JP2002294710A - Construction method for new route utilizing lightweight earth filling method - Google Patents
Construction method for new route utilizing lightweight earth filling methodInfo
- Publication number
- JP2002294710A JP2002294710A JP2001093703A JP2001093703A JP2002294710A JP 2002294710 A JP2002294710 A JP 2002294710A JP 2001093703 A JP2001093703 A JP 2001093703A JP 2001093703 A JP2001093703 A JP 2001093703A JP 2002294710 A JP2002294710 A JP 2002294710A
- Authority
- JP
- Japan
- Prior art keywords
- lightweight embankment
- construction
- new route
- work
- new
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Road Paving Structures (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、軽量盛土工法によ
る新たな路線の構築方法に関し、特に、作業用重機のた
めの仮設足場を建て込むことなく新たな路線を連続して
構築していくことを可能とする軽量盛土工法を利用した
新規な路線構築方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a new line by a lightweight embankment method, and more particularly to a method for continuously constructing a new line without building a temporary scaffold for a heavy working machine. The present invention relates to a novel route construction method using a lightweight embankment method that enables the construction.
【0002】[0002]
【従来の技術】軟弱地盤や地滑り地などでの盛土工法の
一つとしてEPS工法のような軽量盛土材を用いた軽量
盛土工法が知られている。この工法は、地盤改良にかか
る経費の節減、工期の短縮、耐震性の向上などにおいて
優れた効果を発揮することから、種々の土木工事におい
て広く採用されている。施工に当たっては、支持地盤の
整備、支持杭としてのH形鋼の搬入と打ち込み、発泡ポ
リスチレンブロック(EPSブロック)のような軽量盛
土材の積み上げ、など種々の土木工事や作業が必要であ
り、そのためにクレーン車などの種々の重機が用いられ
る。2. Description of the Related Art A lightweight embankment method using a lightweight embankment material such as an EPS method is known as one of embankment methods on soft ground and landslides. This construction method is widely used in various civil engineering works because it has excellent effects in saving costs for ground improvement, shortening the construction period, improving earthquake resistance, and the like. In the construction, various civil works and work are required, such as maintenance of the support ground, loading and driving of H-shaped steel as a support pile, and stacking of lightweight embankment material such as expanded polystyrene block (EPS block). Various heavy machines such as crane trucks are used for such vehicles.
【0003】図4は軽量盛土工法による道路工事の一例
を示しており、ここでは、頂部に作られている既存の道
路1を既存地山の斜面側に拡幅している。支持地盤3を
整備した後、H形鋼2を建て込み、該H形鋼2と支持地
盤3との間に軽量盛土材としてのEPSブロック4を積
み上げて所定の高さの盛土部を形成し、その後、積み上
げたEPSブロック4の全面に所定厚さにコンクリート
を打設して、コンクリート床版5を形成する。また、H
形鋼2を利用して軽量コンクリート板のような壁面保護
材7も取り付ける。[0003] Fig. 4 shows an example of road construction by a lightweight embankment method, in which an existing road 1 formed on the top is widened to the slope side of an existing mountain. After the support ground 3 is prepared, the H-section steel 2 is erected, and the EPS block 4 as a lightweight embankment material is stacked between the H-section steel 2 and the support ground 3 to form an embankment having a predetermined height. Thereafter, concrete is poured into the entire surface of the stacked EPS blocks 4 to a predetermined thickness to form a concrete floor slab 5. Also, H
A wall protection material 7 such as a lightweight concrete plate is attached by using the shape steel 2.
【0004】次に、コンクリート床版5およびEPSブ
ロック4が水平方向の位置ズレを起こさないように、支
持地盤3に埋設固定したアンカー6の先端をコンクリー
ト床版5に一体に固定し、地震などにより支持地盤3が
動いたときに、コンクリート床版5およびEPSブロッ
ク4が支持地盤3から剥離することを回避する。その
後、コンクリート床版5の谷側縁に地覆コンクリート8
が作られ、通常の土木工事のように、路盤9やアスファ
ルト10などの仕上げのための工事が施されて、道路の
拡幅工事は終了する。Next, in order to prevent the concrete slab 5 and the EPS block 4 from being displaced in the horizontal direction, the tip of an anchor 6 embedded and fixed in the supporting ground 3 is fixed integrally to the concrete slab 5, and the earthquake This prevents the concrete floor slab 5 and the EPS block 4 from separating from the supporting ground 3 when the supporting ground 3 moves. After that, ground covering concrete 8
Then, as in the case of ordinary civil engineering work, the work for finishing the roadbed 9 and the asphalt 10 is performed, and the road widening work is completed.
