KR100822265B1 - Revetment structure using natural stones and method for constructing revetment structure using the same - Google Patents

Revetment structure using natural stones and method for constructing revetment structure using the same Download PDF

Info

Publication number
KR100822265B1
KR100822265B1 KR1020060117436A KR20060117436A KR100822265B1 KR 100822265 B1 KR100822265 B1 KR 100822265B1 KR 1020060117436 A KR1020060117436 A KR 1020060117436A KR 20060117436 A KR20060117436 A KR 20060117436A KR 100822265 B1 KR100822265 B1 KR 100822265B1
Authority
KR
South Korea
Prior art keywords
natural stone
native
fiber reinforcement
nut
retaining wall
Prior art date
Application number
KR1020060117436A
Other languages
Korean (ko)
Inventor
송회복
송회성
김성배
Original Assignee
송회복
송회성
김성배
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 송회복, 송회성, 김성배 filed Critical 송회복
Priority to KR1020060117436A priority Critical patent/KR100822265B1/en
Application granted granted Critical
Publication of KR100822265B1 publication Critical patent/KR100822265B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/025Retaining or protecting walls made up of similar modular elements stacked without mortar
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/14Preformed blocks or slabs for forming essentially continuous surfaces; Arrangements thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/205Securing of slopes or inclines with modular blocks, e.g. pre-fabricated
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0241Retaining or protecting walls comprising retention means in the backfill the retention means being reinforced earth elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0266Retaining or protecting walls characterised by constructional features made up of preformed elements

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Revetment (AREA)

Abstract

A native rock retaining wall structure and a construction method of a native rock retaining wall structure are provided to prevent the breakdown and overturn of a retaining wall by supporting native rocks strongly without a welding process, connecting native rocks strongly using a resistance plate and a strap type fiber reinforcement material and improving the degree of compaction for back-filling soil easily, and to heighten constructability and to reduce an economical burden by reducing the number of components. A native rock retaining wall structure includes many native rocks(10) installed to erect, a resistance plate(20) installed to be located at the back part of the native rock by many anchor pins and connected with a strap type fiber reinforcement material to support native rocks and to prevent the native rocks from overturning, an I-bolt(30) inserted into a fastening hole of a wing part of the resistance plate and coupled to the resistance plate by a nut, an I-nut(40) coupled to a set anchor(11) installed at the back part of the native rock, and a strap type fiber reinforcement material(50) inserted to rings of the I-bolt and the I-nut, and connecting and supporting the native rock and the resistance plate to reinforce the ground and to increase the connecting strength of the native rocks and the ground with frictional force of the strap type fiber reinforcement material. A construction method of a native rock retaining wall structure comprises the steps of: pit-excavating the ground where native rocks are to be piled and tamping the ground; placing reinforced concrete foundation on the tamped ground; sitting many native rocks to the reinforced concrete foundation; back-filling soil to a set anchor integrated to the back part of the native rock and an I-nut coupled to the set anchor; installing many resistance plates to the back-filled soil at the back part of the native rock at a certain distance; installing a strap type reinforcement material to reciprocate between a ring of the I-nut of the native rock and a ring of the I-bolt of the resistance plate; forming the bearing ground of the native rocks to be located at the upper part by back-filling soil at a portion of the back part of the native rocks to bury the I-nut of the native rock and the strap type fiber reinforcement material connected to the I-nut; locating native rocks on the bearing ground, and back-filling soil to the set anchor and the I-nut installed at the back part of the native rocks; and repeating above mentioned steps to pile up native rocks in multi-stage.

Description

자연석 옹벽구조물과 그 시공방법{REVETMENT STRUCTURE USING NATURAL STONES AND METHOD FOR CONSTRUCTING REVETMENT STRUCTURE USING THE SAME}Natural stone retaining wall structure and its construction method {REVETMENT STRUCTURE USING NATURAL STONES AND METHOD FOR CONSTRUCTING REVETMENT STRUCTURE USING THE SAME}

도 1 은 본 발명에 따른 구성을 보인 예시도1 is an exemplary view showing a configuration according to the present invention

도 2 는 본 발명에 따른 저항판의 구성을 보인 예시도2 is an exemplary view showing a configuration of a resistance plate according to the present invention

도 3 은 본 발명에 따른 띠형 섬유보강재와 저항판의 연결관계를 보인 예시도Figure 3 is an exemplary view showing a connection between the band-shaped fiber reinforcement and the resistance plate according to the present invention

도 4 는 본 발명에 따른 띠형 섬유보강재의 구성을 보인 예시도Figure 4 is an illustration showing the configuration of the strip-shaped fiber reinforcement according to the present invention

도 5 는 본 발명에 따른 옹벽시공을 보인 블록 예시도Figure 5 is an exemplary block diagram showing a retaining wall construction according to the present invention

* 도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings

(10) : 자연석 (20) : 저항판(10): natural stone (20): resistance plate

(21) : 지지부 (22) : 날개부21: support portion 22: wing portion

(23) : 체결홀 (30) : 아이볼트(23): Fastening hole (30): Eye bolt

(40) : 아이너트 (50) : 띠형 섬유보강재(40): Eye nut (50): Band-shaped fiber reinforcement

(50a) : 분리형 띠형 섬유보강재 (53) : 절개부(50a): Separate strip type fiber reinforcement (53): Incision

(60) : 너트 (70) : 앙카핀60: nut 70: anchor pin

(71) : 제 1 앙카핀 (72) : 제 2 앙카핀71: first anchor pin 72: second anchor pin

(80) : 기초철근 콘크리트 (81) : 기초철근 콘크리트 철근80: reinforced concrete foundation 81: reinforced concrete foundation

(82) : 지지강봉 (100) : 뒷채움(82): support bar (100): backfill

(110) : 지지기반(110): support base

본 발명은 자연석 옹벽구조물과 그 시공방법에 관한 것으로, 조경용 자연석을 다단으로 적층하고, 자연석을 견고하게 지지하며, 뒷채움토에 대한 다짐을 용이하게 할 수 있는 자연석 옹벽구조물과 그 시공방법에 관한 것이다. The present invention relates to a natural stone retaining wall structure and a construction method thereof, and to a natural stone retaining wall structure and a method of constructing the natural stone retaining wall in multiple stages, solidly supporting the natural stone, and facilitating a compaction for the backfill soil. .

일반적으로 옹벽구조물은 도로, 하천 등의 성토지 또는 절개지의 토사유출로 인한 붕괴를 방지하기 위한 것으로, 벽돌, 콘크리트, 콘크리트 패널, 콘크리트 블록 등으로 구축되며, 규모 및 시공의 편리성을 고려하여 콘크리트 재질의 옹벽구조물이 널리 사용되고 있다. In general, the retaining wall structure is designed to prevent the collapse of sediments or cuts in roads, rivers, etc., and is constructed of bricks, concrete, concrete panels, concrete blocks, etc. Retaining wall structures of materials are widely used.

그러나, 상기와 같은 콘크리트 재질의 옹벽은 콘크리트 특유의 색상 및 획일적인 형태로 인하여 위화감을 주게 되고, 자연경관을 해치는 경우가 발생되고 있다. 특히, 아파트 단지 및 공원 등과 같은 공동생활단지 및 공공시설 등의 경사면 및 절개지에 콘크리트 재질의 옹벽을 설치할 경우, 자연친화적인 주거환경을 추구하는 현대인의 취향에 반하는 문제점이 발생되고 있다. However, the retaining wall of the concrete material as described above gives a sense of discomfort due to the color and uniform form peculiar to the concrete, it is a case that spoils the natural landscape. In particular, when concrete retaining walls are installed on slopes and cutouts of common living complexes and public facilities such as apartment complexes and parks, problems that arise from the taste of modern people seeking a natural environment for living are occurring.

이와 같은 콘크리트 재질 옹벽의 문제점을 해소하기 위하여 화단등과 같이 조경을 위주하는 부분의 경사면에 대해서는 자연석을 이용하여 옹벽 즉, 전면에 자 연석을 설치하고, 상기 설치된 자연석을 서로 연결하여 고정한 후, 자연석 뒷부분에 뒷채움토를 채워넣고 이를 다짐함으로써, 외부로 노출되는 전면에 자연석이 위치하여 경관을 수려하게 하는 자연석 옹벽이 시공되고 있다. In order to solve the problem of the concrete retaining wall, the natural stone is used to install the retaining wall, that is, the front surface of the retaining wall, that is, the front of the landscape wall, such as a flower bed. By filling up the backing soil in the back part and pledging it, the natural stone retaining wall is being constructed so that the natural stone is located on the front surface exposed to the outside.

상기와 같은 자연석 옹벽구조물 및 시공방법으로는 대한민국 등록특허번호 10-0296018 호가 등록된바 있으나, 이는 지반에 기립하는 형태로 전면이 외부로 노출되도록 나란히 배열되는 자연석으로 이루어진 복수의 장식석과, 상기 장식석 후방에 배치되는 지지석과, 상기지지석에 일단부가 소정 깊이 삽입되고, 타단부가 장식석에 소정 깊이 삽입되어 장식석과 지지석을 연결하는 복수의 연결앙카로 이루어져 있으며, 상기 장식석과 지지석은 수평 연결앙카와 경사 연결앙카에 의해 연결되도록 되어 있다. The natural stone retaining wall structure and construction method as described above has been registered in Korea Patent No. 10-0296018, which is a plurality of decorative stones made of natural stone arranged side by side so that the front surface is exposed to the outside in the form standing on the ground, the decoration It is composed of a support stone disposed behind the stone, and a plurality of connecting anchors, one end of which is inserted a predetermined depth into the support stone, the other end of which is inserted into the decorative stone by a predetermined depth to connect the decorative stone and the supporting stone, wherein the decorative stone and the supporting stone are horizontal It is connected by connecting anchor and inclined connecting anchor.

이와 같은 종래의 자연석 옹벽은 수평 및 경사 연결앙카에 의해 전면에 위치한 장식석이 지지되도록 되어 있어, 장식석 후부에 채워지는 뒷채움토에 대한 다짐공정을 수행할 수 없는 문제점이 있었다. Such conventional natural stone retaining wall has a problem that the decorative stone located in the front by the horizontal and inclined connection anchor is supported, it is not possible to carry out the compaction process for the backfill soil filled in the rear of the decorative stone.

즉, 종래의 자연석 옹벽은 장식석이 연결앙카에 의해 지지석에 연결되어 지지되고 있으며, 장식석의 후부에 위치하는 토석은 뒷채움토가 아닌 뒷메움토에 해당되어 흙의 상대이동이 증대되고, 이로 인해 옹벽이 전도되는 현상이 발생될 수 있다.In other words, the conventional natural stone retaining wall is supported by decorative stones connected to the support stone by the connecting anchor, the soil located in the rear of the decorative stone corresponds to the backfill soil rather than the backfill soil, the relative movement of the soil is increased, thereby The phenomenon that the retaining wall is conducted may occur.

또한, 종래의 자연석 옹벽은 장식석과 연결앙카가 용접에 의해 서로 연결되도록 되어 있으나, 상기 용접접합은 인장강도에 강한 특성을 구비하나 휨강도 및 비틀림강도에는 취약한 문제점을 구비하고 있으며, 장기간 매립되어 있을 경우, 수 분으로 인하여 부식이 발생되는 등 여러가지 문제점이 있었다. In addition, the conventional natural stone retaining wall is a decorative stone and the connection anchor is connected to each other by welding, but the welding joint has a strong characteristic in the tensile strength, but has a problem that is weak in bending strength and torsional strength, when embedded for a long time There are various problems such as corrosion caused by moisture.

본 발명은 상기와 같은 문제점을 해소하기 위한 것으로, 그 목적은 자연석 옹벽구조물에 있어서, 자연석을 견고하게 연결 고정하고, 뒷채움토의 다짐을 다짐도 85%이상으로 용이하게 실시할 수 있는 자연석 옹벽구조물과 그 시공방법을 제공하는 것이다. The present invention is to solve the above problems, the object of the natural stone retaining wall structure, the natural stone retaining wall structure and the natural stone retaining wall structure that can be firmly connected and secured, the compaction of the backfill soil can be easily carried out to 85% or more It is to provide a construction method.

본 발명의 또다른 목적은 용접작업없이 자연석을 견고하게 지지하여, 용접부위의 부식으로 인한 옹벽의 파괴 및 전도를 방지하는 것이다. Still another object of the present invention is to firmly support natural stone without welding, thereby preventing destruction and fall of the retaining wall due to corrosion of the welded portion.

본 발명의 또다른 목적은 저항판과 띠형 섬유보강재에 의한 자연석의 견고한 연결지지 및 뒷채움토의 다짐도 향상을 통해 자연석 옹벽 구조물의 전도를 방지하는 것이다. Another object of the present invention is to prevent the fall of the natural stone retaining wall structure through the solid connection support of the natural stone by the resistance plate and the strip-shaped fiber reinforcement and the compaction of the backfill soil.

본 발명의 또다른 목적은 옹벽지지대와 띠형 섬유보강재에 의해 자연석을 견고하게 연결지지하고, 뒷채움토의 다짐을 용이하게 실시할 수 있어 시공성을 향상시키고, 부품수의 감소로 인한 경제적 부담을 해소할 수 있는 자연석 옹벽구조물과 그 시공방법을 제공하는 것이다. Another object of the present invention is to support the natural stone firmly by the retaining wall support and the band-shaped fiber reinforcement, it is possible to easily compact the backing soil can improve the workability, and eliminate the economic burden due to the reduction of the number of parts To provide natural stone retaining wall structure and its construction method.

도 1 은 본 발명에 따른 구성을 보인 예시도를, 도 2 는 본 발명에 따른 저항판의 구성을 보인 예시도를, 도 3 은 본 발명에 따른 띠형 섬유보강재와 저항판 의 연결관계를 보인 예시도를, 도 4 는 본 발명에 따른 띠형 섬유보강재의 구성을 보인 예시도를 도시한 것으로, 본 발명은 자연석 옹벽구조물에 있어서, 기립형태로 설치되는 다수개의 자연석(10)과, 상기 자연석의 후부에 위치하도록 매립되어 설치되는 저항판(20)과, 상기 저항판에 너트(60) 결합되는 아이볼트(30)와, 상기 자연석의 후면에 설치된 셋트앙카에 나사결합되는 아이너트(40)와, 상기 아이볼트와 아이너트의 고리에 삽입관통되어 자연석과 저항판을 연결지지하는 띠형 섬유보강재(50)를 포함하도록 되어 있다. 1 is an exemplary view showing a configuration according to the present invention, Figure 2 is an exemplary view showing a configuration of the resistance plate according to the present invention, Figure 3 is an illustration showing a connection relationship between the strip-shaped fiber reinforcement and the resistance plate according to the present invention. Figure 4 shows an exemplary view showing the configuration of the band-shaped fiber reinforcement according to the present invention, the present invention is a natural stone retaining wall structure, a plurality of natural stone 10 installed in the standing form, and the rear of the natural stone A resistance plate 20 embedded in the resistor plate 20, an eye bolt 30 coupled to the nut 60, and an eye nut 40 screwed to a set anchor installed at the rear of the natural stone; Is inserted through the ring of the eye bolt and the eye nut is to include a band-shaped fiber reinforcement 50 for supporting the natural stone and the resistance plate.

상기 자연석(10)은 산석, 해석, 강석등 천연상태의 자연석과, 가공된 자연석 등등 자연상태에 얻을 수 있는 모든 종류의 돌을 포함한다. The natural stone 10 includes all kinds of stones that can be obtained in a natural state such as natural stone, such as mountain stone, analysis, steel stone, processed natural stone.

상기 저항판(20)은 띠형 섬유보강재의 연결에 의해 자연석을 지지하여 전도를 방지하는 것으로, 도 2 및 도 3 에 도시된 바와 같이, 내부에 뒷채움토가 위치하여 지지력을 향상시키도록 굴곡을 구비하는 지지부(21)와, 상기 지지부의 양측단에 각각 일체형으로 형성되고 아이볼트가 너트결합되는 날개부(22)로 이루어져 있어, 전체적인 평면형상이 다수개의 굴곡을 구비하는 모자형상을 구비하도록 되어 있다. The resistance plate 20 is to prevent the fall by supporting the natural stone by the connection of the band-shaped fiber reinforcement, as shown in Figures 2 and 3, the back-filled soil is located inside to bend to improve the supporting force It consists of a support portion 21 and the wing portion 22 is formed integrally at both ends of the support portion and the eye bolt is nut-coupled, the overall planar shape is to have a hat shape having a plurality of bends. .

상기와 같이 구성된 저항판(20)은 다수개의 앙카핀(70)에 의해 고정된다. 즉, 날개부와 지지부의 연결부위에 제 1 앙카핀(71)이 설치되고, 지지부의 굴곡부위에 제 2 앙카핀(72)이 설치되며, 이때, 상기 제 1 앙카핀(71)과 제 2 앙카핀(72)은 저항판(20)을 기준으로 서로 반대되는 위치에 위치하도록 각각 설치되어 있어, 설치되는 제 1 앙카핀(71)과 제 2 앙카핀(72)에 의해 저항판(20)의 위치가 고정되 게 된다. The resistance plate 20 configured as described above is fixed by a plurality of anchor pins 70. That is, the first anchor pin 71 is installed at the connecting portion of the wing and the support, and the second anchor pin 72 is installed at the bent portion of the support. In this case, the first anchor pin 71 and the second anchor pin 71 are provided. The anchor pins 72 are respectively installed so as to be positioned at positions opposite to each other with respect to the resistance plate 20, and the resistance plate 20 is provided by the first and second anchor pins 71 and 72 installed. The position of is fixed.

또한, 상기 저항판(20)은 먼저 뒷채움토에 제 1,2 앙카핀(71,72)를 설치한 후, 이에 저항판(20)을 설치하는 방법에 의해 고정할 수 있다. 즉, 상기 저항판(20)과 앙카핀(70)은 일체형으로 형성될 수 있으나, 분리하여 각각 설치할 수도 있다. In addition, the resistance plate 20 may be fixed by a method of installing the first and second anchor pins 71 and 72 on the backfill soil first, and then installing the resistance plate 20 thereto. That is, the resistance plate 20 and the anchor pin 70 may be formed integrally, but may be separately installed.

또한, 상기 지지부의 양측단에 일체형으로 연결형성되어 있는 날개부(22)는 동일평면상에 위치하도록 형성되어 있으며, 날개부(22)의 일측에 아이볼트(30)가 삽입관통되는 체결홀(23)이 각각 형성되어 있다. In addition, the wing portion 22 is formed integrally connected to both ends of the support portion is formed to be located on the same plane, the fastening hole through which the eye bolt 30 is inserted through one side of the wing portion 22 ( 23) are formed respectively.

상기 아이볼트(30)는 저항판 날개부의 체결홀(23)내로 삽입되어 너트결합에 의해 저항판(20)에 고정되는 것으로, 머리에 고리를 구비한다. The eye bolt 30 is inserted into the fastening hole 23 of the resistance plate wing part is fixed to the resistance plate 20 by nut coupling, and has a ring on the head.

상기 아이너트(40)는 자연석의 후면에 일체형으로 설치된 셋트앙카(11)에 나사결합되는 것으로, 머리에 고리를 구비한다. The eye nut 40 is screwed to the set anchor 11 is integrally installed on the back of the natural stone, it has a ring on the head.

상기 띠형 섬유보강재(50)는 폴리에스테르 원사를 기본 자재로 하여 폴리에틸렌 코팅을 한 것으로, 지반보강 역할을 하며, 띠형 섬유보강재의 마찰력에 의해 자연석과 지반의 연결 강도를 증가시킨다. 또한, 상기 띠형 섬유보강재는 분리형 띠형 섬유보강재(50a)를 사용하는 것이 바람직하며, 재질은 부식되지 않는 것이면 만족하고, 반드시 폴리에스테르 원사를 기본자재로 하여 폴리에틸렌 코팅을 한 것만을 한정하는 것은 아니다. The band-shaped fiber reinforcement 50 is a polyethylene coating based on a polyester yarn, serves as ground reinforcement, and increases the connection strength between natural stone and the ground by the friction of the band-shaped fiber reinforcement. In addition, the strip-fiber reinforcing material is preferably to use a separate strip-fiber reinforcing material (50a), the material is satisfactory if it does not corrode, and is not necessarily limited to the polyethylene coated with a polyester yarn as a base material.

상기 분리형 띠형 섬유보강재(50a)는 2개의 띠형 섬유보강재 일측단이 분리가능하도록 서로 연결되어 일체화를 이루도록 되어 있는 것으로, 도 4 에 도시된 바와 같이, 일측 띠형 섬유보강재(51)와 또다른 띠형 섬유보강재(52)가 절개부(53)를 구비하며 일체형으로 형성되어 있어, 절개부(53)에 의해 2개의 띠형 섬유보강재(51,52)로 분리가 용이하고, 도 3 에 도시된 바와 같이 절개부(53)를 중심으로 2개의 띠형 섬유보강재(51,52)를 포개어(접어서) 사용할 수 있도록 되어 있다. The separate strip-shaped fiber reinforcement (50a) is formed so that the two ends of the strip-shaped fiber reinforcement is connected to each other so as to be separated, as shown in Figure 4, one side of the strip-shaped fiber reinforcement 51 and another strip-shaped fiber The reinforcing material 52 is provided integrally with the cutout 53 and is easily separated into two strip-shaped fiber reinforcements 51 and 52 by the cutout 53, as shown in FIG. 3. The two strip | belt-shaped fiber reinforcement materials 51 and 52 are piled up around the part 53, and can be used.

상기와 같이 구성된 본 발명을 이용한 자연석 옹벽의 시공방법에 대하여 설명하면 다음과 같다. Referring to the construction method of the natural stone retaining wall using the present invention configured as described above are as follows.

도 5 는 본 발명에 따른 옹벽시공을 보인 블록 예시도를 도시한 것으로, 자연석 쌓을 곳의 지반을 터파기한 후 지면을 다짐하는 터파기단계(S100)와, 상기 다짐된 지면에 기초 철근콘크리트를 타설하는 기초단계(S200)와, 상기 타설된 기초 철근콘크리트에 다수개의 자연석을 배석하는 자연석 배석단계(S300)와, 상기 자연석 후면에 일체형으로 설치된 셋트앙카 및 이에 나사결합된 아이너트 하단까지 뒷채움하는 뒷채움단계(S400)와, 상기 자연석 후부의 뒷채움된 토사에 소정거리를 유지하도록 다수개의 저항판을 고정설치하는 저항판 설치단계(S500)와, 상기 배석된 다수개 자연석의 아이너트 고리와 저항판의 아이볼트 고리를 왕복하도록 띠형 섬유보강재를 포설하여 고정하는 띠형 섬유보강재 설치단계(S600)와, 상기 자연석의 아이너트 및 이에 연결된 띠형 섬유보강재가 매립되도록 자연석 후부 일부분을 뒷채움하여 상부에 위치할 자연석의 지지기반을 형성하는 지지기반 형성단계(S700)와, 상기 형성된 지지기반에 또다른 자연석을 위치시키고, 상기 자연석 후면에 설치된 셋트앙카 및 아이너트 하단까지 다시 뒷채움하는 재 뒷채움단계(S800)와, 상기 상 부에 위치하는 자연석에 띠형 섬유보강재 설치단계, 지지기반 형성단계, 재 뒷채움단계를 다수번 반복하여 자연석을 다단계로 적층하는 반복시공단계(S900)를 통해 자연석 옹벽을 시공하도록 되어 있다. Figure 5 is a block diagram showing the retaining wall construction according to the present invention, the excavation step (S100) for compacting the ground after digging the ground of the natural stone stacking place, and reinforce the concrete based on the ground ground The foundation stage (S200), and the natural stone placement step (S300) for arranging a plurality of natural stones on the foundation of reinforced concrete, and the back anchor to the back of the set anchor and integrally screwed in the nut nut installed on the back of the natural stone Step (S400), and the resistance plate installation step (S500) of fixing the plurality of resistance plates to maintain a predetermined distance in the back-filled earth and sand of the natural stone, and the eye nut ring and the resistance plate of the plurality of natural stones A step of installing a strip-shaped fiber reinforcement to install and fix the strip-shaped fiber reinforcement to reciprocate the eye bolt ring (S600), the eye nut of the natural stone and the band-type connected thereto A support base forming step (S700) of forming a support base of a natural stone to be located on the back by filling a rear portion of the natural stone so that the fiber reinforcement is embedded, and placing another natural stone on the formed support base, the set anchor installed on the back of the natural stone. And re-filling back to the bottom of the eye nut (S800), and repeating the multiple-stage stacking of natural stones by repeating the band-shaped fiber reinforcement step, support base forming step, and back-filling step on the natural stone located above. The construction step (S900) through the natural stone retaining wall is to be constructed.

상기 자연석 배석단계(S300)는 다단계의 옹벽축조시 제일 하단에 위치하는 기초자연석(10a)을 배치시키는 것으로, 타설된 콘크리트 구조물(80)에 하부가 일체형으로 고정되도록 각도를 조절하여 배석한다. 이때, 상기 기초자연석(10a)은 직립상태를 유지하도록 각도를 조정하고, 기초자연석 후면을 기초철근 콘크리트의 철근(81)과 지지강봉(82)에 의해 연결하여 기초자연석의 위치를 견고하게 고정할 수 있다. The natural stone arrangement step (S300) is to place the basic natural stone (10a) located at the bottom of the retaining wall when the construction of the multi-stage, is adjusted by adjusting the angle so that the bottom is fixed integrally to the cast concrete structure (80). At this time, the basic natural stone (10a) is adjusted to maintain the upright state, by connecting the back of the basic natural stone by the reinforcing bars 81 and the support steel rods 82 of the reinforced concrete concrete to firmly fix the position of the basic natural stone Can be.

이때, 상기 기초자연석(10a)의 후면에는 셋트앙카(11)가 설치되어 있으며, 상기 셋트앙카(11)에는 아이너트(40)가 나사결합되어 일체형으로 설치되어 있다. At this time, a set anchor 11 is installed on the rear surface of the basic natural stone 10a, and an eye nut 40 is screwed to the set anchor 11 to be integrally installed.

상기 뒷채움단계(S400)는 자연석의 후면에 설치된 셋트앙카(11) 및 이에 결합된 아이너트(40) 하단까지 토사가 위치하도록 약 20∼30㎝ 두께로 토사를 포설한 후, 지반의 지내력 증가와 침하를 방지하기 위하여 콤팩터 및 로울러등의 다짐장비로 층다짐하는 것으로, 기초자연석에 지지강봉(82)이 설치되어 있을 경우, 상기 지지강봉(82)이 매립되도록 뒷채움(100)을 한다. 이때, 상기 기초자연석(10a)은 기초콘크리트 또는 기초콘크리트와 지지강봉에 의해 그 위치가 고정되나 상기 기초철근 콘크리트와 지지강봉이 모두 뒷채움에 의해 매립되므로, 다짐시 간섭현상이 발생되지 않게 되며, 이로 인해 옹벽축조시 요구되는 다짐도 85% 이상의 층다짐을 실시할 수 있다. The backfilling step (S400) is after laying the soil to about 20 ~ 30 ㎝ thickness so that the earth to the bottom of the set anchor (11) and the eye nut (40) coupled to the back of the natural stone is located, and increase the bearing capacity of the ground and In order to prevent settlement, the compaction equipment such as compactors and rollers are compacted. When the supporting steel rods 82 are installed in the basic natural stone, the backing steels 100 are filled so that the supporting steel rods 82 are embedded. At this time, the basic natural stone (10a) is fixed to the position by the base concrete or the foundation concrete and the supporting steel bar, but the base reinforced concrete and the supporting steel rods are all buried by the backfill, so that interference does not occur when compacting, so Therefore, the compaction required for the retaining wall construction can be carried out a layer compaction of 85% or more.

상기 저항판 설치단계(S500)는 다수개의 앙카핀(70)에 의해 저항판(20)을 뒷채움된 토사에 고정설치하는 것으로, 저항판에 설치된 아이볼트(30)가 외부로 노출되도록 제 1,2 앙카핀(71,72)에 의해 저항판(20)을 설치한다. 이때, 상기 저항판(20)은 자연석과 자연석 사이에 위치하도록 자연석 후부에 소정거리를 유지하고 설치된다. The resistance plate installation step (S500) is to fix the resistance plate 20 to the back-filled soil by a plurality of anchor pins 70, the eye bolt 30 installed on the resistance plate to expose the first, 2 The resistance plate 20 is provided by the anchor pins 71 and 72. At this time, the resistance plate 20 is installed while maintaining a predetermined distance to the rear of the natural stone to be located between the natural stone and the natural stone.

상기 아이볼트(30)는 머리에 형성된 고리가 자연석(10) 후부를 향하도록 저항판에 형성된 체결홀(23)내로 나사산을 구비하는 몸체가 삽입되고, 저항판 체결홀(23)을 관통한 몸체에 너트(60)를 체결하여 아이볼트(30)와 저항판(20)을 일체화한다. 이때, 상기 너트(60)와 이에 체결된 아이볼트(30) 몸체에 에폭시 수지 등을 도포할 경우, 너트의 움직임을 방지하게 되므로, 너트의 이탈이 방지된다. The eye bolt 30 is a body having a thread is inserted into the fastening hole 23 formed in the resistance plate so that the ring formed in the head toward the rear of the natural stone 10, the body through the resistance plate fastening hole 23 The eye bolt 30 and the resistance plate 20 are integrated by tightening the nut 60. At this time, when the epoxy resin is applied to the nut 60 and the body of the eye bolt 30 fastened thereto, the movement of the nut is prevented, so that the nut is separated.

상기 자연석과 저항판의 거리관계, 제 1,2 앙카, 저항판의 두께 및 크기 등등의 규격은 통상적인 구조계산에 의해 결정되는 것이므로, 이에 대한 상세한 설명은 생략한다. Since the specifications of the distance relationship between the natural stone and the resistance plate, the first and second anchors, the thickness and the size of the resistance plate, etc. are determined by a conventional structural calculation, a detailed description thereof will be omitted.

상기 띠형 섬유보강재 설치단계(S600)는 자연석의 아이너트(40)와 저항판의 아이볼트(30)를 띠형 섬유보강재(50)로 연결하여 자연석을 견고하게 지지하는 것으로, 다수개의 자연석과 저항판이 서로 연결되도록 띠형 섬유보강재가 지그재그 형상으로 왕복하여 연결되거나, 자연석과 저항판이 서로 사각형상으로 왕복하여 연결된다. The strip-shaped fiber reinforcement step (S600) is to support the natural stone firmly by connecting the eye nut 40 of the natural stone and the eye bolt 30 of the resistance plate with a strip-shaped fiber reinforcement 50, a plurality of natural stone and the resistance plate The strip-shaped fiber reinforcement is reciprocally connected in a zigzag shape to be connected to each other, or the natural stone and the resistance plate are connected to each other in a square shape.

즉, 상기 띠형 섬유보강재(50)는 자연석-저항판-자연석-저항판 등과 같이, 다수개의 자연석과 저항판이 연속적으로 서로 번갈아가며 연결되도록 지그재그 형 상으로 연결하거나, 저항판-자연석-자연석-저항판 등과 같이, 설치된 띠형 섬유보강재가 사각형상으로 연결되도록 설치될 수 있다. 상기와 같이 연결 설치된 띠형 섬유보강재는 뒷채움된 지면에 밀착되도록 긴장하여 설치된다. That is, the strip-shaped fiber reinforcement 50 is connected in a zigzag shape such that a plurality of natural stones and resistance plates are alternately connected to each other in series, such as natural stone-resistance plate-natural stone-resistance plate, or resistance plate-natural stone-natural stone-resistance. Like a plate, the installed strip-shaped fiber reinforcement may be installed to be connected in a square shape. The belt-shaped fiber reinforcement connected as described above is installed to be in close contact with the back-filled ground.

이때, 상기 띠형 섬유보강재(50)로 분리형 띠형 섬유보강재(53)를 사용할 경우, 상기 분리형 띠형 섬유보강재(50a)는 아이볼트 및 아이너트의 고리에 삽입될 시, 중간부분의 절개부(53)를 중심으로 접어서 삽입관통되므로, 아이볼트 및 아이너트 고리와의 연결부위에 대한 인장력(지지력)을 향상시키며, 아이볼트 및 아이너트 고리와의 연결부위 이외에는 모두 펴진 상태를 유지하도록 되어 있어, 이후 뒷채움시, 뒷채움되는 토사내에서는 펴진 상태로 매립되게 되므로, 뒷채움 토사와의 마찰력이 증대된다. At this time, when using a separate strip type fiber reinforcement 53 as the strip type fiber reinforcement 50, the split type strip type fiber reinforcement 50a is inserted into the eye bolt and the eye nut, the incision part of the middle portion 53 Since it is penetrated through the insertion, it improves the tensile force (supporting force) for the connection part between the eye bolt and the eye nut ring, and maintains the state of being stretched except for the connection part with the eye bolt and the eye nut ring. At the time of being filled up in the backfilled soil, it is buried in an expanded state, so the frictional force with the backfilled soil is increased.

상기 지지기반 형성단계(S700)는 자연석의 다단계 적층시, 하부에 위치하는 자연석의 후부 일부를 뒷채움하여, 상부에 위치하는 자연석의 지지기반(110)을 형성하기 위한 것으로, 띠형 섬유보강재(50)가 긴장되도록 설치된 자연석의 후부에, 아이너트 및 띠형 섬유보강재가 매립되도록 하부에 위치하는 자연석과 저항판 사이의 일부분을 뒷채움한다. 이때, 상기 뒷채움되는 부분의 높이는 상부에 위치하는 자연석(10b,10c)의 설치위치에 따라 조절하여 뒷채움한다. 이와 같은 지지기반 형성단계는 상부에 위치하게 될 자연석(10b,10c)의 침하를 방지하고 이를 통해 옹벽의 전도를 방지하기 위한 것으로, 부분적인 뒷채움을 통해 지지기반을 더욱 견고하고 치밀하게 다질 수 있다.The support base forming step (S700) is to form a support base 110 of the natural stone located in the upper part by back-filling a part of the rear part of the natural stone located at the bottom of the multi-stage stacking of the natural stone, the band-shaped fiber reinforcement (50) In the back of the natural stone is installed so that the tension, the portion between the natural stone and the resistance plate located in the lower portion so that the eye nut and the strip-shaped fiber reinforcement is embedded. At this time, the height of the portion to be filled back is adjusted according to the installation position of the natural stone (10b, 10c) located in the upper portion. This support base forming step is to prevent the settlement of the natural stone (10b, 10c) to be located at the top and thereby to prevent the fall of the retaining wall, through the partial backfill can further solidify the support base more firmly .

상기 재 뒷채움단계(S800)는 지지기반(110) 형성에 의해 자연석을 상부와 하 부의 다단계로 적층한 후, 상기 상부에 위치하는 자연석(10b,10c)의 후면에 설치된 셋트앙카 및 이에 결합된 아이너트 하단까지 토사가 위치하도록 약 20∼30㎝ 두께로 토사를 포설한 다음, 지반의 지내력 증가와 침하를 방지하기 위하여 콤팩터 및 로울러등의 다짐장비로 층다짐한다. 이때, 상기 다짐은 다짐도 85% 이상의 층다짐을 실시한다.The backfilling step (S800) is a stack of natural stone by forming the support base 110 in the upper and lower multi-stage, and then set anchors installed on the rear of the natural stone (10b, 10c) located in the upper and the child coupled thereto The soil is laid 20 ~ 30cm thick so that the soil is located up to the bottom of the nut, and then compacted with compactors and compactors to prevent the ground strength increase and settlement. At this time, the compaction is to perform a compaction of 85% or more compaction.

상기 반복시공단계(S900)는 상부에 위치하는 자연석에 띠형 섬유보강재를 긴장 설치하고, 자연석 후부에 다시 상부에 위치할 또다른 자연석의 지지기반을 형성한 다음, 이에 다시 재 뒷채움을 하여 자연석을 견고하게 지지한다.The repeating step (S900) is to install a tension-shaped fiber reinforcement in the natural stone located in the upper portion, and to form a support base of another natural stone to be placed in the upper part in the back of the natural stone, and then backfilled again to solidify the natural stone Support.

본 발명은 이와 같은 반복시공에 의해 자연석이 다단계로 적층시공되어 견고한 자연석 옹벽을 축조할 수 있도록 되어 있다.The present invention is a natural stone is laminated in multiple stages by such repeated construction is to be able to build a solid natural stone retaining wall.

본 발명은 상술한 특정의 바람직한 실시예에 한정되지 아니하며, 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 기술분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변형실시가 가능한 것은 물론이고, 그와 같은 변경은 청구범위 기재의 범위내에 있게 된다.The present invention is not limited to the above-described specific preferred embodiments, and various modifications can be made by any person having ordinary skill in the art without departing from the gist of the present invention claimed in the claims. Of course, such changes will fall within the scope of the claims.

이와 같이 본 발명은 아이볼트와 아이너트 및 띠형 섬유보강재에 의해 자연석과 저항판을 연결하도록 되어 있어, 용접작업이 불필요하며, 이로 인해 조립성, 시공성이 향상되고, 규격화된 아이볼트 및 아이너트 및 간단한 부품에 의해 연결하 므로, 생산성 향상 및 부품조달을 용이하게 할 수 있다.As described above, the present invention is to connect the natural stone and the resistance plate by the eye bolt and the eye nut and the band-shaped fiber reinforcement, which eliminates the need for welding work, thereby improving the assemblability, constructability, and standardized eye bolt and eye nut and Connection by simple parts can improve productivity and facilitate part procurement.

또한, 본 발명은 자연석을 띠형 섬유보강재에 의해 저항판에 연결하여 지지하고, 상기 섬유보강재는 뒷채움된 지반에 밀착되게 또한 긴장되게 설치되도록 되어 있어, 뒷채움시 자연석의 지지로 인한 간섭현상이 발생되지 않으며, 이를 통해 층다짐 85% 이상으로 뒷채움을 실시할 수 있다. In addition, the present invention is to support the natural stone is connected to the resistance plate by the band-shaped fiber reinforcement, the fiber reinforcement is to be installed in close contact with the back ground and tension, so that the interference phenomenon due to the support of the natural stone during back filling In this way, backfilling can be performed with more than 85% of stratification.

또한, 본 발명은 용접부위의 발생없이 자연석을 견고하게 지지하도록 되어 있어, 비틀리거나 꺽이는 각도에 대한 강도가 약한 특성을 구비하는 용접부위로 인한 지지력 저하를 해소할 수 있을 뿐만 아니라, 용접부위의 부식 및 변형으로 인한 문제점 역시 모두 해소할 수 있다.In addition, the present invention is to support the natural stone firmly without the occurrence of a welded portion, it is possible not only to solve the reduction in bearing capacity due to the welded portion having a weak strength for twisting or bending angle, but also corrosion and Any problems caused by the transformation can also be solved.

또한, 본 발명은 아이볼트/너트의 고리와 같이 응력이 집중적으로 발생되는 부위에 대하여, 띠형 섬유보강재를 접어서 삽입설치하므로, 인장강도를 향상시키고, 자연석과 저항판을 견고하게 연결할 수 있다.In addition, the present invention can be installed by folding the belt-shaped fiber reinforcement for the site where the stress is concentrated, such as the eye bolt / nut ring, thereby improving the tensile strength, it is possible to firmly connect the natural stone and the resistance plate.

또한, 본 발명의 띠형 섬유보강재는 뒷채움시 펴진상태를 유지하며 매립되도록 되어 있어, 띠형 섬유보강재의 마찰력을 증대시키고, 이를 통해 자연석과 지반의 연결 강도를 증가시킬 수 있는 등 많은 효과가 있다.In addition, the belt-shaped fiber reinforcement of the present invention is to be embedded while maintaining the unfolded state in the back filling, thereby increasing the frictional force of the belt-shaped fiber reinforcement, thereby increasing the connection strength between the natural stone and the ground has many effects.

Claims (7)

자연석 옹벽구조물에 있어서;Natural stone retaining wall structure; 기립형태로 설치되는 다수개의 자연석과,A number of natural stones installed in a standing form, 상기 자연석의 후부에 위치하도록 앙카핀에 의해 뒷채움된 토사에 고정되는 저항판과,A resistance plate fixed to the earth and sand backfilled with ancafin to be located at the rear of the natural stone; 상기 저항판에 너트 결합되는 다수개의 아이볼트와,A plurality of eye bolts nut-coupled to the resistance plate; 상기 자연석의 후면에 설치된 셋트앙카에 나사결합되는 아이너트와,An eye nut screwed into the set anchor installed at the rear of the natural stone, 상기 아이볼트와 아이너트의 고리에 삽입관통되어 자연석과 저항판을 연결지지하는 띠형 섬유보강재를 포함하되,Inserted through the ring of the eye bolt and the eye nut includes a band-shaped fiber reinforcement for supporting the natural stone and the resistance plate, 상기 저항판은 내부에 뒷채움 토사가 위치하여 지지력을 향상시키도록 굴곡을 구비하는 지지부와, 상기 지지부의 양측단에 각각 일체형으로 형성되고 아이볼트가 너트결합되는 날개부로 이루어져 전체적인 평면형상이 다수개의 굴곡을 구비하는 모자형상을 구비하는 것을 특징으로 하는 자연석 옹벽구조물.The resistance plate is composed of a support portion having a bent to improve the supporting force is located in the back-filled soil inside, and a wing portion which is formed integrally at both ends of the support portion and the eye bolt is nut-coupled, the overall planar shape is a plurality of bends Natural stone retaining wall structure comprising a hat shape having a. 제 1 항에 있어서;The method of claim 1; 상기 띠형 섬유보강재는 분리형 띠형 섬유보강재인 것을 특징으로 하는 자연석 옹벽구조물.The strip-shaped fiber reinforcement is a natural stone retaining wall structure, characterized in that the separate strip-shaped fiber reinforcement. 삭제delete 자연석 옹벽구조물의 시공방법에 있어서;In the construction method of natural stone retaining wall structure; 자연석 쌓을 곳의 지반을 터파기한 후 지면을 다짐하는 터파기단계,Demolition step of digging the ground of natural stone stacking place and then compacting the ground, 상기 다짐된 지면에 기초 철근콘크리트를 타설하는 기초단계,A foundation step of placing the foundation reinforced concrete on the ground; 상기 타설된 기초 철근콘크리트에 다수개의 자연석을 배석하는 자연석 배석단계,Natural stone stone step of placing a plurality of natural stones in the foundation of reinforced concrete, 상기 자연석 후면에 일체형으로 설치된 셋트앙카 및 이에 나사결합된 아이너트 하단까지 뒷채움하는 뒷채움단계,Back filling step of back-filling to the bottom of the set anchor and integrally screwed eye nut installed in the back of the natural stone, 상기 자연석 후부의 뒷채움된 토사에 소정거리를 유지하고 외부로 노출된 아이볼트가 자연석 후부를 향하도록 다수개의 저항판을 앙카핀에 의해 고정설치하는 저항판 설치단계,Resistor plate installation step of maintaining a predetermined distance in the back-filled earth and sand of the natural stone, and fixedly installed by the anchor pin a plurality of resistance plates to the eye bolt exposed to the rear of the natural stone, 상기 배석된 다수개 자연석의 아이너트 고리와 저항판의 아이볼트 고리를 왕복하도록 띠형 섬유보강재를 포설하여 고정하는 띠형 섬유보강재 설치단계,Installing the band-shaped fiber reinforcement to install and fix the band-shaped fiber reinforcement to reciprocate the eye nut ring of the plurality of natural stone and the eye bolt ring of the resistance plate, 상기 자연석의 아이너트 및 이에 연결된 띠형 섬유보강재가 매립되도록 자연석 후부 일부분을 뒷채움하여 상부에 위치할 자연석의 지지기반을 형성하는 지지기반 형성단계,A support base forming step of forming a support base of the natural stone to be located on the upper part by back-filling the rear portion of the natural stone so that the eye nut of the natural stone and the band-shaped fiber reinforcement connected thereto are embedded; 상기 형성된 지지기반에 또다른 자연석을 위치시키고, 상기 자연석 후면에 설치된 셋트앙카 및 아이너트 하단까지 다시 뒷채움하는 재뒷채움단계,Positioning another natural stone on the formed support base, and back-filling step of back-filling back to the bottom of the set anchor and eye nut installed on the back of the natural stone, 상기 상부에 위치하는 자연석에 띠형 섬유보강재 설치단계, 지지기반 형성단계, 재뒷채움단계를 다수번 반복하여 자연석을 다단계로 적층하는 반복시공단계로 이루어진 것을 특징으로 하는 자연석 옹벽구조물 시공방법.Natural stone retaining wall structure construction method characterized in that consisting of a repeating step of laminating the natural stone in multiple stages by repeating the band-shaped fiber reinforcement installation step, the support base forming step, the back-filling step a number of times to the natural stone located on the upper. 제 4 항에 있어서;The method of claim 4; 상기 띠형 섬유보강재는 분리형 띠형 섬유보강재인 것을 특징으로 하는 자연석 옹벽구조물 시공방법.The strip-shaped fiber reinforcement is a natural stone retaining wall structure construction method, characterized in that the separate strip-shaped fiber reinforcement. 제 4 항 또는 제 5 항에 있어서;The method of claim 4 or 5; 상기 띠형 섬유보강재는 아이볼트 및 아이너트의 고리에 삽입될 시, 중간부분의 절개부를 중심으로 접어서 삽입관통하여 아이볼트 및 아이너트 고리와 연결하고, 아이볼트 및 아이너트 고리와의 연결부위 이외에는 모두 펴진 상태를 유지하여 뒷채움시, 뒷채움되는 토사내에서는 펴진 상태로 매립되도록 한 것을 특징으로 하는 자연석 옹벽구조물 시공방법.When the band-shaped fiber reinforcement is inserted into the eye bolt and the eye nut ring, it is folded around the incision part of the middle part and inserted and connected to the eye bolt and the eye nut ring, and all but the connection parts of the eye bolt and the eye nut ring. The method of constructing a natural stone retaining wall structure, characterized in that when the backfilled to maintain the expanded state, in the backfilled soil to be buried in an expanded state. 제 4 항 또는 제 5 항에 있어서;The method of claim 4 or 5; 상기 띠형 섬유보강재는 다수개의 자연석과 저항판이 서로 연결되도록 지그재그 형상으로 왕복하여 연결되거나, 자연석과 저항판이 서로 사각형상으로 왕복하여 연결되는 것을 특징으로 하는 자연석 옹벽구조물 시공방법.The strip-shaped fiber reinforcement is a natural stone retaining wall structure construction method characterized in that the plurality of natural stone and the resistance plate is connected reciprocally in a zigzag shape to be connected to each other, or the natural stone and the resistance plate is connected to each other in a square shape.
KR1020060117436A 2006-11-27 2006-11-27 Revetment structure using natural stones and method for constructing revetment structure using the same KR100822265B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060117436A KR100822265B1 (en) 2006-11-27 2006-11-27 Revetment structure using natural stones and method for constructing revetment structure using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060117436A KR100822265B1 (en) 2006-11-27 2006-11-27 Revetment structure using natural stones and method for constructing revetment structure using the same

Publications (1)

Publication Number Publication Date
KR100822265B1 true KR100822265B1 (en) 2008-04-16

Family

ID=39571511

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060117436A KR100822265B1 (en) 2006-11-27 2006-11-27 Revetment structure using natural stones and method for constructing revetment structure using the same

Country Status (1)

Country Link
KR (1) KR100822265B1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101068943B1 (en) 2009-07-14 2011-09-30 (주)대한콜크 Belt Type Extile Reinforcement and Method thereof
KR101376225B1 (en) * 2010-03-18 2014-03-21 전철수 Retaining Wall Having Natural Rock And Construction Method Thereof
KR101501733B1 (en) * 2014-05-30 2015-03-18 대한이.이엔.씨(주) The eco-friendly precast l type retaining wall fixed with an anchor
KR101574666B1 (en) * 2015-01-21 2015-12-04 안기석 Embankment type reinforced earth retaining wall
KR20190004497A (en) * 2017-07-04 2019-01-14 주식회사 에코밸리 A Eco-friendly retain wall structure
KR20200045997A (en) * 2017-07-04 2020-05-06 주식회사 에코밸리 A Eco-friendly retain wall structure

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100396294B1 (en) * 2001-10-30 2003-09-02 이재경 Process for safe construction of retaining wall by natural stones
KR100401237B1 (en) * 1999-11-04 2003-10-10 (주)천일기술단 Soil improvement technique for foundation applied to reinforced earth theory using reinforcing rod-band-types anchor
KR20060034611A (en) * 2004-10-19 2006-04-24 이정수 Reinforcing strip for supporting reinforced earth wall and its placement method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100401237B1 (en) * 1999-11-04 2003-10-10 (주)천일기술단 Soil improvement technique for foundation applied to reinforced earth theory using reinforcing rod-band-types anchor
KR100396294B1 (en) * 2001-10-30 2003-09-02 이재경 Process for safe construction of retaining wall by natural stones
KR20060034611A (en) * 2004-10-19 2006-04-24 이정수 Reinforcing strip for supporting reinforced earth wall and its placement method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101068943B1 (en) 2009-07-14 2011-09-30 (주)대한콜크 Belt Type Extile Reinforcement and Method thereof
KR101376225B1 (en) * 2010-03-18 2014-03-21 전철수 Retaining Wall Having Natural Rock And Construction Method Thereof
KR101501733B1 (en) * 2014-05-30 2015-03-18 대한이.이엔.씨(주) The eco-friendly precast l type retaining wall fixed with an anchor
KR101574666B1 (en) * 2015-01-21 2015-12-04 안기석 Embankment type reinforced earth retaining wall
KR20190004497A (en) * 2017-07-04 2019-01-14 주식회사 에코밸리 A Eco-friendly retain wall structure
KR20200045997A (en) * 2017-07-04 2020-05-06 주식회사 에코밸리 A Eco-friendly retain wall structure
KR102116085B1 (en) * 2017-07-04 2020-05-27 (주)에코밸리 A Eco-friendly retain wall structure
KR102285192B1 (en) * 2017-07-04 2021-08-04 (주)에코밸리 A Eco-friendly retain wall structure

Similar Documents

Publication Publication Date Title
US6089792A (en) Reinforced retaining wall
JP2016515173A (en) Precast concrete retaining wall
KR100822265B1 (en) Revetment structure using natural stones and method for constructing revetment structure using the same
CN102966119A (en) Geogrid reinforced wall and construction method thereof
JP2007530833A (en) Reinforced soil retaining wall system and construction method
KR100870150B1 (en) A multi-function block for retaining wall and constructing method using the same
CN109235490B (en) Retaining wall and construction method thereof
KR101031583B1 (en) The natural stone retaining structure using blasted rocks and concrete resistance blocks and its construction technique
US7828497B2 (en) Construction and design method
US20030143038A1 (en) Multiple synthetic deformed bars and retaining walls
JPS6245801A (en) Construction of structure by foamed resin block
KR102263958B1 (en) the Method of Construction of Prefabricated Block for Retaining Wall Bulwark
JP3244324B2 (en) Mountain retaining method
JP3364432B2 (en) Stone retaining wall
KR200223114Y1 (en) A structure reinforcing for retaining wall for inclined plane which to cut off a rock wall
JP2963360B2 (en) Wall structure of reinforced soil structure
JP3665896B2 (en) Reinforced embankment body and its construction method
JP4332651B2 (en) Foundation reinforcement device and foundation construction method
JP2547946B2 (en) Reinforced soil structure
JPH10204883A (en) Execution method of reinforcing bank wall
JP5587725B2 (en) Reinforcement method for existing foundations for structures
KR101058628B1 (en) Retaining wall construction structure using landscape stones
KR101782408B1 (en) Methods for constructing retaining wall using fastening unit for stiffener
KR20090129137A (en) Rock construction structure of using anchor and method thereof
JPH0548820B2 (en)

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121009

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee