KR102486675B1 - Precast concrete slab construction method and bridge fabricated by usinr the same - Google Patents

Precast concrete slab construction method and bridge fabricated by usinr the same Download PDF

Info

Publication number
KR102486675B1
KR102486675B1 KR1020220042145A KR20220042145A KR102486675B1 KR 102486675 B1 KR102486675 B1 KR 102486675B1 KR 1020220042145 A KR1020220042145 A KR 1020220042145A KR 20220042145 A KR20220042145 A KR 20220042145A KR 102486675 B1 KR102486675 B1 KR 102486675B1
Authority
KR
South Korea
Prior art keywords
slab
nut
insertion groove
flange
buried
Prior art date
Application number
KR1020220042145A
Other languages
Korean (ko)
Inventor
유영은
김경민
Original Assignee
주식회사 지케이기술
(주)효명피씨
김경민
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 지케이기술, (주)효명피씨, 김경민 filed Critical 주식회사 지케이기술
Priority to KR1020220042145A priority Critical patent/KR102486675B1/en
Application granted granted Critical
Publication of KR102486675B1 publication Critical patent/KR102486675B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/06Arrangement, construction or bridging of expansion joints
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed

Abstract

The present invention relates to a PC slab construction method and a bridge manufactured using the same. According to the present invention, the PC slab can be assembled and installed more stably and quickly on an upper surface of a bridge girder mounted on a bridge substructure, and height adjustment and lateral gradient of the PC slab can be more efficiently adjusted. The PC slab construction method of the present invention includes the steps of mounting both adjacently installed PC slabs on a bridge girder; and installing longitudinal bottom plate fasteners set so that upper and lower through-holes communicate with each other.

Description

PC 슬래브 시공방법 및 이를 이용하여 제작된 교량{PRECAST CONCRETE SLAB CONSTRUCTION METHOD AND BRIDGE FABRICATED BY USINR THE SAME}PC slab construction method and bridge made using it {PRECAST CONCRETE SLAB CONSTRUCTION METHOD AND BRIDGE FABRICATED BY USINR THE SAME}

본 발명은 PC 슬래브 시공방법에 관한 것이다. 교량하부구조에 거치된 교량용 거더 상면에 PC 슬래브를 보다 안정적으로 신속하게 조립 설치함과 더불어, PC 슬래브의 높이조절 및 횡방향 구배를 보다 효율적으로 조절할 수 있는 PC 슬래브 시공방법 및 이를 이용하여 제작된 교량에 관한 것이다.The present invention relates to a PC slab construction method. A PC slab construction method that can more stably and quickly assemble and install a PC slab on the upper surface of a bridge girder mounted on a bridge substructure, as well as more efficiently adjust the height and lateral gradient of the PC slab, and manufacturing using the same It's about bridges.

도 1a는 종래 강교량의 조립예시도를 도시한 것이다.Figure 1a shows an exemplary assembly of a conventional steel bridge.

즉, 강교량의 거더(21)와 바닥판(22)은 모두 강재로 제작한 것임을 알 수 있고, That is, it can be seen that both the girder 21 and the bottom plate 22 of the steel bridge are made of steel,

이에 강재 거더(21)의 종방향 연결부위를 살펴보면 연결볼트(25)와 덧댐판(24)을 이용하여 서로 체결하고 있음을 알 수 있으며, 강 바닥판(22)도 연결볼트(25)와 연결플랜지를 이용하여 서로 체결하고 있음을 알 수 있다.Therefore, looking at the longitudinal connection of the steel girder 21, it can be seen that they are fastened to each other using the connecting bolt 25 and the padding plate 24, and the steel bottom plate 22 is also connected to the connecting bolt 25 It can be seen that the flanges are fastened to each other.

이에 연결볼트(25), 강재로 제작된 덧댐판(24)은 강재로 제작된 거더(21)와 바닥판(22)을 서로 연결 시키는 데에는 효율적이지만, 프리캐스트 콘크리트 바닥판에는 그대로 사용하기에는 체결력 확보 및 시공성확보가 용이하지 않다는 한계가 있게 된다.Accordingly, the connection bolt 25 and the backing plate 24 made of steel are effective in connecting the girder 21 and the bottom plate 22 made of steel to each other, but securing fastening force to use as it is in the precast concrete floor plate And there is a limit that securing constructability is not easy.

도 1b는 종래 프리캐스트 콘크리트 바닥판(10)의 수평연결예시도를 도시한 것이다.Figure 1b shows an exemplary horizontal connection of a conventional precast concrete floor plate (10).

강재거더(21)나 강바닥판(22)이 아닌 프리캐스트 콘크리트 바닥판(11)은 연결볼트, 덧댐판과 같은 체결구를 통상 사용하지 앓고,The precast concrete deck 11, other than the steel girder 21 or the steel deck 22, does not normally use fasteners such as connecting bolts and padding,

U형 수평연결재(16)를 일측 프리캐스트 콘크리트 바닥판(11) 연결면에 형성된 일측수용홈(15)에 수용시키고, The U-shaped horizontal connector 16 is accommodated in the one-side receiving groove 15 formed on the connection surface of the precast concrete floor plate 11 on one side,

와이어를 이용하여 타측 프리캐스트 콘크리트 바닥판(11)의 타측연결홈(15)으로 이동되어 삽입되는 과정에서 In the process of being moved and inserted into the other connection groove 15 of the other precast concrete floor plate 11 using a wire

상기 U형 수평연결재(16)가 프리캐스트 콘크리트 바닥판의 연결면(D) 사이를 경유하도록 하고 일측연결홈(15)과 타측연결홈(15)을 충전재로 충전시켜 일체화시키면서, 연결면(D)은 전단키와 전담홈에 의한 기계적 연결수단(14)을 이용하여 연결시키고 있음을 알 수 있다.While the U-shaped horizontal connector 16 passes between the connecting surfaces D of the precast concrete floor plate and fills and integrates one side connecting groove 15 and the other connecting groove 15 with a filler, the connecting surface D It can be seen that ) is connected using a mechanical connecting means 14 by a shear key and a dedicated groove.

