KR101363878B1 - Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method - Google Patents

Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method Download PDF

Info

Publication number
KR101363878B1
KR101363878B1 KR1020130079702A KR20130079702A KR101363878B1 KR 101363878 B1 KR101363878 B1 KR 101363878B1 KR 1020130079702 A KR1020130079702 A KR 1020130079702A KR 20130079702 A KR20130079702 A KR 20130079702A KR 101363878 B1 KR101363878 B1 KR 101363878B1
Authority
KR
South Korea
Prior art keywords
wall
cip
construction process
construction
upper slab
Prior art date
Application number
KR1020130079702A
Other languages
Korean (ko)
Inventor
정동면
정인혁
Original Assignee
(주)나우기술
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)나우기술 filed Critical (주)나우기술
Priority to KR1020130079702A priority Critical patent/KR101363878B1/en
Application granted granted Critical
Publication of KR101363878B1 publication Critical patent/KR101363878B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0006Plastics
    • E02D2300/0007PVC
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0034Steel; Iron in wire form

Abstract

The present invention relates to an underpass constructing method using a method for combined wall of a temporary structure and a main structure, capable of minimizing the congestion of road due to the limitation of vehicle traffic on a junction and a road; maintaining the smooth traffic flow by restoring road traffic in the shortest time; significantly shortening construction time period by simplifying a construction procedure; and efficiently reducing the entire construction costs of the installation and construction. In order to construct an underpass, a braced temporary member is constructed to be in contact with the coating part of a main structure wall, and an upper slab is pre-constructed and is excavated. A lower slab, a central wall, and a column are reinforced or constructed, and then an inner wall is constructed. When a long underground road or an underpass is constructed in a downtown, the underpass constructing method can widen a distance on a private land, can prevent construction materials from piling up on the road, and can minimize the width of the occupied road. [Reference numerals] (S10) Construction process for a CIP bulb forming both side walls, a central wall, or a column; (S20) One side upper slab construction process; (S30) Other side upper slab construction process; (S40) Central side upper slab construction process; (S50) Corner part reinforcing and earth anchor construction process; (S60) Both sides lower slab and the central wall or the column construction process; (S70) Both sides inner wall construction process; (S80) Finishing process

Description

가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법{Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method}Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method}

본 발명은 건설분야에 관한 것으로 특히 지하차도를 형성하기 위하여 흙막이 가설재를 본 구조벽체의 피복부분에 접하여 시공한 후 상부슬래브를 선시공하고 그 내부를 굴착하여 하부슬래브와 중앙부 벽체 및 기둥을 보강 또는 시공을 하고 이어 벽체를 시공하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법에 관한 것이다.
The present invention relates to the field of construction, in particular, in order to form a subterranean roadway, after the construction of the cladding material in contact with the covering portion of the structural wall, the upper slab is pre-installed and excavated inside to reinforce or construct the lower slab and the central wall and columns Then, the present invention relates to a method of constructing an underground road using a temporary wall construction method of a temporary structure and a main structure.

지하차도는 교차로 등 통행량이 매우 많은 장소의 어느 방향 지하에 마련되거나, 지형적 조건이 지상 운행에 적합하지 않는 장소에 원할한 통행을 위해 설치되는 구조물을 의미한다.Underground roadway means a structure that is provided in the basement in either direction of a place with a lot of traffic, such as an intersection, or is installed for smooth traffic in a place where the topographical conditions are not suitable for ground operation.

최근에는 과거에 고가차도로 이용되던 도로를 철거하고 지하도로를 건설하려는 경향이 있는데, 이는 고가차도가 도시미관을 해치며 소음과 공해로 인하여 도시민에 민원의 대상이 되고 있기 때문이다. Recently, there has been a tendency to demolish roads used in elevated roads and build underground roads, because elevated roads are hurting the city's aesthetics and are subject to civil complaints due to noise and pollution.

이러한 지하차도를 설치하는데 있어서 종래의 공법에서는 H형강의 가설재와 주형보 및 복공판을 이용하는 통상적인 방법에 의하여 지하차도를 건설하여 왔다.In the installation of the underground roadway, the conventional roadway has been constructed by a conventional method using a temporary material of H-beams, a mold beam and a perforated plate.

이러한 지하차도를 시공하는 종래의 통상적인 공법에 의하면, 지하굴착 및 시공과정에서 도로에 자재를 적치하는 등으로 주변의 교통 흐름을 방해하게 되고, 굴착시 탈수나 지반이완으로 인한 주변건물의 변위가 유발되고, 소음과 비산먼지를 유발시키는 가시설 및 복공에 의한 시공방법 때문에 각종 민원이 발생 될 뿐만 아니라, 공사기간도 길어지게 되는 문제점이 항상 노출되어 왔었다.According to the conventional method for constructing such underground roadways, the traffic flows are disturbed due to the accumulation of materials on the road during the underground excavation and construction, and the displacement of the surrounding buildings due to dehydration or ground relaxation during excavation In addition to the various civil complaints caused by the construction method by the temporary facility and the rehabilitation caused by noise and scattering dust, the construction period has also been exposed to a long time.

한편, 상기한 종래의 통상적인 공법외에 선행기술로서 TUS공법(특허등록 제 10-1187369 호)이 있는데 중앙부 벽체 또는 기둥의 CIP구근의 길이가 지표에 까지 닿아있어 방수 시공의 문제점과 내부 버팀보의 설치상 애로점, 그리고 토사층에서만 시공이 가능한 점, CIP구근이 상호 중첩되지 않고 별개의 개체로 되어 있어 차수의 기능을 할 수 없다는 점, 길이가 긴 지하차도의 경우 내부굴착 및 콘크리트 타설을 위한 시설이 없다는 점등의 몇가지 문제점을 갖고 있다.
On the other hand, there is a TUS method (Patent Registration No. 10-1187369) as a prior art in addition to the conventional conventional method described above, the length of the CIP bulb of the central wall or column reaches to the surface, the problem of waterproof construction and the installation of the internal support It can only be constructed in the point of trouble, and the soil layer, CIP bulbs cannot be overlapped with each other and can not function as the order. In the case of long underground roads, there is no facility for internal excavation and concrete casting. There are some problems with lighting.

국내등록특허 제 10-1187369 호Domestic Patent No. 10-1187369

따라서 본 발명은 이러한 문제점 등을 극복하기 위한 것으로, 교차로에서 차량 통행의 제한을 최소화 하면서도 지하차도 공사기간을 단축시키며 공사비를 절감시킬 뿐 아니라 길이가 긴 지하차도의 경우에도 굴착을 위한 장비 반입반출 및 재료를 투입하는 시설을 갖추고 있는 합벽식의 견고한 지하구조물이 구현되도록 하는 데 그 목적이 있다.
Therefore, the present invention is to overcome these problems, such as minimizing the restriction of vehicle traffic at the intersection, shortening the construction period of underground roads and reducing construction costs, as well as carrying in and out equipment for excavation in the case of long underground roads and The objective is to ensure that solid, sturdy underground structures with material inputs are implemented.

상기한 목적을 달성하기 위한 본 발명은, According to an aspect of the present invention,

양 측벽 및 중앙부 벽체 또는 기둥을 이루는, CIP구근 시공공정(S10)과, CIP bulb construction process (S10) forming both side walls and the central wall or column,

상기 CIP구근 시공공정에 의해 형성되어 구분되는 차로의 어느 일측 상부를 터파기 한 후 상부슬래브를 시공하는, 일측 상부슬래브 시공공정(S20)과,One side upper slab construction process (S20), which constructs an upper slab after digging any upper portion of the lane formed and separated by the CIP bulb construction process, and

상기 일측 상부슬래브 시공공정(S20)을 거친 다음, 타측의 차로측에 해당되는 타측 상부를 터파기 한 후 상부슬래브를 시공하는, 타측 상부슬래브 시공공정(S30)과,After passing the one side upper slab construction step (S20), the other side upper slab construction process (S30) and then the upper slab construction after breaking the other upper side corresponding to the other side of the lane,

상기 타측 상부슬래브 시공공정(S30)을 거친 다음, 중앙의 차로측에 해당되는 중앙측 상부를 터파기 한 후 상부슬래브를 시공하는, 중앙측 상부슬래브 시공공정(S40)과,After the other upper slab construction process (S30), the center side upper slab construction process (S40) and the upper slab construction after breaking the upper portion of the center corresponding to the side of the center lane, and

상기 양측 상부슬래브 시공공정(S20, S30)에 의한 양측 상부슬래브 하단측 모서리부분을 내부 굴착하여 코너부 보강을 하고 추가굴착을 하여 양 측벽을 지지하는 어스앙카를 시공하는, 코너부 보강 및 어스앙카 시공공정(S50)과,Corner reinforcement and earth anchor for internally excavating the corners of the lower side of both upper slabs by the both side upper slab construction processes (S20, S30) to reinforce the corners, and to construct earth anchors supporting the side walls by additional excavation. Construction process (S50),

최종 하단부까지 굴착 완료하여 양측 하부슬래브와 함께 중앙부 벽체 또는 기둥의 보강을 시공하는, 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정(S60)과,Both bottom slab and center wall or column reinforcement construction process (S60), and excavation to the final lower end to construct the reinforcement of the central wall or column with both lower slabs,

상기 양측 어스앙카를 철거하고 일부 내벽체를 타설한 후 양생을 거쳐 코너부 보강을 철거한 후 상부슬래브와 연결하는 잔여 내벽체를 시공하는, 양측 내벽체 시공공정(S70)과,Both side inner wall construction process (S70) of dismantling the earth anchors on both sides and placing some inner wall and then reinforcing the corner portion through curing and constructing the remaining inner wall connecting with the upper slab;

내부 벽체 또는 중앙부 벽체 또는 기둥의 내부 타일 시공처리 후 각 하부슬래브 상면으로 아스콘 포장을 하는, 마무리 시공공정(S80)으로 이루어지는 것을 특징으로 한다.
After the interior tile construction process of the inner wall or the central wall or column, characterized in that the finishing construction step (S80), which is ascon pavement to the upper surface of each lower slab.

또한 본 발명은, Further, according to the present invention,

양 측벽 및 중앙부 벽체 또는 기둥을 이루는 CIP구근 시공공정(S10)과, CIP bulb construction process (S10) forming both side walls and the central wall or column,

상기 양 측벽 및 중앙부 벽체 또는 기둥을 이루는 CIP구근 시공공정에 의해 형성되어 구분되는 차로의 어느 일측 상부를 터파기 한 후 PC구조의 상부슬래브를 조립하는, 일측 상부슬래브 시공공정(S20)과, One side upper slab construction process (S20) for assembling the upper slab of the PC structure after the top of one side of the lane formed by the CIP bulb construction process forming the two side walls and the central wall or pillar, and then separated;

상기 PC구조를 갖는 일측 상부슬래브 시공공정(S20)을 거친 다음, 타측의 차로측에 해당되는 타측 상부를 터파기 한 후 PC구조의 상부슬래브를 조립하는 타측 상부슬래브 시공공정(S30)과, After the one side upper slab construction process (S20) having the PC structure, the other side upper slab construction process (S30) for assembling the upper slab of the PC structure after the top of the other side corresponding to the lane side of the other side, and

상기 타측 상부슬래브 시공공정(S30)을 거친 다음, 중앙의 차로측에 해당되는 중앙측 상부를 터파기 한 후 PC구조의 상부슬래브를 조립하는 중앙측 상부슬래브 시공공정(S40)과, After the other upper slab construction process (S30), the center side upper slab construction process (S40) for assembling the upper slab of the PC structure after the top of the central side corresponding to the side of the center lane, and

상기 양측 상부슬래브 시공공정(S20, S30)에 의한 양측 PC구조 상부슬래브 하단측 모서리부분을 내부 굴착하여 코너부 보강을 하고 추가굴착을 하여 양 측벽을 지지하는 어스앙카를 시공하는, 코너부 보강 및 어스앙카 시공공정(S50)과,Corner reinforcement for constructing earth anchors for supporting both sidewalls by reinforcing the corners by internally excavating the lower edges of the upper slab of both PCs by the two upper slab construction processes (S20, S30). Earth anchor construction process (S50) section,

최종 하단부까지 굴착 완료하여 양측 하부슬래브와 함께 중앙부 벽체 또는 기둥의 보강을 시공하는, 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정(S60)과, Both bottom slab and center wall or column reinforcement construction process (S60), and excavation to the final lower end to construct the reinforcement of the central wall or column with both lower slabs,

상기 양측 어스앙카를 철거하고 일부 내벽체를 타설한 후 양생을 거쳐 코너부 보강을 철거한 후 상부슬래브와 연결하는 잔여 내벽체를 시공하는, 양측 내벽체 시공공정(S70)과, Both side inner wall construction process (S70) of dismantling the earth anchors on both sides and placing some inner wall and then reinforcing the corner portion through curing and constructing the remaining inner wall connecting with the upper slab;

내부 벽체 또는 중앙부 벽체 또는 기둥의 내부 타일 시공처리 후 각 하부슬래브 상면으로 아스콘 포장을 하는, 마무리 시공공정(S80)으로 이루어지는 것을 특징으로 한다.
After the interior tile construction process of the inner wall or the central wall or column, characterized in that the finishing construction step (S80), which is ascon pavement to the upper surface of each lower slab.

또한 본 발명은, Further, according to the present invention,

양 측벽은 트렌치 굴착에 의한 단위PC벽체 및 오거 장비굴착에 의한 단위PC 사각파일 투입과 중앙부 벽체 또는 기둥에는 오거 장비굴착에 의한 단위PC 사각파일 투입 및 CIP구근을 시설하는, CIP구근 시공공정(S10)과, CIP bulb construction process, in which both side walls are fitted with unit PC square piles by trench excavation and auger equipment excavation, and unit PC square piles by auger equipment excavation and CIP bulb are installed on central wall or column (S10). )and,

상기 CIP구근 시공공정(S10)에 의해 형성되어 구분되는 차로의 어느 일측 상부를 터파기 한 후 상부슬래브를 조립하는, 일측 상부슬래브 시공공정(S20)과, One side upper slab construction process (S20) and assembling the upper slab after the top of any one side of the lane is formed and divided by the CIP bulb construction process (S10) and,

상기 일측 상부슬래브 시공공정(S20)을 거친 다음, 타측의 차로측에 해당되는 타측 상부를 터파기 한 후 상부슬래브를 시공하는, 타측 상부슬래브 시공공정(S30)과, After passing the one side upper slab construction step (S20), the other side upper slab construction process (S30) and then the upper slab construction after breaking the other upper side corresponding to the other side of the lane,

상기 타측 상부슬래브 시공공정(S30)을 거친 다음, 중앙의 차로측에 해당되는 중앙측 상부를 터파기 한 후 상부슬래브를 시공하는, 중앙측 상부슬래브 시공공정(S30)과,After the other upper slab construction process (S30), the center side upper slab construction process (S30) and then the upper slab construction after the top of the center side corresponding to the side of the middle lane, and

상기 양측 상부슬래브 시공공정(S20, S30)에 의한 양측 상부슬래브 하단측 모서리부분을 내부 굴착하여 코너부 보강을 하고 추가굴착을 하는, 코너부 보강 시공공정(S50-1)과,Corner reinforcement construction step (S50-1), which is to reinforce the corner portion by further excavating the inner corner of the lower edge of both upper slab by the two upper slab construction process (S20, S30), and

최종 하단부까지 굴착 완료하여 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강하는, 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정(S60)과, After the excavation is completed to the bottom end of the lower slab and the central wall or pillar reinforcement, both lower slab and central wall or column reinforcement construction process (S60),

1차 내벽체를 타설한 후 양생을 거쳐 코너부 보강을 철거한 후 상부슬래브와 연결하는 잔여 내벽체를 시공하는, 양측 내벽체 시공공정(S70)과, After pouring the primary inner wall, after reinforcing the corner reinforcement through curing, and constructing the remaining inner wall connecting the upper slab, both inner wall construction process (S70),

내부 벽체 또는 중앙부 벽체 또는 기둥의 내부 타일 시공처리 후 각 하부슬래브 상면으로 아스콘 포장을 하는, 마무리 시공공정(S80)으로 이루어지는 것을 특징으로 한다.
After the interior tile construction process of the inner wall or the central wall or column, characterized in that the finishing construction step (S80), which is ascon pavement to the upper surface of each lower slab.

또한 본 발명은, Further, according to the present invention,

양 측벽은 본체 구조물에 가장 인접하게 엄지말뚝과 중앙부 벽체 또는 기둥 좌우에 중간말뚝 박기를 하는, 말뚝 시공공정(S10-1)과, Both side walls are pile construction process (S10-1), which is the middle piles on the left and right of the thumb pile and the central wall or pillar adjacent to the main body structure;

상기 양 측벽 및 중앙부 벽체 또는 기둥 좌우에 중간말뚝을 시공하는 시공공정에 의해 형성되어 구분되는 중앙측 차로측에 해당되는 중앙측 상부를 터파기 한 후 상부슬래브를 시공하는, 중앙측 상부슬래브 시공공정(S40)과, Center-side upper slab construction process, which is formed by a construction process for constructing intermediate piles on both sides of the sidewalls and central walls or pillars, and then dismantles the upper portion of the central side corresponding to the central side lane side, and then constructs the upper slab. (S40),

상기 중앙측 차로에 의하여 좌우로 구분되는 어느 일측 차로측에 해당되는 상부를 터파기 한 후 상부슬래브를 조립하는, 일측 상부슬래브 시공공정(S20)과, One side upper slab construction process (S20), and assembling the upper slab after the top corresponding to any one side of the lane side divided by left and right by the center side lane,

상기 일측 상부슬래브 시공공정(S20)을 거친 다음, 타측의 차로측에 해당되는 타측 상부를 터파기 한 후 상부슬래브를 시공하는, 타측 상부슬래브 시공공정(S30)과, After passing the one side upper slab construction step (S20), the other side upper slab construction process (S30) and then the upper slab construction after breaking the other upper side corresponding to the other side of the lane,

상기 양측 및 중앙측 상부슬래브 시공공정(S40,S20,S30)에 의한 중앙측 및 양측 상부슬래브 하단측에서 최종굴착선까지 내부굴착하여 어스앙카를 시공하는, 내부굴착 및 어스앙카 시공공정(S50-2)과, Internal excavation and earth anchor construction process by internal excavation from the center side and the lower side of both upper slab bottom by the both side and center side upper slab construction process (S40, S20, S30) to the final excavation line, and the construction of earth anchor (S50- 2) and,

최종 하단부까지 굴착 완료하여 양측 하부슬래브와 함께 중앙부 벽체 또는 기둥을 시공하는, 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정(S60)과, Both bottom slab and center wall or column reinforcement construction process (S60) to complete the excavation to the final lower end and construct the central wall or column with both lower slabs,

상기 중앙측 중간말뚝을 철거함과 아울러 어스앙카를 철거하고 양측 벽체를 1, 2차단위로 시공하는, 양측 내벽체 시공공정(S70)과, Both the inner wall construction process (S70) of dismantling the middle side piling and removing the ground anchors and constructing both walls in primary and secondary units,

상기의 양측 내벽체 시공공정(S70)에 이어 양측의 엄지말뚝을 인발하고, 내부 벽체 또는 중앙부 벽체 또는 기둥의 내부 타일 시공처리 후 각 하부슬래브 상면으로 아스콘 포장을 하는, 마무리 시공공정(S80)으로 이루어지는 것을 특징으로 한다.
Following both side inner wall construction process (S70), the thumb piles on both sides are drawn out, and after finishing the interior tile construction process of the inner wall or the central wall or the pillar, ascon paving to the upper surface of each lower slab, the finishing construction process (S80) Characterized in that made.

또한 본 발명은,Further, according to the present invention,

양 측벽은 트렌치 굴착에 의한 단위PC벽체 및 오거 장비굴착에 의한 단위PC 사각파일 투입과 중앙부 벽체 또는 기둥에는 오거 장비굴착에 의한 단위PC 사각파일 투입하며 CIP구근을 시공하는, CIP구근 시공공정(S10)과,CIP bulb construction process, in which both side walls insert unit PC square pile by trench excavation and auger equipment excavation and unit PC square pile by auger equipment excavation into central wall or column, and construct CIP bulb. )and,

일측 Half PC구조를 이루도록 슬래브 시공하는, 일측 상부슬래브 시공공정(S20)과, One side upper slab construction process (S20), and the slab construction to form one side half PC structure,

타측 Half PC구조를 이루도록 슬래브 시공하는, 타측 상부슬래브 시공공정(S30)과, The other upper slab construction process (S30), and the slab construction to form the other half PC structure,

중앙측 Half PC구조를 이루도록 슬래브 시공하는, 중앙측 상부슬래브 시공공정(S40)과, A center upper slab construction process (S40) for slab construction to form a center side half PC structure,

코너부 보강 시공공정(S50-1)과, Corner reinforcement construction process (S50-1),

양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정(S60)과, Both lower slab and central wall or column reinforcement construction process (S60),

양측 내벽체 시공공정(S70)과, 마무리 시공공정(S80)으로 이루어지는 것을 특징으로 한다.
It is characterized by consisting of both inner wall construction step (S70) and the finish construction step (S80).

또한 본 발명은,Further, according to the present invention,

양 측벽 및 중앙부를 이루는, CIP구근 시공공정(S10)과, CIP bulb construction process (S10) forming both sidewalls and the central portion,

상기 양 측벽 CIP구근 상단의 어느 위치에서 어스앙카를 시공하고 내부굴착을 하는, 내부굴착 및 어스앙카 시공공정(S50-2)과, Internal excavation and earth anchor construction process (S50-2), and the earth excavation at any position of the upper side of the CIP bulb and internal excavation, and

최종 하단부까지 굴착 완료하여 양측 하부슬래브를 시공하는, 양측 하부슬래브 시공공정(S60-1)과, Both bottom slab construction process (S60-1), and excavation is completed to the final lower end portion, and the lower slab construction on both sides,

내벽체를 시공하며 어스앙카를 철거하는, 양측 내벽체 시공공정(S70)과, Both the inner wall construction process (S70), which dismantles the earth anchor while constructing the inner wall,

상기 양측 내벽체에 PSC 빔을 거치하고, 양측 PSC 빔 연단의 내부간을 가로보로 연결하고, PSC 빔 상부슬래브와 배면슬래브를 시공하는, PSC 빔 거치 및 상부슬래브 시공공정(S230)과, PSC beam mounting and upper slab construction process (S230) to mount the PSC beam to the inner wall of both sides, to connect the inner side of the both ends of the PSC beam crosswise, and to construct the PSC beam upper slab and the rear slab;

내부 벽체 타일 시공과 하부슬래브 상면으로 아스콘 포장을 하고, 상부슬래브를 되메우기 하여 아스콘 포장을 하는, 마무리 시공공정(S80)으로 이루어지는 것을 특징으로 한다.
Ascon paving with the inner wall tiles and the upper surface of the lower slab, and ascon packaging by filling the upper slab, characterized in that the finishing construction step (S80).

또한 본 발명은,
U-Type 구조를 갖는 상방이 개방되는 지하도로 시공방법에 있어서,
Further, according to the present invention,
In the construction method of the underground road to the upper side having a U-Type structure,

양 측벽 및 중앙부를 이루는 CIP구근 시공공정(S10)과, CIP bulb construction process (S10) forming both side walls and the central portion,

상기 양측벽 CIP구근 상단의 어느 위치에서 어스앙카를 시공하고 내부굴착을 하는, 내부굴착 및 어스앙카 시공공정(S50-2)과, Internal excavation and earth anchor construction process (S50-2) and the construction of the earth anchor at any position of the upper side of the CIP bulbs on both sides,

최종 하단부까지 굴착 완료하여 양측 하부슬래브를 시공하는, 양측 하부슬래브 시공공정(S60-1)과, Both bottom slab construction process (S60-1), and excavation is completed to the final lower end portion, and the lower slab construction on both sides,

내벽체를 시공하여 어스앙카를 철거하는, 양측 내벽체 시공공정(S70)과, Both inner wall construction process (S70) of constructing an inner wall to remove earth anchor,

내부 벽체 타일 시공과 하부슬래브 상면으로 아스콘 포장을 하는, 마무리 시공공정(S80)으로 이루어지는 것을 특징으로 한다.
Characterized in that it consists of a finishing construction step (S80), the ascon paving to the inner wall tile construction and the lower slab upper surface.

또한 본 발명은, 양 측벽 및 중앙부 벽체 또는 기둥을 이루는 CIP구근 시공공정(S10)과, 일측 상부슬래브 시공공정(S20)과, 타측 상부슬래브 시공공정(S30)과, 중앙측 상부슬래브 시공공정(S40)과, 코너부 보강 및 어스앙카 시공공정(S50), 양측 내벽체 기초 및 중앙부 벽체 또는 기둥의 시공공정(S60-2)과, 양측 내벽체 시공공정(S70)과, 마무리 시공공정(S80)으로 지하차도의 시공이 이루어지는 것을 특징으로 한다.
In addition, the present invention, the CIP bulb construction process (S10), the upper side slab construction process (S20), the other side upper slab construction process (S30), and the central side upper slab construction process that forms both sidewalls and the central wall or column ( S40), corner portion reinforcement and earth anchor construction process (S50), both inner wall foundation and center wall or column construction process (S60-2), both inner wall construction process (S70) and finishing construction process (S80) It is characterized in that the construction of the underground driveway.

본 발명에 의하면, 도시에서의 지하차도 또는 길이가 긴 지하도로를 시공 건설할 때 사유지와 거리를 넓힐 수 있고, 노면에서 공사 자재등이 적치되지 않게 할 수 있으며, 도로의 점유폭을 최소로 할 수 있으므로 교차로 및 일반노면에서의 차량통행 제한 등으로 인한 도로의 혼잡을 최소화 하면서도 노면 교통을 최단 시일 내에 원상복구토록 하여 원활한 교통흐름이 유지될 수 있으며, 시공 간소화와 이에 따른 시공기간을 현저하게 단축시킬 수 있도록 하여, 설치 시공에 따른 전체적 공사비용을 효율적으로 절감시킬 수 있는 효과를 이룰 수 있다.
According to the present invention, when constructing and constructing an underground roadway or a long underground road in a city, the private land and the distance can be widened, construction materials can not be accumulated on the road surface, and the occupation width of the road can be minimized. As a result, road traffic can be restored in the shortest possible time while minimizing congestion of roads due to restrictions on traffic at intersections and general roads, and smooth traffic flow can be maintained, simplifying construction and significantly shortening construction time. By making it possible, the overall construction cost according to the installation can be effectively reduced.

도 1 내지 도 23은 본 발명에 의한 제1실시예를 도시한 도면으로,
도 1은 본 발명에 의한 제1실시예의 공정 흐름을 도시한 도면
도 2는 도 1에서 양 측벽 및 중앙부 벽체 또는 기둥 CIP구근 시공공정을 나타낸 도면
도 3은 본 발명 제1실시예에서의 일측 상부슬래브 시공공정을 도시한 개괄도
도 4는 타측 상부슬래브 시공공정을 도시한 개괄도면
도 5는 중앙측 상부슬래브 시공공정을 도시한 개괄도면
도 6a, b는 하부슬래브 및 중앙 기둥벽 보강 시공을 위한 도면으로, 도 5에 의해 각 상부슬래브가 형성된 후 양측 상부슬래브 코너부를 굴착한 다음, 그 굴착된 공간에 사보강이 설치되어 있으며 최종굴착선 부근으로 어스앙카가 설치되는 하부슬래브 및 중앙 기둥벽 보강 시공을 하고 있는 상태를 도시한 도면
도 7은 도 6a, b에 의해 시공이 완료된 후 내벽체를 시공한 상태를 도시한 도면
도 8은 시공이 완료된 상태를 도시한 표준도면
도 9는 도 8에서의 'A' 부분을 확대 도시한 확대 단면도
도 10은 도 8에서의 'B' 부분을 확대 도시한 단면도
도 11은 상부슬래브의 일단과 벽체의 상단간을 고정 연결하기 위한 것으로, 도 8에서의 'C' 부분을 확대 도시한 단면도
도 12는 도 8에서의 'D' 부분을 확대 도시한 단면도
도 13은 도 8에서의 "D'" 부분을 확대 도시한 단면도
도 14는 도 8에서의 "E" 부분을 확대 도시한 것으로 사보강과 CIP구근과의 연결 상태를 도시한 도면
도 15는 도 8에서의 'A-A'선 단면도
도 16은 도 8에서의 'B-B'선 단면도
도 17은 별도의 흙막이 시설을 도시한 도면
도 18은 토사와 암반의 복합층에서의 CIP구근을 형성하는 방법을 도시한 도면
도 19는 도 18에서의 'C-C'선 단면도와 'D-D'선 단면도
도 20은 TUS공법 구간과 일반공법 구간이 접속되는 위치에서의 측면방수 방법을 도시한 도면
도 21은 상부슬래브 CIP구근이 접하는 부분인 우각부에서의 방수방법을 도시한 도면
도 22는 하부슬래브와 CIP구근이 접하는 부분에서의 방수방법을 도시한 도면
도 23은 장비 및 재료투입구, 토사반출구를 도시한 단면도
도 24 내지 도 38은 본 발명의 제2실시예를 설명하는 도면들로,
도 24는 본 발명의 제2실시예에 의한 공정 흐름을 도시한 도면
도 25는 제2실시예에서의 양 측벽 및 중앙부 벽체 또는 기둥 CIP구근 시공공정을 도시한 도면
도 26은 일측 상부슬래브 시공공정을 도시한 개괄 단면도
도 27은 타측 상부슬래브 시공공정을 도시한 개괄 단면도
도 28은 중앙측 상부슬래브 시공공정을 도시한 개괄 단면도
도 29는 도 28에 의해 각 상부슬래브가 형성된 후 양측 상부슬래브 코너부를 굴착한 후 그 굴착된 공간에 사보강이 설치되어 있으며 최종굴착선 부근으로 어스앙카를 설치하고 하부슬래브와 중앙 기둥벽 보강 시공을 하고 있는 상태를 도시한 도면
도 30은 도 28에 의해 각 상부슬래브가 형성된 후 양측 상부슬래브 코너부를 굴착한 후 그 굴착된 공간에 사보강이 설치되어 있으며 CIP구근 내부 일편측에 PC강연선이 긴장 정착되어 있으며 하부슬래브와 중앙 기둥벽 보강시공을 하고 있는 상태를 도시한 도면
도 31은 도 30에 의해 시공이 완료된 후 내벽체를 시공한 상태를 도시한 도면
도 32는 시공이 완료된 상태를 도시한 표준단면
도 33은 도 32에서의 "A" 부분을 확대 도시한 단면도
도 34는 도 32에서의 "B" 부분을 확대 도시한 단면도
도 35는 상부슬래브의 일단과 벽체의 상단간을 고정 연결하기 위한 것으로 도 32에서의 "C" 부분을 확대 도시한 단면도
도 36은 도 32에서의 "D" 부분을 확대 도시한 단면도
도 37은 도 32에서의 "D' " 부분을 확대 도시한 단면도
도 38은 도 32에서의 "E" 부분을 확대 도시한 단면도
도 39 내지 도 62는 본 발명의 제3실시예에 의한 도면들을 도시한 것으로,
도 39는 본 발명에 의한 제3실시예에서의 공정 흐름을 도시한 도면
도 40은 양 측벽의 PC벽체 및 PC 사각파일벽체 투입과 중앙부 벽체 또는 기둥의 PC 사각파일 투입 및 CIP구근 시공공정을 도시한 도면
도 41은 일측 상부슬래브 시공공정을 도시한 개괄 단면도
도 42는 타측 상부슬래브 시공공정을 도시한 개괄 단면도
도 43은 중앙측 상부슬래브 시공공정을 도시한 개괄 단면도
도 44는 도 43에 의해 각 상부슬래브가 형성된 후 양측 상부슬래브 코너부를 굴착한 후 그 굴착된 공간에 사보강이 설치되어 있으며 최종굴착선까지 굴착되어 하부슬래브가 설치되어 있는 상태를 도시한 도면
도 45는 도 43에 의해 각 상부슬래브가 형성된 후 양측 상부슬래브 하부를 최종굴착선까지 굴착되어 하부슬래브가 설치되어 있는 상태를 도시한 도면
도 46은 도 44에 의해 시공이 완료된 후 내벽체를 시공한 상태를 도시한 도면
도 47은 도 45에 의해 시공이 완료된 상태를 도시한 표준단면
도 48, 도 49는 PC벽체간 연결부와 달아매기벽체를 이용하여 달아매기를 한 확대 단면도
도 50은 도 47에서의 "A" 부분을 확대 도시한 단면도
도 51은 도 47에서의 "B"부분을 확대 도시한 단면도
도 52는 도 47에서의 "C"부분을 확대 도시한 단면도
도 53은 도 47에서의 "D"부분을 확대 도시한 단면도
도 54는 도 47에서의 "D’ "부분을 확대 도시한 단면도
도 55는 시공이 완료된 후 내벽체를 시공한 상태를 도시한 표준단면
도 56은 도 55에서 "A-A" 단면도
도 57은 도 55에서 "B-B" 단면도
도 58은 도 55에서의 "A" 부분을 확대 도시한 단면도
도 59는 도 55에서의 "B"부분을 확대 도시한 단면도
도 60은 도 55에서의 "C"부분을 확대 도시한 단면도
도 61은 도 55에서의 "D"부분을 확대 도시한 단면도
도 62는 도 55에서의 "D’ "부분을 확대 도시한 단면도
도 63 내지 도 77은 본 발명의 제 4 실시예를 설명하기 위한 도면으로,
도 63은 본 발명의 제4실시예에 의한 공정 흐름을 도시한 도면
도 64는 양 측벽부에 엄지말뚝 박기와 중앙부 양측에 중간말뚝 박기를 하는 말뚝막기 시공공정을 도시한 도면
도 65는 중앙측 상부슬래브 시공공정을 도시한 개괄 단면도
도 66은 일측에 상부슬래브 시공공정을 도시한 개괄 단면도
도 67은 타측에 상부슬래브 시공공정을 도시한 개괄 단면도
도 68은 도 65 내지 도 67에 의해 각 상부슬래브가 형성된 후 각 상부슬래브 하부를 굴착한 다음, 그 굴착된 공간에 어스앙카가 설치되어 있으며 최종굴착선까지 굴착하여 하부슬래브와 중앙부를 시공한 상태를 도시한 도면
도 69는 도 68에 의해 시공이 완료된 후 벽체를 시공한 상태를 도시한 도면
도 70은 복토과정에서 되메움 말뚝과 앵커의 상세 도면
도 71은 PC슬래브간 연결부에 있어서 배력철근 이음방법을 확대 도시한 단면도
도 72는 상부슬래브간 연결부에 있어서 주철근 이음방법을 확대 도시한 단면도
도 73은 도 69에서의 "A" 부분을 확대 도시한 단면도
도 74는 도 69에서의 "B" 부분을 확대 도시한 단면도
도 75는 상부슬래브 편측 지지시설을 확대 도시한 단면도
도 76은 콘크리트 PC 1 토류판의 상세 단면도
도 77은 콘크리트 PC 2 토류판의 상세 단면도
도 78 내지 도 95 는 본 발명의 제 5 실시예를 설명하기 위한 도면으로,
도 78은 본 발명의 제5실시예에 의한 공정 흐름을 도시한 도면
도 79는 양 측벽의 PC벽체 및 PC사각파일 벽체 투입과 중앙부 벽체 또는 기둥의 PC사각파일 투입 및 CIP구근 시공공정을 도시한 도면
도 80은 일측 상부슬래브 시공공정(S20)을 도시한 개괄 단면도
도 81은 타측 상부슬래브 시공공정(S30)을 도시한 개괄 단면도
도 82는 중앙측 상부슬래브 시공공정(S40)을 도시한 개괄 단면도
도 83은 도 82에 의해 각 상부슬래브가 형성된 후 양측 상부슬래브 코너부를 굴착한 후 그 굴착된 공간에 사보강이 설치되어 있으며 최종굴착선까지 굴착되어 하부슬래브가 설치되어 있는 상태를 도시한 도면
도 84는 도 82에 의해 각 상부슬래브가 형성된 후 양측 상부슬래브 하부를 최종굴착선까지 굴착되어 하부슬래브가 설치되어 있는 상태를 도시한 도면
도 85는 도 82에 의해 시공이 완료된 후 내벽체를 시공한 상태를 도시한 도면
도 86은 마무리 시공한 상태를 도시한 도면
도 87은 도 7에 의해 시공이 완료된 후 상태를 도시한 표준 단면
도 88은 단위의 PC사각파일 벽체가 결합한 상태에 내벽체가 결합한 상태를 확대 도시한 단면도
도 89는 단위의 PC사각파일 벽체가 결합한 상태를 확대 도시한 단면도
도 90은 도 87에서 상세"A"를 확대 도시한 단면도
도 91은 도 87에서 상세"B"를 확대 도시한 단면도
도 92는 도 87에서 상세"C"를 확대 도시한 단면도
도 93은 도 87에서 상세 "D" 부분을 확대 도시한 단면도
도 94는 도 87에서 "D’ " 부분을 확대 도시한 단면도
도 95는 도 87에서의 "E"부분을 확대 도시한 단면도
도 96 내지 도 107은 본 발명의 제 6 실시예를 도시한 것으로,
도 96은 본 발명의 제6실시예에 의한 공정 흐름을 도시한 도면
도 97은 양 측벽과 중앙부를 이루는 CIP 구근 시공공정을 도시한 도면
도 98은 어스앙카 및 양측 하부슬래브 시공공정을 도시한 개괄 단면도
도 99는 양측 내벽체 시공공정을 도시한 개괄 단면도
도 100은 PSC빔 거치와 상부슬래브 시공공정을 도시한 개괄 단면도
도 101은 도 100에서 하부슬래브를 없이 시공되는 예를 도시한 개괄 단면도
도 102는 도 100의 상세 "A" 확대 도시 단면도
도 103은 도 100의 상세 "B" 확대 도시 단면도
도 104는 도 100의 상세 "C" 확대 도시 단면도
도 105는 단면 A-A를 확대 도시한 단면도
도 106은 부력방지용 또는 지지용 마찰 저항력 증가방법의 일예를 도시한 단면도
도 107은 부력방지용 또는 지지용 마찰 저항력 증가방법의 다른 예를 도시한 단면도
도 108 내지 도 118은 본 발명에서의 제 7 실시예를 도시한 도면으로,
도 108은 제7실시예에 의한 공정 흐름을 도시한 도면
도 109는 양 측벽과 중앙부를 이루는 CIP구근 시공공정을 도시한 도면
도 110은 내부굴착 및 어스앙카, 하부슬래브 시공공정을 도시한 개괄 도면
도 111은 양측 1차 내벽체를 시설하는 시공공정을 도시한 개괄 도면
도 112는 E/A 철거와 잔여 내벽체와 마무리 시공공정을 도시한 개괄 도면
도 113은 도 112에서 하부슬래브 없이 시공처리한 도면
도 114는 도 112에서 상세 "A"를 확대 도시한 도면
도 115는 도 112에서 상세 "B"를 확대 도시한 도면
도 116은 단면 A-A를 확대 도시한 단면도
도 117 내지 도 118은 부력방지용 또는 지지용 마찰 저항력 증가 방법의 각 예를 도시한 단면도
도 119 내지 도 138은 본 발명의 제 8 실시예를 도시한 도면으로,
도 119는 본 발명의 제8실시예에 의한 공정 흐름을 도시한 도면
도 120은 양 측벽 및 중앙부 벽체 또는 기둥 CIP구근 시공공정을 도시한 도면
도 121은 일측 상부슬래브 시공공정을 도시한 개괄 단면도
도 122는 타측 상부슬래브 시공공정을 도시한 개괄 단면도
도 123은 중앙측 상부슬래브 시공공정을 도시한 개괄 단면도
도 124는 도 123에 의해 각 상부슬래브가 형성된 후 양측 상부슬래브 코너부를 굴착한 후 그 굴착된 공간에 사보강이 설치되어 있으며 최종굴착선 부근으로 어스앙카가 설치되어 있으며 내벽체 기초 및 중앙 기둥벽 보강 시공을 하고 있는 상태를 도시한 도면
도 125는 도 123에 의해 각 상부슬래브가 형성된 후 양측 상부슬래브 코너부를 굴착한 후 그 굴착된 공간에 사보강이 설치되어 있으며 CIP구근 내부 일편측에 PC강연선이 긴장 정착되어 있으며 내벽체 기초 및 중앙 기둥벽 보강 시공을 하고 있는 상태를 도시한 도면
도 126 내지 127은 시공이 완료된 후 내벽체를 시공한 상태를 도시한 도면
도 128 내지 도 129는 도 121 내지 도 122의 또 다른 시공예에 의한 실시방법을 도시한 도면
도 130은 토사층에서의 CIP구근을 형성하는 방법을 도시한 것으로 도 127에서 "A" 부분을 확대 도시한 확대 단면도
도 131은 도 127에서 "B"부분을 확대 도시한 단면도
도 132는 상부슬래브의 일단과 벽체의 상단간을 고정 연결하기 위한 것으로 도 127에서의 "C" 부분을 확대 도시한 단면도
도 133은 도 127에서의 "D"부분을 확대 도시한 단면도
도 134는 도 127에서의 "D' "부분을 확대 도시한 단면도
도 135는 도 127에서의 "E"부분을 확대 도시한 것으로 사보강과 CIP구근과의 연결상태를 도시한 도면
도 136은 도 127에서의 "A-A"선 단면도
도 137은 도 127에서의 "B-B"선 단면도
도 138은 별도의 흙막이 시설을 도시한 도면
1 to 23 is a view showing a first embodiment according to the present invention,
1 is a view showing a process flow of a first embodiment according to the present invention.
FIG. 2 is a view illustrating a construction process of both sidewalls and a central wall or column CIP bulb in FIG. 1; FIG.
Figure 3 is a schematic diagram showing a one-side upper slab construction process in the first embodiment of the present invention
Figure 4 is a schematic diagram showing the other upper slab construction process
5 is a schematic view showing the upper side slab construction process in the center
Figure 6a, b is a view for reinforcing the lower slab and the central column wall, after the upper slab is formed by each of the upper slab corners to excavate the upper slab corners on both sides, and the excavation space is installed in the excavated space and the final excavation Drawing showing the state of reinforcing lower slab and center column wall where earth anchor is installed near the line
FIG. 7 is a view illustrating a state in which the inner wall is constructed after the construction is completed by FIGS. 6A and 6B;
8 is a standard drawing showing a state in which construction is completed
9 is an enlarged cross-sectional view illustrating a portion 'A' of FIG. 8 enlarged.
FIG. 10 is an enlarged cross-sectional view of a portion 'B' in FIG. 8.
11 is a cross-sectional view of the 'C' portion of FIG. 8 for enlarging the connection between one end of the upper slab and the upper end of the wall.
12 is an enlarged cross-sectional view of a portion 'D' in FIG. 8.
FIG. 13 is an enlarged cross-sectional view of a portion 'D''of FIG. 8. FIG.
FIG. 14 is an enlarged view of portion “E” in FIG. 8 and illustrates a connection state between the sabotage cavity and the CIP bulb; FIG.
15 is a cross-sectional view taken along the line 'A-A' in FIG.
16 is a cross-sectional view taken along the line 'B-B' in FIG. 8.
17 shows a separate retaining facility.
FIG. 18 illustrates a method for forming CIP bulbs in a composite layer of soil and rock.
19 is a cross-sectional view taken along the line 'C-C' and a line 'D-D' in FIG.
20 is a view showing a side waterproofing method at the position where the TUS method section and the general method section is connected;
FIG. 21 is a view illustrating a waterproofing method at a right angle part where the upper slab CIP bulb is in contact with the upper slab.
FIG. 22 is a view illustrating a waterproofing method at a portion where a lower slab and a CIP bulb contact each other.
Fig. 23 is a cross-sectional view showing equipment and material inlet and earth discharge outlet;
24 to 38 are views for explaining a second embodiment of the present invention.
24 is a view showing a process flow according to a second embodiment of the present invention.
FIG. 25 is a view showing a construction process of both sidewalls and central wall or column CIP bulbs in the second embodiment; FIG.
26 is a schematic cross-sectional view showing one side upper slab construction process
Figure 27 is a schematic cross-sectional view showing the other upper slab construction process
28 is a schematic cross-sectional view showing a central upper slab construction process
FIG. 29 shows that the upper slabs are formed by FIG. 28 and then the corners of both upper slabs are excavated and savo steel is installed in the excavated space, and the earth anchor is installed near the final excavation line, and the lower slab and the central column wall reinforcement construction. Drawing showing the state of doing
FIG. 30 shows that after each upper slab is formed by FIG. 28, excavation of both upper slab corner portions is provided with savo steel in the excavated space, and the PC strand is tension-fixed on one side of the CIP bulb. Drawing showing the state of wall reinforcement construction
FIG. 31 is a view illustrating a state in which the inner wall body is constructed after the construction is completed by FIG. 30.
32 is a standard cross-sectional view showing a state in which construction is completed
33 is an enlarged cross-sectional view of a portion “A” in FIG. 32.
FIG. 34 is an enlarged cross-sectional view of a portion “B” in FIG. 32.
FIG. 35 is an enlarged cross-sectional view of a portion “C” in FIG. 32 for fixedly connecting between one end of an upper slab and an upper end of a wall.
36 is an enlarged cross-sectional view of a portion “D” in FIG. 32.
FIG. 37 is an enlarged cross-sectional view of a portion 'D''in FIG. 32.
FIG. 38 is an enlarged cross-sectional view of a portion “E” in FIG. 32.
39 to 62 show drawings according to a third embodiment of the present invention,
39 shows a process flow in the third embodiment according to the present invention.
40 is a view showing the process of inserting the PC wall and PC square pile walls of both sidewalls and the PC square pile putting and CIP bulb construction process of the central wall or column.
41 is a schematic cross-sectional view showing one side upper slab construction process
42 is a schematic cross-sectional view showing another upper slab construction process
43 is a schematic cross-sectional view showing a process of constructing a central upper slab.
FIG. 44 is a view illustrating a state in which the upper slab is formed by FIG. 43 and then the corners of both upper slabs are excavated, and then the sabot is installed in the excavated space, and the lower slab is excavated to the final excavation line.
FIG. 45 is a view illustrating a state in which lower slabs are installed by digging both upper slab bottoms to a final drilling line after each upper slab is formed by FIG. 43.
46 is a view illustrating a state in which the inner wall is constructed after the construction is completed by FIG. 44;
FIG. 47 is a standard sectional view showing a state in which construction is completed by FIG. 45; FIG.
48 and 49 are enlarged cross-sectional views of the connection between the PC wall and the tie wall.
50 is an enlarged cross-sectional view of a portion “A” in FIG. 47.
FIG. 51 is an enlarged cross-sectional view of a portion “B” in FIG. 47.
52 is an enlarged cross-sectional view of a portion "C" in FIG. 47.
53 is an enlarged cross-sectional view of a portion "D" in FIG. 47.
54 is an enlarged cross-sectional view of a portion "D '" in FIG. 47.
55 is a standard cross-sectional view showing a state in which the inner wall after the construction is completed
FIG. 56 is a sectional view taken along the line “AA” in FIG. 55.
FIG. 57 is a "BB" cross-sectional view of FIG. 55
58 is an enlarged cross-sectional view of a portion “A” in FIG. 55.
FIG. 59 is an enlarged cross-sectional view of a portion “B” in FIG. 55.
60 is an enlarged cross-sectional view of a portion "C" in FIG. 55.
FIG. 61 is an enlarged cross-sectional view of a portion "D" in FIG. 55.
FIG. 62 is an enlarged cross-sectional view of a portion "D '" in FIG. 55.
63 to 77 are views for explaining a fourth embodiment of the present invention.
63 is a diagram showing a process flow according to a fourth embodiment of the present invention.
FIG. 64 is a view illustrating a piling construction process in which both sides of the sidewall portions are piled and the middle piles are piled at both sides of the central portion.
65 is a schematic cross-sectional view showing a process of constructing a central upper slab.
66 is a schematic cross-sectional view showing an upper slab construction process on one side;
Figure 67 is a schematic cross-sectional view showing the upper slab construction process on the other side
FIG. 68 shows that the upper slab is formed by FIGS. 65 to 67, and then the bottom of each upper slab is excavated, and then an earth anchor is installed in the excavated space, and the bottom slab and the central part are constructed by excavating to the final excavation line. Drawing
FIG. 69 is a view showing a state in which walls are constructed after construction is completed by FIG. 68; FIG.
70 is a detailed view of the backfill pile and anchor in the cover process
71 is an enlarged cross-sectional view illustrating a method of connecting reinforcement bars in a connection between PC slabs;
72 is an enlarged cross-sectional view illustrating a method of jointing a reinforcing bar in an upper slab connection part;
73 is an enlarged cross-sectional view of a portion “A” in FIG. 69; FIG.
74 is an enlarged cross-sectional view of a portion “B” in FIG. 69.
75 is an enlarged cross-sectional view of the upper slab one-side support facility.
76 is a detailed sectional view of the concrete PC 1 earth plate
77 is a detailed sectional view of the concrete PC 2 earth plate
78 through 95 are views for explaining a fifth embodiment of the present invention.
78 is a view showing a process flow according to the fifth embodiment of the present invention.
79 is a view showing the process of inserting the PC wall and PC square pile walls of both sidewalls and the PC square pile insert and CIP bulb construction process of the central wall or column.
80 is a schematic cross-sectional view showing one side upper slab construction process (S20).
81 is a schematic sectional view showing the other upper slab construction process (S30)
82 is a schematic cross-sectional view showing a central side upper slab construction step (S40).
FIG. 83 is a view showing a state in which the upper slab is formed and then the upper slab corners on both sides are excavated according to FIG. 82, the sandwiching is installed in the excavated space, and the lower slab is excavated to the final excavation line
FIG. 84 is a view showing a state in which lower slabs are installed by digging both upper slab bottoms to the final digging line after each upper slab is formed by FIG. 82.
FIG. 85 is a view illustrating a state in which an inner wall is constructed after construction is completed by FIG. 82;
86 is a view showing a state of finishing construction
FIG. 87 is a standard sectional view showing a state after construction is completed by FIG. 7; FIG.
88 is an enlarged cross-sectional view illustrating a state in which an inner wall is coupled to a state in which a PC square pile wall is coupled;
89 is an enlarged cross-sectional view illustrating a state in which a PC square pile wall of a unit is coupled;
90 is an enlarged cross-sectional view of detail "A" in FIG. 87.
FIG. 91 is an enlarged cross-sectional view of detail "B" in FIG. 87;
FIG. 92 is an enlarged cross-sectional view of detail "C" in FIG. 87;
FIG. 93 is an enlarged cross-sectional view of a detail "D" portion in FIG. 87; FIG.
94 is an enlarged cross-sectional view of a portion 'D''in FIG. 87.
95 is an enlarged cross-sectional view of a portion "E" in FIG. 87.
96 to 107 show a sixth embodiment of the present invention,
96 is a diagram showing the process flow according to the sixth embodiment of the present invention.
97 is a view showing a CIP bulb construction process forming both sidewalls and a central portion;
98 is a schematic cross-sectional view showing an earth anchor and a lower slab construction process on both sides;
99 is a schematic cross-sectional view showing a process for constructing both inner walls.
100 is a schematic cross-sectional view showing the PSC beam mounting and upper slab construction process
FIG. 101 is a schematic cross-sectional view illustrating an example in which the lower slab is installed in FIG. 100 without FIG.
FIG. 102 is an enlarged sectional view taken along detail “A” of FIG. 100;
FIG. 103 is an enlarged cross-sectional view of the detail “B” of FIG. 100;
FIG. 104 is a detailed “C” enlarged sectional view of FIG. 100.
105 is an enlarged cross-sectional view of a cross-section AA;
106 is a sectional view showing an example of the buoyancy preventing or supporting frictional resistance increasing method
107 is a sectional view showing another example of the buoyancy preventing or supporting friction resistance increasing method
108 to 118 show a seventh embodiment of the present invention.
108 shows a process flow according to the seventh embodiment
109 is a view showing a CIP bulb construction process forming both sidewalls and a central portion;
110 is a schematic diagram showing the process of internal drilling and earth anchor, lower slab construction
111 is a schematic drawing showing a construction process for installing both primary inner wall bodies;
112 is a schematic view showing an E / A demolition, residual inner wall, and finishing construction process
113 is a view showing the construction process without the lower slab in FIG.
FIG. 114 is an enlarged view of detail "A" in FIG. 112.
FIG. 115 is an enlarged view of detail "B" in FIG. 112.
116 is an enlarged cross-sectional view of a cross-section AA;
117 to 118 are cross-sectional views showing examples of the buoyancy preventing or supporting friction resistance increasing method
119 through 138 illustrate an eighth embodiment of the present invention.
119 shows a process flow according to an eighth embodiment of the present invention.
FIG. 120 is a view illustrating a construction process of both side walls and a central wall or column CIP bulb; FIG.
121 is a schematic cross-sectional view showing a process for constructing a single upper slab
122 is a schematic cross-sectional view showing another upper slab construction process
123 is a schematic sectional view showing a construction process of the upper slab of the center side;
FIG. 124 shows that the upper slabs are formed by FIG. 123, and after excavating corner portions of the upper slabs on both sides, the savo steel is installed in the excavated space, and earth anchors are installed near the final excavation line. Drawing which shows state carrying out reinforcement construction
FIG. 125 shows that the upper slab is formed by FIG. 123, and after excavating corner portions of the upper slab on both sides, savo steel is installed in the excavated space, and the PC strand is tension-fixed on one side of the CIP bulb. Drawing showing state of column wall reinforcement construction
126 to 127 are views showing a state in which an inner wall is constructed after construction is completed;
128 to 129 are views showing an implementation method according to another construction example of FIGS. 121 to 122.
FIG. 130 is an enlarged cross-sectional view illustrating a method of forming a CIP bulb in a soil layer and showing an enlarged portion "A" in FIG. 127.
131 is an enlarged cross-sectional view of a portion “B” in FIG. 127;
132 is an enlarged cross-sectional view of a portion “C” in FIG. 127 for fixedly connecting an end of an upper slab to an upper end of a wall;
133 is an enlarged cross-sectional view of a portion “D” in FIG. 127.
134 is an enlarged cross-sectional view of a portion "D '" in FIG. 127;
FIG. 135 is an enlarged view of a portion “E” in FIG. 127 and illustrates a connection state between the sabotage cavity and the CIP bulb;
FIG. 136 is a sectional view taken along the line "AA" in FIG. 127;
FIG. 137 is a sectional view taken along the line "BB" in FIG. 127;
FIG. 138 shows a separate retainer facility

본 발명에서는 TUS 공법을 적용하되 변형된 TUS 공법으로 창안하여, 일반도로하 지하차도 및 지하도로의 건설이 간단해지도록 하면서도 차량 통행 제한 등으로 인한 도로의 혼잡을 최대한으로 축소하고 빠르게 회복토록 하며 공사비용 및 공사기간을 대폭적으로 절감토록 하는 방법을 제시한다.In the present invention, by applying the TUS method, but created a modified TUS method, while simplifying the construction of underground roads and underground roads under the general road, while reducing the congestion of the road due to the restriction of traffic to the maximum, and to recover quickly It suggests how to drastically reduce cost and construction period.

한편 이러한 본 발명에 의해 제시되는 방법에 의해 다양한 실시가 가능하게 되므로 그 각각의 실시 예들을 첨부하는 도면들을 참조하여 설명한다.
Meanwhile, various implementations are possible by the method of the present invention, which will be described with reference to the accompanying drawings.

- 제 1 - 1st 실시예Example - -

본 발명은 도 1에 의한 바와 같이, As the present invention according to Figure 1,

양 측벽 및 중앙측 벽체 또는 기둥을 이루는 CIP구근 시공공정(S10)과, 일측 상부슬래브 시공공정(S20)과, 타측 상부슬래브 시공공정(S30)과, 중앙측 상부슬래브 시공공정(S40)과, 코너부 보강 및 어스앙카 시공공정(S50), 양측 하부슬래브 및 중앙부 벽체 또는 기둥보강 시공공정(S60)과, 양측 내벽체 시공공정(S70)과, 마무리 시공공정(S80)으로 지하차도의 시공이 이루어진다.CIP bulb construction process (S10) forming both sidewalls and the central side wall or column, one upper slab construction process (S20), the other upper slab construction process (S30), the central side upper slab construction process (S40), Corner reinforcement and earth anchor construction process (S50), both lower slab and central wall or column reinforcement construction process (S60), both inner wall construction process (S70) and finishing construction process (S80) Is done.

각 과정별로 나누어 본 발명의 공정 흐름과 이에 따른 각 구성을 설명한다.
The process flow of the present invention and each configuration according thereto will be described by dividing each process.

CIPCIP 구근 시공공정 - Bulb Construction Process- S10S10

본 공정은 양 측벽 및 중앙측 벽체 또는 기둥을 이루도록 하는 CIP구근을 시공하기 위한 공정으로, 지하차도를 건설한 위치의 벽체에 해당되는 측벽과 중앙부의 벽체 또는 기둥을 형성하기 위한 공정이다.This process is a process for constructing the CIP bulbs that form both side walls and the central side wall or pillar, and is a process for forming the side wall and the central wall or pillar corresponding to the wall at the position where the underground roadway is constructed.

이를 위해서 도면에서 보는 바와 같이 지하차도를 구성하기 위한 지역 범위내에서 중앙을 분리하기 위한 중앙부와 양측 측면부에 각각 벽체 즉 측벽이 형성되도록 CIP구근(100)을 형성한다.To this end, as shown in the drawing, the CIP bulb 100 is formed such that a wall, that is, a side wall, is formed in each of the central portion and both side surface portions to separate the center within the region range for constructing the underground roadway.

여기서 상기 중앙부 벽체는 CIP구근을 이용하여 벽체로 형성할 수도 있고, 기둥식 예컨데 중간 중간이 끊겨지는 형태의 기둥 타입으로 CIP구근을 형성할 수 있는바, 현장 조건 및 설계 등에 의해 가변 될 수 있으며, 이러한 변경은 본 발명을 사용하는 자가 선택적으로 적용할 수 있음은 당연하다 할 것이다.Here, the central wall may be formed as a wall using a CIP bulb, a column type, for example, a CIP bulb may be formed in a column type in which an intermediate middle is cut off, and may be varied according to site conditions and designs. It will be appreciated that such changes can be selectively applied by those using the present invention.

상기한 CIP(Cast-in-place) 구근(100)은 도 15 에서 보는 바와 같이 다수의 주철근(110,111)이 직사각형으로 배열 배치되고 그 주철근(110,111)을 감싸는 띠철근(120)을 등간격으로 이격시키며 주철근과 띠철근이 하나로 조합된 철근망태가 형성된다.The cast-in-place (CIP) bulb 100 has a plurality of main reinforcing bars 110 and 111 arranged in a rectangular shape as shown in FIG. 15 and spaced apart at intervals between the strip reinforcing bars 120 surrounding the main reinforcing bars 110 and 111. Reinforcing wire mesh is formed by combining main reinforcing bars and band reinforcing bars.

이러한 철근망태의 최외곽을 에워싸는 관(이하 케이싱이라 칭한다.)을 형성한 후 그 내부에 콘크리트를 타설하여 양생함으로서, 하나의 유닛으로 이루어지는 원기둥 형태의 CIP구근(100)을 형성할 수 있고, 이와는 달리 CIP구근(100)이 삽입되기 위한 홀을 천공한 후 그 홀에 철근망태를 삽입 한 다음 콘크리트를 타설 양생하여 완성된 CIP구근(100)을 얻을 수 있을 것이다.By forming a tube (hereinafter referred to as a casing) that surrounds the outermost part of the reinforcing wire mesh, and then curing by pouring concrete therein, it is possible to form a cylindrical CIP bulb 100 consisting of a single unit, and Otherwise, after drilling the hole for the CIP bulb 100 to be inserted, the reinforcing wire mesh is inserted into the hole, and then the concrete is poured to cure the finished CIP bulb 100.

이렇게 일정한 간격을 벌리면서 형성된 CIP구근(100)과 CIP구근(100) 사이에 미리 형성된 CIP구근(100)의 양 편측을 갈아내면서 천공하여 동형의 신CIP구근(115)을 새로이 형성하게 되는데 CIP구근(100)과 신CIP구근(115)는 상호 겹치도록 한다. The CIP bulb 100 is formed between the CIP bulb 100 and the CIP bulb 100 formed at regular intervals. The CIP bulb 100 is formed to be newly formed. 100 and the new CIP bulb 115 to overlap each other.

또한, 신CIP구근(115)의 형성과정은 CIP구근(100)과 같다.In addition, the formation process of the new CIP bulb 115 is the same as the CIP bulb 100.

도면에서 도면부호 131은 CIP구근(100)과 신CIP구근(115)에 의해 이루어지는 측벽을 지칭하고, 도면부호 130 또한 CIP구근(100)과 신CIP구근(115)에 의해 이루어지는 중앙부 벽체 또는 기둥 즉 중앙부를 의미하는 것으로, 본 발명에서는 CIP구근(100)과 신CIP구근(115)에 의해 이루어지는 단위체로 CIP구근(100)이라 칭하고, 이 CIP구근(100)에 의해 일렬로 매입되어 지하의 중앙과 그 양측의 측벽을 각각 구분하여 도면부호로 표기하였다.In the drawings, reference numeral 131 denotes a side wall formed by the CIP bulb 100 and the new CIP bulb 115, and reference numeral 130 also denotes a central wall or column formed by the CIP bulb 100 and the new CIP bulb 115. In the present invention, the unit consisting of the CIP bulb 100 and the new CIP bulb 115 is referred to as CIP bulb 100, and is embedded in a row by the CIP bulb 100 and is located in the center of the basement. The sidewalls on both sides are divided and denoted by reference numerals.

한편 CIP구근(100)을 형성할 때 철근망태의 일편측(벽체가 형성되는 내측을 지칭하고 이하 일편측이라 명명한다.)에는 합판등의 판넬(102)을 띠철근에 묶인 상태가 되도록 하여 콘크리트 타설시 합판등의 판넬(102) 내측으로는 콘크리트가 타설되지 않도록 하여야 하고, 띠철근 내측에는 부분적으로 쫄대(103)를 배치하는데, 이는 내벽체 철근(181)의 가로방향의 배력철근과 CIP구근(100)의 띠철근에 이어 배치한 배력철근의 상호 연결이 용이하게 하기 위해서이다.On the other hand, when forming the CIP bulb 100, one side of the reinforcing mesh (referring to the inner side where the wall is formed, hereinafter referred to as one side) on the panel 102 such as plywood to be in a state bound to the band reinforcement concrete When pouring, concrete should not be placed inside the panel 102 such as plywood, and the chord 103 is partially arranged inside the band reinforcing bar, which is the horizontal reinforcement bar and the CIP bulb of the inner wall reinforcing bar 181. This is to facilitate the interconnection of the reinforcing bars arranged after the strip reinforcing bars of (100).

더불어, 코너부 보강재(160)를 연결하기 위한 앙카볼트를 미리 구성하도록 하는 것이 좋다. 이것은 코너부 보강재를 설치할 때 즉시 설치가 용이하도록 하기 위함이다.In addition, it is good to configure the anchor bolt for connecting the corner reinforcement 160 in advance. This is to facilitate the installation immediately when installing the corner reinforcement.

또한, 철근망태의 양 편측(중앙부가 형성되는 좌우 양측)에도 합판등의 판넬(102)을 띠철근에 묶인 상태가 되도록 하여 콘크리트 타설시 합판등의 판넬(102) 내측으로는 콘크리트가 타설되지 않도록 하여야 하는데 띠철근 내측에는 부분적으로 쫄대(103)를 배치하고 있다.In addition, the panel 102 such as plywood is tied to the band reinforcement on both sides (right and left sides where the center is formed) of the reinforcement mesh so that concrete is not poured into the panel 102 such as plywood when the concrete is placed. It should be, but the chord 103 is partially disposed inside the band reinforcing bar.

이는 중앙부의 CIP구근(100)이 상호 겹침 이음으로 되어 있지만 철근으로 이어지지 못하고 있으므로 배력철근과 띠철근을 묶어 일체의 구조체로 조성하기 위함이다.This is because the CIP bulb 100 in the central portion is made of overlapping joints but does not lead to reinforcing bars, so that the reinforcement bars and the band reinforcing bars are bundled to form an integral structure.

또한 내벽체(180,180‘)에서는 철근망태 일편측 코너 양측 주철근에 접하여 2개의 PC강연선(123)을 배치하되, CIP구근(100) 일정길이에만 배치하고 중앙부(130)에서도 띠철근(120) 중앙측에 연하여 2개의 PC강연선(123)을 CIP구근(100) 일정길이에만 배치한다.In addition, in the inner wall (180, 180 '), two PC strands 123 are disposed in contact with the main reinforcing bars on one side corner of the reinforcing wire mesh, and the CIP bulb 100 is disposed only at a certain length, and the middle reinforcement of the strip reinforcing rods 120 in the center 130. In connection with the two PC strands 123 is placed only a certain length of the CIP bulb 100.

여기서 철근망태 일편측 코너 양측 주철근에 접하는 2개의 PC강연선(123)의 역할은, 상부슬래브 최외측 우각부에 설치한 코너부 보강재와 최종 굴착선까지의 사이에 어스앙카(210)를 시설하지 않아도 외부작용 부재력에 대처할 수 있도록 CIP구근(100)의 내하력을 증강시키기 위한 구조로서, 매 CIP구근(100)마다 배치하며, 중앙부에서 2가닥의 PC강연선(123)은 좌우 양측의 도드락문양 거푸집에 의하여 얇아진 CIP구근(100)이 외부의 부재력에 의하여 좌굴을 발생시키지 않도록 하기 위함이다. Here, the role of the two PC strands 123 in contact with the reinforcing wire one side corner both side reinforcing bars, even if the earth anchor 210 is not installed between the corner reinforcement provided in the outermost right corner of the upper slab and the final digging line. As a structure for enhancing the load capacity of the CIP bulb 100 to cope with external force absence force, it is disposed every CIP bulb 100, two strands of PC strands 123 in the central portion is formed on both sides of the dodlock pattern formwork. This is to prevent the thinner CIP bulb 100 from generating buckling due to external member force.

한편, PC강연선의 긴장정착 시기는 상부슬래브의 철근 조립이 완료된 시기에 상부슬래브에서 정착시키므로 상부슬래브와 CIP간을 더욱 긴밀히 응집시키는 역할을 겸하고 있으며 우각부 부모멘트를 저감시키는 효과도 함께 거둘 수 있다.On the other hand, the tensioning time of the PC strand is settled in the upper slab when the rebar assembly of the upper slab is completed, thus acting as a more tightly cohesion between the upper slab and the CIP, and can also reduce the corner angle of the right corner. .

그러나, 이러한 CIP구근(100)은 토사층에서만 가능하고 암반구간에서는 불가능한 제약조건이 따른다. However, these CIP bulbs 100 are available only in the soil layer and are subject to constraints that are impossible in rock sections.

이것은 지반을 굴착하는 오거의 장비가 암반을 천공할 수 없기 때문인데 이럴 경우 2.0m마다 암반측까지 천공이 가능한 T4 장비를 이용하여 내부굴착과 함께 구근(100)을 형성하고 그 사이는 토사층까지만 CIP구근(100)을 형성한 다음 상부슬래브(140.150)를 시공하고 암반구간까지 내부굴착하여 CIP 받침앵커(107)를 시설하고 내부굴착을 계속하되 토사층까지만 시설된 CIP구근 하단에서 하부슬래브 버림콘크리트 하단까지 암반을 절취(A)하여 CIP 철근을 이어내리고 분말방수제가 혼합된 콘크리트를 타설하면 견고한 내벽체(180,180‘)가 형성된다.
This is because the auger's equipment that excavates the ground is not able to puncture the rock. In this case, the bulb 100 is formed together with the internal excavation using the T4 equipment that can be perforated to the rock side every 2.0m. After forming the bulb 100, construct the upper slab (140.150) and excavate to the rock section to equip the CIP support anchor 107 and continue the internal excavation, but only to the earth and sand layer from the bottom of the lower slab cast concrete When cutting the rock (A) to continue the CIP reinforcement and poured concrete mixed with the powder waterproofing agent, a solid inner wall (180, 180 ') is formed.

일측One side 상부슬래브 시공공정 -  Upper Slab Construction Process- S20S20

상기한 공정(S10)을 거쳐 CIP구근(100)의 설치 시공이 완료되면 도 2와 같은 도로 단면의 구획이 분리되게 되는데, 본 공정은 이와 같은 상태에서 CIP구근(100)에 의해 구획되어지는 전체 폭원을 기준으로 3등분되는 중 어느 한측을 먼저 상부슬래브를 형성하기 위한 공정으로 이해될 것이다.When the installation of the CIP bulb 100 is completed through the above-described process (S10), the section of the road section as shown in FIG. 2 is separated, and in this state, the whole compartment is divided by the CIP bulb 100 in this state. It will be understood that either side of the third divided by the width source as a process for forming the upper slab first.

이를 위해서 도 3에서 보는 바와 같이 상부슬래브 전체 폭원중 1/3되는 위치중앙부(전술한 바와 같이 CIP구근으로 이루어지는 벽체 중 중앙을 나누는 전체 부분을 중앙부로 명명하고 이를 도면에서 130 으로 표기하며, 상기 CIP구근에 의해 형성되는 기둥 타입도 포함한다)(130) 인근의 어느 일측 도로부분에 H-말뚝을 박고 굴착하여 아스콘층과 흙을 걷어내게 된다.To this end, as shown in FIG. 3, the central portion of the upper half of the upper slab width source (as described above, the entire portion dividing the center of the wall formed of the CIP bulbs is referred to as the central portion and denoted as 130 in the drawing). It also includes a pillar type formed by the bulb) (130) in one side of the road portion near the excavated H-peg to excavate the asphalt layer and soil.

이때, H-말뚝 흙막이 시설로 제4 실시 예에서 적용되고 있는 콘크리트 PC1토류판(104)을 제작하여 설치하는 것으로 하였다.At this time, it is assumed that the concrete PC1 earth plate 104, which is applied in the fourth embodiment, is installed as an H-pile soiling facility.

이와 같이 일정깊이 터파기 공사를 진행 한 다음에 그 터파기면으로 바닥고르기 콘크리트와 거푸집을 시설한 후 상부슬래브를 시설한다. In this way, after the trench work is carried out to a certain depth, the floor slab is equipped with concrete and formwork, and then the upper slab is installed.

이때, 코너부 보강재(160)를 연결하기 위한 앙카볼트를 미리 구성하도록 하는 것이 좋다. 이것은 코너부 보강재(160)를 설치할 때 즉시 설치가 용이하도록 하기 위함이다.At this time, the anchor bolt for connecting the corner reinforcement 160 may be configured in advance. This is to facilitate the installation immediately when installing the corner reinforcement 160.

본 발명에서 상부슬래브는 도 3 내지 도 5에서 보는 바와 같이 전체 폭원을 3등분으로 각각 구분되며 순차적인 타설 과정을 거치게 되는데, 본 발명의 실시 이해를 위해 도면상(도 3) 보았을 때 우측의 상부슬래브를 일측 상부슬래브라 명명하고 도면부호 140으로 표기하였으며, 이와 대향되는 측의 슬래브를 타측 상부슬래브로 명명하고 도면부호 140‘으로 표기하며 중앙측의 슬래브를 중앙측 상부슬래브로 명명하고 도면부호 150으로 표기하여 구분하였다.In the present invention, the upper slab is divided into three equal parts and the sequential pouring process, respectively, as shown in Figures 3 to 5, the upper part of the right side when viewed in the drawings (Fig. 3) for the understanding of the implementation of the present invention. Named slab on one side of upper slab and denoted by reference numeral 140. Named slab on the opposite side as other upper slab, denoted by reference numeral 140 'and named center slab as center-side upper slab. Notation was divided into.

이때 일측 상부슬래브(140)의 철근은 이웃과 접하는 중앙측 상부슬래브(150)와의 철근 연결을 위하여 한곳에서 이음치 않도록 지그재그로 배치 이음을 할 수 있도록 하고 일측 상부슬래브(140)의 시공 후에는 방수재와 보호몰탈을 시공한다. At this time, the reinforcing bar of one side upper slab 140 can be arranged in zigzag so as not to be connected at one place for connecting the reinforcement with the center side upper slab 150 in contact with the neighbor, and after construction of the one side upper slab 140 Install a protective mortar.

이와 같이 일측 상부슬래브(140)를 타설 시공한 후에는 후술하게 되는 타측 상부슬래브(140‘)를 타설하기 위한 터파기 시공(S30)이 이루어지는데 그 전에 교통의 흐름을 방해하지 않기 위해 일측 상부슬래브(140)의 표면을 복토하게 되는 복토과정을 거쳐야 한다.As such, after placing the upper slab 140 on one side, a trench construction (S30) for placing the other upper slab 140 ', which will be described later, is performed, but the upper upper slab does not interfere with the flow of traffic before. Cover the surface of the (140) must go through a cover process.

한편, 복토시에는 일측 상부슬래브(140)와 중앙측 상부슬래브(150)의 지그재그 방식의 철근이음을 위하여 별도의 흙막이 시설을 하면서 복토를 하게 되는데 별도의 흙막이 시설로는 H말뚝(90) 한쪽 플렌지에 다수개의 천공구멍(92)을 내고 이음부로부터 뒤로 일정거리를 후퇴하여 시설하되 철근에 연결된 앵커체(91)를 천공구멍(92) 위치에서 볼트(93)로 결합하는 방식으로 다수개를 횡으로 시설한 후 적층하여 같은 방법으로 지표에 이르기까지 시설한다.On the other hand, in the case of covering the soil to cover the zigzag reinforcement of the zigzag reinforcement of the upper slab 140 and the central side of the upper slab 150 while covering the soil as a separate mud facility H pile 90 one flange After making a plurality of drilling holes 92 in the back and a certain distance back from the joint, the facility is installed, but a plurality of the transverse in such a way to couple the anchor body 91 connected to the reinforcement with the bolt 93 at the drilling hole 92 position After installation, they are stacked and installed to the ground in the same way.

이와같은 방법으로 시설하면 중앙측 상부슬래브(150)를 터파기할 때 일측상부슬래브(140) 시공시 시설된 별도의 흙막이 시설이 토류벽의 역할을 수행하게 되어 중앙측 상부슬래브(150)의 터파기가 용이해진다.When the facility is installed in such a way, when the upper slab 150 is destroyed in the central side, a separate soil barrier facility installed at the construction of the upper upper slab 140 serves as the earth wall so that the trench of the central upper slab 150 is removed. It becomes easy.

한편, 일측 상부슬래브(140)의 시공에 있어서는 상기와는 달리 도로의 사정에 의하여 터파기 시공방법을 중앙부를 기준으로 일측과 타측 양측의 1/2의 방법으로 시공할 수 있다.
On the other hand, in the construction of one side upper slab 140, unlike the above, the construction of the trench can be constructed by the method of 1/2 of one side and the other side with respect to the center part by the circumstances of the road.

타측The other side 상부슬래브 시공공정 -  Upper Slab Construction Process- S30S30

본 공정은 상기한 일측 상부슬래브 시공공정(S20)에 의해 일측 상부슬래브(140)를 타설한 후, 그 일측 상부슬래브(140) 상면을 복토하여 교통의 흐름이 방해되지 않도록 한 다음, 타측 즉 일측 상부슬래브(140)와 대향되는 측(도4) 에서 보았을 때 왼쪽의 상부슬래브(타측 상부슬래브-140‘)를 타설하기 위해 터파기 시공을 하는 과정을 의미한다.This process is after pouring the one side upper slab 140 by the one side upper slab construction step (S20), and then cover the upper surface of one side upper slab 140 so that the flow of traffic is not hindered, then the other side, one side As seen from the side (FIG. 4) opposite the upper slab 140, it refers to a process of constructing the trench to pour the upper slab on the left side (the other upper slab 140 ').

이와 같이 타측 상부슬래브(140‘)를 타설하기 위해 그 주변을 터파기 시공한 다음 도 4에서와 같이 타측 상부슬래브(140’)를 타설 양생하여 지하차도를 구성하기 위한 상측으로의 각 상부슬래브(140,140‘)의 타설 작업을 완료할 수 있으며, 코너부 보강재(160)를 연결하기 위한 앙카볼트 설치과정이라든가, 복토하는 과정이라든가 H-말뚝 박기와 터파기 및 토류판 설치 시공방법은 일측 상부슬래브(140)의 방법과 동일하게 이루어진다.In this way, the periphery of the periphery is carried out to pour the other upper slab 140 ', and then the other upper slab to the upper side for constructing the underground driveway by casting the other upper slab 140' as shown in FIG. 140,140 ') can be completed, the installation process of anchor bolts for connecting the corner reinforcement 160, the process of covering, or the H-piling and digging and earth plate installation construction method of one side upper slab (140 ) Is done in the same way.

한편, 타측 상부슬래브(140‘)의 철근은 이웃과 접하는 중앙측 상부슬래브(150)와의 철근 연결을 위하여 한곳에서 이음치 않도록 지그재그로 배치 이음을 할 수 있도록 하고 타측 상부슬래브(140’)의 시공 후에는 방수재와 보호몰탈을 시공한다.
On the other hand, the reinforcing bar of the other upper slab (140 ') is to be connected in a zigzag arrangement so as not to be jointed in one place for connecting the reinforcement with the center upper slab 150 in contact with the neighbor and the construction of the other upper slab (140') Afterwards waterproofing material and protective mortar should be installed.

중앙측Center 상부슬래브 시공공정 -  Upper Slab Construction Process- S40S40

상기한 일측 및 타측 상부슬래브 시공공정(S20,S30)의 설치시공이 완료되면 도 5에서 보듯이 중앙측 상면 도로 부분을 굴착하여 아스콘층과 흙을 걷어내게 된다. When the installation of the one side and the other upper slab construction process (S20, S30) is completed, as shown in Figure 5 to excavate the central side of the upper road portion to remove the ascon layer and soil.

이처럼 중앙측을 터파기 할 때는 일측 및 타측 상부슬래브 시공공정(S20,S30)시 이미 설치한 H말뚝(90)과 앵커체(91)가 연결되어 있는 흙막이 시설이 있으므로 별도의 흙막이 시설이 없이 터파기가 가능하다. As such, when digging the center side, there is an earthquake facility in which the H pile 90 and the anchor body 91 are already connected during the construction of one side and the other upper slab (S20, S30). It is possible.

이와 같이 일정깊이 터파기 공사를 진행 한 다음에 그 터파기면으로 바닥고르기 콘크리트와 거푸집을 시설한 후 중앙측 상부슬래브(150)를 시설한다. After proceeding the trench work in a predetermined depth as described above, and then install the floor-level concrete and formwork to the trench surface, the upper side slab 150 is installed.

이때 상부슬래브의 철근은 일측 및 타측에서 이미 지그재그로 배열된 상태로 연결하고 콘크리트를 타설하게 되는데, 타설 후에는 방수재와 보호몰탈을 시공한다. At this time, the reinforcing bar of the upper slab is already connected in a zigzag state on one side and the other side, and the concrete is poured. After pouring, the waterproofing material and the protective mortar are constructed.

이와 같이 중앙측 상부슬래브(150)를 시설한 후에는 어느 일측 및 타측 상부슬래브(140,140‘) 시공에 있어서 설치되었던 H-말뚝(90)을 뽑기 위한 볼트를 해제하는 과정과 함께 되메우기를 하면서 H-말뚝(90)을 인발하게 된다.After the central upper slab 150 is installed in this manner, the bolts for pulling the H-pile 90 which were installed in one side and the other upper slab 140 and 140 'are installed together with the process of releasing the bolt H- The pile 90 will be drawn out.

이처럼 상부슬래브의 전체 폭원을 3등분하여 시공하는 것은 우각부와 중앙부에서 발생되는 부모멘트 최대 위치에 철근 이음을 두지 않기 위함이다.In this way, the total width of the upper slab is divided into three parts in order not to place the reinforcing bar at the maximum position of the parent moment generated at the right angle part and the center part.

한편, 1/2 시공일 경우에는 중앙부에서 철근이음을 하여야 하므로 부모멘트로 인한 부담이 될 수 있어 콘크리트 두께를 10㎝ 정도 두껍게 하여야 한다. 이는 부모멘트의 크기를 저감시키기 위함이다.
On the other hand, in the case of 1/2 construction, the reinforcing bar should be made in the center part, so it may be a burden due to the parent's cement. This is to reduce the size of the parent.

코너부Corner portion 보강 및  Reinforcement and 어스앙카Earthanka 시공공정 -  Construction Process- S50S50

본 공정은 상기한 각 상부슬래브(140,140‘)의 타설 작업을 완료한 후 상부슬래브와 CIP가 결합되어 있어 부모멘트가 크게 작용되는 것을 저감시키기 위한 방법으로 상부슬래브(140,140’)나 내벽체(180,180‘)의 지간을 짧게 유도하는 것이다. This process is the upper slab (140,140 ') or the inner wall (180,180) as a way to reduce the effect of the parent moment is large because the upper slab and the CIP is combined after completing the above-mentioned casting of each upper slab (140,140') To shorten the time between ').

이를 위하여 코너부 일부만의 굴착을 하여 일정한 간격으로 사보강재(160)를 설치하는 것이다.To this end, by excavating only a part of the corner portion is to install the stiffeners 160 at regular intervals.

이때, CIP구근(100) 형성을 위한 시공공정(S10)과 각 상부슬래브 시공공정(S20,S30)시 미리 매설된 앵커볼트에 간단히 사보강재(160)를 조립 체결하는 것이다.At this time, during the construction process (S10) and each upper slab construction process (S20, S30) for the formation of the CIP bulb 100 is to simply assembling and fastening the four stiffeners 160 to the anchor bolts already embedded.

이와같이 설치된 사보강재(160)로 인하여 상부슬래브와 CIP구근(100)의 지간이 짧아져 부재력이 작아지므로 한층 안전성이 유지되는 것이며, 내벽체(180,180‘)에서 사보강재(160)연단과 최종 굴착면 사이의 길이를 줄이기 위한 방편으로 어스앙카를 시설한다. Since the interval between the upper slab and the CIP bulb 100 is shortened due to the installed sabotage steel 160, the member force decreases, and thus the safety is further maintained, and the end surface of the sabotage steel 160 and the final excavation surface in the inner wall (180, 180 '). Earth anchors are used to reduce the length of the bridge.

이러한 어스앙카의 시설은 내벽체(180,180‘)의 부재력이 작아지도록 함과 아울러 근입장의 길이도 작게 할 수 있어 경제적 측면에서 유리하다.The facility of Earth Anca is advantageous in terms of economical ability to reduce the member force of the inner wall (180, 180 ') and to reduce the length of the entry.

한편, CIP구근(100)에 매입하여 긴장 정착하는 PC강연선(123)을 이용할 경우 어스앙카를 시설하지 않아도 같은 효과를 얻을 수 있으므로 본 발명을 사용하는 자가 선택적으로 적용할 수 있음은 당연하다 할 것이다.
On the other hand, when using the PC strand (123) to buy a strain on the CIP bulb 100, the same effect can be obtained even without the earth anchor, it will be natural that the person using the present invention can be selectively applied. .

양측 하부슬래브 및 중앙부 벽체 또는 기둥보강 시공공정 - Reinforcement work of both bottom slab and central wall or column- S60S60

본 공정은 전술한 코너부 보강 및 어스앙카 시공공정(S50)이 완료된 후, 하부슬래브(170,170’) 및 중앙부(130)를 시공하여 지하차도를 형성하기 위한 공정이다.This process is a process for forming the underground roadway by constructing the lower slab (170, 170 ') and the central portion 130 after the above-described corner portion reinforcement and earth anchor construction process (S50) is completed.

양측의 굴착 된 공간에 버림콘크리트와 외부시트 방수층을 형성한 후 해당 굴착 부분의 측벽(131)과 그 하단으로 하부슬래브(170,170’)를 타설하게 된다.After forming the discarded concrete and the outer sheet waterproof layer in the excavated space on both sides, the lower slab (170, 170 ') is poured into the side wall 131 and the bottom of the excavated portion.

여기서 상기 하부슬래브(170,170’)는 도면에서 보는 바와 같이 지하차도의 바닥면에 타설되는 타설체를 의미하고, 측벽(131)의 내측에 접하는 헌치부까지 타설한다.Here, the lower slab (170, 170 ') refers to the pour body to be poured on the bottom surface of the underground driveway, as shown in the drawing, pours up to the haunche portion in contact with the inner side of the side wall (131).

상기와 같이 양측의 공간을 굴착 시공한 후 하부슬래브(170,170’)의 타설공정이 완료되면, 중앙부(130)의 좌우 양측에 배력철근을 대고 개소별로 시공되어진 CIP구근(100)을 띠철근과 묶어 일체로 하는 보강벽체(190)를 타설하여 완성된 형태의 중앙부(130)를 구성할 수 있게 된다.
After excavating the spaces on both sides as described above, when the casting process of the lower slab (170, 170 ') is completed, place the reinforcing bars on the left and right sides of the central portion 130 and tie the CIP bulb 100, which was constructed by places, with the band bars. It is possible to form a central portion 130 of the completed form by pouring the reinforcing wall 190 to be integrated.

양측 Both sides 내벽체Inner wall 시공공정 -  Construction Process- S70S70

하부슬래브 양측으로 일체로 수직상 연결되어 측벽(131)의 내측으로 타설되는 일부의 내벽체(180,180‘)는 하부슬래브(170,170‘)에 연이은 어스앙카를 철거한 후 시공되어지며 잔여 내벽체(180“)는 상기의 일부의 내벽체(180,180’)가 양생되어진 후 코너부 보강재(160)를 철거하면서 시공되어진다. 그러나 잔여 내벽체(180“)가 양생될때 콘크리트 수축작용에 의하여 침강이 되어 상부슬래브(140,150,140‘)와 미세한 틈이 발생될 수 있는데, 이곳에 무수축몰탈(183)을 충진하여 완성하게 된다.
Some of the inner walls 180 and 180 'integrally connected to both sides of the lower slab and placed inward of the side wall 131 are constructed after dismantling the earth anchors connected to the lower slabs 170 and 170' and the remaining inner walls 180 ") Is constructed while demolishing the corner reinforcement 160 after some of the inner wall (180, 180 ') is cured. However, when the remaining inner wall (180 ″) is cured, it may be settled by the concrete shrinkage action, and a fine gap may be generated with the upper slabs (140, 150, 140 '), and is completed by filling the non-shrink mortar (183).

마무리 시공공정 - Finishing Construction Process- S80S80

상기와 같은 공정이 완료되면, 지하차도 내부의 보도 및 전기시설, 타일과 아스콘 등을 시설하여 지하차도의 공정을 마무리한다.
When the above process is completed, the process of the underground driveway is completed by installing sidewalks and electric facilities, tiles and ascons inside the underground driveway.

이상과 같은 일련의 공정을 거쳐, CIP구근(100)을 이용한 지하차도를 시공하게 되는데 있어서, 도 9는 측벽(131)과 하부슬래브(170)의 각 철근(181)(111)과 철근(171,172)의 연결 고정되는 상태를 나타내고 있다.In the construction of the underground roadway using the CIP bulb 100 through a series of processes as described above, FIG. 9 shows reinforcing bars 181 and 111 and reinforcing bars 171 and 172 of the side wall 131 and the lower slab 170. ) Is shown in the connection fixed state.

도면에서 보듯이 내벽체의 내측철근(181)의 배력철근이 측벽(131)을 이루는 각 CIP구근(100)에 매입되는 철근(110,111) 중, 내벽체(180)에 접하는 부분을 판넬(102)에 의해 절개되어지는 부분에 의해 노출된 철근(111)의 띠철근(120)과 연결 고정되도록 하여 하부슬래브(170)와 측벽(131) 하단이 연결되도록 구성하였으며, 이러한 연결 구조는 지하도로의 좌우 하단측에 동일하게 적용될 것이다.As shown in the drawing, a portion of the reinforcing bars of the inner reinforcing bars 181 of the inner wall body contacting the inner wall 180 among the reinforcing bars 110 and 111 embedded in the respective CIP bulbs 100 forming the side wall 131. The lower slab 170 and the lower side of the side wall 131 were connected to each other so that the lower slab 170 and the lower side of the sidewall 131 were connected and fixed to the strip reinforcing rod 120 of the rebar 111 exposed by the portion to be cut. The same applies to the bottom side.

도 10은 하부슬래브(170,170‘)와 중앙부(130)를 연결하는 상태를 나타내고 있으며 가로방향으로 천공되는 다수의 가로공(101)을 형성하고, 그 가로공(101)으로 하부슬래브(170)에 매입되는 철근(171,172)을 통과시켜 타측의 하부슬래브(170)에 매입되는 다른 철근(171‘, 172’)과 연결 고정되도록 한 상태를 도시하였으며, 헌치에 연하는 스터럽 철근(173)을 배치하고 있다.FIG. 10 shows a state in which the lower slabs 170 and 170 'and the central portion 130 are connected to each other, and a plurality of horizontal holes 101 are formed in the horizontal direction, and the horizontal slabs 101 are formed in the lower slab 170. Passed reinforcing bars (171, 172) is shown to be connected to the other reinforcing bars (171 ', 172') to be fixed to the lower slab 170 on the other side, and the stirrup reinforcing bars (173) connected to the haunch is placed have.

도 11은 상부슬래브(140,140‘)의 일단과 측벽(131)의 상단간을 고정 연결하기 위한 단면을 나타내는데, 도면에서 보듯이 어느 한측의 상부슬래브(140)와 측벽(131)간의 고정 상태를 도시하고 있으며, 상부슬래브(140,140’)가 타설되어질 때 각 상부슬래브(140,140‘)에 매입되어 있는 복수개의 철근(142,142’/143,143‘)은 각각 측벽(131)을 이루는 CIP구근(100)에 매입되어 있는 철근(110,111) 중 내벽체(180)에 근접하는 철근(111) 및 하부슬래브(170)의 측면으로 일체로 타설되는 내벽체(180)의 철근(181)과 각각 연결 고정되도록 하였으며, 상부슬래브에서 가스압접되어 이어지는 또 다른 철근(144,144’)은 측벽(131)을 이루는 CIP구근(100)에 매입되어 있는 철근(110,111) 중 철근(110)과 연결 고정되도록 하였다.FIG. 11 is a cross-sectional view for fixedly connecting between one end of the upper slab 140 and 140 'and the upper end of the side wall 131. As shown in the drawing, the fixed state between the upper slab 140 and the side wall 131 on one side is shown. When the upper slabs 140 and 140 'are poured, the plurality of reinforcing bars 142, 142' / 143 and 143 'embedded in the upper slabs 140 and 140' are embedded in the CIP bulbs 100 forming the side walls 131, respectively. Among the reinforcing bars 110 and 111, the reinforcing bars 111 and the lower slab 170 adjacent to the inner wall body 180 are respectively connected to and fixed to the reinforcing bars 181 of the inner wall body 180 which are integrally poured. Another reinforcing bars (144,144 ') which are connected by gas pressure in the connection to be fixed to the reinforcing bars 110 of the reinforcing bars (110,111) embedded in the CIP bulb 100 forming the side wall 131.

아울러, 상기한 내벽체(180)의 철근(181)과 교차 배치되는 배력철근과 측벽(131)을 이루는 CIP구근(100)에 매입되는 철근(110,111)중 내벽체(180)에 근접하는 철근(111)에 가로방향으로 띠철근(120)과 이에 접하여 배치된 배력철근을 연결하기 위한 연결철근(182)이 상하로 각각 다수개 등 간격으로 이격시키며 구비되어야 한다. 이러한 연결구조는 지하도로의 좌우 상단측에 동일하게 적용될 것이다.In addition, the reinforcing bars close to the inner wall body 180 of the reinforcing bars (110, 111) formed in the CIP bulb 100 constituting the back-up reinforcement and the side wall 131 intersects with the reinforcing bars 181 of the inner wall 180 ( The connecting reinforcing bars 182 for connecting the strip reinforcing bars 120 and the reinforcing bars arranged in contact with the transverse reinforcing bars 111 are to be spaced apart from each other at equal intervals. This connection structure will be equally applied to the upper left and right sides of the underground road.

또한, 상기 상부슬래브(140,140‘)의 타설시 철근(143,143’)을 피복으로 감싼 상태에서 지중에 매립하여 두고 타설되는데 이후 잔여 내벽체(180”)시설 공정시 상기 매립하여 두었던 철근(143,143‘)과 내벽체(180)에 매입되는 철근(181)이 피복이 제거된 상태에서 상호 연결되도록 하였다.In addition, when reinforcing the reinforcing bars (143,143 ') when the upper slab (140,140') is covered with a covering, it is placed in the ground and placed thereafter. And the reinforcing bars 181 embedded in the inner wall 180 are connected to each other in a state where the coating is removed.

도 12는 도면에서 보듯이 1/3 시공순서에서 보여지며 각 상부슬래브(142,142‘,141,141’/ 152,151) 철근이 한곳에서 연결되지 않고 지그재그로 연결 결합되어야 한다.12 is shown in the construction sequence 1/3 as shown in the drawings, each of the upper slab (142,142 ', 141,141' / 152,151) reinforcing bar should be connected in a zigzag connection without connecting in one place.

즉, 일측 및 중앙측 상부슬래브(140,150) 내부에 매입되는 각각의 철근(141,142 / 151,152)이 연결되어야 하며 타측 및 중앙측 상부슬래브(140‘,150) 내부에 매입되는 각각의 철근(141’,142‘ / 151,152)이 연결되어야 하는 것이다. 이때 상기에서 설명하였듯이 연결되는 각각의 철근은 상호 지기재그로 연결토록 한 후 타설토록 함이 중요하다.That is, each of the reinforcing bars 141, 142/151, 152 to be embedded in one side and the central upper slab (140, 150) should be connected, and each of the reinforcing bars 141 ', which are embedded in the other side and the center upper slab (140', 150), 142 '/ 151,152 should be connected. At this time, as described above, it is important that each reinforcing bar is connected to each other and then placed in place.

도 13은 1/2 시공순서에서 보여지는 상세로서 각 상부슬래브(140,140’) 철근과 CIP구근(100)에서의 철근이 결합되어야 하며 일정 인장부에서의 연결로서 부멘트로 인한 구조적 불리한 상황이 될 수 있으므로 중앙부 상부슬래브의 단면 두께를 외측으로 늘려 부모멘트가 저감되도록 함이 중요하다.13 is a detail shown in the 1/2 construction sequence of the upper slab (140, 140 ') reinforcing bar and the reinforcing bar in the CIP bulb 100 is to be coupled to the structural disadvantage due to the buoy as a connection in a certain tension portion Therefore, it is important to increase the cross-sectional thickness of the central upper slab to the outside to reduce the parenting.

이를 위하여, 각 상부슬래브(140,140‘) 내부에 매입되는 각각의 철근(141,141’ / 142,142‘)을 CIP구근(100)의 중앙부 철근(132)과 서로 고정 연결하여야 하는데, 도면에서 보듯이 중앙부(130)를 이루는 CIP구근(100)의 상단측인 각 상부슬래브(140,140’)와 접하게 되는 위치를 결속하여 고정하고 일측의 상부슬래브(140)를 타설한다. 이때 타측의 상부슬래브의 철근과 연결을 위하여 일정길이의 철근(141, 142)을 타설전에 지그재그로 배열하여 한곳에서만 연결이 되지 않도록 조치하여 타측 상부슬래브(140‘)의 타측철근(141’, 142‘)의 단부와 커플러 또는 가스압접 등의 방법으로 연결 고정한다. 이와 같이 하여 각 상부슬래브(140,140’)와 중앙부(130)를 견고하게 연결한다.To this end, the respective reinforcing bars 141, 141 '/ 142, 142' to be embedded in each upper slab (140, 140 ') should be fixed to the central reinforcing bars 132 of the CIP bulb 100, as shown in the center portion 130 Binding and fixing the position which is in contact with each upper slab (140,140 ') that is the upper side of the CIP bulb 100 forming a) and pours the upper slab 140 on one side. At this time, the reinforcing bars 141 and 142 of a certain length are arranged in a zigzag before being placed in order to connect with the reinforcing bars of the other upper slab, so that they are not connected only in one place, so that the other bars (141 'and 142) of the other upper slab 140' are not connected. Fix the end of ') with a coupler or gas pressure welding method. In this way, the upper slabs 140 and 140 'and the central portion 130 are firmly connected.

도 14는 도 8에서의 "E"부분을 도시한 것으로, 확대도면에서는 코너부 보강재(160)를 CIP구근(100)의 일측면과 고정하기 위한 예를 나타내고 있는데, 도면에서 보듯이 CIP구근(100)에 미리 매설된 앙카볼트와 연결하여 코너부 보강재(160)가 충분한 지지력을 갖도록 구성하게 된다. 이와같은 연결은 상부슬래브(140,140‘)와의 연결에도 적용된다.FIG. 14 illustrates an “E” portion in FIG. 8, and shows an example for fixing the corner reinforcement 160 to one side of the CIP bulb 100 in the enlarged view. As shown in the figure, the CIP bulb ( It is configured to connect the anchor bolt buried in 100 in advance so that the corner reinforcement 160 has a sufficient supporting force. This connection also applies to connections with upper slabs 140 and 140 '.

도 15는 도면에서 보는 바와 같이 내벽체(180)의 외측과 접하면서 전술한 연결철근(182)에 의하여 연결되기 위해서는 측벽(131)을 이루는 CIP구근(100)의 일측면은 일부가 절단되어 CIP구근(100)에 매입되는 철근(110,111)을 감싸는 띠철근(120)이 미리 설치한 쫄대(103)등에 의하여 외부로 노출되도록 합판 등의 판넬(102)에 의해 마감처리 되도록 하여야 한다.15 is one side of the CIP bulb 100 forming the side wall 131 to be connected to the outside of the inner wall body 180 by the connecting reinforcing bar 182 as shown in the drawing is partially cut CIP The band reinforcing bars 120 surrounding the reinforcing bars 110 and 111 to be embedded in the bulb 100 should be finished by the panel 102 such as plywood so as to be exposed to the outside by the pre-installed band 103.

이와 같이 시공되기 위해서 양 측벽 CIP구근 시공공정(S10)에서 측벽(131)을 이루기 위한 CIP구근(100) 형성시 일측을 절개하도록 판넬(102)을 형성하여 타설되도록 하는 것이 바람직하다.In order to be constructed as described above, when forming the CIP bulb 100 for forming the sidewall 131 in both sidewall CIP bulb construction process (S10), it is preferable to form the panel 102 so as to cut one side.

상기와 같이 판넬(102)에 의해 절개면을 얻게 되는 측벽(131)에는 측벽(131)을 구성하는 CIP구근(100)에 매입되는 철근(110,111)을 감싸는 띠철근(120)을 미리 설치한 쫄대(103)등에 의하여 외부로 노출된 상태에서 배력철근을 배치하고, 이 배력철근과 띠철근을 묶어 전술한 가로방향으로 연결하기 위한 연결철근(182)에 의해 상기한 내벽체(180,180‘)의 철근(181)과 교차 배치되는 배력철근과 연결될 수 있는 것이다.In the side wall 131 which is obtained by the panel 102 as described above, the band reinforcing bar 120 that wraps the reinforcing bars (110, 111) embedded in the CIP bulb 100 constituting the side wall 131 in advance The reinforcing bars of the inner wall bodies 180 and 180 'are disposed by connecting reinforcing bars in the state exposed to the outside by the 103 and the connecting reinforcing bars 182 for bundling the reinforcing bars and the band bars and connecting them in the above-described horizontal direction. It can be connected to the reinforcement bars that intersect with (181).

도 16은 중앙부(130) 좌우 양측으로 쫄대(103)와 판넬(102)을 철거하고 배력철근을 배치한 후 쫄대에 의해 노출된 띠철근(120)에 배력철근을 묶어 보강콘크리트를 타설 한 상태를 도시하였다.FIG. 16 shows the state where the reinforcement concrete is poured by tying up the reinforcement to the band reinforcing bar 120 exposed by the reinforcement after dismantling the rod 103 and the panel 102 to the left and right sides of the central portion 130. Shown.

도면부호 S는 상부슬래브(140,150,140‘)의 상면측과 하부슬래브(170,170‘)의 하면측에 구성되는 보호몰탈과 방수시트를 포함하는 보호몰탈 방수시트층을 가르킨다.Reference numeral S denotes a protective mortar waterproof sheet layer including a protective mortar and a waterproof sheet formed on the upper surface side of the upper slab 140,150,140 'and the lower surface side of the lower slab 170,170'.

본 발명에서의 방수방법은 CIP구근(100)에는 분말방수제를 레미콘에 혼합하여 타설하므로 벽체부(측벽(131)과 내벽체(180,180‘)를 합하여 벽체부라 통칭한다) 방수를 실현하고 상하부슬래브에는 시트방수재(S)와 보호몰탈을 포설하는 것으로 실현하는데 각각의 접합부에는 도20,21,22 에서 보듯이 위치에 따라 방법을 각각 달리하고 있다.In the present invention, the waterproofing method of mixing the powder waterproofing agent into the ready-mixed concrete is applied to the CIP bulb 100 so that the wall part (the side wall 131 and the inner wall (180, 180 ') are collectively referred to as the wall part) is realized and the upper and lower slabs The sheet waterproofing material (S) and the protective mortar are provided, and the respective joints have different methods depending on their positions as shown in FIGS. 20, 21, and 22. FIG.

즉, CIP구근(100)과 일반 구조체가 접하는 벽체 접합부에는 도20에서 보듯이 마지막 CIP구근(100) 형성과정에서 시트방수재(S)를 매입하여 형성한 후 일반 구조체의 시트방수재(S)와 겹침이음의 방법으로 하고, 상부 우각 접합부에는 도21에서 보듯이 시트방수재(S) 위에 수밀성 방수재를 추가하고 보호몰탈을 시설한 뒤 주위에는 점토알갱이를 두껍게 깔아주며, 하부 우각 및 중앙 접합부에는 도22에서 보듯이 유공관과 부직포와 자갈을 시트방수재 아래에 깔아준다. That is, the CIP bulb 100 and the wall junction portion in contact with the general structure, as shown in Figure 20 after forming the sheet waterproofing material (S) in the process of forming the last CIP bulb 100 and overlaps with the sheet waterproofing material (S) of the general structure As a method of joining, the upper right joint is added with a watertight waterproofing material on the sheet waterproofing material (S) as shown in Fig. 21, and after the protective mortar is installed, the clay granules are thickly wrapped around the lower right corner and the central joint in Fig. 22. As you can see, lay perforated pipe, non-woven fabric and gravel under the sheet waterproofing material.

한편 지하차도의 길이가 길어질 경우 도23에서와 같이 일정간격의 길이마다 재료투입구(82-1)를 시설하여야 한다. 이 재료투입구(82-1)는 상부슬래브를 시공하고 복토를 하여 노면에 차량을 통행시킬 때 상부슬래브 하면의 굴착과 하부 및 내벽체 시공을 위한 장비 반입반출구와 내부 굴착토사의 반출구, 철근 및 레미콘등 재료투입을 위한 용도로 쓸 수 있다.On the other hand, if the length of the underground road is long, as shown in Figure 23, the material inlet 82-1 should be provided for each length of a certain interval. This material inlet 82-1 is used to excavate the bottom of the upper slab and to carry out the lower and inner walls of the upper slab when constructing and covering the upper slab, and to carry the vehicle on the road surface. And ready-mixed materials such as ready-mixed concrete.

이러한 재료투입구(82-1)는 공사후에는 폐쇄를 하며 지하수에 영향이 없도록 방수등을 철저히 하여야 물론이고 지하차도의 환풍시설이 놓이는 위치와는 간섭되지 않도록 하여야 한다.
This material inlet 82-1 is to be closed after the construction and should be thoroughly waterproof so as not to affect the groundwater, and of course, so as not to interfere with the location of the ventilation facility of the underground roadway.

제 2 Second 실시예Example

본 발명은 도 2에 의한 바와 같이, As the present invention according to Figure 2,

양 측벽 및 중앙부 벽체 또는 기둥을 이루는 CIP구근 시공공정(S10)과, 일측으로 PC구조의 상부슬래브를 조립하는 일측 상부슬래브 시공공정(S20)과, 타측으로 PC구조의 상부슬래브를 시공하는 타측 상부슬래브 시공공정(S30)과, 중앙측으로 PC구조를 조립 설치하는 중앙측 상부슬래브 시공공정(S40)과, 코너부 보강 및 어스앙카 시공공정(S50), 양측 하부슬래브 및 중앙부 벽체 또는 기둥보강 시공공정(S60)과, 양측 내벽체 시공공정(S70)과, 마무리 시공공정(S80)으로 지하차도의 시공이 이루어진다.CIP bulb construction process (S10) forming both sidewalls and central wall or column, one upper slab construction process (S20) for assembling the upper slab of PC structure to one side, and the other upper portion for constructing the upper slab of PC structure to the other side Slab construction process (S30), center side upper slab construction process (S40) for assembling and installing PC structure to the center side, corner portion reinforcement and earth anchor construction process (S50), both lower slab and central wall or column reinforcement construction process The construction of the underground roadway is performed by (S60), both inner wall construction steps (S70), and the finishing construction step (S80).

각 공정별로 나누어 본 발명의 공정 흐름과 이에 따른 각 구성을 설명한다.
The process flow of the present invention and each configuration according thereto will be described by dividing each process.

CIPCIP 구근 시공공정 - Bulb Construction Process- S10S10

본 공정은 지하차도를 건설할 위치의 벽체에 해당되는 측벽과 중앙부의 벽체 또는 기둥을 형성하기 위한 공정으로 제1실시예 (도 1 예시)와 같은 방법으로 시공하므로 상세 설명은 제1실시 예를 참조한다.
This process is a process for forming the side wall and the central wall or pillar corresponding to the wall of the position to build the underground driveway and is constructed in the same manner as in the first embodiment (illustrated in FIG. 1), so the detailed description will be made as follows. See.

일측One side 상부슬래브 시공공정 -  Upper Slab Construction Process- S20S20

상기한 공정(S10)을 거쳐 CIP구근(200)의 설치 시공이 완료되면 도 25와 같은 도로 단면의 구획이 분리되게 되는데, 본 공정은 이와 같은 상태에서 CIP구근(200)에 의해 구획되어지는 전체 폭원을 기준으로 3등분되는 중 어느 한측을 먼저 상부슬래브를 형성하기 위한 공정으로 이해될 것이다.When the installation of the CIP bulb 200 is completed through the above-described process (S10), the section of the road section as shown in FIG. 25 is separated, and in this state, the whole compartment is divided by the CIP bulb 200 in this state. It will be understood that either side of the third divided by the width source as a process for forming the upper slab first.

이를 위해서 도 26에서 보는 바와 같이 상부슬래브 전체 폭원중 1/3되는 위치 중앙부(전술한 바와 같이 CIP구근으로 이루어지는 벽체 중 중앙을 나누는 전체 부분을 중앙부로 명명하고 이를 도면에서 230 으로 표기하며, 상기 CIP구근에 의해 형성되는 기둥 타입도 포함한다)(230) 인근의 어느 일측 도로부분을 굴착하여 아스콘층과 흙을 걷어내게 된다.To this end, as shown in FIG. 26, the center portion of the upper half of the entire width source of the upper slab (as described above, the entire portion dividing the center of the wall made of CIP bulbs is named as the central portion, and this is denoted by 230 in the drawing). It also includes a pillar type formed by the bulb) (230) to excavate any one side of the road portion to remove the ascon layer and soil.

이때, H-말뚝 흙막이 시설로 제4 실시 예에서 적용되고 있는 콘크리트 PC1토류판(204)을 제작하여 설치하는 것으로 하였다.At this time, it is assumed that the concrete PC1 earth plate 204, which is applied in the fourth embodiment, is installed and installed as the H-pile soiling facility.

이와 같이 일정 깊이 터파기 공사를 진행 한 다음에 그 터파기면으로 바닥고르기 콘크리트와 거푸집을 시설한 후 PC구조의 상부슬래브를 시설한다.In this way, after the excavation work is carried out to a certain depth, the flooring concrete and formwork are installed on the excavation surface, and then the upper slab of the PC structure is installed.

이때, 코너부 보강재(260)를 연결하기 위한 앙카볼트를 미리 구성하도록 하는 것이 좋다. 이것은 코너부 보강재(260)를 설치할 때 즉시 설치가 용이하도록 하기 위함이다.At this time, the anchor bolt for connecting the corner reinforcing material 260 may be configured in advance. This is to facilitate the installation immediately when installing the corner reinforcement 260.

본 발명에서 PC구조 상부슬래브는 도 26 내지 도 28 에서 보는 바와 같이 전체 폭원을 3등분으로 각각 구분되며 순차적으로 PC구조 상부슬래브를 시설하게 되는데, 본 발명의 실시 이해를 위해 도면상(도 26) 보았을 때 우측의 상부슬래브를 일측PC구조 상부슬래브라 명명하고 도면부호 240으로 표기하였으며, 이와 대향되는 측의 슬래브를 타측 PC구조 상부슬래브로 명명하고 도면부호 240‘으로 표기하며 중앙측의 슬래브를 중앙측 PC구조 상부슬래브로 명명하고 도면부호 250으로 표기하여 구분하였다.In the present invention, the upper structure of the PC structure slab as shown in Figures 26 to 28 are divided into three equally each of the total width source and sequentially equipped with the upper structure of the PC structure, for the purpose of understanding the embodiment of the present invention (Fig. 26) When viewed, the upper slab on the right side is named the upper slab of one side of the PC structure and denoted by reference numeral 240. The slab on the opposite side is named the upper slab of the other side of the PC structure and denoted by the reference numeral 240 'and the center slab is centered. The side PC structure was named upper slab and marked 250.

이때 일측 PC구조 상부슬래브(240)의 철근은 이웃과 접하는 중앙측 PC구조 상부슬래브(250)와의 철근 연결을 위하여 한곳에서 이음치 않도록 지그재그로 배치 이음을 할 수 있도록 하고 일측 PC구조 상부슬래브(240)의 시공 후에는 방수재와 보호몰탈을 시공한다. At this time, the reinforcing bar of one side PC structure upper slab 240 is arranged to be connected in a zigzag manner so as not to be connected at one place for connecting the reinforcement with the center side PC structure upper slab 250 which is in contact with the neighbor, and the one side PC structure upper slab 240 After the construction of), waterproofing material and protective mortar should be installed.

이와 같이 일측 PC구조 상부슬래브(240)를 시설한 후에는 후술하게 되는 타측 PC구조 상부슬래브(240‘)를 시설하기 위한 터파기 시공(S30)이 이루어지는데 그 전에 교통의 흐름을 방해하지 않기 위해 일측 PC구조 상부슬래브(240)의 표면을 복토하게 되는 복토공정을 거쳐야 한다.In this way, after the one side PC structure upper slab 240 is installed, the trench construction (S30) for installing the other side PC structure upper slab 240 ', which will be described later, is made so as not to disturb the flow of traffic before. One side of the PC structure upper slab 240 has to go through a cover process to cover the surface.

한편, 복토시에는 일측 PC구조 상부슬래브(240)와 타측 PC구조 상부슬래브(240‘)의 지그재그 방식의 철근이음을 위하여 별도의 흙막이 시설을 하면서 복토를 하게 되는데 별도의 흙막이 시설에 대해서는 상기 제1실시 예(도 17 예시)와 같은 방법으로 시공하므로 상세 설명은 제1실시 예를 참조한다.On the other hand, in the case of covering the soil to cover the zigzag reinforcement of the one side PC structure upper slab 240 and the other side PC structure upper slab 240 'while the soil covering facility to cover the first earthquake facility for the first Since construction is performed in the same manner as in the embodiment (illustrated in FIG. 17), the first embodiment will be described in detail.

한편, 일측 PC구조 상부슬래브(240)의 시공에 있어서는 상기와 달리 도로의 사정에 의하여 터파기 시공방법을 중앙부를 기준으로 일측과 타측의 양측으로 구분되는 1/2의 시공방법과 같이 시공할 수 있다.
On the other hand, in the construction of the one-side PC structure upper slab 240, unlike the above, it is possible to construct the trench construction method as the construction method of 1/2 divided into one side and the other side on the basis of the center by the circumstances of the road. have.

타측The other side 상부 슬래브 시공공정 -  Upper Slab Construction Process- S30S30

본 공정은 상기한 일측 상부슬래브 시공공정(S20)에 의해 일측 PC구조 상부슬래브(240)를 타설한 후, 그 일측 PC구조 상부슬래브(240) 상면을 복토하여 교통의 흐름이 방해되지 않도록 한 다음, 타측 즉 일측 PC구조 상부슬래브(240)와 대향되는 측(도 27) 에서 보았을 때 왼쪽의 상부슬래브(타측 PC구조 상부슬래브-240‘)를 타설하기 위해 터파기 시공을 하는 공정을 의미한다.This process, after pouring the one-side PC structure upper slab 240 by the above-described one side upper slab construction process (S20), and covers the upper surface of the one-side PC structure upper slab 240 so that the flow of traffic is not disturbed. When viewed from the other side, that is, the side facing the one side PC structure upper slab 240 (Fig. 27) refers to the process of dig construction to cast the upper upper slab (the other side PC structure upper slab-240 ').

이와 같이 타측 PC구조 상부슬래브(240‘)를 시설하기 위해 그 주변을 터파기 시공한 다음 도 27에서와 같이 타측 PC구조 상부슬래브(240’)를 시설하여 지하차도를 구성하기 위한 상측으로의 각 PC구조 상부슬래브(240,240‘)의 시설 작업을 완료할 수 있으며, 복토하는 공정이라든가 H-말뚝 박기와 터파기 및 토류판 설치 시공방법은 일측 PC구조 상부슬래브(240)의 방법과 같다.In this way, the periphery of the periphery of the other PC structure upper slab 240 'is installed, and then the other side PC structure upper slab 240' as shown in FIG. The facility work of the PC structure upper slabs 240 and 240 'can be completed, and the method of covering the soil or installing the H-piling and digging and earth plate is the same as the method of the one side PC structure upper slab 240.

한편, 타측 PC구조 상부슬래브(240‘)의 철근은 이웃과 접하는 중앙측 PC구조 상부슬래브(250)와의 철근 연결을 위하여 한곳에서 이음치 않도록 지그재그로 배치 이음을 할 수 있도록 하고 타측 PC구조 상부슬래브(240’)의 시공 후에는 방수재와 보호몰탈을 시공한다.
On the other hand, the reinforcing bars of the other PC structure upper slab 240 'allows the joints to be arranged in a zigzag manner so that the bars of the other PC structure upper slab 240 are connected to the neighboring PC structure upper slab 250 so as not to be connected at one place. After construction of 240 ', waterproofing material and protective mortar should be applied.

중앙측Center 상부슬래브 시공공정 -  Upper Slab Construction Process- S40S40

상기한 일측 및 타측 상부슬래브 시공공정(S20,S30)의 설치시공이 완료되면 도 28에서 보듯이 중앙측 상면 도로 부분을 굴착하여 아스콘층과 흙을 걷어내게 된다. When the installation of the one side and the other upper slab construction process (S20, S30) is completed, as shown in Figure 28 to excavate the central side of the upper road portion to remove the ascon layer and soil.

이처럼 중앙측을 터파기 할 때는 일측 및 타측 상부슬래브 시공공정(S20,S30)시 이미 설치한 제1실시예(도 17)의 H말뚝(90)과 앵커체(91)가 연결되어 있는 흙막이 시설이 있으므로 별도의 흙막이 시설이 없이 터파기가 가능하다. As such, when digging the center side, an earth block facility in which the H pile 90 and the anchor body 91 of the first embodiment (FIG. 17) already installed during one side and the other upper slab construction process (S20, S30) are connected. Because of this, it is possible to dig without a separate earthen facility.

이와같이 일정깊이 터파기 공사를 진행 한 다음에 그 터파기면으로 바닥고르기 콘크리트와 거푸집을 시설한 후 중앙측 PC구조 상부슬래브(250)를 시설한다. 이때 상부슬래브의 철근은 일측 및 타측에서 이미 지그재그로 배열된 상태로 연결하고 2차 콘크리트를 타설하게 되는데, 타설 후에는 방수재와 보호몰탈을 시공한다. In this way, after proceeding the trench work in a certain depth, and then install the flooring concrete and formwork to the trench surface, and then install the upper slab 250 of the central PC structure. At this time, the reinforcing bar of the upper slab is already arranged in a zigzag state on one side and the other side, and the secondary concrete is poured. After pouring, the waterproofing material and the protective mortar are constructed.

이와 같이 중앙측 PC구조 상부슬래브(250)를 시설한 후에는 어느 일측 및 타측 PC구조 상부슬래브(240,240‘) 시공에 있어서 설치되었던 H-말뚝(90)을 뽑기 위한 볼트를 해제하는 과정과 함께 되메우기를 하면서 H-말뚝(90)을 인발하게 된다.After installing the central PC structure upper slab 250 as described above, the bolts for pulling the H-pile 90 which were installed in the construction of any one side and the other PC structure upper slab 240 and 240 'are backfilled. While drawing the H-pile 90.

한편, 1/2 시공일 경우에는 중앙부에서 철근이음을 하여야 하므로 부모멘트로 인한 부담이 될 수 있어 콘크리트 두께를 10㎝ 정도 두껍게 하여야 한다. 이는 부모멘트의 크기를 저감시키기 위함이다.
On the other hand, in the case of 1/2 construction, the reinforcing bar should be made in the center part, so it may be a burden due to the parent's cement. This is to reduce the size of the parent.

코너부Corner portion 보강 및  Reinforcement and 어스앙카Earthanka 시공공정 -  Construction Process- S50S50

본 공정은 상기한 각 PC구조 상부슬래브(240,240‘)의 시설작업을 완료한 후 PC구조 상부슬래브(240,240’)나 내벽체(280,280‘)의 지간을 짧게 유도하기 위하여 코너부 보강을 위한 사보강재(260) 및 어스앙카를 시설하는 시공공정으로 도 29와 같은 방법으로 시공하게 되는데 CIP구근 시공공정(S10)에서는 제1실시 예와 같이 사전에 사보강재(260) 설치를 위한 앙카볼트를 매입하여 두고 PC구조 상부슬래브를 제작할 시에도 미리 앙카볼트를 매입한 상태로 제작하여 코너부 일부만의 굴착으로 일정간격 사보강재(260)을 설치하는 것이다.This process, after completing the installation work of each of the above PC structure upper slab (240,240 '), the stiffening steel for corner reinforcement to induce a short interval between the PC structure upper slab 240,240' or the inner wall (280,280 ') The construction process for installing the ground anchors (260) and earth anchors are carried out in the same manner as in FIG. 29. In the CIP bulb construction process (S10), as in the first embodiment, an anchor bolt for installing the stiffener steel 260 is purchased in advance. Even when manufacturing the upper slab of the PC structure, the anchor bolts are manufactured in a state of purchase in advance to install only a certain interval of stiffener 260 by excavation of only a corner portion.

이와같이 설치된 사보강재(260)로 인하여 상부슬래브와 CIP구근(200)의 지간이 짧아져 부재력이 작아지므로 한층 안전성이 유지되는 것이며, 내벽체(280,280‘)에서 사보강재(260)연단과 최종 굴착면 사이의 길이를 줄이기 위한 방편으로 어스앙카를 시설한다. 이러한 어스앙카의 시설은 내벽체(280,280‘)의 부재력이 작아지도록 함과 아울러 근입장의 길이도 작게 할 수 있어 경제적 측면에서 유리하다.Since the interval between the upper slab and the CIP bulb 200 is shortened due to the installed sabot steel 260, the member force decreases, and thus the safety is further maintained, and the end surface and the final drilling surface of the sabor steel 260 in the inner wall 280 and 280 '. Earth anchors are used to reduce the length of the bridge. The facility of Earth Anca is advantageous in terms of economical ability to reduce the member force of the inner wall (280, 280 ') and to reduce the length of the entry.

한편, 도 30에서 보듯이 CIP구근(200)에 매입하여 긴장 정착하는 PC강연선(123)을 이용할 경우 어스앙카를 시설하지 않아도 같은 효과를 얻을 수 있으므로 본 발명을 사용하는 자가 선택적으로 적용할 수 있음은 당연하다 할 것이다.
On the other hand, as shown in Figure 30, when using the PC strand (123) to buy the tension in the CIP bulb 200, the same effect can be obtained even without the earth anchor can be applied by the person using the present invention selectively Will be taken for granted.

양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정 - Reinforcement work of both lower slab and central wall or column- S60S60

본 공정은 전술한 코너부 보강 및 어스앙카 시공공정(S50)이 완료된 후, PC구조 하부슬래브(270,270’) 및 중앙부(230)를 시공하여 지하차도를 형성하기 위한 공정으로 제1실시예 (도 6a, b예시)와 같은 방법으로 시공하므로 상세 설명은 생략한다.
This process is a process for forming the underground roadway by constructing the PC slab lower slab (270 270 ′) and the central portion 230 after the above-described corner portion reinforcement and earth anchor construction process (S50) is completed (FIG. Since the construction is carried out in the same manner as 6a and b), detailed description thereof will be omitted.

양측 Both sides 내벽체Inner wall 시공공정 -  Construction Process- S70S70

하부슬래브 양측으로 일체로 수직상 연결되어 측벽(231)의 내측으로 타설되는 일부의 내벽체는 하부슬래브(270,270‘)에 연이은 어스앙카를 철거한 후 시공되어지며 잔여 내벽체(280“)는 상기의 일부의 내벽체(280,280’)가 양생되어진 후 코너부 보강재(260)를 철거하면서 시공되어진다. 그러나 잔여 내벽체(280“)가 양생될때 콘크리트 수축작용에 의하여 침강이 되어 상부슬래브(240,250,240‘)와 미세한 틈이 발생될 수 있는데, 이곳에 무수축몰탈(283)을 충진하여 완성하게 된다.
A part of the inner wall which is vertically connected to both sides of the lower slab and cast inward of the side wall 231 is constructed after removing the earth anchors connected to the lower slab 270 and 270 ', and the remaining inner wall 280' is A portion of the inner wall (280, 280 ') is cured and is constructed while removing the corner reinforcement (260). However, when the remaining inner wall (280 ″) is cured, it may be settled by the concrete contraction action to generate fine gaps with the upper slabs (240, 250, 240 '), which is completed by filling the non-shrink mortar (283).

마무리 시공공정 - Finishing Construction Process- S80S80

상기와 같은 공정이 완료되면, 지하차도 내부의 보도 및 전기시설, 타일과 아스콘 등을 시설하여 지하차도의 공정을 마무리한다.
When the above process is completed, the process of the underground driveway is completed by installing sidewalks and electric facilities, tiles and ascons inside the underground driveway.

이상과 같은 일련의 공정을 거쳐, CIP구근(200)을 이용한 지하차도를 시공하게 되는데 있어서, 도 33은 측벽(231)과 하부슬래브(270)의 각 철근(281)과 철근(271,272)의 연결 고정되는 상태를 나타내고 있으며 제1실시 예에서와 같은 방법으로 시공되므로 상세 설명은 제1실시 예를 참조한다.In the construction of the underground roadway using the CIP bulb 200 through a series of processes as described above, FIG. 33 shows the connection between the reinforcing bars 281 and the reinforcing bars 271 and 272 of the side wall 231 and the lower slab 270. It shows a fixed state and is constructed in the same manner as in the first embodiment, so the detailed description will be referred to the first embodiment.

도 34는 하부슬래브(270,270‘)와 중앙부(230)를 연결하는 상태를 나타내고 있으며 역시 제1실시 예에서와 같은 방법으로 시공되므로 상세 설명은 제1실시 예를 참조한다.34 shows a state in which the lower slab 270, 270 'and the central portion 230 are connected, and are also constructed in the same manner as in the first embodiment, so the detailed description will refer to the first embodiment.

도 35는 PC구조 상부슬래브(240,240‘)의 일단과 측벽(231)의 상단간을 고정 연결하기 위한 단면을 나타내는데, 도면에서 보듯이 어느 한측의 PC구조 상부슬래브(240)와 측벽(231)간의 고정 상태를 도시하고 있으며, PC구조 상부슬래브(240,240’)가 시설되어질 때 각 PC구조 상부슬래브(240,240‘)에 PVC파이프(244)에 의해 천공된 홀을 통하여 지중에 피복으로 감싸며 사전에 미리 압입한 철근(243,243')을 관통시킨 후 내벽체(280,280‘)의 철근(281,281’)과 연결 고정되도록 하였으며, 각각 측벽(231)을 이루는 CIP구근(200)에 매입되어 있는 철근(210,211)은 PC구조 상부슬래브(240,240‘)에 미리 매입된 PVC파이프(244)에 끼워지며 철근(242,242’)과 가스압접으로 고정시키고 2차 콘크리트를 타설하여 마감토록 한다.FIG. 35 shows a cross section for fixedly connecting the upper end of the sidewall 231 with one end of the upper slab 240 and 240 'of the PC structure, as shown in the figure, between the upper slab 240 and the sidewall 231 of the PC structure on either side. When the PC structure upper slab 240,240 'is installed, it is wrapped in the ground through the hole drilled by the PVC pipe 244 in each PC structure upper slab 240,240' and press-fitted in advance. After passing through one of the reinforcing bars 243 and 243 ', the inner walls 280 and 280' were connected to the reinforcing bars 281 and 281 '. It is fitted to the PVC pipe 244 pre-buried in the structural upper slab (240, 240 ') and fixed by reinforcing bars (242,242') and gas welding, and the secondary concrete is poured to finish.

아울러, 상기한 내벽체(280)의 철근(281,281‘)과 교차 배치되는 배력철근과 측벽(231)을 이루는 CIP구근(200)에 매입되는 철근(210,211)중 내벽체(280,280‘)에 근접하는 철근(211)에 가로방향으로 띠철근(220)에 접하여 배치된 배력철근을 연결하기 위한 연결철근(282)이 상하로 각각 다수개 등간격으로 이격시키며 구비되어야 한다. In addition, close to the inner wall (280, 280 ') of the reinforcing bars (210, 211) to be buried in the reinforcement reinforcing bars and the side wall (231) forming the CIP bulb 200 that intersects with the reinforcing bars (281, 281') of the inner wall (280). Connection reinforcing bars 282 for connecting the reinforcing bars arranged in contact with the strip reinforcing bars 220 in the transverse direction to the reinforcing bars 211 should be provided with a plurality of equal intervals spaced apart.

이러한 연결구조는 지하도로의 좌우 상단측에 동일하게 적용될 것이다.This connection structure will be equally applied to the upper left and right sides of the underground road.

도 36은 도면에서 보듯이 1/3 시공순서에서 보여지며 각 PC구조 상부슬래브(240,240‘/250) 철근이 한곳에서 연결되지 않고 지그재그로 연결 결합되어야 한다.36 is shown in the 1/3 construction sequence, each PC structure upper slab (240, 240 '/ 250) reinforcing bar should be connected in a zigzag connection without connecting in one place.

즉, 일측 및 중앙측 PC구조 상부슬래브(240,250) 내부에 매입되는 각각의 철근(241,251 / 242,252)이 연결되어야 하며 타측 및 중앙측 PC구조 상부슬래브(240‘,250) 내부에 매입되는 각각의 철근(241’,251 / 242‘,252)이 연결되어야 하는 것이다. 이때 상기에서 설명하였듯이 연결되는 각각의 철근은 상호 지기재그로 연결토록 한 후 타설토록 함이 중요하다.That is, each of the reinforcing bars 241, 251/242, 252 to be embedded in one side and the center side PC structure upper slab 240, 250 should be connected, and each of the reinforcing bars embedded in the other side and center side PC structure upper slab 240 ', 250. (241 ', 251/242', 252) should be connected. At this time, as described above, it is important that each reinforcing bar is connected to each other and then placed in place.

도 37은 1/2 시공순서의 도면에서 보듯이 각 PC구조 상부슬래브(240,240’) 철근과 CIP구근(200)에서의 철근(232)이 결합되어야 한다.FIG. 37 shows that the upper slab 240, 240 'reinforcing bars and the reinforcing bars 232 in the CIP bulb 200 are combined as shown in the 1/2 construction sequence.

즉, 각 PC구조 상부슬래브(240,250) 내부에 매입되는 각각의 철근(241,242 / 241‘,242‘)을 CIP구근(200)의 중앙부 철근(232)과 서로 고정 연결하여야 하는데, 도면에서 보듯이 중앙부(230)를 이루는 CIP구근(200)의 상단측에 일측PC구조 상부슬래브(240)를 설치한다. 이때 CIP구근(200)의 철근(232)이 일측PC구조 상부슬래브(240)에 미리 설치한 PVC파이프를 관통하도록 하는데, 일측PC구조 상부슬래브(240)의 철근이 타측의 PC구조 상부슬래브(240’)의 철근과 연결을 위하여 일정길이의 철근(241, 242)을 타설전에 지그재그로 배열하여 한곳에서만 연결이 되지 않도록 조치하여 타측 PC구조 상부슬래브(240’)의 타측철근(241‘, 242‘)의 단부와 커플러 또는 가스압접 등의 방법으로 연결 고정한 후 2차 콘크리트를 타설하여 각 PC구조 상부슬래브(240,240’)와 중앙부(230)를 견고하게 연결한다.That is, each of the reinforcing bars 241,242 / 241 'and 242' embedded in the upper slab 240 and 250 of each PC structure should be fixedly connected to the central reinforcing bars 232 of the CIP bulb 200, as shown in the drawing. One side PC structure upper slab 240 is installed on the upper side of the CIP bulb 200 forming 230. At this time, the reinforcing bar 232 of the CIP bulb 200 passes through the PVC pipe pre-installed on one side PC structure upper slab 240, and the reinforcement of one side PC structure upper slab 240 is the other side PC structure upper slab 240 In order to connect with the reinforcing bar, arrange the reinforcing bars (241, 242) of certain length in zigzag before placing them so that they are not connected at one place, so that the other bars (241 ', 242') of the upper PC slab (240 ') of the other PC structure After fixing the end and the connection by the method of coupler or gas welding, etc., the second concrete is poured to firmly connect the upper slabs 240 and 240 'and the central portion 230 of each PC structure.

한편, 각 PC구조 상부슬래브(240,250,240’)가 배치되는 가로방향 연결부는 종방향 배력철근을 가스압접 또는 Coupler으로 연결한 후 콘크리트를 타설하는 것으로 구성되고 있다.On the other hand, the horizontal connection portion in which each PC structure upper slab 240, 250, 240 'is arranged is connected to the longitudinal reinforcing reinforcement by gas pressure welding or coupler is constructed by pouring concrete.

한편, 각 PC구조 상부슬래브(240‘,250)는 상호 어긋나게 배치하여 연결하여야 한다.On the other hand, each PC structure upper slab (240 ', 250) should be connected to each other arranged displaced.

도 32에서의 "E"부분과 단면A-A, 단면B-B는 제1실시 예(도15, 도16 예시)와 같은 방법으로 시공하므로 상세 설명은 제1실시 예를 참조한다.The section "E", cross section A-A, and cross section B-B in Fig. 32 are constructed in the same manner as in the first embodiment (Figs. 15 and 16), so that the detailed description will be referred to the first embodiment.

한편, 도면부호 S는 하부슬래브(240)의 하면측에 구성되는 보호몰탈과 방수시트를 포함하는 보호몰탈 방수시트층을 가르킨다.Meanwhile, reference numeral S denotes a protective mortar waterproof sheet layer including a protective mortar and a waterproof sheet formed on the lower side of the lower slab 240.

본 발명의 방수방법은 제1실시 예에서의 방법을 그대로 적용하고 있으므로 상세 설명은 제1실시 예를 참조한다.Since the waterproof method of the present invention applies the method in the first embodiment as it is, the detailed description will be referred to the first embodiment.

한편 지하차도의 길이가 길어질 경우 제1실시예의 도면 도 23에서와 같이 일정간격의 길이마다 재료투입구를 시설하여야 하는데, 그에 대한 상세한 사항은 제1실시 예에서와 같은 방법으로 설치하여야 하므로 제1실시 예에서의 설명의 내용을 참조하기로 한다.
On the other hand, when the length of the underground driveway is long, as shown in Figure 23 of the first embodiment, the material inlet should be provided at a predetermined interval, and the details thereof should be installed in the same manner as in the first embodiment. Reference is made to the description in the examples.

제 3 Third 실시예Example

양 측벽의 PC벽체 및 사각파일과 중앙부 벽체 또는 기둥의 PC 사각파일 및 CIP구근을 시공 처리하는, CIP구근 시공공정(S10)과, 일측 상부슬래브 시공공정(S20)과, 타측 상부슬래브 시공공정(S30)과, 중앙측 상부슬래브 시공공정(S40)과, 코너부 보강 시공공정(S50-1), 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정(S60)과, 양측 내벽체 시공공정(S70)과, 마무리 시공공정(S80)으로 지하차도의 시공이 이루어진다.CIP bulb construction process (S10), one side upper slab construction process (S20), and the other side upper slab construction process for constructing and processing PC wall and square piles of both side walls and PC square piles and CIP bulbs of central wall or column ( S30), the central upper slab construction process (S40), the corner reinforcement construction process (S50-1), both the lower slab and the central wall or column reinforcement construction process (S60), and both inner wall construction process (S70) And, the construction of the underground roadway is made by the finishing construction process (S80).

각 공정별로 나누어 본 발명의 공정 흐름과 이에 따른 각 구성을 설명한다.
The process flow of the present invention and each configuration according thereto will be described by dividing each process.

CIPCIP 구근 시공공정 -  Bulb Construction Process- S10S10

본 공정은 양 측벽 단위PC 벽체 및 단위 PC 사각화일과 중앙부 벽체 또는 기둥의 단위 사각 파일 및 CIP구근을 시설하기 위한 시공공정으로, 지하차도를 건설할 위치의 벽체에 해당되는 측벽과 중앙부의 벽체 또는 기둥을 형성하기 위한 공정이다.This process is a construction process to install unit PC piles and unit PC square files and unit square piles and CIP bulbs of central wall or column. It is a process for forming pillars.

이를 위해서 도면에서 보는 바와 같이 지하차도를 구성하기 위한 지역 범위내에서 중앙을 분리하기 위한 중앙부와 양측 측면부에 각각 벽체 즉 측벽이 형성되도록 PC 사각파일벽체(302)와 PC벽체(300') 또는 PC 사각파일벽체(301)를 형성한다.To this end, as shown in the drawing, the PC square pile wall 302 and the PC wall 300 'or PC such that walls or sidewalls are formed at the center portion and both side surface portions to separate the center within the region range for constructing the underground roadway, respectively. The square pile wall 301 is formed.

여기서 상기 중앙부는 PC 사각파일벽체(302) 또는 CIP구근(300)을 이용하여 벽체로 형성할 수도 있고, 기둥식 예컨데 중간 중간이 끊겨지는 형태의 기둥 타입으로 CIP구근을 형성할 수 있는바, 현장 조건 및 설계 등에 의해 가변 될 수 있으며, 이러한 변경은 본 발명을 사용하는 자가 선택적으로 적용할 수 있음은 당연하다 할 것이다.Here, the central portion may be formed as a wall using the PC square pile wall 302 or the CIP bulb 300, a column type, for example, to form a CIP bulb in the form of a column of the middle is broken bar, the site It can be varied depending on the conditions and design, it will be obvious that such a change can be selectively applied by those using the present invention.

상기한 양측 측면부에서의 PC벽체(300')는 단위PC벽체(300'a)가 조립되어 구성되는 것인바 도 48 에서 보는 바와 같이 다수의 주철근(310,311)이 일정규격의 직사각형으로 배열 배치되고 그 주철근(310,311)과 교차하는 배력철근을 등간격으로 이격시키며 스터럽으로 묶어 주철근과 배력철근이 하나로 조합되어 콘크리트가 타설 양생되어 단위PC벽체(300'a)가 건조되는 것이다.The PC wall 300 'at both side portions is composed of unit PC walls 300'a. As shown in FIG. 48, a plurality of cast iron bars 310 and 311 are arranged in a rectangular shape to have a predetermined size. The reinforcing bars crossing the main reinforcing bars 310 and 311 are spaced at equal intervals and tied together with a stirrup. The main reinforcing bars and the reinforcing bars are combined into one and the concrete is poured and the unit PC wall 300'a is dried.

한편, 도 48에서 보듯이 단위PC벽체(300'a)는 연결부에 2개의 돌출 L형강(309)을 매입한 상태로 건조되는 것이며 인접한 단위PC벽체(300'a)는 연결부에 2개의 매입 L형강과 철판(309’)을 매입한 상태로 건조되어 상호 끼워 연결이 가능하도록 구성되어 있다.On the other hand, as shown in FIG. 48, the unit PC wall 300'a is dried with two protruding L-shaped steels 309 embedded in the connecting portion, and the adjacent unit PC wall 300'a has two embedded L in the connecting portion. It is configured to be connected to each other by being dried in a state in which the shaped steel and the iron plate 309 'are embedded.

이러한 단위PC벽체(300'a)는 D-Wall과 같은 대형장비에 의하여 적정한 폭으로 굴착되어진 폭원 내부로 투입하여 결합되는 것이며 이러한 단위PC벽체(300'a)의 다수가 종방향(시종점 방향)의 주열식으로 조립되면 PC벽체(300)가 완성되는 것이다.The unit PC wall 300'a is coupled to the inside of the width source excavated with a suitable width by a large equipment such as D-Wall, and many of these unit PC walls 300'a are longitudinally (the starting point direction). When assembled in a columnar manner of the PC wall 300 is completed.

또한, 상기한 PC 사각파일벽체(301,302) 또한 단위PC 사각파일벽체(301a,302a)가 조립되어 구성되는 것인바 도 56, 57에서 보는 바와 같이 다수의 주철근(310,311)이 일정규격의 정사각형으로 배열 배치되고 그 주철근(310,332)을 감싸는 띠철근(320)을 등간격으로 이격시키며 주철근과 띠철근이 하나로 조합되어 콘크리트가 타설 양생되어 단위PC 사각파일벽체(301a,302a)가 건조되는데, 도 48에서 보듯이 단위PC벽체(300'a)와 같은 연결구조를 갖추고 있는 것이다.In addition, the PC square pile walls (301, 302) is also composed of the unit PC square pile walls (301a, 302a) bar as shown in Figures 56, 57 a plurality of cast steel bars (310,311) arranged in a square of a certain standard It is disposed and spaced apart the strip reinforcing bars 320 surrounding the main reinforcing bars (310,332) at equal intervals, the main reinforcing bar and the reinforcing bars are combined into one, the concrete is poured and curing unit PC square pile walls (301a, 302a) is dried, in Figure 48 As shown, it has the same connection structure as the unit PC wall 300'a.

이러한 단위PC 사각파일벽체(301a,302a)는 SCW, DWM과 같은 오거장비에 의하여 적정한 폭으로 굴착되어진 폭원 내부로 투입되는 것이며 이러한 단위PC 사각파일벽체(301a,302a)의 다수가 종방향(시종점 방향)의 주열식으로 조립되면 PC 사각파일벽체(301,302)가 완성되는 것이다.The unit PC square pile walls 301a and 302a are introduced into a width source excavated with a proper width by augers such as SCW and DWM. Many of the unit PC square pile walls 301a and 302a are longitudinally When assembled in a columnar manner of the dot direction), the PC square pile walls (301, 302) is completed.

한편, 단위PC 사각파일벽체(301a)를 건조할 때 철근망태의 일편측(벽체가 형성되는 내측을 지칭하고 이하 일편측이라 명명한다.)에는 도드락문양 거푸집(322)과 쫄대(303)를 대어 띠철근에 묶인 상태가 되도록 한다.On the other hand, when drying the unit PC square pile wall (301a), on one side (referred to as the inner side where the wall is formed and referred to as one side side) of the reinforcement mesh, the dodak pattern formwork 322 and the chock 303 Be sure to tie it up to the bars.

이는 내벽체(380,380‘) 철근(381)의 가로방향의 배력철근과 PC 사각파일벽체(301)의 띠철근에 이어 배치한 배력철근의 상호 연결이 용이하게 하기 위해서이다.This is to facilitate the interconnection of the reinforcing bars in the transverse direction of the inner walls 380 and 380 'and the reinforcing bars arranged after the band bars of the PC square pile wall 301.

또한 철근망태 일편측 스터럽 철근에 접하여 2개의 PC강연선(323)을 배치하되 단위PC 사각파일벽체(301a) 일정길이에만 배치하는데, 철근망태 일편측 양측 스터럽철근에 접하는 2개의 PC강연선(323)의 역할은 상부슬래브 최외측 우각부에 설치한 코너부 보강재와 최종 굴착선까지의 사이에 어스앙카(210)를 시설하지 않아도 외부작용 부재력에 대처할 수 있도록 단위PC 사각파일벽체(301a)의 내하력을 증가시키기 위한 구조로서 매 단위PC 사각파일벽체(301a)마다 배치한다.In addition, two PC strands 323 are arranged in contact with the one side side stirrup reinforcing bar, but only a certain length of the unit PC square pile wall 301a. The role is to increase the load capacity of the unit PC square pile wall 301a so as to cope with the external action member force without installing the earth anchor 210 between the corner reinforcement installed on the outermost right side of the upper slab and the final digging line. As a structure to make it possible, it arrange | positions for every unit PC square pile wall body 301a.

한편, PC강연선(323)의 긴장정착 시기는 상부슬래브의 철근 조립이 완료된 시기에 상부슬래브에서 정착시키므로 상부슬래브와 CIP간을 더욱 긴밀히 응집시키는 역할을 겸하고 있으며 우각부 부모멘트를 저감시키는 효과도 함께 거둘 수 있다.On the other hand, the tensioning time of the PC strand 323 is settled in the upper slab at the time when the rebar assembly of the upper slab is completed, thereby acting to more tightly aggregate the upper slab and CIP, and also reduce the right angle parent You can reap.

한편, 중앙부에서의 PC 사각파일벽체(302)는 도 57에서 보듯이 양측면부에서의 PC 사각파일벽체(301)와는 달리 내벽체(380,380‘)와 결합되지 않기 때문에 도드락문양 거푸집(322)과 쫄대(303)가 없는 상태에서 양생 건조된 단위PC 사각파일벽체(302a)를 조립하는 방식으로 시공하고 최종으로 종방향(시종점 방향)으로 다수의 PC강연선(324)을 이용하여 긴장 정착하므로 일체화 벽체를 구성토록 한다.On the other hand, since the PC square pile wall 302 in the center is not coupled to the inner wall (380, 380 '), unlike the PC square pile wall 301 at both sides as shown in Figure 57 and the Dodlock pattern formwork 322 Construct the unit PC square pile wall 302a cured and dried in the absence of the stool 303, and finally integrate tension by using a plurality of PC strands 324 in the longitudinal direction (the starting point direction). Make up the wall.

단위벽체(302a)는 지하차도를 이루기 위한 영역에서 중앙부 벽체 또는 기둥(이하 이를 통틀어 중앙부라 명명한다)에 다수열 매입하고, 단위벽체(300'a, 301a)는 그 중앙부를 중심으로 좌우 양측으로 각각 이격 되는 거리의 위치에서 지하에 수직상 일정 간격을 벌리면서 다수열 매입되어 측벽 및 중앙부를 형성하게 되는데. 이러한 단위벽체(302a, 300'a, 301a)는 토사층에서만 가능하고 암반구간에서는 불가능한 제약조건이 따른다. 이것은 지반을 굴착하는 장비가 암반을 천공할 수 없기 때문인데 이럴 경우 2.0m∼2,5m마다 암반측까지 천공이 가능한 T4 장비를 이용하여 단위벽체(301a,302a)를 형성하고 그 사이는 토사층까지만 단위벽체(302a, 300'a, 301a)를 형성한 다음 상부슬래브(340.350)를 시공하고 암반구간까지 내부굴착하여 단위벽체(302a, 300'a, 301a) 받침앵커를 시설하고 내부굴착을 계속하되 토사층까지만 시설된 단위벽체(302a, 300'a, 301a) 하단에서 하부슬래브 버림콘크리트 하단까지 암반을 절취하여 단위벽체(302a, 300'a, 301a)의 철근을 이어내리고 분말방수제가 혼합된 콘크리트를 타설하면 견고한 내벽체(380,380‘)가 형성된다.The unit walls 302a are embedded in a plurality of rows in a central wall or column (hereinafter collectively referred to as a central portion) in an area for forming an underground roadway, and the unit walls 300'a and 301a are moved to both left and right sides around the central portion thereof. They are embedded in a plurality of rows with a predetermined distance vertically spaced in the basement at a distance from each other to form side walls and a central portion. These unit walls 302a, 300'a, 301a are subject to constraints that are only possible in soil layers and impossible in rock sections. This is because the equipment that excavates the ground cannot penetrate the rock. In this case, unit walls 301a and 302a are formed by using T4 equipment that can be perforated to the rock side every 2.0m to 2,5m, and between the soil layers only. After forming the unit walls 302a, 300'a, 301a, construct the upper slab 340.350 and excavate it to the rock section to install the supporting anchors of the unit walls 302a, 300'a, 301a and continue the internal excavation. Cut the rock from the bottom of the unit walls (302a, 300'a, 301a) installed only to the soil layer to the bottom of the lower slab cast concrete to carry out the reinforcing bars of the unit walls (302a, 300'a, 301a) and mix the concrete with water repellent. When poured, solid inner walls 380 and 380 'are formed.

한편, 단위벽체(302a, 300'a, 301a)의 상단고는 굴착고의 높낮이에 따라 상호 달라질 수 있는데, 이를 해결하기 위하여 단위벽체(302a, 300'a, 301a)와 달아매기 벽체(305)를 결합한 상태에서 트렌치 및 오거장비로 굴착된 폭원 내측에 정렬하여 투입하여 결합하여야 한다. On the other hand, the top height of the unit walls (302a, 300'a, 301a) may be different depending on the height of the excavation height, in order to solve this unit wall (302a, 300'a, 301a) and the hanging wall 305 In the combined state, they are to be aligned and introduced inside the width source excavated with trenches and augers.

달아매기 벽체(305)는 콘크리트 제품으로 PC로 제작되어 달아매기 철근(312)과 결합시키는데, 상단에 거치용 H형강(313)을 가로방향으로 배치하여 가이드형강(314)에 안치하고 상부슬래브(340,350,340')와 벽체(302, 300, 301)를 연결할 때 이를 분리하는 것으로 한다. The hanging wall 305 is made of PC as a concrete product and is combined with the hanging reinforcing bar 312. The H-shaped steel 313 for mounting on the top is placed horizontally and placed in the guide steel 314 and the upper slab ( 340, 350, 340 'and the wall 302, 300, 301 is to be separated when connecting.

한편 단위벽체(300'a, 301a)와 달아매기 벽체(305)를 결합한 상태에서 트렌치 및 오거장비로 굴착된 폭원 내측에 투입이 완료된 후 굴착된 폭원 외측에는 되메우기를 하여 공극을 충진토록 한다.Meanwhile, the unit walls 300'a, 301a and the hanging wall 305 are combined to fill the voids by filling back the outside of the excavated width source after completion of the input into the excavated width source with the trench and auger equipment.

이렇듯 단위벽체(300'a, 301a)와 그 연결틈은 지수철판(306)을 이용하여 지수토록 하고 단위벽체(300'a, 301a) 각각의 외면은 제작시에 미리 액체방수제로 도포하여 유해물질로 인하여 부식이 되지 않도록 조치한다.
As such, the unit walls 300'a and 301a and their connection gaps are indexed using the index plate 306, and the outer surfaces of each of the unit walls 300'a and 301a are previously applied with a liquid waterproofing agent in preparation for harmful substances. Take measures to prevent corrosion.

일측One side 상부슬래브 시공공정 -  Upper Slab Construction Process- S20S20

상기한 공정인 CIP구근 시공공정(S10)을 거쳐 벽체(302, 300', 301)의 설치 시공이 완료되면 도 40 과 같은 도로 단면의 구획이 분리되게 되는데, 본 공정은 이와 같은 상태에서 벽체(302, 300', 301)에 의해 구획되어지는 전체 폭원을 기준으로 3등분되는 중 어느 한측을 먼저 상부슬래브를 형성하기 위한 공정으로 제1실시 예 (도 3 예시)와 같은 방법으로 일측 상부슬래브(340)를 시공하므로 상세 설명은 제1실시 예를 참조한다.
When the installation of the walls 302, 300 ′ and 301 is completed through the CIP bulb construction process (S10), the section of the road section as shown in FIG. 40 is separated. In this state, the wall ( One side upper slab in the same manner as in the first embodiment (FIG. 3) is a process for first forming an upper slab, which is divided into three parts based on the total width source partitioned by 302, 300 ', and 301. Since 340 is constructed, detailed description will be referred to the first embodiment.

타측The other side 상부슬래브 시공공정 -  Upper Slab Construction Process- S30S30

본 공정은 상기한 일측 상부슬래브 시공공정(S20)에 의해 일측상부슬래브(340)를 타설한 후, 그 일측상부슬래브(340) 상면을 복토하여 교통의 흐름이 방해되지 않도록 한 다음, 타측 즉 일측상부슬래브(340)와 대향되는 측(도 42) 에서 보았을 때 왼쪽)의 상부슬래브(타측상부슬래브-340‘)를 타설하기 위해 터파기 시공을 하는 공정을 의미는데, 제1실시예 (도 4 예시)와 같은 방법으로 시공하므로 상세 설명은 제1실시 예를 참조할 수 있다.
In this step, after one side upper slab 340 is poured by the above-described one side upper slab construction process (S20), the top surface of the one upper slab 340 is covered so that the flow of traffic is not disturbed, and then the other side, that is, one side Refers to a process of digging the upper slab (the other upper upper slab-340 ') on the side opposite to the upper slab 340 (FIG. 42), the first embodiment (FIG. 4). Since the construction is performed in the same manner as in the example), the detailed description may refer to the first embodiment.

중앙측Center 상부슬래브 시공공정 -  Upper Slab Construction Process- S40S40

상기한 일측 및 타측 상부슬래브 시공공정(S20,S30)의 설치시공이 완료되면 도 43에서 보듯이 중앙측 상면 도로 부분을 굴착하여 아스콘층과 흙을 걷어내게 된다. When the installation of the one side and the other upper slab construction process (S20, S30) is completed, as shown in Figure 43 to excavate the upper portion of the central side road to remove the ascon layer and soil.

이처럼 중앙측을 터파기 할 때는 일측 및 타측 상부슬래브 시공공정(S20,S30)시 이미 설치한 제1실시예(도 17)의 H말뚝(90)과 앵커체(91)가 연결되어 있는 흙막이 시설이 있으므로 별도의 흙막이 시설이 없이 터파기가 가능하다. As such, when digging the center side, an earth block facility in which the H pile 90 and the anchor body 91 of the first embodiment (FIG. 17) already installed during one side and the other upper slab construction process (S20, S30) are connected. Because of this, it is possible to dig without a separate earthen facility.

이와같이 일정깊이 터파기 공사를 진행 한 다음에 그 터파기면으로 바닥고르기 콘크리트와 거푸집을 시설한 후 중앙측 상부슬래브(350)를 시설한다. 이때 상부슬래브의 철근은 일측 및 타측에서 이미 지그재그로 배열된 상태로 연결하고 콘크리트를 타설하게 되는데, 타설 후에는 방수재와 보호몰탈을 시공한다.In this way, after proceeding to the excavation of a certain depth, and then install the flooring concrete and formwork to the trench surface, and then install the upper upper slab (350). At this time, the reinforcing bar of the upper slab is already connected in a zigzag state on one side and the other side, and the concrete is poured. After pouring, the waterproofing material and the protective mortar are constructed.

이와 같이 중앙측 PC구조 상부슬래브(350)를 시설한 후에는 어느 일측 및 타측 PC구조 상부슬래브(340,340‘) 시공에 있어서 설치되었던 H-말뚝(90)을 뽑기 위한 볼트를 해제하는 과정과 함께 되메우기를 하면서 H-말뚝(90)을 인발하게 된다.After installing the central PC structure upper slab 350 as described above, the bolts for pulling out the H-pile 90 which were installed in the construction of any one side and the other PC structure upper slab 340 and 340 'are backfilled together. While drawing the H-pile 90.

한편, 1/2 시공일 경우에는 중앙부에서 철근이음을 하여야 하므로 부모멘트로 인한 부담이 될 수 있어 콘크리트 두께를 10㎝ 정도 두껍게 하여야 한다. 이는 부모멘트의 크기를 저감시키기 위함이다.
On the other hand, in the case of 1/2 construction, the reinforcing bar should be made in the center part, so it may be a burden due to the parent's cement. This is to reduce the size of the parent.

코너부Corner portion 보강 시공공정 -  Reinforcement Construction Process- S50S50 -1-One

본 공정은 상기한 각 상부슬래브(340,350,340‘)의 타설 작업을 완료한 후 상부슬래브와 PC 사각파일벽체(301)가 결합되어 있어 부모멘트가 크게 작용되는 것을 저감시키기 위한 방법으로 상부슬래브(340,350,340‘)나 내벽체(380,380‘)의 지간을 짧게 유도하는 공정에 해당되며, 제1실시예 (도6A,B 예시)와 같은 방법으로 시공하므로 상세 설명은 제1실시 예를 참조한다.This process is the upper slab (340, 350, 340 ') after completing the above-mentioned casting work of the upper slab and the PC square pile wall 301 is coupled to the upper slab (340, 350, 340') as a method for reducing the large acts Or a shorter time between the inner walls 380 and 380 ', and is constructed in the same manner as the first embodiment (FIGS. 6A and B).

한편, 측벽이 PC벽체(300')로 구성될 경우 코너부 보강 시공공정(S50)은 하지 않는다.
On the other hand, when the side wall is composed of the PC wall (300 ') does not perform the corner reinforcement construction process (S50).

양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정 - Reinforcement work of both lower slab and central wall or column- S60S60

본 공정은 전술한 코너부 보강 시공공정(S50-1)이 완료된 후, 하부슬래브(370,370’) 및 중앙부(330)를 시공하여 지하차도를 형성하기 위한 공정이다.This process is a process for forming the underground roadway by constructing the lower slab (370 370 ') and the central portion 330 after the above-described corner reinforcement construction process (S50-1) is completed.

양측의 굴착된 공간에 버림콘크리트와 외부시트 방수층을 형성한 후 해당 굴착 부분의 측벽(331)과 그 하단으로 하부슬래브(370,370’)를 타설하게 된다.After forming the discarded concrete and the outer sheet waterproof layer in the excavated space on both sides, the lower slab (370,370 ') is poured into the side wall 331 and the bottom of the excavated portion.

여기서 상기 하부슬래브(370,370’)는 도 50, 도 51 / 도 58, 도 59에서 보는 바와 같이 지하차도의 바닥면에 타설되는 타설체를 의미하고, 측벽(331)의 내측에 접하는 헌치부까지 타설한다.Here, the lower slab 370, 370 'means a pour body that is poured on the bottom surface of the underground driveway, as shown in Figure 50, 51/58, 59, and even to the haunting portion in contact with the inner side of the side wall 331 do.

하부슬래브(370,370’)와 측벽(331)의 이음은 단위PC 사각파일벽체(301a) 제작시 미리 형성한 채움재 공간(307)의 철근과 가스압접을 하여 철근을 고정하고 하부슬래브(370,370’)와 중앙부(330)의 이음은 단위PC 사각파일벽체(302a) 제작시 미리 설치한 PVC파이프 천공홀(308)을 통하여 철근을 관통시키는 방법으로 한다.The joints of the lower slabs 370 and 370 'and the side walls 331 are gas-welded with the reinforcing bars of the filling material space 307, which is formed when the unit PC square pile wall 301a is manufactured, and the lower slabs are fixed with the lower slabs 370 and 370'. The joint of the central portion 330 is a method of penetrating the reinforcing bar through the PVC pipe hole 308 installed in advance when manufacturing the unit PC square pile wall 302a.

상기와 같이 양측의 공간을 굴착 시공한 후 하부슬래브(370,370’)의 타설공정이 완료되면, 중앙부(330)가 CIP구근(300)일 경우 좌우 양측에 배력철근을 대고 보강벽체(390)를 타설하여 완성된 형태의 중앙부(330)를 구성할 수 있고, PC 사각파일벽체(302)일 경우 단위PC 사각파일벽체(302a)를 조립하는 방식으로 시공하고 최종 종방향(시종점 방향)으로 다수의 PC강연선(324)을 이용하여 긴장 정착하므로 일체화 벽체를 구성토록 한다.After excavation and construction of the space on both sides as described above, when the casting process of the lower slab (370,370 ') is completed, when the central portion 330 is the CIP bulb 300, the reinforcing wall 390 is placed on the left and right sides. The central portion 330 of the completed form can be configured, and in the case of the PC square pile wall 302, the unit PC square pile wall 302a is constructed in a manner of assembling, and in the final longitudinal direction (the starting point direction) The tension is fixed using the PC strand 324 so as to form an integrated wall.

한편, 양측 내벽체(380,380‘)가 PC벽체(300')로 형성되었을 경우 추가보강 내벽체를 시설하지 않는다.
On the other hand, when both inner wall (380, 380 ') is formed of a PC wall (300') does not install additional reinforcing inner wall.

양측 Both sides 내벽체Inner wall 시공공정 -  Construction Process- S70S70

하부슬래브 양측으로 일체로 수직상 연결되어 측벽(331)의 내측으로 타설되는 일부의 내벽체(380,380‘)는 상기 공정(S60)이 완료된 후 시공되어지며 잔여 내벽체(380“)는 상기의 일부의 내벽체(380,380’)가 양생되어진 후 코너부 보강재(360)를 철거하면서 시공되어진다. Some of the inner walls 380 and 380 'which are integrally vertically connected to both sides of the lower slab and poured into the inner side of the side wall 331 are constructed after the process S60 is completed, and the remaining inner walls 380 " After the inner wall (380, 380 ') is cured, it is constructed while removing the corner reinforcement (360).

그러나 잔여 내벽체(380“)가 양생될때 콘크리트 수축작용에 의하여 침강이 되어 상부슬래브(340,350,340‘)와 미세한 틈이 발생될 수 있는데, 이곳에 무수축몰탈(383)을 충진하여 완성하게 된다.
However, when the remaining inner wall (380 ″) is cured, it may be settled by the concrete contraction action to generate fine gaps with the upper slabs (340, 350, 340 '), which is completed by filling the non-shrink mortar (383).

마무리 시공공정 - Finishing Construction Process- S80S80

상기와 같은 공정이 완료되면, 지하차도 내부의 보도 및 전기시설, 타일과 아스콘 등을 시설하여 지하차도의 공정을 마무리한다.
When the above process is completed, the process of the underground driveway is completed by installing sidewalks and electric facilities, tiles and ascons inside the underground driveway.

이상과 같은 일련의 공정을 거쳐, 벽체(302, 300', 301)을 이용한 지하차도를 시공하게 되는데, 전술한 바와 같이 벽체(302, 300', 301)를 이용하여 지하차도의 중앙부(330)와 그 중앙부(330)로부터 적정 간격 이격되며 이루어지는 측벽(331)을 형성한 다음에, 일측 및 타측, 중앙측 상부슬래브(340,340‘,350)를 각각 순차적으로 타설할 때, 도 53, 도 61과 같이 각 상부슬래브(340,340’,350) 철근과 중앙부(302)에서의 철근이 결합되어야 한다.Through the above-described series of steps, the underground roadway using the walls 302, 300 ′ and 301 is constructed. As described above, the central portion 330 of the underground roadway using the walls 302, 300 ′ and 301. And the sidewalls 331 formed at a predetermined interval from the central portion 330, and then sequentially pouring the one side, the other side, and the central side upper slabs 340, 340 ′, and 350, respectively, FIGS. 53 and 61. As described above, the bars of each of the upper slabs 340, 340 'and 350 and the bars of the center portion 302 should be combined.

즉, 각 상부슬래브(340,340‘) 내부에 매입되는 각각의 철근(341,342 / 341’,342‘)을 중앙부(350)의 중앙부 철근(351,352)과 서로 고정 연결하여야 한다.That is, each of the reinforcing bars (341,342 / 341 ', 342') embedded in each upper slab (340, 340 ') must be fixed to the center reinforcing bars (351, 352) of the central portion (350).

이를 위해서, 도 50, 도 58/ 도 51, 도 59 또한 제1실시 예(도9, 도10)에서와 같은 방법으로 시공하므로 상세 설명은 제1실시 예를 참조한다.To this end, FIGS. 50, 58/51, and 59 are also constructed in the same manner as in the first embodiment (FIGS. 9 and 10), so the detailed description will be referred to the first embodiment.

도 52, 도 60은 상부슬래브(340,340‘)의 일단과 측벽(331)의 상단간을 고정 연결하기 위한 단면을 나타내고 있는데, 측벽(331)이 제1실시 예에서는 CIP구근(300)으로 되어있는 것이 다를 뿐 상부슬래브(340,340’)와의 연결방법은 같아 상세 내용은 제1실시 예를 참조한다.52 and 60 show a cross section for fixedly connecting between one end of the upper slab 340 and 340 'and an upper end of the side wall 331. The side wall 331 is a CIP bulb 300 in the first embodiment. The connection method with the upper slabs 340 and 340 'is the same, but the details are referred to the first embodiment.

도 53, 도 61은 제1실시 예 (도12 예시)와 같은 방법으로 시공하므로 상세 설명은 제1실시 예를 참조한다.53 and 61 are constructed in the same manner as in the first embodiment (example of FIG. 12), so the detailed description will be referred to the first embodiment.

도 54, 도 62는 제1실시 예 (도13 예시)와 같은 방법으로 시공하므로 상세 설명은 제1실시 예를 참조한다.54 and 62 are constructed in the same manner as in the first embodiment (FIG. 13), so the detailed description will be referred to the first embodiment.

한편, 도 56은 도면에서 보는 바와 같이 내벽체(180)의 외측과 측벽(331)이 접하는 것을 도시한 것으로 제1실시 예(도15)에서와 같은 방법으로 시공하므로 상세 설명은 제1실시 예를 참조한다.Meanwhile, FIG. 56 illustrates that the outer side of the inner wall body 180 and the side wall 331 are in contact with each other as shown in the drawing, and thus, the construction will be performed in the same manner as in the first embodiment (FIG. 15). See.

도 57은, S60 공정에서 설명하였다.57 was described at step S60.

한편, 도면부호 S는 상부슬래브(340,350,340‘)의 상면측과 하부슬래브(370,370‘)의 하면측에 구성되는 보호몰탈과 방수시트를 포함하는 보호몰탈 방수시트층을 가르킨다.Meanwhile, reference numeral S denotes a protective mortar waterproof sheet layer including a protective mortar and a waterproof sheet formed on the upper surface side of the upper slab 340, 350 and 340 ′ and the lower surface side of the lower slab 370 and 370 ′.

본 발명의 방수방법은 제1실시 예에서의 방법을 그대로 적용하고 있으므로 상세 설명은 제1실시 예를 참조한다.Since the waterproof method of the present invention applies the method in the first embodiment as it is, the detailed description will be referred to the first embodiment.

한편 지하차도의 길이가 길어질 경우 제 1 실시예에 의한 도 23 에서와 같이 일정간격의 길이마다 재료투입구를 시설하여야 하는데, 그에 대한 상세한 사항은 제1실시 예에서와 같은 방법으로 설치하여야 하므로 제1실시 예에서의 설명의 내용을 참조하기로 한다.
On the other hand, when the length of the underground road is long, as shown in Fig. 23 according to the first embodiment, the material inlet should be provided for each length of a predetermined interval, and the details thereof should be installed in the same manner as in the first embodiment, so that the first Reference is made to the description of the embodiments.

제 4 Fourth 실시예Example

본 발명에 의한 제4실시예는 도 4에서 보는 것과 같이, 양 측벽에 엄지말뚝과 중앙부 양측 중간말뚝을 박기 위한 말뚝 시공공정(S10-1)과, 중앙측 상부슬래브 시공공정(S40)과, 일측 상부슬래브 시공공정(S20)과, 타측 상부슬래브 시공공정(S30)과, 내부굴착 및 어스앙카 시공공정(S50-2)과, 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정(S60)과, 양측 내벽체 시공공정(S70)과, 마무리 시공공정(S80)으로 지하차도의 시공이 이루어진다.In the fourth embodiment according to the present invention, as shown in Figure 4, the pile construction step (S10-1), the center side upper slab construction step (S40) for driving the thumb pile and the middle side both sides piles on both side walls, One side upper slab construction process (S20), the other side upper slab construction process (S30), internal excavation and earth anchor construction process (S50-2), both side lower slab and central wall or column reinforcement construction process (S60), The construction of the underground roadway is performed by both inner wall construction steps (S70) and the finishing construction step (S80).

이하 각 공정별로 나누어 본 발명에 의한 제4실시예의 공정 흐름과 이에 따른 각 구성을 설명한다.
Hereinafter, the process flow of the fourth embodiment according to the present invention and the respective constitution according to the process will be described.

말뚝 시공공정 - Pile Construction Process- S10S10 -1-One

본 공정은 지하차도를 건설할 위치의 중앙부에 해당되는 양측에 중간말뚝(400)과 구조체 양 측벽부에 엄지말뚝(401)을 형성하기 위한 공정이다.This process is a process for forming the thumb pile 401 on both sides of the middle pile 400 and the structural sidewalls on both sides corresponding to the central portion of the position to build the underground driveway.

이를 위해서 도면에서 보는 바와 같이 지하차도를 구성하기 위한 지역 범위내에서 중앙을 분리하기 위한 중앙부 좌우 양측과 양측 측벽부에 각각 중간말뚝(400)과 엄지말뚝(401)을 형성한다.To this end, as shown in the drawings, the middle pile 400 and the thumb pile 401 are respectively formed on the left and right sides and both side wall portions of the central portion for separating the center within the region range for constructing the underground roadway.

상기한 중앙부 좌우 양측의 중간말뚝(400)은 4.0m 간격으로 설치되고 구조체 양 측벽부의 엄지말뚝(401)은 2.0m 간격으로 설치하고 있다. 중간말뚝(400)의 터파기는 토압을 받는 상단의 높이가 비교적 얕아 4.0m의 간격으로 설치하여도 충분히 토압을 지탱할 수 있는 반면에 엄지말뚝(401)은 내부 굴착시 비지지장의 거리가 크고 비교적 큰 토압이 작용할 것이므로 2.0m 간격으로 설치토록 하였다.The middle pile 400 at the left and right sides of the center portion is installed at intervals of 4.0 m, and the thumb piles 401 at both side wall portions of the structure are disposed at intervals of 2.0 m. The trench of the middle pile 400 is relatively shallow in height at the top of the earth pressure, so that even when installed at intervals of 4.0 m, it can support the earth pressure sufficiently, whereas the thumb pile 401 has a large and relatively large distance of unsupported during internal excavation. Earth pressure will work, so it was installed at 2.0m intervals.

한편, 이러한 중간 및 엄지말뚝을 이용한 방법은 토사층 뿐만 아니라 암반구간에서도 가능하다. On the other hand, the method using the middle and the thumb pile is possible not only in the soil layer but also in the rock section.

말뚝을 암반측까지 천공이 가능한 T4 장비를 이용하여 건입하고 내부굴착시 토사층까지는 토류판을 부착하고 그 이하 암구간에는 암을 절취하여 토류판과 뒷채움 흙을 채워 토류벽을 형성하여 구조체를 시설할 수 있는 준비를 할 수 있다.
The pile is drilled using T4 equipment that can be drilled to the rock side, and the earth plate is attached to the soil layer during internal excavation, and after that, the arm is cut off to fill the earth plate and the backfilling soil to form the earth wall. You can do

중앙측Center 상부슬래브 시공공정 -  Upper Slab Construction Process- S40S40

상기한 공정인 말뚝 시공공정(S10-1)을 거쳐 중간말뚝(400) 및 엄지말뚝(401)의 설치시공이 완료되면 도 65에서 보듯이 중앙측 상면 도로 부분을 굴착하여 아스콘층과 흙을 걷어내게 된다. When the installation of the intermediate pile 400 and the thumb pile 401 is completed through the above-described pile construction process (S10-1), as shown in FIG. To me.

이처럼 중간말뚝(400) 사이를 터파기 할 때는 중간말뚝에 토류판을 설치하여야 하는데 길이로 인한 안전성을 고려하여 도 76의 콘크리트 PC1토류판(404)을 제작하여 설치하는 것으로 하였고, 엄지말뚝의 간격이 2.0m 임을 고려할 때 도 77의 콘크리트 PC2토류판(410)을 사용하는 것으로 이원화 하였다.As such, when digging between the middle pile 400, the earth plate should be installed in the middle pile. In consideration of the safety due to length, the concrete PC1 earth plate 404 of FIG. 76 was manufactured and installed, and the gap of the thumb pile was 2.0. Considering m is dualized to use the concrete PC2 earth plate 410 of Figure 77.

이와같이 일정깊이 터파기 공사를 진행 한 다음에 그 터파기면으로 바닥고르기 콘크리트와 거푸집을 시설한 후 중앙측 상부슬래브(430)를 시설한다. 이때 상부슬래브의 철근은 이웃과 접하는 중앙측 상부슬래브(430)와의 철근 연결을 위하여 한곳에서 이음치 않도록 지그재그로 배치 이음을 할 수 있도록 하고 중앙측 상부슬래브(430)의 시공 후에는 방수재와 보호몰탈을 시공한다. After proceeding the trench work in a certain depth in this way, after installing the floor-level concrete and formwork to the trench surface, the upper side slab 430 is installed. At this time, the reinforcing bar of the upper slab can be arranged in a zigzag so as to be connected in a zigzag so that the reinforcing bar is connected to the central upper slab 430 in contact with the neighbor, and after the construction of the central upper slab 430, the waterproof material and the protective mortar Construct it.

이와 같이 중앙측 상부슬래브(430)를 타설 시공한 후에는 어느 일측 및 타측상부슬래브(440,450)를 타설하기 위한 터파기시공(S30)이 이루어지는데 그 전에 교통의 흐름을 방해하지 않기 위해 중앙측 상부슬래브(430)의 표면을 복토하게 되는 복토과정을 거쳐야 한다.After placing the central upper slab 430 as described above, a trench construction (S30) for placing one side and the other upper upper slab 440, 450 is made. The surface of the slab 430 must be covered with a cover process.

복토과정에는 별도의 흙막이 시설을 하면서 복토를 하게 되는데 도 70에서 보듯이 별도의 흙막이 시설로는 H말뚝(90) 한쪽 플렌지에 다수개의 천공구멍(92)을 내고 이음부로부터 뒤로 일정거리를 후퇴하여 시설하되 철근을 천공구멍(92) 위치에서 볼트(93)로 결합하는 방식으로 다수개를 횡으로 시설한 후 적층하여 같은 방법으로 지표에 이르기까지 시설한다.In the cover process, the soil is covered with a separate clogging facility. As shown in FIG. 70, as a separate clogging facility, a plurality of perforation holes 92 are made in one flange of the H pile 90, and a predetermined distance is retracted backward from the joint part. The facility is installed in a manner that combines reinforcing bars with bolts 93 at the location of the drilling holes 92, and then stacks them to the ground in the same way.

이와같은 방법으로 시설하면 어느 일측 및 타측 상부슬래브(440,450)를 터파기할 때 중앙측 상부슬래브(430) 시공시 시설된 별도의 흙막이 시설이 토류벽의 역할을 수행하게 되어 어느 일측 및 타측 상부슬래브(450)의 터파기가 용이해진다.
In this way, when one side and the other upper slab 440, 450 is destroyed, a separate mudstone facility installed during the construction of the central upper slab 430 performs the role of the earth wall, so that one side and the other upper slab ( 450 is easy to break.

일측One side 상부슬래브 시공공정 -  Upper Slab Construction Process- S20S20

본 발명에서 상부슬래브는 도 66 내지 도 68에서 보는 바와 같이 중앙측 상부슬래브(430)를 중심으로 양측으로 각각 구분되며 순차적인 타설 과정을 거치게 되는데, 본 발명의 실시 이해를 위해 도면상(도 66) 보았을 때 우측의 상부슬래브를 일측상부슬래브라 명명하고 도면부호 440으로 표기하였으며, 이와 대향되는 측의 슬래브를 타측상부슬래브로 명명하고 도면부호 450으로 표기하여 구분하였다.In the present invention, the upper slab is divided into both sides with respect to the center upper slab 430 as shown in FIGS. 66 to 68, respectively, and is subjected to a sequential pouring process. When viewed, the upper slab on the right side is named one upper slab and denoted by reference numeral 440, and the slab on the opposite side is named the other upper slab and denoted by reference numeral 450.

상기한 공정(S20)을 거쳐 중앙측 상부슬래브(430)의 설치 시공이 완료되면 도 65와 같은 도로 단면의 구획이 분리되게 되는데, 본 공정은 이와 같은 상태에서 중앙측 상부슬래브(430)에 의해 구획되어지는 상부슬래브를 기준으로 양측 중 어느 한측을 먼저 형성하기 위한 공정으로 이해될 것이다.When the installation of the central upper slab 430 is completed through the above-described process (S20), the section of the road section as shown in FIG. 65 is separated, and in this state, the central upper slab 430 is separated by the middle upper slab 430. It will be understood as a process for first forming either side on the basis of the upper slab to be partitioned.

한편 일측 상부슬래브(440)를 터파기 할 경우 중앙측 상부슬래브(430)를 복토할 때 미리 매설하여 두었던 흙막이시설이 있으므로 터파기에서 어려움은 없을 것이고 버팀보만 갖추는 것으로 완료할 수 있는데 복토시에는 볼트(93)를 해제하면서 되메우기를 하여야 할 것이며 되메우기가 종료되면 H말뚝(90)을 뽑아낸다.On the other hand, when digging one side upper slab 440, there is a dirt block that was buried in advance when covering the central upper slab 430, there will be no difficulty in the digging, it can be completed by having only a brace, but in the case of covering the bolt (93) should be backfilled while releasing and the H pile 90 is pulled out when the backfill ends.

이후, 엄지말뚝에 매설되었던 PC강연선(402)을 긴장 정착하여 일측 상부슬래브(440)와 내부굴착시 설치하는 어스앙카와의 사이에 작용되는 부재력에 대응토록 한다.Afterwards, the PC strand wire 402 buried in the thumb pile is tensioned so as to correspond to the member force acting between the one upper slab 440 and the earth anchor installed during the internal excavation.

한편, 일측 상부슬래브(440)를 시공하기 전에는 엄지말뚝 플렌지에 연하는 콘크리트 PC2토류판(410)을 설치하여야 한다. 도 77에서 보듯이 콘크리트 PC2토류판(410)은 엄지말뚝(401) 플렌지를 회전용 철판(409)으로 감싸는 것으로 구성되어 있어 탈락되지 않도록 하였으며 이와 닿는 엄지말뚝(401)은 향후 인발을 용이하게 하기 위하여 약간의 유격이 있도록 하였다.On the other hand, before the construction of one side upper slab 440 should be installed concrete PC2 earth plate 410 that extends to the thumb pile flange. As shown in FIG. 77, the concrete PC2 earth plate 410 is configured to wrap the thumb pile 401 flange with a rotating iron plate 409 so as not to fall off, and the thumb pile 401 that touches it in order to facilitate future drawing. There was a slight play.

또한, 일측 상부슬래브(440)의 편측의 지지는 도 75에서 보듯이 일측 상부슬래브(440)내 앵커에 PC Wire(408)를 걸어 엄지말뚝(401) 한측 플렌지의 천공홀을 통하여 엄지말뚝(401) 상단에 정착토록 하였다.In addition, the support of one side of the upper slab 440 on one side, as shown in Figure 75 by hooking the PC wire 408 to the anchor in the one upper slab 440 through the drill hole of one flange of the thumb pile 401, thumb thumb 401 ) To settle on top.

한편, 2차 내벽체를 시공할 때는 일측 및 타측 상부슬래브(440,450)에 앵커 설치된 PC Wire(408)를 철거하여야 하는데, 1차 내벽체에 일측 및 타측 상부슬래브(440,450)를 받치는 버팀대를 시설한 후 PC Wire(408)를 끊어 시트방수재를 시설하고 2차 내벽체를 타설하는 것으로 형성할 수 있다.Meanwhile, when constructing the secondary inner wall, the PC wire 408 anchored to one side and the other upper slab 440, 450 should be dismantled, and a brace supporting one side and the other upper slab 440, 450 is installed on the primary inner wall. After the PC wire 408 is cut off, it can be formed by installing a sheet waterproofing material and pouring a secondary inner wall body.

또한, 상부슬래브를 시공할 때 제2실시 예에서 처럼 PC구조 슬래브 또는 제5실시 예에서처럼 Half PC구조 슬래브를 적용할 수 있다. In addition, when constructing the upper slab, it is possible to apply the PC structure slab as in the second embodiment or the Half PC structure slab as in the fifth embodiment.

이는 품질이 좋아지고 급속시공이 가능한 관계로 사용자가 선택적으로 적용할 수 있음은 당연하다.It is natural that the user can selectively apply it because the quality is improved and rapid construction is possible.

이때 배력철근의 이음은 도 71에서 보는 것과 같이하고 주철근의 이음은 도 72에서와 같이 한다.
At this time, the joint of the reinforcing bar is as shown in FIG. 71 and the joint of the main reinforcing bar is as shown in FIG.

타측The other side 상부슬래브 시공공정 -  Upper Slab Construction Process- S30S30

본 공정은 상기한 일측상부슬래브 시공공정(S30)에 의해 일측상부슬래브(440)를 타설한 후, 그 일측상부슬래브(440) 상면을 복토하여 교통의 흐름이 방해되지 않도록 한 다음, 타측 즉 일측상부슬래브(440)와 대향되는 측(도 67) 에서 보았을 때 왼쪽)의 상부슬래브(타측상부슬래브-450)를 타설하기 위해 터파기시공을 하는 공정을 의미한다.This step is to cast the one side upper slab 440 by the one side upper slab construction process (S30), and then cover the upper surface of one side upper slab 440 so that the flow of traffic is not obstructed, and then the other side, one side It refers to a process of carrying out the trench for pouring the upper slab (the other upper upper slab-450) of the left side when viewed from the side facing the upper slab 440 (FIG. 67).

이와 같이 타측상부슬래브(450)를 타설하기 위해 그 주변을 터파기 시공한 다음 도 66에서와 같이 타측상부슬래브(450)를 타설 양생하여 지하차도를 구성하기 위한 상측으로의 각 상부슬래브(440,450)의 타설 작업을 완료할 수 있으며, 복토하는 공정이라든가 터파기 시공방법은 일측상부슬래브(440)의 방법과 같으며, 이후, 엄지말뚝에 매설되었던 PC강연선(402)을 긴장 정착하여 타측상부슬래브(450)와 내부굴착시 설치하는 어스앙카와의 사이에 작용되는 부재력에 대응토록 하는 것은 전 실시예에 의한 타측 상부슬래브 시공공정(S30)과 같다.In this way, the periphery of the periphery was carried out to pour the other upper upper slab 450, and then the upper upper slabs 450 and 450 to the upper side for constructing the underground driveway by curing the other upper upper slab 450 as shown in FIG. It is possible to complete the pouring work, and the process of covering or digging construction method is the same as the method of one side upper slab 440, and afterwards, the tension of the PC strand wire 402 buried in the thumb pile is settled on the other side upper slab ( Corresponding to the member force acting between the 450 and the earth anchor installed during the internal drilling is the same as the other upper slab construction process (S30) according to the previous embodiment.

또한, 콘크리트 PC2토류판(410)의 시설방법과 PC Wire(408) 지지구조 시설방법 및 타측상부슬래브(450)를 PC구조로 할 수 있는 방법등은 일측상부슬래브(440)와 같아 상세내용은 일측 상부슬래브 시공공정(S20)에 준하여 설치 시공할 수 있다.
In addition, the facility method of the concrete PC2 earth plate 410, the PC wire 408 support structure facility method, and the method of making the other upper slab 450 into the PC structure is the same as the one upper slab 440, the details are one side It can be installed and installed in accordance with the upper slab construction process (S20).

내부굴착 및 Internal excavation and 어스앙카Earthanka 시공공정 -  Construction Process- S50S50 -2-2

본 공정은 상기한 각 상부슬래브(440,450)의 타설 작업을 완료한 후 상부슬래브가 지지하는 위치와 최종 굴착이 되는 굴착선과의 사이 거리가 커 정모멘트가 크게 작용되는 것을 저감시키기 위한 방법으로 엄지말뚝(401)의 지간을 짧게 유도하는 것이다. The present process is a method for reducing the large moment acts largely the distance between the position of the upper slab supports and the excavation line to be the final excavation after completing the above-mentioned casting of the upper slab (440,450) It is to induce a short period of 401.

이와같이 설치된 어스앙카로 인하여 엄지말뚝(401)의 근입장도 짧게 할 수 있어 경제적 측면에서 유리하다.Due to the earth anchor installed in this way, the position of the thumb pile 401 can also be shortened, which is advantageous in terms of economy.

이러한 어스앙카는 양측 내벽체를 시공할 때 제거되어야 한다, 이렇게 어스앙카를 제거하게 되면 상부슬래브(440, 450)와 하부슬래브(470, 470‘) 사이의 비지지장 거리가 길어지게 되고 큰 부재력이 발생되나 엄지말뚝(401) 편측 플렌지에 PC강연선(402)을 긴장하고 있어 부재력이 감소되는 것이다.These earth anchors should be removed when constructing both inner walls. This removal of the earth anchors increases the unsupported distance between the upper slabs 440 and 450 and the lower slabs 470 and 470 'and increases the large absence force. It is generated but the tension force PC strands 402 on the flange of one side of the thumb pile 401 is to reduce the member force.

한편 여기서 상기한 PC강연선(402)을 배치하지 않으면 부재력을 제어할 다른 부재로 버팀을 하여야 하는데, 좁은 공간내에서 버팀보 설치 및 해체가 어렵고 공사비가 커져 매우 불리한 상황에 직면케 되는 것이다.
On the other hand, if the PC stranded wire 402 is not disposed here, the support should be supported by another member to control the member force, and the installation and dismantling of the support in a narrow space is difficult, and the construction cost is large, thus confronting a very disadvantageous situation.

양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정 - Reinforcement work of both lower slab and central wall or column- S60S60

본 공정은 전술한 어스앙카 시공공정(S50-2)이 완료된 후, 하부슬래브(470,470’) 및 기둥체(481)를 시공하여 지하차도를 형성하기 위한 공정이다.This process is a process for forming the underground roadway by constructing the lower slab (470,470 ') and the column body 481 after the above-mentioned ground anchor construction process (S50-2) is completed.

양측의 굴착 된 공간에 버림콘크리트와 외부시트 방수층을 형성한 후 해당 굴착 부분의 엄지말뚝(401)과 그 하단으로 하부슬래브(470,470’)를 타설하게 된다.After forming the discarded concrete and the outer sheet waterproof layer in the excavated space on both sides, the lower pile (470,470 ') is poured into the thumb pile 401 and the bottom of the excavated portion.

여기서 상기 하부슬래브(470,470’)는 도면에서 보는 바와 같이 지하차도의 바닥면에 타설되는 타설체를 의미하고, 엄지말뚝(401)의 내측에 접하는 헌치부까지 타설한다.Here, the lower slab (470, 470 ') refers to the pour body to be poured on the bottom surface of the underground driveway, as shown in the drawing, and pours up to the haunting portion in contact with the inside of the thumb pile 401.

상기와 같이 양측의 공간을 굴착 시공한 후 하부슬래브(470,470’)의 타설공정이 완료된 후, 기둥체(481)를 시공하게 된다.
After excavating the space on both sides as described above, after the casting process of the lower slab (470,470 ') is completed, the pillar body 481 is constructed.

양측 Both sides 내벽체Inner wall 시공공정 -  Construction Process- S70S70

하부슬래브 양측으로 일체로 수직상 연결되어 엄지말뚝(401)의 내측으로 타설되는 일부의 벽체(480,480‘)는 하부슬래브(470,470‘)에 연이은 어스앙카를 철거한 후 시공되어지며 잔여 벽체(480“)는 상기의 일부의 벽체(480,480’)가 양생되어진 후 시공되어진다. Some of the walls 480 and 480 'which are vertically connected to both sides of the lower slab and poured into the inside of the thumb pile 401 are constructed after dismantling the earth anchors connected to the lower slab 470 and 470' and the remaining walls 480 ". ) Is constructed after some of the walls 480, 480 'are cured.

그러나 잔여벽체(480“)가 양생될때 콘크리트 수축작용에 의하여 침강이 되어 상부슬래브(440,450)와 미세한 틈이 발생될 수 있는데, 이곳에 무수축몰탈을 충진하여 완성하게 된다.
However, when the residual wall 480 ″ is cured, it may be settled by the concrete contraction action, and a fine gap may be generated with the upper slabs 440 and 450.

마무리 시공공정 - Finishing Construction Process- S80S80

상기와 같은 공정이 완료되면, 지하차도 내부의 보도 및 전기시설, 타일과 아스콘 등을 시설하여 지하차도의 공정을 마무리한다.
When the above process is completed, the process of the underground driveway is completed by installing sidewalks and electric facilities, tiles and ascons inside the underground driveway.

이상과 같은 일련의 공정을 거쳐, 중간말뚝(400)과 엄지말뚝(401)을 이용한 지하차도를 시공하게 되는데, 전술한 바와 같이 중앙측 상부슬래브(430)와 그로부터 적정 간격 이격되며 이루어지는 엄지말뚝(401)을 형성한 다음에, 일측 및 타측 상부슬래브(440,450)를 각각 순차적으로 타설할 때, 도 73, 도 74에서와 같이 각 상부슬래브(440,450) 철근이 벽체(480. 480‘)와 기둥체(481)의 철근과 상호 결합되어야 한다.Through a series of processes as described above, the underground pile using the intermediate pile 400 and the thumb pile 401 is to be constructed, as described above, the thumb pile is spaced apart from the central upper slab 430 and an appropriate distance therefrom ( 401 is formed, and then when one side and the other upper slab 440, 450 is poured in sequence, as shown in FIGS. 73 and 74, the reinforcing bars of each upper slab 440 and 450 are formed of the wall 480.480 'and the column body. It must be interlocked with the bars of (481).

이러한 일련의 공정들을 위해서, 도 70은 복토과정에서 필요로 하는 별도의 흙막이 시설로서 H말뚝(90) 한쪽 플렌지에 다수개의 천공구멍(92)을 내고 이음부로부터 뒤로 일정거리를 후퇴하여 시설하되 철근을 천공구멍(92) 위치에서 볼트(93)로 결합하는 방식으로 다수개를 횡으로 시설한 후 적층하여 같은 방법으로 지표에 이르기까지 시설하는 것인바 이러한 시설로 인하여 좌우 양측 상부슬래브를 위한 굴착시 매우 공사를 간편히 할 수 있는 시설이다.For such a series of processes, Figure 70 is a separate clogging facility required in the cover process, a plurality of perforations (92) in one flange of the H pile 90, retreating a certain distance back from the joint, and installed the rebar In this way, a plurality of transversely installed and then stacked to reach the ground in the same manner by combining the bolts 93 in the position of the drilling hole 92 bar due to these facilities at the time of excavation for the left and right upper slabs It is a facility that can be very easily constructed.

또한 도 71은 상부슬래브를 PC구조로 시공할 경우 PC슬래브 간 연결이 되는 배력철근을 연결하는 상세를 도시한 것으로 연결부는 PC구조로 할 수 없고 현장타설 구조로만 할 수 있으므로 상부철근과 하부철근의 연결 위치를 달리하여 가스압접이나 커플러로 연결토록 하는 것이다.In addition, FIG. 71 shows the details of connecting the reinforced reinforcing bars connected between the PC slabs when the upper slab is constructed in the PC structure. The connection part cannot be the PC structure, but only the site casting structure. The connection position is to be connected by gas pressure welding or coupler.

도 72는 중앙측 상부슬래브(430)를 타설시에는 일측 및 타측상부슬래브(440,450)의 철근과 연결을 위하여 일정길이의 철근(431, 432)을 타설전에 지그재그로 배열하여 한곳에서만 연결이 되지 않도록 조치하여 일측 및 타측상부슬래브(440,450)의 타측철근(441,442/451,452)의 단부와 커플러 또는 가스압점 등의 방법으로 연결 고정한다. 이와 같이 하여 각 일측 및 타측상부슬래브(440,450)와 중앙측 상부슬래브(430)를 견고하게 연결할 수 있게 된다.FIG. 72 shows that when reinforcing the central upper slab 430, the reinforcing bars 431 and 432 of a predetermined length are arranged in zigzag before being cast in order to be connected to the reinforcing bars of the one side and the other upper upper slab 440 and 450 so as not to be connected only in one place. By taking measures, the ends of the other reinforcing bars 441, 442/451 and 452 of one side and the other upper slab 440 and 450 are connected and fixed by a coupler or a gas pressure point. In this way, it is possible to firmly connect each one side and the other upper upper slab (440, 450) and the central upper slab (430).

도 73, 도 74에서 상기 기둥체(481) 및 벽체(480,480‘)에 설치되는 기둥체 철근(434)과 벽체철근(483,484)은 사전에 미리 매입 설치하고 각 상부슬래브(430,440,450) 타설시 매입된 철근(433/ 442,443/ 452,453)과 연결되도록 하였다. In FIGS. 73 and 74, the column reinforcing bars 434 and the wall reinforcing bars 483 and 484 installed in the column 481 and the walls 480 and 480 'are pre-installed and installed at the time of placing each upper slab 430, 440, and 450. Reinforcing bars (433 / 442,443 / 452,453).

도 75는 상부슬래브를 편측지지하는 구조로서 좌우 양측 상부슬래브가 벽체와 접촉되는 위치 내부에 앵커로 매입되어 있는 PC Wire(408)를 엄지말뚝 편측플렌지의 홀을 통하여 엄지말뚝 상단에 긴장한 채로 고정하므로 향후 내부 터파기시에도 상부슬래브가 견고히 지지될 수 있도록 하고 있다.FIG. 75 shows a structure in which the upper slab is supported on one side, so that the left and right upper slabs are fixed to the upper end of the thumb pile through holes in the thumb pile one side flange, which is embedded as an anchor inside the position where the upper slab is in contact with the wall. In the future, the upper slab can be firmly supported even during internal trenching.

도 76은 콘크리트 PC1토류판(404)의 상세로서 각 상부슬래브를 위한 터파기시 흙막이용 토류판을 PC구조로 한 것인바 걸쇠철판(405)에 너트1(407-1)을 용접하고 PVC관 천공 홀을 통과한 철근(406)에 너트2(407-2)를 조인 상태에서 토류판을 엄지말뚝 또는 중간말뚝 프렌지에 끼워 시설한 후 너트2(407-2)를 풀면 토류판을 해체할 수 있는 구조로 구성되어 있다. 이러한 토류판은 내측으로는 PC 강연선(403)을 긴장정착하여 시설하고 배면으로는 콘크리트가 두껍게 돌출되도록 하여 토압에 지탱하도록 하였다. Fig. 76 shows the details of the concrete PC1 earth plate 404, which is made of a PC structure of the earth plate for earthing at the time of digging for each upper slab. The nut 1 407-1 is welded to the clasp iron plate 405, and the PVC pipe is drilled. In the state where the nut 2 (407-2) is tightened to the rebar 406 passing through the fitting, the earth plate is installed in the thumb pile or the middle pile flange, and then the nut 2 (407-2) is loosened. It is. The earth plate was installed by tensioning the PC strand (403) on the inside, and the concrete was protruded thick on the back to support the earth pressure.

한편, 토류판의 강성을 키우기 위하여 내부에 H형강을 매립하여 제작할 수도 있으며 토류판 외주면의 모서리 부분에는 L형강을 이용하여 모서리가 깨지지 않도록 할 수도 있다.On the other hand, in order to increase the rigidity of the earth plate may be produced by embedding the H-shaped steel inside, and the corner portion of the outer peripheral surface of the earth plate may be used to prevent the edges from being broken.

도 77은 콘크리트 PC2토류판(410)의 상세로서 각 상부슬래브를 위한 터파기시 흙막이용 토류판을 PC구조로 한 것인바 회전용 철판(409)에 너트1(407-1)을 용접한 후 PVC관 천공 홀을 통과한 철근(406)에 손잡이를 끼워 시계방향으로 회전하여 회전용 철판(409)이 엄지말뚝 플렌지에 끼이도록 한 후 손잡이를 풀고 너트2(407-2)를 조여 토류판을 시설한 후 너트2의 공극을 몰탈로 채우고 시트방수재를 포설하는 구조로 구성되어 있는데, 여기서 회전용 철판(409) 대신에 ¬자로 꺾인 철근(도면 미 도시)으로 대체할 수 있다.FIG. 77 shows the details of the concrete PC2 earth plate 410, which is made of a PC structure of the earth plate for earthing when digging for each upper slab. The PVC pipe after welding the nut 1 (407-1) to the rotating iron plate 409. Insert the handle into the rebar 406 that passed through the drill hole and rotate it clockwise so that the rotating iron plate 409 fits into the thumb pile flange, then loosen the handle and tighten the nut 2 (407-2) to install the earth plate. It is composed of a structure that fills the void of the nut 2 with mortar and installs a sheet waterproofing material, where it can be replaced with a reinforcing bar (not shown) instead of a rotating iron plate 409.

또한, 재사용을 위하여 회수하고자 할 때는 회전용 철판(409)을 반시계 방향으로 회전하면 간단히 회수가 가능하다. 이러한 토류판 역시 콘크리트 PC1 토류판(404)과 마찬가지로 내측으로 PC 강연선(403)을 긴장정착하여 시설하고 배면으로 콘크리트가 두껍게 돌출되도록 하여 토압에 지탱하도록 하였다.In addition, when recovering for reuse, it is possible to simply recover by rotating the rotating iron plate 409 counterclockwise. Like the concrete PC1 earth plate 404, the earth plate was also installed by tensioning the PC strand (403) to the inside, so that the concrete protrudes thickly to the back to support the earth pressure.

한편, 토류판의 강성을 키우기 위하여 내부에 H형강을 매립하여 제작할 수도 있으며 토류판 외주면의 모서리 부분에는 L형강을 이용하여 모서리가 깨지지 않도록 할 수도 있다.On the other hand, in order to increase the rigidity of the earth plate may be produced by embedding the H-shaped steel inside, and the corner portion of the outer peripheral surface of the earth plate may be used to prevent the edges from being broken.

아울러, 도면부호 S는 하부슬래브(440)의 하면측에 구성되는 보호몰탈과 방수시트를 포함하는 보호몰탈 방수시트층을 가르킨다.In addition, reference numeral S denotes a protective mortar waterproof sheet layer including a protective mortar and a waterproof sheet formed on the lower side of the lower slab 440.

본 발명의 방수방법은 제1실시 예에서의 방법을 그대로 적용하고 있으므로 상세 설명은 제1실시 예를 참조할 수 있다.Since the waterproof method of the present invention applies the method in the first embodiment as it is, detailed descriptions can be referred to the first embodiment.

한편 지하차도의 길이가 길어질 경우 일정간격의 길이마다 재료투입구를 시설하여야 하는데, 그에 대한 상세한 사항은 제1실시 예에서와 같은 방법으로 설치하여야 하므로 제1실시 예에서의 설명의 내용을 참조하여 실시할 수 있을 것이다.
On the other hand, when the length of the underground road becomes longer, the material input holes should be installed at every predetermined length, and the details thereof should be installed in the same manner as in the first embodiment. You can do it.

제 5 Fifth 실시예Example

본 발명에 의한 제5실시예는 도 82 에 의한 바와 같이, 양 측벽은 PC벽체 및 PC 사각파일과 중앙부 벽체 또는 기둥의 PC 사각파일 및 CIP구근을 시공하기 위한 CIP구근 시공공정(S10)과, 일측 Half PC구조의 상부슬래브를 시공하기 위한 일측 상부슬래브 시공공정(S20)과, 타측 Half PC구조의 상부슬래브를 시공하기 위한 타측 상부슬래브 시공공정(S30)과, 중앙측으로 Half PC구조 상부슬래브를 시공하기 위한 중앙측 상부슬래브 시공공정(S40)과, 코너부 보강 시공공정(S50-1), 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정(S60)과, 양측 내벽체 시공공정(S70)과, 마무리 시공공정(S80)으로 지하차도의 시공이 이루어진다.According to the fifth embodiment of the present invention, as shown in FIG. 82, both sidewalls have a CIP bulb construction process (S10) for constructing PC wall piles and PC square piles and PC square piles and CIP bulbs of central walls or pillars. One upper slab construction process (S20) for constructing the upper slab of one side PC structure, the other upper slab construction process (S30) for constructing the upper slab of the other half PC structure, and the half PC structure upper slab to the center side Center side upper slab construction process (S40), corner portion reinforcement construction process (S50-1), both bottom slab and central wall or column reinforcement construction process (S60), both side wall construction process (S70) and , The construction of the underground roadway is made by the finishing construction process (S80).

각 공정별로 나누어 본 발명의 공정 흐름과 이에 따른 각 구성을 설명한다.
The process flow of the present invention and each configuration according thereto will be described by dividing each process.

CIPCIP 구근 시공공정 - Bulb Construction Process- S10S10

본 공정은 지하차도를 건설할 위치의 벽체에 해당되는 측벽과 중앙부의 벽체 또는 기둥을 형성하기 위한 공정이다. This process is a process for forming the side wall and the central wall or pillar corresponding to the wall of the position to build the underground driveway.

이를 위해서 도면에서 보는 바와 같이 지하차도를 구성하기 위한 지역 범위내에서 중앙을 분리하기 위한 중앙부와 양측 측면부에 각각 벽체 즉 측벽이 형성되도록 PC 사각파일벽체(502)와 PC벽체(500') 또는 PC 사각파일벽체(501)를 형성한다.To this end, as shown in the drawing, the PC square pile wall 502 and the PC wall 500 'or PC such that walls or sidewalls are formed in the central portion and both side surface portions for separating the center within the region range for constructing the underground roadway, respectively. The square pile wall 501 is formed.

여기서 상기 중앙부는 PC 사각파일벽체(502) 또는 CIP구근(500)을 이용하여 벽체로 형성할 수도 있고, 기둥식 예컨데 중간 중간이 끊겨지는 형태의 기둥 타입으로 CIP구근을 형성할 수 있는바, 현장 조건 및 설계 등에 의해 가변 될 수 있으며, 이러한 변경은 본 발명을 사용하는 자가 선택적으로 적용할 수 있음은 당연하다 할 것이다. Here, the central portion may be formed as a wall using the PC square pile wall 502 or the CIP bulb 500, a column type, for example, to form a CIP bulb in the form of a column of the middle is broken bar, the site It can be varied depending on the conditions and design, it will be obvious that such a change can be selectively applied by those using the present invention.

한편, 본공정은 제3 실시예 에서의 시공방법과 같으므로 상세 설명은 생략하고 제3 실시예를 참조하기로 한다.
In addition, since this process is the same as the construction method in 3rd Example, detailed description is abbreviate | omitted and it refers to 3rd Example.

일측One side 상부슬래브 시공공정 -  Upper Slab Construction Process- S20S20

상기한 공정인 CIP구근 시공공정(S10)을 거쳐 벽체(502, 500, 501)의 설치 시공이 완료되면 도 79와 같은 도로 단면의 구획이 분리되게 되는데, 본 공정은 이와 같은 상태에서 벽체(502, 500', 501)에 의해 구획되어지는 전체 폭원을 기준으로 3등분되는 중 어느 한측을 먼저 상부슬래브를 형성하기 위한 공정으로 이해될 것이다.When the installation of the walls 502, 500, 501 is completed through the CIP bulb construction process (S10) described above, the section of the road section as shown in FIG. 79 is separated, and in this state, the wall 502 It will be understood as a process for forming the upper slab first of any one side divided into three based on the total width source partitioned by, 500 ', 501).

이를 위해서 도 80 에서 보는 바와 같이 상부슬래브 전체 폭원중 1/3되는 위치 중앙부(전술한 바와 같이 PC구조(PC벽체, PC사각파일)로 이루어지는 벽체 중 중앙을 나누는 전체 부분을 중앙부로 명명하고 이를 도면에서 530 으로 표기하며, 상기 PC구조에 의해 형성되는 기둥 타입도 포함한다)(530) 인근의 어느 일측 도로부분을 굴착하여 아스콘층과 흙을 걷어내게 된다.For this purpose, as shown in FIG. 80, the center portion of the upper half of the entire width source of the upper slab (as described above) is named as the central portion of the whole wall dividing the center of the wall composed of the PC structure (PC wall, PC square pile). Indicated as 530, and includes a pillar type formed by the PC structure) 530 to excavate any one side of the road portion in the vicinity and to remove the ascon layer and soil.

이때, H-말뚝 흙막이 시설로 제4 실시 예에서 적용되고 있는 콘크리트 PC1 토류판(504)를 제작하여 설치하는 것으로 하였다.At this time, it is assumed that the concrete PC1 earth plate 504, which is applied in the fourth embodiment, is manufactured and installed as the H-pile soiling facility.

이와 같이 일정 깊이 터파기 공사를 진행 한 다음에 그 터파기면으로 바닥고르기 콘크리트와 거푸집을 시설한 후 Half PC구조 상부슬래브를 시설한다.In this way, after the excavation work is carried out to a certain depth, the flooring concrete and formwork are installed on the trench surface, and then the half PC structure upper slab is installed.

이때, 코너부 보강재(560)을 연결하기 위한 앙카볼트를 미리 구성하도록 하는 것이 좋다. 이것은 코너부 보강재(560)를 설치할 때 즉시 설치가 용이하도록 하기 위함이다.At this time, the anchor bolt for connecting the corner reinforcement 560 may be configured in advance. This is to facilitate the installation immediately when installing the corner reinforcement 560.

본 발명에서 Half PC구조 상부슬래브는 도 80 내지 도 82 에서 보는 바와 같이 전체 폭원을 3등분으로 각각 구분되며 순차적으로 Half PC구조 상부슬래브를 시설하게 되는데, 본 발명의 실시 이해를 위해 도면상(도 80) 보았을 때 우측의 상부슬래브를 일측 Half PC구조 상부슬래브라 명명하고 도면부호 540으로 표기하였으며, 이와 대향되는 측의 상부슬래브를 타측 Half PC구조 상부슬래브로 명명하고 도면부호 540‘으로 표기하며 중앙측의 슬래브를 중앙측 Half PC구조 상부슬래브로 명명하고 550으로 표기하여 구분하였다.In the present invention, the half PC structure upper slab is divided into three parts of the total width source, respectively, as shown in FIGS. 80 to 82, and the half PC structure upper slab is sequentially equipped with a half PC structure upper slab. 80) When viewed, the upper slab on the right side is named one half PC structure upper slab and denoted with reference numeral 540. The upper slab on the opposite side is named the other half PC structure upper slab and denoted with reference numeral 540 'and centered. The slab on the side was named the upper half slab of the middle side of the PC, and was marked with 550.

이때, 일측 Half PC구조 상부슬래브(540)의 철근은 이웃과 접하는 중앙측 Half PC구조 상부슬래브(550)와의 철근 연결을 위하여 한곳에서 이음치 않도록 지그재그로 배치 이음을 할 수 있도록 하고 일측 Half PC구조 상부슬래브(540)의 시공 후에는 방수재와 보호몰탈을 시공한다.At this time, the reinforcing bar of one side half PC structure upper slab 540 is arranged in a zigzag manner so that the reinforcing bar is connected to the center half PC structure upper slab 550 which is in contact with a neighbor, and one side half PC structure After construction of the upper slab 540 is a waterproof material and protective mortar is constructed.

이와 같이 일측 Half PC구조 상부슬래브(540)를 시설한 후에는 현장타설 콘크리트를 타설하게 되는데, 이는 품질과 공기를 위함이기도 하지만 결합 되는 과정을 완벽히 할 수 있는 장점을 갖추고 있다. As such, after installing the one-sided half PC structure upper slab 540, the cast-in-place concrete is poured, which is also for quality and air, but has the advantage of perfecting the combined process.

이어서, 후술하게 되는 타측 Half PC구조 상부슬래브(540‘)를 시설하기 위한 터파기 시공(S30)이 이루어지는데 그 전에 교통의 흐름을 방해하지 않기 위해 일측 Half PC구조 상부슬래브(540)의 표면을 복토하게 되는 복토공정을 거쳐야 한다.Subsequently, a trench construction (S30) for installing the other half PC structure upper slab 540 ', which will be described later, is performed. Before that, the surface of the one side half PC structure upper slab 540 is not interrupted. You have to go through the cover process which is covered.

한편, 복토시에는 일측 Half PC구조 상부슬래브(540)와 타측 Half PC구조 상부슬래브(540‘)의 지그재그 방식의 철근이음을 위하여 별도의 흙막이 시설을 하면서 복토를 하게 되는데 별도의 흙막이 시설에 대해서는 상기 제1실시 예(도 17 예시)와 같은 방법으로 시공하므로 상세 설명은 제1실시 예를 참조한다.On the other hand, in the case of covering the soil to cover the zigzag reinforcement of one side half PC structure upper slab 540 and the other half PC structure upper slab 540 'while covering the soil for the separate soil barrier facility above Since the construction is performed in the same manner as in the first embodiment (illustrated in FIG. 17), the detailed description will be referred to the first embodiment.

한편, 일측 Half PC구조 상부슬래브(540)의 시공에 있어서는 상기와 달리 도로의 사정에 의하여 터파기 시공방법을 중앙부(530)를 기준으로 일측과 타측의 양측으로 구분되는 1/2 시공 방법으로 시공할 수 있다.
On the other hand, in the construction of the one-side Half PC structure upper slab 540, unlike the above, construction of the trench construction method according to the situation of the road by the 1/2 construction method divided into one side and the other side on the basis of the central portion 530. can do.

타측The other side 상부슬래브 시공공정 -  Upper Slab Construction Process- S30S30

본 공정은 상기한 일측상부슬래브 시공공정(S20)에 의해 일측 Half PC구조 상부슬래브(540)를 설치 및 타설한 후, 그 일측 Half PC구조 상부슬래브(540) 상면을 복토하여 교통의 흐름이 방해되지 않도록 한 다음, 타측 즉 일측 Half PC구조 상부슬래브(540)와 대향되는 측(도 81) 에서 보았을 때 왼쪽의 Half PC구조 상부슬래브(타측 Half PC구조 상부슬래브-540‘)를 설치하기 위해 터파기시공을 하는 공정을 의미하는데, 일측 Half PC구조 상부슬래브(540)과 같은 방법으로 시공하므로 상세내용은 생략한다.
This process is one side half PC structure by the above one side upper slab construction process (S20). After installing and pouring the upper slab 540, one side half PC structure Cover the upper surface of the upper slab 540 so that the flow of traffic is not disturbed, then the other side, that is, one half PC structure As seen from the side facing the upper slab 540 (FIG. 81), it refers to a process of digging to install a half PC structure upper slab (the other half PC structure upper slab-540 ') on the left side. Since it is constructed in the same manner as the PC structure upper slab 540, details thereof will be omitted.

중앙측Center 상부슬래브 시공공정 -  Upper Slab Construction Process- S40S40

상기한 일측 및 타측 Half PC구조방식의 일측 및 타측 상부슬래브 시공공정(S20,S30)의 설치시공이 완료되면 도 82에서 보듯이 중앙측 상면 도로 부분을 굴착하여 아스콘층과 흙을 걷어내게 된다. When the installation of the one side and the other upper slab construction process (S20, S30) of the one side and the other half PC structure method is completed, as shown in Figure 82 to excavate the road part of the upper surface of the center side to remove the asphalt concrete and soil.

이처럼 중앙측을 터파기 할 때는 일측 및 타측 Half PC구조 상부슬래브 시공공정(S20,S30)시 이미 설치한 제1실시예(도 17)의 H말뚝(90)과 앵커체(91)가 연결되어 있는 흙막이 시설이 있으므로 별도의 흙막이 시설이 없이 터파기가 가능하다. As such, when digging the center side, the H pile 90 and the anchor body 91 of the first embodiment (FIG. 17) already installed during one side and the other half PC structure upper slab construction process (S20, S30) are connected. Since there is a clogging facility, it is possible to dig without a separate clogging facility.

이와같이 일정깊이 터파기 공사를 진행 한 다음에 그 터파기면으로 바닥고르기 콘크리트와 거푸집을 시설한 후 중앙측 Half PC구조 상부슬래브(550)를 시설한다.In this way, after proceeding the excavation work to a certain depth, after installing the floor-level concrete and formwork to the excavation surface is installed the upper half slab structure 550 in the center side.

이때 상부슬래브의 철근은 일측 및 타측에서 이미 지그재그로 배열된 상태로 연결하고 콘크리트를 타설하게 되는데, 타설 후에는 방수재와 보호몰탈을 시공한다. At this time, the reinforcing bar of the upper slab is already connected in a zigzag state on one side and the other side, and the concrete is poured. After pouring, the waterproofing material and the protective mortar are constructed.

이와 같이 중앙측 Half PC구조 상부슬래브(550)를 시설한 후에는 어느 일측 및 타측 Half PC구조 상부슬래브(540,540‘) 시공에 있어서 설치되었던 H-말뚝을 뽑기 위한 볼트를 해제하는 과정과 함께 되메우기를 하면서 H-말뚝을 인발하게 된다.After the central half PC structure upper slab 550 is installed as described above, the bolts for pulling the H-pile which are installed in the construction of one side and the other half PC structure upper slab 540 and 540 'are released. While pulling the H-pile.

한편, 1/2 시공일 경우에는 중앙부에서 철근이음을 하여야 하므로 부모멘트로 인한 부담이 될 수 있어 콘크리트 두께를 10㎝ 정도 두껍게 하여야 한다. 이는 부모멘트의 크기를 저감시키기 위함이다.
On the other hand, in the case of 1/2 construction, the reinforcing bar should be made in the center part, so it may be a burden due to the parenting, and the concrete thickness should be about 10 cm thick. This is to reduce the size of the parent.

코너부Corner portion 보강 시공공정 -  Reinforcement Construction Process- S50S50 -1-One

본 공정은 상기한 각 상부슬래브(540,540‘)의 타설 작업을 완료한 후 상부슬래브와 PC 사각파일벽체(501)가 결합되어 있어 부모멘트가 크게 작용되는 것을 저감시키기 위한 방법으로 상부슬래브(540,540’)나 내벽체(580,580‘)의 지간을 짧게 유도하는 공정으로 제3실시예 (도 44 예시)와 같은 방법으로 시공하므로 상세 설명은 제3실시 예를 참조 할 수 있다.This process is the upper slab (540,540 ') after completing the above-mentioned casting work of the upper slab and the PC square pile wall 501 is combined with the upper slab (540,540') as a method to reduce the great action of the parent moment ) And the interior walls (580, 580 ') is a process of shortly inducing the construction in the same manner as in the third embodiment (FIG. 44), so a detailed description can be referred to the third embodiment.

한편, 측벽이 PC벽체(500)로 구성될 경우 코너부 보강 시공공정(S50)은 하지 않는다.
On the other hand, when the side wall is composed of the PC wall 500, the corner reinforcement construction process (S50) is not performed.

양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정 - Reinforcement work of both lower slab and central wall or column- S60S60

본 공정은 전술한 코너부 보강 시공공정(S50-1)이 완료된 후, 하부슬래브(570,570’) 및 중앙부(530)를 시공하여 지하차도를 형성하기 위한 공정이다.This process is a process for forming the underground roadway by constructing the lower slab (570, 570 ') and the central portion 530 after the above-described corner reinforcement construction process (S50-1) is completed.

양측의 굴착 된 공간에 버림콘크리트와 외부시트 방수층을 형성한 후 해당 굴착 부분의 측벽(531)과 그 하단으로 하부슬래브(570,570’)를 타설하게 된다.After forming the discarded concrete and the outer sheet waterproof layer in the excavated space on both sides, the lower slab (570,570 ') is poured into the side wall 531 and the bottom of the excavated portion.

여기서 상기 하부슬래브(570,570’)는 도 90, 도 91에서 보는 바와 같이 지하차도의 바닥면에 타설되는 타설체를 의미하고, 측벽(531)의 내측에 접하는 헌치부까지 타설한다. Here, the lower slab (570, 570 ') refers to the pour body to be poured on the bottom surface of the underground driveway, as shown in Figures 90, 91, and pours to the haunting portion in contact with the inner side of the side wall (531).

한편, 본공정은 제3 실시예 에서의 시공방법과 같으므로 상세 설명은 생략하고 제3 실시예를 참조하기로 한다.
In addition, since this process is the same as the construction method in 3rd Example, detailed description is abbreviate | omitted and it refers to 3rd Example.

양측 Both sides 내벽체Inner wall 시공공정 -  Construction Process- S70S70

하부슬래브 양측으로 일체로 수직상 연결되어 측벽(531)의 내측으로 타설되는 일부의 내벽체(580,580‘)는 상기공정(S60)완료된 후 시공되어지며 잔여 내벽체(580“)는 상기의 일부의 내벽체(580,580’)가 양생되어진 후 코너부 보강재(560)를 철거하면서 시공되어진다. 그러나 잔여 내벽체(580“)가 양생될때 콘크리트 수축작용에 의하여 침강이 되어 상부슬래브(540,550,540‘)와 미세한 틈이 발생될 수 있는데, 이곳에 무수축몰탈을 충진하여 완성하게 된다.
Some of the inner walls 580, 580 'which are integrally vertically connected to both sides of the lower slab and poured into the inner side of the side wall 531 are constructed after the process S60 is completed, and the remaining inner walls 580' are partially formed. After the inner walls 580 and 580 'are cured, they are constructed while removing the corner reinforcement 560. However, when the remaining inner wall (580 ″) is cured, it may be settled by the concrete shrinkage action to generate a fine gap with the upper slab (540, 550, 540 '), which is completed by filling the non-shrink mortar.

마무리 시공공정 - Finishing Construction Process- S80S80

상기와 같은 공정이 완료되면, 지하차도 내부의 보도 및 전기시설, 타일과 아스콘 등을 시설하여 지하차도의 공정을 마무리한다.
When the above process is completed, the process of the underground driveway is completed by installing sidewalks and electric facilities, tiles and ascons inside the underground driveway.

이상과 같은 일련의 공정을 거쳐, 벽체(502, 500', 501)을 이용한 지하차도를 시공하게 되는데, 전술한 바와 같이 벽체(502, 500', 501)을 이용하여 지하차도의 중앙부(530)와 그 중앙부(530)로부터 적정 간격 이격되며 이루어지는 측벽(531)을 형성한 다음에, 일측 및 타측 Half PC구조 상부슬래브(540,540‘)를 각각 순차적으로 타설할 때, 각 Half PC구조 상부슬래브(540,540’) 철근과 중앙측(550)에서의 철근이 결합되어야 한다.Through the above-described series of steps, the underground roadway using the walls 502, 500 ', and 501 is constructed. As described above, the central portion 530 of the underground roadway using the walls 502, 500', and 501 is used. And sidewalls 531 formed at a predetermined interval from the central portion 530, and then sequentially placing one side and the other half PC structure upper slabs 540 and 540 ', respectively. ') Reinforcing bar and the reinforcing bar at the central side (550) should be combined.

이를 위해서, 도 90 은 측벽(531)과 하부슬래브(570)의 각 철근(571, 571' / 572, 572')와 PC사각파일 벽체 내측철근(511)을 연결 고정되는 상태를 나타내고 있으며 제3실시 예에서와 같은 방법으로 시공되므로 상세 설명은 제3실시 예를 참조한다.To this end, FIG. 90 illustrates a state in which the respective reinforcing bars 571, 571 ′, 572 and 572 ′ of the side wall 531 and the lower slab 570 and the PC square pile wall inner reinforcing bars 511 are connected and fixed. Since it is constructed in the same manner as in the embodiment, a detailed description will be referred to the third embodiment.

도 91은 하부슬래브(570,570‘)와 중앙부(530)를 연결하는 상태를 나타내고 있으며 역시 제3실시 예에서와 같은 방법으로 시공되므로 상세 설명은 제3실시 예를 참조한다.FIG. 91 illustrates a state in which the lower slabs 570 and 570 'are connected to the central portion 530, and is also constructed in the same manner as in the third embodiment, so the detailed description will be referred to the third embodiment.

도 92는 Half PC구조 상부슬래브(540,540‘)의 일단과 측벽(531)의 상단간을 고정 연결하기 위한 단면을 나타내는데, 도면에서 보듯이 어느 한측의 Half PC구조 상부슬래브(540)와 측벽(531)간의 고정 상태를 도시하고 있으며, Half PC구조 상부슬래브(540,540’)가 시설되어질 때 각 Half PC구조 상부슬래브(540,540‘)에 PVC파이프(544)에 의해 천공된 홀을 통하여 지중에 피복으로 감싸며 사전에 미리 매입된 철근(543,543’)을 관통시킨 후 내벽체(580,580‘)의 철근(581,581’)과 연결 고정되도록 하였으며, 각각 측벽(531)을 이루는 PC벽체(500)과 PC사각파일벽체(501)에 매입되어 있는 철근(510,511)은 Half PC구조 상부슬래브(540,540‘)에 미리 매입된 PVC파이프(544)에 끼워지며 철근(542,542’)과 가스압접으로 고정시키고 콘크리트를 타설하여 마감토록 한다.FIG. 92 is a cross-sectional view for fixedly connecting between one end of a half PC structure upper slab 540 and 540 'and an upper end of the side wall 531. As shown in the drawing, the half PC structure upper slab 540 and the side wall 531 are shown in FIG. When the half PC structure upper slab (540,540 ') is installed, each half PC structure upper slab (540,540') is wrapped in the ground through the hole drilled by the PVC pipe 544. After penetrating the reinforcing bars (543,543 ') pre-buried in advance and connected to the bars (581,581') of the inner wall (580,580 '), respectively, the PC wall 500 and PC square pile wall (constituting the side wall 531) Reinforcing bars 510 and 511 embedded in 501 are fitted to PVC pipes 544 pre-buried in the upper slab 540 and 540 'of the half PC structure, and are fixed with reinforcing bars 542 and 542' and gas-welded, and finished with concrete. .

아울러, 상기한 내벽체(580)의 철근(581,581‘)과 교차 배치되는 배력철근과 측벽(531)을 이루는 PC사각파일벽체(501)에 매입되는 철근(510,511)중 내벽체(580,580‘)에 근접하는 철근(511)에 가로방향으로 띠철근(520)에 접하여 배치된 배력철근을 연결하기 위한 연결철근(582)이 상하로 각각 다수개 등 간격으로 이격시키며 구비되어야 한다. 이러한 연결구조는 지하도로의 좌우 상단측에 동일하게 적용될 것이다.In addition, in the inner wall (580, 580 ') of the reinforcing bars (510, 511) embedded in the PC square pile wall (501) forming a back-up reinforcement and the side wall 531 intersected with the reinforcement (581, 581') of the inner wall (580). Connection bars 582 for connecting the reinforcing bars arranged in contact with the strip reinforcing bar 520 in the transverse direction to the adjacent reinforcing bars 511 should be provided with a plurality of spaced apart at equal intervals. This connection structure will be equally applied to the upper left and right sides of the underground road.

또한, 상기 내벽체(580,580‘)에 매입되는 철근(581,581’)과 지중에 피복으로 감싸며 사전에 매입된 철근(543,543')을 Half PC구조 상부슬래브(540,540‘)의 PVC파이프(544)에 의해 천공된 홀을 통하여 연결되도록 하였다. In addition, the reinforcement (581, 581 ') to be embedded in the inner wall (580, 580') and the reinforcement (543, 543 ') that is pre-buried and covered with a covering in the ground by the PVC pipe (544) of the upper slab (540,540') of the half PC structure Connection was made through perforated holes.

도 93은 도면에서 보듯이 각 Half PC구조 상부슬래브(540,550/540‘,550)의 철근과 상호 연결하여 결합되도록 하였다.FIG. 93 is connected to the reinforcing bars of the upper slab 540, 550/540 ', 550 as shown in the figure.

도 94는 도면에서 보듯이 각 Half PC구조 상부슬래브(540,540’) 철근과 PC사각파일벽체(502)에서의 철근(532)이 결합되어야 한다. 즉, 각 Half PC구조 상부슬래브(540,540‘) 내부에 매입되는 각각의 철근(541,541'/542,542')을 CIP구근(500)의 중앙부 철근(532)과 서로 고정 연결하여야 하는데, 도면에서 보듯이 중앙부(530)를 이루는 PC사각파일벽체(502)의 상단측에 일측 Half PC구조 상부슬래브(540)를 설치한다. 이때 PC사각파일벽체(502)의 철근(532)이 일측 Half PC구조 상부슬래브(540)에 미리 설치한 PVC파이프(544)를 관통하도록 하는데, 일측 Half PC구조 상부슬래브(540)의 철근이 타측의 Half PC구조 상부슬래브의 철근과 연결을 위하여 일정길이의 철근(541,542)을 타설전에 지그재그로 배열하여 한곳에서만 연결이 되지 않도록 조치하여 타측 Half PC구조 상부슬래브(540’)의 타측철근(541’, 542’)의 단부와 커플러 또는 가스압접 등의 방법으로 연결 고정한 후 현장타설 콘크리트를 타설하여 각 Half PC구조 상부슬래브(540,540’)와 중앙부(530)를 견고하게 연결한다.FIG. 94 shows that the reinforcing bar 532 in each of the half PC structure upper slabs 540 and 540 'reinforcing bars and the PC square pile wall 502 is shown in FIG. That is, each of the reinforcing bars 541,541 '/ 542,542' embedded in each half PC structure upper slab 540,540 'must be fixedly connected to the central reinforcing bars 532 of the CIP bulb 500, as shown in the drawing. One side half PC structure upper slab 540 is provided on the upper side of the PC square pile wall 502 forming 530. At this time, the reinforcing bar 532 of the PC square pile wall 502 passes through the PVC pipe 544 pre-installed in the upper half slab 540 of one side, the reinforcing bar of the upper half slab 540 of the other half PC structure In order to connect the reinforcing bar of the upper slab of the double PC structure, the reinforcing bars (541,542) of certain lengths are arranged in a zigzag before being placed so that they cannot be connected in only one place. , 542 ') and fixed by connecting a coupler or a gas pressure welding method, and then cast the cast-in-place concrete to firmly connect each half PC structure upper slab (540,540') and the central portion 530.

한편, 도면부호 S는 하부슬래브(540)의 하면측에 구성되는 보호몰탈과 방수시트를 포함하는 보호몰탈 방수시트층을 가르킨다.Meanwhile, reference numeral S denotes a protective mortar waterproof sheet layer including a protective mortar and a waterproof sheet formed on the lower side of the lower slab 540.

본 발명의 방수방법은 제1실시 예에서의 방법을 그대로 적용하고 있으므로 상세 설명은 제1실시 예를 참조한다.Since the waterproof method of the present invention applies the method in the first embodiment as it is, the detailed description will be referred to the first embodiment.

한편 지하차도의 길이가 길어질 경우 제 1 실시예의 도 23 에서와 같이 일정간격의 길이마다 재료투입구(184)를 시설하여야 하는데, 그에 대한 상세한 사항은 제1실시 예에서와 같은 방법으로 설치하여야 하므로 제1실시 예에서의 설명의 내용을 참조하기로 한다.
On the other hand, when the length of the underground road is long, as shown in Fig. 23 of the first embodiment, the material inlet 184 should be provided for each length of a predetermined interval, and the details thereof should be installed in the same manner as in the first embodiment. Reference will be made to the description in the first embodiment.

제 6 6th 실시예Example

본 발명에 의한 제6실시예는 도 6a, b에 의한 바와 같이, 양 측벽과 중앙부를 이루는 CIP구근 시공공정(S10)과, 내부굴착 및 어스앙카 시공공정(S50-2), 양측 하부슬래브 시공공정(S60-1)과, 양측 내벽체 시공공정(S70)과, PSC빔 거치 및 상부슬래브 시공공정(S230), 마무리 시공공정(S80)으로 지하차도의 시공이 이루어진다.6A and 6B according to the present invention, as illustrated in FIGS. 6A and 6B, a CIP bulb construction process (S10) constituting both sidewalls and a central portion, an internal excavation and earth anchor construction process (S50-2), and both lower slab constructions The underground roadway is constructed by the step S60-1, the inner wall construction step S70, the PSC beam mounting and the upper slab step S230, and the finish step S80.

각 공정별로 나누어 본 발명의 공정 흐름과 이에 따른 각 구성을 설명한다.
The process flow of the present invention and each configuration according thereto will be described by dividing each process.

CIPCIP 구근 시공공정 - Bulb Construction Process- S10S10

본 공정은 지하차도를 건설할 위치의 벽체에 해당되는 측벽과 중앙부를 형성하기 위한 공정이다.This process is a process for forming the side wall and the central portion corresponding to the wall of the position to build the underground driveway.

이를 위해서 도면에서 보는 바와 같이 지하차도를 구성하기 위한 지역 범위내에서 중앙부와 양측 측면부에 각각 CIP구근(600)을 형성하되 중앙부에는 중앙 헌치 상단까지 형성하고 양측 측면부에는 벽체 즉 측벽을 지표까지 형성한다.To this end, as shown in the drawing, the CIP bulb 600 is formed at the center and both side surfaces within the region for constituting the underground driveway, but the central part is formed up to the upper end of the central haunch, and the wall, that is, the side wall is formed up to the surface at both sides. .

상기한 CIP(Cast-in-place) 구근(600)은 도 105 에서 보는 바와 같이 다수의 주철근(610,611)이 직사각형으로 배열 배치되고 그 주철근(610,611)을 감싸는 띠철근(120)을 등간격으로 이격시키며 주철근과 띠철근이 하나로 조합된 철근망태가 형성된다.The cast-in-place (CIP) bulb 600 has a plurality of cast bars 610 and 611 arranged in a rectangular shape as shown in FIG. 105, and spaced apart at intervals between the strip bars 120 surrounding the cast bars 610 and 611. Reinforcing wire mesh is formed by combining main reinforcing bars and band reinforcing bars.

이러한 철근망태의 최외곽을 에워싸는 관(이하 케이싱이라 칭한다.)을 형성한 후 그 내부에 콘크리트를 타설하여 양생함으로서, 하나의 유닛으로 이루어지는 원기둥 형태의 CIP구근(600)을 형성할 수 있고, 이와는 달리 CIP구근(600)이 삽입되기 위한 홀을 천공한 후 그 홀에 철근망태를 삽입 한 다음 콘크리트를 타설 양생하여 완성된 CIP구근(600)을 얻을 수 있을 것이다.By forming a tube (hereinafter referred to as a casing) that surrounds the outermost part of the reinforcing wire mesh, and then curing by pouring concrete therein, it is possible to form a cylindrical CIP bulb 600 consisting of a single unit, and Otherwise, after drilling the hole for the CIP bulb 600 is inserted, the reinforcement mesh is inserted into the hole, and then the concrete is poured to cure the finished CIP bulb 600.

한편, 이렇게 일정한 간격을 벌리면서 형성된 CIP구근(600)과 CIP구근(600) 사이에 미리 형성된 CIP구근(600)의 양 편측을 갈아내면서 천공하여 동형의 신CIP구근(115)을 새로이 형성하게 되는데 CIP구근(600)과 신CIP구근(615)은 상호 겹치도록 한다. 또한, 신CIP구근(615)의 형성과정은 CIP구근(600)과 같다.On the other hand, the gap between the two sides of the CIP bulb 600 formed in advance between the CIP bulb 600 and the CIP bulb 600 formed at regular intervals are punched while forming a new new CIP bulb 115 of the same type. CIP bulb 600 and the new CIP bulb 615 to overlap each other. In addition, the formation process of the new CIP bulb 615 is the same as the CIP bulb 600.

도면에서 도면부호 631은 CIP구근(600)과 신CIP구근(615)에 의해 이루어지는 측벽을 지칭하는데, 본 발명에서는 CIP구근(600)과 신CIP구근(615)에 의해 이루어지는 단위체로 CIP구근(600)이라 칭하고, 이 CIP구근(600)에 의해 일렬로 매입되어 지하 양측의 측벽을 각각 구분하여 도면부호로 표기하였다.In the drawings, reference numeral 631 denotes a sidewall formed by the CIP bulb 600 and the new CIP bulb 615. In the present invention, the CIP bulb 600 is a unit formed by the CIP bulb 600 and the new CIP bulb 615. ), And are embedded in a line by the CIP bulb 600, and the side walls on both sides of the basement are separated and denoted by reference numerals.

또한, 양측 측면부에서 벽체 즉 측벽을 이루는 CIP구근(600)을 형성할 때 철근망태의 일편측(벽체가 형성되는 내측을 지칭하고 이하 일편측이라 명명한다.)에는 합판등의 판넬(602)를 띠철근에 묶인 상태가 되도록 하여 콘크리트 타설시 합판등의 판넬(602) 내측으로는 콘크리트가 타설되지 않도록 하여야 하는데, 띠철근 내측에는 부분적으로 쫄대(603)를 배치한다.In addition, when forming the CIP bulb 600 constituting the wall, that is, the side wall at both side portions, the panel 602 such as plywood is provided on one side of the reinforcing mesh (hereinafter referred to as the one side). In order to be tied to the band reinforcement to prevent the concrete from being placed inside the panel 602, such as plywood when placing concrete, the band 603 is partially disposed inside the band reinforcing bar.

이는 내벽체 철근(681)의 가로방향의 배력철근과 CIP구근(600)의 띠철근에 이어 배치한 배력철근의 상호 연결이 용이하게 하기 위해서이다.This is to facilitate the interconnection of the reinforcing bars in the transverse direction of the inner wall reinforcement (681) and the reinforcing bars arranged after the band reinforcing bars of the CIP bulb (600).

또한 철근망태 일편측 코너 양측 주철근에 접하여 2개의 PC강연선을 배치하되 CIP구근(600) 일정길이에만 배치한다. In addition, two PC strands are arranged in contact with the main reinforcing bars on one side corner of the reinforcing wire mesh, but only in a certain length of the CIP bulb 600.

여기서 철근망태 일편측 코너 양측 주철근에 접하는 2개의 PC강연선(623)의 역할은 제1단의 어스앙카를 설치한 PSC빔이 거치되는 위치로 부터 최종 굴착선까지의 사이에 어스앙카를 시설하지 않아도 외부작용 부재력에 대처할 수 있도록 CIP구근(600)의 내하력을 증강시키기 위한 구조로서 매 CIP구근(600)마다 배치한다. Here, the role of two PC strands 623 in contact with the main reinforcing bars on one side corner of the reinforcing wire mesh does not need to install an earth anchor between the position where the PSC beam installed with the first anchor earth anchor is mounted and the final digging line. The CIP bulb 600 is disposed in every CIP bulb 600 as a structure for enhancing the load capacity of the CIP bulb 600 to cope with an external action member force.

이러한 CIP구근(600)은 지지파일 또는 부력방지 파일로서 역할을 겸하고 있는데 마찰력을 증가시키기 위한 구조로서 일정간격의 마찰 저항력 증가장치를 CIP구근(100)마다 하단에만 배치하는데 제1실시 예에서와 같은 방법으로 시공한다.The CIP bulb 600 serves as a support pile or a buoyancy prevention pile, and as a structure for increasing friction, a frictional resistance increasing device having a predetermined interval is disposed only at the bottom of each CIP bulb 100 as in the first embodiment. Construct by the method.

부력방지용 또는 지지용 마찰 저항력 증가방법에 대하여는 2가지의 방법을 제1실시 예에서 도 106, 도 107에 표현하고 있는데, 이 모두 일정 간격의 CIP구근(600)을 양측벽체 또는 중앙부로서의 역할 길이 이상으로 형성하는 시공을 하여야 하며 이때 CIP구근(600) 하단부에 이러한 방법을 적용하는 것이다. The buoyancy prevention or support friction resistance increase method is shown in Figs. 106 and 107 in the first embodiment, both of which are at least as long as the role of the CIP bulb 600 at regular intervals as both side walls or the central portion. The construction should be to be formed at this time is to apply this method to the lower end of the CIP bulb 600.

우선 도 106에서 2개소의 마찰력저항철근(104)을 고무슬리브(105)에 끼워 “V”모양으로 절곡하고 교차시켜 “+”방향으로 묶은 다음 CIP구근(100) 하단부 일정한 위치에 다수의 종간격을 유지하며 띠철근(120)위에 배치하게 되는데 이때 중심부에 PC강선(106)을 배치한 상태에서 CIP구근(100)을 형성하기 위한 콘크리트를 일정 높이로 타설하면서 콘크리트가 양생되기 전 케이싱을 들어올릴 때 PC강선(106)을 잡아당기게 되면 고무슬리브(105)에 끼워진 양쪽의 마찰력저항철근(104)이 시계와 반시계 방향으로 회전하면서 “V”모양에서 “-”모양으로 펴지게 되는데 이렇게 양생되어 펴진 마찰 저항철근(104)이 CIP구근(100)에서 돌출되게 되므로 부력 작용시 구조체의 상승을 저지시키는 앵커체로서의 역할과 지지말뚝의 역할을 하게 된다.First, in FIG. 106, two frictional resistance steel bars 104 are inserted into the rubber sleeve 105, bent in a “ V” shape, crossed and bundled in the “+” direction, and then a plurality of longitudinal intervals are placed at a constant position at the bottom of the CIP bulb 100. It is placed on the band reinforcement 120 while maintaining the PC steel wire 106 in the center while placing the concrete to form the CIP bulb 100 to a certain height while lifting the casing before the concrete is cured When the PC steel wire 106 is pulled out, both of the frictional resistance steel bars 104 inserted into the rubber sleeve 105 are rotated in a clockwise and counterclockwise direction to be unfolded in a “-” shape from a “ V ” shape. Since the friction-resistant reinforcing bar 104 is protruded from the CIP bulb 100, it acts as an anchor and a support pile to prevent the rise of the structure during buoyancy.

도 107에서 4개소의 마찰력저항철근(604)을 고무슬리브(605)에 끼워 “V”모양에 양 날개가 달린 모양으로 날개철근(607)을 이루고 교차시켜 “+”방향으로 묶은 다음 CIP구근(600) 하단부 일정한 위치에 다수의 종간격을 유지하며 띠철근(620)위에 배치하게 되는데 이때 중심부에 PC강선(606)을 배치한 상태에서 CIP구근(600)을 형성하기 위한 콘크리트를 일정 높이로 타설하면서 콘크리트가 양생되기 전 케이싱을 들어올릴 때 PC강선을 잡아당기게 되면 고무슬리브(605)에 끼워진 양쪽의 마찰력저항철근(604)이 “V”모양에서 “-”모양으로 바뀌면서 날개철근(607)을 수평방향으로 밀어 돌출시킨 상태가 되는데 이렇게 양생되어 펴진 날개철근(607)이 CIP구근(600)에서 돌출되게 되므로 부력 작용시 구조체의 상승을 저지시키는 앵커체로서의 역할과 지지말뚝의 역할을 하게 된다.In Fig. 107, four frictional resistance bars 604 are inserted into the rubber sleeve 605 to form a wing reinforcement 607 in the shape of both wings in a “ V ” shape, crossed and tied in the direction of “+”, and then CIP bulbs ( 600) It is placed on the band reinforcement 620 while maintaining a plurality of longitudinal intervals at a constant position of the lower end, in which the concrete to form the CIP bulb 600 in a state where the PC steel wire 606 is placed at a certain height If you pull out the PC steel wire while lifting the casing before the concrete is cured, the frictional resistance bars 604 of both sides of the rubber sleeve 605 change from “ V ” shape to “-” shape. It is pushed in the horizontal direction to protrude. As the cured and expanded wing reinforcement 607 protrudes from the CIP bulb 600, it acts as an anchor body to prevent the rise of the structure during buoyancy and the reverse of the support pile. A it is.

지지력을 증가시키기 위한 방법으로도 상기와 같은 방법으로 일정 간격의 CIP구근(600)을 양측벽체 또는 중앙부로서의 역할 길이 이상으로 형성하는 시공을 하여야 하며 이때 CIP구근(600) 하단부에 마찰 저항력 증가방법을 적용하는 것이다. As a method for increasing the bearing capacity, a method of forming a CIP bulb 600 at a predetermined interval or longer as a role length as a side wall or a central portion should be performed in the same manner as above, and at this time, a method of increasing frictional resistance at the lower end of the CIP bulb 600 is employed. To apply.

이와 같은 CIP구근(600)은 지하차도를 중심으로 좌우 양측으로 각각 이격 되는 거리의 위치에서 지하에 수직상 일정 간격을 벌리면서 다수열 매입되어 측벽을 형성하게 된다. Such CIP bulb 600 is embedded in a plurality of rows while forming a side wall at a predetermined distance vertically in the basement at the distance of each spaced left and right sides around the underground roadway.

그러나, 이러한 CIP구근(600)은 토사층에서만 가능하고 암반구간에서는 불가능한 제약조건이 따른다.However, these CIP bulbs 600 are subject to constraints that are only possible in soil layers and impossible in rock sections.

이것은 지반을 굴착하는 오거의 장비가 암반을 천공할 수 없기 때문인데 이럴 경우 2.0m마다 암반측까지 천공이 가능한 T4 장비를 이용하여 내부굴착시 구근(600)을 형성하고 그 사이는 토사층까지만 CIP구근(600)을 형성한 다음 암반구간까지 내부굴착하여 CIP 받침앵커(608)를 시설하고 내부굴착을 계속하되 토사층까지만 시설된 CIP구근 하단에서 하부슬래브 버림콘크리트 하단까지 암반을 절취(“A”)하여 CIP 철근을 이어내리고 분말방수제가 혼합된 콘크리트를 타설하면 견고한 내벽체(680,680‘)가 형성된다.
This is because the auger's equipment that excavates the ground can't puncture the rock. In this case, the bulb 600 is formed during internal excavation using T4 equipment that can be drilled to the rock side every 2.0m. (600) and then excavated internally to the rock section to equip the CIP support anchor (608) and continue the internal excavation, but cut the rock from the lower end of the lower slab cast concrete (“A”) to the bottom of the CIP bulb equipped only to the soil layer. When the CIP reinforcement is continued and the concrete mixed with the powder waterproofing agent is poured, a solid inner wall (680, 680 ') is formed.

내부굴착 및 Internal excavation and 어스앙카Earthanka 시공공정 -  Construction Process- S50S50 -2-2

본 공정은 상기한 각 CIP구근(600)의 공정을 완료한 후 CIP구근(600)의 머리부분(즉 PSC빔이 거치되는 부분)에 1단의 어스앙카를 시설하여 측벽(631)의 안정을 도모하는 것이다.In this process, after completing the above-described process of each CIP bulb 600, a single-level ground anchor is installed on the head of the CIP bulb 600 (that is, the portion where the PSC beam is mounted) to stabilize the sidewall 631. It is to plan.

이후 내부 굴착을 계속하여 최종굴착선까지 이르게 되는데 이때 상기 CIP구근(600) 형성 공정에서 긴장 정착하였던 PC강연선(623)이 측벽(631)에 작용되는 부재력을 지탱하므로 안정이 도모되는 것이다.
Afterwards, the internal excavation is continued to reach the final excavation line. At this time, the PC strand wire 623, which was tension-fixed in the CIP bulb 600 forming process, supports the member force acting on the side wall 631, thereby achieving stability.

양측 하부슬래브 시공공정 - Both Side Slab Construction Process- S60S60 -1-One

본 공정은 전술한 내부굴착 및 어스앙카 시공공정(S50-2)이 완료된 후, 하부슬래브(670,670’)를 시공하여 지하차도를 형성하기 위한 공정이다.This process is a process for forming the underground roadway by constructing the lower slab (670,670 ') after the above-described internal drilling and earth anchor construction process (S50-2) is completed.

양측의 굴착된 공간에 버림콘크리트와 외부시트 방수층을 형성한 후 해당 굴착 부분의 측벽(631)과 그 하단으로 하부슬래브(670,670’)를 타설하게 된다.After forming the discarded concrete and the outer sheet waterproof layer in the excavated space on both sides, the lower slab (670,670 ') is poured into the side wall 631 and the bottom of the excavated portion.

여기서 상기 하부슬래브(670,670’)는 도면에서 보는 바와 같이 지하차도의 바닥면에 타설되는 타설체를 의미하고, 측벽(161)의 내측에 접하는 헌치부까지 타설한다.Here, the lower slab (670,670 ') refers to the pour body to be poured on the bottom surface of the underground driveway, as shown in the drawing, and pours to the haunting portion in contact with the inner side of the side wall (161).

상기와 같이 양측의 공간을 굴착 시공한 후 하부슬래브(670,670’)의 타설공정이 완료되면 완성된 형태의 지하차도를 구성할 수 있게 된다.After excavation and construction of the space on both sides as described above it is possible to construct a completed underground roadway when the casting process of the lower slab (670,670 ') is completed.

한편, 도 101에서 보듯이 본 공정에서 하부슬래브(670,670’)를 생략할 수 있는데 이때는 S10공정에서의 CIP근입 심도가 적정길이를 확보하여야 하고 S50-2 공정에서의 어스앙카 시설을 영구적으로 필요로 할 수 있다.
On the other hand, as shown in Figure 101, the lower slab (670,670 ') can be omitted in this process, in this case, the depth of CIP intrusion in the S10 process should ensure the appropriate length and permanently requires the earth anchor facility in the S50-2 process can do.

양측 Both sides 내벽체Inner wall 시공공정 -  Construction Process- S70S70

하부슬래브 양측으로 일체로 수직상 연결되어 측벽(631)의 내측으로 타설되는 일부의 내벽체(680,680‘)는 하부슬래브(670,670‘)에 연이어 시공되어지며 잔여 내벽체(680“)는 상기의 일부의 내벽체(680,680’)가 양생되어진 후 어스앙카를 철거하면서 시공되어진다. Some of the inner walls 680 and 680 ', which are integrally vertically connected to both sides of the lower slab and poured into the side walls 631, are constructed in succession to the lower slabs 670 and 670', and the remaining inner walls 680 'are partially formed. After the inner wall (680,680 ') is cured, it is constructed while removing the earth anchor.

이렇게 형성되는 내벽체(680,680‘)는 자체의 강성을 확보하기 위하여 내벽체(680,680‘)에 매입된 철근(681)의 교차 배치되는 배력철근과 측벽(631)을 이루는 CIP구근(600)에 매입되는 철근(610,611)중 내벽체(680)에 근접하는 철근(611)에 가로방향으로 띠철근(620)에 접하여 배치된 배력철근을 연결하기 위한 연결철근(682)이 상하로 각각 다수개 등 간격 이격 시키며 구비되어야 한다.
The inner wall bodies 680 and 680 'formed as described above are embedded in the CIP bulb 600 constituting the sidewalls 631 and the reinforcement bars intersected with the reinforcing bars 681 embedded in the inner wall bodies 680 and 680' so as to secure their rigidity. Among the reinforcing bars 610 and 611, the connecting bars 682 for connecting the reinforcing bars arranged in contact with the strip reinforcing bars 620 in the transverse direction to the reinforcing bars 611 adjacent to the inner wall body 680 are spaced up and down, respectively. It should be spaced apart.

PSCPSC 빔 거치 및 상부슬래브 시공공정 - Beam Mounting and Upper Slab Construction Process- S230S230

상기한 공정(S70)을 거쳐 내벽체(680,680‘)의 설치 시공이 완료되면 PSC빔(650)을 거치하게 되는데, 내벽체(680,680’) 시공시 매입된 철근(681)과 CIP구근(100)에 매입되어 있는 철근(110,111) 중 내벽체(680,680‘)에 근접하는 철근(111) 이 PSC빔(650) 내부에 미리 구성되어 있는 PVC관(651)을 관통하여 상부슬래브(640)에 배치 되어지는 또 다른 철근(641,642)과 연결 고정되도록 하였다.When the installation of the inner wall (680,680 ') is completed through the above-described process (S70), the PSC beam 650 is mounted, and the reinforcement 681 and the CIP bulb (100) purchased when the inner wall (680,680') is constructed. Among the reinforcing bars 110 and 111 embedded in the reinforcing bar 111 close to the inner wall 680 and 680 ′, the reinforcing bar 111 penetrates the PVC pipe 651 pre-configured inside the PSC beam 650 and is disposed on the upper slab 640. The paper was connected to another bar (641, 642).

이와같이 PSC빔 거치 공정을 양측 내벽체 시공공정(S70) 후에 하는 것은 PSC빔 거치 후 이어지는 후속공정이 길어지므로 발생할 수 있는 빔의 전도등 위험을 줄일 수 있고 보다 안정적인 시공공정을 갖추기 위함이다.In this way, the PSC beam mounting process after the inner wall construction process (S70) on both sides is to reduce the risk of beam conduction, etc., which can occur because the subsequent process is long after the PSC beam mounting and to have a more stable construction process.

또한, CIP구근(100)에 매입되는 철근(110,111)중 외측에 연하여 배치된 철근(110)은 상부슬래브(640)에 배치 되어지는 또 다른 철근(642)과 연결 고정되도록 하였으며, 연단철근과도 측벽(131) 상단 우각부에서 고정 연결되도록 하므로 PSC빔(650)이 외부 작용하중에 의하여 뒤틀림이나 변위가 발생치 않도록 영구 고정하게 된다. In addition, the reinforcing bar (110) arranged in the outer side of the reinforcing bars (110, 111) to be purchased in the CIP bulb 100 is to be connected and fixed to another reinforcing bar (642) disposed on the upper slab 640, In addition, since the upper sidewall 131 is fixedly connected to the upper side wall, the PSC beam 650 is permanently fixed so that no distortion or displacement occurs due to an external working load.

한편 PSC빔(650)은 제작시 단부에 내벽체(680)의 철근(681)이 관통할 수 있는 PVC관(651)을 매설하고, 측벽(131)과 고정 연결할 수 있도록 단부에 연단철근(652)을 배치하였으며, 우각부 부모멘트를 저감시킬 수 있도록 PC강연선(653)을 PSC빔(650) 연단부 상단에 배치하는 것으로 제작하였다.Meanwhile, the PSC beam 650 embeds a PVC pipe 651 through which the reinforcement 681 of the inner wall body 680 penetrates at the end and fabricates the end-stage reinforcement at the end so as to be fixedly connected to the side wall 131. ), And the PC strand 653 was placed on top of the edge of the PSC beam 650 so as to reduce the right parent portion.

이러한 PSC빔(650)에 설치된 PC강연선(653)을 긴장 정착시키는 것은 상기한 내벽체(680,680‘) 강성과 PSC빔(650)의 강성과의 차에서 오는 불균등 부모멘트로 인하여 내벽체(680,680‘)에 불리한 구조적 내력이 전달되지 않도록 하기 위함이다.The tension fixing of the PC strands 653 installed in the PSC beam 650 is caused by the inequality of the inner wall 680,680 'and the difference between the rigidity of the PSC beam 650 and the inner wall 680,680'. This is to prevent the transmission of the structural strength which is disadvantageous to).

또한 CIP구근(100) 내에 매설되어 CIP구근(100) 상단에 긴장 정착한 PC강연선(123)은 PSC빔(650) 내부에 미리 구성되어 있는 PVC관(651)을 관통하여 재 긴장 정착을 하여주므로 상기에 언급된 강성차를 줄여주게 되며 아울러 부모멘트가 저감되는 효과를 거둘 수 있어 전체 구조에서 내하력이 증가되는 장점을 지니게 되고 향후에 발생될 수 있는 하자나 유지관리 비용을 줄일 수 있는 것이다.In addition, since the PC strand 123 buried in the CIP bulb 100 and tension-fixed on the upper part of the CIP bulb 100 penetrates the PVC pipe 651 pre-configured inside the PSC beam 650, it re-tensions and stabilizes. The stiffness difference mentioned above can be reduced, and the effect of reducing the parent moment can be reduced, which has the advantage of increasing the load capacity in the entire structure and can reduce the defects or maintenance costs that may occur in the future.

한편, PSC빔(650)간의 간격은 가로보(654)를 두므로 횡방향 변위를 방지토록 하며 PSC빔(650) 군이 일체로 거동할 수 있도록 하며 PSC빔(650) 군의 연단부는 배면슬래브(660)를 설치하여 배면토사의 유입을 방지하고 방수층을 형성하도록 한다.On the other hand, the interval between the PSC beam 650 has a horizontal beam 654 to prevent lateral displacement and to allow the PSC beam 650 group to act integrally, and the edge of the PSC beam 650 group is the rear slab ( 660) to prevent the introduction of rear soil and to form a waterproof layer.

또한, 본 발명에서 상부슬래브는 PSC빔(650)간을 서로 연결토록 하므로 가로보(654)와 함께 부재력의 횡방향 전달을 용이롭게 하는 구조적 역할을 하는 것이다. 더불어 외부의 토사 유입을 방지하고 방수층을 형성하도록 한다.In addition, in the present invention, the upper slab is to play a structural role to facilitate the transverse transmission of the member force with the cross beam 654, so as to connect between the PSC beams 650 to each other. In addition, to prevent the inflow of external soil and to form a waterproof layer.

이와 같이 상부슬래브(640)와 배면슬래브(660)를 타설 시공한 후에는 표면을 복토하게 되는 복토공정을 거쳐야 한다.
As such, after placing the upper slab 640 and the rear slab 660, the surface must be covered with a cover process.

마무리 시공공정 - Finishing Construction Process- S80S80

상기와 같은 공정(S230)이 완료되면, 복토가 완료된 지표에 아스콘을 포설하여 차량을 통행시키고, 지하차도 내부의 보도 및 전기시설, 타일과 아스콘 등을 시설하여 지하차도의 공정을 마무리 한다.
When the process (S230) as described above is completed, ascon is installed on the completed cover of the cover to pass the vehicle, and to complete the process of the underground driveway by installing the sidewalk and electric facilities, tiles and ascon inside the underground driveway.

이상과 같은 일련의 공정을 거쳐, CIP구근(600)을 이용한 지하차도를 시공하게 되는데 있어서, 도 102는 측벽(631)과 하부슬래브(670,670‘)의 각 철근(671)(672)의 연결 고정되는 상태를 나타내고 있다.In the construction of the underground roadway using the CIP bulb 600 through a series of processes as described above, FIG. 102 illustrates the connection fixing of the reinforcing bars 671 and 672 of the side walls 631 and the lower slabs 670 and 670 '. It shows the state which becomes.

도면에서 보듯이 내벽체의 내측철근(681)의 배력철근이 측벽(631)을 이루는 각 CIP구근(600)에 매입되는 철근(610,611) 중, 내벽체(680,680‘)에 접하는 부분인 판넬(102)에 의해 절개되어지는 부분에 의해 노출된 철근(611)의 띠철근(620)과 연결 고정되도록 하여 하부슬래브(670,670’)와 측벽(631) 하단이 연결되도록 구성하였으며, 이러한 연결 구조는 지하도로의 좌우 하단측에 동일하게 적용될 것이다.As shown in the drawing, the panel 102 which is a part of the reinforcing bars of the inner reinforcement 681 of the inner wall contacting the inner wall 680, 680 'among the reinforcing bars 610 and 611 embedded in each CIP bulb 600 forming the side wall 631. The bottom slab 670, 670 'and the lower sidewall 631 are connected to each other so that the bottom slab 670 and 670' are connected to the strip reinforcing bar 620 of the rebar 611 exposed by the part to be cut. The same will be applied to the lower left and right side of the.

도 103은 하부슬래브(670,670‘)와 중앙부(630)를 연결하는 상태를 나타내고 있으며 가로방향으로 천공되는 다수의 가로공(601)을 형성하고, 그 가로공(601)으로 하부슬래브(670)에 매입되는 철근(671,672)을 통과시켜 타측의 하부슬래브(670’)에 매입되는 다른 철근(671‘, 672’)과 연결 고정되도록 한 상태를 도시하였으며, 헌치에 연하는 스터럽 철근(673)을 배치하고 있다.FIG. 103 illustrates a state in which the lower slabs 670 and 670 'are connected to the central portion 630, and a plurality of horizontal holes 601 are formed in the horizontal direction, and the horizontal slabs 601 are formed in the lower slab 670. Passed reinforcing bars (671,672) is shown connected to the other reinforcing bars (671 ', 672') to be buried in the lower slab (670 ') of the other side, and the stirrup reinforcement (673) connected to the haunch is arranged Doing.

도 104는 상부슬래브(640)의 일단과 측벽(631) 및 내벽체(680,680‘)를 고정 연결하기 위한 단면을 나타내는데, 도면에서 보듯이 어느 한측의 상부슬래브(640)와 측벽(131)과 내벽체(680,680‘)간의 고정 상태를 도시하고 있다.FIG. 104 shows a cross section for fixedly connecting one end of the upper slab 640, the side walls 631, and the inner walls 680 and 680 ', and as shown in the drawing, the upper slab 640 and the side wall 131 and the inner side of the upper slab 640. The fixed state between the walls 680 and 680 'is shown.

한편, PSC빔은 측벽(631) 및 내벽체(680,680‘) 상에 놓이게 되는데 이때 측벽(631)을 구성하는 철근(610,611)중 내벽에 가까운 철근(611)과 내벽체철근(681)은 PSC빔에 미리 매입되어 있는 PVC파이프를 관통하게 되어 상부슬래브(640) 철근(641,642)와 결속하게 되고 상부슬래브(640) 철근(642)은 측벽(631)의 철근(610)과 고정 연결하여 PSC빔이 움직이지 못하도록 구속하는데, 여기에 PSC빔 연단에서 돌출된 연단철근(644)을 더하여 구속하고 있다.On the other hand, the PSC beam is placed on the side walls 631 and the inner walls 680 and 680 ', wherein the reinforcing bars 611 and inner wall reinforcement 681 close to the inner wall of the reinforcing bars 610 and 611 constituting the side walls 631 are PSC beams. Through the PVC pipe that is pre-buried in the upper slab 640, the reinforcing bar (641, 642) and the upper slab 640, the reinforcement (642) is fixed to the reinforcing bar 610 of the side wall (631) PSC beam It restrains it from moving, and adds restraint reinforcing bar 644 protruding from the PSC beam end.

도 105는 도면에서 보는 바와 같이 내벽체(680,680‘)의 외측과 접하면서 전술한 연결철근(682)에 의하여 연결되기 위해서는 측벽(631)을 이루는 CIP구근(600)의 일측면은 일부가 절단되어 CIP구근(600)에 매입되는 철근(610,611)을 감싸는 띠철근(620)이 미리 설치한 쫄대(603)등에 의하여 외부로 노출되도록 합판 등의 판넬(602)에 의해 마감처리 되도록 하여야 한다.105 is one side of the CIP bulb 600 constituting the side wall 631 in order to be connected to the outside of the inner wall (680, 680 ′) by the connecting reinforcing bar 682 as shown in the figure The band reinforcing bars 620 surrounding the reinforcing bars 610 and 611 to be embedded in the CIP bulb 600 should be finished by a panel 602 such as plywood so as to be exposed to the outside by a pre-installed band 603 or the like.

이와 같이 시공되기 위해서 양 측벽 CIP구근 시공공정(S10)에서 측벽(631)을 이루기 위한 CIP구근(600) 형성시 일측을 절개하도록 판넬(602)을 형성하여 타설되도록 하는 것이 바람직하다.In order to be constructed as described above, it is preferable to form the panel 602 so that one side is cut to form the CIP bulb 600 for forming the sidewall 631 in the sidewall CIP bulb construction process (S10).

상기와 같이 판넬(602)에 의해 절개면을 얻게 되는 측벽(631)에는 측벽(631)을 구성하는 CIP구근(600)에 매입되는 철근(610,611)을 감싸는 띠철근(620)을 미리 설치한 쫄대(603)등에 의하여 외부로 노출된 상태에서 배력철근을 배치하고, 이 배력철근과 띠철근을 묶어 전술한 가로방향으로 연결하기 위한 연결철근(682)에 의해 상기한 내벽체(680,680‘)의 철근(681)과 교차 배치되는 배력철근과 연결될 수 있는 것이다.The side wall 631, which is obtained by the panel 602 as described above, is provided with a band reinforcing bar 620, which wraps the reinforcing bars 610 and 611 embedded in the CIP bulb 600 constituting the side wall 631. The reinforcing bars of the inner wall bodies 680 and 680 'are disposed by connecting reinforcing bars in a state exposed to the outside by the 603 and the like, and connecting bars 682 for connecting the reinforcing bars and the band bars in the above-described horizontal direction. It can be connected to the reinforcing bars intersected with (681).

한편, 도면부호 S는 하부슬래브(670,670‘)의 하면측에 구성되는 보호몰탈과 방수시트를 포함하는 보호몰탈 방수시트층을 가르킨다.Meanwhile, reference numeral S denotes a protective mortar waterproof sheet layer including a protective mortar and a waterproof sheet formed on the lower surface side of the lower slab 670, 670 '.

본 발명의 방수방법은 제1실시 예에서의 방법을 그대로 적용하고 있으므로 상세 설명은 제1실시 예를 참조한다.Since the waterproof method of the present invention applies the method in the first embodiment as it is, the detailed description will be referred to the first embodiment.

한편 지하차도의 길이가 길어질 경우 일정간격의 길이마다 재료투입구를 시설하여야 하는데, 그에 대한 상세한 사항은 제1실시 예에서와 같은 방법으로 설치하여야 하므로 제1실시 예에서의 설명의 내용을 참조하기로 한다.
On the other hand, if the length of the underground road is long, the material inlet should be provided for each length of a predetermined interval, and the details thereof should be installed in the same manner as in the first embodiment, so the description of the description in the first embodiment will be referred to. do.

제 7 Seventh 실시예Example

본 발명은 도 108 에 의한 바와 같이, 양 측벽과 중앙부를 이루는 CIP구근 시공공정(S10)과, 내부굴착 및 어스앙카 시공공정(S50-2), 양측 하부슬래브 시공공정(S60-1)과, 양측 내벽체 시공공정(S70)과, 마무리 시공공정(S80)으로 지하차도의 시공이 이루어진다.
본 발명에서의 제 7 실시예는 U-Type 구조의 상면이 개방되는 지하도로에 적용되기 위한 것이다.
일반적으로 지하도로는 Box 구조와 U-Type 구조로 함께 구성되는데, Box 구조의 경우는 상부슬래브를 덮은 구조 형식으로서 상부 노면 교통이 재하될 수 있는 형식으로 주로 교차로에 설치 시공되고, U-Type 구조인 경우는 상면이 개방된 구조 형식으로 지하도로를 이용하기 위한 차량이 진입하고 진출하는데 상면이 저촉되지 않도록 개방한 구조를 일컫는 것으로 본 발명의 제 7 실시예에서는 이러한 U-Type 구조를 합벽식 공법으로 시공하기 위한 방법을 제시하고자 한다.
108, the CIP bulb construction process (S10) forming both sidewalls and the center portion, the internal excavation and earth anchor construction process (S50-2), both the lower slab construction process (S60-1), The construction of the underground roadway is performed by both inner wall construction steps (S70) and the finishing construction step (S80).
A seventh embodiment of the present invention is to be applied to the underground road that the upper surface of the U-Type structure is open.
In general, the underground road is composed of a box structure and a U-type structure. In the case of the box structure, the upper slab is covered and the upper road traffic can be loaded. In the case of, the open top surface is an open structure in which a vehicle for using an underground road enters and exits, and refers to a structure that is opened so that the top surface does not interfere with each other. I would like to suggest a method for construction.

각 공정별로 나누어 본 발명의 공정 흐름과 이에 따른 각 구성을 설명한다.
The process flow of the present invention and each configuration according thereto will be described by dividing each process.

CIPCIP 구근 시공공정 - Bulb Construction Process- S10S10

본 공정은 지하차도를 건설할 위치의 벽체에 해당되는 측벽과 중앙부를 형성하기 위한 공정이다.This process is a process for forming the side wall and the central portion corresponding to the wall of the position to build the underground driveway.

이를 위해서 도면에서 보는 바와 같이 지하차도를 구성하기 위한 지역 범위내에서 중앙부와 양측 측면부에 각각 CIP구근(700)을 형성하되 중앙부에는 중앙 헌치 상단까지 형성하고 양측 측면부에는 벽체 즉 측벽을 지표까지 형성한다.To this end, as shown in the drawing, CIP bulbs 700 are respectively formed in the center and both side surfaces within the region for constituting the underground road, but the central part is formed up to the upper end of the central haunch and the walls, ie, side walls, are formed on both sides. .

상기한 CIP(Cast-in-place) 구근(700)은 도 116 에서 보는 바와 같이 다수의 주철근(710,711)이 직사각형으로 배열 배치되고 그 주철근(710,711)을 감싸는 띠철근(720)을 등간격으로 이격시키며 주철근과 띠철근이 하나로 조합된 철근망태가 형성된다.As described above, the cast-in-place (CIP) bulb 700 has a plurality of main reinforcing bars 710 and 711 arranged in a rectangular shape as shown in FIG. 116, and spaced apart at intervals between the strip reinforcing bars 720 surrounding the main reinforcing bars 710 and 711. Reinforcing wire mesh is formed by combining main reinforcing bars and band reinforcing bars.

이러한 철근망태의 최외곽을 에워싸는 관(이하 케이싱이라 칭한다.)을 형성한 후 그 내부에 콘크리트를 타설하여 양생함으로서, 하나의 유닛으로 이루어지는 원기둥 형태의 CIP구근(700)을 형성할 수 있고, 이와는 달리 CIP구근(700)이 삽입되기 위한 홀을 천공한 후 그 홀에 철근망태를 삽입 한 다음 콘크리트를 타설 양생하여 완성된 CIP구근(700)을 얻을 수 있을 것이다.By forming a tube (hereinafter referred to as a casing) that surrounds the outermost part of the reinforcing wire mesh, and then curing by pouring concrete therein, it is possible to form a cylindrical CIP bulb 700 consisting of a single unit, and Otherwise, after drilling the hole for the CIP bulb 700 is inserted, the reinforcement mesh is inserted into the hole, and then the concrete is poured to cure the finished CIP bulb 700.

한편, 이렇게 일정한 간격을 벌리면서 형성된 CIP구근(700)과 CIP구근(700) 사이에 미리 형성된 CIP구근(700)의 양 편측을 갈아내면서 천공하여 동형의 신CIP구근(715)을 새로이 형성하게 되는데 CIP구근(700)과 신CIP구근(715)은 상호 겹치도록 한다. 또한, 신CIP구근(715)의 형성과정은 CIP구근(700)과 같다.On the other hand, the gap between the CIP bulb 700 and the CIP bulb 700 formed between the gaps formed in the gap between the pre-formed CIP bulb 700 is formed by forming a new CIP bulb 715 of the same type. CIP bulb 700 and the new CIP bulb 715 to overlap each other. In addition, the formation process of the new CIP bulb 715 is the same as the CIP bulb 700.

도면에서 도면부호 731은 CIP구근(700)과 신CIP구근(715)에 의해 이루어지는 측벽을 지칭하고, 도면부호 730 또한 CIP구근(700)과 신CIP구근(715)에 의해 이루어지는 중앙부 벽체 또는 기둥 즉 중앙부를 의미하는 것으로, 본 발명에서는 CIP구근(700)과 신CIP구근(715)에 의해 이루어지는 단위체로 CIP구근(700)이라 칭하고, 이 CIP구근(700)에 의해 일렬로 매입되어 지하 양측의 측벽을 각각 구분하여 도면부호로 표기하였다.In the drawing, reference numeral 731 denotes a side wall formed by the CIP bulb 700 and the new CIP bulb 715, and reference numeral 730 also denotes a central wall or column formed by the CIP bulb 700 and the new CIP bulb 715. In the present invention, the unit formed by the CIP bulb 700 and the new CIP bulb 715 is referred to as a CIP bulb 700, and is embedded in a row by the CIP bulb 700 to form sidewalls on both sides of the basement. Are separated by reference numerals.

또한, 양측 측면부에서 벽체 즉 측벽을 이루는 CIP구근(700)을 형성할 때 철근망태의 일편측(벽체가 형성되는 내측을 지칭하고 이하 일편측이라 명명한다.)에는 합판등의 판넬(702)를 띠철근에 묶인 상태가 되도록 하여 콘크리트 타설시 합판등의 판넬(702) 내측으로는 콘크리트가 타설되지 않도록 하여야 하는데, 띠철근 내측에는 부분적으로 쫄대(703)를 배치한다.In addition, when forming a CIP bulb 700 forming a wall, that is, a side wall at both side portions, a panel 702 such as plywood is provided on one side (referred to as an inner side where a wall is formed and hereinafter referred to as one side) of the reinforcing wire mesh. In order to be tied to the band reinforcement to prevent the concrete from being poured inside the panel 702 such as plywood when placing the concrete, the band 703 is partially disposed inside the band reinforcing bar.

이는 내벽체 철근(781)의 가로방향의 배력철근과 CIP구근(700)의 띠철근에 이어 배치한 배력철근의 상호 연결이 용이하게 하기 위해서이다.This is to facilitate the interconnection of the reinforcing bars in the transverse direction of the inner wall reinforcing bars 781 and the reinforcing bars arranged after the strip reinforcing bars of the CIP bulb 700.

또한, 철근망태 일편측 코너 양측 주철근에 접하여 2개의 PC강연선을 배치하되 CIP구근(700) 일정길이에만 배치한다. In addition, two PC strands are arranged in contact with the main reinforcing bars on both sides of the reinforcing wire mesh one side corner, but only a certain length of the CIP bulb 700.

여기서 철근망태 일편측 코너 양측 주철근에 접하는 2개의 PC강연선(723)의 역할은 제1단의 어스앙카를 설치한 위치로 부터 최종 굴착선까지의 사이에 어스앙카를 시설하지 않아도 외부작용 부재력에 대처할 수 있도록 CIP구근(700)의 내하력을 증강시키기 위한 구조로서 매 CIP구근(700)마다 배치한다. Here, the role of the two PC strands 723 in contact with the main reinforcing bars on one side corner of the reinforcing wire mesh is to cope with the absence of external action without installing the earth anchor between the position of the first anchor earth and the final digging line. It is arranged in every CIP bulb 700 as a structure for enhancing the load capacity of the CIP bulb 700 to be able to.

이러한 CIP구근(700)은 지지파일 또는 부력방지 파일로서 역할을 겸하고 있는데 마찰력을 증가시키기 위한 구조로서 일정간격의 마찰 저항력 증가장치를 CIP구근(700)마다 하단에만 배치하는데 제1실시 예에서와 같은 방법으로 시공한다.The CIP bulb 700 also serves as a support pile or a buoyancy prevention pile, and a structure for increasing frictional force is disposed at a lower end of the CIP bulb 700 at a predetermined interval, as in the first embodiment. Construct by the method.

부력방지용 또는 지지용 마찰 저항력 증가방법에 대하여는 2가지의 방법을 제7실시 예에서 도 117, 도 118에 표현하고 있는데, 이 모두 일정 간격의 CIP구근(700)을 양측벽체 또는 중앙부로서의 역할 길이 이상으로 형성하는 시공을 하여야 하며 이때 CIP구근(100) 하단부에 이러한 방법을 적용하는 것이다. As to the buoyancy preventing or supporting friction resistance increasing method, two methods are shown in Figs. 117 and 118 in the seventh embodiment, all of which have a predetermined interval between the CIP bulbs 700 serving as both sides of the wall or the central part. The construction should be to be formed at this time is to apply this method to the lower end of the CIP bulb (100).

우선 도 117에서 2개소의 마찰력저항철근(704)을 고무슬리브(705)에 끼워 “V”모양으로 절곡하고 교차시켜 열십자(+) 방향으로 묶은 다음 CIP구근(700) 하단부 일정한 위치에 다수의 종간격을 유지하며 띠철근(720)위에 배치하게 되는데 이때 중심부에 PC강선(706)을 배치한 상태에서 CIP구근(700)을 형성하기 위한 콘크리트를 일정 높이로 타설하면서 콘크리트가 양생되기 전 케이싱을 들어올릴 때 PC강선(706)을 잡아당기게 되면 고무슬리브(705)에 끼워진 양쪽의 마찰력저항철근(704)이 시계와 반시계 방향으로 회전하면서 “V”모양에서 “-”모양으로 펴지게 되는데 이렇게 양생되어 펴진 마찰 저항철근(704)이 CIP구근(700)에서 돌출되게 되므로 부력 작용시 구조체의 상승을 저지시키는 앵커체로서의 역할과 지지말뚝의 역할을 하게 된다.First, in FIG. 117, two frictional resistance bars 704 are inserted into the rubber sleeve 705, bent in a “ V ” shape, crossed and tied in a crisscross (+) direction, and then a plurality of reinforcement bars in a fixed position at the bottom of the CIP bulb 700 are first placed. Maintain the longitudinal spacing and is placed on the band reinforcement (720) at this time, while placing the PC steel wire (706) in the center of the concrete to form a CIP bulb 700 to a certain height while placing the casing before curing When pulling up the PC steel wire 706, the frictional resistance bars 704 of both sides of the rubber sleeve 705 are rotated clockwise and counterclockwise to unfold in a “-” shape in a “ V” shape. Cured friction-resistant reinforcing bar 704 is protruded from the CIP bulb 700, and thus serves as an anchor and a support pile to prevent the rise of the structure during buoyancy action.

도 118에서 4개소의 마찰력저항철근(704)을 고무슬리브(705)에 끼워 “V”모양에 양 날개가 달린 모양으로 날개철근(707)을 이루고 교차시켜 “+”방향으로 묶은 다음 CIP구근(700) 하단부 일정한 위치에 다수의 종간격을 유지하며 띠철근(720)위에 배치하게 되는데 이때 중심부에 PC강선(706)을 배치한 상태에서 CIP구근(700)을 형성하기 위한 콘크리트를 일정 높이로 타설하면서 콘크리트가 양생되기 전 케이싱을 들어올릴 때 PC강선을 잡아당기게 되면 고무슬리브(705)에 끼워진 양쪽의 마찰력저항철근(704)이 “V”모양에서 “-”모양으로 바뀌면서 날개철근(707)을 수평방향으로 밀어 돌출시킨 상태가 되는데 이렇게 양생되어 펴진 날개철근(707)이 CIP구근(700)에서 돌출되게 되므로 부력 작용시 구조체의 상승을 저지시키는 앵커체로서의 역할과 지지말뚝의 역할을 하게 된다.In FIG. 118, four frictional resistance bars 704 are inserted into the rubber sleeve 705 to form a wing reinforcement 707 in the shape of both wings in a “ V ” shape, intersect and tie in the “+” direction, and then CIP bulbs ( 700) A plurality of longitudinal intervals are maintained at a predetermined position at the lower end and are disposed on the band reinforcement 720. At this time, the concrete for forming the CIP bulb 700 is placed at a predetermined height with the PC steel wire 706 disposed at the center. If you pull out the PC steel wire while lifting the casing before the concrete is cured, the frictional resistance bars 704 of both sides of the rubber sleeve 705 change from “ V ” shape to “-” shape. It is pushed in the horizontal direction to protrude, so the cured wing reinforcement 707 protrudes from the CIP bulb 700, thus acting as an anchor body to prevent the rise of the structure during buoyancy and the reverse of the support pile. A it is.

지지력을 증가시키기 위한 방법으로도 상기와 같은 방법으로 일정 간격의 CIP구근(700)을 양측벽체 또는 중앙부로서의 역할 길이 이상으로 형성하는 시공을 하여야 하며 이때 CIP구근(700) 하단부에 마찰 저항력 증가방법을 적용하는 것이다. As a method for increasing the bearing capacity, a method of forming a CIP bulb 700 at a predetermined interval or longer as a role length as a side wall or a central portion should be performed in the same manner as above, and at this time, a method of increasing frictional resistance at the lower end of the CIP bulb 700 is employed. To apply.

이와 같은 CIP구근(100)은 지하차도를 중심으로 좌우 양측으로 각각 이격 되는 거리의 위치에서 지하에 수직상 일정 간격을 벌리면서 다수열 매입되어 측벽을 형성하게 된다. 이러한 방법 또한 제6실시 예와 같은 방법으로 시공하게 된다.Such CIP bulb 100 is embedded in a plurality of rows while forming a side wall at a distance vertically spaced in the basement at a distance from each other to the left and right sides around the underground road. This method is also constructed in the same manner as in the sixth embodiment.

그러나, 이러한 CIP구근(700)은 토사층에서만 가능하고 암반구간에서는 불가능한 제약조건이 따른다. 이것은 지반을 굴착하는 오거의 장비가 암반을 천공할 수 없기 때문인데 이럴 경우 2.0m마다 암반측까지 천공이 가능한 T4 장비를 이용하여 내부굴착과 함께 CIP구근(700)을 형성하고 그 사이는 토사층까지만 CIP구근(700)을 형성한 다음 암반구간까지 내부굴착하여 CIP 받침앵커(708)를 시설하고 내부굴착을 계속하되 토사층까지만 시설된 CIP구근 하단에서 하부슬래브 버림콘크리트 하단까지 암반을 절취(“A”)하여 CIP 철근을 이어내리고 분말방수제가 혼합된 콘크리트를 타설하면 견고한 내벽체(780,780‘)가 형성된다.
However, these CIP bulbs 700 are subject to constraints that are only possible in soil layers and impossible in rock sections. This is because the auger's equipment that excavates the ground is not able to puncture the rock. In this case, CIP bulb 700 is formed with internal excavation using T4 equipment that can be drilled to the rock side every 2.0m. CIP bulb 700 is formed and then excavated to the rock section to equip the CIP support anchor 708 and continue the internal excavation, but the rock is cut from the bottom of the lower slab cast concrete to the soil layer (“A”). If you continue the CIP reinforcement and cast concrete mixed with powder waterproofing agent, a solid inner wall (780, 780 ') is formed.

내부굴착 및 Internal excavation and 어스앙카Earthanka 시공공정 -  Construction Process- S50S50 -2-2

본 공정은 상기한 각 CIP구근(700)의 공정을 완료한 후 CIP구근(700)의 머리부분에 1단의 어스앙카를 시설하여 측벽(131)의 안정을 도모하는 것이다.The present step is to stabilize the side wall 131 by installing a single earth anchor on the head of the CIP bulb 700 after completing the process of each CIP bulb 700 described above.

이후 내부 굴착을 계속하여 최종굴착선까지 이르게 되는데 이때 상기 CIP구근(700) 형성 공정에서 긴장 정착하였던 PC강연선(723)이 측벽(731)에 작용되는 부재력을 지탱하여주므로 안정이 도모되는 것이다.
After the internal excavation continues to reach the final excavation line at this time, since the PC strand wire 723 that was tension-fixed in the CIP bulb 700 forming process supports the member force acting on the side wall 731 is stable.

양측 하부슬래브 시공공정 - Both Side Slab Construction Process- S60S60 -1-One

본 공정은 전술한 내부굴착 및 어스앙카 시공공정(S50-2)이 완료된 후, 하부슬래브(770,770’)를 시공하여 지하차도를 형성하기 위한 공정이다.This process is a process for forming the underground roadway by constructing the lower slab (770,770 ') after the above-described internal excavation and earth anchor construction process (S50-2) is completed.

양측의 굴착된 공간에 버림콘크리트와 외부시트 방수층을 형성한 후 해당 굴착 부분의 측벽(731)과 그 하단으로 하부슬래브(770,770’)를 타설하게 된다.After forming the discarded concrete and the outer sheet waterproof layer in the excavated space on both sides, the lower slab (770,770 ') is poured into the side wall 731 and the bottom of the excavated portion.

여기서 상기 하부슬래브(770,770’)는 도면에서 보는 바와 같이 지하차도의 바닥면에 타설되는 타설체를 의미하고, 측벽(731)의 내측에 접하는 헌치부까지 타설한다.Here, the lower slab 770, 770 'means a pour body that is placed on the bottom surface of the underground driveway, as shown in the drawing, and pours up to the haunting portion in contact with the inner side of the side wall 731.

상기와 같이 양측의 공간을 굴착 시공한 후 하부슬래브(770,770’)의 타설공정이 완료되면 완성된 형태의 지하차도를 구성할 수 있게 된다.After excavation and construction of the space on both sides as described above, when the pouring process of the lower slab (770,770 ') is completed, it is possible to construct a completed underground roadway.

한편, 도 113에서 보듯이 본 공정에서 하부슬래브(770,770’)를 생략할 수 있는데 이때는 S10공정에서의 CIP근입 심도가 적정길이를 확보하여야 하고 S50-2 공정에서의 어스앙카 시설을 영구적으로 필요로 할 수 있다.
Meanwhile, as shown in FIG. 113, the lower slab (770,770 ') can be omitted in this process. In this case, the depth of CIP incorporation in the S10 process must be secured and the earth anchor facility in the S50-2 process is permanently required. can do.

양측 Both sides 내벽체Inner wall 시공공정 -  Construction Process- S70S70

하부슬래브 양측으로 일체로 수직상 연결되어 측벽(731)의 내측으로 타설되는 일부의 내벽체(780,780‘)는 하부슬래브(770,770‘)에 연이어 시공되어지며 잔여 내벽체(780“)는 상기의 일부의 내벽체(680,680’)가 양생되어진 후 어스앙카를 철거하면서 시공되어진다. Some of the inner walls 780, 780 ', which are integrally vertically connected to both sides of the lower slab and poured into the side walls 731, are constructed in succession to the lower slabs 770, 770' and the remaining inner walls 780 'are part of the above. After the inner wall (680,680 ') is cured, it is constructed while removing the earth anchor.

이렇게 형성되는 내벽체(780,780‘)는 자체의 강성을 확보하기 위하여 내벽체(780,780‘)에 매입된 철근(781)의 교차 배치되는 배력철근과 측벽(731)을 이루는 CIP구근(700)에 매입되는 철근(710,711)중 내벽체(780,780’)에 근접하는 철근(711)에 가로방향으로 띠철근(720)에 접하여 배치된 배력철근을 연결하기 위한 연결철근(782)이 상하로 각각 다수개 등 간격 이격 시키며 구비되어야 한다.
The inner walls 780 and 780 'formed as described above are embedded in the CIP bulb 700 forming the sidewalls 731 and the reinforcing bars that are intersected with the reinforcing bars 781 embedded in the inner walls 780 and 780' to secure their rigidity. Among the reinforcing bars 710 and 711, a plurality of connecting bars 782 for connecting the reinforcing bars arranged in contact with the band reinforcing bars 720 in the horizontal direction to the reinforcing bars 711 adjacent to the inner wall bodies 780 and 780 ', respectively. It should be provided at intervals apart.

마무리 시공공정 - Finishing Construction Process- S80S80

상기와 같이 양측 내벽체 시공공정(S70)이 완료되면, 지하차도 내부의 보도 및 전기시설, 타일과 아스콘 등을 시설하여 지하차도의 공정을 마무리 한다.
As described above, when the inner wall construction process (S70) on both sides is completed, the process of the underground roadway is completed by installing a sidewalk and an electric facility, a tile and an ascon inside the underground roadway.

이상과 같은 일련의 공정을 거쳐, CIP구근(700)을 이용한 지하차도를 시공하게 되는데 있어서, 도 114는 측벽(731)과 하부슬래브(770,770‘)의 각 철근(771,772)의 연결 고정되는 상태를 나타내고 있다.In the construction of the underground roadway using the CIP bulb 700 through a series of processes as described above, FIG. 114 shows a state in which the side walls 731 and the respective bars 771 and 772 of the lower slab 770 and 770 'are connected and fixed. It is shown.

도면에서 보듯이 내벽체의 내측철근(781)의 배력철근이 측벽(731)을 이루는 각 CIP구근(700)에 매입되는 철근(710,711) 중, 내벽체(780,780‘)에 접하는 부분을 판넬(702)에 의해 절개되어지는 부분에 의해 노출된 철근(711)의 띠철근(720)과 연결 고정되도록 하여 하부슬래브(770,770’)와 측벽(731) 하단이 연결되도록 구성하였으며, 이러한 연결 구조는 지하도로의 좌우 하단측에 동일하게 적용될 것이다.As shown in the drawing, a portion of the reinforcing bars of the inner reinforcing bar 781 of the inner wall body contacting the inner wall 780,780 'among the reinforcing bars 710 and 711 that are embedded in the respective CIP bulbs 700 forming the side wall 731. The bottom slab 770, 770 'and the lower side of the side wall 731 are connected to be fixed to the strip reinforcement 720 of the reinforcing bar 711 exposed by the part to be cut by), such a connection structure is an underground road The same will be applied to the lower left and right side of the.

도 115는 하부슬래브(770,770‘)와 중앙부(730)를 연결하는 상태를 나타내고 있으며 가로방향으로 천공되는 다수의 가로공(701)을 형성하고, 그 가로공(701)으로 하부슬래브(770)에 매입되는 철근(771,772)을 통과시켜 타측의 하부슬래브(770’)에 매입되는 다른 철근(771‘, 772’)과 연결 고정되도록 한 상태를 도시하였으며, 헌치에 연하는 스터럽 철근(773)을 배치하고 있다.115 illustrates a state in which the lower slabs 770 and 770 'are connected to the central portion 730, and a plurality of horizontal holes 701 are formed in the horizontal direction, and the horizontal slabs 701 are connected to the lower slab 770. Passed reinforcing bars (771, 772) through the lower slab (770 ') on the other side of the reinforcing bars (771', 772 ') to be connected and fixed, the stub reinforcement (773) connected to the haunche is shown Doing.

도 116은 도면에서 보는 바와 같이 내벽체(780,780‘)의 외측과 접하면서 전술한 연결철근(782)에 의하여 연결되기 위해서는 측벽(731)을 이루는 CIP구근(700)의 일측면은 일부가 절단되어 CIP구근(700)에 매입되는 철근(710,711)을 감싸는 띠철근(720)이 미리 설치한 쫄대(703)등에 의하여 외부로 노출되도록 합판 등의 판넬(102)에 의해 마감처리 되도록 하여야 한다.FIG. 116 is one side of the CIP bulb 700 forming the side wall 731 in order to be connected to the outside of the inner wall (780, 780 ') as described in the drawing by the connecting bar 782 described above. The band reinforcing bars 720 surrounding the reinforcing bars 710 and 711 to be embedded in the CIP bulb 700 should be finished by the panel 102 such as plywood so as to be exposed to the outside by the pre-installed band 703.

이와 같이 시공되기 위해서 양 측벽 CIP구근 시공공정(S10)에서 측벽(731)을 이루기 위한 CIP구근(700) 형성시 일측을 절개하도록 판넬(702)을 형성하여 타설되도록 하는 것이 바람직하다.In order to be constructed as described above, it is preferable to form the panel 702 so that one side is cut to form the CIP bulb 700 for forming the sidewall 731 in both sidewall CIP bulb construction process (S10).

상기와 같이 판넬(702)에 의해 절개면을 얻게 되는 측벽(731)에는 측벽(731)을 구성하는 CIP구근(700)에 매입되는 철근(710,711)을 감싸는 띠철근(720)을 미리 설치한 쫄대(703)등에 의하여 외부로 노출된 상태에서 배력철근을 배치하고, 이 배력철근과 띠철근을 묶어 전술한 가로방향으로 연결하기 위한 연결철근(782)에 의해 상기한 내벽체(780,780‘)의 철근(781)과 교차 배치되는 배력철근과 연결될 수 있는 것이다.As described above, the side wall 731 having the cut surface obtained by the panel 702 is pre-installed with a band reinforcing bar 720 wrapping the reinforcing bars 710 and 711 embedded in the CIP bulb 700 constituting the side wall 731. Reinforcement of the inner wall (780, 780 ') by arranging the reinforcement bar in the state exposed to the outside by the (703), and by the connecting bar (782) for tying the reinforcement bar and the band reinforcement to connect in the horizontal direction described above. It can be connected to the reinforcement bars that intersect with (781).

한편, 도면부호 S는 하부슬래브(770,770‘)의 하면측에 구성되는 보호몰탈과 방수시트를 포함하는 보호몰탈 방수시트층을 가르킨다.Meanwhile, reference numeral S denotes a protective mortar waterproof sheet layer including a protective mortar and a waterproof sheet formed on the lower surface side of the lower slab 770,770 '.

본 발명의 방수방법은 제1실시 예에서의 방법을 그대로 적용하고 있으므로 상세 설명은 제1실시 예를 참조하여 이해될 수 있을 것이다.
Since the waterproof method of the present invention applies the method in the first embodiment as it is, the detailed description will be understood with reference to the first embodiment.

- 제 8 8th 실시예Example - -

본 발명은 도 119에 의한 바와 같이, As the present invention according to Figure 119,

양 측벽 및 중앙부 벽체 또는 기둥을 이루는 CIP구근 시공공정(S10)과, 일측 상부슬래브 시공공정(S20)과, 타측 상부슬래브 시공공정(S30)과, 중앙측 상부슬래브 시공공정(S40)과, 코너부 보강 및 어스앙카 시공공정(S50), 양측 내벽체 기초 및 중앙부 벽체 또는 기둥의 시공공정(S60-2)과, 양측 내벽체 시공공정(S70)과, 마무리 시공공정(S80)으로 지하차도의 시공이 이루어진다.CIP bulb construction process (S10) forming both sidewalls and central wall or column, one upper slab construction process (S20), the other upper slab construction process (S30), the central side upper slab construction process (S40), and the corner Sub-reinforcement and earth anchor construction process (S50), both inner wall foundation and central wall or column construction process (S60-2), both inner wall construction process (S70) and finishing construction process (S80) Construction is done.

각 과정별로 나누어 본 발명의 공정 흐름과 이에 따른 각 구성을 설명한다.
The process flow of the present invention and each configuration according thereto will be described by dividing each process.

양 측벽 및 중앙부 벽체 또는 기둥을 이루는 Forming both sidewalls and central walls or columns CIPCIP 구근 시공공정 - Bulb Construction Process- S10S10

본 공정은 지하차도를 건설할 위치의 벽체에 해당되는 측벽과 중앙부의 벽체 또는 기둥을 형성하기 위한 공정이다.This process is a process for forming the side wall and the central wall or pillar corresponding to the wall of the position to build the underground driveway.

이를 위해서 도면에서 보는 바와 같이 지하차도를 구성하기 위한 지역 범위내에서 중앙을 분리하기 위한 중앙부와 양측 측면부에 각각 벽체 즉 측벽이 형성되도록 CIP구근(800)을 형성한다.To this end, as shown in the drawing, the CIP bulb 800 is formed such that a wall, ie, a side wall, is formed in each of a central part and both side surfaces for separating the center within an area range for constructing an underground roadway.

여기서 상기 중앙부 벽체는 CIP구근을 이용하여 벽체로 형성할 수도 있고, 기둥식 예컨데 중간 중간이 끊겨지는 형태의 기둥 타입으로 CIP구근을 형성할 수 있는바, 현장 조건 및 설계 등에 의해 가변 될 수 있으며, 이러한 변경은 본 발명을 사용하는 자가 선택적으로 적용할 수 있음은 당연하다 할 것이다.Here, the central wall may be formed as a wall using a CIP bulb, a column type, for example, a CIP bulb may be formed in a column type in which an intermediate middle is cut off, and may be varied according to site conditions and designs. It will be appreciated that such changes can be selectively applied by those using the present invention.

상기한 CIP(Cast-in-place) 구근(800)은 도 136 에서 보는 바와 같이 다수의 주철근(810,811)이 직사각형으로 배열 배치되고 그 주철근(810,811)을 감싸는 띠철근(820)을 등간격으로 이격시키며 주철근과 띠철근이 하나로 조합된 철근망태가 형성된다.As shown in FIG. 136, the cast-in-place (800) CIP (800) has a plurality of main reinforcing bars 810 and 811 arranged in a rectangular shape and spaced apart at intervals between the strip reinforcing bars 820 surrounding the main reinforcing bars 810 and 811. Reinforcing wire mesh is formed by combining main reinforcing bars and band reinforcing bars.

이러한 철근망태의 최외곽을 에워싸는 관(이하 케이싱이라 칭한다.)을 형성한 후 그 내부에 콘크리트를 타설하여 양생함으로서, 하나의 유닛으로 이루어지는 원기둥 형태의 CIP구근(800)을 형성할 수 있고, 이와는 달리 CIP구근(800)이 삽입되기 위한 홀을 천공한 후 그 홀에 철근망태를 삽입 한 다음 콘크리트를 타설 양생하여 완성된 CIP구근(800)을 얻을 수 있을 것이다.By forming a tube (hereinafter referred to as a casing) that surrounds the outermost part of the reinforcing wire mesh, and then curing by pouring concrete therein, it is possible to form a cylindrical CIP bulb 800 consisting of a single unit, and Otherwise, after drilling the hole for the CIP bulb 800 is inserted, the reinforcing wire mesh is inserted into the hole, and then the concrete is poured to cure the finished CIP bulb 800.

이렇게 일정한 간격을 벌리면서 형성된 CIP구근(800)과 CIP구근(800) 사이에 미리 형성된 CIP구근(800)의 양 편측을 갈아내면서 천공하여 동형의 신CIP구근(815)을 새로이 형성하게 되는데 CIP구근(800)과 신CIP구근(815)는 상호 겹치도록 한다. 또한, 신CIP구근(815)의 형성과정은 CIP구근(800)과 같다.The CIP bulb 800 and the CIP bulb 800 formed at regular intervals are then drilled by changing both sides of the pre-formed CIP bulb 800 between the CIP bulbs 800 to form a new CIP bulb 815 of the same type. 800 and the new CIP bulb 815 to overlap each other. In addition, the formation process of the new CIP bulb 815 is the same as the CIP bulb 800.

도면에서 도면부호 831은 CIP구근(800)과 신CIP구근(815)에 의해 이루어지는 측벽을 지칭하고, 도면부호 830 또한 CIP구근(800)과 신CIP구근(815)에 의해 이루어지는 중앙부 벽체 또는 기둥 즉 중앙부를 의미하는 것으로, 본 발명에서는 CIP구근(800)과 신CIP구근(815)에 의해 이루어지는 단위체로 CIP구근(800)이라 칭하고, 이 CIP구근(800)에 의해 일렬로 매입되어 지하의 중앙과 그 양측의 측벽을 각각 구분하여 도면부호로 표기하였다.In the drawing, reference numeral 831 denotes a side wall formed by the CIP bulb 800 and the new CIP bulb 815, and reference numeral 830 also denotes a central wall or column formed by the CIP bulb 800 and the new CIP bulb 815. In the present invention, the unit consisting of the CIP bulb 800 and the new CIP bulb 815 is referred to as CIP bulb 800, and is embedded in a row by the CIP bulb 800 and is located in the center of the basement. The sidewalls on both sides are divided and denoted by reference numerals.

한편 CIP구근(800)을 형성할 때 철근망태의 일편측(벽체가 형성되는 내측을 지칭하고 이하 일편측이라 명명한다.)에는 합판등의 판넬(802)을 띠철근에 묶인 상태가 되도록 하여 콘크리트 타설시 합판등의 판넬(802) 내측으로는 콘크리트가 타설되지 않도록 하여야 하고, 띠철근 내측에는 부분적으로 쫄대(803)를 배치하는데, 이는 내벽체 철근(881)의 가로방향의 배력철근과 CIP구근(800)의 띠철근에 이어 배치한 배력철근의 상호 연결이 용이하게 하기 위해서이다.On the other hand, when forming the CIP bulb 800, one side of the reinforcing mesh (referring to the inner side where the wall is formed and referred to as one side). The panel 802, such as plywood, is bound to the band reinforcement concrete When pouring, concrete should not be placed inside the panel 802 such as plywood, and a chock 803 is partially disposed inside the band reinforcing bar, which is a horizontal reinforcing bar of the inner wall reinforcement 881 and a CIP bulb. This is to facilitate the interconnection of the reinforcing bars arranged after the band reinforcing bars of (800).

더불어, 코너부 보강재(860)를 연결하기 위한 앙카볼트를 미리 구성하도록 하는 것이 좋다. 이것은 코너부 보강재를 설치할 때 즉시 설치가 용이하도록 하기 위함이다.In addition, it is good to configure the anchor bolt for connecting the corner reinforcement 860 in advance. This is to facilitate the installation immediately when installing the corner reinforcement.

또한, 철근망태의 양 편측(중앙부가 형성되는 좌우 양측)에도 합판등의 판넬(802)을 띠철근에 묶인 상태가 되도록 하여 콘크리트 타설시 합판등의 판넬(802) 내측으로는 콘크리트가 타설되지 않도록 하여야 하는데 띠철근 내측에는 부분적으로 쫄대(803)를 배치하고 있다.In addition, the panel 802 such as plywood is tied to the band reinforcement on both sides (right and left sides of which the center part is formed) of the reinforcing wire mesh so that concrete is not placed inside the panel 802 such as plywood when placing concrete. It should be, but the chord 803 is partially disposed inside the band reinforcing bar.

이는 중앙부 CIP구근(800)이 상호 겹침 이음으로 되어 있지만 철근으로 이어지지 못하고 있으므로 배력철근과 띠철근을 묶어 일체의 구조체로 조성하기 위함이다.This is because the central CIP bulbs 800 are overlapping joints but do not lead to reinforcing bars, so that the reinforced bars and the band reinforcing bars are bundled to form an integral structure.

또한 내벽체(880,880‘)에서는 철근망태 일편측 코너 양측 주철근에 접하여 2개의 PC강연선(823)을 배치하되 CIP구근(800) 일정길이에만 배치하고 중앙부(830)에서도 띠철근(820) 중앙측에 연하여 2개의 PC강연선(823)을 CIP구근(800) 일정길이에만 배치한다.In addition, in the inner wall (880,880 '), two PC strands 823 are disposed in contact with the main reinforcing bars on one side corner of the reinforcing wire mesh, but only in a certain length of the CIP bulb 800, and in the center of the strip reinforcing bar 820 in the central part 830. The two PC strands 823 are arranged only in a certain length of the CIP bulb 800.

여기서 철근망태 일편측 코너 양측 주철근에 접하는 2개의 PC강연선(823)의 역할은 상부슬래브 최외측 우각부에 설치한 코너부 보강재와 최종 굴착선까지의 사이에 어스앙카를 시설하지 않아도 외부작용 부재력에 대처할 수 있도록 CIP구근(800)의 내하력을 증강시키기 위한 구조로서 매 CIP구근(800)마다 배치하며, 중앙부에서 2가닥의 PC강연선(823)은 좌우 양측의 도드락문양 거푸집에 의하여 얇아진 CIP구근(800)이 외부의 부재력에 의하려 좌굴을 발생시키지 않도록 하기 위함이다. Here, the role of the two PC strands 823 in contact with the reinforcing rods on one side corner of the reinforcing wire mesh is that the external reinforcing member does not need to install an earth anchor between the corner reinforcement provided on the outermost right side of the upper slab and the final digging line. As a structure for enhancing the load capacity of the CIP bulb 800 so as to cope with it, it is arranged every CIP bulb (800), the two strands of PC strands 823 in the center of the CIP bulb thinned by the left and right sides of the Dodlock-shaped formwork ( This is to prevent the 800 from buckling due to external force.

한편, PC강연선의 긴장정착 시기는 상부슬래브의 철근 조립이 완료된 시기에 상부슬래브에서 정착시키므로 상부슬래브와 CIP간을 더욱 긴밀히 응집시키는 역할을 겸하고 있으며 우각부 부모멘트를 저감시키는 효과도 함께 거둘 수 있다.On the other hand, the tensioning time of the PC strand is settled in the upper slab when the rebar assembly of the upper slab is completed, thus acting as a more tightly cohesion between the upper slab and the CIP, and can also reduce the corner angle of the right corner. .

더불어 철근망태를 조립할 때 철근망태 상단에 수직 H-형강(822)을 매입하여 조립토록 하는데, 일정길이의 수직 H-형강(822)을 양측 측면부 CIP구근(800)에만 설치토록하고 일측 및 타측 상부슬래브(840,840‘)와 접속되는 위치까지 돌출토록 한다. 이는 하부슬래브가 없어 부재력이 상부슬래브 우각부에 크게 발생되므로 이를 제어하기 위한 수단으로 활용될 것이다.In addition, when assembling the reinforcing wire mesh, the vertical H-shaped steel 822 is purchased at the top of the reinforcing steel mesh to be assembled, and the vertical H-shaped steel 822 of a certain length is installed only at both side CIP bulbs 800, and one side and the other upper portion are installed. It protrudes to a position where it is connected with the slabs 840 and 840 '. Since there is no lower slab, the member force is largely generated in the upper slab right corner portion, and thus will be used as a means for controlling the slab.

그러나, 이러한 CIP구근(800)은 토사층에서만 가능하고 암반구간에서는 불가능한 제약조건이 따른다. 이것은 지반을 굴착하는 오거의 장비가 암반을 천공할 수 없기 때문인데 이럴 경우 2.0m마다 암반측까지 천공이 가능한 T4 장비를 이용하여 내부굴착과 함께 구근(800)을 형성하고 그 사이는 토사층까지만 CIP구근(800)을 형성한 다음 상부슬래브(840.850)를 시공하고 암반구간까지 내부굴착하여 CIP 받침앵커(807)를 시설하고 내부굴착을 계속하되 토사층까지만 시설된 CIP구근 하단에서 하부슬래브 버림콘크리트 하단까지 암반을 절취(A)하여 CIP 철근을 이어내리고 분말방수제가 혼합된 콘크리트를 타설하면 견고한 내벽체(880,880‘)가 형성된다.
However, these CIP bulbs 800 are subject to constraints that are only possible in soil layers and impossible in rock sections. This is because the auger's equipment that excavates the ground cannot penetrate the rock. In this case, by using T4 equipment that can drill to the rock side every 2.0m, the bulb 800 is formed together with the internal excavation. After forming the bulb 800, construct the upper slab (840.850) and excavate to the rock section to install the CIP support anchor 807 and continue the internal excavation, but only to the soil layer, from the bottom of the lower slab cast concrete When cutting the rock (A) to continue the CIP reinforcement and poured concrete mixed with a powder waterproofing agent, a solid inner wall (880,880 ') is formed.

일측One side 상부슬래브 시공공정 -  Upper Slab Construction Process- S20S20

상기한 공정(S10)을 거쳐 CIP구근(800)의 설치 시공이 완료되면 도 120과 같은 도로 단면의 구획이 분리되게 되는데, 본 공정은 이와 같은 상태에서 CIP구근(800)에 의해 구획되어지는 전체 폭원을 기준으로 3등분되는 중 어느 한측을 먼저 상부슬래브를 형성하기 위한 공정으로 이해될 것이다.When the installation of the CIP bulb 800 is completed through the above-described process (S10), the section of the road section as shown in FIG. 120 is separated, and in this state, the entire compartment partitioned by the CIP bulb 800 in this state. It will be understood that either side of the third divided by the width source as a process for forming the upper slab first.

이를 위해서 도 121에서 보는 바와 같이 상부슬래브 전체 폭원중 1/3되는 위치중앙부(전술한 바와 같이 CIP구근으로 이루어지는 벽체 중 중앙을 나누는 전체 부분을 중앙부로 명명하고 이를 도면에서 830 으로 표기하며, 상기 CIP구근에 의해 형성되는 기둥 타입도 포함한다)(830) 인근의 어느 일측 도로부분에 H-말뚝을 박고 굴착하여 아스콘층과 흙을 걷어내게 된다.To this end, as shown in FIG. 121, the central portion of the upper portion of the upper slab width source 1/3 (as described above, the entire portion dividing the center of the wall made of CIP bulbs is named as the central portion, and this is denoted as 830 in the drawing). It also includes a column type formed by the bulb) (830) to the excavated H-peg to one side of the road portion near to excavate the asphalt layer and soil.

이때, H-말뚝 흙막이 시설로 제4 실시 예에서 적용되고 있는 콘크리트 PC1토류판(804)을 제작하여 설치하는 것으로 하였다.At this time, it was supposed to manufacture and install the concrete PC1 earth plate 804 that is applied in the fourth embodiment as an H-pile soiling facility.

이와 같이 일정깊이 터파기 공사를 진행 한 다음에 그 터파기면으로 바닥고르기 콘크리트와 거푸집을 시설한 후 상부슬래브를 시설한다. In this way, after the trench work is carried out to a certain depth, the floor slab is equipped with concrete and formwork, and then the upper slab is installed.

이때, 코너부 보강재(860)를 연결하기 위한 앙카볼트를 미리 구성하도록 하는 것이 좋다. 이것은 코너부 보강재(860)를 설치할 때 즉시 설치가 용이하도록 하기 위함이다.At this time, the anchor bolt for connecting the corner reinforcement 860 may be configured in advance. This is to facilitate the installation immediately when installing the corner reinforcement 860.

또한, 측면부 측벽의 CIP구근(800)에 돌출되어 매입되어 있는 일정길이의 수직 H-형강(822)과 연결되는 일정길이의 수평 H-형강(822)을 설치토록 하므로 우각부의 부재력을 제어할 수 있는 역할을 담당하도록 하는 것이 좋다.In addition, it is possible to control the member force of the right angle part by installing a horizontal H-shaped steel 822 of a predetermined length connected to the vertical H-shaped steel 822 of a predetermined length protruding from the CIP bulb 800 of the side wall. It is a good idea to play a role.

더불어 PC강연선(821)을 수평수직 H-형강(822)이 배치되지 않은 곳에 배치하여 긴장정착하므로 부재력 값을 저감 시킬 수 있다. In addition, since the PC strand 821 is placed in a position where the horizontal vertical H-shaped steel 822 is not disposed, tension fixation may reduce the member force value.

본 발명에서 상부슬래브는 도 121 내지 도 123에서 보는 바와 같이 전체 폭원을 3등분으로 각각 구분되며 순차적인 타설 과정을 거치게 되는데, 본 발명의 실시 이해를 위해 도면상(도 121) 보았을 때 우측의 상부슬래브를 일측 상부슬래브라 명명하고 도면부호 840으로 표기하였으며, 이와 대향되는 측의 슬래브를 타측 상부슬래브로 명명하고 도면부호 840‘으로 표기하며 중앙측의 슬래브를 중앙측 상부슬래브로 명명하고 도면부호 850으로 표기하여 구분하였다.In the present invention, the upper slab is divided into three parts each of the total width source as shown in Figures 121 to 123, and undergoes a sequential pouring process, the upper part of the right side when viewed in the drawings (Fig. 121) for the understanding of the present invention. Named slab on one side of upper slab and denoted by reference numeral 840. Named slab on the opposite side as other upper slab, denoted by reference numeral 840 'and named center slab as center-side upper slab. Notation was divided into.

이때 일측 상부슬래브(840)의 철근은 이웃과 접하는 중앙측 상부슬래브(850)와의 철근 연결을 위하여 한곳에서 이음치 않도록 지그재그로 배치 이음을 할 수 있도록 하고 일측 상부슬래브(840)의 시공 후에는 방수재와 보호몰탈을 시공한다. At this time, the reinforcing bar of one side upper slab 840 is arranged in a zigzag so as not to be connected at one place for connecting the reinforcement with the center side upper slab 850 in contact with the neighbor and after construction of the one side upper slab 840 Install a protective mortar.

이와 같이 일측 상부슬래브(840)를 타설 시공한 후에는 후술하게 되는 타측 상부슬래브(840‘)를 타설하기 위한 터파기 시공(S30)이 이루어지는데 그 전에 교통의 흐름을 방해하지 않기 위해 일측 상부슬래브(840)의 표면을 복토하게 되는 복토과정을 거쳐야 한다.In this way, after placing the one side upper slab 840, a trench construction (S30) for placing the other side upper slab 840 ', which will be described later, is performed, but one side upper slab does not interfere with the flow of traffic before. Cover the surface of the (840) must go through the cover process.

한편, 복토시에는 일측 상부슬래브(840)와 중앙측 상부슬래브(850)의 지그재그 방식의 철근이음을 위하여 별도의 흙막이 시설을 하면서 복토를 하게 되는데 별도의 흙막이 시설로는 도 138의 H말뚝(90) 한쪽 플렌지에 다수개의 천공구멍(92)을 내고 이음부로부터 뒤로 일정거리를 후퇴하여 시설하되 철근에 연결된 앵커체(91)를 천공구멍(92) 위치에서 볼트(93)로 결합하는 방식으로 다수개를 횡으로 시설한 후 적층하여 같은 방법으로 지표에 이르기까지 시설한다.On the other hand, in the case of covering the soil to cover the zigzag reinforcement of the one side upper slab 840 and the center side of the upper slab 850 while covering the soil as a separate mud facility H pile (90) of Figure 138 ) A plurality of drilling holes 92 are provided in one flange, and the facility is installed by retreating a certain distance backward from the joint portion, but the anchor body 91 connected to the reinforcing bar is coupled to the bolt 93 at the drilling hole 92 position. Dogs are placed laterally, stacked and laid down to the ground in the same way.

이와같은 방법으로 시설하면 중앙측 상부슬래브(850)를 터파기할 때 일측상부슬래브(840) 시공시 시설된 별도의 흙막이 시설이 토류벽의 역할을 수행하게 되어 중앙측 상부슬래브(850)의 터파기가 용이해진다.When the facility is installed in such a way, when the upper slab 850 is destroyed in the middle side, a separate retaining facility installed at the construction of the upper upper slab 840 serves as the earth wall, so that the trench of the middle upper slab 850 is removed. It becomes easy.

한편, 일측 상부슬래브(840)의 시공에 있어서는 상기와는 달리 도로의 사정에 의하여 터파기 시공방법을 중앙부를 기준으로 일측과 타측의 양측으로 도 124, 도 125와 같이 시공할 수 있다.
On the other hand, in the construction of one side upper slab 840, unlike the above, it is possible to construct the trench construction method on both sides of one side and the other side with respect to the center as shown in Figures 124 and 125, depending on the road conditions.

타측The other side 상부슬래브 시공공정 -  Upper Slab Construction Process- S30S30

본 공정은 상기한 일측 상부슬래브 시공공정(S20)에 의해 일측 상부슬래브(840)를 타설한 후, 그 일측 상부슬래브(840) 상면을 복토하여 교통의 흐름이 방해되지 않도록 한 다음, 타측 즉 일측 상부슬래브(840)와 대향되는 측(도 122) 에서 보았을 때 왼쪽의 상부슬래브(타측 상부슬래브-840‘)를 타설하기 위해 터파기 시공을 하는 과정을 의미한다.This process is after placing the one side upper slab 840 by the one side upper slab construction process (S20), and then cover the upper surface of one side upper slab 840 so that the flow of traffic is not disturbed, then the other side, one side As seen from the side (FIG. 122) facing the upper slab 840, it refers to a process of carrying out the trench to pour the upper slab (the other upper slab-840 ') on the left side.

이와 같이 타측 상부슬래브(840‘)를 타설하기 위해 그 주변을 터파기 시공한 다음 도 122에서와 같이 타측 상부슬래브(840’)를 타설 양생하여 지하차도를 구성하기 위한 상측으로의 각 상부슬래브(840,840‘)의 타설 작업을 완료할 수 있으며, 코너부 보강재(860)를 연결하기 위한 앙카볼트 설치과정이라든가, 우각부 부재력 제어 수평 H-형강(822) 및 PC강연선(821)을 설치하는 과정이라든가, 복토하는 과정이라든가 H-말뚝 박기와 터파기 및 토류판 설치 시공방법은 일측 상부슬래브(840)의 방법과 같다.In this manner, the periphery of the upper slab for pouring the other upper slab 840 'and then curing the other upper slab 840' by placing the upper slab to the upper side to construct the underground driveway as shown in FIG. 840,840 ') can be completed, and the process of installing the anchor bolt for connecting the corner reinforcement 860, the process of installing the horizontal angle control member H-beam (822) and PC strand (821) For example, the process of covering the soil, or the installation method of the H-piling and the trench and the earth plate is the same as the method of the upper slab 840.

한편, 타측 상부슬래브(840‘)의 철근은 이웃과 접하는 중앙측 상부슬래브(850)와의 철근 연결을 위하여 한곳에서 이음치 않도록 지그재그로 배치 이음을 할 수 있도록 하고 타측 상부슬래브(840’)의 시공 후에는 방수재와 보호몰탈을 시공한다.
On the other hand, the reinforcing bar of the other upper slab 840 'is to be connected in a zigzag arrangement so as not to be jointed at one place for connecting the reinforcement with the center upper slab 850 in contact with the neighbor and the construction of the other upper slab 840' Afterwards waterproofing material and protective mortar should be installed.

중앙측Center 상부슬래브 시공공정- Upper slab construction process S40S40

상기한 일측 및 타측 상부슬래브 시공공정(S20,S30)의 설치시공이 완료되면 도 123에서 보듯이 중앙측 상면 도로 부분을 굴착하여 아스콘층과 흙을 걷어내게 된다. When the installation of the one side and the other upper slab construction process (S20, S30) is completed, as shown in Figure 123 to excavate the central side of the upper road portion to remove the ascon layer and soil.

이처럼 중앙측을 터파기 할 때는 일측 및 타측 상부슬래브 시공공정(S20,S30)시 이미 설치한 도 138의 H말뚝(90)과 앵커체(91)가 연결되어 있는 흙막이 시설이 있으므로 별도의 흙막이 시설이 없이 터파기가 가능하다. As such, when digging the center side, there is a seismic facility that is connected to the H pile 90 and the anchor body 91 of FIG. 138 which is already installed during one side and the other upper slab construction process (S20, S30). Destruction is possible without this.

이와같이 일정깊이 터파기 공사를 진행 한 다음에 그 터파기면으로 바닥고르기 콘크리트와 거푸집을 시설한 후 중앙측 상부슬래브(850)를 시설한다. 이때 상부슬래브의 철근은 일측 및 타측에서 이미 지그재그로 배열된 상태로 연결하고 콘크리트를 타설하게 되는데, 타설 후에는 방수재와 보호몰탈을 시공한다. In this way, after proceeding to dig a certain depth, and then install the floor-level concrete and formwork to the dig surface, the upper side slab (850) is installed. At this time, the reinforcing bar of the upper slab is already connected in a zigzag state on one side and the other side, and the concrete is poured. After pouring, the waterproofing material and the protective mortar are constructed.

이와 같이 중앙측 상부슬래브(850)를 시설한 후에는 어느 일측 및 타측 상부슬래브(840,840‘) 시공에 있어서 설치되었던 H-말뚝을 뽑기 위한 볼트를 해제하는 과정과 함께 되메우기를 하면서 H-말뚝을 인발하게 된다.After the central upper slab 850 is installed, the H-pile is pulled out while backfilling with the process of releasing the bolts for pulling the H-peg installed in one and the other upper slab 840,840 '. Done.

이처럼 상부슬래브의 전체 폭원을 3등분하여 시공하는 것은 우각부와 중앙부에서 발생되는 부모멘트 최대 위치에 철근 이음을 두지 않기 위함이다.In this way, the total width of the upper slab is divided into three parts in order not to place the reinforcing bar at the maximum position of the parent moment generated at the right angle part and the center part.

한편, 1/2 시공일 경우에는 중앙부에서 철근이음을 하여야 하므로 부모멘트로 인한 부담이 될 수 있어 콘크리트 두께를 10㎝ 정도 두껍게 하여야 한다. 이는 부모멘트의 크기를 저감시키기 위함이다.
On the other hand, in the case of 1/2 construction, the reinforcing bar should be made in the center part, so it may be a burden due to the parent's cement. This is to reduce the size of the parent.

코너부Corner portion 보강 및  Reinforcement and 어스앙카Earthanka 시공공정 -  Construction Process- S50S50

본 공정은 상기한 각 상부슬래브(840,840‘)의 타설 작업을 완료한 후 상부슬래브와 CIP가 결합되어 있어 부모멘트가 크게 작용되는 것을 저감시키기 위한 방법으로 상부슬래브(840,840’)나 내벽체(880,880‘)의 지간을 짧게 유도하는 것이다. This process is the upper slab (840,840 ') or the inner wall (880,880) as a method for reducing the parent slag acting largely because the upper slab and the CIP is combined after completing the above-mentioned casting of the upper slab (840,840') To shorten the time between ').

이를 위하여 코너부 일부만의 굴착을 하여 일정한 간격으로 사보강재(860)를 설치하는 것이다.To this end, only part of the corner is excavated to install the stiffeners 860 at regular intervals.

이때, CIP구근(800) 형성을 위한 시공공정(S10)과 각 상부슬래브 시공공정(S20,S30)시 미리 매설된 앵커볼트에 간단히 사보강재(860)를 조립 체결하는 것이다.At this time, during the construction process (S10) and the upper slab construction process (S20, S30) for the formation of the CIP bulb 800 is to simply assembling and fastening the yarn-reinforced material 860 to the anchor bolts already embedded.

이와같이 설치된 사보강재(860)로 인하여 상부슬래브와 CIP구근(800)의 지간이 짧아져 부재력이 작아지므로 한층 안전성이 유지되는 것이며, 내벽체(880,880‘)에서 사보강재(860)연단과 최종 굴착면 사이의 길이를 줄이기 위한 방편으로 어스앙카를 시설한다. 이러한 어스앙카의 시설은 내벽체(880,880‘)의 부재력이 작아지도록 함과 아울러 근입장의 길이도 작게 할 수 있어 경제적 측면에서 유리하다.Since the space between the upper slab and the CIP bulb 800 is shortened due to the installed sabotage steel 860, the member force decreases, and thus the safety is further maintained, and the end surface and the final drilling surface of the sabotage steel 860 in the inner wall 880,880 '. Earth anchors are used to reduce the length of the bridge. The facility of Earth Anca is advantageous in terms of economical ability to reduce the absent force of the inner wall (880,880 ′) and to reduce the length of the entry.

한편, CIP구근(800)에 매입하여 긴장 정착하는 PC강연선(823)을 이용할 경우 어스앙카를 시설하지 않아도 같은 효과를 얻을 수 있으므로 본 발명을 사용하는 자가 선택적으로 적용할 수 있음은 당연하다 할 것이다.
On the other hand, if you use the PC strand (823) to buy a strain on the CIP bulb 800, the same effect can be obtained even without the earth anchor, it will be natural that those who use the present invention can be selectively applied. .

양측 Both sides 내벽체Inner wall 기초 및 중앙부 벽체 또는 기둥보강 시공공정 -  Foundation and central wall or column reinforcement construction process- S60S60 -2-2

본 공정은 전술한 코너부 보강 및 어스앙카 시공공정(S50)이 완료된 후, 내벽체 기초(870,870') 및 중앙부(830)를 시공하여 지하차도를 형성하기 위한 공정이다.This step is a step for forming the underground roadway by constructing the inner wall foundations (870,870 ') and the central portion (830) after the above-described corner portion reinforcement and earth anchor construction process (S50) is completed.

양측의 굴착된 공간에 버림콘크리트를 형성한 후 해당 굴착 부분의 측벽(831) 하단으로 내벽체 기초(870,870’)를 타설하게 된다.After the discarded concrete is formed in the excavated spaces at both sides, the inner wall foundations 870 and 870 'are poured into the lower end of the side wall 831 of the excavated portion.

여기서 상기 내벽체 기초(870,870’)는 도면에서 보는 바와 같이 지하차도의 바닥면에 타설되는 타설체를 의미하고, 측벽(831)의 내측에 접하는 헌치부까지 타설한다.Here, the inner wall foundations 870 and 870 'refer to a pour body that is placed on the bottom surface of the underground driveway, as shown in the drawing, and pours up to the haunting portion that is in contact with the inner side of the side wall 831.

상기와 같이 양측의 공간을 굴착 시공한 후 내벽체 기초(870,870’)의 타설공정이 완료되면, 중앙부(830)의 좌우 양측에 배력철근을 대고 개소별로 시공되어진 CIP구근(800)을 띠철근과 묶어 일체로 하는 보강벽체(890)를 타설하여 완성된 형태의 중앙부(830)를 구성할 수 있게 된다.
After excavation and construction of the space on both sides as described above, when the casting process of the inner wall foundations (870,870 ') is completed, placing the reinforcement bars on the left and right sides of the central portion 830, the CIP bulbs 800, which are constructed by places, By placing the reinforcing wall 890 to be bundled together to form a central portion 830 of the completed form.

양측 Both sides 내벽체Inner wall 시공공정 -  Construction Process- S70S70

양측으로 연결되어 측벽(831)의 내측으로 타설되는 일부의 내벽체(880,880‘)는 내벽체 기초(870,870‘)에 연이은 어스앙카를 철거한 후 시공되어지며 잔여 내벽체(880“)는 상기의 일부의 내벽체(880,880’)가 양생되어진 후 코너부 보강재(860)를 철거하면서 시공되어진다. 그러나 잔여 내벽체(880“)가 양생될때 콘크리트 수축작용에 의하여 침강이 되어 상부슬래브(840,850,840‘)와 미세한 틈이 발생될 수 있는데, 이곳에 무수축몰탈(883)을 충진하여 완성하게 된다.
Some of the inner walls 880 and 880 'connected to both sides and poured into the inner side of the side wall 831 are constructed after dismantling the earth anchors connected to the inner wall foundations 870 and 870', and the remaining inner walls 880 " Some inner walls 880 and 880 ′ are cured and then constructed while removing the corner reinforcement 860. However, when the remaining inner wall (880 ") is cured, it may be settled by the contraction of the concrete, and a fine gap may be generated with the upper slab (840, 850, 840 '), which is completed by filling the non-shrink mortar (883).

마무리 시공공정 - Finishing Construction Process- S80S80

상기와 같은 공정이 완료되면, 지하차도 내부의 보도 및 전기시설, 타일과 아스콘 등을 시설하여 지하차도의 공정을 마무리한다.When the above process is completed, the process of the underground driveway is completed by installing sidewalks and electric facilities, tiles and ascons inside the underground driveway.

이상과 같은 일련의 공정을 거쳐, CIP구근(800)을 이용한 지하차도를 시공하게 되는데 있어서, 도 130은 측벽(831)과 내벽체 기초(870)의 각 철근(881)과 철근(871,872)의 연결 고정되는 상태를 나타내고 있다.In the construction of the underground roadway using the CIP bulb 800 through a series of steps as described above, FIG. 130 shows the reinforcement 881 and the reinforcement 871 and 872 of the side wall 831 and the inner wall foundation 870. The connection is fixed.

도면에서 보듯이 내벽체의 내측철근(881)의 배력철근이 측벽(831)을 이루는 각 CIP구근(800)에 매입되는 철근(810,811) 중, 내벽체(880)에 접하는 부분을 판넬(802)에 의해 절개되어지는 부분에 의해 노출된 철근(811)의 띠철근(820)과 연결 고정되도록 하여 내벽체 기초(870)와 측벽(831) 하단이 연결되도록 구성하였으며, 이러한 연결 구조는 지하도로의 좌우 하단측에 동일하게 적용될 것이다.As shown in the drawing, a portion of the reinforcing bars of the inner reinforcement 881 of the inner wall body contacting the inner wall 880 of the reinforcing bars 810 and 811 embedded in the respective CIP bulbs 800 forming the side wall 831. The inner wall foundation 870 and the lower side of the side wall 831 are connected to each other by being fixed to the strip reinforcing bar 820 of the reinforcing bar 811 exposed by the part to be cut by the connecting part. The same applies to the lower left and right sides.

도 131은 중앙부(830)의 기초를 나타내고 있으며 가로방향으로 천공되는 다수의 가로공(801)을 형성하고, 그 가로공(801)으로 하부거더의 철근을 묶는 스터럽 철근(873)을 배치하고 있다.FIG. 131 shows the basis of the central portion 830 and forms a plurality of horizontal holes 801 which are punctured in the horizontal direction, and the stub reinforcing bars 873 are arranged to bind the reinforcing bars of the lower girder with the horizontal holes 801. .

도 132는 상부슬래브(840,840‘)의 일단과 측벽(831)의 상단간을 고정 연결하기 위한 단면을 나타내는데, 도면에서 보듯이 어느 한측의 상부슬래브(840)와 측벽(831)간의 고정 상태를 도시하고 있으며, 상부슬래브(840,840’)가 타설되어질 때 각 상부슬래브(840,840‘)에 매입되어 있는 복수개의 철근(842,842’/843,843‘)은 각각 측벽(831)을 이루는 CIP구근(800)에 매입되어 있는 철근(810,811) 중 내벽체(880)에 근접하는 철근(811) 및 하부슬래브(870)의 측면으로 일체로 타설되는 내벽체(880)의 철근(881)과 각각 연결 고정되도록 하였으며, 상부슬래브에서 가스압접되어 이어지는 또 다른 철근(844,844’)은 측벽(831)을 이루는 CIP구근(800)에 매입되어 있는 철근(810,811) 중 철근(810)과 연결 고정되도록 하였다.132 is a cross-sectional view for fixedly connecting between one end of the upper slab 840, 840 'and the upper end of the side wall 831, as shown in the figure shows a fixed state between the upper slab 840 and the side wall 831 on either side When the upper slabs 840 and 840 'are poured, a plurality of reinforcing bars 842, 842' / 843 and 843 'embedded in each upper slab 840 and 840' are embedded in the CIP bulb 800 constituting the side wall 831, respectively. Among the reinforcing bars 810 and 811, the reinforcing bars 811 adjacent to the inner wall 880 and the reinforcing bars 881 of the inner wall body 880 integrally placed on the side surfaces of the lower slab 870 were respectively connected and fixed. Another reinforcing bars (844, 844 ') is connected to the reinforcing bars (810) of the reinforcing bars (810,811) embedded in the CIP bulb 800 forming the side wall (831).

아울러, 상기한 내벽체(880)의 철근(881)과 교차 배치되는 배력철근과 측벽(831)을 이루는 CIP구근(800)에 매입되는 철근(810,811)중 내벽체(880)에 근접하는 철근(811)에 가로방향으로 띠철근(820)에 접하여 배치된 배력철근을 연결하기 위한 연결철근(882)이 상하로 각각 다수개 등 간격으로 이격시키며 구비되어야 한다. 이러한 연결구조는 지하도로의 좌우 상단측에 동일하게 적용될 것이다.In addition, the reinforcing bars close to the inner wall (880) of the reinforcing bars (810,811) embedded in the reinforcement reinforcement and the side wall 831 forming the reinforced reinforcement (881) of the inner wall (880) of the inner wall 880 ( Connection bars 882 for connecting the reinforcing bars arranged in contact with the strip reinforcing bar 820 in the horizontal direction 811 to be spaced apart from each other at equal intervals. This connection structure will be equally applied to the upper left and right sides of the underground road.

또한, 상기 상부슬래브(840,840‘)의 타설시 철근(843,843’)을 피복으로 감싼 상태에서 지중에 매립하여 두고 타설되는데 이후 잔여 내벽체(880”)시설 공정시 상기 매립하여 두었던 철근(843,843‘)과 내벽체(880)에 매입되는 철근(881)이 피복이 제거된 상태에서 상호 연결되도록 하였다.Further, when reinforcing the upper slab 840,840 ', the reinforcing bars 843, 843' are embedded in the ground while being covered with a covering, and then the reinforcing bars 843, 843 'that were embedded during the remaining inner wall 880' 'facility process. And the reinforcement 881 embedded in the inner wall 880 are interconnected in a state in which the covering is removed.

도 133은 도면에서 보듯이 1/3 시공순서에서 보여지며 각 상부슬래브(842,842‘,841,841’/ 852,851) 철근이 한곳에서 연결되지 않고 지그재그로 연결 결합되어야 한다.133 is shown in the 1/3 construction sequence as shown in the drawing, each of the upper slab (842,842 ', 841,841' / 852,851) reinforcing bar should be connected in a zigzag connection without connecting in one place.

즉, 일측 및 중앙측 상부슬래브(840,850) 내부에 매입되는 각각의 철근(841,842 / 851,852)이 연결되어야 하며 타측 및 중앙측 상부슬래브(840‘,850) 내부에 매입되는 각각의 철근(841’,842‘ / 851,852)이 연결되어야 하는 것이다. 이때 상기에서 설명하였듯이 연결되는 각각의 철근은 상호 지기재그로 연결토록 한 후 타설토록 함이 중요하다.That is, each of the reinforcing bars (841,842 / 851,852) to be embedded in one side and the middle side upper slab (840,850) should be connected, and each of the reinforcing bars (841 ', embedded in the other side and the center upper slab 840', 850), 842 '/ 851,852) should be connected. At this time, as described above, it is important that each reinforcing bar is connected to each other and then placed in place.

도 134는 1/2 시공순서에서 보여지는 상세로서 각 상부슬래브(840,840’) 철근과 CIP구근(800)에서의 철근이 결합되어야 하며 일정 인장부에서의 연결로서 부멘트로 인한 구조적 불리한 상황이 될 수 있으므로 중앙부 상부슬래브의 단면 두께를 외측으로 늘려 부모멘트가 저감되도록 함이 중요하다.Figure 134 shows the details shown in the 1/2 construction sequence, each of the upper slab (840, 840 ') reinforcement and the reinforcing bar in the CIP bulb 800 will be a structural disadvantage due to the buoy as a connection in a certain tension Therefore, it is important to increase the cross-sectional thickness of the central upper slab to the outside to reduce the parenting.

이를 위하여, 각 상부슬래브(840,840‘) 내부에 매입되는 각각의 철근(841,841’ / 842,842‘)을 CIP구근(800)의 중앙부 철근(832)과 서로 고정 연결하여야 하는데, 도면에서 보듯이 중앙부(830)를 이루는 CIP구근(800)의 상단측인 각 상부슬래브(840,840’)와 접하게 되는 위치를 결속하여 고정하고 일측의 상부슬래브(840)를 타설한다. 이때 타측의 상부슬래브의 철근과 연결을 위하여 일정길이의 철근(841, 842)을 타설전에 지그재그로 배열하여 한곳에서만 연결이 되지 않도록 조치하여 타측 상부슬래브(840‘)의 타측철근(841’,842‘)의 단부와 커플러 또는 가스압접 등의 방법으로 연결 고정한다. 이와 같이 하여 각 상부슬래브(840,840’)와 중앙부(830)를 견고하게 연결한다.To this end, each of the reinforcing bars (841,841 '/ 842,842') embedded in each upper slab (840,840 ') must be fixedly connected to the central reinforcing bar 832 of the CIP bulb 800, as shown in the center portion 830 Binding and fixing the position which is in contact with each upper slab 840,840 'which is the upper side of the CIP bulb 800 forming a) and pours the upper slab 840 on one side. At this time, the reinforcing bars (841, 842) of a certain length in order to connect with the reinforcing bars of the other upper slab is arranged in a zigzag before placing so that the other bars (841 ', 842') of the other upper slab (840 ') is not connected. Fix the end of ') with a coupler or gas pressure welding method. In this way, the upper slabs 840 and 840 'and the center portion 830 are firmly connected.

도 135는 도 127에서의 "E"부분을 도시한 것으로, 확대도면에서는 코너부 보강재(860)를 CIP구근(800)의 일측면과 고정하기 위한 예를 나타내고 있는데, 도면에서 보듯이 CIP구근(800)에 미리 매설된 앙카볼트와 연결하여 코너부 보강재(860)가 충분한 지지력을 갖도록 구성하게 된다. 이와같은 연결은 상부슬래브(840,840‘)와의 연결에도 적용된다.FIG. 135 is a view illustrating a portion “E” in FIG. 127. In an enlarged view, an example for fixing the corner reinforcement 860 to one side of the CIP bulb 800 is illustrated. In connection with the anchor bolt pre-embedded in 800, the corner reinforcement 860 is configured to have a sufficient supporting force. This connection also applies to the upper slab 840,840 '.

도 136은 도면에서 보는 바와 같이 내벽체(180)의 외측과 접하면서 전술한 연결철근(882)에 의하여 연결되기 위해서는 측벽(831)을 이루는 CIP구근(800)의 일측면은 일부가 절단되어 CIP구근(800)에 매입되는 철근(810,811)을 감싸는 띠철근(820)이 미리 설치한 쫄대(803)등에 의하여 외부로 노출되도록 합판 등의 판넬(802)에 의해 마감처리 되도록 하여야 한다. FIG. 136 shows one side of the CIP bulb 800 constituting the side wall 831 to be connected to the outside of the inner wall 180 while being connected by the connecting reinforcing bars 882 as shown in the drawing. The band reinforcing bars 820 surrounding the reinforcing bars 810 and 811 to be buried in the bulbs 800 should be finished by the panel 802 such as plywood so as to be exposed to the outside by the pre-installed band 803.

이와 같이 시공되기 위해서 양 측벽 CIP구근 시공공정(S10)에서 측벽(831)을 이루기 위한 CIP구근(800) 형성시 일측을 절개하도록 판넬(802)을 형성하여 타설되도록 하는 것이 바람직하다.In order to be constructed as described above, it is preferable that the panel 802 is formed to be poured to cut one side when forming the CIP bulb 800 for forming the sidewall 831 in both sidewall CIP bulb construction process (S10).

상기와 같이 판넬(802)에 의해 절개면을 얻게 되는 측벽(831)에는 측벽(831)을 구성하는 CIP구근(800)에 매입되는 철근(810,811)을 감싸는 띠철근(820)을 미리 설치한 쫄대(803)등에 의하여 외부로 노출된 상태에서 배력철근을 배치하고, 이 배력철근과 띠철근을 묶어 전술한 가로방향으로 연결하기 위한 연결철근(882)에 의해 상기한 내벽체(880,880‘)의 철근(881)과 교차 배치되는 배력철근과 연결될 수 있는 것이다.As described above, the side wall 831 obtained by the panel 802 is provided with a band reinforcing bar 820 covering the reinforcing bars 810 and 811 embedded in the CIP bulb 800 constituting the side wall 831. Reinforcement of the inner wall (880, 880 ') by arranging the reinforcement reinforcement in the state exposed to the outside by the (803), and by the connecting reinforcement (882) for tying the reinforcement reinforcement and the band reinforcement in the above-described horizontal direction It can be connected to the reinforcing bars intersected with (881).

도 137은 중앙부(830) 좌우 양측으로 쫄대(803)와 판넬(802)을 철거하고 배력철근을 배치한 후 쫄대에 의해 노출된 띠철근(820)에 배력철근을 묶어 보강콘크리트를 타설 한 상태를 도시하였다.FIG. 137 shows the state where the reinforcement concrete is poured by tying up the reinforcement to the band reinforcing bar 820 exposed by the wand after dismantling the chocks 803 and the panel 802 to the left and right sides of the central part 830. Shown.

도면부호 S는 상부슬래브(840,850,840‘)의 상면측에 구성되는 보호몰탈과 방수시트를 포함하는 보호몰탈 방수시트층을 가르킨다.Reference numeral S denotes a protective mortar waterproof sheet layer including a protective mortar and a waterproof sheet formed on the upper surface side of the upper slab 840, 850, 840 '.

본 발명에서의 방수방법은 CIP구근(800)에는 분말방수제를 레미콘에 혼합하여 타설하므로 벽체부 측벽(831)과 내벽체(880,880‘)를 합하여 벽체부라 통칭한다) 방수를 실현하고 상부슬래브에는 시트방수재(S)와 보호몰탈을 포설하는 것으로 실현하는데 각각의 접합부에는 위치에 따라 방법을 각각 달리하고 있다.In the present invention, the waterproofing method of the CIP bulb 800 is mixed with a powdered waterproofing agent and placed in a ready-mixed concrete, so that the wall side wall 831 and the inner wall 880 and 880 'are collectively referred to as a wall portion) to realize waterproofing, and the upper slab sheet The waterproofing material S and the protective mortar are provided. The method is different depending on the position of each joint.

즉, CIP구근(800)과 일반 구조체가 접하는 벽체 접합부에는 제1실시 예에서의 도 20 에서 보듯이 마지막 CIP구근(800) 형성과정에서 시트방수재(S)를 매입하여 형성한 후 일반 구조체의 시트방수재(S)와 겹침이음의 방법으로 하고, 상부 우각 접합부에는 도 21에서 보듯이 시트방수재(S) 위에 수밀성 방수재를 추가하고 보호몰탈을 시설한 뒤 주위에는 점토알갱이를 두껍게 깔아준다.That is, in the wall junction portion where the CIP bulb 800 and the general structure are in contact with each other, as shown in FIG. 20 in the first embodiment, the sheet waterproofing material S is formed in the process of forming the last CIP bulb 800, and then the sheet of the general structure is formed. As a method of overlapping with the waterproofing material (S), the upper right corner joint is added to the watertight waterproofing material on the sheet waterproofing material (S), as shown in Figure 21 and after installing a protective mortar thickly laid clay grains around.

한편 지하차도의 길이가 길어질 경우 제1실시 예의 도 23 에서와 같이 일정간격의 길이마다 재료투입구(184)를 시설하여야 한다. 이 재료투입구(184)는 상부슬래브를 시공하고 복토를 하여 노면에 차량을 통행시킬 때 상부슬래브 하면의 굴착과 하부 및 내벽체 시공을 위한 장비 반입반출구와 내부 굴착토사의 반출구, 철근 및 레미콘등 재료투입을 위한 용도로 쓸 수 있다.On the other hand, when the length of the underground road is long, as shown in Figure 23 of the first embodiment, the material inlet 184 should be provided for each length of a predetermined interval. This material inlet 184 is a device for loading and unloading equipment for excavation of the lower surface of the upper slab and construction of lower and inner walls when the upper slab is constructed and covered, and the outlet, reinforcement and ready-mixed concrete It can be used for material input.

이러한 재료투입구(184)는 공사후에는 폐쇄를 하며 지하수에 영향이 없도록 방수등을 철저히 하여야 물론이고 지하차도의 환풍시설이 놓이는 위치와는 간섭되지 않도록 하여야 한다.
Such a material inlet 184 is to be closed after the construction and should be thoroughly waterproof so as not to affect the groundwater, of course, so as not to interfere with the location of the ventilation facility of the underground roadway.

- 제 1 실시예에서의 도면 부호 -
S10; CIP구근 시공공정
S20; 일측 상부슬래브 시공공정
S30; 타측 상부슬래브 시공공정
S40; 중앙측 상부슬래브 시공공정
S50; 코너부 보강 및 어스앙카 시공공정
S60; 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정
S70; 양측 내벽체 시공공정
S80; 마무리 시공공정
100; CIP구근 101; 가로공
102; 판넬(도드락문양 거푸집) 103; 쫄대
104; 콘크리트 PC1 토류판 107; CIP 받침앵커
115; 신CIP구근 110,111; 철근
120; 띠철근 123; PC강연선
130; 중앙부 131; 측벽
132; 중앙부 철근 140; 일측 상부슬래브
140‘; 타측 상부슬래브 141,142, 151,152; 철근
150; 중앙측 상부슬래브 160; 사보강재
170,170‘; 하부슬래브 173; 스터럽철근
180,180‘; 내벽체
180“; 잔여 내벽체(2차 내벽체)
181; 철근 182; 연결철근
183; 무수축 몰탈 184; 재료투입구
A; 암반 절취부분
S; 시트방수재 및 보호몰탈
- 제 2 실시예에서의 도면 부호 -
S10; CIP구근 시공공정
S20; 일측 상부슬래브 시공공정
S30; 타측 상부슬래브 시공공정
S40; 중앙측 상부슬래브 시공공정
S50; 코너부 보강 및 어스앙카 시공공정
S60; 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정
S70; 양측 내벽체 시공공정
S80; 마무리 시공공정
204; 콘크리트 PC1 토류판 223; PC강연선
240; 일측PC구조 상부슬래브
241,251; PC구조 상부슬래브 하부철근
242,252; PC구조 상부슬래브 상부철근
243,253; 철근 244; PVC파이프
250; 일측PC구조 타측상부슬래브 260; 사보강재
270,270‘; 하부슬래브 280,280‘; 내벽체
280“; 잔여 내벽체 281; 내벽체 내측철근
282; 연결철근 283; 무수축 몰탈
- 제 3 실시예에서의 도면 부호 -
S10; 양측벽의 PC벽체 또는 PC 사각파일과 중앙부 벽체 또는 기둥의 CIP구근 시공공정
S20; 일측 상부슬래브 시공공정
S30; 타측 상부슬래브 시공공정
S40; 중앙측 상부슬래브 시공공정
S50-1; 코너부 보강 시공공정
S60; 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정
S70; 양측 내벽체 시공공정
S80; 마무리 시공공정
300'; PC벽체 300; CIP구근
301; PC사각파일벽체
302; PC사각파일벽체(중앙부) 302a,300a,301a; 단위벽체
303; 쫄대 304; 갈고리 저항철근
305 달아매기 벽체 306; 지수철판
307; 채움재 공간 308; PVC파이프 천공홀
309; 돌출 L형강 309‘; 매입 L형강
310,311; 주철근 312; 달아매기 철근
313; 거치용 H형강 314; 가이드 형강
320; 띠철근 322; 도드락문양거푸집
323; PC강연선 330; 중앙부
331; 측벽 332 중앙부 철근
340,350; 상부슬래브
341,351,342,352; 상부슬래브 철근
360; 코너부 보강재 370,370‘; 하부슬래브
380,380’; 내벽체 380“; 잔여 내벽체
381; 내벽체 철근 383; 무수축 몰탈
390; 중앙부 보강벽체
- 제 4 실시예에서의 도면부호 -
S10-1; 말뚝 시공공정
S40; 중앙측 상부슬래브 시공공정
S20; 일측 상부슬래브 시공공정
S30; 타측 상부슬래브 시공공정
S50-2; 내부굴착 및 어스앙카 시공공정
S60; 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정
S70; 양측 내벽체 시공공정
S80; 마무리 시공공정
90; H말뚝 92; 천공구멍
93; 볼트 400; 중간말뚝
401; 엄지말뚝 402, 403; PC강연선
404; 콘크리트 PC1 토류판 405; 걸쇠철판
406; PVC관 및 철근 407-1; 너트1
407-2; 너트2 408; PC Wire
409; 회전용 철판 410; 콘크리트 PC2 토류판
431,432; 중앙측 상부슬래브 철근 433; 중앙측 상부슬래브 연결철근
434; 벽체철근 440; 일측 상부슬래브
441;,442,443; 일측 상부슬래브철근
450; 타측 상부슬래브 451,452,453; 타측 상부슬래브철근
470,470‘; 하부슬래브 480,480‘; 벽체
480“; 잔여벽체 481; 기둥체
483; 벽체철근 484; 기둥체철근
- 제 5 실시예에서의 도면부호 -
S10; 양측벽의 PC벽체 또는 PC 사각파일과 중앙부 벽체 또는 기둥의 PC 사각
파일 또는 CIP구근 시공공정
S20; 일측 상부슬래브 시공공정
S30; 타측 상부슬래브 시공공정
S40; 중앙측 상부슬래브 시공공정
S50-1; 코너부 보강 시공공정
S60; 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정
S70; 양측 내벽체 시공공정
S80; 마무리 시공공정
504; 콘크리트 PC1 토류판
510,511; 측벽의 외내측 주철근
520; 띠철근 530; 중앙부
531; 측벽부 532; 중앙부 철근
540; 일측 Half PC구조 상부슬래브
540‘; 타측 Half PC구조 상부슬래브
541,541‘,542,542’,551,552; 일측 및 타측, 중앙측 상부슬래브 철근
544; PVC 파이프
550; 중앙측 Half PC구조 상부슬래브
551,552; 중앙측 상부슬래브 철근 550“; 잔여 현장타설 콘크리트
560; 코너부 보강재 570,570‘; 하부슬래브
580,580’; 내벽체 580“; 잔여 내벽체
582; 연결철근 583; 무수축 몰탈
- 제 6 실시예에서의 도면부호 -
S10; CIP구근 시공공정
S50-2; 내부굴착 및 어스앙카 시공공정
S60-1; 양측 하부슬래브 시공공정
S70; 양측 내벽체 시공공정
S230; PSC빔 거치 및 상부슬래브 시공공정
S80; 마무리 시공공정
601; 가로공 602; 판넬
603; 쫄대 604; 마찰력저항철근
605; 고무슬리브 606; PC강선
607; 날개철근 608; CIP받침 철근
620; 띠철근 640; 상부슬래브
641,642; 상부슬래브철근 623,653; PC강연선
644; 연단철근 650; PSC빔
654; 가로보 660; 배면슬래브
670,670‘; 하부슬래브 673; 스터럽 철근
680,680’; 내벽체 681; 내벽체 철근
682; 연결철근
- 제 7 실시예에서의 도면부호 -
S10; CIP구근 시공공정
S50-2; 내부굴착 및 어스앙카 시공공정
S60-1; 양측 하부슬래브 시공공정
S70; 양측 내벽체 시공공정
S80; 마무리 시공공정
704; 마찰력저항철근 707; 날개철근
705; 고무슬리브 706; PC강선
708; CIP받침 철근 720; 띠철근
770,770‘; 하부슬래브 771,772; 일측 하부슬래브철근
771‘,772’; 타측 하부슬래브철근 773; 스터럽철근
780,780’; 내벽체 781; 내벽체 철근
782; 연결철근
- 제 8 실시예에서의 도면 부호 -
S10; 양 측벽 및 중앙부 벽체 또는 기둥을 이루는 CIP구근 시공공정
S20; 일측 상부슬래브 시공공정
S30; 타측 상부슬래브 시공공정
S40; 중앙측 상부슬래브 시공공정
S50; 코너부 보강 및 어스앙카 시공공정
S60-2; 양측 내벽체 기초 및 중앙부 벽체 또는 기둥 보강 시공공정
S70; 양측 내벽체 시공공정
S80; 마무리 시공공정
800; CIP구근 801; 가로공
802; 판넬(도드락문양 거푸집) 803; 쫄대
804; 콘크리트 PC1 토류판 807; CIP 받침앵커
815; 신CIP구근 810,811; 철근
820; 띠철근 821;823; PC강연선
822; H-형강 830; 중앙부
831; 측벽 832; 중앙부 철근
840; 일측 상부슬래브 840‘; 타측 상부슬래브
841,842, 851,852; 철근 850; 중앙측 상부슬래브
860; 사보강재 870,870‘; 내벽체 기초
873; 스터럽철근 880,880‘; 내벽체
880“; 잔여 내벽체(2차 내벽체) 881; 철근
882; 연결철근 883; 무수축 몰탈
A; 암반 절취부분
S; 시트방수재 및 보호몰탈
Reference numerals in the first embodiment
S10; CIP bulb construction process
S20; One side upper slab construction process
S30; Other upper slab construction process
S40; Center Slab Construction Process
S50; Corner reinforcement and earth anchor construction process
S60; Reinforcement work of both lower slab and central wall or column
S70; Both side inner wall construction process
S80; Finishing construction process
100; CIP bulb 101; Cross ball
102; Panel (Dod Rock Pattern) 103; Chock
104; Concrete PC1 earth plate 107; CIP Support Anchors
115; New CIP bulb 110,111; rebar
120; Band steel 123; PC strand
130; Central portion 131; Side wall
132; Central reinforcing bars 140; One side upper slab
140 '; The other upper slabs 141, 142, 151, 152; rebar
150; Center side upper slab 160; Sabo Steel
170,170 '; Bottom slab 173; Stirrup Rebar
180,180 '; Inner wall
180 “; Residual inner wall (secondary inner wall)
181; Rebar 182; Rebar
183; Anhydrous mortar 184; Material entrance
A; Rock cutout
S; Sheet waterproofing and protection mortar
Reference numerals in the second embodiment
S10; CIP bulb construction process
S20; One side upper slab construction process
S30; Other upper slab construction process
S40; Center Slab Construction Process
S50; Corner reinforcement and earth anchor construction process
S60; Reinforcement work of both lower slab and central wall or column
S70; Both side inner wall construction process
S80; Finishing construction process
204; Concrete PC1 earth plate 223; PC strand
240; Single side PC structure upper slab
241,251; PC structure Upper slab Lower reinforcing bar
242,252; PC Structure Upper Slab Upper Reinforcing Bar
243,253; Rebar 244; PVC pipe
250; One side PC structure and the other side upper slab 260; Sabo Steel
270,270 '; Bottom slab 280,280 '; Inner wall
280 “; Residual inner wall 281; Inner reinforcing wall
282; Connecting bars 283; Anhydrous mortar
Reference numerals in the third embodiment
S10; CIP bulb construction process of PC wall or PC square pile and central wall or column on both side walls
S20; One side upper slab construction process
S30; Other upper slab construction process
S40; Center Slab Construction Process
S50-1; Corner reinforcement construction process
S60; Reinforcement work of both lower slab and central wall or column
S70; Both side inner wall construction process
S80; Finishing construction process
300 '; PC wall 300; CIP bulb
301; PC square file wall
302; PC square pile wall (center part) 302a, 300a, 301a; Unit wall
303; Chord 304; Hook Rebar
305 Hanging Walls 306; Steel plate
307; Filler space 308; PVC Pipe Drilling Hole
309; Protruding L-beam 309 '; Embedded L section steel
310,311; Cast iron 312; Strapping rebar
313; Mounting H-beam 314; Guide section steel
320; Band steel 322; Tod Rock Glyph
323; PC strand 330; Central part
331; Sidewalls 332 Center Bar
340,350; Upper slab
341,351,342,352; Upper slab rebar
360; Corner reinforcement 370,370 '; Bottom slab
380,380 '; Inner wall 380 “; Residual inner wall
381; Lining reinforcing bars 383; Anhydrous mortar
390; Center Reinforcement Wall
Reference numerals in the fourth embodiment
S10-1; Pile construction process
S40; Center Slab Construction Process
S20; One side upper slab construction process
S30; Other upper slab construction process
S50-2; Internal excavation and earth anchor construction process
S60; Reinforcement work of both lower slab and central wall or column
S70; Both side inner wall construction process
S80; Finishing construction process
90; H pile 92; Perforation hole
93; Bolt 400; Middle pile
401; Thumb piles 402, 403; PC strand
404; Concrete PC1 earth plate 405; Clasp
406; PVC pipe and rebar 407-1; Nut 1
407-2; Nut 2 408; PC Wire
409; Rotating iron plate 410; Concrete PC2 Earth Plate
431,432; Central side upper slab reinforcing bar 433; Center Slab Reinforcing Bar
434; Wall rebar 440; One side upper slab
441 ;, 442,443; One side upper slab rebar
450; Other upper slab 451,452,453; Upper slab reinforcement on the other side
470,470 '; Bottom slab 480,480 '; Wall
480 “; Residual wall 481; Column
483; Wall reinforcement 484; Column
Reference numerals in the fifth embodiment
S10; PC wall or PC square file of both side wall and PC square of central wall or pillar
Pile or CIP bulb construction process
S20; One side upper slab construction process
S30; Other upper slab construction process
S40; Center Slab Construction Process
S50-1; Corner reinforcement construction process
S60; Reinforcement work of both lower slab and central wall or column
S70; Both side inner wall construction process
S80; Finishing construction process
504; Concrete PC1 Earth Plate
510,511; Outer medial cast iron on the sidewall
520; Band steel 530; Central part
531; Sidewall portions 532; Center reinforcement
540; One side half PC structure upper slab
540 '; Upper half slab on the other side
541,541 ', 542,542', 551,552; One side, other side, center side upper slab rebar
544; PVC pipe
550; Center side Half PC structure Upper slab
551,552; Center side upper slab rebar 550 “; Residual Cast-In Concrete
560; Corner reinforcement 570,570 '; Bottom slab
580,580 '; Inner wall 580 “; Residual inner wall
582; Connecting bars 583; Anhydrous mortar
Reference numerals in the sixth embodiment
S10; CIP bulb construction process
S50-2; Internal excavation and earth anchor construction process
S60-1; Both sides lower slab construction process
S70; Both side inner wall construction process
S230; PSC beam mounting and upper slab construction process
S80; Finishing construction process
601; Cross hole 602; panel
603; Maximum 604; Frictional resistance rebar
605; Rubber sleeve 606; PC steel wire
607; Wing reinforcement 608; CIP bearing rebar
620; Band steel 640; Upper slab
641,642; Upper slab rebar 623,653; PC strand
644; Malleable rebar 650; PSC beam
654; Crossbeam 660; Back slab
670,670 '; Bottom slab 673; Stirrup reinforcement
680,680 '; Inner wall 681; Internal wall rebar
682; Rebar
Reference numerals in the seventh embodiment
S10; CIP bulb construction process
S50-2; Internal excavation and earth anchor construction process
S60-1; Both sides lower slab construction process
S70; Both side inner wall construction process
S80; Finishing construction process
704; Frictional resistance bar 707; Wing rebar
705; Rubber sleeve 706; PC steel wire
708; CIP bearing rebar 720; Steel bars
770,770 '; Bottom slab 771,772; One side lower slab rebar
771 ', 772'; The other lower slab reinforcing bar 773; Stirrup Rebar
780,780 '; Inner wall 781; Internal wall rebar
782; Rebar
Reference numerals in the eighth embodiment
S10; CIP bulb construction process consisting of both side walls and central wall or column
S20; One side upper slab construction process
S30; Other upper slab construction process
S40; Center Slab Construction Process
S50; Corner reinforcement and earth anchor construction process
S60-2; Reinforcement construction process of both inner wall foundation and central wall or column
S70; Both side inner wall construction process
S80; Finishing construction process
800; CIP bulb 801; Cross ball
802; Panel (Dodlock pattern) 803; Chock
804; Concrete PC1 earth plate 807; CIP Support Anchors
815; New CIP bulb 810,811; rebar
820; Strip reinforcing bars 821; 823; PC strand
822; H-beam 830; Central part
831; Sidewall 832; Center reinforcement
840; One side upper slab 840 '; Upper Slab
841,842, 851,852; Rebar 850; Center side upper slab
860; Sabo steel 870,870 '; Interior wall foundation
873; Stirrups 880,880 '; Inner wall
880 “; Residual inner wall (secondary inner wall) 881; rebar
882; Connecting bars 883; Anhydrous mortar
A; Rock cutout
S; Sheet waterproofing and protection mortar

Claims (29)

양 측벽 및 중앙부 벽체 또는 기둥을 이루는, CIP구근 시공공정(S10)과,
상기 CIP구근 시공공정에 의해 형성되어 구분되는 차로의 어느 일측 상부를 터파기 한 후 상부슬래브를 시공하는, 일측 상부슬래브 시공공정(S20)과,
상기 일측 상부슬래브 시공공정(S20)을 거친 다음, 타측의 차로측에 해당되는 타측 상부를 터파기 한 후 상부슬래브를 시공하는, 타측 상부슬래브 시공공정(S30)과,
상기 타측 상부슬래브 시공공정(S30)을 거친 다음, 중앙의 차로측에 해당되는 중앙측 상부를 터파기 한 후 상부슬래브를 시공하는, 중앙측 상부슬래브 시공공정(S40)과,
상기 양측 상부슬래브 시공공정(S20, S30)에 의한 양측 상부슬래브 하단측 모서리부분을 내부 굴착하여 코너부 보강을 하고 추가굴착을 하여 양 측벽을 지지하는 어스앙카를 시공하는, 코너부 보강 및 어스앙카 시공공정(S50)과,
최종 하단부까지 굴착 완료하여 양측 하부슬래브와 함께 중앙부 벽체 또는 기둥의 보강을 시공하는, 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정(S60)과,
상기 양측 어스앙카를 철거하고 일부 내벽체를 타설한 후 양생을 거쳐 코너부 보강을 철거한 후 상부슬래브와 연결하는 잔여 내벽체를 시공하는, 양측 내벽체 시공공정(S70)과,
내부 벽체 또는 중앙부 벽체 또는 기둥의 내부 타일 시공처리 후 각 하부슬래브 상면으로 아스콘 포장을 하는, 마무리 시공공정(S80)으로 이루어지는 것을 특징으로 하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
CIP bulb construction process (S10) forming both side walls and the central wall or column,
One side upper slab construction process (S20), which constructs an upper slab after digging any upper portion of the lane formed and separated by the CIP bulb construction process, and
After passing the one side upper slab construction step (S20), the other side upper slab construction process (S30) and then the upper slab construction after breaking the other upper side corresponding to the other side of the lane,
After the other upper slab construction process (S30), the center side upper slab construction process (S40) and the upper slab construction after breaking the upper portion of the center corresponding to the side of the center lane, and
Corner reinforcement and earth anchor for internally excavating the corners of the lower side of both upper slabs by the both side upper slab construction processes (S20, S30) to reinforce the corners, and to construct earth anchors supporting the side walls by additional excavation. Construction process (S50),
Both bottom slab and center wall or column reinforcement construction process (S60), and excavation to the final lower end to construct the reinforcement of the central wall or column with both lower slabs,
Both side inner wall construction process (S70) of dismantling the earth anchors on both sides and placing some inner wall and then reinforcing the corner portion through curing and constructing the remaining inner wall connecting with the upper slab;
Underground road construction using a temporary wall construction method of the temporary structure and the main structure, characterized in that the finishing construction process (S80), the ascon pavement to the upper surface of each lower slab after the interior tile construction process of the inner wall or central wall or column. Way.
양 측벽 및 중앙부 벽체 또는 기둥을 이루는 CIP구근 시공공정(S10)과,
상기 양 측벽 및 중앙부 벽체 또는 기둥을 이루는 CIP구근 시공공정에 의해 형성되어 구분되는 차로의 어느 일측 상부를 터파기 한 후 PC구조의 상부슬래브를 조립하는, 일측 상부슬래브 시공공정(S20)과,
상기 PC구조를 갖는 일측 상부슬래브 시공공정(S20)을 거친 다음, 타측의 차로측에 해당되는 타측 상부를 터파기 한 후 PC구조의 상부슬래브를 조립하는 타측 상부슬래브 시공공정(S30)과,
상기 타측 상부슬래브 시공공정(S30)을 거친 다음, 중앙의 차로측에 해당되는 중앙측 상부를 터파기 한 후 PC구조의 상부슬래브를 조립하는 중앙측 상부슬래브 시공공정(S40)과,
상기 양측 상부슬래브 시공공정(S20, S30)에 의한 양측 PC구조 상부슬래브 하단측 모서리부분을 내부 굴착하여 코너부 보강을 하고 추가굴착을 하여 양 측벽을 지지하는 어스앙카를 시공하는, 코너부 보강 및 어스앙카 시공공정(S50)과,
최종 하단부까지 굴착 완료하여 양측 하부슬래브와 함께 중앙부 벽체 또는 기둥의 보강을 시공하는, 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정(S60)과,
상기 양측 어스앙카를 철거하고 일부 내벽체를 타설한 후 양생을 거쳐 코너부 보강을 철거한 후 상부슬래브와 연결하는 잔여 내벽체를 시공하는, 양측 내벽체 시공공정(S70)과,
내부 벽체 또는 중앙부 벽체 또는 기둥의 내부 타일 시공처리 후 각 하부슬래브 상면으로 아스콘 포장을 하는, 마무리 시공공정(S80)으로 이루어지는 것을 특징으로 하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
CIP bulb construction process (S10) forming both side walls and the central wall or column,
One side upper slab construction process (S20) for assembling the upper slab of the PC structure after the top of one side of the lane formed by the CIP bulb construction process forming the two side walls and the central wall or pillar, and then separated;
After the one side upper slab construction process (S20) having the PC structure, the other side upper slab construction process (S30) for assembling the upper slab of the PC structure after the top of the other side corresponding to the lane side of the other side, and
After the other upper slab construction process (S30), the center side upper slab construction process (S40) for assembling the upper slab of the PC structure after the top of the central side corresponding to the side of the center lane, and
Corner reinforcement for constructing earth anchors for supporting both sidewalls by reinforcing the corners by internally excavating the lower edges of the upper slab of both PCs by the two upper slab construction processes (S20, S30). Earth anchor construction process (S50) section,
Both bottom slab and center wall or column reinforcement construction process (S60), and excavation to the final lower end to construct the reinforcement of the central wall or column with both lower slabs,
Both side inner wall construction process (S70) of dismantling the earth anchors on both sides and placing some inner wall and then reinforcing the corner portion through curing and constructing the remaining inner wall connecting with the upper slab;
Underground road construction using a temporary wall construction method of the temporary structure and the main structure, characterized in that the finishing construction process (S80), the ascon pavement to the upper surface of each lower slab after the interior tile construction process of the inner wall or central wall or column. Way.
양 측벽은 트렌치 굴착에 의한 단위PC벽체 및 오거 장비굴착에 의한 단위PC 사각파일 투입과 중앙부 벽체 또는 기둥에는 오거 장비굴착에 의한 단위PC 사각파일 투입 및 CIP구근을 시설하는, CIP구근 시공공정(S10)과,
상기 CIP구근 시공공정(S10)에 의해 형성되어 구분되는 차로의 어느 일측 상부를 터파기 한 후 상부슬래브를 조립하는, 일측 상부슬래브 시공공정(S20)과,
상기 일측 상부슬래브 시공공정(S20)을 거친 다음, 타측의 차로측에 해당되는 타측 상부를 터파기 한 후 상부슬래브를 시공하는, 타측 상부슬래브 시공공정(S30)과,
상기 타측 상부슬래브 시공공정(S30)을 거친 다음, 중앙의 차로측에 해당되는 중앙측 상부를 터파기 한 후 상부슬래브를 시공하는, 중앙측 상부슬래브 시공공정(S30)과,
상기 양측 상부슬래브 시공공정(S20, S30)에 의한 양측 상부슬래브 하단측 모서리부분을 내부 굴착하여 코너부 보강을 하고 추가굴착을 하는, 코너부 보강 시공공정(S50-1)과,
최종 하단부까지 굴착 완료하여 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강하는, 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정(S60)과,
1차 내벽체를 타설한 후 양생을 거쳐 코너부 보강을 철거한 후 상부슬래브와 연결하는 잔여 내벽체를 시공하는, 양측 내벽체 시공공정(S70)과,
내부 벽체 또는 중앙부 벽체 또는 기둥의 내부 타일 시공처리 후 각 하부슬래브 상면으로 아스콘 포장을 하는, 마무리 시공공정(S80)으로 이루어지는 것을 특징으로 하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
CIP bulb construction process, in which both side walls are fitted with unit PC square piles by trench excavation and auger equipment excavation, and unit PC square piles by auger equipment excavation and CIP bulb are installed on central wall or column (S10). )and,
One side upper slab construction process (S20) and assembling the upper slab after the top of any one side of the lane is formed and divided by the CIP bulb construction process (S10) and,
After passing the one side upper slab construction step (S20), the other side upper slab construction process (S30) and then the upper slab construction after breaking the other upper side corresponding to the other side of the lane,
A middle side upper slab construction step (S30) for constructing the upper slab after finishing the central upper part corresponding to the center lane side after the above-mentioned upper side slab construction step (S30)
Corner reinforcement construction step (S50-1), which is to reinforce the corner portion by further excavating the inner corner of the lower edge of both upper slab by the two upper slab construction process (S20, S30), and
After the excavation is completed to the bottom end of the lower slab and the central wall or pillar reinforcement, both lower slab and central wall or column reinforcement construction process (S60),
After pouring the primary inner wall, after reinforcing the corner reinforcement through curing, and constructing the remaining inner wall connecting the upper slab, both inner wall construction process (S70),
Underground road construction using a temporary wall construction method of the temporary structure and the main structure, characterized in that the finishing construction process (S80), the ascon pavement to the upper surface of each lower slab after the interior tile construction process of the inner wall or central wall or column. Way.
양 측벽은 본체 구조물에 가장 인접하게 엄지말뚝과 중앙부 벽체 또는 기둥 좌우에 중간말뚝 박기를 하는, 말뚝 시공공정(S10-1)과,
상기 양 측벽 및 중앙부 벽체 또는 기둥 좌우에 중간말뚝을 시공하는 시공공정에 의해 형성되어 구분되는 중앙측 차로측에 해당되는 중앙측 상부를 터파기 한 후 상부슬래브를 시공하는, 중앙측 상부슬래브 시공공정(S40)과,
상기 중앙측 차로에 의하여 좌우로 구분되는 어느 일측 차로측에 해당되는 상부를 터파기 한 후 상부슬래브를 조립하는, 일측 상부슬래브 시공공정(S20)과,
상기 일측 상부슬래브 시공공정(S20)을 거친 다음, 타측의 차로측에 해당되는 타측 상부를 터파기 한 후 상부슬래브를 시공하는, 타측 상부슬래브 시공공정(S30)과,
상기 양측 및 중앙측 상부슬래브 시공공정(S40,S20,S30)에 의한 중앙측 및 양측 상부슬래브 하단측에서 최종굴착선까지 내부굴착하여 어스앙카를 시공하는, 내부굴착 및 어스앙카 시공공정(S50-2)과,
최종 하단부까지 굴착 완료하여 양측 하부슬래브와 함께 중앙부 벽체 또는 기둥을 시공하는, 양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정(S60)과,
상기 중앙측 중간말뚝을 철거함과 아울러 어스앙카를 철거하고 양측 벽체를 1, 2차단위로 시공하는, 양측 내벽체 시공공정(S70)과,
상기의 양측 내벽체 시공공정(S70)에 이어 양측의 엄지말뚝을 인발하고, 내부 벽체 또는 중앙부 벽체 또는 기둥의 내부 타일 시공처리 후 각 하부슬래브 상면으로 아스콘 포장을 하는, 마무리 시공공정(S80)으로 이루어지는 것을 특징으로 하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
Both side walls are pile construction process (S10-1), which is the middle piles on the left and right of the thumb pile and the central wall or pillar adjacent to the main body structure;
Center-side upper slab construction process, which is formed by a construction process for constructing intermediate piles on both sides of the sidewalls and central walls or pillars, and then dismantles the upper portion of the central side corresponding to the central side lane side, and then constructs the upper slab. (S40),
One side upper slab construction process (S20), and assembling the upper slab after the top corresponding to any one side of the lane side divided by left and right by the center side lane,
After passing the one side upper slab construction step (S20), the other side upper slab construction process (S30) and then the upper slab construction after breaking the other upper side corresponding to the other side of the lane,
Internal excavation and earth anchor construction process by internal excavation from the center side and the lower side of both upper slab bottom by the both side and center side upper slab construction process (S40, S20, S30) to the final excavation line, and the construction of earth anchor (S50- 2) and,
Both bottom slab and center wall or column reinforcement construction process (S60) to complete the excavation to the final lower end and construct the central wall or column with both lower slabs,
Both the inner wall construction process (S70) of dismantling the middle side piling and removing the ground anchors and constructing both walls in primary and secondary units,
Following both side inner wall construction process (S70), the thumb piles on both sides are drawn out, and after finishing the interior tile construction process of the inner wall or the central wall or the pillar, ascon paving to the upper surface of each lower slab, the finishing construction process (S80) Underground road construction method using a temporary wall construction method of the temporary structure and the main structure, characterized in that made.
양 측벽은 트렌치 굴착에 의한 단위PC벽체 및 오거 장비굴착에 의한 단위PC 사각파일 투입과 중앙부 벽체 또는 기둥에는 오거 장비굴착에 의한 단위PC 사각파일 투입하며 CIP구근을 시공하는, CIP구근 시공공정(S10)과,
일측 Half PC구조를 이루도록 슬래브 시공하는, 일측 상부슬래브 시공공정(S20)과,
타측 Half PC구조를 이루도록 슬래브 시공하는, 타측 상부슬래브 시공공정(S30)과,
중앙측 Half PC구조를 이루도록 슬래브 시공하는, 중앙측 상부슬래브 시공공정(S40)과,
코너부 보강 시공공정(S50-1)과,
양측 하부슬래브 및 중앙부 벽체 또는 기둥 보강 시공공정(S60)과,
양측 내벽체 시공공정(S70)과, 마무리 시공공정(S80)으로 이루어지는 것을 특징으로 하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
CIP bulb construction process, in which both side walls insert unit PC square pile by trench excavation and auger equipment excavation and unit PC square pile by auger equipment excavation into central wall or column, and construct CIP bulb. )and,
One side upper slab construction process (S20), and the slab construction to form one side half PC structure,
The other upper slab construction process (S30), and the slab construction to form the other half PC structure,
A center upper slab construction process (S40) for slab construction to form a center side half PC structure,
Corner reinforcement construction process (S50-1),
Both lower slab and central wall or column reinforcement construction process (S60),
A method of constructing an underground road using a combined wall method of a temporary structure and a main structure, characterized by comprising both inner wall construction steps (S70) and a finish construction step (S80).
양 측벽 및 중앙부를 이루는, CIP구근 시공공정(S10)과,
상기 양 측벽 CIP구근 상단의 어느 위치에서 어스앙카를 시공하고 내부굴착을 하는, 내부굴착 및 어스앙카 시공공정(S50-2)과,
최종 하단부까지 굴착 완료하여 양측 하부슬래브를 시공하는, 양측 하부슬래브 시공공정(S60-1)과,
내벽체를 시공하며 어스앙카를 철거하는, 양측 내벽체 시공공정(S70)과,
상기 양측 내벽체에 PSC 빔을 거치하고, 양측 PSC 빔 연단의 내부간을 가로보로 연결하고, PSC 빔 상부슬래브와 배면슬래브를 시공하는, PSC 빔 거치 및 상부슬래브 시공공정(S230)과,
내부 벽체 타일 시공과 하부슬래브 상면으로 아스콘 포장을 하고, 상부슬래브를 되메우기 하여 아스콘 포장을 하는, 마무리 시공공정(S80)으로 이루어지는 것을 특징으로 하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
CIP bulb construction process (S10) forming both sidewalls and the central portion,
Internal excavation and earth anchor construction process (S50-2), and the earth excavation at any position of the upper side of the CIP bulb and internal excavation, and
(S60-1) for constructing both the lower slabs by completing the excavation to the final lower end,
Both the inner wall construction process (S70), which dismantles the earth anchor while constructing the inner wall,
PSC beam mounting and upper slab construction process (S230) to mount the PSC beam to the inner wall of both sides, to connect the inner side of the both ends of the PSC beam crosswise, and to construct the PSC beam upper slab and the rear slab;
Underground road using the temporary structure and the plywood method of the main structure, characterized in that the finishing construction process (S80), which is ascon pavement to the inner wall tiles and the upper surface of the lower slab, and ascon pavement by filling the upper slab back. Construction method.
CIP구근 시공공정(S10)과, 최종 하단부까지 굴착 완료하여 양측 하부슬래브를 시공하는, 양측 하부슬래브 시공공정(S60-1)과, 내벽체를 시공하여 어스앙카를 철거하는, 양측 내벽체 시공공정(S70)과, 내부 벽체 타일 시공과 하부슬래브 상면으로 아스콘 포장을 하는, 마무리 시공공정(S80)으로 이루어지는 것으로, 지하도로 시공 영역 중 U-Type 구조를 갖는 상방이 개방되는 지하도로 영역에서의 시공방법에 있어서,
상기 CIP구근 시공공정(S10)은, 양 측벽 및 중앙부를 이루도록 지하차도를 구성하기 위한 지역 범위내에서 중앙부와 양측 측면부에 각각 CIP구근(700)을 형성하되 중앙부에는 중앙 헌치 상단까지 형성하고 양측 측면부에는 벽체 즉 측벽을 지표까지 형성하도록 하고,
상기 CIP구근 시공공정(S10)과 상기 양측 하부슬래브 시공공정(S60-1) 단계 사이에, 상기 양측벽 CIP구근 상단의 어느 위치에서 1단의 어스앙카를 시설하여 측벽(131)이 안정되도록 시공하고 내부굴착을 하여 상기 CIP구근 시공공정(S10)에서 긴장 정착하게 되는 PC강연선(723)이 측벽(731)에 작용되는 부재력을 지탱하도록 하는, 내부굴착 및 어스앙카 시공공정(S50-2)을 포함하는 것을 특징으로 하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
CIP bulb construction process (S10), both bottom slab construction process (S60-1), which excavates to the final lower end and constructs both side lower slabs, and both inner wall construction process of removing the earth anchor by constructing the inner wall body (S70) and the finishing construction step (S80), which is an ascon pavement to the inner wall tiles and the upper surface of the lower slab, the construction in the underground road area in which the upper side having a U-Type structure is opened in the underground road construction area. In the method,
The CIP bulb construction process (S10), forming the CIP bulb 700 in the central portion and both side sides within the region range for configuring the underground roadway to form both sidewalls and the central portion, but forms the central portion to the upper end of the central haunch and both side sides To form walls or side walls to the ground,
Between the CIP bulb construction process (S10) and the both sides of the lower slab construction process (S60-1) step, the construction of the ground anchors of the first stage at any position of the upper side of the CIP bulb on both sides to install the side wall 131 is stabilized And the internal drilling and earth anchor construction process (S50-2) to the PC strand wire 723 to be tension-fixed in the CIP bulb construction process (S10) to support the member force acting on the side wall 731 Underground road construction method using a temporary wall construction method of the temporary structure and the main structure, characterized in that it comprises.
양 측벽 및 중앙부 벽체 또는 기둥을 이루는 CIP구근 시공공정(S10)과, 일측 상부슬래브 시공공정(S20)과, 타측 상부슬래브 시공공정(S30)과, 중앙측 상부슬래브 시공공정(S40)과, 코너부 보강 및 어스앙카 시공공정(S50)과, 양측 내벽체 기초 및 중앙부 벽체 또는 기둥의 시공공정(S60-2)과, 양측 내벽체 시공공정(S70)과, 마무리 시공공정(S80)으로 지하차도의 시공이 이루어지는 지하차도 시공방법에 있어서,
상기 일측 상부슬래브 시공공정(S20)에서, 복토시에는 일측 상부슬래브와 중앙측 상부슬래브의 지그재그 방식의 철근이음을 위하여 H말뚝 한쪽 플렌지에 다수개의 천공구멍을 내고 이음부로부터 뒤로 일정거리를 후퇴하여 시설하되 철근에 연결된 앵커체를 천공구멍 위치에서 볼트로 결합하는 방식으로 다수개를 횡으로 시설한 후 적층하며 지표에 이르기까지 시설하는 것과,
상기 중앙측 상부슬래브 시공공정(S40)은 상기 상부슬래브의 전체 폭원을 3등분 또는 2등분 시공하여 우각부와 중앙부에서 발생되는 부모멘트 최대 위치에 철근 이음을 두지 않도록 시설하는 것과,
상기 양측 내벽체 시공공정(S70)에서 지하도로의 좌우 상단측에 각각 동일하게 적용되기 위한 것으로, 상기 내벽체의 철근과 교차 배치되는 배력철근과, 측벽을 이루는 CIP구근에 매입되는 철근 중 내벽체에 근접하는 철근에 가로방향으로 띠철근에 접하여 배치된 배력철근을 연결하기 위한 연결철근이 상하로 각각 다수개 등간격 이격 구비되는 것과,
상기 마무리 시공공정(S80)에서, 내벽체의 내측철근의 배력철근이 측벽을 이루는 각 CIP구근에 매입되는 철근 중, 내벽체에 접하는 부분인 판넬에 의해 절개되어지는 부분에 의해 노출된 철근의 띠철근과 연결 고정되도록 하여 하부슬래브와 측벽 하단이 연결되도록 구성하는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
CIP bulb construction process (S10) forming both sidewalls and central wall or column, one upper slab construction process (S20), the other upper slab construction process (S30), the central side upper slab construction process (S40), and the corner Underground reinforcement by secondary reinforcement and earth anchor construction process (S50), both inner wall foundation and center wall or column construction process (S60-2), both inner wall construction process (S70) and finishing construction process (S80) In the method of construction of the underground road where the construction of the
In the one side upper slab construction process (S20), during the covering, a plurality of perforation holes are made in one flange of the H pile for the zigzag reinforcement of the one side upper slab and the center side upper slab, and then retreat a certain distance backward from the joint part. Facility, but the anchor body connected to the reinforcing bar by bolting at the position of the drilling hole to install a plurality of laterally and laminating and to the ground surface,
The upper slab construction process (S40) includes installing the entire widthwise portion of the upper slab in three or two equal portions so as not to allow the reinforcing bars to be located at the maximum positions of the vertical moments generated in the right and left portions,
In both the inner wall construction process (S70) to be applied equally to the upper left and right sides of the underground road, respectively, the inner wall body of the reinforcement reinforcement intersected with the reinforcement of the inner wall and embedded in the CIP bulb forming the side wall Connecting reinforcing bars for connecting the reinforcing bars arranged in contact with the band bars in the transverse direction to the reinforcing bars adjacent to the upper and lower, respectively, and provided with a plurality of equal intervals,
In the finishing construction step (S80), the strip of reinforcing bar exposed by the part which is cut by the panel which is a part in contact with the inner wall of the reinforcing bars of the inner reinforcement of the inner wall is embedded in each CIP bulb forming the side wall A method of constructing an underground road using a temporary wall construction method of the temporary structure and the main structure, comprising the lower slab and the lower sidewall connected to each other to be fixed to the reinforcing bars.
제 1 항 내지 제 8 항 중 어느 한 항에 있어서,
상기 CIP구근이 시설되는 지반이 암반 지역일 경우, 토사층까지만 CIP구근을 형성한 다음, 상부슬래브를 시공하고 암반구간까지 내부 굴착 하여 CIP 받침앵커를 시설하고 내부굴착을 계속하되, 토사층까지만 시설된 상기 CIP구근 하단에서 하부슬래브 버림콘크리트 하단까지 암반을 절취하여 CIP 구근을 이어 내린 후 분말방수제가 혼합 처리된 콘크리트를 타설하여 내벽체를 이루는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
The method according to any one of claims 1 to 8,
If the ground where the CIP bulb is installed is a rock area, the CIP bulb is formed only up to the soil layer, and then the upper slab is constructed and the excavator is internally excavated to the rock zone to install the CIP support anchor and continue the internal excavation, but only to the soil layer. Underpass using the plywood construction method of the hypothetical structure and the main structure, which includes cutting the rock from the bottom of the CIP bulb to the bottom of the slab cast concrete, extending the CIP bulb, and then pouring concrete mixed with the powder waterproofing agent to form an inner wall. Construction method
제 1 항 내지 제 6 항 중 어느 한 항에 있어서,
상기 상부슬래브의 전체 폭원을 3등분 또는 2등분 시공하여 우각부와 중앙부에서 발생되는 부모멘트 최대 위치에 철근 이음을 두지 않는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
7. The method according to any one of claims 1 to 6,
Underground construction method using the plywood construction method of the hypothetical structure and the main structure, including not including the reinforcing bars at the maximum position of the parent moment generated in the right angle and the center by constructing the entire width source of the upper slab in three or two parts .
제 1 항 내지 제 6 항 중 어느 한 항에 있어서,
지하도로의 좌우 상단측에 각각 동일하게 적용되기 위한 것으로, 상기 내벽체의 철근과 교차 배치되는 배력철근과, 측벽을 이루는 CIP구근에 매입되는 철근 중 내벽체에 근접하는 철근에 가로방향으로 띠철근에 접하여 배치된 배력철근을 연결하기 위한 연결철근이 상하로 각각 다수개 등간격 이격 구비되는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
7. The method according to any one of claims 1 to 6,
To be applied equally to the upper left and right sides of the underground road, the reinforcing bars intersected with the reinforcing bars of the inner wall, and the reinforcing bars in the transverse direction to the reinforcing bars close to the inner wall among the reinforcing bars embedded in the CIP bulbs forming the side walls. A method of constructing an underground road using a plywood construction method of the temporary structure and the present structure, including a plurality of connecting rebars, each of which is spaced up and down, equidistantly spaced apart to connect the reinforcing bars arranged in contact with each other.
제 1 항 내지 제 5 항 중 어느 한 항에 있어서,
상기 일측 상부슬래브 시공공정에서, 복토시에는 일측 상부슬래브와 중앙측 상부슬래브의 지그재그 방식의 철근이음을 위하여 H말뚝 한쪽 플렌지에 다수개의 천공구멍을 내고 이음부로부터 뒤로 일정거리를 후퇴하여 시설하되 철근에 연결된 앵커체를 천공구멍 위치에서 볼트로 결합하는 방식으로 다수개를 횡으로 시설한 후 적층하며 지표에 이르기까지 시설하는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
6. The method according to any one of claims 1 to 5,
In the one-side upper slab construction process, during the covering, a plurality of perforation holes are made in one flange of the H-pile for the zigzag reinforcement of the one-side upper slab and the center-side upper slab, and the facility is retracted a certain distance backward from the joint, but the rebar is installed. A method of assembling an anchor body connected to a perforation hole by a bolt, installing a plurality of the anchor body laterally and stacking the anchor body to the surface, .
제 3 항 또는 제 5 항에 있어서,
지하차도를 구성하는 지역 범위내에서 중앙을 분리하기 위한 중앙부와 양측 측면부 형성에 있어서 벽체 즉 측벽부에는 PC 사각파일벽체 또는 PC벽체를 형성토록 하고, 상기 중앙부에는 PC 사각파일벽체 또는 CIP구근을 이용하여 벽체로 형성하거나 또는, 중간 중간이 끊겨지는 형태의 기둥 타입을 이루는 CIP구근을 형성하여 시설되는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
The method according to claim 3 or 5,
In forming the central part and the two side parts to separate the center within the area of the underground roadway, the wall, that is, the side wall part, has to be formed with the PC square pile wall or PC wall, and the center portion uses PC square pile wall or CIP bulb. Forming a wall or forming a CIP bulb forming a column type in which the middle is broken. The construction of the underground road using the construction of the temporary structure and the plywood method of the present structure.
제 13 항에 있어서,
상기 PC 사각파일 벽체 또는 PC벽체는 단위PC벽체가 조립되어 구성되도록 하기 위해, 다수의 주철근이 일정규격의 정사각형 또는 직사각형으로 배열 배치되고 상기 주철근과 교차하는 배력철근을 등간격으로 이격시키며 스터럽으로 묶어 주철근과 배력철근이 하나로 조합되어 콘크리트가 타설 양생되어 단위 PC사각파일 벽체 또는 단위 PC벽체가 건조되도록 하는 것과,
상기 단위PC벽체는 연결부위에 2개의 돌출 L형강을 매입한 상태로 건조하며, 인접한 단위PC벽체는 연결부위에 2개의 매입 L형강과 철판을 매입한 상태로 건조하여 상호 끼워 연결 가능하도록 하는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
The method of claim 13,
In order for the PC square pile wall or PC wall to be assembled by unit PC walls, a plurality of main bars are arranged in a square or rectangle of a predetermined size, and the reinforcing bars intersecting the main bars are spaced at equal intervals and tied with a stub. The combination of cast iron rope and steel reinforcing bar is used to make the concrete paved concrete, so that the unit PC rectangular pile wall or unit PC wall is dried,
The unit PC wall is dried in a state where two projecting L-shaped steel bars are embedded in a connecting portion, and adjacent unit PC walls are dried in a state in which two embedded L-shaped steel plates and steel plates are embedded in a connecting portion so that they can be connected to each other Underground road construction method using temporary structure and plywood method of this structure to include.
제 1 항에 있어서,
상기 코너부 보강 및 어스앙카 시공공정(S50)에서, 상기 각 상부슬래브의 타설 작업을 완료한 후 상기 상부슬래브와 CIP가 결합되어 있어 부모멘트가 크게 작용되는 것을 저감시키기 위해 상기 상부슬래브나 내벽체의 지간을 짧게 유도하기 위해 코너부 일부만을 굴착하여 일정한 간격으로 사보강재를 설치하는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
The method of claim 1,
In the corner reinforcement and earth anchor construction process (S50), after finishing the casting of each upper slab and the upper slab and CIP is combined to reduce the large parent moment acts the upper slab or inner wall body Underground construction method using the construction of the temporary structure and the combined wall method of the main structure, including excavating only a part of the corner portion to install a stiffener steel at regular intervals in order to guide the interval of the short.
제 1 항 내지 제 7 항 중 어느 한 항에 있어서,
상기한 마감공정에서, 내벽체의 내측철근의 배력철근이 측벽을 이루는 각 CIP구근에 매입되는 철근 중, 내벽체에 접하는 부분인 판넬에 의해 절개되어지는 부분에 의해 노출된 철근의 띠철근과 연결 고정되도록 하여 하부슬래브와 측벽 하단이 연결되도록 구성하는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
The method according to any one of claims 1 to 7,
In the above finishing process, the reinforcing bars of the inner reinforcement of the inner wall are connected to the band reinforcing bars exposed by the part cut by the panel, which is the part contacting the inner wall, among the reinforcing bars embedded in each CIP bulb forming the side wall. A method of constructing an underground road using a combined wall construction method of the temporary structure and the main structure, including fixing the lower slab and the lower sidewall of the side wall to be fixed.
제 14 항에 있어서,
상기 단위PC벽체를 이루는 구간이 암반 구간일 경우, 토사층까지만 단위PC벽체를 형성한 다음 상부슬래브를 시공하고 암반구간까지 내부굴착하여 단위PC벽체 받침앵커를 시설하고 내부굴착을 계속하되 토사층까지만 시설된 단위PC벽체 하단에서 하부슬래브 버림콘크리트 하단까지 암반을 절취하여 단위PC벽체의 철근을 이어내리고 분말방수제가 혼합된 콘크리트를 타설하면 견고한 내벽체가 형성되도록 하는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
15. The method of claim 14,
If the section constituting the unit PC wall is a rock section, the unit PC wall is formed only up to the soil layer, and then the upper slab is constructed and the unit is excavated to the rock section, and the unit PC wall support anchor is installed and the internal excavation is continued, but only the soil layer is installed. The sum of the hypothetical structure and the main structure, including cutting the rock from the bottom of the unit PC wall to the bottom of the slab cast concrete, extending the reinforcing bars of the unit PC wall, and placing the concrete mixed with powder waterproofing agent to form a solid inner wall. Underground road construction method using wall method.
제 14 항에 있어서,
상기 단위PC벽체 상단고가 굴착고의 높낮이에 따라 달라질 경우 상기 단위PC벽체와 달아매기 벽체를 결합하여 정렬 투입하며 결합하는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
15. The method of claim 14,
If the upper height of the unit PC wall is different depending on the height of the excavation height, including the combination of the unit PC wall and the hanging wall, and put into the combination, the construction method of the underground road using the combined wall construction method of the temporary structure and the present structure.
제 18 항에 있어서,
상기 달아매기 벽체는, 콘크리트로 PC 제작되어 달아매기 철근과 결합시키되, 상기 달아매기 벽체 상단에 거치용 H형강을 가로방향으로 배치하여 가이드형강에 안치하고 상부슬래브와 벽체를 연결할 때 상기 거치용 H형강을 분리하는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
The method of claim 18,
The hanging wall is made of concrete PC to be combined with the hanging reinforcing bar, the mounting H-shaped steel placed on the top of the hanging wall in the horizontal direction and placed in the guide-shaped steel when connecting the upper slab and the wall for mounting H A method of constructing an underground road using a temporary wall construction method of a temporary structure and a main structure including separating a section steel.
제 4 항에 있어서,
상기 말뚝 시공공정에서의 말뚝은 중앙부의 중간말뚝과 양 측벽부의 엄지말뚝으로 구분되어 형성되는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
5. The method of claim 4,
Wherein the piles in the pile construction process are divided into a middle pile at the center and a thumb pile at both side walls, and a method of constructing the underpass using the combined structure method of the present structure.
제 20 항에 있어서,
상기 일측 상부슬래브 시공공정에서, 엄지말뚝의 플렌지에는 콘크리트 PC2 토류판을 설치하고 중간말뚝 플렌지에는 콘크리트 PC1 토류판을 설치하되, 상기 PC2 토류판은 엄지말뚝 플렌지를 회전용 철판으로 감싸되 유격이 형성되도록 하고, PC1 토류판은 걸쇠철판에 너트와 철근을 이용하여 조립한 상태에서 엄지와 중간말뚝 플렌지에 끼워지도록 시설하며, 상기 일측 상부슬래브의 편측 지지를 위해 일측 상부슬래브내 앵커에 PC Wire를 걸어 엄지말뚝 한측 플렌지의 천공홀을 통하여 상기 엄지말뚝 상단에 정착하는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
21. The method of claim 20,
In the one side upper slab construction process, concrete PC2 earth plate is installed on the flange of the thumb pile and concrete PC1 earth plate is installed on the middle pile flange, the PC2 earth plate is wrapped with the iron plate for the thumb pile flange to form a play, PC1 earth plate is installed on the clasp plate with nuts and rebars to be fitted to the thumb and middle pile flanges, and hangs PC wire to the anchor in one upper slab to support one side of the upper slab on one side And fixing the pile to the upper end of the thumb pile through a perforation hole in the bottom of the pile.
제 3 항 또는 제 5 항에 있어서,
상기 CIP(Cast-in-place) 구근은 다수의 주철근이 직사각형으로 배열 배치되고 상기 주철근을 감싸는 띠철근을 등간격으로 이격시키며 주철근과 띠철근이 하나로 조합된 철근망태가 형성되도록 한 후 내부에 콘크리트 타설 양생하여 유닛화된 원기둥 형태의 CIP 구근을 이루도록 하거나, 또는 상기 CIP구근이 삽입되기 위한 홀을 천공한 후 상기 홀에 철근망태를 삽입 한 다음 콘크리트를 타설 양생하여 완성된 CIP구근을 얻도록 하는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
The method according to claim 3 or 5,
The cast-in-place (CIP) bulb has a plurality of cast irons arranged in a rectangular shape and spaced apart the band reinforcing bars surrounding the main bars at equal intervals. Placing curing to form unitary cylindrical CIP bulbs, or drilling holes for inserting the CIP bulbs, inserting reinforcing bars into the holes, and then curing the concrete to obtain finished CIP bulbs. Underground road construction method using the temporary structure of the temporary structure and the main structure including the thing.
제 22 항에 있어서,
상기 CIP구근과 CIP구근 사이에 미리 형성된 CIP구근의 양 편측을 갈아내면서 천공하여 동형의 신CIP구근을 새로이 형성하여, 상기 CIP구근과 상기 신CIP구근이 상호 겹치며 시설되는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
23. The method of claim 22,
Hypothesis structure, including the CIP bulb and the new CIP bulb overlapping with each other by forming a new CIP bulb of the same type by drilling and grinding both sides of the pre-formed CIP bulb between the CIP bulb and the CIP bulb A method of constructing underground road using combined structure method of this structure.
제 6 항에 있어서,
상기 PSC빔 거치 및 상부슬래브 시공공정에서, 상기 양측 내벽체 시공공정(S70)을 거쳐 상기 내벽체의 설치 시공이 완료되면 PSC빔을 거치하되, 상기 내벽체에 근접하는 철근이 상기 PSC빔 내부에 미리 구성되어 있는 PVC관을 관통하여 상부슬래브에 배치 되어지는 또 다른 철근과 연결 고정되도록 하는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
The method according to claim 6,
In the PSC beam mounting and upper slab construction process, when the installation of the inner wall is completed through the both inner wall construction steps (S70), the PSC beam is mounted, and reinforcing bars close to the inner wall are placed inside the PSC beam. A method of constructing an underground road using a temporary wall construction method of the temporary structure and the main structure, including connecting and fixing with another reinforcing bar disposed on the upper slab through a pre-configured PVC pipe.
제 24 항에 있어서,
상기 PSC빔은 단부에 내벽체의 철근이 관통할 수 있는 PVC관을 매설하고, 측벽과 고정 연결하기 위해 상기 PSC빔 단부에 연단철근을 배치하고, 우각부 부모멘트를 저감하기 위한 PC강연선을 PSC빔 연단부 상단에 배치하며 제작되는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
25. The method of claim 24,
The PSC beam embeds a PVC pipe through which the reinforcing bars of the inner wall can penetrate at the end, and arranges the stepped reinforcing bar at the end of the PSC beam for fixed connection with the side wall, and a PC stranded wire for reducing the right corner portion. And a bottom end of the beam, wherein the method comprises the steps of:
제 8 항에 있어서,
상기 양측 내벽체 기초 및 중앙부 벽체 또는 기둥보강 시공공정(S60-2)에서,
양측의 굴착된 공간에 버림콘크리트를 형성한 후 해당 굴착 부분의 측벽 하단으로 내벽체 기초를 타설하고, 중앙부의 좌우 양측에 배력철근을 대고 개소별로 시공되어진 CIP구근을 띠철근과 묶어 일체로 하는 보강벽체를 타설하여 완성된 형태의 중앙부를 구성하는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
The method of claim 8,
In both the inner wall base and the central wall or column reinforcement construction process (S60-2),
After forming discarded concrete in the excavated space on both sides, the inner wall foundation is laid at the bottom of the side wall of the excavated part, and the reinforcement is integrated by banding the CIP bulbs that are constructed by places with backing bars on the left and right sides of the center. And constructing a central part of the finished form by pouring the wall into the underground structure using the combined structure method of this structure.
제 6 항 또는 제 7 항에 있어서,
상기 CIP구근을 양측벽체 또는 중앙부로서의 역할과 부력방지용 또는 지지용 마찰 저항을 얻도록, 상기 CIP 구근 하단부에 2개소의 마찰력저항철근을 고무슬리브에 끼워 V모양으로 절곡하고 교차시켜 열십자(+)로 교차되도록 묶은 다음 CIP구근 하단부 일정한 위치에 다수의 종간격을 유지하며 띠철근위에 배치하되, 중심부에 PC강선을 배치한 상태에서 CIP구근을 형성하기 위한 콘크리트를 일정 높이로 타설하면서 콘크리트가 양생되기 전 케이싱을 들어올릴 때 PC강선을 잡아당겨 고무슬리브에 끼워진 양쪽의 마찰력저항철근이 시계와 반시계 방향으로 회전하면서 V모양에서 모양으로 펴진 상태에서 양생되도록 하며 CIP구근에서 돌출되도록 하여 부력 작용시 구조체의 상승을 저지시키도록 하는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
The method according to claim 6 or 7,
The CIP bulb serves as both sides of the wall or the center portion, and two frictional resistance steels are bent into the rubber sleeve at the lower end of the CIP bulb to obtain a friction resistance for preventing or supporting buoyancy. After placing them so as to intersect, they are placed on the band reinforcement, maintaining a plurality of longitudinal intervals at the lower part of the CIP bulb, and the concrete is cured while placing the concrete to form a CIP bulb at a certain height with the PC steel wire in the center. When lifting the entire casing, pull the PC steel wire so that the frictional resistance bars on both sides of the rubber sleeve rotate in the clockwise and counterclockwise direction to cure in the form of V-shaped and protrude from the CIP bulb. Using a plywood method of the temporary structure and the main structure, including preventing the rise of Underground road construction method.
제 6 또는 제 7 항에 있어서,
상기 CIP구근을 양측벽체 또는 중앙부로서의 역할과 부력방지용 또는 지지용 마찰 저항을 얻도록, 상기 CIP 구근 하단부에 4개소의 마찰력저항철근을 고무슬리브에 끼워 V모양에 양 날개가 달린 모양으로 날개철근을 이루고 교차시켜 열십자(+)로 교차되도록 묶은 다음 CIP구근 하단부 일정한 위치에 다수의 종간격을 유지하며 띠철근(720)위에 배치하되 중심부에 PC강선을 배치한 상태에서 CIP구근을 형성하기 위한 콘크리트를 일정 높이로 타설시 콘크리트가 양생되기 전 케이싱을 들어올릴 때 PC강선을 잡아당겨 고무슬리브에 끼워진 양쪽의 마찰력저항철근이 V모양에서 모양으로 바뀌면서 날개철근을 수평방향으로 밀어 돌출시킨 상태로 양생되어 펴지며 CIP구근에서 돌출되도록 하여 부력 작용시 구조체의 상승을 저지시키도록 하는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
The method according to claim 6 or 7,
In order to obtain the frictional resistance for supporting or supporting buoyancy and buoyancy of the CIP bulb as a side wall or a central portion, four frictional resistance steels are inserted in the rubber sleeve at the lower end of the CIP bulb in a V-shape with wing wings in the shape of both wings. After forming and intersecting to cross the crisscross (+) to cross, and maintain a plurality of longitudinal intervals at a certain position at the bottom of the CIP bulb and placed on the band reinforcement 720, the concrete to form a CIP bulb with a PC steel wire in the center When placing the casing at a certain height, when lifting the casing before the concrete is cured, the frictional resistance bars on both sides of the rubber sleeve are pulled into the shape of the rubber sleeve by pulling the PC steel wire and cured by pushing the wing reinforcement horizontally. Hypothesis, which includes extending and protruding from the CIP bulb to arrest the rise of the structure upon buoyancy. Construction method as underground tank and using the sum Wall construction method of the present structure.
제 8 항에 있어서,
상기 CIP구근 시공공정에서, 상기 CIP구근의 철근망태 상단과 벽체 상단에 일정길이의 수직 H-형강을 양측 측면부 CIP구근에만 설치토록하고 일측 및 타측 상부슬래브와 접속되는 위치까지 돌출시킨 후 연결되는 일정길이의 수평 H-형강을 설치하고 철근망태를 조립하여, 하부슬래브가 없어 부재력이 상부슬래브 우각부에 크게 발생되는 것을 제어하고, PC강연선을 수평수직 H-형강이 배치되지 않은 곳에 배치하여 긴장정착하므로 부재력 값을 저감 시킬 수 있는 것을 포함하는, 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법.
The method of claim 8,
In the CIP bulb construction process, a predetermined length of vertical H-beams are installed only on both side CIP bulbs at the top of the reinforcing mesh top and the wall of the CIP bulb, and then projected to a position connected to one side and the other upper slab, and then connected. By installing horizontal H-shaped steel of length and reinforcing steel mesh, it controls the absence of lower slab so that member force is largely generated in upper slab right part, and PC strand is placed where horizontal vertical H-shaped steel is not placed Therefore, the method of construction of the underground road using the plywood method of the temporary structure and the main structure, including that the member force value can be reduced.
KR1020130079702A 2013-07-08 2013-07-08 Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method KR101363878B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020130079702A KR101363878B1 (en) 2013-07-08 2013-07-08 Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020130079702A KR101363878B1 (en) 2013-07-08 2013-07-08 Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method

Publications (1)

Publication Number Publication Date
KR101363878B1 true KR101363878B1 (en) 2014-02-17

Family

ID=50271202

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020130079702A KR101363878B1 (en) 2013-07-08 2013-07-08 Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method

Country Status (1)

Country Link
KR (1) KR101363878B1 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20150143952A (en) 2014-06-13 2015-12-24 한국철도기술연구원 Method for constructing underground structure having precast wall using h-pile, method for connecting precast wall and slab
KR20150143951A (en) 2014-06-13 2015-12-24 한국철도기술연구원 Precast wall using h-pile, underground structure having precast wall using h-pile and method for connecting precast wall
KR20160103723A (en) * 2015-02-25 2016-09-02 (주)나우기술 The Construction Method and Structure of Non-excavation tunnel what press in extruding Steel pipe by Arch type Precast Upperslab
KR20160125671A (en) 2015-04-22 2016-11-01 한국철도기술연구원 Precast wall using soil interception pile, underground structure having Precast wall and Method for connecting precast wall
KR20160131410A (en) 2015-05-07 2016-11-16 (주)나우기술 Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method
KR20170010881A (en) 2017-01-19 2017-02-01 한국철도기술연구원 Method for connecting precast wall and slab, and underground structure constructed by the same
KR20170013366A (en) 2017-01-19 2017-02-06 한국철도기술연구원 Underground structure having Precast wall using H­pile
KR20210154337A (en) * 2020-06-12 2021-12-21 정하동 Construction Method of Underground Structures

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07197772A (en) * 1993-12-29 1995-08-01 Okumura Corp Construction method for underground passage introduction section
KR20010083635A (en) * 2000-02-17 2001-09-01 박병무 Underground Roadway and Production Method Thereof
KR100542384B1 (en) 2003-03-10 2006-01-10 아이앤아이스틸 주식회사 Construction system of underground roadway
KR101187369B1 (en) * 2010-05-04 2012-10-02 (주)나우이앤씨 Cip use of underground motorways construction work method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07197772A (en) * 1993-12-29 1995-08-01 Okumura Corp Construction method for underground passage introduction section
KR20010083635A (en) * 2000-02-17 2001-09-01 박병무 Underground Roadway and Production Method Thereof
KR100542384B1 (en) 2003-03-10 2006-01-10 아이앤아이스틸 주식회사 Construction system of underground roadway
KR101187369B1 (en) * 2010-05-04 2012-10-02 (주)나우이앤씨 Cip use of underground motorways construction work method

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20150143952A (en) 2014-06-13 2015-12-24 한국철도기술연구원 Method for constructing underground structure having precast wall using h-pile, method for connecting precast wall and slab
KR20150143951A (en) 2014-06-13 2015-12-24 한국철도기술연구원 Precast wall using h-pile, underground structure having precast wall using h-pile and method for connecting precast wall
KR20160103723A (en) * 2015-02-25 2016-09-02 (주)나우기술 The Construction Method and Structure of Non-excavation tunnel what press in extruding Steel pipe by Arch type Precast Upperslab
KR101662096B1 (en) 2015-02-25 2016-10-14 (주)나우기술 The Construction Method of Non-excavation tunnel what press in extruding Steel pipe by Arch type Precast Upperslab
KR20160125671A (en) 2015-04-22 2016-11-01 한국철도기술연구원 Precast wall using soil interception pile, underground structure having Precast wall and Method for connecting precast wall
KR20160131410A (en) 2015-05-07 2016-11-16 (주)나우기술 Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method
KR20170010881A (en) 2017-01-19 2017-02-01 한국철도기술연구원 Method for connecting precast wall and slab, and underground structure constructed by the same
KR20170013366A (en) 2017-01-19 2017-02-06 한국철도기술연구원 Underground structure having Precast wall using H­pile
KR20210154337A (en) * 2020-06-12 2021-12-21 정하동 Construction Method of Underground Structures
KR102431393B1 (en) 2020-06-12 2022-08-11 정하동 Construction Method of Underground Structures

Similar Documents

Publication Publication Date Title
KR101363878B1 (en) Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method
KR100866162B1 (en) Chair-type self-supported earth retaining wall constructing method
KR101344063B1 (en) The construction method of steel-concrete underpass
KR20160131410A (en) Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method
KR101388521B1 (en) Construction method of underground structure under the pier with supporting piles
KR100938395B1 (en) The Construction Method of Underpass using Steel-Concrete Composite Wall Pile
KR101167511B1 (en) Underpass using precast concrete pile and method for constructing the same
KR100546432B1 (en) A arch-shaped composite structure with the precast concrete pannel and the steel frame using the open trench tunnel method, and method for it
KR101206860B1 (en) Excavation tunnel constructing method using vertical side wall and arch ceiling
KR101288601B1 (en) Underpass using precast concrete pile and bottom slab and method for constructing the same
KR101187369B1 (en) Cip use of underground motorways construction work method
JP2003213708A (en) Construction method for underground structure and elevated traffic roadway
KR101011805B1 (en) Method of constructing underground structure crossing pile bases in a pile-based ground and underground structure constructed using the same
JP3893056B2 (en) Construction method of underground structure
KR100806867B1 (en) Steel pipe roof assembly and the construction method for Tunnel using thereof
JP5480744B2 (en) Foundation for structure and its construction method
JP3486602B2 (en) Pier foundation method and pier foundation structure
JP7061002B2 (en) How to repair a bridge
KR101787366B1 (en) A Retaining wall using Precast pile and Construction method thereof
JP6340044B2 (en) Overhang trail construction body and construction method of overhang trail using these
KR102021496B1 (en) Retaining wall construction method and retaining wall structure by the method
JP4680676B2 (en) Three-dimensional intersection construction method using backfilling material and construction material of fluidized soil
JP3251698B2 (en) Tunnel lining element and tunnel construction method using the same
KR20110034831A (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
JP2013087516A (en) Method of forming underground space under ground traffic road

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E90F Notification of reason for final refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20170206

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20180211

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20190211

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20200106

Year of fee payment: 7