JP5868352B2 - How to lay a road on the slope - Google Patents

How to lay a road on the slope Download PDF

Info

Publication number
JP5868352B2
JP5868352B2 JP2013121932A JP2013121932A JP5868352B2 JP 5868352 B2 JP5868352 B2 JP 5868352B2 JP 2013121932 A JP2013121932 A JP 2013121932A JP 2013121932 A JP2013121932 A JP 2013121932A JP 5868352 B2 JP5868352 B2 JP 5868352B2
Authority
JP
Japan
Prior art keywords
road
row
sandbag
sand
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2013121932A
Other languages
Japanese (ja)
Other versions
JP2014237980A (en
Inventor
良輔 山内
良輔 山内
大悟 石井
大悟 石井
勝則 小拂
勝則 小拂
Original Assignee
旭化成ジオテック株式会社
大分綜合建設株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 旭化成ジオテック株式会社, 大分綜合建設株式会社 filed Critical 旭化成ジオテック株式会社
Priority to JP2013121932A priority Critical patent/JP5868352B2/en
Publication of JP2014237980A publication Critical patent/JP2014237980A/en
Application granted granted Critical
Publication of JP5868352B2 publication Critical patent/JP5868352B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Description

本発明は、法面に道路を敷設する方法に関する。より詳しくは、本発明は、大型土嚢、ジオグリッド、及びコンクリート型枠を用いて、法面(斜面)に道路、例えば、林道を開削する工法に関する。   The present invention relates to a method for laying a road on a slope. More specifically, the present invention relates to a method of excavating a road, for example, a forest road, on a slope (slope) using a large sandbag, geogrid, and concrete formwork.

従来、法面(斜面)に林道、道路、鉄道等を開削するには、油圧ショベル等の重機を用いて、法面の土砂を掘削し、掘削により発生した土砂を、道路築造方向の後方の仮置き場に運搬し、さらに、道路築造方向に向かって、路面となる略水平な盛土を構築するために、再び土砂等を、運搬するという工法が採られてきた。かかる工法においては、土砂を掘削現場から仮置き場まで、また、仮置き場から盛土構築現場まで運搬するという作業が必要となる。更に、土砂の仮置き場となる一定スペースの確保が必要である。   Conventionally, in order to excavate forest roads, roads, railways, etc. on a slope (slope), excavate the slope with heavy equipment such as a hydraulic excavator, and remove the sediment generated by excavation in the rear of the road construction direction. In order to construct a substantially horizontal embankment that becomes a road surface in the direction of road construction, a method of conveying earth and sand again has been adopted. In this construction method, it is necessary to carry the earth and sand from the excavation site to the temporary storage site and from the temporary storage site to the embankment construction site. Furthermore, it is necessary to secure a certain space for temporary storage of earth and sand.

以下に挙げるように、従来、盛土を構築するために土嚢やジオテキスタイル等を用いることは知られている。
以下の特許文献1には、通水性を有する撓性のシート状体の平面部の端部を折り返してループ状部を形成し、少なくとも通気性を有する撓性のシート状体で、閉塞した袋体を形成し、この袋体を前記ループ状部内に設置し、袋体に設けた注入口から袋体内に充填材を圧送により充填して土嚢を成形し、この土嚢の前記シート状体平面部上に盛土を行い、この盛土部の縁部に沿って型枠を組み立て、型枠内にコンクリートを打設して剛体壁を構築し、一端にフックを有する連結棒を用い、この連結棒のフックを土嚢に引っ掛け、他端を剛体壁に定着して剛体壁と土嚢を連結した、盛土の築造方法が開示されている。
As described below, conventionally, it is known to use sandbags or geotextiles for constructing embankments.
In Patent Document 1 below, a bag that is closed with a flexible sheet-like body having air permeability is formed by folding an end portion of a flat portion of the flexible sheet-like body having water permeability to form a loop-like portion. Forming a body, placing the bag body in the loop-shaped portion, filling the bag body with a filler from an injection port provided in the bag body to form a sandbag, and forming the sheet-like body plane portion of the sandbag Filling up, assembling a mold along the edge of the bank, constructing a rigid wall by placing concrete in the mold, and using a connecting rod with a hook at one end, An embankment construction method is disclosed in which a hook is hooked on a sandbag, the other end is fixed to a rigid wall, and the rigid wall and the sandbag are connected.

また、以下の特許文献2には、法面を形成する盛土端部が、土嚢等のブロック体が積み重ねられてなる擁壁により構成され、かつ該擁壁の背面側に土砂等の盛土材が転圧されてなる盛土であって、該盛土内には、ほぼ水平方向に延在するジオテキスタイルが前記擁壁を所定高さ毎に上下方向より包み込む如く多層に埋設され、しかも、これらジオテキスタイルの端部は所定層置きに前記擁壁の充分後方にて終端されていることを特徴とする急勾配盛土が開示されている。   Moreover, in the following patent document 2, the embankment edge part which forms a slope is comprised by the retaining wall on which block bodies, such as a sandbag, are piled up, and embankment materials, such as earth and sand, are on the back side of this retaining wall. In the embankment, the geotextile extending in a substantially horizontal direction is embedded in multiple layers so as to wrap the retaining wall in a vertical direction at a predetermined height, and the ends of these geotextiles. A steep embankment is disclosed in which the portions are terminated sufficiently behind the retaining wall in predetermined layers.

また、以下の特許文献3には、周縁の少なくとも一部を剛性材料で構成し、強度・可撓性・透水性がある素材からなる大型の容器に、土を充填し、次いで、法面に敷設する斜面安定工法において、上記容器は、盛土内に略水平方向、層状に敷設されたジオグリッド材などのアンカー材に連結されたことを特徴とする、斜面安定工法が開示されている。   Further, in Patent Document 3 below, at least a part of the periphery is made of a rigid material, a large container made of a material having strength, flexibility, and water permeability is filled with soil, and then, on the slope. In the slope stabilization method for laying, a slope stabilization method is disclosed in which the container is connected to an anchor material such as a geogrid material laid in layers in a substantially horizontal direction in the embankment.

また、以下の特許文献4には、土嚢を積み上げて斜面を造成する土留工法において、縦横に積み重ねた複数個の土嚢上面に、複数の掛止用長穴を開口した鋼板を、コの字形に形成した鋼棒の曲折部間に固定して成る足脚掛止用アンカーの複数個を、所要の間隔にて載置するとともに、積み重ねた前記土嚢と前記アンカーとを網にて斜面側から一体的に包み込み、包み込む際の網の緊張力にてアンカーの突出端を斜面位置まで押し込むことによりアンカーを土嚢間に固定し、長手方向の中間部分及び下端に掛止ピンを固定した足脚の掛止ピンそれぞれを、アンカーに開口した長穴に掛止し、一方、足脚の上端に接続部材を介して曲折可能にフェンス軸を接続するとともに、該フェンス軸相互間にフェンスを構築する土留工法が開示されている。   Further, in Patent Document 4 below, in the earth retaining method in which sandbags are piled up to form a slope, a steel plate having a plurality of retaining holes opened on a plurality of sandbags stacked vertically and horizontally in a U-shape. A plurality of anchors for anchoring leg legs, which are fixed between the bent portions of the formed steel bars, are placed at a required interval, and the sandbags and the anchors stacked are integrated from the slope side with a net. The anchor is fixed between the sandbags by pushing the protruding end of the anchor to the slope position by the tension of the net when wrapping, and the hook of the leg with the latch pin fixed at the middle part and the lower end in the longitudinal direction Each retaining pin is hooked into a long hole opened in the anchor, and on the other hand, a fence shaft is connected to the upper end of the leg leg so that it can be bent via a connecting member, and a fence is constructed between the fence shafts. Is disclosed.

また、以下の特許文献5には、最外壁として大型土嚢を積み上げ、その内側は、大型土嚢の各段に対応して改良土壁、及びその内側に盛土を敷設し、これらの表面を転圧してジオグリッドを敷設し、順次これらを層状に形成して急勾配盛土を構築することを特徴とする急勾配盛土造成方法、及び前記大型土嚢の一段に対して、その内側の前記改良土壁、盛土、ジオグリッドが一層となるように順次対応して形成される該急勾配盛土の造成方法が開示されている。   Further, in Patent Document 5 below, a large sandbag is stacked as the outermost wall, and an inner side of the large sandbag is provided with an improved soil wall corresponding to each step of the large sandbag, and an embankment is laid on the inside, and these surfaces are rolled. A steep slope embankment construction method characterized by laying a geogrid and sequentially forming these layers in a layered manner, and the improved soil wall inside the large sandbag, There is disclosed a method for creating the steep embankment that is formed so as to correspond to the embankment and the geogrid in order.

さらに、以下の特許文献6には、地山ののり面に配置される大型土のうの上に袋体をのり肩からのり尻にかけて配置し、前記袋体に前記のり肩側から充填材を充填し、前記地山と前記袋体の型枠との間に定着材を配置することにより壁体を構築することを特徴とする袋体を用いた壁面工構築方法が開示されている。   Further, in Patent Document 6 below, a bag body is placed on a large sandbag placed on a slope surface of a natural mountain from the shoulder to the bottom of the shoulder, and the bag body is filled with filler from the shoulder side. A wall surface construction method using a bag body is disclosed in which a wall body is constructed by disposing a fixing material between the natural ground and the formwork of the bag body.

このように、盛土の構築において、大型土嚢を積み上げて擁壁を構築すること、擁壁の後方においてジオグリッド等を用いることは知られている。   Thus, in the construction of embankment, it is known to build a retaining wall by stacking large sandbags, and to use a geogrid or the like behind the retaining wall.

特開平02−164921号公報Japanese Patent Laid-Open No. 02-164921 特開平03−069721号公報Japanese Patent Laid-Open No. 03-069721 特開平05−171652号公報JP 05-171652 A 特開平10−183626号公報JP-A-10-183626 特開2003−082666号公報JP 2003-082666 A 特開2011−094443号公報JP 2011-094443 A

前記したように、盛土の構築において、大型土嚢を積み上げて擁壁を構築すること、擁壁の後方においてジオグリッド等を用いることは知られている。しかしながら、法面(斜面)に林道、道路、鉄道等を開削するには、油圧ショベル等の重機を用いて、法面の土砂を掘削し、掘削により発生した土砂を、道路築造方向の後方の仮置き場に運搬し、さらに、道路築造方向に向かって、路面となる略水平な盛土を構築するために、再び土砂等を、運搬するという従来工法において、土砂を掘削現場から仮置き場まで、また、仮置き場からも盛土構築現場まで運搬するという作業を不要とする工法は、未だ提案されていない。
かかる状況下、本発明が解決しようとする課題は、法面(斜面)に道路、例えば、林道を開削するに際し、土砂を掘削現場から仮置き場まで、また、仮置き場から盛土構築現場まで運搬するという作業を不要とする工法を提供することである。
As described above, in the construction of embankment, it is known to build a retaining wall by stacking large sandbags, and to use a geogrid or the like behind the retaining wall. However, in order to excavate forest roads, roads, railways, etc. on slopes (slopes), excavate soil on the slopes using heavy machinery such as hydraulic excavators, and remove the sediment generated by excavation in the rear of the road construction direction. In the conventional method of transporting earth and sand again in order to construct a substantially horizontal embankment that becomes the road surface in the direction of road construction in the direction of road construction, earth and sand are transported again from the excavation site to the temporary storage site. A construction method that does not require the work of transporting from the temporary storage to the embankment construction site has not been proposed yet.
Under such circumstances, the problem to be solved by the present invention is to transport the earth and sand from the excavation site to the temporary storage site and from the temporary storage site to the embankment construction site when excavating a road, such as a forest road, on a slope (slope). It is to provide a construction method that eliminates the need for such work.

発明者らは、鋭意検討し実験を重ねた結果、以下の工程を含む開削工法により前記課題を解決しうることを見出し、本発明を完成するに至ったものである。
すなわち、本発明は以下のとおりのものである。
[1]法面(斜面)に道路を敷設するための開削工法であって、以下の工程:
(1)該道路敷設予定地近傍の草木を伐採し;
(2)油圧ショベルを用いて該草木を伐採した法面を掘削して、該道路の路面と並列する略水平な面を形成し、該掘削により発生した土砂を大型土嚢に充填し、該土砂を充填した大型土嚢を、該略水平な面上の法面端部に沿って1又は2段載置し、該載置された大型土嚢と地山との隙間に、該載置された大型土嚢の上面と略同一高さとなるまで土砂を充填し、該同一高さに、該油圧ショベルの作業場となる所定面積の略水平な仮設ステージを構築し;
(3)必要により鋼板を敷いた前記仮設ステージ上に、前記油圧ショベルを移動し、該仮設ステージの上方又は下方の法面を、該油圧ショベルのアームが届く範囲で、段切りし、該段切り作業において発生した土砂を複数の大型土嚢に充填して、該土砂が充填された複数の大型土嚢を該仮設ステージ上に仮置きし;
(4)工程(3)において土砂が充填された複数の大型土嚢の一部を、前記段切りした法面の最下段上に、前記道路の敷設方向に沿って整列するように載置し、該載置された大型土嚢と、前記段切りされた地山との隙間に、現場発生土、栗石又は廃棄物を、該大型土嚢の上面と略同一高さとなるまで充填し、転圧して略水平面とし、該略水平面上に、かつ、該段切りされた地山に跨って、ジオグリッドを敷設して、1列目1段を構築し;
(5)前記1列目1段の上に、工程(3)において土砂が充填された複数の大型土嚢の残部を、前記道路の敷設方向に沿って一列で整列するように載置し、該載置された大型土嚢と、前記段切りされた地山との隙間に、現場発生土、栗石又は廃棄物を、該大型土嚢の上面と略同一高さとなるまで充填し、転圧して略水平面とし、該略水平面上に、かつ、該段切りされた地山に跨って、ジオグリッドを敷設して、1列目2段を構築し;
(6)工程(5)を(n−2)回繰り返して、1列目n段(nは2以上の整数)を構築し;
(7)工程(4)〜(6)において整列された大型土嚢の側面側に、コンクリート型枠を、前記1〜n段の各段に敷設されたジオグリッドの端部に固定手段を用いて固定し、該コンクリート型枠と該大型土嚢の側面との間にコンクリートを充填し、コンクリート側壁を構築して、前記道路の敷設方向に向かって1列目を完成させ;
(8)工程(1)〜(7)を(m−1)回繰り返して、前記道路の敷設方向に向かってm列目(mは1以上の整数)を完成させ;
(9)完成した1〜m列に亘って、n段上に、現場発生土、栗石又は路面材を、被せ、転圧し、路面を構築して、法面に道路を開削する;
を含む、前記工法。
As a result of intensive studies and experiments, the inventors have found that the above problems can be solved by a cutting method including the following steps, and have completed the present invention.
That is, the present invention is as follows.
[1] An excavation method for laying a road on a slope (slope), the following steps:
(1) Cutting down vegetation near the planned site for road construction;
(2) Excavating the slope from which the vegetation was cut using a hydraulic excavator to form a substantially horizontal plane parallel to the road surface of the road, filling the large sandbag with the earth and sand generated by the excavation, Is placed in one or two steps along the sloped end on the substantially horizontal surface, and the placed large sandbag is placed in a gap between the placed large sandbag and the ground. Filling the sand until it is almost the same height as the top surface of the sandbag, and constructing a substantially horizontal temporary stage of a predetermined area to be a working place of the hydraulic excavator at the same height;
(3) The hydraulic excavator is moved onto the temporary stage on which a steel plate is laid if necessary, and the upper or lower slope of the temporary stage is cut within a range that the arm of the hydraulic excavator can reach. Filling a plurality of large sandbags with the earth and sand generated in the cutting operation, and temporarily placing the plurality of large sandbags filled with the sand and sand on the temporary stage;
(4) A part of the plurality of large sandbags filled with earth and sand in the step (3) is placed on the lowest step of the stepped slope so as to be aligned along the laying direction of the road, The gap between the placed large sandbag and the stepped ground is filled with the soil generated in the field, chestnut stone or waste until it is approximately the same height as the upper surface of the large sandbag, and is compacted by rolling. Construct a horizontal plane, lay a geogrid on the substantially horizontal plane and straddle the cut ground, and build the first row and the first row;
(5) The remaining portions of the plurality of large sandbags filled with earth and sand in the step (3) are placed on the first row and the first row so as to be aligned in a row along the laying direction of the road, The gap between the placed large sandbag and the stepped ground is filled with on-site generated soil, chestnut stone or waste until it is approximately the same height as the upper surface of the large sandbag, and is rolled to a substantially horizontal plane. And laying a geogrid on the substantially horizontal plane and straddling the cut ground, and constructing the first row and the second row;
(6) Step (5) is repeated (n-2) times to construct the first row and n stages (n is an integer of 2 or more);
(7) Using concrete means on the side of the large sandbag aligned in steps (4) to (6), and fixing means at the end of the geogrid laid on each of the 1 to n stages Fixing, filling concrete between the concrete formwork and the side of the large sandbag, constructing concrete side walls, and completing the first row in the direction of laying the road;
(8) Steps (1) to (7) are repeated (m-1) times to complete the m-th row (m is an integer of 1 or more) toward the road laying direction;
(9) Over the completed 1 to m rows, the n-stage top is covered with ground-generated soil, crushed stone or road surface material, rolled, and the road surface is constructed, and the road is cut to the slope;
The said construction method containing.

[2]前記工程(7)を、n段完成時に代えて、各段又はk段(但し、k<n)完成時毎に、実施する、前記[1]に記載の工法。   [2] The method according to [1], wherein the step (7) is performed at the completion of each stage or k stages (where k <n) instead of at the completion of the n stages.

[3]1列完成毎に、仮設ステージ及び該仮設ステージ下に載置した大型土嚢を、撤去し、必要により、撤去した大型土嚢を、次列目の構築に使用する、前記[1]又は[2]に記載の工法。   [3] Every time one row is completed, the temporary stage and the large sandbag placed under the temporary stage are removed, and if necessary, the removed large sandbag is used for the construction of the next row, [1] or The construction method according to [2].

[4]前記道路の路面幅が、約3〜4mである、前記[1]〜[3]のいずれかに記載の工法。   [4] The construction method according to any one of [1] to [3], wherein a road surface width of the road is about 3 to 4 m.

[5]前記コンクリート型枠は、ラス型枠である、前記[1]〜[4]のいずれかに記載の工法。   [5] The method according to any one of [1] to [4], wherein the concrete formwork is a lath formwork.

本発明に係る開削工法においては、掘削により発生した土砂を充填した大型土嚢を用いて仮設ステージを作ることにより、掘削により発生した土砂を、道路築造後方に運搬、仮置き等する必要は原則としてない。また、現地で発生した土砂を大型土嚢に充填し、これを、道路築造方向への盛土の構築に使用することができるので、重機が道路築造方向に出て行くことができ、また、掘削により発生した大量の土砂を、道路築造後方に運搬、仮置き等する必要がない。さらに、コンクリート側壁とジオグリッドが固定されるのでプロック等のように金具がいらない。さらに、コンクリート側壁の構築に、ラス型枠を使用した場合には、打設時の側圧(液圧)が低くなり、また、大きな鋼管支持等が不要であり、さらに、コンクリート打設面がギザギザなので、自然の蔦や苔が生え自然にマッチするのが早い。さらに、載置された大型土嚢と、段切りされた地山との隙間に、廃棄物等を充填することができるので、廃棄物等の有効活用が図れる。   In the open-cut method according to the present invention, as a general rule, it is necessary to transport and temporarily place the earth and sand generated by excavation to the rear of the road by making a temporary stage using a large sandbag filled with earth and sand generated by excavation. Absent. In addition, large sandbags filled with earth and sand generated locally can be used for construction of embankments in the direction of road construction, so that heavy machinery can go out in the direction of road construction. There is no need to transport or temporarily store the large amount of generated earth and sand behind the road. Furthermore, since the concrete side wall and geogrid are fixed, there is no need for metal fittings such as Plock. In addition, when a lath formwork is used to construct a concrete side wall, the lateral pressure (hydraulic pressure) at the time of casting is low, and a large steel pipe support is not required, and the concrete casting surface is jagged. So, natural cocoons and moss grow quickly to match nature. Furthermore, since a waste etc. can be filled into the clearance gap between the mounted large sandbag and the cut ground, the waste can be effectively used.

道路を開削しようとする地山の法面の勾配を示す断面図である。It is sectional drawing which shows the slope of the slope of the natural ground which is going to excavate a road. 法面に開削しようとする道路の計画位置を示す態を示す断面図である。It is sectional drawing which shows the state which shows the planned position of the road which is going to excavate on a slope. 仮設ステージと段切り上に載置された土嚢の位置関係を示す概略図である。It is the schematic which shows the positional relationship of the sandbag placed on the temporary stage and the stage cut. 大型土嚢が3段積まれた状態を示す概略図である。It is the schematic which shows the state in which the large sandbag was piled up in three steps. 大型土嚢が、4段、すなわち、開削計画位置まで、積まれた状態を示す概略図である。It is the schematic which shows the state in which the large sandbag was piled up to 4 steps | paragraphs, ie, an excavation plan position. 法面を側面から見て、道路敷設方向に沿って1列〜m列に開削が進行する状態を説明する概略図である。It is the schematic explaining the state which excavation advances to 1 row-m row along a road laying direction seeing a slope from a side. 大型土嚢の上面にジオグリッドが敷設され、ラス型枠が大型土嚢の側面側に固定された状態を示す概略図である。It is the schematic which shows the state by which the geogrid was laid on the upper surface of a large sandbag, and the lath formwork was fixed to the side surface side of a large sandbag. ジオグリッドの端部を折り返し、折り返し部に鉄筋を挿入した状態を示す概略図である。It is the schematic which shows the state which turned up the edge part of a geogrid and inserted the reinforcing bar in the turned-up part. 鉄筋とラス型枠を固定するための鋼管と番線で固定した状態を説明する概略図である。It is the schematic explaining the state fixed with the steel pipe and number wire for fixing a reinforcing bar and a lath formwork. ラス型枠と大型土嚢の側面との間にコンクリート側壁を構築し、必要により作業足場を設けた状態を示す概略図である。It is the schematic which shows the state which constructed | assembled the concrete side wall between the lath formwork and the side surface of the large sandbag, and provided the work scaffold as needed.

以下、本発明を詳細に説明する。
本発明は、法面(斜面)に道路を敷設するための開削工法であって、以下の工程:
(1)該道路敷設予定地近傍の草木を伐採し;
(2)油圧ショベルを用いて該草木を伐採した法面を掘削して、該道路の路面と並列する略水平な面を形成し、該掘削により発生した土砂を大型土嚢に充填し、該土砂を充填した大型土嚢を、該略水平な面上の法面端部に沿って1又は2段載置し、該載置された大型土嚢と地山との隙間に、該載置された大型土嚢の上面と略同一高さとなるまで土砂を充填し、該同一高さに、該油圧ショベルの作業場となる所定面積の略水平な仮設ステージを構築し;
(3)必要により鋼板を敷いた前記仮設ステージ上に、前記油圧ショベルを移動し、該仮設ステージの上方又は下方の法面を、該油圧ショベルのアームが届く範囲で、段切りし、該段切り作業において発生した土砂を複数の大型土嚢に充填して、該土砂が充填された複数の大型土嚢を該仮設ステージ上に仮置きし;
(4)工程(3)において土砂が充填された複数の大型土嚢の一部を、前記段切りした法面の最下段上に、前記道路の敷設方向に沿って整列するように載置し、該載置された大型土嚢と、前記段切りされた地山との隙間に、現場発生土、栗石又は廃棄物を、該大型土嚢の上面と略同一高さとなるまで充填し、転圧して略水平面とし、該略水平面上に、かつ、該段切りされた地山に跨って、ジオグリッドを敷設して、1列目1段を構築し;
(5)前記1列目1段の上に、工程(3)において土砂が充填された複数の大型土嚢の残部を、前記道路の敷設方向に沿って一列で整列するように載置し、該載置された大型土嚢と、前記段切りされた地山との隙間に、現場発生土、栗石又は廃棄物を、該大型土嚢の上面と略同一高さとなるまで充填し、転圧して略水平面とし、該略水平面上に、かつ、該段切りされた地山に跨って、ジオグリッドを敷設して、1列目2段を構築し;
(6)工程(5)を(n−2)回繰り返して、1列目n段(nは2以上の整数)を構築し;
(7)工程(4)〜(6)において整列された大型土嚢の側面側に、コンクリート型枠を、前記1〜n段の各段に敷設されたジオグリッドの端部に固定手段を用いて固定し、該コンクリート型枠と該大型土嚢の側面との間にコンクリートを充填し、コンクリート側壁を構築して、前記道路の敷設方向に向かって1列目を完成させ;
(8)工程(1)〜(7)を(m−1)回繰り返して、前記道路の敷設方向に向かってm列目(mは1以上の整数)を完成させ;
(9)完成した1〜m列に亘って、n段上に、現場発生土、栗石又は路面材を、被せ、転圧し、路面を構築して、法面に道路を開削する;
を含む、前記工法に関する。
Hereinafter, the present invention will be described in detail.
The present invention is an excavation method for laying a road on a slope (slope), and includes the following steps:
(1) Cutting down vegetation near the planned site for road construction;
(2) Excavating the slope from which the vegetation was cut using a hydraulic excavator to form a substantially horizontal plane parallel to the road surface of the road, filling the large sandbag with the earth and sand generated by the excavation, Is placed in one or two steps along the sloped end on the substantially horizontal surface, and the placed large sandbag is placed in a gap between the placed large sandbag and the ground. Filling the sand until it is almost the same height as the top surface of the sandbag, and constructing a substantially horizontal temporary stage of a predetermined area to be a working place of the excavator at the same height;
(3) The hydraulic excavator is moved onto the temporary stage on which a steel plate is laid if necessary, and the upper or lower slope of the temporary stage is cut within a range that the arm of the hydraulic excavator can reach. Filling a plurality of large sandbags with the earth and sand generated in the cutting operation, and temporarily placing the plurality of large sandbags filled with the sand and sand on the temporary stage;
(4) A part of the plurality of large sandbags filled with earth and sand in the step (3) is placed on the lowest step of the stepped slope so as to be aligned along the laying direction of the road, The gap between the placed large sandbag and the stepped ground is filled with the soil generated in the field, chestnut stone or waste until it is approximately the same height as the upper surface of the large sandbag, and is compacted by rolling. Construct a horizontal plane, lay a geogrid on the substantially horizontal plane and straddle the cut ground, and build the first row and the first row;
(5) The remaining portions of the plurality of large sandbags filled with earth and sand in the step (3) are placed on the first row and the first row so as to be aligned in a row along the laying direction of the road, The gap between the placed large sandbag and the stepped ground is filled with on-site generated soil, chestnut stone or waste until it is approximately the same height as the upper surface of the large sandbag, and is rolled to a substantially horizontal plane. And laying a geogrid on the substantially horizontal plane and straddling the cut ground, and constructing the first row and the second row;
(6) Step (5) is repeated (n-2) times to construct the first row and n stages (n is an integer of 2 or more);
(7) Using concrete means on the side of the large sandbag aligned in steps (4) to (6), and fixing means at the end of the geogrid laid on each of the 1 to n stages Fixing, filling concrete between the concrete formwork and the side of the large sandbag, constructing concrete side walls, and completing the first row in the direction of laying the road;
(8) Steps (1) to (7) are repeated (m-1) times to complete the m-th row (m is an integer of 1 or more) toward the road laying direction;
(9) Over the completed 1 to m rows, the n-stage top is covered with ground-generated soil, crushed stone or road surface material, rolled, and the road surface is constructed, and the road is cut to the slope;
It is related with the said construction method containing.

以下、本発明に係る開削工法を、図面を参照しながら説明する。
図1は、道路を開削しようとする地山の法面の勾配を示す断面図である。図1中では、地山Aの法面の法勾配は、1:1.00であるが、かかる法勾配は特に制限されない。
図2は、かかる地山Aの法面に開削しようとする道路の計画位置Bを示す断面図である。中央の水平部が、敷設しようとする道路等の路面となる場所であり、その幅は、特に制限されないが、約3〜4mであることができる。本発明に係る開削工法においては、該水平部上の土砂が、該水平部下に、土嚢に充填された形態で、以下に説明する列毎に、移動されることになる。
Hereinafter, the cutting method according to the present invention will be described with reference to the drawings.
FIG. 1 is a cross-sectional view showing the slope of a slope of a natural mountain to be excavated on a road. In FIG. 1, the slope of the slope of the natural ground A is 1: 1.00, but the slope is not particularly limited.
FIG. 2 is a cross-sectional view showing a planned position B of a road to be excavated on the slope of the natural ground A. The central horizontal portion is a place to be a road surface such as a road to be laid, and the width is not particularly limited, but can be about 3 to 4 m. In the excavation method according to the present invention, the earth and sand on the horizontal portion are moved for each row described below in a form filled with sandbags below the horizontal portion.

図3は、仮設ステージと段切り上に載置された土嚢の位置関係を示す概略図である。本発明においては、道路敷設予定地近傍の草木を伐採し;油圧ショベルを用いて該草木を伐採した法面を掘削して、該道路の路面と並列する略水平な面を形成し、該掘削により発生した土砂を大型土嚢に充填し、該土砂を充填した大型土嚢を、該略水平な面上の法面端部に沿って1又は2段載置し、該載置された大型土嚢と地山との隙間に、該載置された大型土嚢の上面と略同一高さとなるまで土砂を充填し、該同一高さに、該油圧ショベルの作業場となる所定面積の略水平な仮設ステージを構築する。大型土壌に充填される土砂に草木が混入すると大型土嚢の形状が経時変化する場合があるので、道路敷設予定地近傍の草木は予め伐採しておくことが好ましい。   FIG. 3 is a schematic diagram showing the positional relationship between the temporary stage and the sandbag placed on the stage cut. In the present invention, the vegetation in the vicinity of the planned road laying site is cut down; the slope from which the vegetation is cut down is excavated using a hydraulic excavator to form a substantially horizontal plane parallel to the road surface of the road; A large sandbag filled with the sand and sand, and the large sandbag filled with the sand and sand is placed in one or two steps along the slope end on the substantially horizontal surface, and the placed large sandbag and The earth and sand are filled in the gap with the natural ground until the top surface of the placed large sandbag is approximately the same height, and a substantially horizontal temporary stage having a predetermined area serving as a work place of the excavator is provided at the same height. To construct. Since the shape of the large sandbag may change with time when vegetation is mixed in the soil filled in the large soil, it is preferable to cut the vegetation in the vicinity of the planned road laying site in advance.

次いで、必要により鋼板を敷いた前記仮設ステージ上に、前記油圧ショベルを移動し、該仮設ステージの上方又は下方の法面を、該油圧ショベルのアームが届く範囲で、段切りし、該段切り作業において発生した土砂を複数の大型土嚢に充填して、該土砂が充填された複数の大型土嚢を該仮設ステージ上に仮置きし;土砂が充填された複数の大型土嚢の一部を、前記段切りした法面の最下段上に、前記道路の敷設方向に沿って整列するように載置し、該載置された大型土嚢と、前記段切りされた地山との隙間に、現場発生土、栗石又は廃棄物を、該大型土嚢の上面と略同一高さとなるまで充填し、転圧して略水平面とし、該略水平面上に、かつ、該段切りされた地山に跨って、ジオグリッドを敷設して、1列目1段を構築する。図3は、仮設ステージの下に大型土嚢を2段載置し、また、仮設ステージの下方の法面を段切りし、土砂が充填された複数の大型土嚢の一部を、段切りした法面の最下段、及び次の段(2段)に、載置し、さらに、段切りされた地山との隙間に、栗石を、該2段目の大型土嚢の上面と略同一高さとなるまで充填し、転圧して略水平面とし、該略水平面上に、かつ、該段切りされた地山に跨って、ジオグリッドを敷設して、1列目2段を構築した状態を示している。   Next, the hydraulic excavator is moved onto the temporary stage on which a steel plate is laid if necessary, and the upper or lower slope of the temporary stage is cut within a range that the arm of the hydraulic excavator reaches, and the step cutting is performed. Filling a plurality of large sandbags with the earth and sand generated in the work, and temporarily placing the plurality of large sandbags filled with the sand and sand on the temporary stage; a part of the plurality of large sandbags filled with earth and sand; Placed on the lowest step of the stepped slope so as to align along the road laying direction, and generated in the field in the gap between the placed large sandbag and the stepped ground Fill the soil, chestnut or waste with the same level as the upper surface of the large sandbag, roll it into a substantially horizontal plane, and on the substantially horizontal plane and straddling the stepped ground, Laying the grid and constructing the first row and the first row. FIG. 3 shows a method in which two large sandbags are placed under the temporary stage, the slope below the temporary stage is stepped, and a part of a plurality of large sandbags filled with earth and sand is stepped. Place the chestnut stone on the lowest level of the surface and the next level (2 levels), and the gap between the cut ground and the top surface of the large sandbag of the second level. It is shown that the first row and the second row are constructed by laying a geogrid on the substantially horizontal surface and straddling the stepped natural ground. .

前記計画位置Bの水平面に至るまで、前記工程を繰り返して、1列目n段を完成させる。図4は、大型土嚢が3段積まれた状態を示す概略図であり、また、図5は、大型土嚢が、4段、すなわち、開削計画位置Bまで、積まれた状態を示す概略図である。   The above steps are repeated until the horizontal plane of the planned position B is reached, and the first row and n stages are completed. FIG. 4 is a schematic diagram showing a state in which large sandbags are stacked in three stages, and FIG. 5 is a schematic diagram showing a state in which large sandbags are stacked in four stages, that is, up to the planned cutting position B. is there.

以下、本発明に係る開削工法における「列」の概念を説明する。
図6は、法面を側面から見て、道路敷設方向に沿って1列〜m列に開削が進行する状態を説明する概略図である。図3に示すように、仮設ステージ上の油圧ショベルのアームの届く範囲は限られたものとなる。かかる限られた範囲で大型土嚢を段積みできる範囲を1列とする。図6は、1列が道路の敷設方向に大型土嚢3個分であり、上下方向に大型土嚢4個分であることを示している。1列内の土嚢の数は、特に制限されず、油圧ショベルのアームの長さや仮設ステージの面積に依存して変化する。
Hereinafter, the concept of “row” in the open-cut method according to the present invention will be described.
FIG. 6 is a schematic diagram for explaining a state in which excavation proceeds in 1 to m rows along the road laying direction when the slope is viewed from the side. As shown in FIG. 3, the reach of the arm of the excavator on the temporary stage is limited. A range in which large sandbags can be stacked in such a limited range is defined as one row. FIG. 6 shows that one row corresponds to three large sandbags in the road laying direction and four large sandbags in the vertical direction. The number of sandbags in one row is not particularly limited, and varies depending on the length of the arm of the excavator and the area of the temporary stage.

図7は、大型土嚢の上面にジオグリッドが敷設され、ラス型枠が大型土嚢の側面側に固定された状態を示す概略図であり、図8は、ジオグリッドの端部を折り返し、折り返し部に鉄筋を挿入した状態を示す概略図であり、図9は、鉄筋とラス型枠を固定するための鋼管と番線で固定した状態を説明する概略図であり、そして図10は、ラス型枠と大型土嚢の側面との間にコンクリート側壁を構築し、必要により作業足場を設けた状態を示す概略図である。
本発明に係る開削工法においては、1列目の作業において、整列された大型土嚢の側面側に、コンクリート型枠を、前記1〜n段の各段に敷設されたジオグリッドの端部に固定手段を用いて固定し、該コンクリート型枠と該大型土嚢の側面との間にコンクリートを充填し、コンクリート側壁を構築して、前記道路の敷設方向に向かって1列目を完成させる。図9は、かかる固定手段が、ラス型枠8を固定する鋼管9とジオグリッド5折り返し部に挿入された鉄筋10との間の番線であること示している。かかるコンクリート充填は、n段完成時に代えて、各段又はk段(但し、k<n)完成時毎に、実施してもよい。
FIG. 7 is a schematic view showing a state in which a geogrid is laid on the upper surface of the large sandbag and the lath formwork is fixed to the side surface side of the large sandbag. FIG. FIG. 9 is a schematic view illustrating a state in which the reinforcing bar is inserted into the steel plate, FIG. 9 is a schematic diagram illustrating a state in which the reinforcing bar and the lath mold are fixed with a steel pipe and a wire, and FIG. 10 is a lath mold It is the schematic which shows the state which constructed | assembled the concrete side wall between the side of a large sandbag, and provided the work scaffold as needed.
In the excavation method according to the present invention, the concrete formwork is fixed to the end of the geogrid laid on each of the 1 to n stages on the side of the aligned large sandbags in the first row of work. Fixing using means, filling concrete between the concrete formwork and the side of the large sandbag, constructing a concrete side wall, and completing the first row in the direction of laying the road. FIG. 9 shows that the fixing means is a wire between the steel pipe 9 for fixing the lath mold 8 and the reinforcing bar 10 inserted in the geogrid 5 folded portion. Such concrete filling may be performed at the completion of each stage or k stages (where k <n), instead of at the completion of n stages.

本発明に係る開削工法においては、図6に示すように、前記工程を繰り返して、道路の敷設方向に向かってm列目を完成させ、完成した1〜m列に亘って、n段上に、現場発生土、栗石又は路面材を、被せ、転圧し、路面を構築して、法面に道路を開削する。   In the excavation method according to the present invention, as shown in FIG. 6, the above steps are repeated to complete the m-th row toward the road laying direction, and over the completed 1 to m rows on the nth stage. Cover the site-generated soil, chestnut stone or road surface material, roll it down, build the road surface, and cut the road to the slope.

本発明に係る開削工法においては、1列完成毎に、仮設ステージ及び該仮設ステージ下に載置した大型土嚢を、撤去してもよいし、撤去した大型土嚢を、次列目の構築に使用してもよい。仮設ステージが道路よりも上方にあると、落下の危険があるため、仮設ステージに使用した大型土嚢又は仮設ステージ上に仮置きした大型土嚢は、速やかに撤去することが好ましい。仮設ステージが道路の下方にある場合には、仮設ステージに使用した大型土嚢又は仮設ステージ上に仮置きした大型土嚢の撤去は不要である。   In the excavation method according to the present invention, each time a row is completed, the temporary stage and the large sandbag placed under the temporary stage may be removed, or the removed large sandbag is used for the construction of the next row. May be. If the temporary stage is above the road, there is a risk of falling. Therefore, it is preferable to quickly remove the large sandbag used for the temporary stage or the large sandbag temporarily placed on the temporary stage. When the temporary stage is below the road, it is not necessary to remove the large sandbag used for the temporary stage or the large sandbag temporarily placed on the temporary stage.

本発明に係る開削工法に使用する大型土嚢は、円筒状ポリプロピレン製の直径約1100mm、高さ約1100mm、容量約1mの大型土嚢であることができる。大型土嚢は、例えば、萩原工業株式会社製のターピー(登録商標)耐候性大型土のうBLACK(2t用)であることができる。大型土嚢は法面に埋設されるため、耐候性を有さないものでも構わない。 The large sandbag used in the excavation method according to the present invention can be a large sandbag made of cylindrical polypropylene having a diameter of about 1100 mm, a height of about 1100 mm, and a capacity of about 1 m 2 . The large sandbag can be, for example, Tarpy (registered trademark) weather-resistant large sandbag BLACK (for 2t) manufactured by Ebara Industries Co., Ltd. Since the large sandbag is buried on the slope, it may be one that does not have weather resistance.

本発明に係る開削工法に使用するラス型枠は、クギン株式会社製のエコウェルメッシュであることができる。   The lath form used for the open-cut method according to the present invention can be an Ecowell mesh manufactured by Kugin Co., Ltd.

実施例を記載するまでもなく、技術常識及び以上の説明を参酌すれば、当業者が本発明に係る開削工法を実施し得るものであることは明らかであろう。   It goes without saying that the embodiments will be described, and it will be obvious that those skilled in the art can implement the excavation method according to the present invention in view of the common general technical knowledge and the above explanation.

本発明に係る開削工法は、法面(斜面)に道路、例えば、林道を開削するに際し、土砂を掘削現場から仮置き場まで、また、仮置き場から盛土構築現場まで運搬するという作業を不要とする工法であるため、仮置き場の確保等が難しい場所において、好適に利用可能な開削工法である。   The excavation method according to the present invention eliminates the need for transporting earth and sand from the excavation site to the temporary storage site and from the temporary storage site to the embankment construction site when excavating a road such as a forest road on the slope (slope). Since it is a construction method, it is an open-cut construction method that can be suitably used in places where it is difficult to secure a temporary storage space.

A 地山
B 開削計画
1 仮設ステージ
2 油圧ショベル
3 大型土嚢
4 段切り
5 ジオグリッド
6 現場発生土、栗石又は廃棄物
7 コンクリート側壁
8 ラス型枠
9 鋼管
10 鉄筋
11 足場
A Ground mountain B Drilling plan 1 Temporary stage 2 Hydraulic excavator 3 Large sandbag 4 Stage cut 5 Geogrid 6 On-site generated soil, chestnut or waste 7 Concrete side wall 8 Lath form 9 Steel pipe 10 Reinforcement 11 Scaffolding

Claims (5)

法面(斜面)に道路を敷設するための開削工法であって、以下の工程:
(1)該道路敷設予定地近傍の草木を伐採し;
(2)油圧ショベルを用いて該草木を伐採した法面を掘削して、該道路の路面と並列する略水平な面を形成し、該掘削により発生した土砂を大型土嚢に充填し、該土砂を充填した大型土嚢を、該略水平な面上の法面端部に沿って1又は2段載置し、該載置された大型土嚢と地山との隙間に、該載置された大型土嚢の上面と略同一高さとなるまで土砂を充填し、該同一高さに、該油圧ショベルの作業場となる所定面積の略水平な仮設ステージを構築し;
(3)必要により鋼板を敷いた前記仮設ステージ上に、前記油圧ショベルを移動し、該仮設ステージの上方又は下方の法面を、該油圧ショベルのアームが届く範囲で、段切りし、該段切り作業において発生した土砂を複数の大型土嚢に充填して、該土砂が充填された複数の大型土嚢を該仮設ステージ上に仮置きし;
(4)工程(3)において土砂が充填された複数の大型土嚢の一部を、前記段切りした法面の最下段上に、前記道路の敷設方向に沿って整列するように載置し、該載置された大型土嚢と、前記段切りされた地山との隙間に、現場発生土、栗石又は廃棄物を、該大型土嚢の上面と略同一高さとなるまで充填し、転圧して略水平面とし、該略水平面上に、かつ、該段切りされた地山に跨って、ジオグリッドを敷設して、1列目1段を構築し;
(5)前記1列目1段の上に、工程(3)において土砂が充填された複数の大型土嚢の残部を、前記道路の敷設方向に沿って一列で整列するように載置し、該載置された大型土嚢と、前記段切りされた地山との隙間に、現場発生土、栗石又は廃棄物を、該大型土嚢の上面と略同一高さとなるまで充填し、転圧して略水平面とし、該略水平面上に、かつ、該段切りされた地山に跨って、ジオグリッドを敷設して、1列目2段を構築し;
(6)工程(5)を(n−2)回繰り返して、1列目n段(nは2以上の整数)を構築し;
(7)工程(4)〜(6)において整列された大型土嚢の側面側に、コンクリート型枠を、前記1〜n段の各段に敷設されたジオグリッドの端部に固定手段を用いて固定し、該コンクリート型枠と該大型土嚢の側面との間にコンクリートを充填し、コンクリート側壁を構築して、前記道路の敷設方向に向かって1列目を完成させ;
(8)工程(1)〜(7)を(m−1)回繰り返して、前記道路の敷設方向に向かってm列目(mは1以上の整数)を完成させ;
(9)完成した1〜m列に亘って、n段上に、現場発生土、栗石又は路面材を、被せ、転圧し、路面を構築して、法面に道路を開削する;
を含む、前記工法。
An open-cut method for laying roads on slopes (slopes), which includes the following steps:
(1) Cutting down vegetation near the planned site for road construction;
(2) Excavating the slope from which the vegetation was cut using a hydraulic excavator to form a substantially horizontal plane parallel to the road surface of the road, filling the large sandbag with the earth and sand generated by the excavation, Is placed in one or two steps along the sloped end on the substantially horizontal surface, and the placed large sandbag is placed in a gap between the placed large sandbag and the ground. Filling the sand until it is almost the same height as the top surface of the sandbag, and constructing a substantially horizontal temporary stage of a predetermined area to be a working place of the hydraulic excavator at the same height;
(3) The hydraulic excavator is moved onto the temporary stage on which a steel plate is laid if necessary, and the upper or lower slope of the temporary stage is cut within a range that the arm of the hydraulic excavator can reach. Filling a plurality of large sandbags with the earth and sand generated in the cutting operation, and temporarily placing the plurality of large sandbags filled with the sand and sand on the temporary stage;
(4) A part of the plurality of large sandbags filled with earth and sand in the step (3) is placed on the lowest step of the stepped slope so as to be aligned along the laying direction of the road, The gap between the placed large sandbag and the stepped ground is filled with the soil generated in the field, chestnut stone or waste until it is approximately the same height as the upper surface of the large sandbag, and is compacted by rolling. Construct a horizontal plane, lay a geogrid on the substantially horizontal plane and straddle the cut ground, and construct the first row and the first row;
(5) The remaining portions of the plurality of large sandbags filled with earth and sand in the step (3) are placed on the first row and the first row so as to be aligned in a row along the laying direction of the road, The gap between the placed large sandbag and the stepped ground is filled with on-site generated soil, chestnut stone or waste until it is approximately the same height as the upper surface of the large sandbag, and is rolled to a substantially horizontal plane. And laying a geogrid on the substantially horizontal plane and straddling the cut ground, and constructing the first row and the second row;
(6) Step (5) is repeated (n-2) times to construct the first row and n stages (n is an integer of 2 or more);
(7) Using concrete means on the side of the large sandbag aligned in steps (4) to (6), and fixing means at the end of the geogrid laid on each of the 1 to n stages Fixing, filling concrete between the concrete formwork and the side of the large sandbag, constructing concrete side walls, and completing the first row in the direction of laying the road;
(8) Steps (1) to (7) are repeated (m-1) times to complete the m-th row (m is an integer of 1 or more) toward the road laying direction;
(9) Over the completed 1 to m rows, the n-stage top is covered with ground-generated soil, crushed stone or road surface material, rolled, and the road surface is constructed, and the road is cut to the slope;
The said construction method containing.
前記工程(7)を、n段完成時に代えて、各段又はk段(但し、k<n)完成時毎に、実施する、請求項1に記載の工法。   The method according to claim 1, wherein the step (7) is performed at the completion of each stage or k stages (where k <n), instead of at the completion of the n stages. 1列完成毎に、仮設ステージ及び該仮設ステージ下に載置した大型土嚢を、撤去し、必要により、撤去した大型土嚢を、次列目の構築に使用する、請求項1又は2に記載の工法。   Each time a row is completed, the temporary stage and the large sandbag placed under the temporary stage are removed, and if necessary, the removed large sandbag is used for the construction of the next row. Construction method. 前記道路の路面幅が、約3〜4mである、請求項1〜3のいずれか1項に記載の工法。   The construction method according to any one of claims 1 to 3, wherein a road surface width of the road is about 3 to 4 m. 前記コンクリート型枠は、ラス型枠である、請求項1〜4のいずれか1項に記載の工法。   The construction method according to claim 1, wherein the concrete formwork is a lath formwork.
JP2013121932A 2013-06-10 2013-06-10 How to lay a road on the slope Active JP5868352B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013121932A JP5868352B2 (en) 2013-06-10 2013-06-10 How to lay a road on the slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013121932A JP5868352B2 (en) 2013-06-10 2013-06-10 How to lay a road on the slope

Publications (2)

Publication Number Publication Date
JP2014237980A JP2014237980A (en) 2014-12-18
JP5868352B2 true JP5868352B2 (en) 2016-02-24

Family

ID=52135329

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013121932A Active JP5868352B2 (en) 2013-06-10 2013-06-10 How to lay a road on the slope

Country Status (1)

Country Link
JP (1) JP5868352B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106245652A (en) * 2016-08-04 2016-12-21 中建三局第二建设工程有限责任公司 A kind of construction method of deep foundation pit earthwork digging near a river

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105133466B (en) * 2015-09-06 2018-07-20 广东承施安建设工程有限公司 Cobblestone pavement automates paving machine
CN115142388A (en) * 2022-07-14 2022-10-04 浙江省围海建设集团股份有限公司 Aqueduct concrete composite road mold construction method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2750364B2 (en) * 1989-07-28 1998-05-13 清水建設株式会社 Steep embankment
JP2002294710A (en) * 2001-03-28 2002-10-09 Sekisui Plastics Co Ltd Construction method for new route utilizing lightweight earth filling method
JP4699655B2 (en) * 2001-09-10 2011-06-15 大日本土木株式会社 How to create steep banking
JP5691069B2 (en) * 2010-12-17 2015-04-01 日鐵住金建材株式会社 Earth retaining wall of forestry road or forest work road and its construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106245652A (en) * 2016-08-04 2016-12-21 中建三局第二建设工程有限责任公司 A kind of construction method of deep foundation pit earthwork digging near a river
CN106245652B (en) * 2016-08-04 2018-02-23 中建三局第二建设工程有限责任公司 A kind of construction method of deep foundation pit earthwork digging near a river

Also Published As

Publication number Publication date
JP2014237980A (en) 2014-12-18

Similar Documents

Publication Publication Date Title
CN103669399A (en) Concrete panel reinforced retaining wall and construction method thereof
WO2022083785A1 (en) Rapid repair structure for second-level or higher soil slope shallow landslide, and construction method therefor
KR100679873B1 (en) Construction method of breast wall for tree planting
KR101177394B1 (en) Fill-Up Structure for Back-Area of Rigid Wall Structure and Construction Method of the Same
JP5418369B2 (en) Filling reinforcement structure
JP5868352B2 (en) How to lay a road on the slope
JP5500903B2 (en) Retaining wall and how to construct a retaining wall
JP5714338B2 (en) Embankment reinforced earth wall construction method and temporary restraint material for embankment reinforced earth wall used therefor
JP5043750B2 (en) Reinforced embankment method
KR100923290B1 (en) Abutment structure of bridge
KR100654936B1 (en) Method for constructing retaining wall
KR102116085B1 (en) A Eco-friendly retain wall structure
KR20110046209A (en) Method Of Construction For Scour Prevension And Reinforcement Of Bridge Pier, And Structure Of The Same
KR101206668B1 (en) Multilayer revetment structure using natural strones
JP6676462B2 (en) Embankment reinforcement method
CN213173779U (en) Cutting slope protection structure
CN211773854U (en) Soil retaining structure permeates water with soil nail
CN113216248A (en) Hydraulic engineering combined retaining wall structure and construction method thereof
JP3472708B2 (en) Slope and seawall retaining wall structures and their construction methods
KR20180101986A (en) Methods for constructing retaining wall using fastening unit for stiffener
KR101149038B1 (en) Reinforcement construction method of poor subsoil by horizontal geogrid and vertical geogrid
CN208152061U (en) Method steel pipe pile cofferdam structure is unidirectionally attacked and occupied suitable for Soft Clay
JPH0369721A (en) Steep gradient banking
JP2011026792A (en) Structure and construction method of reinforced soil banking
KR101074267B1 (en) A revetment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20150212

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20151119

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20151208

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20160105

R150 Certificate of patent or registration of utility model

Ref document number: 5868352

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250