavating rod connection type, the screw rod Rs of the earth auger AA used for excavation of the pile holes H1 and H2, the kelly bar K of the earth drilling machine AD, etc. are used. Then, by connecting the penetration testing machine M2 instead of the excavation tip member (the tip rod member Rh, the shaft excavation bucket B1, the bottom expansion bucket B2), the pile hole H1, H2 can be efficiently moved in and out, There is an advantage that the penetration tester M2 can be easily manufactured.

請求項の構成によれば、貫入試験機M3が掘削部材の中空ロッド内蔵型であり、杭孔H1,H2を掘削した掘削部材、例えばアースオーガAAのスクリューロッドRs、アースドリル機ADのケリーバKに連結した軸堀りバケットB1や拡底バケットB2等を該杭孔H1,H2から抜出することなく、引き続いて貫入試験による孔底Hb1,Hb2の支持強度の判定を行えるから、杭施工の途中に貫入試験工程を挟むにも関わらず作業能率が非常に良好となる。 According to the configuration of the fourth aspect , the penetration testing machine M3 is a hollow rod built-in type of excavation member, and excavation members excavating the pile holes H1, H2, for example, the screw rod Rs of the earth auger AA, the kelly bar of the earth drill machine AD. Since the shaft excavation bucket B1 and the bottom expansion bucket B2 etc. connected to K can be continuously extracted from the pile holes H1 and H2, the support strength of the hole bottoms Hb1 and Hb2 can be determined by the penetration test. Despite having a penetration test process in the middle, work efficiency is very good.

本発明の杭施工管理方法に用いる吊下げ式の貫入試験機の一例を示す全体の斜視図である。It is the whole perspective view which shows an example of the suspension type penetration testing machine used for the pile construction management method of this invention. 同貫入試験機の内部を示し、(a)は縦断正面図、(b)は(a)のX−X線の矢視断面図である。The inside of the penetration testing machine is shown, (a) is a longitudinal front view, (b) is a cross-sectional view taken along line XX of (a). 同貫入試験機におけるハンマーケーシングの内部を示し、(a)は落下位置にあるドライブハンマーを吊上げ機構のクランプ部でドライブハンマーを把持した状態、(b)は吊上げ機構によって上限位置へ持ち上げたドライブハンマーを開放した状態、のそれぞれ縦断正面図である。The inside of the hammer casing in the penetration tester is shown, (a) is a state in which the drive hammer in the fall position is gripped by the clamp part of the lifting mechanism, (b) is a drive hammer lifted to the upper limit position by the lifting mechanism It is a vertical front view of each in the state which opened. 同貫入試験機による貫入試験操作を示し、(a)貫入試験機を杭孔内に着底させた状態、(b)は貫入軸を孔底に貫入させた状態、のそれぞれ縦断正面図である。The penetration test operation by the penetration test machine is shown, (a) a state where the penetration test machine is bottomed in the pile hole, (b) is a longitudinal front view of the state where the penetration shaft is penetrated into the hole bottom. . 同貫入試験機を用いたプレボーリング工法による杭施工において、貫入試験による孔底の支持強度が所定値以上であった場合の工程を(a)〜(g)の順に示す概略縦断面図である。It is a schematic longitudinal cross-sectional view which shows the process when the support strength of the hole bottom by a penetration test is more than predetermined value in the pile construction by the pre-boring method using the penetration testing machine in order of (a)-(g). . 同プレボーリング工法による杭施工において、貫入試験による孔底の支持強度が所定値未満であった場合の貫入試験以降の工程を(a)〜(f)の順に示す概略縦断面図である。In pile construction by the pre-boring method, it is a schematic longitudinal cross-sectional view which shows the process after a penetration test when the support strength of the hole bottom by a penetration test is less than predetermined value in order of (a)-(f). 同プレボーリング工法で用いるPHC杭を示し、(a)は下部の正面図、(b)は下部の縦断面図、(c)は底面図である。The PHC pile used by the pre-boring method is shown, (a) is a front view of the lower part, (b) is a longitudinal sectional view of the lower part, and (c) is a bottom view. 同PHC杭に対する第一構成例の鋼管杭の継ぎ足し連結を示し、(a)は連結前の分解斜視図、(b)は連結後の正面図、(c)は連結部の縦断面図である。The steel pipe pile addition connection of the 1st structural example with respect to the PHC pile is shown, (a) is an exploded perspective view before connection, (b) is a front view after connection, (c) is a longitudinal cross-sectional view of a connection part. . 同鋼管杭の下端部構造を示し、(a)は下端板が外嵌型である縦断面図、(b)は下端板が内嵌型である縦断面図である。The lower end part structure of the steel pipe pile is shown, (a) is a longitudinal cross-sectional view in which the lower end plate is an external fitting type, and (b) is a longitudinal sectional view in which the lower end plate is an internal fitting type. 同PHC杭に対する第二構成例の鋼管杭の継ぎ足し連結を示し、(a)は連結前の分解斜視図、(b)は連結後の正面図である。The joint connection of the steel pipe pile of the 2nd structural example with respect to the PHC pile is shown, (a) is an exploded perspective view before connection, (b) is a front view after connection. 同PHC杭に対する第三構成例の鋼管杭の継ぎ足し連結を示し、(a)は連結前の分解斜視図、(b)は連結後の正面図、(c)は連結部の縦断面図である。The steel pipe pile addition connection of the 3rd structural example with respect to the PHC pile is shown, (a) is an exploded perspective view before connection, (b) is a front view after connection, (c) is a longitudinal cross-sectional view of a connection part. . 継ぎ足し用鋼管杭の変形例を示し、(a)は外周にスクリュー羽根を設けた鋼管、(b)は外周に一定間隔置きに環状羽根を設けた鋼管、のそれぞれ正面図である。The modification of the steel pipe pile for extension is shown, (a) is each a front view of the steel pipe which provided the screw blade | wing on the outer periphery, (b) is the steel pipe which provided the annular blade | wing on the outer periphery at regular intervals. プレボーリング工法に用いるアースオーガを示し、(a)は全体の側面図、(b)はスクリューロッドに掘削ロッド連結式の貫入試験機を連結した状態の要部の側面図である。The earth auger used for a pre-boring method is shown, (a) is a whole side view, (b) is a side view of the principal part of the state which connected the drill rod connection type penetration test machine to the screw rod. ケリーバ式アースドリル機を示し、(a)は全体の側面図、(b)はケリーバに掘削ロッド連結式の貫入試験機を連結した状態の要部の側面図である。FIG. 2 shows a kelly bar type earth drill machine, in which (a) is a side view of the whole, and (b) is a side view of a main part in a state where a drill rod connecting type penetration tester is connected to the kelly bar. 中空ロッド内蔵型の貫入試験機を組み込んだアースオーガ用スクリューロッドの先端ロッド部材を示し、(a)は掘削時、(b)は試験準備時、(c)は試験開始時のそれぞれ縦断側面図である。The end rod member of a screw rod for earth auger incorporating a hollow rod built-in penetration tester is shown, (a) at the time of excavation, (b) at the time of test preparation, and (c) at the start of the test. It is. 中空ロッド内蔵型の貫入試験機を用いたプレボーリング工法による杭施工において、貫入試験による孔底の支持強度が所定値以上であった場合の工程を(a)〜(g)の順に示す概略縦断面図である。In pile construction by pre-boring method using a hollow rod built-in type penetration tester, a schematic longitudinal section showing the steps in the order of (a) to (g) when the support strength of the hole bottom by the penetration test is greater than or equal to a predetermined value. FIG. 同プレボーリング工法による杭施工において、貫入試験による孔底の支持強度が所定値未満であった場合の貫入試験以降の工程を(a)〜(f)の順に示す概略縦断面図である。In pile construction by the pre-boring method, it is a schematic longitudinal cross-sectional view which shows the process after a penetration test when the support strength of the hole bottom by a penetration test is less than predetermined value in order of (a)-(f).

以下に、本発明に係る杭施工管理方法の実施形態について、図面を参照して具体的に説明する。なお、各実施形態において共通する構成部分には同一符号を附している。   Below, the embodiment of the pile construction management method concerning the present invention is described concretely with reference to drawings. In addition, the same code | symbol is attached | subjected to the component which is common in each embodiment.

図1〜図4は、本発明の杭施工管理方法で使用する貫入試験機の一例である吊下げ式の貫入試験機M1を示す。この貫入試験機M1は、図1及び図2に示すように、縦筒状の外側ケーシング3内に筒状のハンマーケーシング5が昇降自在に装填されており、外側ケーシング3の上側テーパーキャップ31に設けた上端側開口部31aから棒軸状の吊支部材6が、同下側テーパーキャップ32に設けた下端側開口部32aから貫入軸4が各々垂直に突出すると共に、上端側開口部31aの周囲の筒口部31bと吊支部材6の上部との間、ならびに下端側開口部32aの周囲の筒口部32bと貫入軸4の中間部との間に、これら上端側開口部31a及び下端側開口部32aを外部に対して封止するベローズ筒体7A,7Bがそれぞれ装着されている。また、外側ケーシング3の下部には、上下の径大のパイプリング33a,33bを複数本(図では4本)のパイプ支柱33cで連結した支脚33が、下側パイプリング33bを外側ケーシング3の下端より低位とするように、上部側で放射状に配置するブラケット33dを介して固設されている。   1 to 4 show a penetrating penetration testing machine M1 which is an example of a penetration testing machine used in the pile construction management method of the present invention. As shown in FIGS. 1 and 2, the penetration testing machine M 1 has a cylindrical hammer casing 5 mounted in a vertically cylindrical outer casing 3 so as to be movable up and down, and is attached to an upper taper cap 31 of the outer casing 3. The rod-like suspension member 6 projects vertically from the provided upper end opening 31a, and the penetrating shaft 4 projects vertically from the lower end opening 32a provided in the lower taper cap 32, while the upper end opening 31a The upper end opening 31a and the lower end opening are provided between the surrounding tube opening 31b and the upper portion of the suspension member 6, and between the tube opening 32b around the lower end opening 32a and the intermediate portion of the penetrating shaft 4. Bellows cylinders 7A and 7B for sealing the portion 32a to the outside are mounted, respectively. Further, at the lower part of the outer casing 3, a support leg 33 in which upper and lower large-diameter pipe rings 33 a and 33 b are connected by a plurality of (four in the figure) pipe columns 33 c, and the lower pipe ring 33 b is connected to the outer casing 3. It is fixed via brackets 33d arranged radially on the upper side so as to be lower than the lower end.

そして、この杭孔用貫入試験装置M1では、クローラクレーンのブーム等より垂下するワイヤ(図示省略)の下端に吊持したフックHoに対し、吊支部材6の上端に連結した吊り金具61に通したワイヤ製の掛け輪62を掛けることにより、装置全体を吊り下げて杭孔H(図4参照)に対する入出を行う一方、杭孔Hへの着底時に装置全体が支脚33によって直立姿勢を保つようになっている。   In this penetration test apparatus M1 for pile holes, the hook Ho suspended at the lower end of a wire (not shown) suspended from the boom or the like of a crawler crane is passed through a suspension fitting 61 connected to the upper end of the suspension support member 6. By hanging the hanging ring 62 made of the wire, the entire apparatus is suspended to enter and exit the pile hole H (see FIG. 4), while the entire apparatus maintains an upright posture by the support legs 33 when the pile hole H is settled. It is like that.

吊支部材6は、図2(a)で示すように、下端を枢支ピン63を介してハンマーケーシング5の上端に枢着連結しているが、外側ケーシング3の内側に位置する中間部に円形フランジ状のストッパー60が設けてあり、このストッパー60を介して装置吊下げ時の外側ケーシング3を上側テーパーキャップ31の内側において支承するように構成されている。そして、この装置吊下げ状態では、貫入軸4の先端が支脚33の下端つまり下側のパイプリング33bに対して同レベルもしくは若干高位になるように設定されている。また、図2(a)(b)で示すように、外側ケーシング3の内周には、上下方向に沿う平行2条の凸条より構成されるガイドレール33が周方向複数箇所(図では4カ所)に等配形成され、ハンマーケーシング5の外周の上下部に突設した嵌合キー53が各ガイドレール33に摺動自在に嵌合している。なお、貫入軸4は、鋼製であって先端が開口した筒軸状をなすが、地質試料を採取できるように、先端側がシューと二つ割り可能なスプリットバーレル(図示省略)より構成されるサンプラー41になっている。   As shown in FIG. 2A, the suspension support member 6 has a lower end pivotally connected to the upper end of the hammer casing 5 via a pivot pin 63, but is attached to an intermediate portion located inside the outer casing 3. A circular flange-like stopper 60 is provided, and the outer casing 3 when the apparatus is suspended is supported on the inner side of the upper taper cap 31 via the stopper 60. And in this apparatus suspended state, the front-end | tip of the penetration shaft 4 is set so that it may become the same level or a slightly high position with respect to the lower end of the support leg 33, ie, the lower side pipe ring 33b. As shown in FIGS. 2 (a) and 2 (b), guide rails 33 constituted by two parallel strips along the vertical direction are provided on the inner periphery of the outer casing 3 at a plurality of locations in the circumferential direction (4 in the figure). The fitting keys 53 are formed at equal positions at the upper and lower portions of the outer periphery of the hammer casing 5 and are slidably fitted to the guide rails 33. The penetrating shaft 4 is made of steel and has a cylindrical shaft shape with an open front end. However, a sampler 41 composed of a split barrel (not shown) whose front end side can be divided into two so that a geological sample can be collected. It has become.

更に、外側ケーシング3の内側上部には取付板34が固設されており、この取付板34の下面側とハンマーケーシング5の上端との間に、ハンマーケーシング5内の後述する油圧シリンダー80(図3参照)に対する作動油の給排路を構成する二重管式の2本の伸縮配管81,81が介装されている。また、該取付板34の下面側には、外側ケーシング3に対するハンマーケーシング5の下降量を計測するエンコーダー9が取り付けられ、該エンコーダー9から延出する計測コード9aがハンマーケーシング5の上端に止着されている。そして、外側ケーシング3の取付板34と上側テーパーキャップ31との間には、各伸縮配管81の上端側に接続する油圧ホースhと、エンコーダー8用の電気配線eが配設されている。なお、上側テーパーキャップ31には上端側開口部31aの両側にホース接続用の筒軸部31cが上方へ突設されており、両筒軸部31c,31cに外部の油圧供給源(図示省略)に繋がる油圧ホースh1,h2がアダプタaを介して接続され、その一方の油圧ホースh2は二重構造の間にエンコーダー9用の電気配線eを挿通させている。また、取付板34の中央には透孔34aが形成され、吊支部材6が該透孔34aを貫通している。   Further, a mounting plate 34 is fixed on the inner upper portion of the outer casing 3, and a hydraulic cylinder 80 (described later) in the hammer casing 5 is provided between the lower surface side of the mounting plate 34 and the upper end of the hammer casing 5. 2), two double-pipe expansion and contraction pipes 81 and 81 constituting the hydraulic oil supply / discharge path are interposed. An encoder 9 for measuring the descending amount of the hammer casing 5 with respect to the outer casing 3 is attached to the lower surface side of the mounting plate 34, and a measurement cord 9 a extending from the encoder 9 is fixed to the upper end of the hammer casing 5. Has been. Between the attachment plate 34 of the outer casing 3 and the upper taper cap 31, a hydraulic hose h connected to the upper end side of each telescopic pipe 81 and an electrical wiring e for the encoder 8 are disposed. The upper taper cap 31 is provided with hose connecting cylindrical shaft portions 31c projecting upward on both sides of the upper end opening portion 31a, and external hydraulic pressure supply sources (not shown) are provided on both cylindrical shaft portions 31c and 31c. Are connected via an adapter a, and one hydraulic hose h2 has an electrical wiring e for the encoder 9 inserted between the double structures. Further, a through hole 34a is formed in the center of the mounting plate 34, and the suspension support member 6 passes through the through hole 34a.

上下のベローズ筒体7A,7Bは、ゴムや半硬質合成樹脂等の可撓性材料によって全体的に同径の蛇腹状に形成されており、外側ケーシング3内でのハンマーケーシング5の昇降に伴い、一方が伸長するのに対応して他方が収縮する。しかして、両ベローズ筒体7A,7Bは共に、伸長時に細長い筒形になるが、水圧で押し潰されるのを防ぐために、内側には各襞(谷部)ごとに保形用の金属リング71が嵌装されている。また、これらベローズ筒体7A,7Bの両端部は、上下のテーパーキャップ31,32の筒口部31b,32bならびに吊支部材6及び貫入軸4に対し、締結バンドの如き留め具72によって液密に止着されている。   The upper and lower bellows cylinders 7A and 7B are formed in a bellows shape having the same diameter as a whole by a flexible material such as rubber or semi-rigid synthetic resin, and the hammer casing 5 moves up and down in the outer casing 3. The other contracts in response to one stretching. Thus, both the bellows cylinders 7A and 7B are formed into an elongated cylindrical shape when extended, but in order to prevent being crushed by water pressure, a metal ring 71 for shape retention is provided on the inner side for each ridge (valley). Is fitted. Further, both end portions of the bellows cylinders 7A and 7B are liquid-tight with respect to the cylinder opening portions 31b and 32b of the upper and lower taper caps 31 and 32, the suspension member 6 and the penetrating shaft 4 by a fastener 72 such as a fastening band. It is fastened.

ハンマーケーシング5は、図3に示すように、下端にノッキングブロック51が固着され、内部に該ノッキングブロック51を自由落下によって打撃するドライブハンマー52と、落下後のドライブハンマー52を吊り上げて所定高さで下放する吊上げ機構8とを内蔵しており、該ノッキングブロック51の下面に貫入軸4が上端の円板部4aで固着している。その吊上げ機構8は、油圧シリンダー80の伸縮ロッド80aの先端部に固着した下向き二股状の枢支枠82に、一対のクランプアーム83,83が垂直面内で揺動自在に枢着されると共に、該油圧シリンダー80の下端外周部に、下向きに開口して内周下部を下方へ拡大する環状テーパー面84aとする短円筒状の把持解除筒84が固着されている。また、各クランプアーム83は、各下端に内向きの係止爪83aを備え、上端部の外面側が上方斜めの傾斜面83bになっている。そして、両クランプアーム83,83は、相互の対向する上端部間に介在するコイルスプリング85により、互いの係止爪83a,83aが接近する閉方向に付勢されている。なお、吊上げ機構8の油圧シリンダー80から導出する2本の油圧ホースh,hは、各々上側の伸縮配管81に接続している。一方、ドライブハンマー52の上面中央には、頂部を径大の裁頭円錐部52bとする係止軸52aが植設されている。   As shown in FIG. 3, the hammer casing 5 has a knocking block 51 fixed to the lower end, a drive hammer 52 that strikes the knocking block 51 by free fall inside, and a drive hammer 52 that has been dropped is lifted to a predetermined height. And a lifting mechanism 8 that is released at the bottom, and the penetrating shaft 4 is fixed to the lower surface of the knocking block 51 by a disc portion 4a at the upper end. The lifting mechanism 8 includes a pair of clamp arms 83, 83 pivotally mounted on a vertically bifurcated pivot support frame 82 fixed to the distal end of the telescopic rod 80 a of the hydraulic cylinder 80. A short cylindrical gripping release tube 84 is fixed to the outer peripheral portion of the lower end of the hydraulic cylinder 80 as an annular tapered surface 84a that opens downward and expands the lower portion of the inner periphery downward. Each clamp arm 83 is provided with an inwardly engaging claw 83a at each lower end, and an outer surface side of the upper end portion is an upward inclined surface 83b. The clamp arms 83 and 83 are urged in the closing direction in which the locking claws 83a and 83a approach each other by a coil spring 85 interposed between upper ends facing each other. Note that the two hydraulic hoses h and h led out from the hydraulic cylinder 80 of the lifting mechanism 8 are connected to the upper expansion pipe 81, respectively. On the other hand, in the center of the upper surface of the drive hammer 52, a locking shaft 52a having a top portion having a large truncated cone portion 52b is implanted.

この吊上げ機構8では、ハンマーケーシング5内でドライブハンマー52が落下位置にあるとき、油圧シリンダー80のピストンロッド80aを伸長させることにより、図3(a)で示すように、両クランプアーム83,83の係止爪83a,83aのテーパ面がドライブハンマー52の係止軸52aの裁頭円錐部52bに接触し、傾斜誘導作用によって両クランプアーム83,83がコイルスプリング85の付勢に抗して開くことで、両係止爪83a,83aが裁頭円錐部52bの下側に係合する。そして、この係合状態でピストンロッド80aを収縮作動させることで、ドライブハンマー5を把持して吊り上げるが、ピストンロッド80aが上限位置まで来た際に、図3(b)に示すように、両クランプアーム83,83の上端部の傾斜面83b,83bが把持解除筒84のテーパ面84aに接触し、傾斜誘導作用によって両クランプアーム83,83がコイルスプリング85の付勢に抗して強制的に開くため、把持解除されたドライブハンマー52が自由落下してハンマーケーシング5の底端のノッキングブロック51を打撃し、その打撃力によってハンマーケーシング5が下動し、それだけ貫入軸4が下がることになる。   In the lifting mechanism 8, when the drive hammer 52 is in the dropping position in the hammer casing 5, the piston rod 80 a of the hydraulic cylinder 80 is extended to extend both clamp arms 83, 83 as shown in FIG. The taper surfaces of the locking claws 83a and 83a come into contact with the truncated cone portion 52b of the locking shaft 52a of the drive hammer 52, and both the clamp arms 83 and 83 resist the biasing force of the coil spring 85 by the tilt induction action. By opening, both locking claws 83a, 83a engage with the lower side of the truncated cone portion 52b. In this engaged state, the piston rod 80a is contracted to hold and lift the drive hammer 5. When the piston rod 80a reaches the upper limit position, as shown in FIG. The inclined surfaces 83b and 83b at the upper ends of the clamp arms 83 and 83 come into contact with the tapered surface 84a of the grip release cylinder 84, and both the clamp arms 83 and 83 are forcibly resisted against the bias of the coil spring 85 by the inclination inducing action. Therefore, the released drive hammer 52 falls freely and strikes the knocking block 51 at the bottom end of the hammer casing 5, and the hammer casing 5 is moved downward by the impact force, and the penetrating shaft 4 is lowered accordingly. Become.

従って、この貫入試験機M1は、クローラクレーンのブーム等を介してワイヤで吊り下げ、図4(a)に示すように地盤Gに穿設した杭孔H内に挿入して着底させ、吊り下げていたワイヤを弛緩させて自立させることにより、外側ケーシング内のハンマーケーシング2が自重降下し、貫入軸4の先端が孔底Hbに接当する。そして、この状態で該貫入試験機M1を駆動して、前記ドライブハンマー52による打撃を繰り返すことにより、図4(b)で示すように貫入軸4が孔底Hbの地盤に貫入してゆくから、該貫入軸4が孔底Hbから所定深さまで貫入するのに要する打撃回数を計測し、その打撃回数に基づいて杭底Hbの地盤の支持強度が所定値以上であるか否かを判定できる。   Therefore, this penetration testing machine M1 is hung with a wire via a boom of a crawler crane, inserted into a pile hole H drilled in the ground G as shown in FIG. By loosening and lowering the wire that has been lowered, the hammer casing 2 in the outer casing is lowered by its own weight, and the tip of the penetrating shaft 4 comes into contact with the hole bottom Hb. In this state, the penetration testing machine M1 is driven, and the impact by the drive hammer 52 is repeated, so that the penetration shaft 4 penetrates into the ground of the hole bottom Hb as shown in FIG. 4 (b). The number of impacts required for the penetration shaft 4 to penetrate from the hole bottom Hb to a predetermined depth is measured, and it can be determined whether or not the support strength of the ground of the pile bottom Hb is greater than or equal to a predetermined value based on the number of impacts. .

ドライブハンマー52の打撃回数(N値)は油圧シリンダー80の作動を司る地上側の油圧駆動制御装置(図示省略)によってカウントされ、孔底地盤への貫入軸4の貫入量はハンマーケーシング5の下降量としてエンコーダー9で計測される。そして、エンコーダー9による計測信号は、電気配線eを通して地上の自動計測装置(図示省略)に送られ、1打撃当たりの沈下量つまり貫入軸4の地盤Gに対する貫入量及び累計貫入量が打撃回数(N値)と共に記録・表示される。なお、JIS A 1219で規定される標準貫入試験では、質量63.5±0.5kgのドライブハンマーを76±1cm自由落下させてノッキングブロックを打撃し、外径51±1mm,内径35±1mmの貫入軸が地盤に30cm貫入するのに要する打撃回数をN値として表すから、この貫入試験機M1でも上記標準貫入試験に準拠して支持強度をN値として掌握すればよい。   The number of hits (N value) of the drive hammer 52 is counted by a hydraulic drive control device (not shown) on the ground side that controls the operation of the hydraulic cylinder 80, and the penetration amount of the penetration shaft 4 into the hole bottom ground is the descent of the hammer casing 5. The quantity is measured by the encoder 9. Then, the measurement signal from the encoder 9 is sent to an automatic measuring device (not shown) on the ground through the electric wiring e, and the amount of subsidence per hit, that is, the penetration amount and the total penetration amount of the penetration shaft 4 with respect to the ground G are the number of hits ( N value) is recorded and displayed. In the standard penetration test stipulated in JIS A 1219, a drive hammer having a mass of 63.5 ± 0.5 kg is freely dropped by 76 ± 1 cm, and the knocking block is hit, and the outer diameter is 51 ± 1 mm and the inner diameter is 35 ± 1 mm. Since the number of impacts required for the penetration shaft to penetrate 30 cm into the ground is expressed as an N value, the penetration strength tester M1 may hold the support strength as the N value in accordance with the standard penetration test.

上記吊下げ式の貫入試験機M1を用いた杭施工管理方法として、まずプレボーリング工法による第一実施形態の杭施工について、図5及び図6で示す工程順に説明する。この杭施工では、図5(a):三点式杭打機等のリーダ(図示省略)に沿って昇降するオーガーマシンAにスクリューロッドRsを取り付け、該スクリューロッドRsを回転駆動しつつ下降させることによって地盤Gを掘削し、同(b):想定される地下深部の支持層Ghに達する深さの杭孔H1を形成したのち、同(c):スクリューロッドRsを引き上げつつ、ソイルセメント等の根固め液Lsを注入し、同(d):続いて孔周固定液Lfを杭孔Hの上部まで注入し、該スクリューロッドRsを抜出したのち、同(e):前記三点式杭打機や別のクレーン等のワイヤWで吊り下げた貫入試験機M1を杭孔H1内へ挿入して孔底Hb1に着底させ、ワイヤWの弛緩状態で前述した杭底地盤の支持強度を測定する。そして、該支持強度が所定値以上であれば、同(f):オーガーマシンAに連結用ロッドRjを介してPHC杭やPRC杭の如き既製杭Pを取り付け、この既製杭Pを杭孔H1に挿入し、同(g):該杭孔H1の底まで埋め込んで既製杭Pの建て込みを完了する。   As a pile construction management method using the penetrating penetration tester M1, the pile construction according to the first embodiment by the pre-boring method will be described in the order shown in FIGS. In this pile construction, a screw rod Rs is attached to an auger machine A that moves up and down along a leader (not shown) such as a three-point pile driver, and the screw rod Rs is lowered while being driven to rotate. After excavating the ground G, (b): after forming a pile hole H1 with a depth reaching the support layer Gh in the deep underground, the same (c): Roots of soil cement etc. while lifting the screw rod Rs (D): Subsequently, the hole periphery fixing liquid Lf is injected up to the top of the pile hole H, the screw rod Rs is extracted, and then (e): the three-point pile driver or the like The penetration test machine M1 suspended by a wire W such as a crane is inserted into the pile hole H1 and settled on the hole bottom Hb1, and the support strength of the above-mentioned pile bottom ground is measured in the relaxed state of the wire W. If the supporting strength is equal to or greater than a predetermined value, the same (f): a ready-made pile P such as a PHC pile or a PRC pile is attached to the auger machine A via a connecting rod Rj, and the ready-made pile P is attached to the pile hole H1. (G): The bottom of the pile hole H1 is buried to complete the construction of the ready-made pile P.

しかるに、例えば図6(a)で示すように、地下深部の支持層Ghが当初の想定よりも深い位置にあり、杭孔H1が該支持層Ghに達していないこと等で、前記貫入試験機M1にて測定した杭底地盤の支持強度が所定値に満たなかった場合には、本発明の杭施工管理方法を適用する。すなわち、貫入試験機M1を抜出した杭孔H1に対し、図6(b):再びスクリューロッドRsを挿入して掘削することにより、より深い杭孔H2を形成することになるが、この際、この再掘削の深い杭孔H2の再掘削深さは一律になっており、この一律の掘削深さの掘削孔H2を形成したのち、該スクリューロッドRsを引上げつつ根固め液Lsを追加注入し、同(c):再掘削後の杭孔H2に再びワイヤWで吊り下げた貫入試験機M1を挿入して着底させ、前記同様にして杭底地盤の支持強度を測定する。そして、該一律の切削深さの杭孔H2が当初の想定より深い位置にあった支持層Ghに達していること等で、該支持強度が所定値以上であれば、同(d):当初想定の杭孔H1用の既製杭Pを杭本体P1として、該杭本体P1に、一律の再深さの杭孔H2に対応した一律の長さの短尺杭部材P2を継ぎ足し連結した既製杭PAを用い、同(e):再掘削後の杭孔H2に前記同様にして該既製杭PAを挿入し、同(f):該杭孔H2の底まで埋め込んで既製杭PAの建て込みを完了する。   However, for example, as shown in FIG. 6 (a), the penetration tester has a structure in which the support layer Gh in the deep underground is deeper than originally assumed and the pile hole H1 does not reach the support layer Gh. When the support strength of the pile bottom ground measured at M1 is less than a predetermined value, the pile construction management method of the present invention is applied. That is, for the pile hole H1 extracted from the penetration testing machine M1, FIG. 6 (b): a deeper pile hole H2 is formed by inserting the screw rod Rs again and excavating, The re-drilling depth of this deep excavation pile hole H2 is uniform, and after forming the excavation hole H2 of this uniform excavation depth, the root-setting liquid Ls is additionally injected while pulling up the screw rod Rs. (C): The penetration test machine M1 suspended by the wire W is inserted again into the pile hole H2 after re-excavation and settled, and the support strength of the pile bottom ground is measured in the same manner as described above. And if this support strength is more than predetermined value by the pile hole H2 of this uniform cutting depth having reached the support layer Gh which was in a deeper position than originally assumed, etc., (d): A ready-made pile PA in which a ready-made pile P for an assumed pile hole H1 is used as a pile body P1, and a short pile member P2 having a uniform length corresponding to the pile hole H2 having a uniform depth is added to the pile body P1. (E): Insert the ready-made pile PA into the pile hole H2 after re-excavation in the same manner as described above. (F): Complete the construction of the ready-made pile PA by embedding it to the bottom of the pile hole H2. To do.

なお、この再掘削後の杭孔H2でも測定した杭底地盤の支持強度が所定値に満たなかった場合は、該支持強度が所定値以上になるまで同様の再掘削と再測定を繰り返せばよい。ただし、その繰り返しには当然にコスト及び時間の両面から限度があるため、通常、数回程度の再掘削・再測定で支持強度不足であれば、その場所は杭施工に不適と判断して施工位置を変更することになる。   In addition, when the support strength of the pile bottom ground measured also in this pile hole H2 after re-excavation does not satisfy a predetermined value, the same re-excavation and re-measurement may be repeated until the support strength becomes a predetermined value or more. . However, the repetition of this is naturally limited in terms of both cost and time. Therefore, if the support strength is usually insufficient after several re-excavations and re-measurements, the site is considered unsuitable for pile construction. The position will be changed.

再掘削後の杭孔H2に挿入する既製杭PAは、上述のように当初想定の杭孔H1に対応する既製杭Pを杭本体P1とし、この杭本体P1に短尺杭部材P2を継ぎ足して再掘削後の杭孔H2に対応する長さにしたものであるが、該杭本体P1が例えばPHC杭やPRC杭の如きコンクリート杭である場合、短尺杭部材P2として鋼管杭を継ぎ足し連結するのが簡易である。   For the ready-made pile PA to be inserted into the pile hole H2 after re-excavation, the ready-made pile P corresponding to the initially assumed pile hole H1 is used as the pile body P1, and the short pile member P2 is added to the pile body P1 and re- Although the length corresponds to the pile hole H2 after excavation, when the pile body P1 is a concrete pile such as a PHC pile or a PRC pile, a steel pipe pile is added and connected as the short pile member P2. It is simple.

すなわち、PHC杭やPRC杭の如きコンクリート杭では、図7(a)〜(c)に示すように、コンクリート筒体11の下端に、その端面に接当する円環状の鋼製端板12と、外周面を周回する鋼製の補強バンド13とが固着されている。そして、鋼製端板12には、周方向に等配する複数箇所(図では9箇所)に、ねじ孔12aと、その両側に配置する鋼線孔12bとが設けられている。一方、短尺杭部材P2に用いる鋼管杭としては、特に構造的な制約はないが、溶接又は/及びボルト止めによる継ぎ足し連結に適するものとして、図8に示す鋼管杭P2A、図10示す鋼管杭P2B、図11に示す鋼管杭P2C等を例示できる。   That is, in concrete piles such as PHC piles and PRC piles, as shown in FIGS. 7 (a) to (c), an annular steel end plate 12 contacting the end surface of the concrete cylinder 11, and The steel reinforcing band 13 that goes around the outer peripheral surface is fixed. The steel end plate 12 is provided with screw holes 12a and steel wire holes 12b arranged on both sides thereof at a plurality of locations (9 locations in the figure) equally distributed in the circumferential direction. On the other hand, the steel pipe pile used for the short pile member P2 is not particularly limited in structure, but is suitable for addition connection by welding or / and bolting, such as a steel pipe pile P2A shown in FIG. 8 and a steel pipe pile P2B shown in FIG. A steel pipe pile P2C shown in FIG.

鋼管杭P2Aは、図8(a)の如く、上端外周に垂止めリング20aを固着した鋼管20と、その上端に嵌着する連結リング部材21と、同下端に嵌着する底プレート22とで構成されている。その連結リング部材21は、鋼管20の上端開口部に内嵌させる縦円環状のリング部21aの上端に、横円環状のフランジ部21bが一体に固着してなり、フランジ部21bには杭本体P1における鋼製端板12の各ねじ孔12aに対応するボルト挿通孔21cが穿設されている。また、底プレート22は、縦円環状のリング部22aの下端に横円環状のフランジ部22bが一体に固着してなる。そして、杭本体P1に鋼管杭P2Aを継ぎ足し連結するには、連結リング部材21のフランジ部21bを杭本体P1の鋼製端板12に接合してボルト23を介して固定し、この連結リング部材21のリング部21aに鋼管20の上端側を外嵌したのち、鋼製端板12と連結リング部材21のフランジ部21bとの接合部の外周側を溶接し、次いで該フランジ部21bの外周縁と垂止めリング20aと上端周縁とを溶接し、最後に鋼管20の下端開口部に底プレート22を嵌合して溶接固着すればよい。   As shown in FIG. 8A, the steel pipe pile P2A is composed of a steel pipe 20 having a retaining ring 20a fixed to the outer periphery of the upper end, a connecting ring member 21 fitted to the upper end, and a bottom plate 22 fitted to the lower end. It is configured. The connecting ring member 21 is formed by integrally fixing a horizontal annular flange portion 21b to an upper end of a vertical annular ring portion 21a to be fitted into an upper end opening of the steel pipe 20, and the pile body is attached to the flange portion 21b. A bolt insertion hole 21c corresponding to each screw hole 12a of the steel end plate 12 at P1 is formed. Further, the bottom plate 22 is formed by integrally fixing a horizontal annular flange portion 22b to a lower end of a vertical annular ring portion 22a. And in order to add and connect the steel pipe pile P2A to the pile main body P1, the flange portion 21b of the connection ring member 21 is joined to the steel end plate 12 of the pile main body P1 and fixed via the bolt 23, and this connection ring member After the upper end side of the steel pipe 20 is externally fitted to the ring portion 21a of 21, the outer peripheral side of the joint portion between the steel end plate 12 and the flange portion 21b of the connecting ring member 21 is welded, and then the outer peripheral edge of the flange portion 21b The bottom ring 22 may be welded to the bottom end opening of the steel pipe 20, and the bottom ring 22 may be finally welded.

しかして、底プレート22は、図8(b)では鋼管20にリング部22aを外嵌しているが、該リング部22aを鋼管20に内嵌する形でもよい。外嵌型の底プレート22では、図9(a)に示すように、鋼管20の外周面とリング部22aの上端周縁とを溶接bする。また、内嵌型の底プレート22では、図9(b)に示すように、鋼管20の外周下端部とフランジ部22bの上面側とを溶接bする。なお、この底プレート22については、次に説明する鋼管杭P2B及び鋼管杭P2Cでも同様である。   Thus, in FIG. 8B, the bottom plate 22 has the ring portion 22a externally fitted to the steel pipe 20, but the ring portion 22a may be internally fitted to the steel pipe 20. In the outer fitting type bottom plate 22, as shown in FIG. 9A, the outer peripheral surface of the steel pipe 20 and the upper peripheral edge of the ring portion 22a are welded b. Moreover, in the internal fitting type bottom plate 22, as shown in FIG.9 (b), the outer peripheral lower end part of the steel pipe 20 and the upper surface side of the flange part 22b are welded b. The same applies to the bottom plate 22 in the steel pipe pile P2B and the steel pipe pile P2C described below.

鋼管杭P2Bは、図10(a)の如く、鋼管20と、その上端に固着する連結用ほぞ部材24と、前記同様の底プレート22とで構成されている。その連結用ほぞ部材24は、横円環状のベース部24aの中央に縦円筒状のほぞ部24bが一体に突設されてなる。そして、杭本体P1に対する鋼管杭P2Bの継ぎ足し連結は、連結用ほぞ部材24のベース部24aを鋼管20の上端に溶接固着した状態で、同図(b)で示すように、そのほぞ部24bを杭本体P1の内側に嵌入し、鋼製端板12とベース部24aとの接合部の外周側を溶接固着すればよい。   As shown in FIG. 10A, the steel pipe pile P2B includes a steel pipe 20, a connecting tenon member 24 fixed to the upper end thereof, and a bottom plate 22 similar to the above. The connecting tenon member 24 is formed by integrally projecting a vertical cylindrical tenon portion 24b at the center of a horizontal annular base portion 24a. Then, the steel pipe pile P2B is connected to the pile body P1 with the base portion 24a of the connecting tenon member 24 welded and fixed to the upper end of the steel pipe 20, as shown in FIG. What is necessary is just to insert inside the pile main body P1, and to weld-fix the outer peripheral side of the junction part of the steel end plates 12 and the base part 24a.

鋼管杭P2Cは、図11(a)の如く、鋼管20と、その上端に固着する横円環状で若干径大の端板25と、前記同様の底プレート22とで構成されており、端板25の上面外周側には環状溝25aが設けてある。そして、杭本体P1に対する鋼管杭P2Cの継ぎ足し連結は、端板25を外周下縁側で鋼管20の上端に溶接固着した状態で、該端板25を杭本体P1の鋼製端板12に合接し、その鋼製端板12の外周部を端板25の環状溝25a部分で溶接固着すればよい。   As shown in FIG. 11 (a), the steel pipe pile P2C is composed of a steel pipe 20, a horizontal annular end plate 25 fixed to the upper end thereof, and a bottom plate 22 similar to the end plate. An annular groove 25 a is provided on the outer peripheral side of the upper surface of 25. Then, the steel pipe pile P2C is connected to the pile body P1 by joining the end plate 25 to the steel end plate 12 of the pile body P1 in a state where the end plate 25 is welded and fixed to the upper end of the steel pipe 20 on the outer peripheral lower edge side. The outer peripheral portion of the steel end plate 12 may be welded and fixed at the annular groove 25a portion of the end plate 25.

これら鋼管杭P2A〜P2Cに用いる鋼管20は、予め施工現場に長尺の鋼管原材を搬入しておき、その鋼管原材から上記再掘削による杭孔H2の深さ増大に応じた長さ分を切り取り、連結リング部材21、底プレート22、連結用ほぞ部材24、端板25等と組み合わせて鋼管杭P2A〜P2Cを形成するようにすれば、再掘削による深さの違いに対応できる。一方、再掘削の掘削深さを一律とし、その掘削深さに対応する長さの同じ鋼管20の複数本を予め用意しておけば、再掘削が必要になった時に迅速に対応できる。   The steel pipes 20 used for these steel pipe piles P2A to P2C are previously loaded with a long steel pipe raw material at the construction site, and the length corresponding to the depth increase of the pile hole H2 by the re-excavation from the steel pipe raw material. If the steel pipe piles P2A to P2C are formed in combination with the connecting ring member 21, the bottom plate 22, the connecting tenon member 24, the end plate 25, etc., it is possible to cope with the difference in depth due to re-excavation. On the other hand, if the excavation depth of re-excavation is made uniform and a plurality of steel pipes 20 having the same length corresponding to the excavation depth are prepared in advance, it is possible to respond quickly when re-excavation becomes necessary.

また、鋼管本体20は、鋼管杭P2A〜P2Cでは単なる円筒状として示しているが、杭としての耐引抜き力を高めるために、その外周に、例えば図12(a)で示すような螺旋羽根20bを設けたり、同図(b)で示すように環状フランジ20cを所定間隔置きに設ける等、種々の付設形態を採用可能である。なお、杭本体P1に短尺杭部材P2を継ぎ足し連結する手段として、上記の溶接又は/及びボルト止め以外に、例えば、杭本体P1と短尺杭部材P2の接合部の外周に、分割形で外周テーパ状の係止リングを両者P1,P2間に亘って嵌合し、その外側に内周テーパー状の締付リングを強制的にスライド圧嵌させて連結部を固定する方法等、種々の機械的連結方式も採用可能である。   Moreover, although the steel pipe main body 20 is shown as a simple cylindrical shape in the steel pipe piles P2A to P2C, in order to increase the pull-out resistance as a pile, a spiral blade 20b as shown in FIG. Various attachment forms, such as providing the annular flange 20c at predetermined intervals as shown in FIG. In addition to the above welding and / or bolting as means for connecting and connecting the short pile member P2 to the pile main body P1, for example, the outer peripheral taper is divided into the outer periphery of the joint between the pile main body P1 and the short pile member P2. A variety of mechanical methods, such as a method in which a ring-shaped locking ring is fitted between both P1 and P2, and an inner taper-shaped fastening ring is forcibly slide-fitted to the outside to fix the connecting portion. A connection method can also be adopted.

しかして、掘削ロッド連結式や中空ロッド内蔵型の貫入試験機でも、縦筒状のケーシング内に、下方突出する貫入軸を一体化したノッキングブロックと、該ノッキングブロックを自由落下によって打撃するドライブハンマーと、落下後のドライブハンマーを吊り上げて所定高さで下放する吊上げ機構とを備え、着底させた貫入軸が孔底に所定深さまで貫入するのに要する打撃回数から孔底の支持強度を判定する、という基本構成は例示した吊下げ式と同様である。図13及び図14で掘削ロッド連結式の貫入試験機M2を、図15で中空ロッド内蔵型の貫入試験機M3をそれぞれ例示するが、掘削ロッド連結式の貫入試験機については既述の特許文献6(特願2016−078302号)に、中空ロッド内蔵型の貫入試験機については既述の特許文献7(特許第5932178号公報)に、それぞれ詳細な開示があるため、ここでは細部にわたる説明は省略する。   Even in a drilling rod connection type or hollow rod built-in type penetration tester, a knocking block in which a vertically protruding penetration shaft is integrated in a vertical cylindrical casing, and a drive hammer that hits the knocking block by free fall And a lifting mechanism that lifts the drive hammer after dropping and releases it at a predetermined height, and determines the support strength of the hole bottom from the number of impacts required for the bottomed penetration shaft to penetrate the hole bottom to a predetermined depth. The basic configuration is the same as the illustrated suspension type. 13 and 14 illustrate a drill rod connecting type penetration tester M2, and FIG. 15 illustrates a hollow rod built-in type penetration tester M3. 6 (Japanese Patent Application No. 2006-07832) and the hollow rod built-in type penetration tester are described in detail in Patent Document 7 (Patent No. 5932178) described above. Omitted.

図13(a)はプレボーリング工法に用いるアースオーガAAを示す。このアースオーガAAは、三点支持式杭打ち機の垂直に保持されたリーダLeにオーガーマシンAMが昇降可能に装着され、該オーガーマシンAMにスクリューロッドRsが上端部で保持されている。このスクリューロッドRsは、直線状の中空ロッドRの周囲に略全長にわたって螺旋羽根Scが形成されたもので、先端側が下端に掘削刃Eを備える独立の短い先端ロッド部材Rhより構成されている。しかして、図13(b)に示すように、地盤Gに杭孔Hを形成後、その孔底の支持強度を判定するために、スクリューロッドRsの下端に連結していた先端ロッド部材Rhに代えて、掘削ロッド連結式の貫入試験機M2を該スクリューロッドRsの下端に連結して用いるようになっている。   FIG. 13A shows an earth auger AA used for the pre-boring method. In this earth auger AA, an auger machine AM is mounted on a leader Le held vertically of a three-point support pile driver, and a screw rod Rs is held at the upper end of the auger machine AM. This screw rod Rs is formed with a spiral blade Sc formed over the entire length of a straight hollow rod R, and is composed of an independent short tip rod member Rh having a digging blade E at its lower end. Thus, as shown in FIG. 13 (b), after forming the pile hole H in the ground G, the tip rod member Rh connected to the lower end of the screw rod Rs is used to determine the support strength of the hole bottom. Instead, a drill rod connecting type penetration tester M2 is connected to the lower end of the screw rod Rs for use.

図14(a)はケリーバ式アースドリル工法に用いるアースドリル機ADを示す。このアースドリル機ADは、ブームBo及びフロントフレームFを備えた走行式クレーンよりなり、斜め前方へ張出するフロントフレームFの先端にケリードライブ装置KDが保持され、ブームBoによって巻上げロープWを介して吊持されたケリーバKが該ケリードライブ装置KDに上下動可能に挿通しており、ケリードライブ装置KDの下位には、一対のホースリールHrを設置したロータリーテーブルRTが取り付けられ、このロータリーテーブルRTには油圧用及び電気配線用のロータリーカップリング(図示省略)が設けてある。そして、ケリーバKの下端に実線で示す軸堀りバケットB1や仮想線で示す拡底バケットB2を連結し、地盤Gの掘孔や掘孔後の拡底掘削を行うようになっている。しかして、図19(b)に示すように、地盤Gに杭孔Hを形成後、その孔底の支持強度を判定するために、ケリーバKの下端に連結していた軸堀りバケットB1や拡底バケットB2に代えて、掘削ロッド連結式の貫入試験機M2を該ケリーバKの下端に連結して用いるようになっている。なお、Psはスタントパイプである。   FIG. 14A shows an earth drill machine AD used in the Keriba type earth drill method. This earth drill machine AD is composed of a traveling crane equipped with a boom Bo and a front frame F. A kelly drive device KD is held at the tip of the front frame F projecting obliquely forward, and the boom Bo passes a hoisting rope W. A suspended kerry bar K is inserted through the kelly drive device KD so as to be movable up and down. A rotary table RT having a pair of hose reels Hr is attached to the lower part of the kelly drive device KD. The RT is provided with a rotary coupling (not shown) for hydraulic and electric wiring. Then, a shaft digging bucket B1 indicated by a solid line and a bottom expansion bucket B2 indicated by a phantom line are connected to the lower end of the kelly bar K so as to perform excavation of the ground G or bottom expansion after digging. Then, as shown in FIG. 19 (b), after forming the pile hole H in the ground G, in order to determine the support strength of the hole bottom, the shaft-drilling bucket B1 connected to the lower end of the kelly bar K Instead of the expanded bucket B2, an excavation rod connection type penetration tester M2 is connected to the lower end of the kelly bar K for use. Ps is a stunt pipe.

掘削部材の中空ロッド内蔵型の貫入試験機は、図13(a)で示すスクリューロッドRsの中空状をなす先端ロッド部材Rh内に組み込まれたり、図14(a)で示す軸堀りバケットB1や拡底バケットB2の中空軸部内に組み込まれるものである。その具体例として、スクリューロッドRsの先端ロッド部材Rh内に該貫入試験機を組み込んだものを図15(a)〜(C)に示す。   A hollow rod built-in type penetration tester for a drilling member is incorporated in a tip rod member Rh having a hollow shape of a screw rod Rs shown in FIG. 13 (a), or a shaft digging bucket B1 shown in FIG. 14 (a). And is incorporated into the hollow shaft portion of the bottomed bucket B2. As a specific example, FIGS. 15A to 15C show an example in which the penetration tester is incorporated in the tip rod member Rh of the screw rod Rs.

図示の如く、先端ロッド部材Rhは、円筒状の中空ロッド100内に貫入試験機M3を内蔵しており、該中空ロッド100の上端板101に連結用凸型ブロック110が突設される一方、下端板102の中央に丸孔状の開口部103が形成されると共に、常時は該開口部103を図示省略したばねの付勢によって下方側から閉鎖する可動封板104が取り付けられている。また、中空ロッド100の外周には全長にわたって螺旋羽根Scが固設されると共に、該螺旋羽根Scの下縁に複数の掘削刃Eが突設されている。そして、中空ロッド100の下端側には側方へ開口するグラウト放出口105を備え、中空ロッド100内には連結用凸型ブロック110の中心孔110aからグラウト放出口105に至るグラウト配管120が設けてある。   As shown in the figure, the tip rod member Rh has a penetration tester M3 built in a cylindrical hollow rod 100, and a connecting convex block 110 projects from an upper end plate 101 of the hollow rod 100, A round hole-shaped opening 103 is formed at the center of the lower end plate 102, and a movable sealing plate 104 that normally closes the opening 103 from below is attached by a biased spring (not shown). In addition, a spiral blade Sc is fixed over the entire length of the outer periphery of the hollow rod 100, and a plurality of excavation blades E project from the lower edge of the spiral blade Sc. The hollow rod 100 is provided with a grout discharge port 105 opening laterally at the lower end side, and a grout pipe 120 extending from the central hole 110a of the connecting convex block 110 to the grout discharge port 105 is provided in the hollow rod 100. It is.

貫入試験機M3は、中空ロッド100内に同心状に配設固定された円筒状の外側ケーシング3内に、円筒状のハンマーケーシング5が昇降自在に装填されると共に、該ハンマーケーシング5の下端から突出する貫入軸4が垂下している。そして、ハンマーケーシング5の下端と中空ロッド100の下端の開口部103との間には、貫入軸4を取囲む形で、ゴムや半硬質合成樹脂等の可撓性材料からなる伸縮可能なベローズ筒体7Cが装着されている。なお、図示を省略するが、ハンマーケーシング5内には、既述した吊下げ式の貫入試験機M1と同様に、ノッキングブロック51及びドライブハンマー52と吊上げ機構8(図3参照)を備える。   In the penetration tester M3, a cylindrical hammer casing 5 is loaded in a cylindrical outer casing 3 concentrically disposed and fixed in the hollow rod 100 so as to be movable up and down, and from the lower end of the hammer casing 5. A protruding penetrating shaft 4 hangs down. Between the lower end of the hammer casing 5 and the opening 103 at the lower end of the hollow rod 100, an expandable bellows made of a flexible material such as rubber or semi-rigid synthetic resin so as to surround the penetration shaft 4. A cylindrical body 7C is attached. In addition, although illustration is abbreviate | omitted, in the hammer casing 5, the knocking block 51, the drive hammer 52, and the lifting mechanism 8 (refer FIG. 3) are provided similarly to the suspension type penetration testing machine M1 already described.

外側ケーシング3内の上部側には、ケーシング変位手段200として下向きの伸縮ロッド201aを備える油圧シリンダー201が垂設され、その伸縮ロッド201aの先端に下端側を逆円錐状に尖った係止頭部203aとする係止軸203が固着される一方、ハンマーケーシング5の上端に周方向に等配配置した4本のクランプアーム205が内外方向に傾動自在に枢着されている。そして、係止軸203の係止頭部203aよりも上位側には、クランプアーム205に対する位置を確認するためのセンサーリング204が昇降自在に嵌装されている。また、各クランプアーム205の上端には内向きの係止爪205aが形成され、クランプアーム205同士がスプリング(図示省略)によって一体に起立方向に付勢されている。なお、図示を省略しているが、外側ケーシング3内の上部側には既述した吊下げ式の貫入試験機M1と同様にハンマーケーシング5の下降量を計測するエンコーダー〔図2(a)参照〕が取り付けられている。   On the upper side in the outer casing 3, a hydraulic cylinder 201 having a downwardly extending telescopic rod 201a as a casing displacing means 200 is suspended, and a locking head whose lower end is pointed in an inverted conical shape at the tip of the telescopic rod 201a. While the locking shaft 203 as 203a is fixed, four clamp arms 205 equally arranged in the circumferential direction are pivotally attached to the upper end of the hammer casing 5 so as to be tiltable inward and outward. A sensor ring 204 for confirming the position with respect to the clamp arm 205 is fitted on the upper side of the locking head 203 above the locking head 203a so as to be movable up and down. Further, inwardly engaging claws 205a are formed at the upper ends of the clamp arms 205, and the clamp arms 205 are urged together in a standing direction by a spring (not shown). Although not shown, an encoder for measuring the amount of descent of the hammer casing 5 is provided on the upper side of the outer casing 3 in the same manner as the above-described penetrating penetration testing machine M1 [see FIG. 2 (a). ] Is attached.

このように先端ロッド部材Rhに貫入試験機M3を内蔵したスクリューロッドRSにおいて、該貫入試験機M3の不使用時には、図15(a)に示すように、油圧シリンダー201の伸縮ロッド203がその係止頭部203aにクランプアーム205を係合した状態で収縮しており、これによってハンマーケーシング5が外側ケーシング3内での上方待機位置に保持され、貫入軸4が中空ロッド100内に納まることで、該中空ロッド100の下端の開口部103が可動封板104によって閉鎖されている。従って、スクリューロッドRSによる掘削過程で、貫入軸4が地盤や破砕物に触れて損傷する懸念がなく、また掘削で生じた泥砂、砂礫、泥水等が外側ケーシング3内へ入り込むこともない。   Thus, in the screw rod RS in which the penetration test machine M3 is built in the tip rod member Rh, when the penetration test machine M3 is not used, the expansion rod 203 of the hydraulic cylinder 201 is engaged as shown in FIG. By contracting with the clamp arm 205 engaged with the stop head 203 a, the hammer casing 5 is held at the upper standby position in the outer casing 3, and the penetrating shaft 4 is accommodated in the hollow rod 100. The opening 103 at the lower end of the hollow rod 100 is closed by a movable sealing plate 104. Therefore, there is no concern that the penetrating shaft 4 touches the ground or crushed material during the excavation process by the screw rod RS, and mud sand, sand gravel, mud water, etc. generated by excavation does not enter the outer casing 3.

一方、杭孔形成後に貫入試験機M3による測定を行う場合は、図15(b)に示すように、まず油圧シリンダー201のピストンロッド201aを伸長させることにより、係止軸203の係止頭部203aで各クランプアーム205をばね力の付勢に抗して外側へ押し開き、更に上方待機位置で保持していたハンマーケーシング5を押圧して下動させる。このハンマーケーシング5の下動に伴い、貫入軸4が可動封板104を押し開いて開口部103から下方へ突出するから、次いで図15(c)に示すように、油圧シリンダー201のピストンロッド201aを急速に短縮させることにより、係止頭部203aがクランプアーム25から上方へ離脱し、もって係止解除されたハンマーケーシング5は貫入軸4の先端が孔底に着底するまで自重で降下する。従って、この着底状態で該貫入試験機M3を駆動することにより、既述した吊り下げ式の貫入試験機M1と同様に杭底の地盤の支持強度が所定値以上であるか否かを判定できる。   On the other hand, when measurement is performed by the penetration testing machine M3 after the formation of the pile hole, as shown in FIG. 15 (b), first, the piston rod 201a of the hydraulic cylinder 201 is extended to thereby lock the locking head of the locking shaft 203. At 203a, the clamp arms 205 are pushed outward against the bias of the spring force, and the hammer casing 5 held at the upper standby position is pressed and moved downward. As the hammer casing 5 moves downward, the penetrating shaft 4 pushes open the movable sealing plate 104 and protrudes downward from the opening 103. Next, as shown in FIG. 15C, the piston rod 201a of the hydraulic cylinder 201 By rapidly shortening, the locking head 203a is disengaged upward from the clamp arm 25, and the unlocked hammer casing 5 is lowered by its own weight until the tip of the penetrating shaft 4 reaches the bottom of the hole. . Therefore, by driving the penetration testing machine M3 in this bottomed state, it is determined whether or not the support strength of the ground at the bottom of the pile is equal to or higher than a predetermined value in the same manner as the suspension type penetration testing machine M1 described above. it can.

しかして、貫入試験が終了すれば、油圧シリンダー201のピストンロッド201aを伸長させることにより、その係止軸203の係止頭部203aをクランプアーム205の間に割り込ませ、該係止頭部203aに各クランプアーム205の係止爪205aを係合させ、この係止状態で油圧シリンダー201を短縮作動させることにより、該ハンマーケーシング5を上方待機位置まで持ち上げて保持することができる。   When the penetration test is finished, the piston rod 201a of the hydraulic cylinder 201 is extended to interrupt the locking head 203a of the locking shaft 203 between the clamp arms 205, and the locking head 203a. By engaging the locking claws 205a of each clamp arm 205 and shortening the hydraulic cylinder 201 in this locked state, the hammer casing 5 can be lifted to the upper standby position and held.

この中空ロッド内蔵型の貫入試験機M3を用いたプレボーリング工法における杭施工管理方法について、図16及び図17で示す工程順に説明する。この杭施工では、図16(a):三点式杭打機等のリーダ(図示省略)に沿って昇降するオーガーマシンAにスクリューロッドRsを取り付け、該スクリューロッドRsを回転駆動しつつ下降させることによって地盤Gを掘削し、同(b):想定される地下深部の支持層Ghに達する深さの杭孔H1を形成したのち、同(c):スクリューロッドRsを僅かに引き上げて掘削刃Eを離底させ、この状態で先端ロッド部材Rhに内蔵する貫入試験機M3の貫入軸4を下方突出させて孔底Hb1に着底させ、既述のように杭底地盤の支持強度を測定する。そして、該支持強度が所定値以上であれば、同(d):スクリューロッドRsを引き上げつつソイルセメント等の根固め液Lsを注入し、同(e):続いて孔周固定液Lfを杭孔Hの上部まで注入し、該スクリューロッドRsを抜出したのち、同(f):オーガーマシンAに連結用ロッドRjを介してPHC杭やPRC杭の如き既製杭Pを取り付け、この既製杭Pを杭孔H1に挿入し、同(g):該杭孔H1の底まで埋め込んで既製杭Pの建て込みを完了する。   The pile construction management method in the pre-boring method using this hollow rod built-in penetration test machine M3 will be described in the order of steps shown in FIGS. In this pile construction, a screw rod Rs is attached to an auger machine A that moves up and down along a leader (not shown) such as a three-point pile driver, and the screw rod Rs is lowered while being driven to rotate. After excavating the ground G, (b): after forming a pile hole H1 having a depth reaching the support layer Gh in the deep underground, the same (c): slightly lifting the screw rod Rs to In this state, the penetration shaft 4 of the penetration tester M3 built in the tip rod member Rh protrudes downward to land on the hole bottom Hb1, and the support strength of the pile bottom ground is measured as described above. If the supporting strength is equal to or greater than a predetermined value, the same (d): the root-setting liquid Ls such as soil cement is injected while pulling up the screw rod Rs, and the same (e): the hole periphery fixing liquid Lf is subsequently piled. After injecting up to the upper part of the hole H and extracting the screw rod Rs, the same (f): A ready-made pile P such as a PHC pile or a PRC pile is attached to the auger machine A via the connecting rod Rj. Is inserted into the pile hole H1, and (g): the bottom of the pile hole H1 is embedded to complete the construction of the ready-made pile P.

しかるに、例えば図17(a)で示すように、地下深部の支持層Ghが当初の想定よりも深い位置にあり、杭孔H1が該支持層Ghに達していないこと等で、前記貫入試験機M3にて測定した杭底地盤の支持強度が所定値に満たなかった場合には、本発明の杭施工管理方法を適用する。すなわち、杭孔H1に挿入している貫入試験後のスクリューロッドRsをそのまま用い、貫入試験機M3の貫入軸4を退入させた上で、図17(b):該杭孔H1を再掘削することにより、より深い杭孔H2を形成したのち、同(c):スクリューロッドRsを僅かに引き上げて掘削刃Eを離底させた状態で、前回同様に貫入試験機M3の貫入軸4を孔底Hb2に着底させて杭底地盤の支持強度を再測定する。そして、該杭孔H2が当初の想定より深い位置にあった支持層Ghに達していること等で、該支持強度が所定値以上であれば、スクリューロッドRsを引上げつつ根固め液Ls及び孔周固定液Lfを注入したのち、同(d):当初想定の杭孔H1用の既製杭Pを杭本体P1として、該杭本体P1に短尺杭部材P2を継ぎ足し連結した既製杭PAを用い、同(e):再掘削後の杭孔H2に該既製杭PAを挿入し、同(f):該杭孔H2の底まで埋め込んで既製杭PAの建て込みを完了する。なお、この杭本体P1に短尺杭部材P2を継ぎ足し連結した既製杭PAは、既述の第一実施形態で説明したものと同様である。   However, for example, as shown in FIG. 17 (a), the penetration testing machine is configured such that the support layer Gh in the deep underground is deeper than originally assumed and the pile hole H1 does not reach the support layer Gh. When the support strength of the pile bottom ground measured in M3 is less than a predetermined value, the pile construction management method of the present invention is applied. That is, the screw rod Rs after the penetration test inserted into the pile hole H1 is used as it is, and the penetration shaft 4 of the penetration test machine M3 is retracted, and then FIG. 17B: the pile hole H1 is re-excavated. After forming the deeper pile hole H2, the same (c): With the screw rod Rs slightly lifted and the excavating blade E detached from the bottom, the penetration shaft 4 of the penetration testing machine M3 is moved in the same manner as the previous time. The bottom is grounded to the hole bottom Hb2, and the support strength of the pile bottom ground is measured again. And if this support strength is more than predetermined value because this pile hole H2 has reached the support layer Gh which was deeper than originally assumed, etc., the root-solidifying liquid Ls and the hole are lifted while pulling up the screw rod Rs. After injecting the peripheral fixing liquid Lf, the same (d): using the ready-made pile PA in which the pre-made pile P for the initially assumed pile hole H1 is connected to the pile main body P1 by adding the short pile member P2 to the pile main body P1, (E): The ready-made pile PA is inserted into the pile hole H2 after the re-excavation, and (f): the built-in of the ready-made pile PA is completed by embedding to the bottom of the pile hole H2. In addition, the ready-made pile PA which added and connected the short pile member P2 to this pile main body P1 is the same as that of what was described in 1st embodiment as stated above.

以上のように、本発明の杭施工管理方法によれば、掘削した設定深度の杭孔H1の孔底Hb1の支持強度が不足しても、場所を代えて新たに杭孔を形成する必要はなく、同じ杭孔H1の再掘削と再判定を行うことで対応できるから、建造物の設計変更、大幅な施工コスト増大や工期延長等を回避できる上、設定深度の杭孔H1用として予め準備している既製杭Pを杭本体P1として長さ不足分だけ簡単に継ぎ足す形で利用できるから、資材コストが嵩まず、且つ能率よく杭の建て込み作業を行える。また、既製杭の施工において再掘削による深度増加分に対応する短尺杭部材P2を杭本体P1に継ぎ足し連結して用いることにより、再掘削による深度増加に容易に対応できると共に、同じ寸法形状の短尺杭部材P2を利用して一律な杭施工管理を行える。   As described above, according to the pile construction management method of the present invention, even if the support strength of the hole bottom Hb1 of the excavated set depth pile hole H1 is insufficient, it is necessary to form a new pile hole at a different location. Since it can be handled by re-excavating and re-determining the same pile hole H1, it is possible to avoid changes in the design of the building, a significant increase in construction cost, extension of construction period, etc. Since the ready-made pile P can be used as a pile main body P1 by simply adding only the shortage of the length, the material cost is not increased and the pile can be built efficiently. In addition, by using the short pile member P2 corresponding to the depth increase due to re-excavation in the construction of ready-made piles, it is possible to easily cope with the depth increase due to re-excavation, and the short size of the same size and shape. Uniform pile construction management can be performed using the pile member P2.

B1 軸堀りバケット(掘削先部材)
B2 拡底バケット(掘削先部材)
G 地盤
H1,H2 杭孔
Hb1,Hb2 孔底
M1〜M3 貫入試験機
P 既製杭
P1 杭本体
P2 短尺杭部材
P2A〜P2C 鋼管杭
PA 継ぎ足し連結した既製杭
Rh 先端ロッド部材(掘削先部材)
W ワイヤ
3 外側ケーシング(ケーシング)
4 貫入軸
51 ノッキングブロック
52 ドライブハンマー
8 吊上げ機構
B1 Shaft-drilling bucket (drilling destination member)
B2 Expanded bucket (Drilling destination member)
G Ground H1, H2 Pile hole Hb1, Hb2 Hole bottom M1-M3 Penetration test machine P Ready-made pile P1 Pile body P2 Short pile member P2A-P2C Steel pipe pile PA Ready-made pile Rh Tip rod member (drilling tip member)
W wire 3 outer casing (casing)
4 Penetration shaft 51 Knocking block 52 Drive hammer 8 Lifting mechanism

Claims (4)

地盤に設定深度の杭孔を形成後、該杭孔内への設定深度に相当する杭長さの杭の建て込み前に、
縦筒状のケーシング内に、該ケーシングの下端から下方突出する貫入軸を一体化したノッキングブロックと、該ノッキングブロックを自由落下によって打撃するドライブハンマーと、落下後のドライブハンマーを吊り上げて所定高さで下放する吊上げ機構とを備えてなる貫入試験機を用い、
杭孔内に配置させた貫入試験機の前記貫入軸を孔底に着底させ、該貫入軸が孔底から所定深さまで貫入するのに要する打撃回数から孔底の支持強度を判定し、その支持強度が所定値に満たない場合に、該杭孔を更に深く再掘削して、再掘削後の孔底の支持強度を前記貫入試験機によって同様にして判定し、
この際、再掘削の掘削深さを一律とし、
且つ、その一律の再掘削深さに対応する長さの同じ杭の複数本を予め用意しておき、
一律の掘削深さの再掘削により、該支持強度が所定値以上に達した場合に、元の設定深度に相当する杭長さに対して再掘削による一律の掘削深さの深度増加分の予め用意した長さの杭を継ぎ足し調整した杭を該杭孔に建て込む杭施工管理方法であって、
元の設定深度に相当する杭長さの杭本体がコンクリート杭であり、前記再掘削による一律の掘削深さの深度増加分に対応する短尺杭部材が鋼管杭であり、
該鋼管杭は、再掘削による一律の掘削深さに対応する同じ長さの予め容易した複数本の鋼管と、該鋼管の上端部に固着され、前記コンクリート杭の下端部に固着された鋼製端板に溶接又は/及びボルト止めされる連結リング部材とからなり、
コンクリート杭の下端部の鋼製端板に鋼管の上端部の連結リング部材を溶接又は/及びボルト止めすることによって、再掘削による一律の掘削深さの深度増加分の予め用意した長さの杭を継ぎ足し調整した杭として、この継ぎ足し調整した杭を再掘削後の杭孔に建て込むことを特徴とする杭施工管理方法。
After forming a pile hole with a set depth in the ground, before building a pile with a pile length equivalent to the set depth into the pile hole,
A knocking block in which a penetrating shaft that protrudes downward from the lower end of the casing is integrated in a vertical cylindrical casing, a drive hammer that strikes the knocking block by free fall, and a drive hammer that has been dropped is lifted to a predetermined height. Using a penetrating tester equipped with a lifting mechanism
The penetration shaft of the penetration tester placed in the pile hole is grounded to the bottom of the hole, and the support strength of the bottom of the hole is determined from the number of impacts required for the penetration shaft to penetrate from the bottom of the hole to a predetermined depth. When the support strength is less than a predetermined value, the pile hole is re-excavated further deeply, and the support strength of the hole bottom after the re-excavation is similarly determined by the penetration testing machine,
At this time, the digging depth of re-digging is made uniform,
And prepare a plurality of piles of the same length corresponding to the uniform re-digging depth in advance,
When the support strength reaches a predetermined value or more by re-excavation with a uniform excavation depth, the amount of increase in the uniform excavation depth by re-excavation in advance for the pile length corresponding to the original set depth A pile construction management method in which a pile having a prepared length is added and adjusted to be built in the hole ,
The pile body of the pile length corresponding to the original set depth is a concrete pile, and the short pile member corresponding to the depth increase of the uniform excavation depth by the re-excavation is a steel pipe pile,
The steel pipe pile is made of a plurality of steel pipes having the same length corresponding to a uniform excavation depth by re-excavation, and a steel pipe fixed to the upper end of the steel pipe and fixed to the lower end of the concrete pile. A connecting ring member welded and / or bolted to the end plate,
A pile with a pre-prepared length corresponding to the increased depth of uniform excavation depth by re-excavation by welding or / and bolting the connecting ring member at the upper end of the steel pipe to the steel end plate of the lower end of the concrete pile A pile construction management method characterized in that , as a pile that has been added and adjusted, the pile that has been added and adjusted is built in a pile hole after re-excavation .
前記貫入試験機が吊下げ式であり、該貫入試験機をクレーンのワイヤで吊下げて杭孔に出入させる請求項1に記載の杭施工管理方法。   The pile construction management method according to claim 1, wherein the penetration tester is a suspension type, and the penetration tester is suspended by a crane wire to enter and exit the pile hole. 前記貫入試験機が掘削ロッド連結式であり、杭孔を掘削後の掘削先部材に代えて該貫入試験機を連結して杭孔に出入させる請求項1又は2に記載の杭施工管理方法。   The pile construction management method according to claim 1 or 2, wherein the penetration testing machine is a drilling rod connection type, and the pile hole is connected to the drilling destination member after excavation and the penetration testing machine is connected to enter and exit the pile hole. 前記貫入試験機が掘削部材の中空ロッド内蔵型であり、掘削後の杭孔内に該掘削部材を挿入した状態で該貫入試験機を作動させて貫入試験を行う請求項1〜3のいずれかに記載の杭施工管理方法。   The penetration test machine is a hollow rod built-in type of excavation member, and the penetration test machine is operated in a state in which the excavation member is inserted into the pile hole after excavation to perform a penetration test. The pile construction management method described in 1.
JP2018024377A 2018-02-14 2018-02-14 Pile construction management method Active JP6588585B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018024377A JP6588585B2 (en) 2018-02-14 2018-02-14 Pile construction management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018024377A JP6588585B2 (en) 2018-02-14 2018-02-14 Pile construction management method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2016120081A Division JP6329590B2 (en) 2015-12-25 2016-06-16 Pile construction management method

Publications (2)

Publication Number Publication Date
JP2018091132A JP2018091132A (en) 2018-06-14
JP6588585B2 true JP6588585B2 (en) 2019-10-09

Family

ID=62565317

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018024377A Active JP6588585B2 (en) 2018-02-14 2018-02-14 Pile construction management method

Country Status (1)

Country Link
JP (1) JP6588585B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113818498B (en) * 2021-09-30 2022-10-04 河北工业大学 Multidirectional pseudo-static test device for building ground structure and pile foundation composite stress body

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57193622A (en) * 1981-05-22 1982-11-29 Kubota Ltd Driving method of composite pile and used composite pile therefor
JPS60212516A (en) * 1984-04-07 1985-10-24 Riyouka Kogyo Kk Method of constructing steel-pipe pile
JPH073054B2 (en) * 1988-12-16 1995-01-18 清水建設株式会社 Foundation pile construction method
JPH0751782B2 (en) * 1990-05-10 1995-06-05 株式会社ホクコン Construction method of the root fixing part for fixing the pile
JP2003232033A (en) * 2002-02-06 2003-08-19 Taisei Corp Foundation pile structure
US20040065453A1 (en) * 2002-10-07 2004-04-08 Jiin-Song Tsai Downhole sampling method and device used in standard penetration test
JP2009138435A (en) * 2007-12-06 2009-06-25 Sekisui Chem Co Ltd Method of constructing foundation structure
JP2009162034A (en) * 2008-01-10 2009-07-23 Tokyo Electric Power Co Inc:The Method of constructing foundation of structure
JP5932178B1 (en) * 2016-03-10 2016-06-08 株式会社オーク Pile hole excavation apparatus and pile construction management method

Also Published As

Publication number Publication date
JP2018091132A (en) 2018-06-14

Similar Documents

Publication Publication Date Title
JP5932178B1 (en) Pile hole excavation apparatus and pile construction management method
JP6329590B2 (en) Pile construction management method
WO2017110314A1 (en) Piling construction management method
JP5994035B1 (en) Pile hole penetration test device and pile construction management method
US6540443B2 (en) Apparatus for and a method of boring the ground
JP5972494B1 (en) Penetration testing machine for excavation rod connection and pile construction management method
CN110629747A (en) Full-casing full-rotation construction process for pile foundation under complex geological conditions
JP6242466B1 (en) Penetration testing machine for pile holes
JP2006241919A (en) Pile construction machine and pile construction method
JP2020070687A (en) Construction method for steel pipe pile
CN103397632B (en) PHC pile tube and pile-sinking method thereof
KR101414756B1 (en) Non welding type linked casing
JP5918435B1 (en) Pile construction management method
JP6588585B2 (en) Pile construction management method
US20090285637A1 (en) Pile mandrel with extendable reaming members
KR102178354B1 (en) Pile pullout apparatus
JP6047257B1 (en) Pile hole penetration testing machine and pile construction management method
JP6754662B2 (en) Dynamic load test device and method for confirming the bearing capacity of the excavated tip ground of cast-in-place concrete piles using this device
EP3351688B1 (en) Apparatus and method for stabilizing a foundation of a building
JP3293796B2 (en) Pile driver
KR101722518B1 (en) Drilled large diameter rotary drilling equipment and drilling process using multi-bucket
CN217923525U (en) Hole digging and wall protecting pile forming structure for adjacent existing underground structure in karst area
JP2023061669A (en) Ground excavation method
JPS6033148Y2 (en) Pile driving device
JPH02140311A (en) Pipe anchor construction for avalanche preventing fence

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180214

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20190123

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190213

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190308

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20190821

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20190912

R150 Certificate of patent or registration of utility model

Ref document number: 6588585

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250