KR20180101986A - Methods for constructing retaining wall using fastening unit for stiffener - Google Patents

Methods for constructing retaining wall using fastening unit for stiffener Download PDF

Info

Publication number
KR20180101986A
KR20180101986A KR1020170121578A KR20170121578A KR20180101986A KR 20180101986 A KR20180101986 A KR 20180101986A KR 1020170121578 A KR1020170121578 A KR 1020170121578A KR 20170121578 A KR20170121578 A KR 20170121578A KR 20180101986 A KR20180101986 A KR 20180101986A
Authority
KR
South Korea
Prior art keywords
fixing unit
retaining wall
reinforcing
stiffener
transverse
Prior art date
Application number
KR1020170121578A
Other languages
Korean (ko)
Inventor
송준호
Original Assignee
송준호
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 송준호 filed Critical 송준호
Priority to KR1020170121578A priority Critical patent/KR20180101986A/en
Publication of KR20180101986A publication Critical patent/KR20180101986A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0233Retaining or protecting walls comprising retention means in the backfill the retention means being anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/025Retaining or protecting walls made up of similar modular elements stacked without mortar
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0266Retaining or protecting walls characterised by constructional features made up of preformed elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Retaining Walls (AREA)

Abstract

According to a construction method of the present invention, when installing a stiffener such as a reinforcing bar, geogrid, and a strand to reinforce a retaining wall, a fastening unit for the stiffener is used to efficiently perform work and shorten working time. Moreover, a compressive force is applied to the ground with a strand to actively reinforce the retaining wall.

Description

보강재 고정유닛을 이용한 옹벽 시공방법{Methods for constructing retaining wall using fastening unit for stiffener}BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a retaining wall using a stiffener fixing unit,

본 발명은 옹벽 시공방법에 관한 것으로서, 더욱 구체적으로는, 보강토 옹벽을 보강하는 철근, 지오그리드, 강연선과 같은 보강재를 지반에 설치시, 보강재 고정유닛을 이용하여 작업을 효율적으로 할 수 있고 작업 시간을 단축시킬 수 있으며, 강연선을 이용하여 지반에 압축력을 인가함으로써 능동적인 보강이 가능한 시공 방법에 대한 것이다. The present invention relates to a method of constructing a retaining wall, and more particularly, it relates to a method of constructing a retaining wall, which can efficiently perform a work using a stiffener fixing unit when reinforcing materials such as reinforcing bars reinforcing reinforcing earth retaining walls, geogrid, And can be actively reinforced by applying a compressive force to the ground using a stranded wire.

일반적으로, 보강토 옹벽은 흙과의 결속력이 큰 보강재를 흙 속에 삽입하여 흙과 보강재가 복합체를 이루게 함으로써 추가적인 구속압을 발생시켜 토체를 안정화시키는 옹벽이다. Generally, the reinforced earth retaining wall is a retaining wall that stabilizes the body by generating additional confining pressure by inserting a reinforcing material having a large binding force with the soil into the soil to form a composite of the soil and the reinforcing material.

이러한 보강토 옹벽은, 기존의 다른 옹벽과 비교하여, 시공이 간편하고, 기초 지반의 부등침하, 지진 등에 대해 안정적이다. 또한, 공사 현장에서 거푸집을 제작하여 콘크리트를 타설하는 기존의 옹벽과는 달리, 전면판(패널, 블록 등)과 보강재의 순차적인 조립에 의해 제작되므로 옹벽 구조물의 높이가 높고, 공사 물량이 클수록 공기(工期) 단축과 공사비 절감효과가 크며, 외관상으로도 미려하다는 장점을 갖는다. Such a reinforced earth retaining wall is easier to construct than other existing retaining walls, and is stable against uneven settlement and earthquake of foundation ground. In addition, unlike existing retaining walls, which are made of concrete at the construction site, the height of the retaining wall structure is high because the front wall (panel, block, etc.) and the reinforcing material are sequentially assembled. (Construction period) is shortened and the construction cost is greatly reduced, and it is advantageous in appearance.

상기 보강재로는 지오그리드, 띠, 부직포, 직포 등과 같은 토목섬유가 사용되거나 철근 등이 사용된다. 예를 들어, 지오그리드는 옹벽 전면(前面)에서 블록 사이에 설치되고 옹벽 후방의 뒤채움재에 매립된다. 그리고, 지오그리드의 후단은 소정의 고정 장치를 이용하여 사면 등에 고정된다. 상기 고정 장치는 대한민국 특허등록 제817901호 등에 그 구성이 개시되어 있다.As the reinforcing material, geosynthetics such as geogrid, belt, nonwoven fabric, woven fabric, etc. may be used, or reinforcing bars may be used. For example, the geogrid is installed between the blocks on the front of the retaining wall and is embedded in backfill material behind the retaining walls. The rear end of the geogrid is fixed to a slope or the like using a predetermined fixing device. The fixing device is disclosed in Korean Patent No. 817901 and the like.

그러나, 상기 고정 장치는 시공 과정이 복잡하고 공사비가 비싸지며, 사면에 앵커가 설치된 경우에만 적용될 수 있고 앵커가 없는 경우에는 적용될 수 없다는 문제점이 있다. 또한, 상기 고정 장치는 지오그리드에만 적용이 가능하고 보강재로서 철근이 사용된 경우에는 사용될 수 없다는 문제점이 있다. However, the fixing device is complicated in construction process, has a high construction cost, can be applied only when an anchor is installed on a slope, and can not be applied when there is no anchor. Further, the fixing device is applicable only to geogrids, and can not be used when a reinforcing bar is used as a reinforcing material.

한편, 보강토 옹벽에서 전면판(패널)은 옹벽의 전면(前面)을 형성하고 토사 유실을 방지하는 소극적인 역할만 한다. 즉, 전면판(패널)은 옹벽을 보강하는 역할을 하지 못한다는 한계가 있다. On the other hand, in the reinforced earth retaining wall, the front panel (panel) forms the front surface of the retaining wall and plays a passive role in preventing the earth leakage. That is, there is a limit that the front panel (panel) can not serve to reinforce the retaining wall.

본 발명은 상기 문제점들을 해결하기 위해 제안된 것으로서, 보강토 옹벽을 보강하는 철근, 지오그리드와 같은 보강재를 지반에 설치하는 작업을 효율적으로 할 수 있고 작업 시간을 단축시킬 수 있는 시공 방법을 제공하는 것에 그 목적이 있다. The present invention has been proposed in order to solve the above problems, and it is an object of the present invention to provide a construction method capable of effectively installing a reinforcing material such as a reinforcing bar reinforcing reinforcing earth retaining wall or geogrid on the ground, There is a purpose.

본 발명의 또 다른 목적은 보강재로서 철근이 사용되는 경우와 지오그리드가 사용되는 경우에 모두 사용될 수 있는 보강재 고정 유닛을 이용하는 시공방법을 제공하는 것에 있다.Another object of the present invention is to provide a construction method using a stiffener fixing unit which can be used both when a reinforcing bar is used and when a geogrid is used.

본 발명의 또 다른 목적은 전면판(패널)이 옹벽을 보강하는 역할도 하는 시공방법을 제공하는 것에 있다.It is still another object of the present invention to provide a construction method in which a front panel (panel) plays a role of reinforcing a retaining wall.

상술한 과제를 해결하기 위해서, 본 발명의 바람직한 실시예에 따른 옹벽 시공방법은, (a1) 블록(10) 또는 패널(20)의 후방에 보강재 고정유닛(110)을 설치하는 단계; (b1) 횡방향 보강근(125)이 다수 개의 보강재 고정유닛(110)을 서로 연결하도록 횡방향으로 설치되는 단계; 및, (c1) 종방향 보강근(123)의 후단을 보강재 고정유닛(110)에 연결하고 종방향 보강근(120)의 선단을 블록(10) 또는 패널(20)에 연결하는 단계;를 포함한다.In order to solve the above-mentioned problems, a method of constructing a retaining wall according to a preferred embodiment of the present invention comprises the steps of: (a1) installing a stiffener fixing unit 110 at the rear of a block 10 or a panel 20; (b1) installing the transverse reinforcement rods (125) in the lateral direction so as to connect the plurality of stiffener fixing units (110) to each other; And (c1) connecting the rear end of the longitudinal reinforcement rope 123 to the stiffener fixing unit 110 and connecting the tip of the longitudinal reinforcement rope 120 to the block 10 or the panel 20.

보강재 고정유닛(110)은 제1 평판(112)과 제2 평판(116)을 포함한다. 제1 평판(112)은 블록(10) 또는 패널(20)과 동일한 방향으로 설치되고 제1 평판(112)에는 제1 관통공(113)(114)이 형성되며, 제1 관통공(113)(114)에는 종방향 보강근(123)의 후단이 삽입되어 결합된다. The stiffener fixing unit 110 includes a first flat plate 112 and a second flat plate 116. The first flat plate 112 is installed in the same direction as the block 10 or the panel 20 and the first through holes 113 and 114 are formed in the first flat plate 112. The first through holes 113, And the rear end of the longitudinal reinforcing bar 123 is inserted and coupled to the rear end portion 114 of the frame.

그리고, 제2 평판(116)은 제1 평판(112)에 수직으로 결합된다. 제2 평판(116)에는 제2 관통공(117)이 형성되고, 제2 관통공(117)에는 횡방향 보강근(123)이 관통하여 설치된다.The second flat plate 116 is vertically coupled to the first flat plate 112. A second through hole 117 is formed in the second flat plate 116 and a transverse reinforcement 123 is inserted through the second through hole 117.

제1 평판(112)은 높이(h)가 폭(w) 보다 큰 것이 바람직하다. 그리고, 제2 평판(116)은 제1 평판(112)의 양측에 각각 설치되되, 제1 평판(112)의 상부에 설치되며, 상기 양측의 제2 평판(116)에는 제2 관통공(117)이 서로 대응되는 위치에 형성되어 횡방향 보강근(125)이 상기 양측의 제2 평판(116)을 관통할 수 있는 것이 바람직하다. The height h of the first flat plate 112 is preferably larger than the width w. The second flat plates 116 are provided on both sides of the first flat plate 112 and are provided on the first flat plate 112. The second flat plates 116 are provided with second through holes 117 Are formed at positions corresponding to each other so that the transverse reinforcement rods 125 can pass through the second flat plates 116 on both sides.

한편, 상기 (c1) 단계에서, 종방향 보강근(120)은 그 선단이 횡방향 결속근(121)에 결합되고 그 후단이 보강재 고정유닛(110)에 결합되거나, 그 선단이 블록(10) 또는 패널(20)에 결합되고 그 후단이 횡방향 보강근(125)에 결합되거나, 그 선단이 횡방향 결속근(121)에 결합되고 그 후단이 횡방향 보강근(125)에 결합될 수도 있다. In the step (c1), the longitudinal reinforcement rods 120 are connected to the transverse coupling rods 121 at the front end thereof and the rear ends thereof are coupled to the stiffener fixing unit 110, The rear end thereof may be coupled to the panel 20 and the rear end thereof may be coupled to the transverse reinforcement rope 125 or the front end thereof may be coupled to the transverse coupling rope 121 and the rear end thereof may be coupled to the transverse reinforcement rope 125.

본 발명의 바람직한 또 다른 실시예에 따른 옹벽 시공방법은, (가) 사면을 절개하고 사면에 천공홀(40)을 형성하는 단계; (나) 천공홀(40)에 보강 수단(42)을 삽입하여 설치하되, 보강 수단(42)의 상단이 천공홀(40)의 바깥으로 돌출되도록 하는 단계; (다) 보강 수단(42)의 상단에 보강재 고정유닛(110)을 설치하는 단계; (라) 횡방향 보강근(125)이 다수 개의 보강재 고정유닛(110)을 서로 연결하도록 횡방향으로 설치되는 단계; 및, (마) 종방향 보강근(123)의 후단을 횡방향 보강근(125)에 연결하고, 종방향 보강근(123)의 선단을 블록(10) 또는 패널(20)에 연결하거나 횡방향 결속근(121)에 연결하는 단계;를 포함한다. According to another preferred embodiment of the present invention, a method of constructing a retaining wall comprises: (A) cutting a slope and forming a perforation hole (40) on a slope; (B) inserting the reinforcing means (42) into the perforation hole (40) so that the upper end of the reinforcing means (42) protrudes out of the perforation hole (40); (C) installing a stiffener fixing unit 110 on the upper end of the reinforcing means 42; (D) installing the transverse reinforcement rods 125 in a lateral direction so as to connect the plurality of stiffener fixing units 110 to each other; And (e) connecting the rear end of the longitudinal reinforcement rope 123 to the transverse reinforcement rope 125 and connecting the tip of the longitudinal reinforcement rope 123 to the block 10 or the panel 20, 121).

상기 (다) 단계 이후에, (ㄱ) 보강재 고정유닛(110)의 주위에 콘크리트를 타설하여 제1 평판(112)의 하부가 콘크리트에 매설되도록 하는 단계;를 포함할 수 있다.After step (c), (a) placing the concrete around the stiffener fixing unit 110 so that the lower part of the first flat plate 112 is embedded in the concrete.

(ㄱ) 단계는 (라) 단계의 이전 또는 이후에 이루어지고, (마) 단계의 이후에는 보강재 고정유닛(110)의 주위에 콘크리트가 타설되어 제1 평판(112)의 상부를 매설한다. 상기 콘크리트는 보강재 고정유닛(110)의 주위에만 타설되거나 보강재 고정유닛(110)을 매설하도록 횡방향 보강근(125)을 따라 연속적으로 타설될 수도 있다.The step (a) is performed before or after step (d), and after step (e), concrete is buried around the stiffener fixing unit 110 so that the upper part of the first flat plate 112 is buried. The concrete may be poured only around the reinforcing material fixing unit 110 or continuously inserted along the transverse reinforcing bars 125 to embed the reinforcing material fixing unit 110. [

상기 블록(10)은 철근홈(13)을 포함하고, 철근홈(13)은 블록(10)을 횡방향으로 관통하거나 블록(10)의 윗면에 횡방향으로 형성된다. 횡방향 결속근(121)이 철근홈(13)에 설치되어 이웃하는 블록(10)을 서로 결속시키고, 종방향 보강근(123)의 선단이 횡방향 결속근(121)에 결합되거나 블록(10)에 체결된다. The block 10 comprises a reinforcing groove 13 and the reinforcing groove 13 is formed laterally through the block 10 or laterally on the upper surface of the block 10. The transverse coupling rods 121 are provided in the reinforcing groove 13 to bind the adjacent blocks 10 together and the distal ends of the longitudinal reinforcing rods 123 are coupled to the transverse coupling rods 121, Respectively.

본 발명의 바람직한 또 다른 실시예에 따른 옹벽 시공방법은, (a2) 블록(10) 또는 패널(20)의 후방에 보강재 고정유닛(110)을 설치하는 단계; (b2) 횡방향 보강근(125)이 다수 개의 보강재 고정유닛(110)을 서로 연결하도록 횡방향으로 설치되는 단계; 및, (c2) 지오그리드(310)의 후단을 횡방향 보강근(125)에 연결하고 지오그리드(310)의 선단을 블록(10)에 연결하는 단계;를 포함한다.According to another preferred embodiment of the present invention, a method of constructing a retaining wall comprises the steps of: (a2) installing a stiffener fixing unit 110 at the rear of a block 10 or a panel 20; (b2) installing the transverse reinforcement rods (125) transversely to connect the plurality of stiffener fixing units (110) to each other; And (c2) connecting the rear end of the geogrid 310 to the transverse reinforcement rope 125 and connecting the tip of the geogrid 310 to the block 10.

본 발명의 바람직한 또 다른 실시예에 따른 옹벽 시공방법은, 상기 (a2) 단계 이전에, (ㄱ) 사면을 절개하고 사면에 천공홀(40)을 형성하는 단계; 및, (ㄴ) 천공홀(40)에 보강 수단(42)을 삽입하여 설치하되, 보강 수단(42)의 상단이 천공홀(40)의 바깥으로 돌출되도록 하는 단계;를 더 포함한다. The method for constructing a retaining wall according to another preferred embodiment of the present invention may further include the steps of: (a2) cutting the slope and forming a perforation hole (40) on the slope; And (b) inserting the reinforcing means 42 into the perforation hole 40 so that the upper end of the reinforcing means 42 protrudes outside the perforation hole 40.

상기 (a2) 단계 이후에, (a2') 보강재 고정유닛(110)의 주위에 콘크리트를 타설하여 제1 평판(112)의 하부가 콘크리트에 매설되도록 하고, 뒤채움재를 이용하여 상기 콘크리트와 동일한 높이로 블록(10) 또는 패널(20)의 후방을 메우는 단계;를 포함할 수 있다. (a2') 단계는 (b2) 단계의 이전 또는 이후에 이루어진다. 그리고, (c2) 단계의 이후에는 보강재 고정유닛(110)의 주위에 콘크리트가 타설되어 제1 평판(112)의 상부를 매설한다. 상기 콘크리트는 보강재 고정유닛(110)의 주위에만 타설되거나 보강재 고정유닛(110)을 매설하도록 횡방향 보강근(125)을 따라 연속적으로 타설될 수도 있다. After step (a2), concrete is placed around the stiffener fixing unit 110 so that the lower part of the first flat plate 112 is embedded in the concrete, and the same height as the concrete (10) or the back of the panel (20). (a2 ') is performed before or after step (b2). After step (c2), concrete is placed around the stiffener fixing unit 110 so that the upper part of the first flat plate 112 is buried. The concrete may be poured only around the reinforcing material fixing unit 110 or continuously inserted along the transverse reinforcing bars 125 to embed the reinforcing material fixing unit 110. [

한편, 본 발명의 바람직한 또 다른 실시예에 따른 옹벽 시공방법은 강연선(710)을 인장하여 옹벽에 압축력을 인가하는 공정을 갖는다는 특징을 갖는다. Meanwhile, a method for constructing a retaining wall according to another preferred embodiment of the present invention is characterized in that it has a step of applying a compressive force to a retaining wall by pulling the strand 710.

구체적으로 상기 옹벽의 시공방법은, (a3) 바닥면에 지오그리드(310)를 설치하는 단계; (b3) 지오그리드(310) 위에 뒤채움재(f)를 채우되, 지오그리드(310)의 앞쪽 부분이 뒤채움재(f)의 앞면을 감싸도록 벤딩된 후 뒤채움재(f)의 윗면 중 적어도 일부 구간을 덮도록 하는 단계; (c3) 뒤채움재(f)의 앞면과 소정 간격 이격된 위치에 패널(30)을 설치하고, 뒤채움재(f) 구간의 후단에 보강재 고정유닛(110)을 설치하는 단계; (d3) 패널(30)과 보강재 고정유닛(110)을 연결하는 강연선(710)을 설치하는 단계; (e3) 뒤채움재(f)의 앞면과 패널(30) 사이의 공간을 골재(720) 또는 현장 타설콘크리트로 채우는 단계; (f3) 뒤채움재(f)가 패널(30)의 상단과 동일 높이로 될 때까지 상기 (b3) 단계와 (e3) 단계를 반복하는 단계; 및, (g3) 강연선(710)을 인장하여 패널(30)이 골재(720) 또는 현장 타설콘크리트 및 뒤채움재(f)에 압축력을 인가하도록 하는 단계;를 포함한다. More specifically, the method for constructing the retaining wall includes the steps of: (a3) installing a geogrid 310 on a bottom surface; (b3) The backfill material f is filled on the geogrid 310 and the front portion of the geogrid 310 is bent to cover the front surface of the backfill material f. At least a part of the top surface of the backfill material f ; (c3) installing the panel (30) at a position spaced apart from the front surface of the backfill material (f) by a predetermined distance, and installing a stiffener fixing unit (110) at the rear end of the backfill material (f) section; (d3) installing a strand 710 connecting the panel 30 and the stiffener fixing unit 110; (e3) filling the space between the front surface of the backfill material (f) and the panel (30) with the aggregate (720) or the cast-in-place concrete; (f3) repeating the steps (b3) and (e3) until the backfill material (f) becomes flush with the top of the panel (30); And (g3) tensioning the stranded wire 710 to cause the panel 30 to apply a compressive force to the aggregate 720 or the poured concrete and the backfill material f.

또한, 상기 옹벽의 시공방법은, (a4) 패널(30)을 설치하고 뒤채움재(f)를 소정 높이까지 채우는 단계; (b4) 패널(30)의 후방에 보강재 고정유닛(110)을 설치하고, 서로 이웃하는 보강재 고정유닛(110)을 횡방향 보강근(125)을 이용하여 서로 연결하는 단계; (c4) 강연선(710)의 선단이 패널(30)의 관통공(32)을 관통하여 설치되고 강연선(710)의 후단이 횡방향 보강근(125) 또는 보강재 고정유닛(110)에 결합되도록 하는 단계; (d4) 상기 (c4) 단계 이후에, 뒤채움재(f)를 채우는 단계; 및, (e4) 상기 (d4) 단계 이후에, 강연선(710)의 선단을 인장하여 패널(30)이 뒤채움재(f)에 압축력을 인가하도록 하는 단계;를 포함할 수도 있다. The method for constructing the retaining wall may further include the steps of: (a4) installing the panel 30 and filling the backfilling material f to a predetermined height; (b4) installing a stiffener fixing unit 110 on the rear side of the panel 30 and connecting adjacent stiffener fixing units 110 to each other by using the transverse reinforcing bars 125; (c4) the front end of the strand 710 is installed through the through hole 32 of the panel 30 and the rear end of the strand 710 is joined to the transverse reinforcement rope 125 or the stiffener fixing unit 110 ; (d4) filling the backfilling material (f) after the step (c4); And (e4) after the step (d4), stretching the leading end of the strand 710 to cause the panel 30 to apply a compressive force to the backfill material f.

본 발명에 따른 옹벽 시공방법은 다음과 같은 효과를 가진다.The retaining wall construction method according to the present invention has the following effects.

첫째, 보강토 옹벽을 보강하는 철근, 지오그리드와 같은 보강재를 지반에 설치하는 작업을 효율적으로 할 수 있고 작업 시간을 단축시킬 수 있다. First, it is possible to efficiently install reinforcing materials such as reinforcing bars reinforcing reinforcing earth retaining walls and geogrid on the ground, and shorten the working time.

둘째, 보강재로서 철근이 사용되는 경우와 지오그리드가 사용되는 경우에 모두 사용될 수 있는 보강재 고정 유닛을 이용하므로, 그 적용 범위가 넓다. Secondly, since a stiffener fixing unit that can be used both in the case of using reinforcing bars as a reinforcing material and in the case of using geogrid is used, its application range is wide.

셋째, 패널이 옹벽의 전면(前面)을 형성하고 토사 유실을 방지할 뿐만 아니라, 뒤채움재 등에게 압축력을 제공한다. 따라서, 패널은 옹벽의 구조적인 안정에 기여하는 능동적인 역할도 한다. Third, the panel forms the front surface of the retaining wall and prevents the earth leakage, and provides a compressive force to the back filling material. Therefore, the panel also plays an active role in contributing to the structural stability of the retaining wall.

도 1a와 도 1b는 각각 본 발명에 따른 옹벽 시공방법에 사용되는 보강재 고정유닛을 보여주는 사시도.
도 2는 본 발명의 제1 실시예에 따른 옹벽 시공방법에서 블록과 보강재(보강근) 및 보강재 고정유닛의 배치 구조를 보여주는 평면도.
도 3a는 도 2의 블록을 보여주는 사시도.
도 3b는 블록의 변형예를 보여주는 사시도.
도 4는 도 2의 배치 구조를 갖는 옹벽을 보여주는 단면도.
도 5는 본 발명의 제1 실시예에 따른 옹벽 시공방법에서 블록과 보강재(보강근) 및 보강재 고정유닛의 또 다른 배치 구조를 보여주는 평면도.
도 6은 도 5의 배치 구조를 갖는 옹벽을 보여주는 단면도.
도 7은 본 발명의 제1 실시예에 따른 옹벽 시공방법에서 블록과 보강재(보강근) 및 보강재 고정유닛의 또 다른 배치 구조를 보여주는 평면도.
도 8은 본 발명의 제1 실시예에 따른 옹벽 시공방법에서 블록과 보강재(보강근) 및 보강재 고정유닛의 또 다른 배치 구조를 보여주는 평면도.
도 9a 내지 도 9c는 도 4의 옹벽을 시공하는 과정을 순차적으로 보여주는 단면도.
도 10은 본 발명의 제2 실시예에 따른 옹벽을 보여주는 도면으로서, 블록과 보강재(보강근) 및 보강재 고정유닛이 도 7의 배치 구조를 갖는 옹벽을 보여주는 단면도.
도 11은 본 발명의 제2 실시예에 따른 옹벽을 보여주는 도면으로서, 블록과 보강재(보강근) 및 보강재 고정유닛이 도 8의 배치 구조를 갖는 옹벽을 보여주는 단면도.
도 12a 내지 도 12g는 도 10의 옹벽을 시공하는 과정을 순차적으로 보여주는 단면도.
도 13은 본 발명의 제3 실시예에 따른 옹벽 시공방법에서 블록과 보강재(지오그리드) 및 보강재 고정유닛의 배치 구조를 보여주는 평면도.
도 14는 도 13의 배치 구조를 갖는 옹벽을 보여주는 단면도.
도 15a 내지 도 15c는 도 14의 옹벽을 시공하는 과정을 순차적으로 보여주는 단면도.
도 16은 본 발명의 제4 실시예에 따라 시공된 옹벽을 보여주는 단면도.
도 17a 내지 도 17g는 도 16의 옹벽을 시공하는 과정을 순차적으로 보여주는 단면도.
도 18은 본 발명의 제5 실시예에 따라 시공된 옹벽에서 패널과 보강재(보강근) 및 보강재 고정유닛의 배치 구조를 보여주는 평면도.
도 19는 패널과 보강재(보강근) 및 보강재 고정유닛의 또 다른 배치 구조를 보여주는 평면도.
도 20은 본 발명의 제6 실시예에 따라 시공된 옹벽에서 패널과 보강재(지오그리드) 및 보강재 고정유닛의 배치 구조를 보여주는 평면도.
도 21은 본 발명의 제7 실시예에 따라 시공된 옹벽을 보여주는 단면도.
도 22a는 도 21의 옹벽에 사용된 패널을 보여주는 도면.
도 22b는 도 22a의 XXII-XXII' 단면을 보여주는 도면.
도 23과 도 24는 각각 패널의 변형예를 보여주는 도면.
도 25a ~ 25e는 도 21의 옹벽을 시공하는 과정을 순차적으로 보여주는 도면.
도 26 ~ 27은 각각 본 발명의 제8 실시예에 따라 시공된 옹벽을 보여주는 단면도.
도 28 ~ 29는 각각 본 발명의 제9 실시예에 따라 시공된 옹벽을 보여주는 단면도.
1A and 1B are perspective views showing a stiffener fixing unit used in a method of constructing a retaining wall according to the present invention, respectively.
2 is a plan view showing a layout structure of a block, a stiffener (reinforcing bar) and a stiffener fixing unit in a method of constructing a retaining wall according to a first embodiment of the present invention.
Figure 3a is a perspective view showing the block of Figure 2;
3B is a perspective view showing a modification of the block.
4 is a cross-sectional view showing a retaining wall having the arrangement of FIG. 2;
5 is a plan view showing another arrangement structure of a block, a stiffener (reinforcing bar) and a stiffener fixing unit in the method of constructing a retaining wall according to the first embodiment of the present invention.
6 is a cross-sectional view showing a retaining wall having the arrangement of FIG. 5;
7 is a plan view showing another arrangement structure of a block, a stiffener (reinforcing bar) and a stiffener fixing unit in the method of constructing a retaining wall according to the first embodiment of the present invention.
8 is a plan view showing another arrangement structure of a block, a stiffener (reinforcing bar) and a stiffener fixing unit in the method of constructing a retaining wall according to the first embodiment of the present invention.
FIGS. 9A to 9C are sectional views sequentially showing a process of constructing the retaining wall of FIG. 4. FIG.
Fig. 10 is a sectional view showing a retaining wall according to a second embodiment of the present invention, showing a retaining wall having a block, a stiffener (reinforcing bar) and a stiffener fixing unit having the arrangement structure of Fig. 7;
Fig. 11 is a sectional view showing a retaining wall according to a second embodiment of the present invention, showing a retaining wall having a block, a reinforcement (reinforcing bar), and a stiffener fixing unit having the arrangement of Fig.
12A to 12G are sectional views sequentially showing a process of constructing the retaining wall of FIG. 10;
13 is a plan view showing an arrangement structure of a block, a stiffener (geogrid) and a stiffener fixing unit in a method of constructing a retaining wall according to a third embodiment of the present invention.
14 is a sectional view showing a retaining wall having the arrangement structure of Fig. 13;
15A to 15C are sectional views sequentially showing a process of constructing the retaining wall of Fig.
16 is a sectional view showing a retaining wall constructed according to a fourth embodiment of the present invention;
17A to 17G are sectional views sequentially showing a process of constructing the retaining wall of Fig.
18 is a plan view showing an arrangement structure of a panel, a reinforcing member (reinforcing bar) and a stiffener fixing unit in a retaining wall constructed according to a fifth embodiment of the present invention;
Fig. 19 is a plan view showing another arrangement structure of the panel, the stiffener (reinforcing bar) and the stiffener fixing unit. Fig.
20 is a plan view showing an arrangement structure of a panel, a stiffener (geogrid) and a stiffener fixing unit in a retaining wall constructed according to a sixth embodiment of the present invention;
21 is a sectional view showing a retaining wall constructed according to a seventh embodiment of the present invention;
22A is a view showing a panel used in the retaining wall of FIG. 21; FIG.
22B is a cross-sectional view taken along a line XXII-XXII 'in FIG. 22A;
23 and 24 are views showing a modification of the panel, respectively.
25A to 25E sequentially illustrate the process of constructing the retaining wall of Fig. 21; Fig.
26 to 27 are sectional views showing a retaining wall constructed according to an eighth embodiment of the present invention, respectively.
28 to 29 are sectional views showing a retaining wall constructed according to a ninth embodiment of the present invention, respectively.

이하, 첨부된 도면들을 참조로 본 발명에 대해서 상세히 설명하기로 한다. 이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정해서 해석되어서는 아니되며, 발명자는 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다. 따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 실시예들에 불과할 뿐이고 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 출원시점에 있어서 이들을 대체할 수 있는 다양한 균등물과 변형예들이 있을 수 있음을 이해하여야 한다. Hereinafter, the present invention will be described in detail with reference to the accompanying drawings. Prior to this, terms and words used in the present specification and claims should not be construed as limited to ordinary or dictionary terms, and the inventor should appropriately interpret the concepts of the terms appropriately It should be interpreted in accordance with the meaning and concept consistent with the technical idea of the present invention based on the principle that it can be defined. Therefore, the embodiments described in the present specification and the configurations shown in the drawings are merely examples of the present invention and are not intended to represent all of the technical ideas of the present invention, so that various equivalents And variations are possible.

아울러, 각 도면에서 동일한 도면 참조부호는 동일한 구성요소를 나타낸다. In the drawings, the same reference numerals denote like elements.

보강재 고정유닛Stiffener fixing unit

도 1a는 본 발명에 따른 옹벽 시공방법에 사용되는 보강재 고정유닛을 보여주는 사시도이다.1A is a perspective view showing a stiffener fixing unit used in a method of constructing a retaining wall according to the present invention.

도면을 참조하면, 보강재 고정유닛(110)은 제1 평판(112)과, 제1 평판(112)에 수직으로 결합된 제2 평판(116)을 포함한다. 제1,2 평판(112)(116)은 합성수지 또는 금속으로 만들어질 수 있는데, 금속으로 만들어지는 경우에는 스테인리스 스틸과 같이 내부식성과 내구성이 우수한 금속으로 만들어지는 것이 바람직하다. Referring to the drawings, the stiffener fixing unit 110 includes a first flat plate 112 and a second flat plate 116 vertically coupled to the first flat plate 112. The first and second flat plates 112 and 116 may be made of synthetic resin or metal. When the first and second flat plates 112 and 116 are made of metal, they are preferably made of a metal having excellent corrosion resistance and durability such as stainless steel.

제1 평판(112)은 블록(10)과 동일한 방향으로 설치된다. 제1 평판(112)에는 제1 관통공(113)이 형성될 수 있다. 제1 관통공(113)에는, 도 2와 도 5에 나타난 바와 같이, 종방향 보강근(123)의 후단이 삽입되어 결합되거나, 도 10과 도 12에 나타난 바와 같이, 보강수단(42)의 상단이 삽입되어 결합될 수 있다. The first flat plate 112 is installed in the same direction as the block 10. A first through hole 113 may be formed in the first flat plate 112. As shown in Figs. 2 and 5, the rear end of the longitudinal reinforcing bar 123 is inserted into and engaged with the first through hole 113, or the upper end of the reinforcing means 42 Can be inserted and coupled.

한편, 도 7 및 도 8에 나타난 바와 같이, 종방향 보강근(123)의 후단이 횡방향 보강근(125)에 결합되고 사면을 안정화시키는 보강수단(42)이 없는 경우에는 제1 관통공(113)이 필요하지 않을 수도 있다. 7 and 8, when the rear end of the longitudinal reinforcement 123 is coupled to the transverse reinforcement 125 and there is no reinforcing means 42 for stabilizing the slope, the first through hole 113, May not be necessary.

제1 평판(112)은 폭(w) 보다 높이(h)가 큰 직사각 형상으로 이루어지는 것이 바람직하다. 이것은 제1 평판(112)의 하부를 콘크리트에 먼저 매립한 상태에서 종방향 보강근(123) 또는 지오그리드(310)를 설치하는 것이 효율적이기 때문인데, 이 점에 대해서는 아래에서 더 설명하기로 한다. The first flat plate 112 preferably has a rectangular shape with a height h greater than the width w. This is because it is efficient to install the longitudinal reinforcement 123 or the geogrid 310 in a state where the lower portion of the first flat plate 112 is embedded in the concrete in advance, which will be described below.

제2 평판(116)은 제1 평판(112)에 수직으로 결합된다. 제2 평판(116)은 제1 평판(112)의 상부 또는 중앙 보다 위쪽에 설치되는 것이 바람직하다. 그리고, 제1 평판(112)이 사면 또는 콘크리트에 설치된 경우, 제2 평판(116)은 옹벽쪽을 향하게 된다. 제2 평판(116)에는 제2 관통공(117)이 형성되어 있다. The second flat plate 116 is vertically coupled to the first flat plate 112. The second flat plate 116 is preferably disposed above or above the first flat plate 112. When the first flat plate 112 is installed on a slope or concrete, the second flat plate 116 is directed toward the retaining wall. A second through hole 117 is formed in the second flat plate 116.

제2 평판(116)은 제1 평판(112)의 양측에 각각 설치되고, 상기 양측 제2 평판(116)의 제2 관통공(117)이 서로 대응되는 위치에 형성되는 것이 바람직하다. 이것은 횡방향 보강근(125)이 양측 제2 평판(116)의 제2 관통공(117)을 관통하도록 설치되어 보강재 고정유닛(110)을 횡방향으로 서로 연결할 수 있도록 하기 위함이다. It is preferable that the second flat plates 116 are formed on both sides of the first flat plate 112 and the second through holes 117 of the both side second flat plates 116 are formed to correspond to each other. This is to allow the transverse reinforcement rods 125 to pass through the second through holes 117 of the second flat plates 116 so that the stiffener fixing units 110 can be connected to each other in the transverse direction.

도 1b는 보강재 고정유닛의 변형예를 보여준다. 상기 보강재 고정유닛(110)은, 도 1a의 보강재 고정유닛(110)과 비교하여, 제1 관통공(114)이 홈으로 형성되었다는 점에서 차이가 있다. 즉, 제1 관통공(114)이 제1 평판(112)의 상단에서 아래쪽으로 요입된 형상으로 형성되었다는 점에서 제1 관통공(113)과 다르다. 이러한 제1 관통공(114)은 종방향 보강근(123)의 설치 높이를 결정하는데 있어서 다소 융통성이 생기므로 유리하다. 즉, 제1 관통공(113)은 구멍으로 형성되었으므로 종방향 보강근(123) 선단과 제1 관통공(113)의 높이를 일치시켜야 하지만, 제1 관통공(114)은 긴 홈으로 형성되었으므로 종방향 보강근(123) 선단을 반드시 특정 높이에 맞출 필요가 없다. Fig. 1B shows a modification of the stiffener fixing unit. The stiffener fixing unit 110 differs from the stiffener fixing unit 110 of FIG. 1A in that the first through holes 114 are formed as grooves. That is, the first through hole 114 is different from the first through hole 113 in that the first through hole 114 is formed in a shape recessed downward from the upper end of the first flat plate 112. This first through hole 114 is advantageous because it provides some flexibility in determining the installation height of the longitudinal reinforcement rods 123. That is, since the first through hole 113 is formed as a hole, the height of the first through hole 113 and the tip of the longitudinal reinforcement 123 must be the same. However, since the first through hole 114 is formed as a long groove, It is not necessary to align the tip of the direction reinforcement rods 123 to a specific height.

아래에서는 보강재 고정유닛(110)을 이용하는 옹벽 시공방법을 설명하기로 한다. 아래의 제1,2 실시예는 전면(前面)이 블록으로 이루어지고 보강재로서 철근이 이용된 보강토 옹벽에 대한 것이고, 제3,4 실시예는 전면(前面)이 블록으로 이루어지고 보강재로서 지오그리드가 이용된 보강토 옹벽에 대한 것이다. 그리고, 제5 실시예는 전면(前面)이 패널로 이루어지고 보강재로서 철근이 이용된 보강토 옹벽에 대한 것이고, 제6 실시예는 전면(前面)이 패널로 이루어지고 보강재로서 지오그리드가 이용된 보강토 옹벽에 대한 것이다. 제7 실시예는 전면(前面)이 패널로 이루어지고 보강재로서 강연선과 지오그리드가 이용된 보강토 옹벽에 대한 것이고, 제8 실시예는 전면(前面)이 조경석으로 이루어지고 보강재로서 철근이 이용된 보강토 옹벽에 대한 것이다. 제9 실시예는 전면(前面)이 패널로 이루어지고 보강재로서 강연선이 이용된 보강토 옹벽에 대한 것이다. Hereinafter, a method of constructing a retaining wall using a stiffener fixing unit 110 will be described. The first and second embodiments described below relate to a reinforced earth retaining wall having a front surface made of a block and reinforcing steel as a reinforcing material. In the third and fourth embodiments, the front surface is made of a block and the geogrid And the reinforcing earth retaining wall used. The fifth embodiment relates to a reinforced earth retaining wall having a front surface made of a panel and reinforcing steel as a reinforcing material. In a sixth embodiment, a reinforced earth retaining wall made of panel and having geogrid as a reinforcing material, Lt; / RTI > The seventh embodiment relates to a reinforced earth retaining wall having a front surface made of a panel and using a stranded wire and geogrid as a reinforcing material. In the eighth embodiment, the reinforced earth retaining wall made of reinforcing- Lt; / RTI > The ninth embodiment relates to a reinforced earth retaining wall having a front surface formed of a panel and a stranded wire as a reinforcing material.

아래의 설명에서는 제1 관통공(113)이 형성된 보강재 고정유닛(110)을 이용한 옹벽만을 예로 들어서 설명을 하고 제1 관통공(114)이 형성된 보강재 고정유닛(110)을 적용한 옹벽은 그 설명을 생략하기로 한다. 종방향 보강근(123)의 후단을 제1 관통공(113)에 결합시키는 구성은 종방향 보강근(123)의 후단을 제1 관통공(114)에 결합시키는 경우에도 동일하게 적용될 수 있기 때문이다. In the following description, only the retaining wall using the stiffener fixing unit 110 formed with the first through hole 113 is described as an example, and the retaining wall using the stiffener fixing unit 110 formed with the first through hole 114 is explained It will be omitted. The structure for connecting the rear end of the longitudinal reinforcing bars 123 to the first through holes 113 can be equally applied to the case where the rear end of the longitudinal reinforcing bars 123 is joined to the first through holes 114.

제1 실시예First Embodiment

도 2는 본 발명의 제1 실시예에 따른 옹벽 시공방법에서 블록과 보강재(보강근) 및 보강재 고정유닛의 배치 구조를 보여주는 평면도이고, 도 3a는 상기 블록을 보여주는 사시도이다. 2 is a plan view showing an arrangement structure of a block, a stiffener (reinforcing bar) and a stiffener fixing unit in a method of constructing a retaining wall according to a first embodiment of the present invention, and FIG. 3A is a perspective view showing the block.

도면을 참조하면, 상기 옹벽(100)은 블록(10)과, 블록(10)을 횡방향으로 결속시키는 횡방향 결속근(121)과, 블록(10)에 연결된 종방향 보강근(123)과, 종방향 보강근(123)의 후단에 연결된 보강재 고정유닛(110)과, 이웃하는 보강재 고정유닛(110)을 횡방향으로 연결하는 횡방향 보강근(125) 및, 보강재 고정유닛(110)의 주변에 타설된 콘크리트(c)를 포함한다.Referring to the drawings, the retaining wall 100 includes a block 10, a transverse binding muscle 121 for laterally binding the block 10, a longitudinally reinforcing bar 123 connected to the block 10, A reinforcing material fixing unit 110 connected to the rear end of the longitudinal direction reinforcement rope 123, a lateral direction reinforcement rope 125 connecting the neighboring reinforcing material fixing unit 110 in the lateral direction, (C). ≪ / RTI >

블록(10)은 몸체(11)와, 몸체(11)를 상하로 관통하는 관통부(12)와, 몸체(11)의 윗면에 횡방향으로 형성된 철근홈(13)과, 몸체(11)의 후면에서 관통부(12)까지 관통하도록 형성된 삽입구(14)를 포함한다.The block 10 includes a body 11, a penetrating portion 12 penetrating the body 11 up and down, a reinforcing groove 13 formed in the lateral direction on the upper surface of the body 11, And an insertion port (14) formed to penetrate from the rear surface to the penetration portion (12).

블록(10)은 본 발명에 적용될 수 있는 한도내에서 그 구조가 다양하게 변형될 수 있다. 예를 들어, 도 3b에 도시된 바와 같이, 삽입구(15)가 몸체(11)의 상단에서부터 길게 요입 형성될 수도 있는데, 이 경우에는 삽입구(15)가 길게 형성되어 있으므로 종방향 보강근(123)의 상단을 결합시키기가 용이하다. The structure of the block 10 may be variously modified to the extent that it can be applied to the present invention. For example, as shown in FIG. 3B, the insertion port 15 may be elongatedly formed from the upper end of the body 11. In this case, since the insertion opening 15 is long, It is easy to join the top.

아래에서는 동일한 설명의 중복을 피하기 위해서, 삽입구(14)가 형성된 블록(10)이 적용된 옹벽만을 설명을 하고 삽입구(15)가 형성된 블록(10)이 적용된 옹벽은 그 설명을 생략하기로 한다. 종방향 보강근(123)의 선단을 삽입구(14)에 고정하는 방법은 방향 보강근(123)의 선단을 삽입구(15)에 고정하기 위해서 동일하게 사용될 수 있다. In order to avoid duplication of the same description, only the retaining wall to which the block 10 having the insertion opening 14 is applied will be described below, and the retaining wall to which the block 10 having the insertion opening 15 is applied will not be described. The method of fixing the tip end of the longitudinal reinforcing bar 123 to the insertion port 14 can be equally used to fix the tip of the direction reinforcing bar 123 to the insertion port 15. [

횡방향 결속근(121)은 철근홈(13)에 삽입되어 안착되도록 설치된다. 그리고, 횡방향 결속근(121)은 이웃하는 블록(10)을 횡방향으로 결속하는 역할을 한다. 비록, 도면에는 도시되지 않았지만 횡방향 결속근(121)의 양쪽 단부에는 너트 또는 다른 고정구(이하, '고정수단'이라 함)가 설치되어 블록(10)을 횡방향으로 결속할 수 있다. The transverse coupling rods 121 are inserted into the reinforcing rib grooves 13 to be seated. The transverse coupling rods 121 serve to bind the adjacent blocks 10 in the transverse direction. Although not shown in the drawing, nuts or other fasteners (hereinafter referred to as " fastening means ") may be provided at both ends of the transverse coupling rods 121 to bind the blocks 10 in the transverse direction.

종방향 보강근(123)은 그 선단이 삽입구(14)에 삽입된 후 관통부(12) 내에서 고정수단과 결합되고, 그 후단이 제1 관통공(113)에 삽입된 후 고정수단과 결합되어 보강재 고정유닛(110)에 결합된다. The distal end of the longitudinal reinforcing bar 123 is connected to the fixing means in the through portion 12 after the tip thereof is inserted into the insertion port 14 and the rear end thereof is inserted into the first through hole 113 and then combined with the fixing means And is coupled to the stiffener fixing unit 110.

횡방향 보강근(125)은 제2 관통공(117)을 관통하도록 설치되어 이웃하는 보강재 고정유닛(110)을 서로 연결한다. The transverse reinforcement rods 125 are installed to penetrate through the second through holes 117 to connect the neighboring stiffener fixing units 110 to each other.

보강재 고정유닛(110)은 옹벽 후방에 설치되는데, 현장 타설 콘크리트(c)에 매립되도록 설치되는 것이 인발 저항력 향상을 위해서 바람직하다. 상기 콘크리트(c)는 보강재 고정유닛(110)의 주위에만 타설될 수도 있는데, 이 때 콘크리트가 타설되는 범위는 인발 저항력을 충분히 제공할 수 있는 정도인 것이 바람직하다. 한편, 콘크리트(c)는, 보강재 고정유닛(110)의 주위에만 타설되는 것이 아니라, 보강재 고정유닛(110)을 매설하도록 횡방향 보강근(125)을 따라 연속되도록 타설될 수 있다. The stiffener fixing unit 110 is installed behind the retaining wall, and it is preferable that the stiffener fixing unit 110 is installed so as to be embedded in the on-site concrete c. The concrete c may be poured only around the reinforcing material fixing unit 110. It is preferable that the range where the concrete is poured is sufficient to provide the pulling resistance force. The concrete c may be laid continuously along the transverse reinforcement rods 125 so as not to be poured only around the reinforcing material fixing unit 110 but to embed the stiffener fixing unit 110 therein.

한편, 도 5는 블록과 보강재 및 보강재 고정유닛의 또 다른 배치 구조를 보여주는 평면도이고, 도 6은 상기 배치 구조를 갖는 옹벽을 보여주는 단면도이다.FIG. 5 is a plan view showing another arrangement structure of the block, the stiffener and the stiffener fixing unit, and FIG. 6 is a sectional view showing the retaining wall having the arrangement structure.

상기 배치 구조는, 도 2의 배치 구조와 비교하여, 종방향 보강근(123)의 선단이 횡방향 결속근(121)에 결합된다는 차이점이 있다. 이러한 배치 구조는 보강재 고정유닛(110)의 설치 위치를 블록(10)의 삽입구(14)와 일치하도록 할 필요가 없으므로 시공이 편리해진다. 종방향 보강근(123)과 횡방향 결속근(121)의 결합은 통상적인 용접 또는 고리결속 장치 등으로 이루어질 수 있다. This arrangement is different from the arrangement of FIG. 2 in that the tip of the longitudinal reinforcement 123 is coupled to the transverse coupling rods 121. This arrangement makes it unnecessary to make the installation position of the stiffener fixing unit 110 coincide with the insertion opening 14 of the block 10, which facilitates the construction. The coupling of the longitudinal reinforcing rods 123 and the transverse coupling rods 121 may be made by a conventional welding or ring binding device or the like.

도 2와 도 5의 배치 구조에서는 종방향 보강근(123)의 후단이 제1 관통공(113)에 삽입되어 설치되었으나, 도 7과 도 8에 나타난 바와 같이, 종방향 보강근(123)의 후단은 횡방향 보강근(125)에 결합될 수도 있다. 종방향 보강근(123)과 횡방향 보강근(125)의 결합은 용접 또는 통상의 결속장치 등으로 이루어질 수 있다. 2 and 5, the rear end of the longitudinal reinforcement 123 is inserted into the first through-hole 113. However, as shown in FIGS. 7 and 8, Or may be coupled to the transverse reinforcement rods 125. The combination of the longitudinal reinforcing rods 123 and the lateral reinforcing rods 125 may be made by welding or a conventional binding device or the like.

그러면, 도 4의 옹벽을 시공하는 과정을 도 9a ~ 9c를 참조하여 설명하기로 한다. The construction of the retaining wall of Fig. 4 will now be described with reference to Figs. 9a to 9c.

먼저, 도 9a에 나타난 바와 같이, 보강재 고정유닛(110)을 설치한 후, 제1 판(112)의 하부가 매립되도록 현장 콘크리트(c)를 타설하고 해당 콘크리트 높이까지 뒤채움재(f)를 채운다. 이 때, 상기 콘크리트 타설 전에 제2 관통공(117)을 관통하도록 횡방향 보강근(125)을 설치하여 보강재 고정유닛(110)을 서로 연결하는 것이 바람직한데, 이것은 콘크리트 타설로 인해서 보강재 고정유닛(110)이 움직이면 블록(10)과의 상대적 위치가 맞지 않기 때문이다. 9A, after the stiffener fixing unit 110 is installed, the site concrete c is laid so that the lower portion of the first plate 112 is buried, and the backfill material f is filled up to the concrete height . At this time, it is preferable to connect the reinforcing material fixing units 110 to each other by installing the transverse reinforcing bars 125 to penetrate the second through holes 117 before the concrete is poured. This is because the reinforcing material fixing unit 110 The relative position with respect to the block 10 is not matched.

이어서, 블록(10)을 설치한 후 종방향 보강근(123)을 설치한다. 구체적으로, 종방향 보강근(123)의 선단이 삽입구(14)에 삽입되도록 설치하고 종방향 보강근(123)의 후단이 제1 관통공(113)에 삽입되도록 설치한다. Subsequently, the block 10 is installed and then the longitudinal reinforcing bars 123 are installed. Specifically, the distal end of the longitudinal reinforcing bar 123 is inserted into the insertion port 14, and the rear end of the longitudinal reinforcing bar 123 is inserted into the first through hole 113.

종방향 보강근(123)의 설치가 완료되면, 도 9b에 나타난 바와 같이, 보강재 고정유닛(110)을 완전히 매설하도록 콘크리트(c)를 타설한다. 한편, 상기 콘크리트(c)가 타설되는 부분을 제외한 나머지 부분에는 뒤채움재(f)를 채운다. 상기 콘크리트(c)는 보강재 고정유닛(110)의 주위에만 타설되거나 보강재 고정유닛(110)을 매설하도록 횡방향 보강근(125)을 따라 연속적으로 타설될 수 있다. When the installation of the longitudinal reinforcing bars 123 is completed, as shown in FIG. 9B, the concrete c is poured so as to completely fill the stiffener fixing unit 110. As shown in FIG. On the other hand, the remaining portion except the portion where the concrete (c) is poured is filled with the backfill material (f). The concrete c may be poured only around the stiffener fixing unit 110 or continuously inserted along the transverse reinforcing bars 125 to embed the stiffener fixing unit 110.

상기 뒤채움재를 채운 후에는, 블록을 추가로 쌓고 보강재 고정유닛을 설치하는 상기 과정을 반복한다. After filling the backfilled material, the process of further stacking the blocks and installing the stiffener fixing unit is repeated.

한편, 위에서는 '보강재 고정유닛 설치 → 횡방향 보강근 설치 → 제1 판(112)의 하부가 매설되도록 콘크리트 타설하고 뒤채움재 채우기 → 종방향 보강근 설치 → 보강재 고정유닛(110)을 완전히 매설하도록 콘크리트를 타설하고 뒤채움재 채우기'의 순서로 시공이 진행되었으나, 상기 과정은 약간씩 변경될 수도 있다. On the other hand, the concrete is placed so that the bottom of the first plate 112 is buried, the backfill material is filled, the longitudinal reinforced concrete reinforcement is installed, and the reinforcing material fixing unit 110 is completely embedded. Filling and backfill filling ', but the above process may be slightly changed.

예를 들어, '보강재 고정유닛 설치 → 제1 판(112)의 하부가 매설되도록 콘크리트 타설하고 뒤채움재 채우기 → 횡방향 보강근 설치 → 종방향 보강근 설치 → 보강재 고정유닛(110)을 완전히 매설하도록 콘크리트를 타설하고 뒤채움재 채우기'의 순서로 시공될 수도 있다. For example, 'installing a stiffener fixing unit', pouring concrete so that a lower portion of the first plate 112 is buried, filling a backfill material, installing a transverse reinforcement bar, installing a longitudinal reinforcement bar, and installing the reinforcing material fixing unit 110 And filling the back filler '.

한편, 도 5~7의 배치구조를 갖는 옹벽의 시공 방법은 위 설명을 참조하면 쉽게 그 구성을 알 수 있을 것이므로 여기서는 설명을 생략하기로 한다. On the other hand, the construction method of the retaining wall having the arrangement structure of FIGS. 5 to 7 can be easily understood by referring to the above description, and therefore, a description thereof will be omitted here.

제2 실시예Second Embodiment

도 10은 본 발명의 제2 실시예에 따른 옹벽을 보여주는 도면으로서, 블록과 보강재(보강근) 및 보강재 고정유닛이 도 7의 배치 구조를 갖는 옹벽을 보여주는 단면도이다. Fig. 10 is a sectional view showing a retaining wall according to a second embodiment of the present invention, in which a block, a stiffener (reinforcing bar) and a stiffener fixing unit have a retaining structure having the arrangement of Fig.

상기 옹벽(200)은 사면을 보강 수단(42)으로 안정화시킨 것으로서, 보강 수단(42)의 상단이 보강재 고정유닛(110)에 결합된다는 점에서 제1 실시예의 옹벽과 차이가 있다. The retaining wall 200 is stabilized by the reinforcing means 42 and differs from the retaining wall of the first embodiment in that the upper end of the reinforcing means 42 is coupled to the stiffener fixing unit 110.

상기 옹벽(200)은 블록(10)과, 블록(10)을 횡방향으로 결속시키는 횡방향 결속근(121)과, 블록(10)에 연결된 종방향 보강근(123)과, 종방향 보강근(123)의 후단에 연결된 횡방향 보강근(125)과, 보강 수단(42)의 상단에 결합된 보강재 고정유닛(110) 및, 보강재 고정유닛(110)의 주변에 타설된 콘크리트(c)를 포함한다.The retaining wall 200 includes a block 10, a transverse binding muscle 121 which laterally binds the block 10, a longitudinal reinforcing bar 123 connected to the block 10 and a longitudinal reinforcing bar 123 A reinforcing material fixing unit 110 coupled to the upper end of the reinforcing means 42 and a concrete c placed around the reinforcing material fixing unit 110. The transverse reinforcement rope 125 is connected to the rear end of the reinforcing material fixing unit 110,

종방향 보강근(123)은 그 선단이 삽입구(14)에 삽입된 후 고정수단에 의해 블록(10)과 결합되고, 그 후단이 횡방향 보강근(125)에 용접 등으로 결합되되 이웃하는 보강재 고정유닛(110) 사이에서 결합된다. The rear end of the longitudinal reinforcing bar 123 is joined to the block 10 by the fixing means after the leading end of the longitudinal reinforcing bar 123 is inserted into the insertion hole 14 and the rear end of the longitudinal reinforcing bar 123 is welded to the transverse reinforcing bar 125, (110).

횡방향 보강근(125)은 제2 관통공(117)을 관통하도록 설치되어 다수 개의 보강재 고정유닛(110)을 횡방향으로 연결한다.The transverse reinforcement rods 125 are installed to penetrate through the second through holes 117 to connect the plurality of stiffener fixing units 110 in the transverse direction.

보강 수단(42)은 사면을 보강하기 위해서 사면에 설치되는 것으로서, 보강 수단(42)으로는 앵커, 락볼트 등과 같이 당업계에 알려진 수단들이 사용될 수 있다. 도면에는 천공홀(40)에 앵커(42)가 설치되어 있는데, 비록 도면에는 도시되지 않았지만 천공홀(40)에 그라우팅액을 주입하여 천공홀 주변 지반을 고결화시킬 수도 있다. The reinforcing means 42 is provided on the slope to reinforce the slope. As the reinforcing means 42, means known in the art such as an anchor, a rock bolt and the like can be used. The anchor 42 is provided in the perforation hole 40. Although not shown in the drawing, the grouting solution may be injected into the perforation hole 40 to solidify the perimeter of the perforation hole.

보강 수단(42)의 상단은 사면 밖으로 돌출되는데, 상기 돌출된 부분은 제1 관통공(113)에 삽입된 후 고정수단(너트 등)으로 고정된다. 이러한 설치에 따라, 제1 판(112)은 사면에 접하거나 사면에 근접하게 배치된다. 그리고, 제1 판(112)은 사면 또는 옹벽과 평행하게 위치하게 된다. The upper end of the reinforcing means 42 protrudes out of the slope, and the protruded portion is inserted into the first through hole 113 and fixed by a fixing means (nut or the like). In accordance with this installation, the first plate 112 is disposed adjacent to the slope or close to the slope. The first plate 112 is positioned parallel to the slope or the retaining wall.

한편, 도 11은 블록과 보강재(보강근) 및 보강재 고정유닛이 도 8의 배치 구조를 갖는 옹벽을 보여주는 단면도이다. 상기 옹벽(200)은 종방향 보강근(123)의 선단이 횡방향 결속근(121)에 결합된다는 점에서 도 10의 옹벽과 다르다. 11 is a sectional view showing a retaining wall having a block, a stiffener (reinforcing bar) and a stiffener fixing unit having the arrangement structure of Fig. The retaining wall 200 differs from the retaining wall of FIG. 10 in that the tip of the longitudinally extending reinforcement 123 is coupled to the transverse coupling rods 121.

그러면, 도 10의 옹벽을 시공하는 과정을 도 12a ~ 12g를 참조하여 설명하기로 한다. The process of constructing the retaining wall of Fig. 10 will now be described with reference to Figs. 12a to 12g.

먼저, 도 12a에 나타난 바와 같이, 사면을 절개하고 천공홀(40)을 형성한 후, 천공홀(40)에 앵커(보강수단, 42)를 설치한다. 그리고, 비록, 도면에는 나타나지 않았지만, 천공홀(40)에 그라이팅액을 주입하여 천공홀(40) 주위의 지반을 고결화시킬 수도 있다. First, as shown in FIG. 12A, an anchor (reinforcing means) 42 is provided in the perforation hole 40 after the slope is cut and the perforation hole 40 is formed. And, although not shown in the drawing, it is also possible to solidify the ground around the perforation hole 40 by injecting the lighting solution into the perforation hole 40.

이어서, 도 12b에 나타난 바와 같이, 앵커(보강수단, 42)의 상단을 제1 관통공(113)에 삽입한 후 고정수단(너트 등)으로 고정시킨다. 앵커의 상단을 고정수단(너트 등)으로 고정시키는 방법은 이미 공지되어 있다. Then, as shown in FIG. 12B, the upper end of the anchor (reinforcing means) 42 is inserted into the first through hole 113 and fixed with fixing means (nut or the like). A method of fixing the upper end of an anchor with a fixing means (e.g., a nut) is already known.

다음으로, 도 12c에 나타난 바와 같이, 블록(10)을 쌓고, 제1 판(112)의 하부가 매설되도록 콘크리트(c)를 타설한다. 이 때, 콘크리트(c)를 타설하기 전에 횡방향 보강근(125)을 설치하여 다수 개의 보강재 고정유닛(125)을 횡방향으로 서로 연결하는 것이 바람직하다. Next, as shown in FIG. 12C, concrete 10 is laid and concrete c is laid so that the lower portion of the first plate 112 is embedded. At this time, it is preferable that the transverse reinforcement rods 125 are installed before the concrete c is laid, so that the plurality of stiffener fixing units 125 are connected to each other in the transverse direction.

상기 콘크리트를 타설한 후에는 횡방향 결속근(121)과 종방향 보강근(123)을 설치한다. 횡방향 결속근(121)은 블록(10)을 횡방향으로 서로 결속한다. 그리고, 종방향 보강근(123)의 선단은 삽입구(14)에 삽입된 후 고정수단(너트 등)으로 고정되고, 종방향 보강근(123)의 후단은 횡방향 보강근(125)에 용접 또는 연결고리 등으로 결합된다.After the concrete is laid, the transverse coupling rods 121 and the longitudinal reinforcing rods 123 are installed. The transverse coupling rods 121 couple the blocks 10 laterally to each other. The rear end of the longitudinal reinforcing rope 123 is fixed to the transverse reinforcing rope 125 by means of welding or the like, Lt; / RTI >

이어서, 도 12d에 나타난 바와 같이, 콘크리트(c)를 타설하여 보강재 고정유닛(110)이 완전히 매설되도록 한다. Then, as shown in FIG. 12D, the concrete c is laid so that the stiffener fixing unit 110 is completely embedded.

한편, 도 12e ~ 12g는 상기 과정을 반복하는 것을 보여준다. 보강재 고정유닛(110)을 매설하는 콘크리트(c)는 보강재 고정유닛(110) 주변에만 타설되므로, 그 나머지 부분에는 뒤채움재(f)로 채운다. 이 때, 도 12f에 나타난 바와 같이, 각 단계에서 뒤채움재(f)는 콘크리트(c)와 동일한 높이까지 채우는 것이 바람직하다. 한편, 콘크리트(c)는, 보강재 고정유닛(110) 주변에만 타설되는 것이 아니라, 보강재 고정유닛(110)을 매설하도록 횡방향 보강근(125)을 따라 연속적으로 타설될 수도 있다. 12E to 12G show that the above process is repeated. Since the concrete c embedded in the stiffener fixing unit 110 is only installed around the stiffener fixing unit 110, the remaining portion is filled with the backfill material f. At this time, as shown in Fig. 12F, it is preferable that the backfill material f is filled to the same height as the concrete c in each step. The concrete c may be continuously laid along the transverse reinforcing bars 125 so as not to be poured only around the reinforcing material fixing unit 110 but to embed the reinforcing material fixing units 110. [

위에서는 '사면을 절개하고 천공홀(40)을 형성 → 보강재 고정유닛(110)을 보강수단(42)의 상단에 고정 → 횡방향 보강근(125)을 설치 → 콘크리트(c)를 타설하여 제1 판(112)의 하부가 매설되도록 함 → 블록을 설치하고 횡방향 결속근(121) 및 종방향 보강근(123)을 설치 → 콘크리트(c)를 타설하여 보강재 고정유닛(110)을 완전히 매설'의 순서로 시공되는 것을 설명하였으나, 상기 시공 순서는 약간씩 변경될 수 있다.The reinforcing material fixing unit 110 is fixed to the upper end of the reinforcing means 42 → the transverse reinforcing rope 125 is installed → the concrete (c) is poured and the first The block 112 is installed and the transverse coupling roots 121 and the longitudinal reinforcing rods 123 are installed and the concrete c is laid so that the stiffener fixing unit 110 is completely buried. However, the order of construction may be slightly changed.

예를 들어, '사면을 절개하고 천공홀(40)을 형성 → 보강재 고정유닛(110)을 보강수단(42)의 상단에 고정 → 콘크리트를 타설하여 제1 판(112)의 하부가 매설되도록 함 → 횡방향 보강근(125)을 설치 → 블록을 설치하고 횡방향 결속근(121) 및 종방향 보강근(123)을 설치 → 콘크리트(c)를 타설하여 보강재 고정유닛(110)을 완전히 매설'의 순서로 시공될 수도 있다.For example, the slope is cut and a perforation hole 40 is formed. - The stiffener fixing unit 110 is fixed to the upper end of the reinforcing means 42. - The concrete is laid so that the lower portion of the first plate 112 is embedded. → Install the transverse reinforcement rods 125 → Install the blocks and install the transverse coupling rods 121 and the longitudinal reinforcing rods 123 → Put the concrete c in place to completely fill the stiffener fixing unit 110 ' . ≪ / RTI >

또한, '사면을 절개하고 천공홀(40)을 형성 → 보강재 고정유닛(110)을 보강수단(42)의 상단에 고정 → 횡방향 보강근(125)을 설치 → 블록을 설치하고 횡방향 결속근(121) 및 종방향 보강근(123)을 설치 → 콘크리트(c)를 타설하여 보강재 고정유닛(110)을 완전히 매설'의 순서로 시공될 수도 있다.The stiffener fixing unit 110 is fixed to the upper end of the reinforcing means 42. The transverse reinforcement rope 125 is installed. The block is installed and the transverse coupling rope 121 and the longitudinal reinforcing bars 123 are installed, and the concrete c is installed to completely fill the stiffener fixing unit 110. In this case,

한편, 도 11의 옹벽을 시공하는 과정은 상기 설명을 참조한 당업자가 쉽게 알 수 있을 것이므로 여기서는 설명을 생략하기로 한다.Meanwhile, the process of constructing the retaining wall of FIG. 11 will be readily apparent to those skilled in the art with reference to the above description, and a description thereof will be omitted.

제3 실시예Third Embodiment

도 13은 본 발명의 제3 실시예에 따른 옹벽 시공방법에서 블록과 보강재(지오그리드) 및 보강재 고정유닛의 배치 구조를 보여주는 평면도이고, 도 14는 상기 배치 구조를 갖는 옹벽을 보여주는 단면도이다.FIG. 13 is a plan view showing an arrangement structure of a block, a stiffener (geogrid) and a stiffener fixing unit in a method of constructing a retaining wall according to a third embodiment of the present invention, and FIG. 14 is a sectional view showing a retaining wall having the above arrangement structure.

도면을 참조하면, 상기 옹벽(300)은 블록(10)과, 블록(10)을 횡방향으로 결속시키는 횡방향 결속근(121)과, 보강재 고정유닛(110)과, 이웃하는 보강재 고정유닛(110)을 횡방향으로 연결하는 횡방향 보강근(125)과, 횡방향 결속근(121)과 횡방향 보강근(125)에 결합된 지오그리드(310) 및, 보강재 고정유닛(110)의 주변에 타설된 콘크리트(c)를 포함한다.Referring to the drawings, the retaining wall 300 includes a block 10, a transverse coupling piece 121 that laterally binds the block 10, a stiffener fixing unit 110, a neighboring stiffener fixing unit A geogrid 310 coupled to the transverse coupling rods 121 and the transverse reinforcing rods 125 and a geogrid 310 coupled to the stiffener fixing unit 110 And concrete (c).

블록(10)은 상술한 블록(10)과 동일한 구조를 갖는다. 따라서, 횡방향 결속근(121)은 철근홈(13)에 삽입되어 설치된다. 횡방향 결속근(121)은 지오그리드(110)의 선단과 결합된다. 상기 결합은 횡방향 결속근(121)의 길이 방향을 따라 지오그리드(310)의 위사를 횡방향 결속근(121)에 소정 간격으로 체결하는 것에 의해서 이루어질 수 있다. 상기 체결은 통상적인 체결수단(312) 예를 들어, 시중에 판매되고 있는 케이블 타이, 철선 등으로 이루어질 수 있다. Block 10 has the same structure as block 10 described above. Therefore, the transverse coupling rods 121 are inserted into the reinforcing rib grooves 13 and installed. The transverse coupling rods 121 are engaged with the tip of the geogrid 110. The coupling may be accomplished by fastening the weft of the geogrid 310 along the longitudinal direction of the transverse coupling rods 121 to the transverse coupling rods 121 at predetermined intervals. The fastening may be accomplished by conventional fastening means 312, for example, cable ties, wire, etc., which are commercially available.

횡방향 보강근(125)은 제2 관통공(117)을 관통하도록 설치되어 다수의 보강재 고정유닛(110)을 횡방향으로 연결한다. 횡방향 보강근(125)은 지오그리드(310)의 후단에 결합된다. 한편, 도면에는 지오그리드(310)의 후단에 남은 부분이 옹벽쪽으로 접혀진 것으로 도시되었다. The transverse reinforcement rods 125 are installed to penetrate through the second through holes 117 to connect the plurality of stiffener fixing units 110 in the transverse direction. The transverse reinforcement rods 125 are joined to the rear end of the geogrid 310. Meanwhile, in the drawing, a portion left behind at the rear end of the geogrid 310 is shown folded toward the retaining wall.

상기 결합은 횡방향 보강근(125)의 길이 방향을 따라 지오그리드(310)의 위사를 횡방향 보강근(125)에 소정 간격으로 체결하는 것에 의해서 이루어질 수 있다. The coupling may be accomplished by fastening the weft of the geogrid 310 along the longitudinal direction of the transverse reinforcement rods 125 to the transverse reinforcing rods 125 at predetermined intervals.

위와 같이, 지오그리드(310)는 그 선단이 횡방향 결속근(121)에 체결되고 그 후단이 횡방향 보강근(125)에 체결되어 있으므로, 시공 완료 후에도 팽팽하게 당겨진 상태가 계속 유지될 수 있고 이에 따라, 옹벽(300)의 변형을 방지할 수 있다. As described above, since the end of the geogrid 310 is fastened to the transverse coupling roots 121 and the rear end thereof is fastened to the transverse reinforcing rods 125, the state in which the geogrid 310 is pulled up after the completion of the construction can be maintained So that deformation of the retaining wall 300 can be prevented.

그러면, 도 14의 옹벽을 시공하는 과정을 도 15a ~ 15c를 참조하여 설명하기로 한다. The process of constructing the retaining wall of Fig. 14 will now be described with reference to Figs. 15A to 15C.

먼저, 도 15a에 나타난 바와 같이, 보강재 고정유닛(110)을 설치한 후, 제1 판(112)의 하부가 매립되도록 현장 콘크리트(c)를 타설하고 해당 콘크리트 높이까지 뒤채움재(f)를 채운다. 이 때, 상기 콘크리트 타설 전에 제2 관통공(117)을 관통하도록 횡방향 보강근(125)을 설치하여 보강재 고정유닛(110)을 횡방향으로 서로 연결하는 것이 바람직한데, 이것은 콘크리트 타설로 인해서 보강재 고정유닛(110)이 움직이면 횡방향 보강근(125)을 설치하기가 어렵기 때문이다. 상기 콘크리트(c)는 보강재 고정유닛(110)의 주위에만 타설되거나 보강재 고정유닛(110)을 매설하도록 횡방향 보강근(125)을 따라 연속적으로 타설될 수 있다.15A, after the stiffener fixing unit 110 is installed, the site concrete c is laid so that the lower part of the first plate 112 is buried, and the backfill material f is filled up to the concrete height . In this case, it is preferable that the transverse reinforcement rods 125 are installed so as to penetrate the second through holes 117 before the concrete is poured so that the stiffener fixing units 110 are connected to each other in the transverse direction. This is because it is difficult to install the transverse reinforcement rope 125 when the unit 110 moves. The concrete c may be poured only around the stiffener fixing unit 110 or continuously inserted along the transverse reinforcing bars 125 to embed the stiffener fixing unit 110.

그리고, 상기 콘크리트(c)의 타설 높이와 뒤채움재(f)의 채움 높이는 블록(10)의 상면과 동일한 높이로 하는 것이 지오그리드(310)를 팽팽하게 설치하기 위해서 바람직하다. The placement height of the concrete c and the filling height of the backfill material f are preferably the same height as the top surface of the block 10 in order to provide the tension of the geogrid 310.

이어서, 도 15b에 나타난 바와 같이, 철근홈(13)에 횡방향 결속근(121)을 설치하고 지오그리드(310)를 설치한다. 구체적으로, 지오그리드(310)의 선단을 횡방향 결속근(121)에 체결되고 지오그리드(310)의 후단을 횡방향 보강근(125)에 체결한다. Subsequently, as shown in Fig. 15B, the transverse coupling rods 121 are installed in the reinforcing groove 13 and the geogrid 310 is installed. Concretely, the tip end of the geogrid 310 is fastened to the transverse coupling muscle 121 and the rear end of the geogrid 310 is fastened to the transverse direction reinforcing muscle 125.

지오그리드(310)의 설치가 완료되면, 도 15c에 나타난 바와 같이, 보강재 고정유닛(110)을 완전히 매설하도록 콘크리트(c)를 타설한다. 한편, 상기 콘크리트(c)가 타설되는 부분을 제외한 나머지 부분에는 뒤채움재(f)를 채운다.When the installation of the geogrid 310 is completed, as shown in FIG. 15C, the concrete c is laid so as to completely fill the stiffener fixing unit 110. On the other hand, the remaining portion except the portion where the concrete (c) is poured is filled with the backfill material (f).

상기 뒤채움재를 채운 후에는 상기 과정을 반복한다. After filling the backfilling material, the above process is repeated.

제4 실시예Fourth Embodiment

도 16은 본 발명의 제4 실시예에 따라 시공된 옹벽을 보여주는 단면도이다. 16 is a sectional view showing a retaining wall constructed according to a fourth embodiment of the present invention.

상기 옹벽(400)은 사면을 보강 수단(42)으로 안정화시킨 것으로서, 보강 수단(42)의 상단이 보강재 고정유닛(110)에 결합된다는 점에서 제3 실시예의 옹벽과 차이가 있다. The retaining wall 400 differs from the retaining wall of the third embodiment in that the slope is stabilized by the reinforcing means 42 and the upper end of the reinforcing means 42 is coupled to the reinforcing member fixing unit 110.

도면을 참조하면, 상기 옹벽(400)은 블록(10)과, 블록(10)을 횡방향으로 결속시키는 횡방향 결속근(121)과, 사면에 설치된 보강 수단(42)과, 보강 수단(42)의 상단에 결합된 보강재 고정유닛(110)과, 다수 개의 보강재 고정유닛(110)을 횡방향으로 연결하는 횡방향 보강근(125)과, 횡방향 결속근(121)과 횡방향 보강근(125)에 결합된 지오그리드(310) 및, 보강재 고정유닛(110)의 주변에 타설된 콘크리트(c)를 포함한다. Referring to the drawing, the retaining wall 400 includes a block 10, a transverse coupling muscle 121 which binds the block 10 in the transverse direction, a reinforcing means 42 provided on the slope, A transverse reinforcing rope 125 connecting the plurality of stiffener fixing units 110 in the transverse direction and a transverse reinforcing rope 121 and a transverse reinforcing rope 125 connected to the upper ends of the transverse reinforcing rods 121, And a concrete (c) placed around the stiffener fixing unit 110. As shown in Fig.

지오그리드(310)의 선,후단이 횡방향 결속근(121) 및 횡방향 보강근(125)에 체결되는 것과, 상기 체결 방법은 제3 실시예에서 설명한 바와 동일하다. The line and the rear end of the geogrid 310 are fastened to the transverse coupling roots 121 and the transverse reinforcing rods 125 and the fastening method is the same as that described in the third embodiment.

보강 수단(42)은 사면을 보강하기 위해서 사면에 설치되는 것으로서, 보강 수단(42)으로는 앵커, 락볼트 등과 같이 당업계에 알려진 수단들이 사용될 수 있다. 도면에는 천공홀(40)에 앵커(42)가 설치되어 있는데, 비록 도면에는 도시되지 않았지만 천공홀(40)에 그라우팅액을 주입하여 천공홀 주변 지반을 고결화시킬 수도 있다. The reinforcing means 42 is provided on the slope to reinforce the slope. As the reinforcing means 42, means known in the art such as an anchor, a rock bolt and the like can be used. The anchor 42 is provided in the perforation hole 40. Although not shown in the drawing, the grouting solution may be injected into the perforation hole 40 to solidify the perimeter of the perforation hole.

보강 수단(42)의 상단은 사면 밖으로 돌출되는데, 상기 돌출된 부분은 제1 관통공(113)에 삽입된 후 고정수단(너트 등)으로 고정된다. 이러한 설치에 따라, 제1 판(112)은 사면에 접하거나 사면에 근접하게 배치된다. 그리고, 제1 판(112)은 사면 또는 옹벽과 평행하게 위치하게 된다. The upper end of the reinforcing means 42 protrudes out of the slope, and the protruded portion is inserted into the first through hole 113 and fixed by a fixing means (nut or the like). In accordance with this installation, the first plate 112 is disposed adjacent to the slope or close to the slope. The first plate 112 is positioned parallel to the slope or the retaining wall.

그러면, 도 16의 옹벽을 시공하는 과정을 도 17a ~ 17g를 참조하여 설명하기로 한다. Then, the process of constructing the retaining wall of Fig. 16 will be described with reference to Figs. 17A to 17G.

먼저, 도 17a에 나타난 바와 같이, 사면을 절개하고 천공홀(40)을 형성한 후 앵커(보강수단, 42)를 설치한다. 이 때, 앵커(42)의 상단은 천공홀(40)의 외부로 돌출된다. 그리고, 천공홀(40)에 그라우팅액을 주입하여 천공홀 주변 지반을 고결화시킬 수도 있다. First, as shown in Fig. 17A, an anchor (reinforcement means) 42 is provided after the slope is cut and the perforation hole 40 is formed. At this time, the upper end of the anchor 42 protrudes outside the perforation hole 40. The grouting solution may be injected into the perforation hole 40 to solidify the perimeter of the perforation hole.

이어서, 도 17b에 나타난 바와 같이, 보강재 고정유닛(110)을 사면 하단의 앵커(42)에 설치한다. 구체적으로, 제1 관통공(113)에 앵커(42)의 상단이 삽입되도록 보강재 고정유닛(110)을 설치한 후, 고정수단(너트 등)으로 고정시킨다. 상기 고정에 의해서, 제1 평판(112)은 사면과 접하거나 사면과 근접하게 위치하게 되고, 옹벽 또는 사면과 평행한 방향으로 설치된다. 그리고, 제2 관통공(117)을 관통하도록 횡방향 보강근(125)을 설치하여 다수 개의 보강재 고정유닛(110)을 횡방향으로 서로 연결한다. Subsequently, as shown in Fig. 17B, the stiffener fixing unit 110 is installed on the anchor 42 at the lower end of the slope. Specifically, after the stiffener fixing unit 110 is installed in the first through hole 113 to insert the upper end of the anchor 42, the stiffener fixing unit 110 is fixed with a fixing means (nut or the like). By this fixation, the first flat plate 112 is brought into contact with the slope face or located close to the slope face, and is installed in a direction parallel to the retaining wall or slope face. A plurality of stiffener fixing units 110 are laterally connected to each other by installing a transverse reinforcement rope 125 so as to pass through the second through holes 117.

다음으로, 도 17c에 나타난 바와 같이, 블록(10)을 쌓고 블록(10)에 횡방향 결속근(121)을 설치한다. 그리고, 보강재 고정유닛(110)의 주변에 콘트리트(c)를 타설하여 제1 평판(112)의 하부가 콘크리트(c)에 매설되도록 하거나 제2 관통공(117)의 바로 아래까지 콘크리트(c)에 매설되도록 한다. 상기 콘크리트 타설은 블록(10) 상면과 동일한 높이가 되도록 하는 것이 지오그리드(310)의 인발 저항력 유지를 위해서 바람직하다. Next, as shown in Fig. 17C, the blocks 10 are stacked and the transverse coupling rods 121 are installed in the block 10. Fig. The concrete c is placed in the vicinity of the stiffener fixing unit 110 so that the lower portion of the first flat plate 112 is embedded in the concrete c or the concrete c is inserted into the lower portion of the second through hole 117, . It is preferable for the concrete pouring to have the same height as the upper surface of the block 10 in order to maintain the pull resistance of the geogrid 310.

상기 콘크리트 타설이 완료되면, 지오그리드(310)를 설치한다. 지오그리드(310)의 선단은 횡방향 결속근(121)에 체결되고 지오그리드(310)의 후단은 횡방향 보강근(125)에 체결된다. 이 때, 지오그리드(310)의 후단에 남는 부분이 있다면 횡방향 보강근(125)을 중심으로 옹벽쪽으로 접어서 처리할 수도 있다.When the concrete pouring is completed, the geogrid 310 is installed. The front end of the geogrid 310 is fastened to the transverse coupling rods 121 and the rear end of the geogrid 310 is fastened to the transverse reinforcing rods 125. At this time, if there is a portion remaining at the rear end of the geogrid 310, it may be folded toward the retaining wall about the transverse reinforcement rope 125 to be processed.

이어서, 도 17d에 나타난 바와 같이, 블록(10)을 추가로 쌓고 콘크리트를 타설하여 보강재 고정유닛(110)이 완전히 매설되도록 한다. Then, as shown in FIG. 17D, the block 10 is further stacked and the concrete is poured so that the stiffener fixing unit 110 is completely buried.

이후에는 상기 공정을 반복한다. 다만, 콘크리트(c)는 보강재 고정유닛(110)의 주변에만 타설되면 되므로, 상기 콘크리트 타설 부분을 제외한 나머지 부분에는 뒤채움재(f)가 채워진다. 이 때, 뒤채움재(f)와 콘크리트(c)는 블록 상면과 동일한 높이가 되도록 하는 것이 지오그리드의 인발 저항력 유지를 위해서 바람직하다. 한편, 상기 콘크리트(c)는, 보강재 고정유닛(110)의 주변에만 타설되는 것이 아니라, 보강재 고정유닛(110)을 매설하도록 횡방향 보강근(125)을 따라 연속적으로 타설될 수도 있다. Thereafter, the above process is repeated. However, since the concrete (c) is installed only in the periphery of the stiffener fixing unit 110, the backfill material f is filled in the remaining portion except for the concrete pouring portion. At this time, it is preferable that the backfill material (f) and the concrete (c) have the same height as the upper surface of the block in order to maintain the pull resistance of the geogrid. The concrete c may be continuously installed along the transverse reinforcing bars 125 so as not to be poured only around the reinforcing material fixing unit 110 but to embed the stiffener fixing unit 110 therein.

한편, 도 13, 14, 16 및 그와 관련된 설명에서는 지오그리드(310)의 선단이 횡방향 결속근(121)에 체결된 구성이 도시되고 설명되어 있으나, 지오그리드(310)의 선단은 상,하층 블록(10) 사이에 설치될 수도 있는데, 구체적으로, 지오그리드(310)의 선단은 핀[블록(10)에 삽입되어 설치되는 핀]에 의해 고정(핀 결합 방식)되거나 블록(10)에 형성된 단차(계단턱)에 의해 고정(러그 결합 방식)될 수도 있다. 13, 14 and 16 and the related description show the structure in which the tip of the geogrid 310 is fastened to the transverse coupling roots 121, the tip of the geogrid 310 is connected to the upper and lower layer blocks 121, The tip of the geogrid 310 may be fixed (pin-coupled) by a pin (a pin inserted into the block 10), or a step (not shown) formed in the block 10 (Lug-coupled manner) by means of a stepped jaw.

제5,6 실시예(패널에 적용)Examples 5 and 6 (applied to panel)

위에서는 본 발명이 블록으로 이루어진 보강토 옹벽에 적용되는 것을 설명하였으나, 본 발명은 패널로 이루어진 보강토 옹벽에도 적용될 수 있는데, 이를 설명하면 아래와 같다. In the above description, the present invention is applied to a reinforced earth retaining wall made of a block, but the present invention can also be applied to a reinforced earth retaining wall made of a panel.

도 18은 본 발명의 제5 실시예에 따라 시공된 옹벽에서 패널과 보강재(보강근) 및 보강재 고정유닛의 배치 구조를 보여주는 평면도이다. 18 is a plan view showing an arrangement structure of a panel, a stiffener (reinforcing bar) and a stiffener fixing unit in a retaining wall constructed according to a fifth embodiment of the present invention.

상기 배치구조를 갖는 옹벽은 패널(20)과, 패널(20) 뒷면에 횡방향으로 설치된 횡방향 결속근(121)과, 횡방향 결속근(121)에 연결된 종방향 보강근(123)과, 종방향 보강근(123)의 후단에 연결된 보강재 고정유닛(110)과, 다수 개의 보강재 고정유닛(110)을 횡방향으로 연결하는 횡방향 보강근(125) 및, 보강재 고정유닛(110)의 주변에 타설된 콘크리트(c, 도 18에 미도시)를 포함한다.The retaining wall having the above-described arrangement structure comprises a panel 20, a transverse coupling piece 121 provided transversely to the rear surface of the panel 20, a longitudinally reinforcing reinforcing piece 123 connected to the transverse coupling piece 121, A reinforcing material fixing unit 110 connected to the rear end of the directional reinforcement 123, a transverse reinforcement rope 125 connecting the plurality of the stiffener fixing units 110 in the transverse direction, Concrete (c, not shown in FIG. 18).

패널(20)은 프리캐스트 콘크리트(PC)로 만들어질 수 있는데, 그 뒷면에는 고리(22)가 설치되어 있다. 고리(22)는 패널(20)을 이동시킬 때 작업자가 잡을 수 있는 부분이다.The panel 20 can be made of precast concrete PC, with a ring 22 on its back. The ring 22 is a part that the operator can hold when the panel 20 is moved.

횡방향 결속근(121)은 다수 개의 고리(22)를 관통하도록 횡방향으로 설치된다. 횡방향 결속근(121)은 고리(22)에 결합될 수 있는데, 이러한 결합은 용접 등과 같은 통상의 방법으로 이루어질 수 있다. The transverse coupling rods 121 are installed laterally to penetrate the plurality of rings 22. The transverse coupling rods 121 can be coupled to the ring 22, which coupling can be done in a conventional manner, such as by welding.

종방향 보강근(123)은 그 선단이 횡방향 결속근(121)에 용접 또는 연결고리 등으로 결합되고 그 후단이 제1 관통공(113)에 삽입된 후 고정수단(너트 등)으로 고정된다. 그리고, 횡방향 보강근(125)은 제2 관통공(117)을 관통하도록 설치되어 다수 개의 보강재 고정유닛(110)을 횡방향으로 연결한다. The distal end of the longitudinal reinforcing bar 123 is connected to the transverse coupling rods 121 by welding or a coupling ring and the rear end of the longitudinal reinforcing rope 123 is inserted into the first through hole 113 and then fixed by a fixing means (nut or the like). The transverse reinforcement rods 125 are installed to penetrate through the second through holes 117 to connect the plurality of stiffener fixing units 110 in the lateral direction.

한편, 종방향 보강근(123)의 선단은 패널(20)에 직접 결합될 수도 있다. 예를 들어, 패널(20)에 관통공(도면에 미도시)이 형성되고 종방향 보강근(123)의 선단이 상기 관통공을 관통하도록 설치된 후 고정수단(너트 등, 도면에 미도시)과 결합될 수 있다. On the other hand, the tip of the longitudinal reinforcing bar 123 may be directly coupled to the panel 20. For example, when the panel 20 is provided with a through hole (not shown in the figure) and the distal end of the longitudinal reinforcing bar 123 passes through the through hole, .

도 19는 패널과 보강재(보강근) 및 보강재 고정유닛의 또 다른 배치 구조를 보여주는 평면도이다. 19 is a plan view showing another arrangement structure of the panel, the stiffener (reinforcing bar) and the stiffener fixing unit.

상기 배치 구조는, 도 18의 배치 구조와 비교하여, 종방향 보강근(123)의 후단이 횡방향 보강근(125)에 결합된다는 차이점이 있다. 이러한 배치 구조는 종방향 보강근(123)을 제1 관통공(113)과 일직선상에 위치시킬 필요가 없으므로 작업이 용이해진다는 장점이 있다. The above arrangement is different from that of Fig. 18 in that the rear end of the longitudinal reinforcement 123 is coupled to the transverse reinforcement 125. Fig. This arrangement structure is advantageous in that it is not necessary to position the longitudinal reinforcing bars 123 in a straight line with the first through holes 113, thereby facilitating the operation.

상기 배치 구조에서는 보강수단(42)의 선단이 제1 관통공(113)에 삽입되어 체결될 수도 있다. 보강수단(42)의 선단이 제1 관통공(113)에 체결되는 구성은 상술한 바 있다. In this arrangement, the tip of the reinforcing means 42 may be inserted into the first through hole 113 and fastened. The structure in which the tip of the reinforcing means 42 is fastened to the first through hole 113 has been described above.

본 발명은 패널 옹벽에서 철근(보강근)을 이용하는 경우 뿐만 아니라, 지오그리드를 이용하는 경우에도 적용될 수 있다. The present invention can be applied not only to the case of using reinforcing bars (reinforcing bars) in the panel retaining wall but also in the case of using the geogrid.

도 20은 본 발명의 제6 실시예에 따라 시공된 옹벽에서 패널과 보강재(지오그리드) 및 보강재 고정유닛의 배치 구조를 보여준다. 도 20에서는 이해를 돕기 위해서 지오그리드를 붉은 선으로 표시하였다. 20 shows a layout structure of a panel, a stiffener (geogrid), and a stiffener fixing unit in a retaining wall constructed according to the sixth embodiment of the present invention. In Figure 20, the geogrids are marked with red lines to aid understanding.

상기 배치구조에 따른 옹벽은 패널(20)과, 패널(20) 뒷면에 횡방향으로 설치된 횡방향 결속근(121)과, 횡방향 결속근(121)과 횡방형 보강근(125)에 연결된 지오그리드(310)와, 보강재 고정유닛(110)과, 다수 개의 보강재 고정유닛(110)을 횡방향으로 연결하는 횡방향 보강근(125) 및, 보강재 고정유닛(110)의 주변에 타설된 콘크리트(c, 도 20에 미도시)를 포함한다.The retaining wall according to the above arrangement structure includes a panel 20, a transverse coupling piece 121 provided transversely to the rear surface of the panel 20, and a geogrid (not shown) connected to the transverse coupling piece 121 and the transverse- A reinforcing material fixing unit 110 and a transverse reinforcing bar 125 connecting the plurality of stiffener fixing units 110 in the lateral direction and a concrete c 20).

횡방향 결속근(121)이 다수 개의 고리(22)를 관통하도록 설치되는 것과, 횡방향 보강근(125)이 다수 개의 보강재 고정유닛(110)을 관통하도록 설치되는 것은 도 18에서와 동일하다. 18 in that the transverse coupling roots 121 are provided so as to penetrate the plurality of rings 22 and the transverse reinforcing rods 125 are installed so as to pass through the plurality of stiffener fixing units 110. [

그리고, 지오그리드(310)는 체결수단(312)에 의해서 그 선단과 후단이 횡방향 결속근(121)과 횡방향 보강근(125)에 결합된다. 상기 선,후단이 지오그리드(310)와 결합되는 방법은 상술한 바 있다.The front end and the rear end of the geogrid 310 are coupled to the transverse coupling rods 121 and the transverse reinforcing rods 125 by fastening means 312. A method in which the line and the rear end are combined with the geogrid 310 has been described above.

위에서 설명한 바와 같이, 본 발명은 블록 옹벽 뿐만 아니라 패널 옹벽에도 적용이 가능하다. 패널 옹벽의 시공은 블록 웅벽의 시공과 동일한 원리로 이루어지므로 여기서는 그 설명을 생략하기로 한다. As described above, the present invention is applicable not only to the block retaining wall but also to the panel retaining wall. The construction of the panel retaining wall is the same as the construction of the block wall, so that the description thereof will be omitted here.

제7 실시예(강연선과 패널을 이용한 옹벽)Seventh Embodiment (Retaining Wall Using Stranded Wire and Panel)

도 21은 본 발명의 제7 실시예에 따라 시공된 옹벽을 보여주는 단면도이다. 21 is a sectional view showing a retaining wall constructed according to a seventh embodiment of the present invention.

상기 옹벽(700)은 패널(30)과, 패널(30)의 후방에 설치된 보강재 고정유닛(110)과, 패널(30)과 보강재 고정유닛(110)을 연결하는 강연선(710)과, 지오그리드(310)와, 뒤채움재(f) 및, 골재(720)를 포함한다. The retaining wall 700 includes a panel 30, a stiffener fixing unit 110 installed at the rear of the panel 30, a strand 710 connecting the panel 30 and the stiffener fixing unit 110, 310, a backfill material (f), and aggregate (720).

옹벽(700)은, 기존의 보강토 옹벽과 비교하여, 패널(30)이 골재(720) 또는 현장 타설 콘크리트와 뒤채움재(f)에 압축력을 인가한다는 차이점이 있다. 즉, 기존의 보강토 옹벽에서는 패널이 단순히 토사 유실을 방지하고 옹벽 전면(前面)을 형성하는 역할만을 했지만, 옹벽(700)에서는 패널(30)이 토사 유실 방지 및 옹벽 전면 형성 뿐만 아니라, 골재(720) 또는 현장 타설 콘크리트와 뒤채움재(f)에 압축력을 인가하는 능동적인 보강 역할도 한다는 특징이 있다. The retaining wall 700 differs from the conventional reinforcing earth retaining wall in that the panel 30 applies compressive force to the aggregate 720 or the backfill material f and the cast concrete. That is, in the existing reinforced earth retaining wall, the panel merely plays a role of preventing the earth leakage and forming the front surface of the retaining wall. However, in the retaining wall 700, the panel 30 can prevent aggregation of the aggregate 720 ), Or actively reinforcing by applying a compressive force to the on-site concrete and backfill material (f).

패널(30)은, 도 22a ~ 22b에 나타난 바와 같이, 콘크리트로 이루어진 몸체(31)와, 몸체(31)를 관통하는 관통공(32)을 포함한다. 몸체(31)의 내부에는 강도 보강을 위한 철근(도면에 미도시) 등이 매설될 수 있다. 그리고, 관통공(32)은 강연선(710)의 선단이 관통하는 구멍으로서, 필요에 따라서는 두 개 이상의 강연선(710)이 관통할 수 있는 크기를 가질 수도 있다. The panel 30 includes a body 31 made of concrete and a through hole 32 passing through the body 31 as shown in Figs. 22A to 22B. A reinforcing bar (not shown) for reinforcing the strength may be embedded in the inside of the body 31. The through hole 32 is a hole through which the leading end of the strand 710 passes, and may have a size such that at least two strands 710 can penetrate.

패널(30)은 다양한 크기와 형상을 가질 수 있다. 도 23에 나타난 바와 같이, 두 개 또는 그 이상의 관통공(32)이 패널(30)에 형성될 수 있다. 그리고, 도 24에 나타난 바와 같이, 패널(30)이 사다리꼴 형상으로 형성될 수도 있다. The panel 30 may have various sizes and shapes. As shown in FIG. 23, two or more through holes 32 may be formed in the panel 30. 24, the panel 30 may be formed in a trapezoidal shape.

보강재 고정유닛(110)은 상술한 보강재 고정유닛(110)과 그 구성이 동일할 수 있다. 아울러, 보강재 고정유닛(110)은 제1 평판(112)의 하단이 상부에 위치하고 제1 평판(112)의 상단이 하부에 위치하며 제2 평판(116)이 패널(30)의 반대쪽을 향하도록 설치될 수도 있는데, 이 경우에는 보강재 고정유닛(110)을 세로로 세우기가 용이하다. The stiffener fixing unit 110 may have the same configuration as the stiffener fixing unit 110 described above. The stiffener fixing unit 110 is installed in the stiffener fixing unit 110 so that the lower end of the first flat plate 112 is positioned at the upper portion and the upper end of the first flat plate 112 is positioned at the lower portion, In this case, it is easy to erect the stiffener fixing unit 110 vertically.

나아가, 제1 평판(112)에는 두 개 또는 그 이상의 제1 관통공(113)(114)이 형성될 수도 있는 데, 이 경우에는 하나의 보강재 고정유닛(110)에 두 개 또는 그 이상의 강연선(710) 후단이 결합된다. Further, two or more first through holes 113 and 114 may be formed in the first flat plate 112. In this case, two or more stiffeners (not shown) may be provided in one stiffener fixing unit 110 710).

그리고, 제2 관통공(117)에 횡방향 보강근(125)이 설치될 수도 있다. 횡방향 보강근(125)은 이웃하는 보강재 고정유닛(110)을 횡방향으로 서로 연결한다. Further, a transverse direction reinforcing bar 125 may be provided in the second through hole 117. The transverse reinforcement rods 125 interconnect the neighboring stiffener fixing units 110 in the transverse direction.

한편, 도면에는 도시되지 아니하였지만, 보강재 고정유닛(110)의 주변에는 현장 콘크리트(c)가 타설될 수도 있다. 현장 콘크리트(c)는 보강재 고정유닛(110)의 인발을 방지하는 역할 등을 한다. 현장 콘크리트(c)는 보강재 고정유닛(110)의 주변에만 타설되거나 보강재 고정유닛(110)를 매설하도록 횡방향 보강근(125)을 따라 연속적으로 타설될 수 있다.Meanwhile, although not shown in the figure, the on-site concrete c may be installed around the stiffener fixing unit 110. The site concrete (c) serves to prevent the withdrawal of the stiffener fixing unit (110). The in-situ concrete c may be poured only around the stiffener fixing unit 110 or continuously inserted along the transverse reinforcing bars 125 so as to embed the stiffener fixing unit 110 therein.

강연선(710)은 패널(30)과 보강재 고정유닛(110)을 서로 연결한다. 즉, 강연선(710)의 선단은 관통공(32)을 관통하도록 설치된 후 인장 고정장치(인장 헤드)와 지지판(34) 등에 의해서 패널(30)에 고정되고, 압착 그립이 설치된 강연선(710)의 후단은 제1 관통공(113)(114)에 삽입되어 결합된다. 한편, 강연선(710)의 후단이, 제1 관통공(113)(114)에 설치되지 않고, 횡방향 보강근(125)에 결합될 수도 있는데, 이러한 구성은 도 7, 8 등을 참조하면 쉽게 알 수 있을 것이다. 강연선(710)은 옹벽(700)에 압축력을 도입하는 역할도 하는데, 이에 대해서는 후술하기로 한다. The stranded wire 710 connects the panel 30 and the stiffener fixing unit 110 to each other. That is, the leading end of the strand 710 is fixed to the panel 30 by means of a tension fixing device (tensioning head) and a supporting plate 34 after passing through the through hole 32, And the rear end is inserted and coupled to the first through holes 113 and 114. On the other hand, the rear end of the strand 710 may not be provided in the first through hole 113 (114) but may be coupled to the transverse reinforcement rope 125, It will be possible. The strand 710 also serves to introduce a compressive force to the retaining wall 700, which will be described later.

지오그리드(310)는 뒤채움재(f) 사이에 설치되어 옹벽(700)을 보강하는 역할을 한다. 구체적으로, 지오그리드(310)의 앞쪽 부분은 뒤채움재(f)의 앞면을 감싸도록 벤딩된 후, 뒤채움재(f)의 윗면 중 일부, 바람직하게는 뒤채움재(f)의 앞면으로부터 1m 이내를 덮도록 설치된다. 따라서, 지오그리드(310)는 그 단면 형상이

Figure pat00001
가 되도록 설치된다. 물론, 지오그리드(310)가 뒤채움재(f)의 윗면 전체를 덮도록 설치될 수도 있다. The geogrid 310 is installed between the backfilling materials f and serves to reinforce the retaining wall 700. Specifically, the front portion of the geogrid 310 is bent so as to enclose the front surface of the backfill material f, and then covered with a part of the upper surface of the backfill material f, preferably within 1 m from the front surface of the backfill material f. Respectively. Thus, the geogrid 310 has a cross-
Figure pat00001
Respectively. Of course, the geogrid 310 may be installed so as to cover the entire upper surface of the back filling material f.

지오그리드(310)의 후단은 뒤채움재(f)의 후단 또는 보강재 고정유닛(110)까지 연장될 수 있다. 그리고, 지오그리드(310)의 후단이 횡방향 보강재(125)에 결합될 수도 있다. 지오그리드(310)의 후단과 횡방향 보강재(125)의 결합은 도 13 등을 참조하면 그 구성을 알 수 있을 것이다. The rear end of the geogrid 310 may extend to the rear end of the backfill material f or the stiffener fixing unit 110. [ The rear end of the geogrid 310 may be coupled to the transverse stiffener 125. The combination of the rear end of the geogrid 310 and the transverse stiffener 125 will be described with reference to FIG.

하나의 패널(30)에는 두 개 또는 그 이상의 지오그리드(310)가 대응되도록 설치될 수 있다. 도면에는 하나의 패널(30)에 지오그리드(310)가 두 개 설치된 것이 도시되어 있지만, 지오그리드(310)의 개수는 필요에 따라 증가될 수 있다. Two or more geogrid 310 may correspond to one panel 30. Although the figure shows the installation of two geogrid 310 in one panel 30, the number of geogrid 310 can be increased as needed.

도 21에 나타난 바와 같이, 하나의 패널(30)에 두 개의 지오그리드(310)가 설치될 경우, 상부 지오그리드(310)와 하부 지오그리드(310) 사이에 강연선(710)이 위치하는 것이 뒤채움재(f) 등의 시공에 편리하다. 21, when two pieces of geogrid 310 are installed on one panel 30, the presence of the strand 710 between the upper and lower geogrid 310 and 310 causes the backfill material f ) Is convenient for construction.

뒤채움재(f)의 앞면과 패널(30)은 소정 간격으로 이격되는데, 이 이격된 공간에는 골재(720) 또는 현장 타설 콘크리트가 타설되어 채워진다. 상기 이격된 공간에 골재(720) 또는 현장 타설 콘크리트가 설치 완료된 후, 강연선(710)에 인장력을 인가하여 패널(30)이 골재(720) 또는 현장 타설 콘크리트와 뒤채움재(f)에 압축력을 인가하도록 한다. The front surface of the back filling material f and the panel 30 are spaced apart from each other by a predetermined distance, and the aggregate 720 or the cast concrete is filled in the spaced spaces. A tensile force is applied to the strand 710 so that the panel 30 applies a compressive force to the aggregate 720 or the backfilled concrete and the backfilling material f after the aggregate 720 or the on- .

상기 인장력 인가가 완료되면 강연선(710)의 선단에 설치된 인장 고정장치(인장 헤드)가 지지판(34)에 고정하게 되고 그 후에 덮개(36)를 덮어서 완료한다. When the application of the tensile force is completed, the tension fixing device (tensioning head) provided at the tip of the strand 710 is fixed to the support plate 34, and then the lid 36 is covered and completed.

그러면, 도 25a ~ 25e를 참조하여 옹벽(700)의 시공 과정을 설명하기로 한다.The construction process of the retaining wall 700 will now be described with reference to FIGS. 25A to 25E.

먼저, 도 25a에 나타난 바와 같이, 레벨링 콘크리트(701)를 시공하고 바닥면을 고르게 한다.First, as shown in FIG. 25A, the leveling concrete 701 is installed and the bottom surface is leveled.

이어서, 도 25b에 나타난 바와 같이, 바닥면에 지오그리드(310)를 설치하고 뒤채움재(f)를 채운다. 구체적으로, 지오그리드(310)를

Figure pat00002
형상으로 설치함으로써, 지오그리드(310)의 앞쪽 부분이 뒤채움재(f)의 앞면을 감싸도록 벤딩된 후 뒤채움재(f)의 윗면을 1m 이내로 덮도록 설치된다. Next, as shown in FIG. 25B, the geogrid 310 is installed on the bottom surface and the back filling material f is filled. Specifically, the geogrid 310
Figure pat00002
So that the front portion of the geogrid 310 is bent to enclose the front surface of the backfill material f and then covers the top surface of the backfill material f within 1 m.

다음으로, 도 25c에 나타난 바와 같이, 패널(30)과 보강재 고정유닛(110)을 설치하고, 강연선(710)을 이용하여 패널(30)과 보강재 고정유닛(110)을 연결한다. 이 때, 패널(30)이 뒤채움재(f)의 앞면으로부터 소정 간격으로 이격되도록 한다.Next, as shown in Fig. 25C, the panel 30 and the stiffener fixing unit 110 are installed, and the panel 30 is connected to the stiffener fixing unit 110 by using the stranded wire 710. Fig. At this time, the panel 30 is spaced apart from the front surface of the backfill material f by a predetermined distance.

구체적으로, 강연선(710)의 후단이 제1 관통공(113)(114)을 관통한 후 압착 그립 등으로 고정되도록 하고, 강연선(710)의 선단이 패널(30)의 관통공(32)을 관통하도록 설치한다. Specifically, the rear end of the strand 710 is passed through the first through holes 113 and 114 and then fixed by a grip or the like, and the front end of the strand 710 is inserted into the through hole 32 of the panel 30 So as to penetrate.

이어서, 도 25d에 나타난 바와 같이, 뒤채움재(f)의 앞면과 패널(30) 사이의 공간에 골재(720) 또는 현장 타설 콘크리트를 채운다. 그리고, 뒤채움재(f)의 윗면에 지오그리드(310)를

Figure pat00003
형상으로 추가로 설치하고 뒤채움재(f)를 채운다.Then, as shown in Fig. 25D, the space between the front surface of the back filling material f and the panel 30 is filled with the aggregate 720 or the cast concrete. The top surface of the backfill material f is covered with a geogrid 310
Figure pat00003
And then fill the backfill (f).

다음으로, 도 25e에 나타난 바와 같이, 뒤채움재(f)의 앞면과 패널(30) 사이의 공간에 골재(720) 또는 현장 타설 콘크리트를 채운다.Next, as shown in Fig. 25E, the space between the front surface of the back filling material f and the panel 30 is filled with the aggregate 720 or the cast concrete.

상기와 같은 공정을 반복한 후, 강연선(710)의 선단을 인장하여 패널(30)이 골재(720) 또는 현장 타설 콘크리트와 뒤채움재(f)에 압축력을 인가하도록 한다. 상기 인장이 완료되면 강연선(710)의 선단에 설치된 인장 고정장치(인장 헤드)가 지지판(34)에 고정하게 되고 그 후에 덮개(36)를 덮어서 완료한다. After repeating the above process, the front end of the strand 710 is pulled so that the panel 30 applies a compressive force to the aggregate 720 or the backfilled concrete and the backfilling material f. When the tension is completed, the tension fixing device (tensioning head) provided at the tip of the strand 710 is fixed to the support plate 34, and then the cover 36 is covered and completed.

제8 실시예(조경석을 이용한 옹벽)Eighth Embodiment (Retaining Wall Using Coast Guard)

도 26은 본 발명의 제8 실시예에 따라 시공된 옹벽을 보여주는 단면도이다. 26 is a sectional view showing a retaining wall constructed according to an eighth embodiment of the present invention.

상기 옹벽(800)은 조경석으로 만들어진 패널(20)과, 패널(20)의 후방에 설치된 보강재 고정유닛(110)과, 패널(20)과 보강재 고정유닛(110)을 연결하는 종방향 보강근(123)과, 보강재 고정유닛(110)을 횡방향으로 서로 연결하는 횡방향 보강근(125) 및, 뒤채움재(f)를 포함한다. 상기 구성 요소 중에서 보강재 고정유닛(110)과, 종방향 보강근(123)과, 횡방향 보강근(125) 및, 뒤채움재(f)는 전술한 실시예의 보강재 고정유닛(110)과, 종방향 보강근(123)과, 횡방향 보강근(125) 및, 뒤채움재(f)와 각각 동일하다. The retaining wall 800 includes a panel 20 made of a glazed stone, a stiffener fixing unit 110 installed at the rear of the panel 20, a longitudinal reinforcing bar 123 connecting the panel 20 and the stiffener fixing unit 110 A transverse reinforcement rope 125 for interconnecting the stiffener fixing units 110 in the transverse direction, and a backfill material f. Among the above components, the stiffener fixing unit 110, the longitudinal direction reinforcing bars 123, the lateral direction reinforcing bars 125, and the backfill member f are similar to the stiffener fixing unit 110 of the above- 123, the transverse reinforcement rods 125, and the backfill material f, respectively.

패널(20)은 조경석으로 만들어진 것으로서, 종방향 보강근(123)의 선단과 샘 앵커 등으로 결합될 수 있다. 구체적으로, 조경석(20)의 뒷면에 소정 깊이의 천공홀을 형성하고, 상기 천공홀에 충진재(접착제 역할을 함)를 충진한 후 종방향 보강근(123)의 선단을 천공홀에 삽입함으로써 종방향 보강근(123)의 선단을 조경석(20)과 결합시킨다. 한편, 이러한 결합방식을 현장에서는 샘 앵커라고도 한다.The panel 20 is made of a gravel stone, and can be joined to the tip of the longitudinal reinforcing bar 123 by a spring anchor or the like. Specifically, a perforation hole having a predetermined depth is formed on the back surface of the gravel stone 20, a filling material (serving as an adhesive) is filled in the perforation hole, and the tip of the longitudinal reinforcing bar 123 is inserted into the perforation hole, And the front end of the reinforcement rods 123 is engaged with the landscape stone 20. On the other hand, this coupling method is also called a fountain anchor in the field.

그리고, 도면에는 도시되지 않았지만, 보강재 고정유닛(110)의 주변에는 현장 콘크리트(c)가 타설될 수도 있다. 현장 콘크리트(c)는 보강재 고정유닛(110)의 주변에만 타설되거나 보강재 고정유닛(110)를 매설하도록 횡방향 보강근(125)을 따라 연속적으로 타설될 수도 있다. Although not shown in the figure, the concrete concrete (c) may be installed around the stiffener fixing unit 110. The in-situ concrete c may be laid only around the stiffener fixing unit 110 or continuously laid along the lateral stiffener 125 to embed the stiffener fixing unit 110.

종방향 보강근(123)의 후단은 보강재 고정유닛(110)의 제1 관통공(113)(114)에 삽입되어 결합될 수도 있지만, 횡방향 보강근(125)에 결합될 수도 있다. The rear end of the longitudinal reinforcing bars 123 may be inserted into the first through holes 113 and 114 of the stiffener fixing unit 110 and may be coupled to the transverse reinforcing bars 125.

한편, 도 27은 보강수단(42)이 사면에 설치되고, 보강수단(42)의 상단이 제1 관통공(113)(114)에 삽입되어 결합된 것을 보여준다. 27 shows that the reinforcing means 42 is provided on the oblique surface and the upper end of the reinforcing means 42 is inserted into the first through holes 113 and 114 and joined thereto.

제9 실시예(패널을 이용한 옹벽)Ninth Embodiment (Retaining Wall Using Panel)

도 28은 본 발명의 제9 실시예에 따라 시공된 옹벽을 보여주는 단면도이다. 28 is a sectional view showing a retaining wall constructed according to a ninth embodiment of the present invention.

상기 옹벽(900)은, 옹벽(700)과 마찬가지로, 패널(30)이 토사 유실 방지, 옹벽 전면(前面) 형성 등의 역할을 할 뿐만 아니라 뒤채움재(f)에 압축력을 인가하는 능동적인 보강 역할도 한다. Like the retaining wall 700, the retaining wall 900 serves as an active reinforcement function for applying a compressive force to the back filling material f as well as preventing dust leakage and forming a front wall of the retaining wall Also.

상기 옹벽(900)은 패널(30)과, 패널(30)의 후방에 설치된 보강재 고정유닛(110)과, 패널(30)과 보강재 고정유닛(110)을 연결하는 강연선(710)과, 보강재 고정유닛(110)을 횡방향으로 서로 연결하는 횡방향 보강근(125) 및, 뒤채움재(f)를 포함한다. The retaining wall 900 includes a panel 30, a stiffener fixing unit 110 installed at the rear of the panel 30, a strand 710 connecting the panel 30 and the stiffener fixing unit 110, A transverse reinforcement rope 125 that interconnects the units 110 in the transverse direction, and a backfill material f.

강연선(710)의 선단은 패널(30)의 관통공(32)을 관통하도록 설치된 후 패널(30)에 고정된다. 그리고, 강연선(710)의 후단은 제1 관통공(113)(114)에 삽입되어 결합되거나 횡방향 보강근(125)에 용접 등으로 결합된다. 강연선(710)의 선,후단이 패널(30)과 보강재 고정유닛(110)에 각각 고정되는 방법은 제7 실시예에서 이미 설명된 바 있다. The leading end of the strand 710 is fixed to the panel 30 after being installed to penetrate the through hole 32 of the panel 30. [ The rear end of the strand 710 is inserted into the first through holes 113 and 114 and joined to the transverse reinforcement rods 125 by welding or the like. The method in which the line and the rear end of the strand 710 are respectively fixed to the panel 30 and the stiffener fixing unit 110 has already been described in the seventh embodiment.

뒤채움재(f) 시공이 완료된 후, 강연선(710)의 선단을 인장하여 패널(30)이 뒤채움재(f)에 압축력을 인가하도록 한다. After completion of the backfill material (f), the front end of the strand 710 is pulled so that the panel 30 applies compressive force to the backfill material f.

한편, 도 28에는 도시되지 않았지만, 옹벽(900)에도 지오그리드(310)가 도 21과 같은 구조로 설치될 수도 있다. 즉, 지오그리드(310)가

Figure pat00004
형상으로 설치됨으로써, 지오그리드(310)의 앞쪽 부분이 뒤채움재(f)의 앞면을 감싸도록 벤딩된 후 뒤채움재(f)의 윗면을 1m 이내로 덮도록 설치될 수 있다. Although not shown in FIG. 28, the retaining wall 900 may also be provided with the geogrid 310 as shown in FIG. That is, the geogrid 310
Figure pat00004
So that the front portion of the geogrid 310 can be bent so as to enclose the front surface of the backfill material f and then cover the top surface of the backfill material f within 1 m.

아울러, 보강재 고정유닛(110)의 주변에는 현장 콘크리트(c)가 타설될 수도 있는데, 현장 콘크리트(c)는 보강재 고정유닛(110)의 주변에만 타설되거나 보강재 고정유닛(110)를 매설하도록 횡방향 보강근(125)을 따라 연속적으로 타설될 수 있다.The in-situ concrete c may be installed only in the periphery of the stiffener fixing unit 110 or in the lateral direction of the stiffener fixing unit 110 so as to be embedded in the stiffener fixing unit 110. [ And can be continuously pushed along the reinforcing rods 125.

도 29는 기존 도로 측방향의 사면을 절개한 후, 옹벽을 시공하여 도로를 확장한 것을 보여주는 단면도이다. 그리고, 원래의 사면은 점선으로 도시되었다. 상기 옹벽(900)은, 도 28의 옹벽과 마찬가지로, 패널(30)이 뒤채움재(f)에 압축력을 인가하는 능동적인 보강을 한다. 29 is a cross-sectional view showing that a road is extended by installing a retaining wall after cutting slopes in the existing road side direction. And, the original slope was shown by a dotted line. The retaining wall 900, like the retaining wall in Fig. 28, performs active reinforcement in which the panel 30 applies compressive force to the backfill material f.

아울러, 현장 콘크리트(c)가 보강재 고정유닛(110)의 주변에만 타설되거나 보강재 고정유닛(110)를 매설하도록 횡방향 보강근(125)을 따라 연속적으로 타설될 수 있다.In addition, the in-situ concrete c may be poured only around the stiffener fixing unit 110 or continuously inserted along the transverse reinforcing bars 125 to embed the stiffener fixing unit 110.

10 : 블록 12 : 관통부
13 : 철근홈 14, 15 : 삽입구
20, 30 : 패널 22 : 고리
32 : 패널의 관통공 34 : 지지판
36 : 덮개
40 : 천공홀 42 : 보강수단
100, 200, 300, 400, 700, 800, 900 : 옹벽
110 : 보강재 고정유닛 112 : 제1 판
113, 114 : 제1 관통공 116 : 제2 판
117 : 제2 관통공 121 : 횡방향 결속근
123 : 종방향 보강근 125 : 횡방향 보강근
310 : 지오그리드 312 : 체결 수단
701 : 레벨링 콘크리트
710 : 강연선 720 : 골재 또는 현장 타설 콘크리트
w : 제1 판의 폭 h : 제1 판의 높이
c : 현장 타설 콘크리트 f : 뒤채움재
10: Block 12:
13: reinforcing groove 14, 15: insertion hole
20, 30: panel 22: ring
32: through hole of panel 34:
36: Cover
40: perforation hole 42: reinforcing means
100, 200, 300, 400, 700, 800, 900:
110: stiffener fixing unit 112: first plate
113, 114: first through hole 116: second edition
117: second through hole 121: transverse coupling
123: longitudinal reinforcement 125: transverse reinforcement
310: geogrid 312: fastening means
701: Leveling concrete
710: Stranded wire 720: Aggregate or spotted concrete
w: width of the first plate h: height of the first plate
c: Cast-in-place concrete f: Backfill

Claims (1)

(a1) 블록(10) 또는 패널(20)의 후방에 보강재 고정유닛(110)을 설치하는 단계;
(b1) 횡방향 보강근(125)이 다수 개의 보강재 고정유닛(110)을 서로 연결하도록 횡방향으로 설치되는 단계; 및,
(c1) 종방향 보강근(123)의 후단을 보강재 고정유닛(110)에 연결하고 종방향 보강근(120)의 선단을 블록(10) 또는 패널(20)에 결합시키거나 블록(10) 또는 패널(20)을 횡방향으로 관통하는 횡방향 결속근(121)에 결합시키는 단계;를 포함하고,
보강재 고정유닛(110)은 제1 평판(112)과 제2 평판(116)을 포함하며,
제1 평판(112)은 블록(10) 또는 패널(20)과 동일한 방향으로 설치되고 제1 평판(112)에는 제1 관통공(113)(114)이 형성되며, 제1 관통공(113)(114)에는 종방향 보강근(123)의 후단이 삽입되어 결합되고,
제2 평판(116)은 제1 평판(112)에 수직으로 결합되며, 제2 평판(116)에는 제2 관통공(117)이 형성되고, 제2 관통공(117)에는 횡방향 보강근(125)이 관통하여 설치되는 것을 특징으로 하는, 보강재 고정유닛을 이용한 옹벽 시공방법.
(a1) installing a stiffener fixing unit (110) behind the block (10) or the panel (20);
(b1) installing the transverse reinforcement rods (125) in the lateral direction so as to connect the plurality of stiffener fixing units (110) to each other; And
(c1) connecting the rear end of the longitudinal reinforcement rope 123 to the stiffener fixing unit 110 and connecting the tip of the longitudinal reinforcement rope 120 to the block 10 or panel 20, 20 to a laterally extending transverse binding muscle 121,
The stiffener fixing unit 110 includes a first flat plate 112 and a second flat plate 116,
The first flat plate 112 is installed in the same direction as the block 10 or the panel 20 and the first through holes 113 and 114 are formed in the first flat plate 112. The first through holes 113, The rear end of the longitudinal reinforcing bar 123 is inserted and joined to the rear end portion 114,
The second flat plate 116 is vertically coupled to the first flat plate 112. The second flat plate 116 is provided with a second through hole 117 and the second through hole 117 is provided with a transverse reinforcing bar 125 Wherein the reinforcing member fixing unit is installed through the reinforcing member fixing unit.
KR1020170121578A 2017-09-21 2017-09-21 Methods for constructing retaining wall using fastening unit for stiffener KR20180101986A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170121578A KR20180101986A (en) 2017-09-21 2017-09-21 Methods for constructing retaining wall using fastening unit for stiffener

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170121578A KR20180101986A (en) 2017-09-21 2017-09-21 Methods for constructing retaining wall using fastening unit for stiffener

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020170028168A Division KR101782408B1 (en) 2017-03-06 2017-03-06 Methods for constructing retaining wall using fastening unit for stiffener

Publications (1)

Publication Number Publication Date
KR20180101986A true KR20180101986A (en) 2018-09-14

Family

ID=63599508

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170121578A KR20180101986A (en) 2017-09-21 2017-09-21 Methods for constructing retaining wall using fastening unit for stiffener

Country Status (1)

Country Link
KR (1) KR20180101986A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102342958B1 (en) * 2021-12-02 2021-12-23 조영현 retaining wall structure for cutting area and builtup soil area using curved coupler and rock backfill structure
KR102554654B1 (en) * 2023-03-21 2023-07-12 휘성개발 주식회사 Retaining wall structure for cutting area and builtup soil area using rock backfill structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102342958B1 (en) * 2021-12-02 2021-12-23 조영현 retaining wall structure for cutting area and builtup soil area using curved coupler and rock backfill structure
KR102554654B1 (en) * 2023-03-21 2023-07-12 휘성개발 주식회사 Retaining wall structure for cutting area and builtup soil area using rock backfill structure

Similar Documents

Publication Publication Date Title
KR101088158B1 (en) Method for underground roadway using slurry wall method
JP2007530833A (en) Reinforced soil retaining wall system and construction method
KR100904857B1 (en) A constructing method of underground structure using steel pipe and segment
CN109235490B (en) Retaining wall and construction method thereof
KR101568956B1 (en) Excavation method for sluice on soft ground using front h-pile with multi-wire
KR101177394B1 (en) Fill-Up Structure for Back-Area of Rigid Wall Structure and Construction Method of the Same
KR101077949B1 (en) Block for reinforcement and construction method
KR20180101986A (en) Methods for constructing retaining wall using fastening unit for stiffener
KR100822265B1 (en) Revetment structure using natural stones and method for constructing revetment structure using the same
KR100583294B1 (en) A Facing panel for reinforced earth wall and its construction method
KR100923290B1 (en) Abutment structure of bridge
KR101782408B1 (en) Methods for constructing retaining wall using fastening unit for stiffener
KR101015619B1 (en) adjustable anchor device, retaining wall and method for constructing a retaining wall with reinforcement soil
KR100468034B1 (en) Construction Method of Reinforced Earth Retaining-Wall for using Anchoring
KR101390683B1 (en) Retaining wall using precast concrete panel and construction method of the same
KR101552065B1 (en) Apparatus for connecting block with stiffener in retaining wall
CN1132980C (en) Method for preventing and treating landslide o earth slope
JP2018003477A (en) Construction method of civil engineering structure, and civil engineering building block and anchoring member used with the same
KR101527703B1 (en) Revetment Block and Installation Method Thereof
KR200223114Y1 (en) A structure reinforcing for retaining wall for inclined plane which to cut off a rock wall
KR101732497B1 (en) Method for building a retaining wall
KR20000041500A (en) Method of reinforcing earth using waste tire
US20240026618A1 (en) Protective structure and method for dissipating tensile load applied to a support cable in a support cable arrangement of the protective structure
JPH073777A (en) Method for constructing self-supporting land slide protection wall
KR102511386B1 (en) Connecting structure of reinforced wall using reinforced block and constructing method thereof

Legal Events

Date Code Title Description
A107 Divisional application of patent