【0005】[0005]
【発明が解決しようとする課題】前記のように、軽量盛
土工法においては、支持地盤の整備やH形鋼の搬入と打
ち込み、あるいは軽量盛土材の積み上げなどの重作業が
必須であり、そのためにクレーン車のような大型重機が
多く用いられる。しかし、軽量盛土工法は、本来、軟弱
地盤や地滑り地などにおいて採用される工法であり、工
事現場の近くに重機用の足場を確保することは容易でな
い。通常、図4に示すように、例えば既設の道路1を一
時的に閉鎖するなどして大がかりな重機用の仮設足場2
0を施工現場に近接して構築し、その仮設足場20を利
用して重機21による作業が行われる。As described above, in the lightweight embankment method, heavy work such as maintenance of the supporting ground, loading and driving of the H-section steel, or stacking of the lightweight embankment material is indispensable. Large heavy equipment such as a crane truck is often used. However, the lightweight embankment method is originally used on soft ground and landslides, and it is not easy to secure a scaffold for heavy equipment near the construction site. Normally, as shown in FIG. 4, a temporary scaffold 2 for large heavy equipment is constructed by temporarily closing an existing road 1, for example.
0 is constructed close to the construction site, and the work is performed by the heavy equipment 21 using the temporary scaffold 20.
【0006】仮設足場20上でのクレーン車などによる
作業範囲はそのブーム22の長さに限られることから、
施工する路線に沿って、仮設足場20も順次移動させる
ことが必要であり、仮設足場20の構築と移設にかかる
費用は、全施工コストの大きな割合を占める。道路の拡
幅工事のような場合に、全作業路線にわたり既設の道路
1を重機21の足場として用いることは可能であるが、
その場合には、当該既設路線1を作業期間中長期にわた
り共用から外すこととなり、現実的な解決策ではない。[0006] Since the working range of the crane truck or the like on the temporary scaffold 20 is limited to the length of the boom 22,
It is necessary to sequentially move the temporary scaffolding 20 along the construction line, and the cost of constructing and relocating the temporary scaffolding 20 accounts for a large proportion of the total construction cost. In the case of road widening work, it is possible to use the existing road 1 as a scaffold for the heavy equipment 21 over the entire work route,
In this case, the existing line 1 is removed from the common use for a long period during the work period, and is not a practical solution.
【0007】本発明は上記の事情に鑑みてなされたもの
であり、作業用重機のための仮設足場を建て込むことな
く新たな路線を連続して構築していくことを可能とし、
それにより、工期の短縮と工事に要するコストを大幅に
低減することを可能とする軽量盛土工法を利用した新規
な路線構築方法を提供することを目的とする。The present invention has been made in view of the above circumstances, and enables a new route to be continuously constructed without building a temporary scaffold for a heavy working machine.
Accordingly, it is an object of the present invention to provide a new route construction method using a lightweight embankment method capable of shortening the construction period and significantly reducing the cost required for construction.
【0008】[0008]
【課題を解決するための手段】上記の課題を解決するた
めの本発明による軽量盛土工法を利用した新たな路線の
構築方法は、新たな路線を構築するに際し、既存地山ま
たは既存構築物を少なくとも最初の基地としてそこに重
機を配置し、該重機を利用して少なくとも新規路線用の
軽量盛土材の積み上げとその上への適宜の荷重分散処理
までの工事を行って最初の基地に連続する新たな前進基
地を構築し、その後、新たに構築した前進基地に重機を
移動させて再度同様な工事を行い、そこに連続する新た
な前進基地を構築していくことを所要の路線長にわたり
繰り返し行うことを特徴とする。According to the present invention, there is provided a method for constructing a new route using a lightweight embankment method for solving the above-mentioned problems. A heavy equipment is placed there as the first base, and the heavy equipment is used to at least stack the lightweight embankment material for the new route and to perform an appropriate load dispersing process thereon, and to continue the new base to the first base. A new forward base, then move heavy equipment to the newly built forward base, perform the same work again, and build a continuous new forward base there repeatedly over the required line length. It is characterized by the following.
【0009】本発明において、最初の基地として利用す
る既存地山または既存構築物としては、好ましくは、構
築しようとする新たな路線に近接する安定地盤を利用す
る。その場合に、重機一台分のスペースが確保できれば
よく、確保は容易である。スペースが確保できない場合
には、既存の道路などを一時的に利用する。その場合
に、既存道路のその部分は共用できなくなるが、次の新
たな基地を作るまでの短い期間の共用停止であり、大き
な問題とはならない。In the present invention, as the existing ground or existing building used as the first base, a stable ground close to a new line to be built is preferably used. In this case, it is only necessary to secure a space for one heavy machine, and it is easy to secure the space. If space is not available, temporarily use existing roads. In that case, that part of the existing road cannot be shared, but the sharing will be stopped for a short period of time until the next new base is created, and this will not be a major problem.
【0010】既存の基地を利用し、通常の軽量盛土工法
による新たな路線の構築手順に準じて、重機による支持
地盤の整備やH形鋼の建て込みなどの土木工事を行う。
その範囲は、使用するクレーン車などのブーム長の範囲
である。その後、建て込んだH形鋼と支持地盤との間に
EPSブロックのような軽量盛土材を所定の高さに積み
上げて盛土部を形成する。EPSブロックのような発泡
樹脂製の軽量盛土材は自立性を備えており、土砂による
盛土と比較して作業前進方向の積み上げ面の角度を急な
角度とすることができる。実際に、ほぼ垂直端面状態に
積み上げることが可能である。したがって、軽量盛土工
法による路線の構築工法においては、重機のブーム長い
っぱいの長さ分の路線距離を有効作業領域とすることが
できる利点がある。Using existing bases, civil works such as maintenance of supporting ground by heavy equipment and embedding of H-shaped steel are carried out in accordance with a procedure for constructing a new line by a normal lightweight embankment method.
The range is the range of the boom length of the used crane truck or the like. After that, a lightweight embankment material such as an EPS block is stacked at a predetermined height between the laid H-shaped steel and the support ground to form an embankment portion. A lightweight embankment made of a foamed resin, such as an EPS block, is self-supporting, and the angle of the stacking surface in the work advance direction can be made steeper than that of embankment made of earth and sand. In fact, it is possible to stack up to a substantially vertical end state. Therefore, in the construction method of the route by the lightweight embankment method, there is an advantage that the route distance corresponding to the full length of the boom of the heavy equipment can be used as the effective work area.
【0011】軽量盛土材の積み上げ後、その上へ適宜の
荷重分散処理工事を行う。荷重分散処理工事は、積み上
げた軽量盛土材の上に作業用の重機が乗っても、その荷
重により軽量盛土材に変形や破壊が生じないようにする
ためのものであり、仮設の鉄板を一時的に敷き詰める作
業でもよく、通常の軽量盛土工法で必須の工程であるコ
ンクリート床版の形成処理、さらには、その上への路盤
の形成処理などであってもよい。実際に行う新たな路線
の構築現場における作業環境や作業効率などを考慮して
適宜の荷重分散処理工事を選択して行えばよい。After stacking the lightweight embankment material, an appropriate load dispersing process is performed thereon. The load dispersing work is intended to prevent the deformation and destruction of the lightweight embankment due to the load, even if heavy work equipment is loaded on the piled lightweight embankment. It may be a work of laying down concretely, a forming process of a concrete floor slab, which is an essential step in a normal lightweight embankment method, and a forming process of a roadbed thereon. What is necessary is just to select and perform an appropriate load distribution processing work in consideration of the work environment, work efficiency, and the like at the construction site of a new route to be actually performed.
【0012】荷重分散処理を施すことにより、その領域
は最初の基地に連続しかつ重機が乗っても安全な新たな
前進基地となる。そこで、新たな前進基地の構築に使用
した重機および必要なその他の関連資材を、最初の基地
から新たな前進基地へ移動する。移動後に、そこを新た
に基地として、重機による前回と同様な作業を行う。そ
れにより、第1の新たな前進基地に連続する第2の新た
な前進基地が構築される。以下、同様な作業を所要の路
線長にわたり繰り返し行う。By performing the load distribution process, the area becomes a new forward base which is continuous with the first base and which is safe even when heavy equipment is loaded. Thus, the heavy equipment and other necessary materials used to construct the new forward base are moved from the first base to the new forward base. After moving, make the new base there and carry out the same work as the previous time using heavy equipment. Thereby, a second new forward base that is continuous with the first new forward base is established. Hereinafter, the same operation is repeated over a required route length.
【0013】上記のように、本発明による軽量盛土工法
を利用した新たな路線の構築方法によれば、重機用に特
別の仮設足場を構築することなく、また、既存の道路を
閉鎖することもなく、閉鎖するとしてもごく短い期間で
もって、新たな路線を連続して構築していくことを可能
となり、工期の短縮および工事に要するコストを大幅に
低減することが可能となる。[0013] As described above, according to the new route construction method using the lightweight embankment method according to the present invention, it is possible to close an existing road without constructing a special temporary scaffold for heavy equipment. In addition, even if it is closed, it is possible to continuously build a new route in a very short period of time, and it is possible to shorten the construction period and greatly reduce the cost required for the construction.
【0014】さらに、従来の軽量盛土工法では、軽量盛
土材を積み上げて所定の高さの盛土部を形成した後、積
み上げた軽量盛土材の全面に所定厚さにコンクリートを
打設してコンクリート床版を形成し、その後、コンクリ
ート床版の谷側に地覆コンクリートが作られ、さらに、
通常の土木工事のように路盤やアスファルトなどの仕上
げのための工事が施される。その際に、路盤やアスファ
ルトなどの仕上げ工事により生じる荷重の作用により、
軽量盛土材の馴染みによる沈下が起こり、そのためら
に、完成後に地覆コンクリートあるいはアスファルトの
増し打ちを行う必要がある。しかしながら、上記本発明
による工法を採用する場合には、施工の過程で、盛土部
は路盤の荷重あるいは重機による繰り返し荷重を受ける
ことから、その過程で各軽量盛土材がよく馴染むように
なり、沈下が十分に進行する。そのために、完成後に地
覆コンクリートあるいはアスファルトの増し打ちを行う
必要がなくなるという効果ももたらされる。Further, in the conventional lightweight embankment method, a lightweight embankment material is piled up to form an embankment portion having a predetermined height, and then concrete is poured into a predetermined thickness on the entire surface of the piled lightweight embankment material to form a concrete floor. The slab is formed, and then the lining concrete is made on the valley side of the concrete slab.
The work for finishing roadbed and asphalt etc. is done like usual civil engineering work. At that time, due to the effect of the load generated by finishing work such as roadbed and asphalt,
Settlement occurs due to the familiarity of the lightweight embankment material, and for that reason it is necessary to reinforce the ground covering concrete or asphalt after completion. However, when the construction method according to the present invention is adopted, in the process of construction, the embankment portion receives a load of a roadbed or a repeated load by a heavy machine, so that each lightweight embankment material becomes familiar with the process and sinks. Progresses well. For this reason, there is also an effect that it is not necessary to perform additional beating of ground covering concrete or asphalt after completion.
【0015】[0015]
【発明の実施の形態】以下、図面を参照しながら本発明
の一実施の形態を説明する。図1は、本発明にかかる軽
量盛土工法を利用した新たな路線の構築方法を、既存の
路線の拡幅工事に採用している場合の一実施の形態を説
明する平面図であり、図2はその一部を示す側面図、図
3は路線延長方向から見た正面図である。図示のよう
に、山Aの斜面の一部を水平に削るようにして既存の道
路1が設けられており、本発明による構築方法により、
その道路1を谷側に拡幅する工事を行っている。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings. FIG. 1 is a plan view illustrating an embodiment in which a new route construction method using the lightweight embankment method according to the present invention is applied to widening work of an existing route, and FIG. FIG. 3 is a front view as seen from the direction in which the route extends. As shown in the figure, the existing road 1 is provided so as to cut a part of the slope of the mountain A horizontally, and by the construction method according to the present invention,
Work is underway to widen the road 1 to the valley side.
【0016】図1に示すように、最初に、拡幅しようと
する既存道路1の始発点近傍の既存地山を削り、最初の
発進基地10を作り出す。この作業は、既存道路1を一
時的に閉鎖してそこに重機を持ち込むことにより、容易
にかつ短期間で終えることができる。もちろん、他に適
切な安定地盤がある場合には、そこを利用すればよい。
また、最初の発進基地10は始発点に限ることなく、拡
幅工事を行う工事区間の任意の場所であってよい。As shown in FIG. 1, first, the existing ground near the starting point of the existing road 1 to be widened is cut off to create the first starting base 10. This operation can be completed easily and in a short time by temporarily closing the existing road 1 and bringing heavy equipment there. Of course, if there is another suitable stable ground, it may be used.
Further, the first starting base 10 is not limited to the starting point, and may be any place in the construction section where the widening work is performed.
【0017】作り上げた最初の発進基地10に作業用の
重機21を持ち込み、該重機21により谷側斜面の支持
地盤3を整備しながら、所定位置に所要本数のH型鋼2
を建て込む。この例では、図2に示すように、用いる作
業用重機との関係で2a〜2fの6本のH形鋼が第1ユ
ニットとして建て込んでいる。建て込んだH形鋼2a〜
2fと支持地盤3の傾斜面との間に、所定高さまで第1
ユニットのEPSブロック4Aを積み上げて、上面を平
坦面とする。前記したように、EPSブロックは自立性
を備えており、作業前進方向の積み上げ面を最前線のH
形鋼2fの位置に合わせてほぼ垂直面とすることがで
き、重機21のブーム22の全長さを有効作業領域とす
ることがでる。なお、図2の場合では、EPSブロック
4を垂直面ではなく階段状に積み上げているが、これ
は、次のユニットのEPSブロック4Bとの繋ぎ目に縁
切りを生じさせないためである。A heavy machine 21 for work is brought into the first starting base 10 that has been built, and while the support ground 3 on the valley slope is being maintained by the heavy machine 21, the required number of H-beams 2
Build. In this example, as shown in FIG. 2, six H-section steels 2a to 2f are built in as a first unit in relation to a heavy working machine to be used. H-shaped steel 2a built
2f and the inclined surface of the support ground 3, the first
The EPS blocks 4A of the units are stacked to make the upper surface flat. As described above, the EPS block is self-supporting, and the stacking surface in the work advance direction is set to the frontmost H
A substantially vertical surface can be formed in accordance with the position of the section steel 2f, and the entire length of the boom 22 of the heavy equipment 21 can be set as an effective working area. In the case of FIG. 2, the EPS blocks 4 are stacked not in a vertical plane but in a stepwise manner. This is because no border is formed at the joint with the EPS block 4B of the next unit.
【0018】EPSブロック4Aの積み上げの途中で、
必要な場合には、中間コンクリート床版31の形成や中
間コンクリート床版31を既存地山に固定するためのア
ンカー32の埋設固定などの作業も行う(図3参照)。
所定高さまでEPSブロック4Aを積み上げた後、その
上面全面にコンクリートを打設してコンクリート床版5
を形成する。中間コンクリート床版31の場合と同様
に、支持地盤3にアンカー6を埋設固定する作業も平行
して行い、アンカー6の先端をコンクリート床版5に一
体形成したアンカーヘッド5aに固定する。それによ
り、コンクリート床版5およびEPSブロック4Aが支
持地盤3に対して一体に固定され、剥離などが生じるこ
とはない。さらに、コンクリート床版5の上に路盤9を
作る。なお、コンクリート床版5および路盤9は、従来
の軽量盛土工法を利用して路線を構築する場合と同じ機
能を持つものとして作られるが、この実施の形態におい
て、コンクリート床版5と路盤9は、さらに、重機21
の荷重を分散して、積み上げたEPSブロック4Aを変
形や破壊から守るための、荷重分散機能をも持つように
される。During the stacking of the EPS block 4A,
If necessary, operations such as formation of the intermediate concrete slab 31 and burying and fixing of the anchor 32 for fixing the intermediate concrete slab 31 to the existing ground are also performed (see FIG. 3).
After stacking the EPS blocks 4A up to a predetermined height, concrete is poured over the entire upper surface thereof to form a concrete floor slab 5.
To form Similar to the case of the intermediate concrete slab 31, the work of burying and fixing the anchor 6 to the support ground 3 is also performed in parallel, and the tip of the anchor 6 is fixed to the anchor head 5a integrally formed with the concrete slab 5. Thereby, the concrete floor slab 5 and the EPS block 4A are integrally fixed to the support ground 3, and peeling or the like does not occur. Further, a roadbed 9 is formed on the concrete slab 5. The concrete slab 5 and the subgrade 9 are made to have the same functions as those in the case of constructing a route using the conventional lightweight embankment method. In this embodiment, the concrete slab 5 and the subgrade 9 are , And heavy equipment 21
Is distributed to protect the stacked EPS blocks 4A from deformation and destruction.
【0019】第1ユニットでのコンクリート床版5およ
び路盤9の形成作業を終えた後に、発信基地10にある
重機21を新たに形成した前進基地である第1ユニット
領域の路盤9上に移動させる。そこで、該重機21によ
り、第1ユニットにおけると同様に、谷側斜面の支持地
盤3の整備、6本のH型鋼2a〜2fの建て込み、第2
ユニット分のEPSブロック4Bを積み上げなど、所要
の作業を行い、第1ユニット領域に続く第2のユニット
領域を完成させる。完成後、第1ユニット領域にある重
機21を新たに形成した前進基地である第2ユニット領
域の路盤9上に移動させ、移動してきた重機21を利用
して、第2ユニット領域に連続する第3ユニット領域形
成のために同様な作業を行う(図2はその作業状態を示
している)。以下、同じ作業手順を所要の路線長にわた
り繰り返し行うことにより、全拡幅路線長における路盤
形成までの作業は終了する。その後、あるいは、各ユニ
ット領域での作業と平行して、アスファルト舗装などの
追加的仕上げ工事を行うことにより、道路の拡幅作業は
終了する。After the work of forming the concrete floor slab 5 and the subbase 9 in the first unit is completed, the heavy equipment 21 at the transmitting base 10 is moved onto the subbase 9 in the first unit area, which is a newly formed forward base. . Therefore, as in the first unit, maintenance of the support ground 3 on the valley side slope, installation of the six H-section steels 2a to 2f,
A required operation such as stacking the EPS blocks 4B for units is performed to complete the second unit area following the first unit area. After completion, the heavy equipment 21 in the first unit area is moved to the newly formed forward base on the roadbed 9 in the second unit area, and the heavy equipment 21 that has moved is used to continue the second heavy equipment 21 in the second unit area. A similar operation is performed to form a three-unit area (FIG. 2 shows the operation state). Hereinafter, by repeating the same operation procedure over the required route length, the operation up to the formation of the roadbed in the entire widened route length is completed. Thereafter or in parallel with the work in each unit area, additional finishing works such as asphalt pavement are performed, thereby completing the road widening work.
【0020】なお、上記のようなEPS工法では、前記
のように、1m3のEPSブロック4を積み上げて所定
の高さの盛土部を形成し、その後、積み上げたEPSブ
ロック4の全面に所定厚さにコンクリートを打設して、
コンクリート床版5を形成する。その後、コンクリート
床版5の谷側に地覆コンクリート8が作られ、通常の土
木工事のように路盤9やアスファルト10などの仕上げ
のための工事が施されるため、舗装荷重により各ブロッ
クの馴染みによる沈下が起こり、そのため、完成後に地
覆コンクリート8あるいはアスファルト10の増し打ち
を行う必要があった。しかし、上記本発明による工法を
採用する場合には、施工時に、盛土部は路盤9の荷重あ
るいは重機21による繰り返し荷重を受けることから、
その過程で各ブロックがよく馴染み沈下が十分に進行す
る。そのために、完成後に地覆コンクリート8あるいは
アスファルト10の増し打ちを行う必要がなくなるとい
う効果ももたらされる。In the above-described EPS method, as described above, the EPS blocks 4 each having a thickness of 1 m 3 are stacked to form an embankment portion having a predetermined height, and thereafter, a predetermined thickness is formed on the entire surface of the stacked EPS blocks 4. Then put concrete in it,
The concrete slab 5 is formed. Then, ground covering concrete 8 is made on the valley side of the concrete floor slab 5, and the work for finishing the subbase 9 and asphalt 10 is performed as in the case of ordinary civil engineering work. , And it was necessary to re-strike the ground covering concrete 8 or asphalt 10 after completion. However, when the construction method according to the present invention is adopted, the embankment portion receives the load of the roadbed 9 or the repeated load of the heavy equipment 21 at the time of construction,
In the process, each block becomes familiar and subsidence proceeds sufficiently. For this reason, there is also an effect that it is not necessary to additionally beat the ground covering concrete 8 or the asphalt 10 after completion.
【0021】また、上記の実施の形態では、谷側にH形
鋼2を建て込んだ状態で拡幅工事を行うようにしている
が、発泡樹脂製ブロック(例えばEPSブロック)は相
互間およびコンクリート床版との間で所要の摩擦抵抗を
有していることは前記のとおりであり、十分に自立性が
あるので、H形鋼を建て込むことなく発泡樹脂ブロック
の積み上げ施工を行うことも可能である。なお、その際
には、耐候性を出すために、発泡樹脂ブロックの側面に
モルタルなどの吹き付けが行われる。In the above-described embodiment, the widening work is performed with the H-section steel 2 erected on the valley side. However, foam resin blocks (for example, EPS blocks) are provided between the concrete floors. As described above, it has the required frictional resistance with the plate, and since it is sufficiently self-supporting, it is also possible to carry out the stacking of the foamed resin block without embedding an H-section steel. is there. In this case, mortar or the like is sprayed on the side surface of the foamed resin block in order to obtain weather resistance.
【0022】[0022]
【発明の効果】上記のように、本発明による軽量盛土工
法を利用した新たな路線の構築方法では、作業用重機の
ための仮設足場を別途構築することなく、本工事の途中
状態にある施工現場を重機の足場として利用しながら、
作業を路線方向に前進させていくようにしたので、工期
を大幅に短縮することができ、また、完成後に地覆コン
クリートあるいはアスファルトの増し打ちを行う作業も
省略可能である。それらにより、施工に要する費用を大
幅に低減することができる。As described above, in the new route construction method using the lightweight embankment method according to the present invention, the construction work in the middle of the main construction work without separately constructing a temporary scaffold for the heavy equipment for work. While using the site as a scaffold for heavy machinery,
Since the work is advanced in the direction of the route, the construction period can be greatly reduced, and the work of additionally adding ground lining concrete or asphalt after completion can be omitted. Thus, the cost required for construction can be significantly reduced.
【図1】本発明にかかる軽量盛土工法を利用した新たな
路線の構築方法を、既存の路線の拡幅工事に採用してい
る場合の一実施の形態を説明する平面図。FIG. 1 is a plan view illustrating an embodiment in which a new route construction method using the lightweight embankment method according to the present invention is adopted for widening work of an existing route.
【図2】図1の示す拡幅工事現場の一部を示す側面図。FIG. 2 is a side view showing a part of the widening construction site shown in FIG.
【図3】図1の示す拡幅工事現場の路線延長方向から見
た正面図。FIG. 3 is a front view of the widening construction site shown in FIG. 1 as viewed from a line extending direction.
【図4】従来の軽量盛土工法による拡幅工事現場を路線
延長方向から見た正面図。FIG. 4 is a front view of a widening construction site using a conventional lightweight embankment method as viewed from a line extending direction.
2…H形鋼、3…支持地盤、4…軽量盛土材としての樹
脂発泡体、5コンクリート床版、6…アンカー、9…荷
重分散処理工事の例としての路盤、10…最初の基地、
21…作業用重機、22…ブーム2 ... H-section steel, 3 ... Support ground, 4 ... Resin foam as lightweight embankment material, 5 concrete floor slab, 6 ... Anchor, 9 ... Rodbed as an example of load distribution processing work, 10 ... First base,
21: heavy equipment for work, 22: boom
Claims (5)
築するに際し、既存地山または既存構築物を少なくとも
最初の基地としてそこに重機を配置し、該重機を利用し
て少なくとも新規路線用の軽量盛土材の積み上げとその
上への適宜の荷重分散処理までの工事を行って、最初の
基地に連続する新たな前進基地を構築し、その後、新た
に構築した前進基地に重機を移動させて再度同様な工事
を行いそこに連続する新たな前進基地を構築していくこ
とを、所要の路線長にわたり繰り返し行う作業手順を少
なくとも含むことを特徴とする軽量盛土工法を利用した
新たな路線の構築方法。When constructing a new route using a lightweight embankment method, an existing ground or an existing building is placed at least as a first base, and heavy equipment is arranged there, and at least a new route is constructed using the heavy equipment. Construction of the lightweight embankment material and the appropriate load distribution process on it are carried out, constructing a new forward base connected to the first base, and then moving heavy equipment to the newly constructed forward base The construction of a new line using the lightweight embankment method, characterized by at least including the work procedure of repeating the same work and building a new continuous base there over the required line length Method.
幅工事であることを特徴とする請求項1記載の軽量盛土
工法を利用した新たな路線の構築方法。2. The method for constructing a new route using the lightweight embankment method according to claim 1, wherein the construction of the new route is a widening work of an existing route.
散処理が、少なくともコンクリート床版の形成処理を含
むことを特徴とする請求項1または2記載の軽量盛土工
法を利用した新たな路線の構築方法。3. A new route using a lightweight embankment method according to claim 1 or 2, wherein the load distribution processing applied to the piled lightweight embankment material includes at least a concrete floor slab formation processing. How to build.
散処理が、仮設鉄板を敷設する処理であることを特徴と
する請求項1または2記載の軽量盛土工法を利用した新
たな路線の構築方法。4. The construction of a new route using the lightweight embankment method according to claim 1 or 2, wherein the load distribution processing applied to the piled lightweight embankment material is a process of laying a temporary iron plate. Method.
くは、発泡ポリスチレンブロックであることを特徴とす
る請求項1ないし4いずれか記載の軽量盛土工法を利用
した新たな路線の構築方法。5. The method for constructing a new route using the lightweight embankment method according to claim 1, wherein the lightweight embankment material is a foamed resin block, preferably a foamed polystyrene block.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001093703A JP2002294710A (en) | 2001-03-28 | 2001-03-28 | Construction method for new route utilizing lightweight earth filling method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001093703A JP2002294710A (en) | 2001-03-28 | 2001-03-28 | Construction method for new route utilizing lightweight earth filling method |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2002294710A true JP2002294710A (en) | 2002-10-09 |
Family
ID=18948006
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001093703A Pending JP2002294710A (en) | 2001-03-28 | 2001-03-28 | Construction method for new route utilizing lightweight earth filling method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2002294710A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014237980A (en) * | 2013-06-10 | 2014-12-18 | 旭化成ジオテック株式会社 | Method for laying road on slope face |
CN112144542A (en) * | 2020-10-14 | 2020-12-29 | 中建八局广西建设有限公司 | Backfill system for use above built underground structure and construction method thereof |
CN113481771A (en) * | 2021-08-05 | 2021-10-08 | 常熟市第二市政路桥建设工程有限公司 | Permanent-temporary combined construction structure for municipal road and construction method thereof |
-
2001
- 2001-03-28 JP JP2001093703A patent/JP2002294710A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014237980A (en) * | 2013-06-10 | 2014-12-18 | 旭化成ジオテック株式会社 | Method for laying road on slope face |
CN112144542A (en) * | 2020-10-14 | 2020-12-29 | 中建八局广西建设有限公司 | Backfill system for use above built underground structure and construction method thereof |
CN113481771A (en) * | 2021-08-05 | 2021-10-08 | 常熟市第二市政路桥建设工程有限公司 | Permanent-temporary combined construction structure for municipal road and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101363878B1 (en) | Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method | |
KR20160131410A (en) | Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method | |
CN108301273A (en) | The fore-telling shaped pile anchor structure and its construction method of guardrail reinforcing integrated with roadbed | |
CN111305027A (en) | Rapid repairing construction method and repairing structure for subsidence of karst area pavement | |
CN112832079A (en) | Construction method of foamed light soil spliced wide-height highway embankment | |
KR101011805B1 (en) | Method of constructing underground structure crossing pile bases in a pile-based ground and underground structure constructed using the same | |
KR101761477B1 (en) | Construction method of jointless bridge with reinforced earth retaining wall and spread bearing block | |
JP2002294710A (en) | Construction method for new route utilizing lightweight earth filling method | |
KR20030097084A (en) | Construction Method of Reinforced Earth Retaining-Wall for using Anchoring | |
CN114562129A (en) | Trinity reinforcing method for basement roof on crawler crane | |
CN112900181B (en) | Construction method for widening thin layer of asphalt pavement | |
JP2000212979A (en) | Underground structure having arch roof and construction method therefor | |
KR100615149B1 (en) | A method of construction top-down for the ground fabric construction | |
JP3881916B2 (en) | Method for reducing settlement of soft ground | |
JP5073960B2 (en) | Construction method of underground structure and underground structure | |
Lee et al. | Nonshored formwork system for top-down construction | |
Paek et al. | Innovative building construction technique: Modified up/down method | |
JP2813807B2 (en) | How to build an underground tunnel | |
JP2000345502A (en) | Boundary jointing structure for road with enlarged width and method for jointing boundary | |
JPH07243269A (en) | Method of building underground parking lot | |
JP3343598B2 (en) | Hanging wall type retaining wall method for lightweight embankment method | |
JP2003301454A (en) | Earth retaining wall and construction method for underground structure | |
JPH10205277A (en) | Tunnel constructing method | |
JPH1150407A (en) | Road and construction method thereof | |
JP2001164559A (en) | Construction method of continuous underground wall guide wall making use of l-type precast member |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050818 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050823 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20051021 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20051129 |