JP5852315B2 - Precast concrete member connection structure - Google Patents
Precast concrete member connection structure Download PDFInfo
- Publication number
- JP5852315B2 JP5852315B2 JP2011069131A JP2011069131A JP5852315B2 JP 5852315 B2 JP5852315 B2 JP 5852315B2 JP 2011069131 A JP2011069131 A JP 2011069131A JP 2011069131 A JP2011069131 A JP 2011069131A JP 5852315 B2 JP5852315 B2 JP 5852315B2
- Authority
- JP
- Japan
- Prior art keywords
- precast concrete
- floor slab
- girder
- steel
- steel girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Description
本発明は、例えば、床版等のプレキャストコンクリート部材、及び、プレキャストコンクリート部材結合構造に関する。 The present invention relates to a precast concrete member such as a floor slab and a precast concrete member coupling structure, for example.
従来の鉄道橋は、鋼桁と、鋼桁の上に設置されたまくらぎと、まくらぎの上に設置されたレールを有する。近年、新設構造では、橋まくらぎの代りにプレキャストコンクリート製の床版を鋼桁に設置して合成桁とするケースが多い。床版は鋼桁に対してずれ止めで固定されている。 A conventional railway bridge has a steel girder, a sleeper installed on the steel girder, and a rail installed on the sleeper. In recent years, there are many cases in new constructions where precast concrete floor slabs are installed on steel girders instead of bridge sleepers to form composite girders. The slab is fixed to the steel girder with a stopper.
既設の鋼桁にコンクリート製の床版を設置する場合、既設の鋼桁のリベット孔を利用したボルトを取り付け、このボルトにより床版の位置ずれを止める方法が考えられる。しかし、この方法は、通常現場で鋼桁の上にコンクリートを打設して床版を作製するため、多くの日時と施工の手間を必要としていた。 When installing a concrete floor slab on an existing steel girder, it is possible to attach a bolt using the rivet hole of the existing steel girder and stop the displacement of the floor slab with this bolt. However, this method usually requires a lot of time and work to construct a floor slab by placing concrete on a steel girder on site.
上記問題は、床板と鋼桁を一般化したプレキャストコンクリート部材と相手部材とを結合する場合でも同様である。 The above problem is the same even when the precast concrete member generalizing the floor board and the steel beam and the mating member are combined.
そこで、本発明の目的は、施工性を向上させたプレキャストコンクリート部材、及び、プレキャストコンクリート部材結合構造を提供することにある。 Then, the objective of this invention is providing the precast concrete member which improved workability | operativity, and the precast concrete member coupling | bonding structure.
以下、符号を付して本発明の特徴を説明する。なお、符号は参照のためであり、本発明を実施形態に限定するものでない。 Hereinafter, the features of the present invention will be described with reference numerals. Note that the reference numerals are for reference, and the present invention is not limited to the embodiments.
本発明の第2の特徴に係るプレキャストコンクリート部材結合構造(5、10、10A、10B)は、相手部材(2、12)と、相手部材(2、12)と結合されるプレキャストコンクリート部材(1、11、11A、11B)とを有し、プレキャストコンクリート部材(1、11、11A、11B)は、相手部材(1、12)と対向するプレキャストコンクリート体(3、13、13A、13B)と、プレキャストコンクリート体(3、13、13A、13B)から相手部材(2、12)へ向けて突出すると共に相手部材(2、12)に対してプレキャストコンクリート体(3、13、13A、13B)の位置ずれを防止するずれ止め(4、14)を有し、前記ずれ止めは凸体からなり、前記凸体はプレキャストコンクリートからなり、前記相手部材(2、12)は、構造物(12)と、前記構造物(12)と前記プレキャストコンクリート体(13A、13B)との間に充填される結合材(M1)を有し、前記結合材(M1)はずれ止め(14)の周りに配置されることを特徴とする。 The precast concrete member coupling structure (5, 10, 10A, 10B) according to the second feature of the present invention includes a mating member (2, 12) and a precast concrete member (1) coupled to the mating member (2, 12). , 11, 11A, 11B), and the precast concrete member (1, 11, 11A, 11B) is a precast concrete body (3, 13, 13A, 13B) facing the counterpart member (1, 12), Projecting from the precast concrete body (3, 13, 13A, 13B) toward the mating member (2, 12) and the position of the precast concrete body (3, 13, 13A, 13B) with respect to the mating member (2, 12) deviation has a displacement preventing (4,14) for preventing the displacement preventing consists convex body, the Totsutai is Ri Do from precast concrete, before The mating member (2, 12) has a structure (12) and a binding material (M1) filled between the structure (12) and the precast concrete body (13A, 13B). disposed around the timber (M1) off stop (14), characterized in Rukoto.
相手部材は、構造物(12)と、構造物(12)とプレキャストコンクリート体(13A、13B)との間に充填される結合材(M1)を有し、結合材(M1)はずれ止め(14)の周りに配置される。 The mating member has a structure (12) and a bonding material (M1) filled between the structure (12) and the precast concrete body (13A, 13B), and the bonding material (M1) is prevented from slipping (14 ) Is placed around.
構造物(12)とプレキャストコンクリート体(13A、13B)との間に隙間(C1)を保持する保持具(16、19)を有する。 There are holders (16, 19) for holding the gap (C1) between the structure (12) and the precast concrete bodies (13A, 13B).
保持具(16)は、プレキャストコンクリート体(13A)の孔(13a)の中に固定された埋め込み部材(16a)と、埋め込み部材(16a)に固定されると共にプレキャストコンクリート体(13A)の孔(13a)から構造物(12)へ向けてずれ止め(14)を越えて延び、構造物(12)に突き当たる保持棒(16b)とを有する。
The retainer (16) is precast Conch rie preparative body and holes of (13A) fixed embedded member in (13a) (16a), embedded precast CONC rie preparative member is fixed to a member (16a) A holding rod (16b) that extends beyond the slip stopper (14) from the hole (13a) of (13A) toward the structure (12) and abuts against the structure (12).
保持具(19)は、プレキャストコンクリート体(13B)を支持すると共に構造物(12)へ向けてずれ止め(14)を越えて延び、構造物(12)に固定される支持部材(119a)を有する。 The holder (19) supports the precast concrete body (13B) and extends beyond the detent (14) toward the structure (12), and includes a support member (119a) fixed to the structure (12). Have.
前記相手部材は桁(12)を有し、前記プレキャストコンクリート部材は床版(11、11A、11B)を有する。 The counterpart member has a girder (12), and the precast concrete member has a floor slab (11, 11A, 11B).
本発明の特徴によれば、ずれ止めは、プレキャストコンクリート体と相手部材とのせん断応力に抵抗して相手部材に対するプレキャストコンクリート部材の位置ずれを阻止することができる。 According to the feature of the present invention, the slip stopper can resist the shearing stress between the precast concrete body and the mating member and prevent the precast concrete member from being displaced relative to the mating member.
ずれ止めを備えたプレキャストコンクリート部材は予め作製されるので、相手部材に対して容易に取り付けられ、簡易に位置ずれ阻止を達成し、施工性を向上させる。 Since the precast concrete member provided with the slip stopper is prepared in advance, it is easily attached to the mating member, easily prevents displacement and improves workability.
結合材は、コンクリート部材と相手部材とを結合するととともにずれ止めにアンカー機能を奏させることができる。 The binding material can combine the concrete member and the mating member, and can provide an anchoring function to prevent slippage.
保持具は、コンクリート部材と相手部材との間に隙間を確保するので、ずれ止めを隙間に配置させ、隙間に結合材を充填することができる。これにより、ずれ止めにアンカー機能を奏させることができる。 Since the holder secures a gap between the concrete member and the mating member, the stopper can be disposed in the gap and the gap can be filled with the binder. As a result, the anchor function can be exhibited in the stopper.
以下、図面を参照して実施の形態を詳細に説明する。 Hereinafter, embodiments will be described in detail with reference to the drawings.
第1の実施形態
図1に示すように、プレキャストコンクリート(以下、PCと称する)部材結合構造5はPC部材1と、PC部材1と結合される相手部材2を有する。
First Embodiment As shown in FIG. 1, a precast concrete (hereinafter referred to as PC) member coupling structure 5 includes a PC member 1 and a mating member 2 coupled to the PC member 1.
図2は、図1に示したPC部材1のみを示す斜視図である。図1、図2に示すように、相手部材と結合される前段階のPC部材1、及び、相手部材2と結合された後のPC部材結合構造5の何れも本発明である。 FIG. 2 is a perspective view showing only the PC member 1 shown in FIG. As shown in FIGS. 1 and 2, both the PC member 1 in the previous stage to be coupled with the mating member and the PC member coupling structure 5 after being coupled to the mating member 2 are the present invention.
図2に示すように、PC部材1は、相手部材2と結合されるPC体3と、PC体3の結合面3aから突出すると共に相手部材2の中に差し込まれる複数のずれ止め4−4群を有する。ここで、ずれ止め4−4は凸体からなり、この凸体は、例えば、鉄筋であり、また、PCで作製してもよい。また、ずれ止め4−4群同士は所定間隔で配置されている。ずれ止め4−4の形状は、円柱形に加えて、楕円柱形、三角柱、四角柱その他の多角柱形でもよい。ずれ止め4−4の先端部は、T形になるようにフランジを有してもよい。 As shown in FIG. 2, the PC member 1 includes a PC body 3 coupled with the mating member 2 and a plurality of stoppers 4-4 that protrude from the coupling surface 3 a of the PC body 3 and are inserted into the mating member 2. Have a group. Here, the shift stopper 4-4 is made of a convex body, and the convex body is, for example, a reinforcing bar, and may be made of PC. Further, the shift stoppers 4-4 are arranged at a predetermined interval. The shape of the stopper 4-4 may be an elliptical column shape, a triangular column shape, a quadrangular column shape, or other polygonal column shapes in addition to the cylindrical shape. The tip of the stopper 4-4 may have a flange so as to be T-shaped.
次に、PC部材1の作製方法を説明する。 Next, a method for producing the PC member 1 will be described.
図3に示すように型枠F1にコンクリートを流し込み、PC体3を作製する。PC体3に、所定の間隔でずれ止め4−4群を差し込む。PC体3を養生し、硬化させる。これにより、ずれ止め4−4はPC体3に固定される。別の方法として、PC体3が硬化する前に、PC体3の上にコンクリートを打ち継いでずれ止め4−4を作製してもよい。 As shown in FIG. 3, concrete is poured into the mold F <b> 1 to produce the PC body 3. The group 4-4 is inserted into the PC body 3 at a predetermined interval. The PC body 3 is cured and cured. Thereby, the slippage stopper 4-4 is fixed to the PC body 3. As another method, before the PC body 3 is cured, concrete may be cast on the PC body 3 to produce the shift stopper 4-4.
次に、図1を用いてPC部材1と相手部材2との結合方法を説明する。 Next, a method for connecting the PC member 1 and the mating member 2 will be described with reference to FIG.
相手部材2の上にPC部材1を載せる。このとき、ずれ止め4−4を相手部材2の中に差し込む。ずれ止め4はPC体3と相手部材2とのせん断応力に抵抗して相手部材2に対するPC部材1の位置ずれを阻止する。最後に、PC体3と相手部材2をボルト等の結合具によって固定する。 The PC member 1 is placed on the mating member 2. At this time, the stopper 4-4 is inserted into the mating member 2. The slip stopper 4 resists the shear stress between the PC body 3 and the mating member 2 and prevents the PC member 1 from being displaced relative to the mating member 2. Finally, the PC body 3 and the mating member 2 are fixed with a coupling tool such as a bolt.
以上の実施形態によれば、ずれ止め4は予めPC体3に形成されているので、現場でずれ止めを形成する必要がなく、PC部材1の位置ずれを簡易に阻止することができる。よって、施工性が向上する。 According to the above embodiment, since the slip stopper 4 is formed in the PC body 3 in advance, it is not necessary to form a slip stopper at the site, and the positional deviation of the PC member 1 can be easily prevented. Therefore, the workability is improved.
第2の実施形態
図4に示すように、PC部材結合構造としての合成桁10は、PC部材としての床版11と、床版11と結合された相手部材としての鋼桁12及びモルタルM1を有する。床版11は、構造物としての鋼桁12と向き合うPC体13と、PC体13から鋼桁12へ向けて延びるずれ止めとしてのずれ止め鉄筋14−14を有する。
2nd Embodiment As shown in FIG. 4, the synthetic | combination girder 10 as a PC member coupling | bonding structure has the floor slab 11 as a PC member, the steel girder 12 as a mating member couple | bonded with the floor slab 11, and the mortar M1. Have. The floor slab 11 has a PC body 13 that faces a steel girder 12 as a structure, and a locking rebar 14-14 as a locking that extends from the PC body 13 toward the steel girder 12.
ずれ止め鉄筋14−14はPC体13に差し込まれると共にPC体13からモルタルM1の中へ突出し、アンカー機能を奏する。 The anti-slip bar 14-14 is inserted into the PC body 13 and protrudes from the PC body 13 into the mortar M1 to perform an anchor function.
結合材としてのモルタルM1はずれ止め鉄筋14−14のそれぞれの周りに配置される。また、モルタルM1はPC体13と鋼桁12とを結合する。なお、モルタルM1の代わりに、結合材としてコンクリート等のセメント系固化材、又は、樹脂等の接着剤を用いてもよい。 A mortar M1 as a binding material is disposed around each of the retaining bars 14-14. In addition, the mortar M1 joins the PC body 13 and the steel beam 12 together. In place of the mortar M1, a cement-based solidifying material such as concrete or an adhesive such as a resin may be used as the binder.
以上の実施形態によれば、ずれ止め鉄筋14−14は鋼桁12とPC体13と間のせん断応力に抵抗するので、鋼桁12に対して床版11の位置ずれを阻止することができる。 According to the above embodiment, since the slip-off reinforcing bars 14-14 resist the shear stress between the steel beam 12 and the PC body 13, it is possible to prevent the displacement of the floor slab 11 with respect to the steel beam 12. .
床版11は鋼桁12に取り付ける前に作製されるので、鋼桁12に対して容易に取り付けられ、床版11の位置ずれを簡易に阻止することができる。 Since the floor slab 11 is produced before being attached to the steel girder 12, it can be easily attached to the steel girder 12 and the displacement of the floor slab 11 can be easily prevented.
第3の実施形態
図10(A)−(C)に示すように、鉄道橋は、橋脚に支持された合成桁10Aと、合成桁10Aの上に配置されたレールR1を有する。PC部材結合構造としての合成桁10Aは、PC部材としてのPC床版(以下、床版と称する)11Aと、床版11Aと結合された相手部材としての鋼桁12及びモルタルM1と、PC体13Aと鋼桁12と床版11Aとの間に隙間C1を保持する保持具16を有する。
Third Embodiment As shown in FIGS. 10A to 10C, the railway bridge includes a composite girder 10A supported by a bridge pier and a rail R1 disposed on the composite girder 10A. A composite girder 10A as a PC member coupling structure includes a PC floor slab (hereinafter referred to as a floor slab) 11A as a PC member, a steel girder 12 and a mortar M1 as mating members coupled to the floor slab 11A, and a PC body. A holding tool 16 that holds a gap C1 is provided between 13A, the steel beam 12, and the floor slab 11A.
図5に示すように、鋼桁12は、ウェブ12aとウェブ12aの上端に配置された上フランジ12bを有する。結合材としてのモルタルM1はPC体13Aと鋼桁12との間の隙間C1に充填され、PC体13Aと鋼桁12とを結合する。 As shown in FIG. 5, the steel girder 12 has a web 12a and an upper flange 12b arranged at the upper end of the web 12a. The mortar M1 as the binding material is filled in the gap C1 between the PC body 13A and the steel beam 12, and connects the PC body 13A and the steel beam 12.
床版11Aは、PC体13Aと、PC体13Aに固定されたずれ止めとしてのずれ止め鉄筋14−14を有する。 The floor slab 11A includes a PC body 13A and a detent bar 14-14 as a detent that is fixed to the PC body 13A.
PC体13Aは、保持具16を挿入するための貫通孔13aを有する。貫通孔13aは鋼桁12の上フランジ12bと一致するように位置決めされる。 The PC body 13 </ b> A has a through hole 13 a for inserting the holder 16. The through hole 13 a is positioned so as to coincide with the upper flange 12 b of the steel beam 12.
ずれ止め鉄筋14−14はPC体13Aの所定の箇所に差し込まれている。ずれ止め鉄筋14−14のそれぞれの周りにモルタルM1が配置される。ずれ止め鉄筋14−14はモルタルM1の中に延びてアンカー機能を奏する。 The non-slip bar 14-14 is inserted into a predetermined portion of the PC body 13A. A mortar M1 is disposed around each of the anti-slip bars 14-14. The anti-slip bar 14-14 extends into the mortar M1 and performs an anchor function.
本発明の保持具は、PC体13Aと鋼桁12との間に隙間C1を保持し、この隙間C1にずれ止め鉄筋14−14を配置させ、隙間C1にモルタルM1を充填させ、ずれ止め鉄筋14にアンカー機能を奏させるものである。本発明の保持具は、同作用を奏するものであれば、本実施形態の保持具16の他、例えば、スペーサ、ジャッキ、シリンダでもよい。 The holder of the present invention holds the gap C1 between the PC body 13A and the steel beam 12, and arranges the anti-slip bar 14-14 in the gap C1, fills the gap C1 with the mortar M1, and prevents the anti-slipping bar. 14 has an anchor function. The holder of the present invention may be, for example, a spacer, a jack, or a cylinder in addition to the holder 16 of the present embodiment as long as the same action is achieved.
保持具16は、PC体13Aの貫通孔13aに固定されると共にねじ孔を有する埋め込み金具16aと、ワッシャを介在して埋め込み金具16aのねじ孔にねじ込まれた保持棒としての保持ボルト16bを有する。保持ボルト16bはずれ止め鉄筋14−14の先端を越えて延びる。保持ボルト16bは鋼桁12の上フランジ12bに当接し、鋼桁12に対してPC体13Aを支持する。保持ボルト13bは鋼桁12とPC体13Aとの間に所定の隙間C1を設定する。なお、保持ボルト13bの代わりに棒状の部材を用いても良い。 The holder 16 has an embedded metal fitting 16a that is fixed to the through hole 13a of the PC body 13A and has a screw hole, and a holding bolt 16b as a holding rod screwed into the screw hole of the embedded metal fitting 16a with a washer interposed. . The holding bolt 16b extends beyond the tip of the locking bar 14-14. The holding bolt 16 b abuts on the upper flange 12 b of the steel beam 12 and supports the PC body 13 </ b> A with respect to the steel beam 12. The holding bolt 13b sets a predetermined gap C1 between the steel beam 12 and the PC body 13A. A rod-shaped member may be used instead of the holding bolt 13b.
次に、既設鉄道橋100の桁を合成桁に更新する方法を説明する。 Next, a method for updating the girder of the existing railway bridge 100 to the composite girder will be described.
図6(A)―(C)に示すように、既設の鉄道橋100は、橋脚に支持された鋼桁12と、鋼桁12の上に固定されたまくらぎ101と、まくらぎ101に設置されたレール102からなる。まくらぎ101とレール102は軌道を構成する。 As shown in FIGS. 6 (A)-(C), the existing railway bridge 100 is installed in a steel beam 12 supported by a pier, a sleeper 101 fixed on the steel beam 12, and a sleeper 101. The rail 102 is formed. The sleeper 101 and the rail 102 constitute a track.
図7(A)―(C)に示すように、鋼桁12からまくらぎ101及びレール102を撤去する。 As shown in FIGS. 7A to 7C, the sleeper 101 and the rail 102 are removed from the steel girder 12.
図8(A)―(C)に示すように、予め作製した床版11Aを用意する。PC体13Aの貫通孔13aに保持具16の埋め込み金具16aを固定し、保持ボルト16bを埋め込み金具16aのねじ孔に挿入しておく。これにより、鋼桁12に対する床版11Aの取り付けは容易になる。 As shown in FIGS. 8A to 8C, a floor slab 11A prepared in advance is prepared. The embedded bracket 16a of the holder 16 is fixed to the through hole 13a of the PC body 13A, and the holding bolt 16b is inserted into the screw hole of the embedded bracket 16a. Thereby, attachment of the floor slab 11A to the steel beam 12 is facilitated.
鋼桁12の上フランジ12bの上に床版11Aを設置する。この際、保持ボルト12bは上フランジ12bに当たり、PC体13Aと上フランジ12bとの間に隙間C1を保持する。この隙間C1にずれ止め鉄筋14−14は配置される。 The floor slab 11A is installed on the upper flange 12b of the steel girder 12. At this time, the holding bolt 12b hits the upper flange 12b and holds the gap C1 between the PC body 13A and the upper flange 12b. The slip prevention reinforcing bars 14-14 are arranged in the gap C1.
図9(A)―(C)に示すように、PC体13Aと上フランジ12bとの間にモルタルM1を充填する。これにより、ずれ止め鉄筋14−14の周りにモルタルM1が配置され、ずれ止め鉄筋14−14はアンカー機能を奏する。また、モルタルM1は鋼桁12とPC体13Aとを結合する。これにより、合成桁10Aが完成する。 As shown in FIGS. 9A to 9C, the mortar M1 is filled between the PC body 13A and the upper flange 12b. Thereby, the mortar M1 is arrange | positioned around the non-shifting reinforcing bar 14-14, and the locking bar 14-14 has an anchor function. Further, the mortar M1 joins the steel beam 12 and the PC body 13A. Thereby, the composite digit 10A is completed.
図10(A)−(C)に示すように、最後に、床版11Aの上にレールR1を固定する。 As shown in FIGS. 10A to 10C, finally, the rail R1 is fixed on the floor slab 11A.
次に、合成桁10Aの作用を説明する。 Next, the operation of the composite digit 10A will be described.
図10(A)に示すレールR1の上に鉄道車両が通過すると、床版11Aの長手方向、横方向に応力が加わる。これにより、図5において、床版11Aは鋼桁12に対して長手方向、横方向にずれ(変位)ようとする。このとき、各ずれ止め鉄筋14はモルタルM1を介して床版11Aと鋼桁12とのせん断応力に抵抗して床版11Aの位置ずれを阻止する。 When the railway vehicle passes over the rail R1 shown in FIG. 10A, stress is applied in the longitudinal direction and the lateral direction of the floor slab 11A. Accordingly, in FIG. 5, the floor slab 11 </ b> A tends to shift (displace) in the longitudinal direction and the lateral direction with respect to the steel beam 12. At this time, each misalignment reinforcing bar 14 resists the shear stress between the floor slab 11A and the steel girder 12 through the mortar M1 and prevents the position deviation of the floor slab 11A.
以上の実施形態によれば、ずれ止め鉄筋14−14を配置した床版11Aを予め作製するので、施工の手間を省略することができる。これにより、床版11Aの位置ずれを簡易に阻止することができる。 According to the above embodiment, since the floor slab 11A in which the slip-resisting reinforcing bars 14-14 are arranged is prepared in advance, it is possible to omit the labor of construction. Thereby, the position shift of the floor slab 11A can be easily prevented.
保持具16は床版11Aと鋼桁12との間に隙間C1を保持するので、ずれ止め鉄筋14−14をPC体13Aと鋼桁12との間の隙間C1に配置させ、隙間C1にモルタルM1が充填される。これにより、ずれ止め鉄筋14−14の周りにモルタルM1が配置され、ずれ止め鉄筋14−14はアンカー機能を奏することができる。 Since the retainer 16 holds the gap C1 between the floor slab 11A and the steel girder 12, the anti-slip bar 14-14 is disposed in the gap C1 between the PC body 13A and the steel girder 12, and the mortar is placed in the gap C1. M1 is filled. Thereby, the mortar M1 is arrange | positioned around the prevention | control rod 14-14, and the prevention rod 14-14 can show an anchor function.
第4の実施形態
図11に示すように、PC部材結合構造としての合成桁10Bは、第3の実施形態と同様の基本構造を有する。合成桁10Bは、互いに結合されるPC部材としての床版11B及び相手部材としての鋼桁12及びモルタルM1と、鋼桁12に床版11Bを固定する固定具18と、鋼桁12と床版11Bとの間に隙間C1を保持する保持具19を有する。
Fourth Embodiment As shown in FIG. 11, a composite beam 10B as a PC member coupling structure has a basic structure similar to that of the third embodiment. The composite girder 10B includes a floor slab 11B as a PC member and a steel girder 12 and a mortar M1 as mating members, a fixture 18 for fixing the floor slab 11B to the steel girder 12, a steel girder 12 and a floor slab. It has the holder 19 which hold | maintains the clearance gap C1 between 11B.
床版11Bは、鋼桁12と向き合うPC体13Bと、PC体13Bに差し込まれたずれ止め鉄筋14−14を有する。 The floor slab 11B has a PC body 13B facing the steel girder 12 and a slip-off reinforcing bar 14-14 inserted into the PC body 13B.
固定金具18は、鋼桁12のフランジ12bに係合すると共にフランジ12bの外側へ延び、PC体13Bに当接するL形の固定ブラケット18aを有する。固定金具14は、固定ブラケット18aを貫通すると共にPC体13Bの中にねじ込まれた固定ボルト18bを有する。 The fixing bracket 18 has an L-shaped fixing bracket 18a that engages with the flange 12b of the steel beam 12 and extends to the outside of the flange 12b and contacts the PC body 13B. The fixture 14 has a fixing bolt 18b that penetrates the fixing bracket 18a and is screwed into the PC body 13B.
保持具19は、PC体13Bと鋼桁12との間に隙間C1を保持する。保持具19は鋼桁12のウェブ12aにボルトで固定された支持部材19aを有する。支持部材19aはPC体13Bから鋼桁12へ向けてずれ止め鉄筋14−14を越えて延び、さらに、鋼桁12の上フランジ12bを横切ってウェブ12aに達する。また、支持部材19aは鋼桁12のウェブ12aの両側から斜め上方に延びて鋼桁12の上フランジ12bの上方に突出する(図12(B)参照)。支持部材19aは曲げられて鋼桁12の上フランジ12bと平行に延びる。支持部材19aはワッシャを介在してボルトB1でPC体13Bに固定される。保持具19は、支持部材19aの上下端で横方向に延びる上及び下フランジ19b、19cを有する。上フランジ19bはPC体13Bの底面に接する。ボルトB1は上フランジ19bを貫通して、PC体13Bの中にねじ込まれる。 The holder 19 holds a gap C1 between the PC body 13B and the steel beam 12. The holder 19 has a support member 19a fixed to the web 12a of the steel beam 12 with bolts. The support member 19 a extends from the PC body 13 </ b > B toward the steel girder 12 beyond the anti-slip bar 14-14, and further reaches the web 12 a across the upper flange 12 b of the steel girder 12. The support member 19a extends obliquely upward from both sides of the web 12a of the steel beam 12 and protrudes above the upper flange 12b of the steel beam 12 (see FIG. 12B). The support member 19a is bent and extends parallel to the upper flange 12b of the steel girder 12. The support member 19a is fixed to the PC body 13B with a bolt B1 with a washer interposed. The holder 19 has upper and lower flanges 19b and 19c extending in the lateral direction at the upper and lower ends of the support member 19a. The upper flange 19b is in contact with the bottom surface of the PC body 13B. The bolt B1 passes through the upper flange 19b and is screwed into the PC body 13B.
次に、既設鉄道橋100の更新方法を説明する。 Next, a method for updating the existing railway bridge 100 will be described.
図12(A)−(C)に示すように、既設鉄道橋100において、鋼桁12のフランジ12bの上であってまくらぎ101同士の間にモルタルM2を打設する。さらに、鋼桁12の長手方向に沿って所定の間隔で鋼桁12のウェブ12aの両側にボルトで保持具19の支持部材19aを固定する。 As shown in FIGS. 12A to 12C, in the existing railway bridge 100, a mortar M <b> 2 is placed between the sleepers 101 on the flange 12 b of the steel beam 12. Furthermore, the supporting member 19a of the holder 19 is fixed with bolts on both sides of the web 12a of the steel beam 12 at a predetermined interval along the longitudinal direction of the steel beam 12.
図13(A)−(C)に示すように、鋼桁12からまくらぎ101及びレール102を撤去する。 As shown in FIGS. 13A to 13C, the sleeper 101 and the rail 102 are removed from the steel beam 12.
図14(A)−(C)に示すように、予め作製した床版11Bを用意する。PC体13Bには、ボルト孔13b形成し、ずれ止め鉄筋14を配置しておく。これにより、鋼桁12に対する床版11Bの取り付けが容易になる。 As shown in FIGS. 14A to 14C, a floor slab 11B prepared in advance is prepared. Bolt holes 13b are formed in the PC body 13B, and the anti-slip bars 14 are arranged. Thereby, attachment of the floor slab 11B with respect to the steel beam 12 becomes easy.
鋼桁12の上に床版11Bを設置する。ここで、保持具19の支持部材19aの上フランジ19bの上に床版11Bを載せて、PC体13Bと鋼桁12との間に隙間C1を形成する。この隙間C1にずれ止め鉄筋14−14は位置決めされる。保持具19の上フランジ19bの孔及びPC体13Bのボルト孔13aにボルトB1をねじ込む。また、固定ブラケット18aを鋼桁12のフランジ12bの下に係合させ、PC体13Bの底面に当接させる。固定ボルト18bを固定ブラケット18aに貫通させ、PC体13Bの中にねじ込む。 The floor slab 11B is installed on the steel girder 12. Here, the floor slab 11B is placed on the upper flange 19b of the support member 19a of the holder 19, and a gap C1 is formed between the PC body 13B and the steel beam 12. The slip prevention reinforcing bars 14-14 are positioned in the gap C1. The bolt B1 is screwed into the hole of the upper flange 19b of the holder 19 and the bolt hole 13a of the PC body 13B. Further, the fixing bracket 18a is engaged under the flange 12b of the steel beam 12 and brought into contact with the bottom surface of the PC body 13B. The fixing bolt 18b is passed through the fixing bracket 18a and screwed into the PC body 13B.
図15(A)−(C)に示すように、鋼桁12のフランジ12bとPC体13Bとの間隙間にモルタルM1を充填する。モルタルM1はずれ止め鉄筋14−14の周りに配置され、ずれ止め鉄筋14−14はアンカー機能を奏する。モルタルM1は、硬化後、鋼桁12とPC体13Bとを結合する。これにより、合成桁10Bが完成する。 As shown in FIGS. 15A to 15C, the mortar M1 is filled in the gap between the flange 12b of the steel beam 12 and the PC body 13B. The mortar M1 is disposed around the locking bar 14-14, and the locking bar 14-14 performs an anchor function. The mortar M1 bonds the steel beam 12 and the PC body 13B after hardening. Thereby, the composite digit 10B is completed.
図16(A)−(C)に示すように、最後に、床版11Bの上に軌道としてのレールR1を設置する。レールR1はPC体13BにボルトB2で固定する。 As shown in FIGS. 16A to 16C, finally, a rail R1 as a track is installed on the floor slab 11B. The rail R1 is fixed to the PC body 13B with a bolt B2.
次に、合成桁10Bの作用を説明する。 Next, the operation of the composite digit 10B will be described.
図16(A)に示すレールR1の上に鉄道車両が通過すると、床版11Bの長手方向、横方向に応力が加わる。これにより、床版11Bは鋼桁12に対して長手方向、横方向に位置ずれ(変位)ようとする。このとき、図11に示すように、ずれ止め鉄筋14−14はPC体13Bと鋼桁12と間のせん断応力に抵抗して床版11Bの位置ずれを阻止する。 When the railway vehicle passes over the rail R1 shown in FIG. 16A, stress is applied in the longitudinal direction and the lateral direction of the floor slab 11B. Thereby, the floor slab 11B tends to be displaced (displaced) in the longitudinal direction and the lateral direction with respect to the steel beam 12. At this time, as shown in FIG. 11, the slip reinforcing bars 14-14 resist the shear stress between the PC body 13 </ b> B and the steel beam 12 and prevent the displacement of the floor slab 11 </ b> B.
以上の実施例によれば、保持具19は床版11Bと鋼桁12との間に隙間C1を確保するので、ずれ止め鉄筋14−14を隙間C1に配置させ、隙間C1にモルタルM1を充填することができる。これにより、ずれ止め鉄筋14−14の周りにモルタルM1が配置され、ずれ止め鉄筋14−14はアンカー機能を奏することができる。 According to the above embodiment, since the retainer 19 secures the gap C1 between the floor slab 11B and the steel girder 12, the retaining bars 14-14 are arranged in the gap C1, and the gap C1 is filled with the mortar M1. can do. Thereby, the mortar M1 is arrange | positioned around the prevention | control rod 14-14, and the prevention rod 14-14 can show an anchor function.
なお、本発明は本実施形態に限定されず、また、各実施形態は発明の趣旨を変更しない範囲で変更、修正可能である。 In addition, this invention is not limited to this embodiment, Moreover, each embodiment can be changed and corrected in the range which does not change the meaning of invention.
1 プレキャスト(PC)コンクリート部材
2 相手部材
3 プレキャストコンクリート体
4 ずれ止め
5 PC部材結合構造
10、10A、10B 合成桁
11、11A、11B プレキャストコンクリート床版
12 鋼桁
13、13A、13B プレキャストコンクリート体
14 ずれ止め鉄筋
16、19 保持具
M1 モルタル
DESCRIPTION OF SYMBOLS 1 Precast (PC) concrete member 2 Counterpart 3 Precast concrete body 4 Detachment 5 PC member coupling structure 10, 10A, 10B Composite girder 11, 11A, 11B Precast concrete floor slab 12 Steel girder 13, 13A, 13B Precast concrete body 14 Anti-slip bar 16, 19 Holder M1 mortar
Claims (5)
前記相手部材と結合されるプレキャストコンクリート部材とを有し、
前記プレキャストコンクリート部材は、
前記相手部材と対向するプレキャストコンクリート体と、
前記プレキャストコンクリート体から前記相手部材へ向けて突出すると共に前記相手部材に対して前記プレキャストコンクリート体の位置ずれを防止するずれ止めを有し、
前記ずれ止めは凸体からなり、
前記凸体はプレキャストコンクリートからなり、
前記相手部材は、構造物と、前記構造物と前記プレキャストコンクリート体との間に充填される結合材を有し、
前記結合材はずれ止めの周りに配置されることを特徴とする
プレキャストコンクリート部材結合構造。 A mating member;
A precast concrete member to be coupled with the mating member;
The precast concrete member is
A precast concrete body facing the counterpart member;
Protruding toward the mating member from the precast concrete body, and having a displacement stopper that prevents positional displacement of the precast concrete body with respect to the mating member,
The slip stopper is a convex body,
The Totsutai is Ri Do from precast concrete,
The mating member has a structure and a binder filled between the structure and the precast concrete body,
The precast concrete member coupling structure, wherein the coupling material is disposed around a stopper .
請求項1に記載のプレキャストコンクリート部材結合構造。 Having a holder for holding a gap between the structure and the precast concrete body,
The precast concrete member coupling structure according to claim 1 .
請求項2に記載のプレキャストコンクリート部材結合構造。 The holder is embedded in the hole of the precast concrete body, and is fixed to the embedded member and extends from the hole of the precast concrete body to the structure beyond the detent. A holding rod that strikes the structure;
The precast concrete member coupling structure according to claim 2 .
請求項2に記載のプレキャストコンクリート部材結合構造。 The holder includes a support member that supports the precast concrete body and extends toward the structure beyond the slip stopper and is fixed to the structure.
The precast concrete member coupling structure according to claim 2 .
前記プレキャストコンクリート部材は床版を有する、
請求項1に記載のプレキャストコンクリート部材結合構造。 The counterpart member has a girder,
The precast concrete member has a floor slab,
The precast concrete member coupling structure according to claim 1 .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2011069131A JP5852315B2 (en) | 2011-03-28 | 2011-03-28 | Precast concrete member connection structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2011069131A JP5852315B2 (en) | 2011-03-28 | 2011-03-28 | Precast concrete member connection structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2012202150A JP2012202150A (en) | 2012-10-22 |
JP5852315B2 true JP5852315B2 (en) | 2016-02-03 |
Family
ID=47183435
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2011069131A Expired - Fee Related JP5852315B2 (en) | 2011-03-28 | 2011-03-28 | Precast concrete member connection structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5852315B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP7221105B2 (en) * | 2019-03-27 | 2023-02-13 | 首都高速道路株式会社 | Joint structure and floor slab joint method |
Family Cites Families (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5033330B1 (en) * | 1969-08-20 | 1975-10-29 | ||
US4972537A (en) * | 1989-06-05 | 1990-11-27 | Slaw Sr Robert A | Orthogonally composite prefabricated structural slabs |
JP2872346B2 (en) * | 1990-05-18 | 1999-03-17 | 横河工事株式会社 | Prefab slab installation method |
JPH04306303A (en) * | 1991-01-29 | 1992-10-29 | Harumoto Tekkosho:Kk | Jointing structure |
JPH0522611U (en) * | 1991-08-30 | 1993-03-23 | 石川島播磨重工業株式会社 | Joint structure of precast floor slab and girder |
JP2830703B2 (en) * | 1993-08-12 | 1998-12-02 | 鹿島建設株式会社 | Buried concrete formwork and concrete structures |
JPH0952211A (en) * | 1995-08-14 | 1997-02-25 | Taisei Corp | Pca panel and manufacture thereof |
JP4116951B2 (en) * | 2003-08-05 | 2008-07-09 | 積水化学工業株式会社 | Sleeper tree and sleeper tree fixing structure |
JP4568656B2 (en) * | 2005-08-05 | 2010-10-27 | ショーボンド建設株式会社 | Steel synthetic concrete precast slab |
-
2011
- 2011-03-28 JP JP2011069131A patent/JP5852315B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2012202150A (en) | 2012-10-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2009041227A (en) | Structure and method for joining precast floor slabs together | |
JP2007239301A (en) | Method of integrating precast concrete members interposed by filling concrete | |
KR101170922B1 (en) | The rahmen bridge construction technique for which tendon and the connection support stand was used | |
JP5367297B2 (en) | Bridge with precast cross girder and precast girder and its construction method | |
JP4823937B2 (en) | Fall bridge prevention structure | |
JP2023085814A (en) | Installation structure of floor slab and installation method of floor slab | |
KR101086646B1 (en) | Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method thereof, and built-up type slab bridge construction method using the same | |
KR101037478B1 (en) | Partially embedded composite slab | |
JP5852315B2 (en) | Precast concrete member connection structure | |
JP2008248648A (en) | Concrete structure and joining method of concrete structure | |
JP5575032B2 (en) | Synthetic girder floor slab detent structure and floor slab detent method | |
KR20140125754A (en) | Bridge construction method for forming continuous point part of pier using copping for connecting girder | |
JP6308502B2 (en) | Construction method of pre-tension slab in overhang construction | |
KR20100123405A (en) | Structure for filling-up a steel reinforced concrete on h shaped section steel in slab bridge | |
KR102486675B1 (en) | Precast concrete slab construction method and bridge fabricated by usinr the same | |
JP4086863B2 (en) | Continuous girder structure in double span girder bridge | |
JP5439016B2 (en) | Buried formwork | |
JP4969116B2 (en) | Connected structure of concrete girder | |
KR20100137749A (en) | Precast concrete girder unified with slab | |
JP7372506B2 (en) | Concrete slab and concrete slab connection structure | |
JP2019183481A (en) | Joining structure of composite floor slabs | |
KR102086267B1 (en) | Precasted Inverted T Concerete Girder and Method for making thereof | |
JP2006214219A (en) | Pc rail tie doubling as crossbeam and construction method using it | |
JP2010281040A (en) | Steel concrete composite floor slab, panel for constructing the steel concrete composite floor slab, and construction method for steel concrete composite floor slab | |
JP5112369B2 (en) | Bolt-type slip prevention method used for composite structuring of existing steel railway bridge and concrete slab. |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20130621 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20140127 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20140805 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20140930 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20150407 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20150604 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20150617 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20151117 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20151204 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5852315 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |