JP6179020B2 JP2013136536A JP2013136536A JP6179020B2 JP 6179020 B2 JP6179020 B2 JP 6179020B2 JP 2013136536 A JP2013136536 A JP 2013136536A JP 2013136536 A JP2013136536 A JP 2013136536A JP 6179020 B2 JP6179020 B2 JP 6179020B2
Authority
JP
Japan
Prior art keywords
wire
underground
pipe material
cut
housing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2013136536A
Other languages
Japanese (ja)
Other versions
JP2015010387A (en
Inventor
直宏 大西
直宏 大西
亨 徳野
亨 徳野
康明 豊田
康明 豊田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP2013136536A priority Critical patent/JP6179020B2/en
Publication of JP2015010387A publication Critical patent/JP2015010387A/en
Application granted granted Critical
Publication of JP6179020B2 publication Critical patent/JP6179020B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Description

本発明は、第1躯体部と第2躯体部とを一体に形成した躯体部において、第1躯体部と第2躯体部との境目を切断して分離する際にパイプ材を使用する躯体分離方法に関する。 The present invention relates to a housing separation in which a pipe material is used when a boundary between the first housing portion and the second housing portion is cut and separated in a housing portion in which the first housing portion and the second housing portion are integrally formed. Regarding the method .

例えば、鉄筋コンクリート製の躯体部において、第1躯体部と第2躯体部との境目を切断して分離する場合、従来、削岩機などを使用して第1躯体部と第2躯体部との境目部分のコンクリートを破砕し、必要に応じて鉄筋などをガス切断して分離していた。
しかし、削岩機などを使用する従来の方法では、騒音や塵埃などによる公害問題が生じるため、近年、ワイヤーソーを使用し、ワイヤーソーのワイヤーを第1躯体部と第2躯体部との境目外周部にループ状に巻き付け、ワイヤーソーを駆動して切断、分離する方法が提案された(適切な特許文献等は見当たらない)。
For example, in the case of a reinforced concrete frame part, when the boundary between the first frame part and the second frame part is cut and separated, conventionally, using a rock drill or the like, the first frame part and the second frame part The concrete at the boundary was crushed and separated by gas cutting of rebar as necessary.
However, in the conventional method using a rock drill or the like, there is a problem of pollution due to noise or dust. In recent years, a wire saw has been used, and the wire saw wire is connected to the boundary between the first and second housing parts. There has been proposed a method in which a loop is wound around the outer periphery and a wire saw is driven to cut and separate (there are no appropriate patent documents or the like).

しかしながら、ワイヤーソーを使用する方法では、ワイヤーソーのワイヤーを切断すべき躯体部の外周部、つまり、第1躯体部と第2躯体部との境目外周部にループ状に巻き付ける必要がある。
ところが、現実の問題として、第1躯体部と第2躯体部との境目外周部に壁などの他物が存在することが多く、その場合には、ドリルなどを使用して壁などにワイヤー挿通用の孔を穿孔する作業が必要となる。更に、切断対象となる躯体部が地下にある場合には、その地下躯体部の裏側が地盤であることも多く、切断対象である地下躯体部の外周部にワイヤーをループ状に巻き付けることが非常に困難な作業となる。
However, in the method using a wire saw, it is necessary to wrap around the outer periphery of the housing part to be cut of the wire of the wire saw, that is, the outer periphery of the boundary between the first housing part and the second housing part.
However, as a practical problem, there are many other objects such as walls on the outer periphery of the boundary between the first housing part and the second housing part. In this case, a wire is inserted into the wall using a drill or the like. An operation for drilling a common hole is required. Furthermore, when the body part to be cut is in the basement, the back side of the base body part is often the ground, and it is very easy to wrap the wire around the outer periphery of the base part to be cut in a loop shape It will be a difficult task.

本発明は、このような問題点に着目したもので、その目的は、切断対象となる躯体部がたとえ地下にある躯体部であっても、切断の必要が生じた場合、その躯体部の切断箇所の外周部にワイヤーソーのワイヤーを容易、迅速にループ状に巻き付けることのできる躯体分離方法を提供することにある。 The present invention pays attention to such problems, and its purpose is to cut the housing part when it is necessary to cut the housing part even if the body part to be cut is an underground body part. An object of the present invention is to provide a housing separation method capable of easily and quickly winding a wire saw wire in a loop shape around the outer periphery of a portion.

本発明の特徴は、第1躯体部と第2躯体部とを一体に形成した躯体部において、ワイヤーソー用のワイヤーを挿通自在なパイプ材を、前記第1躯体部と前記第2躯体部との境目外周部に沿う状態に、かつ、前記パイプ材のワイヤー挿通用端部が前記ワイヤーソーによる切断作業空間側に位置する状態に設置する方法によって設置した前記パイプ材を使用して前記ワイヤーソーで前記躯体部を切断する躯体分離方法であって、
前記躯体部は、逆打ち工法の実施過程で設置する地下梁であり、前記第1躯体部は、本設地下梁となる前記第2躯体部から土留め壁側に突出した仮設地下梁であり、前記パイプ材を設置してある前記第1躯体部と前記第2躯体部との境目は、本設地下構造物の外周面と面一に設定してあり、前記切断作業空間に前記ワイヤーソーを設置するとともに、前記パイプ材に前記ワイヤーを挿通させて、そのワイヤーを使用して前記躯体部を切断する点にある。
A feature of the present invention is that , in a housing part in which a first housing part and a second housing part are integrally formed, a pipe material through which a wire for a wire saw can be inserted, the first housing part and the second housing part, The wire saw using the pipe material installed by a method in which the wire insertion end of the pipe material is located on the cutting work space side by the wire saw in a state along the boundary outer periphery of the pipe A housing separating method for cutting the housing portion with
The frame part is an underground beam that is installed in the course of the reverse driving method, and the first frame part is a temporary underground beam that protrudes toward the retaining wall from the second frame part that is a permanent underground beam. The boundary between the first housing part and the second housing part in which the pipe material is installed is set to be flush with the outer peripheral surface of the main underground structure, and the wire saw is placed in the cutting work space. In addition, the wire is inserted through the pipe material, and the casing is cut using the wire.

上記特徴構成によれば、ワイヤーソー用のワイヤーを挿通自在なパイプ材が、躯体部の切断箇所の外周部に沿う状態に、つまり、第1躯体部と第2躯体部との境目外周部に沿う状態に設置してあり、しかも、そのパイプ材のワイヤー挿通用端部がワイヤーソーによる切断作業空間側に位置する状態に設置してあるので、切断対象となる躯体部がたとえ地下にある躯体部であっても、切断作業空間側からパイプ材のワイヤー挿通用端部を通してワイヤーソー用のワイヤーを挿通することにより、切断箇所である第1躯体部と第2躯体部の境目外周部に沿ってワイヤーソー用のワイヤーを容易、迅速にループ状に巻き付けることができる。   According to the above characteristic configuration, the pipe material through which the wire for the wire saw can be freely inserted is in a state along the outer peripheral portion of the cutting portion of the housing portion, that is, at the boundary outer peripheral portion between the first housing portion and the second housing portion. Since the pipe insertion end of the pipe material is located on the side of the cutting work space with the wire saw, the casing part to be cut is even in the basement. Even if it is a section, by inserting the wire for the wire saw from the cutting work space side through the wire insertion end of the pipe material, along the boundary outer peripheral portion of the first and second housing portions that are the cutting locations Wire for wire saw can be easily and quickly wound in a loop.

また、切断作業空間にワイヤーソーを設置し、上述の設置方法によって設置したパイプ材にワイヤーソーのワイヤーを挿通させて、そのワイヤーを使用して切断することにより、逆打ち工法の実施過程で設置する地下梁において、本設地下梁から土留め壁側に突出した仮設地下梁、すなわち、逆打ち工法の実施中は土留め壁の倒壊を防ぐために必要ではあるが、本設地下梁に対して土留め壁から予期せぬ荷重が作用するのを回避するため、最終的に切断して分離する必要のある仮設地下梁をパイプ材と一緒に容易に切断することができる。
そして、ワイヤーを挿通させるパイプ材が、本設地下構造物の外周面と面一に設定した境目に設置してあるので、仮設地下梁を切断した状態では、その切断面が本設地下構造物の外周面と面一となる。したがって、例えば、仮設地下梁の一部が本設地下構造物の外周面から突出した状態で切断した場合のように、その突出部分を介して本設地下構造物に予期せぬ荷重が集中的に作用することが回避される。
In addition , by installing a wire saw in the cutting work space, inserting the wire saw wire into the pipe material installed by the above installation method, and cutting using the wire, it is installed in the implementation process of the reverse hammering method The temporary underground beam that protrudes from the permanent underground beam to the retaining wall side, that is, it is necessary to prevent the retaining wall from collapsing during the reverse driving method. In order to avoid an unexpected load from the earth retaining wall, a temporary underground beam that needs to be finally cut and separated can be easily cut together with the pipe material.
And since the pipe material through which the wire is inserted is installed at the boundary set to be flush with the outer peripheral surface of the permanent underground structure, when the temporary underground beam is cut, the cut surface is the permanent underground structure. It becomes flush with the outer peripheral surface. Therefore, for example, when a part of the temporary underground beam is cut in a state of protruding from the outer peripheral surface of the permanent underground structure, an unexpected load is concentrated on the permanent underground structure through the protruding portion. Acting on is avoided.

本発明による躯体分離方法の更なる特徴構成は、前記切断作業空間は、切断対象の前記地下梁のうち、最上段に位置する地下梁の上に設定する点にある。   A further characteristic configuration of the frame separating method according to the present invention is that the cutting work space is set on an underground beam located at the uppermost stage among the underground beams to be cut.

上記特徴構成によれば、切断作業空間が、切断対象の地下梁のうちの最上段に位置する地下梁の上に設定してあるので、パイプ材にワイヤーソーのワイヤーを挿通させた状態では、ワイヤーが上下方向に位置する複数本の地下梁の外周部に沿ってループ状に巻き付けられ、その結果、複数本の仮設地下梁を一挙に切断することができる。   According to the above characteristic configuration, since the cutting work space is set on the underground beam located at the top of the underground beams to be cut, in a state where the wire saw wire is inserted through the pipe material, A wire is wound in a loop shape along the outer periphery of a plurality of underground beams positioned in the vertical direction, and as a result, the plurality of temporary underground beams can be cut at a time.

地下構造物の要部の概略を示す縦断正面図Longitudinal front view showing the outline of the main part of the underground structure 図1におけるII−II矢視図II-II arrow view in FIG. 別実施形態の要部の概略を示す縦断側面図Longitudinal side view schematically showing the main part of another embodiment 別実施形態の要部の概略を示す横断平面図Cross-sectional plan view showing outline of main part of another embodiment 別実施形態の要部の概略を示す縦断正面図Longitudinal front view schematically showing the main part of another embodiment 別実施形態の要部の概略を示す縦断正面図Longitudinal front view schematically showing the main part of another embodiment

本発明実施形態を図面に基づいて説明する。
本発明、例えば、図1に示すように、既存の地下構造物の一部である既存壁1を土留め壁として残し、その既存壁1の内側に新たに地下構造物(本設地下構造物)2を新築する際などに実施される。
既存壁1を残して新たに地下構造物2を新築する場合、図示はしないが、既存壁1を土留め壁として残して既存の地下構造物を解体した後、その既存壁1の倒壊を防ぐため、既存壁1の内側に土壌などを投入して埋め戻し、例えば、形鋼からなる構真柱を打設して逆打ち工法により地下構造物2を構築することになる。
The embodiments of the present invention will be described with reference to the drawings.
The present invention is, for example, as shown in FIG. 1, leaving the existing wall 1 is part of an existing underground structures as earth retaining walls, new underground construction (the設地under construction on the inside of the existing wall 1 This will be done when building 2).
When a new underground structure 2 is newly built while leaving the existing wall 1, although not shown, the existing wall 1 is left as a retaining wall and the existing underground structure is demolished to prevent the existing wall 1 from collapsing. Therefore, soil etc. are thrown into the inside of the existing wall 1 and backfilled, for example, a structural pillar made of a shaped steel is placed, and the underground structure 2 is constructed by the reverse driving method.

逆打ち工法の実施においては、まず、埋め戻した土壌の上方部分を取り除いて、地下1階B1の空間部分と地下2階B2の上方空間部分を露出させ、構真柱(図示せず)の周りに鉄筋を配筋するとともに、地下梁用の鉄筋を配筋してコンクリートを打設し、地下1階B1部分の柱3aと地下1階B1と地下2階B2の間に位置する躯体部としての地下梁4を構築する。
躯体部としての地下梁4は、第1躯体部としての仮設地下梁4aと第2躯体部としての本設地下梁4bとを一体的に備えて構築され、仮設地下梁4aは、最終的に切断されて本設地下梁4bから分離され、必要な場合には、後述するように解体される。
In the reverse driving method, first, the upper portion of the backfilled soil is removed to expose the space portion of the first basement floor B1 and the upper space portion of the second basement floor B2, and the structure pillar (not shown) is exposed. Reinforcing bars around it, placing reinforcing bars for underground beams and placing concrete, and the frame part located between the pillar 3a of the B1 part of the first basement B1, the first basement B1 and the second basement B2 As an underground beam 4 is constructed.
The underground beam 4 as the frame part is constructed integrally with the temporary underground beam 4a as the first frame part and the permanent underground beam 4b as the second frame part. It is cut and separated from the main underground beam 4b and, if necessary, disassembled as described later.

すなわち、逆打ち工法では、地下構造物2の地下1階B1部分を構築した後、地下2階B2部分の土壌を取り除き、地下構造物2の地下2階B2部分を構築するのであり、それを順次繰り返すことになる。
その間、既存壁1の倒壊を防ぐため、本設地下梁4bと既存壁1との間に仮設地下梁4aを設けることが不可欠となる。しかし、そのまま放置すると、仮設地下梁4aを介して本設地下梁4bに、更には、新築した地下構造物2に対し既存壁1から予期しない荷重が作用することになるため、最終的に、仮設地下梁4aと本設地下梁4bとを切断して分離する必要がある。
That is, in the reverse driving method, after building the first basement B1 part of the underground structure 2, the soil of the second basement B2 part is removed and the second basement B2 part of the basement structure 2 is constructed. It will be repeated sequentially.
Meanwhile, in order to prevent the existing wall 1 from collapsing, it is indispensable to provide the temporary underground beam 4 a between the main underground beam 4 b and the existing wall 1. However, if left as it is, an unexpected load will act on the newly installed underground structure 2 from the existing wall 1 to the permanent underground beam 4b via the temporary underground beam 4a. It is necessary to cut and separate the temporary underground beam 4a and the main underground beam 4b.

そこで、図1に示すように、後日の切断に備えて、ワイヤーソー(図示せず)用のワイヤーW(図2参照)を挿通自在なCD管(合成樹脂可撓電線管)や金属管などのパイプ材5を切断箇所に予め設置しておくのである。
具体的には、地下2階B2部分の土壌を取り除いた後、補強壁6用の型枠を組んで、その型枠と既存壁1との間にコンクリートを打設して補強壁6を構築する。この補強壁6についても、既存壁1からの予期せぬ荷重の作用を回避するため、構築した補強壁6の表面(地下2階B2の内側表面)に絶縁用のポリスチレンフォーム、例えば、スタイロフォーム(ダウ化工(株)の商品名)からなる絶縁シート7を貼り、その絶縁シート7を貼った補強壁6を型枠の一部として、地下2階B2部分の柱3bおよび側壁(図示せず)を構築する。
Therefore, as shown in FIG. 1, a CD tube (synthetic resin flexible wire tube), a metal tube, or the like through which a wire W (see FIG. 2) for a wire saw (not shown) can be inserted in preparation for cutting at a later date. The pipe material 5 is previously installed at the cutting location.
Specifically, after removing the soil in the B2 part of the second basement, a formwork for the reinforcing wall 6 is assembled, and concrete is placed between the formwork and the existing wall 1 to construct the reinforcing wall 6 To do. Also for this reinforcing wall 6, in order to avoid an unexpected load from the existing wall 1, an insulating polystyrene foam, for example, a styrofoam (on the inner surface of the second floor B <b> 2), is provided on the surface of the constructed reinforcing wall 6. An insulating sheet 7 made of Dow Chemical Co., Ltd.) is attached, and the reinforcing wall 6 to which the insulating sheet 7 is attached is a part of the formwork, and the pillar 3b and the side wall (not shown) of the B2 portion of the basement 2nd floor. Build up.

この補強壁6の構築前または構築の途中において、切断箇所である第1躯体部としての仮設地下梁4aと第2躯体部としての本設地下梁4bとの境目外周部に沿う状態にパイプ材5を設置する。
パイプ材5は、その両端開口部5a、つまり、ワイヤーソーのワイヤーWの挿通用端部となる両端開口部5aが、ワイヤーソーを設置して切断作業を行う切断作業空間8側、図1に示す実施形態の場合には、地下1階B1側に位置する状態に設置する。
例えば、図2の(a)に示すように、補強壁6が仮設地下梁4aの上面と面一になるように構築する場合であれば、パイプ材5の両端開口部5aが補強壁6から上方の切断作業空間8へ突出するようにU字状に設置する。また、図2の(b)に示すように、補強壁6が仮設地下梁4aの下面と面一になる場合であれば、パイプ材5の両端開口部5aが補強壁6から上方の切断作業空間8へ突出するようにほぼ一直線状に設置するのである。
Before or during the construction of the reinforcing wall 6, the pipe material is brought into a state along the outer periphery of the boundary between the temporary underground beam 4 a as the first frame part and the permanent underground beam 4 b as the second frame part, which are cut portions. 5 is installed.
The pipe material 5 has both end openings 5a, that is, both end openings 5a serving as insertion ends of the wires W of the wire saw, on the side of the cutting work space 8 where the wire saw is installed to perform the cutting operation, FIG. In the case of the embodiment shown, it is installed in a state located on the first basement B1 side.
For example, as shown in FIG. 2 (a), when the reinforcing wall 6 is constructed so as to be flush with the upper surface of the temporary underground beam 4a, both end openings 5a of the pipe material 5 are separated from the reinforcing wall 6. It is installed in a U shape so as to protrude into the upper cutting work space 8. In addition, as shown in FIG. 2B, when the reinforcing wall 6 is flush with the lower surface of the temporary underground beam 4a, the both-end opening 5a of the pipe material 5 is cut upward from the reinforcing wall 6. It is installed in a substantially straight line so as to protrude into the space 8.

このようにして設置したパイプ材5を使用してワイヤーソーにより躯体部の一例である地下梁4を切断する躯体分離方法を実施するには、地下1階B1の切断作業空間8にワイヤーソー(図示せず)を設置し、ワイヤーソーのワイヤーWをパイプ材5の両端開口部5aの一方から他方へ挿通させて地下梁4の外周部にループ状に巻き付け、そのワイヤーWを使用してワイヤーソーによりパイプ材5と一緒に地下梁4を切断するのである。
その場合、パイプ材5が、第1躯体部である仮設地下梁4aと第2躯体部である本設地下梁4bとの境目外周部に沿って、かつ、柱3a、3bや本設地下梁4bなどにより構成される本設地下構造物2の外周面と面一になるように設置されているので、ワイヤーソーによる切断面は、本設地下構造物2の外周面と面一となる。
In order to carry out the case separation method of cutting the underground beam 4 which is an example of the case portion with the wire saw using the pipe material 5 thus installed, a wire saw ( (Not shown), wire W of the wire saw is inserted from one end of the both ends opening 5a of the pipe material 5 to the other and wound around the outer periphery of the underground beam 4 in a loop shape, and the wire W is used to wire The underground beam 4 is cut together with the pipe material 5 by a saw.
In that case, the pipe material 5 is formed along the outer periphery of the boundary between the temporary underground beam 4a that is the first frame part and the permanent underground beam 4b that is the second frame part, and the columns 3a and 3b and the permanent underground beam. Since it is installed so as to be flush with the outer peripheral surface of the permanent underground structure 2 constituted by 4b and the like, the cut surface by the wire saw is flush with the outer peripheral surface of the permanent underground structure 2.

また、上述したパイプ材5を使用してワイヤーソーにより躯体部の一例である地下梁4を切断し、切断した地下梁4の一部を解体するは、上述した躯体分離方法と同様に、地下1階B1の切断作業空間8にワイヤーソーを設置し、ワイヤーソーのワイヤーWをパイプ材5の両端開口部5aの一方から他方へ挿通させ、そのワイヤーWを使用してワイヤーソーにより地下梁4を切断する。
この場合にも、躯体分離方法の場合と同様に、躯体部である地下梁4は、仮設地下梁4aと本設地下梁4bとの境目に沿って、本設地下構造物2の外周面と面一となるように切断される。しかし、この法では、切断した仮設地下梁4aをそのまま放置するのではなく、例えば、完全に撤去するか、または、細かく粉砕して補強壁6の一部として使用することになる。
したがって、この法では、躯体部である地下梁4が、一部を解体する既存建物における梁に相当し、第1躯体部である仮設地下梁4aが、躯体部4のうちの解体対象となる解体梁となり、また、第2躯体部である本設地下梁4bが、躯体部4のうちの残置対象となる残置梁となる。
Further, by using the pipe member 5 described above by cutting the underground beams 4 which is an example of a skeleton portion by a wire saw, to dismantle part of the underground beams 4 cut, like the skeleton separation method described above, A wire saw is installed in the cutting work space 8 on the first basement floor B1, and the wire W of the wire saw is inserted from one end to the other end of the both ends 5a of the pipe material 5, and the wire W is used for the underground beam. 4 is cut.
Also in this case, as in the case of the case separation method, the underground beam 4 which is the frame part is arranged along the boundary between the temporary underground beam 4a and the permanent underground beam 4b. Cut to be flush. However, in this way, rather than as it left the temporary underground beams 4a cut, for example, either completely removed or made to be finely ground as part of the reinforcing wall 6.
Thus, in this method, underground beams 4 is a skeleton unit is equivalent to a beam in existing buildings to dismantle part, temporary underground beam 4a is first Mukuro body, and demolition subject of the skeleton portion 4 In addition, the main underground beam 4b, which is the second frame part, becomes the remaining beam to be left in the frame part 4.

〔別実施形態〕
(1)先の実施形態では、既存の地下構造物の一部である既存壁1をそのまま土留め壁として使用した例を示したが、本発明方法は、新たに土留め壁を構築する場合にも適用可能である。
また、体分離方法では、1本の地下梁4において、切断箇所である仮設地下梁4aと本設地下梁4bとの境目外周部にパイプ材5を設置し、ワイヤーソーのワイヤーWを使用して地下梁4を切断した例を示したが、例えば、図3に示すように、複数本の地下梁4にわたってパイプ材5をU字状に設置し、最上段に位置する地下梁4の上に切断作業空間8を設定して、複数本の地下梁4をその仮設地下梁4aと本設地下梁4bとの境目に沿って分離することもできる。
[Another embodiment]
(1) In the previous embodiment, the example in which the existing wall 1 which is a part of the existing underground structure is used as the retaining wall has been shown, but the method of the present invention is a case where a retaining wall is newly constructed. It is also applicable to.
Moreover, in the skeleton separation method, in one underground beams 4, the pipe 5 is placed in the boundary peripheral portion of the temporary underground beam 4a and the設地under the beam 4b is a cut portion, using a wire W of the wire saw In this example, the underground beam 4 is cut. For example, as shown in FIG. 3, the pipe material 5 is installed in a U shape over the plurality of underground beams 4, and the underground beam 4 positioned at the uppermost stage is It is also possible to set a cutting work space 8 above and to separate the plurality of underground beams 4 along the boundary between the temporary underground beam 4a and the permanent underground beam 4b.

(2)先の実施形態では、本発明方法を地下構造物2の地下梁4に適用した例を示したが、地上に新築する構造物にも適用することができる。例えば、図4および図5に示すように、鉄筋コンクリート製の柱12や床スラブ10、更には、鉄筋コンクリート製の壁11などを備えた地上構造物9の構築時において、将来、切断または解体の可能性のある床スラブ10や壁11の切断箇所に予めパイプ材5を設置しておくことも可能である。
この別実施形態の場合、床スラブ10や壁11の裏側に空間があるため、パイプ材5は床スラブ10や壁11を貫通する状態で一対ずつ設置することになる。そして、切断または解体の必要が生じたとき、切断作業空間8にワイヤーソーを設置し、一対ずつ設置したパイプ材5において、一方のパイプ材5の開口部5aからワイヤーWを挿入し、裏側の空間を通して、他のパイプ材5の開口部5aからワイヤーWを引き出して床スラブ10や壁11を切断するのである。
したがって、この別実施形態では、地上構造物9が躯体部に相当し、床スラブ10と壁11が第1躯体部に、柱12が第2躯体部に相当することになる。
(2) In the previous embodiment, an example in which the method of the present invention is applied to the underground beam 4 of the underground structure 2 has been shown, but it can also be applied to a structure newly built on the ground. For example, as shown in FIGS. 4 and 5, when a ground structure 9 including a reinforced concrete column 12, a floor slab 10 and a reinforced concrete wall 11 is constructed, it can be cut or disassembled in the future. It is also possible to install the pipe material 5 in advance at the cut portion of the floor slab 10 or the wall 11 having the property.
In the case of this another embodiment, since there is a space behind the floor slab 10 and the wall 11, a pair of pipe members 5 are installed in a state of penetrating the floor slab 10 and the wall 11. And when the necessity of cutting or dismantling arises, a wire saw is installed in the cutting work space 8, and in the pipe material 5 installed one by one, the wire W is inserted from the opening 5a of one pipe material 5, and the back side Through the space, the wire slab 10 and the wall 11 are cut by pulling the wire W from the opening 5a of the other pipe material 5.
Therefore, in this other embodiment, the ground structure 9 corresponds to the housing part, the floor slab 10 and the wall 11 correspond to the first housing part, and the pillar 12 corresponds to the second housing part.

更に、図6に示すように、地下に構築する構造物の壁11や梁13において、将来の切断または解体に備えて、その構築時に、一部の壁11や一部の梁13の裏側に地盤中を通る状態でパイプ材5を設置し、パイプ材5の両端開口部5aを切断作業空間8側に位置するように設置しておくことも可能である。また、図示はしないが、下方に位置する耐圧板に関しても、壁11や梁13と同様に、その裏側の地盤中を通る状態でパイプ材5を設置しておくこともできる。
この実施形態では、地下に構築する構造物が躯体部に相当し、一部の壁11と一部の梁13が第1躯体部に、残りの壁11と梁13が第2躯体部に相当することになる。
Further, as shown in FIG. 6, in the wall 11 and the beam 13 of the structure to be built underground, in preparation for future cutting or dismantling, the back side of some of the walls 11 and some of the beams 13 is provided at the time of the construction. It is also possible to install the pipe material 5 while passing through the ground, and to install both end openings 5a of the pipe material 5 on the cutting work space 8 side. Moreover, although not shown in figure, also about the pressure | voltage resistant board located below, the pipe material 5 can also be installed in the state which passes in the ground of the back side like the wall 11 and the beam 13.
In this embodiment, the structure constructed in the basement corresponds to the housing part, a part of the walls 11 and part of the beams 13 correspond to the first housing part, and the remaining walls 11 and the beams 13 correspond to the second housing part. Will do.

1 土留め壁
2 本設地下構造物
4 躯体部としての地下梁または既存構造物における梁
4a 第1躯体部としての仮設地下梁または解体梁
4b 第2躯体部としての本設地下梁または残置梁
5 パイプ材
5a パイプ材のワイヤー挿通用端部
8 切断作業空間
9 躯体部としての地上構造物
10 第1躯体部としての床スラブ
11 第1躯体部としての壁
12 第2躯体部としての柱
13 第1躯体部としての梁
W ワイヤーソー用のワイヤー
DESCRIPTION OF SYMBOLS 1 Earth retaining wall 2 Main underground structure 4 Underground beam as frame part or beam in existing structure 4a Temporary underground beam or demolition beam as first frame part 4b Main underground beam or remaining beam as second frame part DESCRIPTION OF SYMBOLS 5 Pipe material 5a End part for wire insertion of pipe material 8 Cutting work space 9 Ground structure as a frame part 10 Floor slab as a first frame part 11 Wall as a first frame part 12 Column as a second frame part 13 Beam as the first housing part W Wire for wire saw

Claims (2)

第1躯体部と第2躯体部とを一体に形成した躯体部において、ワイヤーソー用のワイヤーを挿通自在なパイプ材を、前記第1躯体部と前記第2躯体部との境目外周部に沿う状態に、かつ、前記パイプ材のワイヤー挿通用端部が前記ワイヤーソーによる切断作業空間側に位置する状態に設置する躯体分離用パイプ材の設置方法によって設置した前記パイプ材を使用して前記ワイヤーソーで前記躯体部を切断する躯体分離方法であって、
前記躯体部は、逆打ち工法の実施過程で設置する地下梁であり、前記第1躯体部は、本設地下梁となる前記第2躯体部から土留め壁側に突出した仮設地下梁であり、前記パイプ材を設置してある前記第1躯体部と前記第2躯体部との境目は、本設地下構造物の外周面と面一に設定してあり、前記切断作業空間に前記ワイヤーソーを設置するとともに、前記パイプ材に前記ワイヤーを挿通させて、そのワイヤーを使用して前記躯体部を切断する躯体分離方法。
In the case part in which the first case part and the second case part are integrally formed, a pipe material through which a wire for a wire saw can be inserted is provided along the boundary outer peripheral part between the first case part and the second case part. The wire using the pipe material installed by the installation method of the pipe material for separating the casing installed in a state and in a state where the wire insertion end of the pipe material is located on the cutting work space side by the wire saw A method of separating a casing by cutting the casing with a saw,
The frame part is an underground beam that is installed in the course of the reverse driving method, and the first frame part is a temporary underground beam that protrudes toward the retaining wall from the second frame part that is a permanent underground beam. The boundary between the first housing part and the second housing part in which the pipe material is installed is set to be flush with the outer peripheral surface of the main underground structure, and the wire saw is placed in the cutting work space. A housing separating method in which the wire is inserted through the pipe material and the housing portion is cut using the wire.
前記切断作業空間は、切断対象の前記地下梁のうち、最上段に位置する地下梁の上に設定する請求項に記載の躯体分離方法。 2. The housing separating method according to claim 1 , wherein the cutting work space is set on an underground beam located at an uppermost stage among the underground beams to be cut.
JP2013136536A 2013-06-28 2013-06-28 Housing separation method Active JP6179020B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013136536A JP6179020B2 (en) 2013-06-28 2013-06-28 Housing separation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013136536A JP6179020B2 (en) 2013-06-28 2013-06-28 Housing separation method

Publications (2)

Publication Number Publication Date
JP2015010387A JP2015010387A (en) 2015-01-19
JP6179020B2 true JP6179020B2 (en) 2017-08-16

Family

ID=52303789

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013136536A Active JP6179020B2 (en) 2013-06-28 2013-06-28 Housing separation method

Country Status (1)

Country Link
JP (1) JP6179020B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6006896B1 (en) * 2016-03-07 2016-10-12 環境商事株式会社 Temporary foundation, temporary foundation construction method, temporary foundation dismantling method, and concrete block

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0643368Y2 (en) * 1988-01-22 1994-11-14 前田建設工業株式会社 Structure of the crushed part of the concrete structure
JPH0642198A (en) * 1992-07-24 1994-02-15 Marushin Doro Kogyo:Kk Wire saw method
JP2972545B2 (en) * 1995-04-19 1999-11-08 戸田建設株式会社 Dismantling method of retaining wall

Also Published As

Publication number Publication date
JP2015010387A (en) 2015-01-19

Similar Documents

Publication Publication Date Title
KR20140055639A (en) A execution method of architecture beam
KR20180133748A (en) Earth retaining wall construction method using castinplace concrete pile of impermeable peristyle type
KR101674656B1 (en) CIP retaining wall with steel tube
JP2007162266A (en) Two-step earth retaining wall and its construction method
KR101521556B1 (en) Underground wall construction method using wall members
JP2005120663A (en) Structure of earth retaining wall
KR20100094140A (en) Wall structure capable of earth retaining and the building method of the same
JP6179020B2 (en) Housing separation method
KR100898969B1 (en) Tunnel Boring Method Using Sheet Pile and Tunnel Structure therof
JP5525850B2 (en) Mountain fastening method
KR101314764B1 (en) Retaining wall using corrugated steel plate and construction method thereof
KR101035404B1 (en) Slurry wall and slab junction structure and its using top-down construction method
KR101521558B1 (en) Underground wall construction method using the wall members
JP2009287172A (en) Method for constructing base-isolated building by inverted construction method
KR102072889B1 (en) Construction method of smallcaliber composite pile wall using small drilling rig at adjacent building proximity section
JP6768477B2 (en) How to build an underground structure
KR101385090B1 (en) Foundation Structure and the method of wall and cut off wall
JP5016521B2 (en) Earth anchor and its removal method
JP4407716B2 (en) Construction method of earth retaining wall
JP6265736B2 (en) Underground demolition method
JP2011157719A (en) Earth retaining method
KR20100138455A (en) Block for backfilling and method backfilling by that
KR101219451B1 (en) Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same
KR101047257B1 (en) Construction method of earth wall using composite sheet pile
KR101025179B1 (en) Reinforcement assembly and c.i.p. construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160328

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20161121

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20161129

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170130

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20170620

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20170627

R150 Certificate of patent or registration of utility model

Ref document number: 6179020

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150