하지만 상기 U형 수평연결재(16)는 인접한 프리캐스트 콘크리트 바닥판의 연결면(D)에 걸쳐지도록 하는 정도로 설치되는 봉부재로서 설치되기 때문에 충전재룰 이용하더라도 프리캐스트 콘크리트 바닥판의 종방향 연결성능을 크게 기대할 정도는 아니라는 한계가 있게 되고, 시공성과 작업성 다소 떨어지는 문제가 있었다.However, since the U-shaped horizontal connector 16 is installed as a rod member installed to the extent of spanning the connection surface D of the adjacent precast concrete floor plate, the longitudinal connection performance of the precast concrete floor plate is improved even when a filler is used. There is a limit that is not expected to be high, and there is a problem with somewhat poor workability and workability.

도 1c는 종래 프리캐스트 콘크리트 거더(31)와 프리캐스트 콘크리트 바닥판(32)의 상,하 연결예시도를 도시한 것이다.Figure 1c shows an example of the upper and lower connection between the conventional precast concrete girder 31 and the precast concrete floor plate 32.

즉, 교각, 교대와 같은 교량하부구조에 프리캐스트 콘크리트 거더(31)를 거치시킨 이후에 프리캐스트 콘크리프 바닥판(32)을 프리캐스트 콘크리트 거더 상면에 얹어지도록 설치하고, 상기 프리캐스트 콘크리트 거더(31)와 프리캐스트 콘크리트 바닥판(32)을 서로 결속시키기 위해서,That is, after placing the precast concrete girder 31 on a bridge substructure such as a pier or abutment, the precast concrete floor plate 32 is installed so as to be placed on the upper surface of the precast concrete girder, and the precast concrete girder ( In order to bind 31) and the precast concrete floor plate 32 to each other,

미리 프리캐스트 콘크리트 거더(31) 상면에는 전단하우징(33)과 하부전단연결재(34)를 미리 세팅시키고, 프리캐스트 콘크리트 바닥판(32)의 전단포켓(35)에 전단하우징(33)을 별도 해체하여 전단홈(36)이 노출되도록 한 후,The shear housing 33 and the lower shear connector 34 are set in advance on the upper surface of the precast concrete girder 31, and the shear housing 33 is separately dismantled in the shear pocket 35 of the precast concrete floor plate 32. After the shear groove 36 is exposed,

상부전단연결재(37)를 전단홈(36)에 형성되어 있는 하부전단연결재(34)와 체결너트에 의하여 추가로 설치되도록 하고, The upper shear connector 37 is additionally installed by the lower shear connector 34 formed in the shear groove 36 and the fastening nut,

전단홈(36)과 전단포켓(35)을 충전재(38)로 마감하는 방식으로 프리캐스트 콘크리트 거더(31) 상면에 프리캐스트 콘크리트 바닥판(32)이 서로 강결되도록 하고 있음을 알 수 있다. It can be seen that the shear groove 36 and the shear pocket 35 are closed with the filler 38 so that the precast concrete floor plate 32 on the upper surface of the precast concrete girder 31 is rigidly connected to each other.

하지만, 전단하우징(33)을 미리 설치하고, 해체하는 작업은 작업성이 떨어지는 문제점이 있을 수밖에 없었다.However, the work of installing and disassembling the shear housing 33 inevitably has a problem of poor workability.

도 1d는 종래 교량용 거더(42)와 바닥판(42)을 서로 힌지연결구조로 연결시키는 시공예시도를 도시한 것이다.1D shows a construction example of connecting a conventional bridge girder 42 and a floor plate 42 with a hinge connection structure.

즉, 교량용 거더(41) 상면에 오목홈(43)이 형성된 하부블록(44)을 세팅하고, 상기 오목홈(43)에 접하는 볼록부(45)가 형성된 상부블록(46)을 상,하로 접하도록 하여 회전이 구속되지 않도록 하는 방식으로 교량용 거더(41)와 바닥판(42)을 서로 상,하 힌지 연결되도록 함을 알 수 있다.That is, the lower block 44 having the concave groove 43 formed on the upper surface of the bridge girder 41 is set, and the upper block 46 having the convex part 45 formed in contact with the concave groove 43 is moved up and down. It can be seen that the bridge girder 41 and the floor plate 42 are hinged up and down to each other in such a way that rotation is not constrained by contacting each other.

이에 바닥판(42)으로 전달되는 휨 모멘트가 교량용 거더(41)에는 전달되지 않도록 할 수 있다는 장점은 있으나 하부블록(44), 상부블록(46)과 같은 힌지연결구조를 별도로 설치해야 한다는 점에서 용도가 제한적일 수 밖에 없음을 알 수 있다.This has the advantage of preventing the bending moment transmitted to the floor plate 42 from being transmitted to the bridge girder 41, but the lower block 44 and the upper block 46. Hinge connection structures such as the need to be installed separately It can be seen that the use is bound to be limited.

대한민국 공개특허 제10-2008-0093261호(발명의 명칭: 초간편시공이 가능한 강합성 교량 시공방법, 공개일자: 2008년10월21일)Republic of Korea Patent Publication No. 10-2008-0093261 (Title of Invention: Method for constructing a steel composite bridge capable of ultra-simple construction, Publication date: October 21, 2008) 대한민국 특허 제10-2073169호(발명의 명칭:U형 다웰바를 이용한 포장용 프리캐스트 슬래브 시공방법, 공개일자: 2020년02월04일)Korean Patent No. 10-2073169 (Title of Invention: Precast Slab Construction Method for Paving Using U-Shaped Dowel Bar, Publication Date: February 4, 2020) 대한민국 특허 제 10-2144400호(발명의 명칭: 프리캐스트 슬래브용 PSC거더 및 이를 이용한 교량시공방법, 공개일자: 2020년08월13일)Republic of Korea Patent No. 10-2144400 (title of invention: PSC girder for precast slab and bridge construction method using the same, publication date: August 13, 2020) 대한민국 특허 제 10-0538832호(발명의 명칭: 레일링 시스템을 이용한 프리캐스트 바닥판과 거더의설치구조, 공개일자: 2005년05월27일)Korean Patent No. 10-0538832 (Title of Invention: Installation Structure of Precast Floor Plate and Girder Using Railing System, Publication Date: May 27, 2005)

이에 본 발명은 PC 슬래브를 현장에서 간단하게 체결볼트와 덧댐판과 같은 종방향 바닥판 체결구로 안정적으로 조립 시공할 수 있으며, 교량용 거더와 PC 슬래브를 전단포켓을 이용하여 전단연결장치로 간단하게 강결시킬 수 있어 신속한 교량시공이 가능한 PC 슬래브 시공방법 및 이를 이용하여 제작된 교량 제공을 해결하고자 하는 기술적 과제로 한다.Therefore, the present invention can stably assemble and construct PC slabs in the field with fastening bolts and longitudinal floor plate fasteners such as backing plates, and simply connects bridge girders and PC slabs with shear connectors using shear pockets. It is a technical task to solve the PC slab construction method that can be rigidly constructed, enabling rapid bridge construction, and the provision of a bridge manufactured using the PC slab construction method.

또한, 본 발명은 PC 슬래브를 간단하게 높이조절 하면서, 횡방향 구배도 안정적으로 세팅할 수 있는 PC 슬래브 시공방법 및 이를 이용하여 제작된 교량 제공을 해결하고자 하는 기술적 과제로 한다.In addition, the present invention is a technical problem to solve the PC slab construction method that can stably set the lateral gradient while simply adjusting the height of the PC slab and the provision of a bridge manufactured using the same.

상기 과제를 달성하기 위해서, 본 발명의 PC 슬래브 시공방법은,In order to achieve the above object, the PC slab construction method of the present invention,

(a) 몸통부의 연결단부면(B) 주위의 상면에 상부수용홈이 형성되고, 상기 연결단부면(B)의 중간에 중간삽입홈이 형성되어 연결단부면(B)에서 상부수용홈과 중간삽입홈이 서로 수평으로 접하여 연통되도록 인접 설치되는 양 PC 슬래브를 교량용 거더에 거치하는 단계; 및 (b) 상기 양 PC 슬래브의 상부수용홈 및 중간삽입홈에 상부덧댐판 및 중간덧댐판이 삽입되어 상,하로 관통홀이 연통되도록 세팅되는 종방향 바닥판체결구를 설치하는 단계;를 포함하여, 상기 상부덧댐판과 중간덧댐판은 서로 인접한 PC 슬래브의 연결단부면(B)에서 상,하로 연통된 관통홀을 통해 체결볼트가 체결되도록 하여 PC 슬래브를 종방향으로 연결하면서 설치되도록 하며, 상기 (b)단계의 중간덧댐판(132)은 일측 PC 슬래브(120)의 중간삽입홈(124)에 삽입시켜 놓은 상태에서, 연결되는 타측 PC 슬래브(120)의 중간삽입홈(124)쪽으로 이동시켜 중간덧댐판(132)의 개략 중간부분이 연결단부면(B)을 경유하도록 세팅하여, 중간덧댐판(132)은 일측 PC 슬래브(120)의 중간삽입홈(124)에 완전히 삽입된 상태가 되어 타측 PC슬래브(120)가 일측 PC 슬래브(120)로 인접하는 과정에서 방해 요인이 되지 않도록 하게 된다.(a) An upper receiving groove is formed on the upper surface around the connecting end face (B) of the body, and an intermediate insertion groove is formed in the middle of the connecting end face (B), so that the upper receiving groove and the intermediate portion are formed on the connecting end face (B). Mounting both PC slabs installed adjacent to each other on a bridge girder so that the insertion grooves are in horizontal contact with each other and communicate; And (b) installing a longitudinal bottom plate fastener set so that the upper and lower through-holes are in communication with each other by inserting the upper and middle backing plates into the upper receiving groove and the middle insertion groove of the two PC slabs; including , The upper and middle pads are installed while connecting the PC slabs in the longitudinal direction by fastening fastening bolts through through-holes communicating up and down at the connection end surface (B) of the PC slabs adjacent to each other, the In the state where the intermediate padding plate 132 in step (b) is inserted into the intermediate insertion groove 124 of the PC slab 120 on one side, it is moved toward the intermediate insertion groove 124 of the PC slab 120 on the other side to be connected. By setting the approximate middle portion of the middle pad 132 to pass through the connection end surface B, the middle pad 132 is completely inserted into the middle insertion groove 124 of the PC slab 120 on one side The other side PC slab 120 is prevented from being an obstacle in the process of adjoining the one side PC slab 120.

또한, 상기 과제를 달성하기 위해서, 본 발명의 PC 슬래브 시공방법은,In addition, in order to achieve the above object, the PC slab construction method of the present invention,

(a) 시공된 교량하부구조에 교량용 거더를 거치하되, 전단연결장치(A)인 하우징을 교량용 거더의 상부플랜지 상면에 노출되도록 형성시키는 단계; (b) 거치된 교량용 거더 상면에 노출된 하우징과 PC 슬래브의 전단포켓이 서로 연통되도록 설치되는 것으로서, 몸통부의 연결단부면(B) 주위의 상면에 상부수용홈이 형성되고, 상기 연결단부면(B)의 중간에 중간삽입홈이 형성되어 연결단부면(B)에서 상부수용홈과 중간삽입홈이 서로 수평으로 접하여 연통되도록 인접 설치되는 PC 슬래브를 초기 세팅하는 단계; (c) 전단포켓과 하우징이 서로 연통되도록 거치된 PC 슬래브의 높이와 횡방향구배를 바닥판 높이조절장치와 횡방향구배용 새들을 이용하여 조절하는 단계; (d) 종방향 바닥판체결구를 이용하여 PC 슬래브를 종방향으로 연결시키는 단계; 및 (e) 전단포켓을 통해 하우징에 전단연결재를 고정 설치하고, 전단포켓에 무수축모를타르를 포함하는 충전재를 충전시켜 교량용 거더와 PC 슬래브를 서로 강결시키는 단계;를 포함하며, 상기 (d) 단계의 종방향 바닥판체결구는 PC 슬래브들의 상부수용홈 및 중간삽입홈에 상부덧댐판 및 중간덧댐판이 삽입되어 상,하로 관통홀이 연통되도록 세팅되어 상기 상부덧댐판과 중간덧댐판은 서로 인접한 PC 슬래브의 연결단부면(B)에서 상,하로 연통된 관통홀을 통해 체결볼트가 체결되도록 하여 PC 슬래브를 종방향으로 연결하면서 설치되도록 하며, 상기 중간덧댐판은 일측 PC 슬래브의 중간삽입홈에 삽입시켜 놓은 상태에서, 연결되는 타측 PC 슬래브의 중간삽입홈쪽으로 이동시켜 중간덧댐판의 개략 중간부분이 연결단부면(B)을 경유하도록 세팅하여, 중간덧댐판은 일측 PC 슬래브의 중간삽입홈에 완전히 삽입된 상태가 되어 타측 PC슬래브가 일측 PC 슬래브로 인접하는 과정에서 방해 요인이 되지 않도록 하게 된다.(a) mounting a bridge girder on the constructed bridge substructure, but forming a housing, which is a shear connection device (A), to be exposed on the upper surface of the upper flange of the bridge girder; (b) It is installed so that the housing exposed on the upper surface of the mounted bridge girder and the shear pocket of the PC slab communicate with each other, and an upper receiving groove is formed on the upper surface around the connection end surface (B) of the body, and the connection end surface (B) an intermediate insertion groove is formed in the middle of the connection end surface (B), the upper receiving groove and the intermediate insertion groove are in contact with each other horizontally and initially setting the adjacent PC slab to communicate; (c) adjusting the height and lateral gradient of the PC slab mounted so that the shear pocket and the housing communicate with each other using a floor plate height adjusting device and saddles for lateral gradient; (d) connecting the PC slabs in the longitudinal direction using longitudinal floor fasteners; And (e) fixing the shear connector to the housing through the shear pocket, and filling the shear pocket with a filler containing non-shrinkable mortar to stiffen the bridge girder and the PC slab to each other; ) step, the upper and middle pads are inserted into the upper receiving groove and the middle insertion groove of the PC slabs, and the through-holes are set so that the upper and lower through-holes are in communication, so that the upper and middle pads are adjacent to each other. The PC slab is installed while connecting the PC slab in the longitudinal direction by fastening the fastening bolt through the through-hole communicating up and down on the connection end surface (B) of the PC slab, and the intermediate pad is installed in the middle insertion groove of the PC slab on one side In the state of being inserted, it is moved toward the middle insertion groove of the PC slab on the other side to be connected, and the approximate middle portion of the intermediate pad is set to pass through the connection end surface (B), so that the intermediate pad is inserted into the middle insertion groove of the PC slab on one side. It is completely inserted so that the other side PC slab does not become an obstacle in the process of adjoining one side PC slab.

본 발명에 의하면, 교량용 거더와 PC 슬래브를 상,하 및 종방향으로 전단포켓과 전단연결장치(A)로 간단하게 강결시킬 수 있으며, PC 슬래브를 교축방향(종방향)으로 체결볼트와 덧댐판과 같은 종방향 바닥판 체결구로 안정적으로 신속하게 연결 시공할 수 있는 PC 슬래브 시공방법 및 이를 이용하여 제작된 교량 제공이 가능하게 된다.According to the present invention, the bridge girder and the PC slab can be simply rigidized with the shear pocket and the shear connecting device (A) in the upper, lower and longitudinal directions, and the PC slab is attached with fastening bolts in the axial direction (longitudinal direction) It is possible to provide a PC slab construction method that can be stably and quickly connected with a longitudinal floor plate fastener such as a plate and a bridge manufactured using the same.

또한, 본 발명에 의하면 PC 슬래브의 높이조절과 횡방향구배를 바닥판 높이조절장치와 바닥판용 새들을 이용하여 간단하게 세팅할 수 있기때문에, 보다 신속하고 경제적으로 PC 슬래브에 의한 교량시공이 가능한 PC 슬래브 시공방법 및 이를 이용하여 제작된 교량 제공이 가능하게 된다.In addition, according to the present invention, since the height adjustment and the lateral gradient of the PC slab can be simply set using the floor plate height adjusting device and the floor plate saddle, PC capable of constructing bridges with PC slabs more quickly and economically It is possible to provide a slab construction method and a bridge manufactured using the slab construction method.

도 1a는 종래 강교량의 조립예시도
도 1b는 종래 PC 슬래브의 수평연결예시도
도 1c는 종래 프리캐스트 콘크리트 거더와 프리캐스트 바닥판의 상,하 연결예시도
도 1d는 종래 교량용 거더와 바닥판을 서로 힌지연결구조로 연결시키는 시공예시도
도 2는 본 발명의 PC 슬래브 시공방법을 이용하여 제작된 교량의 예시도,
도 3a는 본 발명의 PC 슬래브와 교량용 거더의 시공예시도,
도 3b 및 도 3c는 본 발명의 PC 슬래브의 시공예시도,
도 3d는 본 발명의 PC 슬래브의 높이조절 시공예시도,
도 3e는 본 발명의 PC 슬래브의 횡방향구배 시공예시도,
도 4는 본 발명의 PC 슬래브 시공방법의 순서도를 도시한 것이다.
Figure 1a is an assembly example of a conventional steel bridge
Figure 1b is an example of horizontal connection of a conventional PC slab
Figure 1c is an example of upper and lower connection between a conventional precast concrete girder and a precast floor plate
1d is a construction example of connecting a conventional bridge girder and a floor plate with a hinge connection structure
2 is an exemplary view of a bridge manufactured using the PC slab construction method of the present invention;
3a is a construction example of a PC slab and a girder for a bridge of the present invention;
3b and 3c are construction examples of the PC slab of the present invention;
Figure 3d is an example of height adjustment construction of the PC slab of the present invention,
Figure 3e is an example of the transverse gradient construction of the PC slab of the present invention,
Figure 4 shows a flow chart of the PC slab construction method of the present invention.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.Hereinafter, embodiments of the present invention will be described in detail so that those skilled in the art can easily practice with reference to the accompanying drawings. However, the present invention may be embodied in many different forms and is not limited to the embodiments described herein. And in order to clearly explain the present invention in the drawings, parts irrelevant to the description are omitted, and similar reference numerals are attached to similar parts throughout the specification.

명세서 전체에서, 어떤 부분이 어떤 구성요소를 "포함"한다고 할 때, 이는 특별히 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것을 의미한다.Throughout the specification, when a certain component is said to "include", it means that it may further include other components without excluding other components unless otherwise stated.

[ 본 발명의 PC 슬래브 시공방법을 이용하여 제작된 교량(100) ][Bridge 100 manufactured using the PC slab construction method of the present invention]

도 2는 본 발명의 PC 슬래브 시공방법을 이용하여 제작된 교량(100, 이하 간단하게 본 발명의 교량이라고 지칭할 수 있다.)의 예시도, 도 3a는 본 발명의 PC 슬래브(120)와 교량용 거더(110)의 연결예시도, 도 3b 및 도 3c는 본 발명의 PC 슬래브(120)의 시공예시도, 도 3d는 본 발명의 PC 슬래브(120)의 높이조절 시공예시도, 도 3e는 본 발명의 PC 슬래브(120)의 횡방향구배 시공예시도를 도시한 것이다.Figure 2 is an exemplary view of a bridge (100, which can be simply referred to as the bridge of the present invention hereinafter) manufactured using the PC slab construction method of the present invention, Figure 3a is a PC slab 120 and a bridge of the present invention 3b and 3c are examples of construction of the PC slab 120 of the present invention, FIG. 3d is an example of height adjustment of the PC slab 120 of the present invention, and FIG. It shows an example of the transverse gradient construction of the PC slab 120 of the present invention.

먼저 상기 본 발명의 교량(100)은 도 2를 참조하면, 교각, 교대와 같은 교량하부구조(200)에 교량용 거더(110) 다수를 횡방향으로 다수 이격시켜 거치하고, 교량용 거더(110) 상면에서 높이조절과 횡방향구배가 세팅된 PC 슬래브(120, 프리캐스트 콘크리트 슬래브)를 종방향으로 조립 연결시키게 된다.First, referring to FIG. 2, in the bridge 100 of the present invention, a plurality of bridge girders 110 are spaced apart in the transverse direction on a bridge substructure 200 such as piers and abutments, and the bridge girder 110 ) PC slab (120, precast concrete slab) with height adjustment and lateral gradient set on the upper surface is assembled and connected in the longitudinal direction.

공장등에서 미리 제작된 PC 슬래브(120)를 체결볼트, 덧댐판과 같은 종방향 바닥판체결구(130)를 그대로 사용하더라도 연결 성능과 작업성을 충분히 확보할 수 있고, Even if the PC slab 120 pre-manufactured in a factory is used as it is, the longitudinal bottom plate fasteners 130 such as fastening bolts and backing plates can be sufficiently secured for connection performance and workability,

PC 슬래브(120)의 높이조절은 바닥판 높이조절장치(140)에 의하여 이루지도록 하게 되며, 횡방향구배 조절은 횡방향구배용 새들(150)을 이용하여 간단하게 작업자가 작업할 수 있도록 하게 된다.The height adjustment of the PC slab 120 is made by the floor plate height adjusting device 140, and the lateral gradient adjustment is made simple by using the saddle 150 for horizontal gradient so that the operator can work .

이에 상기 본 발명의 PC 슬래브 시공방법을 이용하여 제작된 교량(100)는 도 2와 같이 교량하부구조(200)에 시공되는 전단연결장치(A)가 구비된 교량용 거더(110), PC 슬래브(120), 종방향 바닥판체결구(130), 바닥판 높이조절장치(140), 횡방향구배용 새들(150)을 포함하도록 하게 된다.Therefore, the bridge 100 manufactured using the PC slab construction method of the present invention is a bridge girder 110 equipped with a shear connection device (A) installed on the bridge lower structure 200 as shown in FIG. 2, PC slab (120), a longitudinal bottom plate fastener 130, a bottom plate height adjusting device 140, and a saddle 150 for lateral gradient.

이에 먼저 상기 교량하부구조(200)는 도 2와 같이, 현장에 교각, 교대로 시공되는 것으로서 일정한 높이로 시공되며 상면에 교량용 거더(110)를 횡방향으로 다수가 이격 되도록 하되, First, as shown in FIG. 2, the bridge substructure 200 is constructed at a constant height as piers and alternately constructed at the site, and a plurality of bridge girders 110 are spaced apart in the transverse direction on the upper surface,

종방향(교축방향)으로 거치한 후, PC 슬래브(120)를 교량용 거더(110) 상면에 높이와 횡방향구배를 바닥판 높이조절장치(140)와 횡방향구배용 새들(150)을 이용하게 세팅하고, 종방향으로 조립, 연결시키게 된다.After mounting in the longitudinal direction (bridge axis direction), the height and lateral gradient of the PC slab 120 on the upper surface of the bridge girder 110 are adjusted using the floor plate height adjusting device 140 and the saddle 150 for lateral gradient It is set up, assembled, and connected in the longitudinal direction.

다음으로 상기 전단연결장치(A)가 구비된 교량용 거더(110)는 도 2와 같이, 교량하부구조(200) 상면에 횡방향으로 다수가 이격되도록 하되 종방향을 거치되는 것으로서 본 발명은 PSC 거더를 기준으로 살펴본다.Next, as shown in FIG. 2, the bridge girder 110 equipped with the shear connecting device (A) is spaced apart in the transverse direction on the upper surface of the bridge lower structure 200, but is mounted in the longitudinal direction, and the present invention PSC Let's look at the girder as a standard.

상기 교량용 거더(110)는 공장등에서 미리 제작하게 되는데 통상 I형 단면으로 상부플랜지(111), 복부 및 하부플랜지로 형성된 철근콘크리트 거더로서 PC강연선등을 이용하여 프리스트레스가 도입된 것을 이용하게 된다.The bridge girder 110 is pre-manufactured in a factory or the like. It is usually a reinforced concrete girder formed of an upper flange 111, an abdomen and a lower flange in an I-shaped cross section, and prestress is introduced using PC steel strands. It is used.

이러한 교량용 거더(110)는 상면에 PC 슬래브(120)이 얹어지면서 강결시켜 일체로 거동하도록 시공하게 되는데, 이러한 강결을 위해서 도 2와 같이 상부플랜지 상면에 전단연결장치(A)를 미리 형성시키게 된다.The bridge girder 110 is constructed so that it behaves integrally by being rigidized while the PC slab 120 is placed on the upper surface. For this rigidity, as shown in FIG. do.

이러한 전단연결장치(A)는 교량용 거더(110)와 PC 슬래브(120)의 전단포켓(121)을 이용하여 상,하로 강결시키기 위한 것이다.This shear connection device (A) is for rigidity up and down using the shear pocket 121 of the bridge girder 110 and the PC slab 120.

이에 상기 전단연결장치(A)는 도 2 및 도 3a를 기준으로 살펴보면 하우징(112), 스터드(113), 전단연결재(114)를 포함하게 된다.Accordingly, the shear connecting device (A) includes a housing 112, a stud 113, and a shear connecting member 114 based on FIGS. 2 and 3A.

먼저 하우징(112)은 도 3a와 같이, 교량용 거더(110)의 상부플랜지(111) 상면에 상부가 노출되도록 매립된 형강부재를 이용하게 되며 상부플랜지(111)의 연장방향(종방향)으로 연속하여 형성시킨 것이다.First, as shown in FIG. 3A, the housing 112 uses a steel member embedded so that the upper portion is exposed on the upper surface of the upper flange 111 of the bridge girder 110, and extends in the extension direction (longitudinal direction) of the upper flange 111. formed successively.

이와 같이, 종방향으로 하우징(112)이 연속되도록 형성시키게 되면, 시공오차가 발생하더라도 PC 슬래브(120)의 전단포켓(121)을 통해 전단연결재(114)를 하우징(112)에 용이하게 설치할 수 있다는 장점이 있게 된다.In this way, when the housing 112 is formed continuously in the longitudinal direction, even if a construction error occurs, the shear connector 114 can be easily installed in the housing 112 through the shear pocket 121 of the PC slab 120. There is an advantage to being there.

이러한 하우징(112)은 ㄷ자 형강을 미리 교량용 거더(110) 제작 시, 상부플랜지에 매립되도록 하여 세팅하여 내부가 노출되어 하우징(112)의 내부공간을 통해 전단연결재(114)가 전단포켓(121)을 통해 삽입 체결?? 수 있도록 하게 된다.When the bridge girder 110 is manufactured in advance, the housing 112 is set so that it is embedded in the upper flange, and the inside is exposed, and the shear connector 114 passes through the inner space of the housing 112 to the shear pocket 121 ) through insert tightening?? will make it possible

이와 같은 하우징(112)을 이용하게 되면, 형강부재를 그대로 사용할 수 있다는 장점이 있게 되고, When such a housing 112 is used, there is an advantage that the section steel member can be used as it is,

교량용 거더(110) 상부로 노출되는 전단연결재(114)를 미리 설치하지 않기 때문에 시공간섭이 발생하지 않게 되며, Since the shear connector 114 exposed to the upper part of the bridge girder 110 is not installed in advance, space-time interference does not occur,

PC 슬래브(120)를 대차를 이용하여 이동시킬 때 레일역할도 할 수 있어 매우 효율적이게 된다.When moving the PC slab 120 using a bogie, it can also act as a rail, making it very efficient.

다음으로 상기 스터드(113)는 도 3a와 같이, 하우징(112)의 저면으로부터 하방으로 연장되어 하우징(112)이 교량용 거더(110)의 상부플랜지(111)에 고정 설치되도록 하는 역할을 하게 된다. Next, as shown in FIG. 3A, the stud 113 extends downward from the bottom surface of the housing 112 so that the housing 112 is fixed to the upper flange 111 of the bridge girder 110. It serves to be installed .

다음으로 상기 전단연결재(114)는 도 3a와 같이, PC 슬래브(120)에 형성된 전단포켓(121)을 통해 하우징(112) 저면에 용접등의 방법으로 고정되도록 하되 전단포켓(121) 내부로 연장되도록 설치한 것이다.Next, as shown in FIG. 3A, the shear connector 114 is fixed to the bottom of the housing 112 by welding or the like through the shear pocket 121 formed in the PC slab 120, but extends into the shear pocket 121. installed as much as possible.

이에 전단연결재(114)가 전단포켓(121)과 하우징(112)에 설치된 상태에서 전단포켓(121)에 무수축모르타르와 같은 충전재(148)를 충전시켜 교량용 거더(110)와 PC 슬래브(120)를 서로 상,하로 강결시킬 수 있게 된다.Accordingly, with the shear connector 114 installed in the shear pocket 121 and the housing 112, the shear pocket 121 is filled with a filler 148 such as non-shrinkage mortar to form the bridge girder 110 and the PC slab 120. ) can be forced up and down each other.

다음으로 상기 PC 슬래브(120)는 도 2 및 도 3b와 같이 교량용 거더(110) 상면에 종방향(교축방향)으로 조립 연결해가면서 시공되는 교량용 바닥판이다.Next, the PC slab 120 is a bridge floor plate constructed by assembling and connecting the upper surface of the bridge girder 110 in the longitudinal direction (bridge axis direction) as shown in FIGS. 2 and 3B.

이러한 PC 슬래브(120)는 미리 공장등에서 제작되어, 현장에 운반 및 인양을 위해서 일정한 두께와 단면적을 가진 수평판 형태로 제작한 것을 이용하게 되는데, This PC slab 120 is manufactured in advance in a factory, etc., and is used in the form of a horizontal plate having a constant thickness and cross-sectional area for transportation and lifting to the site.

도 3b를 참조하면 PC 슬래브(120)는 횡방향으로 4개의 교량용 거더(110) 상면에 2개의 PC 슬래브(120)가 종방향으로 연결되도록 하고 있음을 알 수 있으나 크기 및 설치개수는 달리 제한이 없다.Referring to FIG. 3B, it can be seen that the PC slab 120 is connected in the longitudinal direction to the upper surface of the four bridge girders 110 in the transverse direction, but the size and number of installations are otherwise limited there is no

이러한 PC 슬래브(120)는 직사각형 수평판 형태의 몸통부(122)에 교량용 거더(110)와의 강결을 위해 전단포켓(121) 다수가 상면과 하면을 관통하도록 형성되어 있으며, 종방향 연결을 위한 연결단부면(B)에서 종방향 바닥판체결구(130)에 의하여 종방향으로 연결되도록 하게 된다.In this PC slab 120, a number of shear pockets 121 are formed to penetrate the upper and lower surfaces of the rectangular horizontal plate-shaped body 122 for rigidity with the bridge girder 110, and for longitudinal connection It is to be connected in the longitudinal direction by the longitudinal bottom plate fastener 130 at the connection end surface (B).

이에 도 3b를 참조하면, 상기 전단포켓(121)에 의하여 교량용 거더(110)의 전단연결장치(A)를 구성하는 하우징(112)이 노출되게 되므로, 전단연결재(114)를 전단포켓(121)을 통해 하우징(112)에 고정시킬 수 있게 된다.3B, since the housing 112 constituting the shear connecting device A of the bridge girder 110 is exposed by the shear pocket 121, the shear connector 114 is replaced with the shear pocket 121. ) through which it can be fixed to the housing 112.

또한, 도 3b를 참조하면, 종방향 연결을 위한 연결단부면(B)에 종방향 바닥판체결구(130)를 설치할 수 있도록 몸통부(122)의 연결단부면(B) 주위 상면에 상부수용홈(123)이 사각 홈 형태로 형성되어 있고, In addition, referring to FIG. 3B, the upper portion is accommodated on the upper surface around the connection end surface (B) of the body portion 122 so that the longitudinal bottom plate fastener 130 can be installed on the connection end surface (B) for longitudinal connection. The groove 123 is formed in the form of a square groove,

상부수용홈(123)은 인접한 PC 슬래브(120)의 상면에도 동일하게 마주 보도록 형성시켜 상부수용홈(123)이 서로 수평으로 연통되도록 하고 있음을 알 수 있고, 상기 연결단부면(B)의 개략 중간에 중간삽입홈(124)이 형성되어 있음을 알 수 있다.It can be seen that the upper receiving groove 123 is formed to face the same on the upper surface of the adjacent PC slab 120 so that the upper receiving groove 123 is in horizontal communication with each other, and the outline of the connection end surface (B) It can be seen that the intermediate insertion groove 124 is formed in the middle.

이에, 도 3b와 같이, 서로 연통된 상부수용홈(123)에는 종방향 바닥판체결구(130)의 상부덧댐판(131)이 삽입되도록 하여 배치되고,Accordingly, as shown in FIG. 3B, the upper padding plate 131 of the longitudinal bottom plate fastener 130 is inserted into the upper receiving groove 123 communicating with each other, and

상기 중간삽입홈(124)에는 종방향 바닥판체결구(130)의 중간덧댐판(132)이 삽입되도록 하게 되며,The intermediate padding plate 132 of the longitudinal bottom plate fastener 130 is inserted into the intermediate insertion groove 124,

상기 상부덧댐판(131)과 중간덧댐판(132)은 서로 인접한 PC 슬래브(120)의 연결단부면(B)에서 상하로 연통된 관통홀(131a,132a)을 통해 체결볼트(133)에 의하여 체결되도록 함으로서 교량용 거더(110)에서 PC 슬래브(120)를 종방향으로 연결시킬 수 있게 된다.The upper padding plate 131 and the middle padding board 132 are connected by a fastening bolt 133 through through-holes 131a and 132a communicating vertically at the connection end surface B of the PC slab 120 adjacent to each other. By fastening, it is possible to connect the PC slab 120 in the bridge girder 110 in the longitudinal direction.

즉, PC 슬래브(120)를 종방향 바닥판체결구(130)를 이용할 경우 간단하게 종방향으로 순차적으로 연결시공 할 수 있게 되며, 이는 미 도시 하였으나 횡방향으로도 동일하게 적용 가능하다.That is, when using the PC slab 120 in the longitudinal direction floor plate fastener 130, it is possible to simply connect and sequentially connect in the longitudinal direction, which is not shown, but is equally applicable in the transverse direction.

다음으로 종방향 바닥판체결구(130)는 도 3b 및 도 3c와 같이, 교량용 거더(110)와 PC 슬래브(120)를 종방향 연결시키기 위한 체결구이다.Next, the longitudinal floor plate fastener 130 is a fastener for longitudinally connecting the bridge girder 110 and the PC slab 120 as shown in FIGS. 3B and 3C.

이러한 종방향 바닥판체결구(130)는 도 3b 및 도 3c와 같이, 상부덧댐판(131), 중간덧댐판(132), 체결볼트(133)를 포함하게 된다.The longitudinal bottom plate fastener 130 includes an upper padding plate 131, a middle padding plate 132, and a fastening bolt 133, as shown in FIGS. 3B and 3C.

먼저 상기 상부덧댐판(131)은 도 3b 및 도 3c를 참조하면, 사각판 형태로서 체결볼트(133)가 관통할 수 있도록 관통홀(131a)이 다수 형성시키게 된다.First, referring to FIGS. 3B and 3C , the upper backing plate 131 has a rectangular plate shape and has a plurality of through holes 131a through which fastening bolts 133 can pass through.

이를 위해 상기 상부덧댐판(131)은 PC 슬래브(120)의 인접한 양 PC 슬래브(120)의 연통된 상부수용홈(123)에 딱 맞게 삽입 설치되도록 하여 위치 조절이 이루어질 수 있도록 하게 되며,To this end, the upper pad 131 is inserted and installed to fit into the upper receiving groove 123 of the PC slab 120 connected to the adjacent PC slab 120, so that the position can be adjusted.

상부덧댐판(131)에 체결볼트(133)를 관통 체결하는 것으로 양 PC 슬래브(120)이 조립 연결되도록 하게 된다.By fastening through and fastening the fastening bolt 133 to the upper back plate 131, both PC slabs 120 are assembled and connected.

상기 중간덧댐판(132)은 도 3b를 참조하면, 상부덧댐판(131)만 사용하게 되면 조립 연결 성능이 일부 저하될 수 있으므로 상기 양 PC 슬래브(120)의 연결단부면(B) 중간에 양 중간삽입홈(124)에 삽입되도록 하고, 상부덧댐판(131)에 관통 체결된 체결볼트(133)가 역시 관통되도록 하여 조립 연결 성능을 추가로 확보할 수 있도록 한 것이다. Referring to FIG. 3B, the middle pad 132 is in the middle of the connection end surface (B) of the two PC slabs 120 because the assembly connection performance may be partially deteriorated when only the upper pad 131 is used. It is inserted into the intermediate insertion groove 124, and the fastening bolt 133 fastened through the upper back plate 131 is also penetrated so that the assembly connection performance can be additionally secured.

이에 역시 사각판 형태로서 체결볼트(133)가 관통할 수 있도록 관통홀(132a)이 다수 형성되어 있으며, 이에 상부덧댐판(131)과 중간덧댐판(132)의 관통홀(131a,132a)은 상,하 연통되도록 세팅시키게 된다.Accordingly, a plurality of through-holes 132a are formed in the form of a square plate so that the fastening bolt 133 can pass therethrough. It is set to be in communication with the upper and lower parts.

이에 본 발명의 상부덧댐판(131), 중간덧댐판(132)은 동일한 크기로 제작된 것을 이용 함으로서 제작도 용이하고 설치 및 해체도 간단하게 진행이 가능하게 된다.Accordingly, the upper padding board 131 and the middle padding board 132 of the present invention are manufactured in the same size, so that they are easy to manufacture and can be easily installed and dismantled.

이때 상부덧댐판(131)은 PC 슬래브(120)의 상면에서 수평으로 연통된 상부수용홈(123)에 삽입시켜 설치할 수 있으나, At this time, the upper padding plate 131 can be installed by inserting it into the upper receiving groove 123 communicating horizontally on the upper surface of the PC slab 120,

중간덧댐판(132)은 일측 PC 슬래브(120)의 중간삽입홈(124)에 삽입시켜 놓은 상태에서, 연결되는 타측 PC 슬래브(120)의 중간삽입홈(124)쪽으로 이동시켜 중간덧댐판(132)의 개략 중간부분이 연결단부면(B)을 경유하도록 세팅시키게 된다.In the state where the intermediate padding plate 132 is inserted into the intermediate insertion groove 124 of the PC slab 120 on one side, it is moved toward the intermediate insertion groove 124 of the PC slab 120 on the other side to be connected to the intermediate padding plate 132 ) is set to pass through the connection end surface (B).

도 3c는 상기 중간덧댐판(132)을 일측 PC 슬래브(120)의 중간삽입홈(124)에 삽입시켜 놓은 상태에서, 연결되는 타측 PC 슬래브(120)의 중간삽입홈(124)쪽으로 이동시키는 방법을 도시하고 있다.3c is a method of moving the intermediate pad 132 toward the intermediate insertion groove 124 of the PC slab 120 on the other side to be connected in a state where it is inserted into the intermediate insertion groove 124 of the PC slab 120 on one side is showing

이러한 방법은 일측 PC 슬래브(120)의 중간삽입홈(124)에 삽입된 중간덧댐판(132)에 이동공구(134)를 연결하고, 이동공구(134)를 작업자가 PC 슬래브(120) 상면쪽에서 잡아당겨 타측 PC 슬래브(120)의 중간삽입홈(124)쪽으로 중간덧댐판(132)이 이동 삽입되도록 하는 방식이라 할 수 있다.In this method, the moving tool 134 is connected to the intermediate padding plate 132 inserted into the intermediate insertion groove 124 of the PC slab 120 on one side, and the moving tool 134 is moved by the operator from the upper surface of the PC slab 120. It can be said to be a method in which the intermediate padding plate 132 is moved and inserted toward the intermediate insertion groove 124 of the other side PC slab 120 by pulling.

이에 도 3c에 의하면 서로 수평으로 인접한 일측 및 타측 PC 슬래브(120)에는 각각 상부수용홈(123)과 중간삽입홈(124)이 서로 상,하 연통될 수 있도록 형성되어 있음을 알 수 있고, Accordingly, according to FIG. 3C, it can be seen that the upper receiving groove 123 and the intermediate insertion groove 124 are formed in upper and lower communication with each other in the PC slabs 120 on one side and the other side horizontally adjacent to each other, respectively,

연결단부면(B) 주위는 상부수용홈(123)과 중간삽입홈(124)에 의한 단면 손실이 발생하므로 수평 U형 보강철근(135)이 상부수용홈(123)과 중간삽입홈(124) 사이에 배근되어 있음을 알 수 있다.Around the connection end surface (B), cross-section loss occurs due to the upper receiving groove 123 and the intermediate insertion groove 124, so the horizontal U-shaped reinforcing bar 135 is the upper receiving groove 123 and the intermediate insertion groove 124 It can be seen that there is a distribution in between.

이때 수평 U형 보강철근(135)의 반원형 절곡부에 삽입홀(136)이 형성되어 삽입홀(136)에 삽입된 삽입볼트(미도시)에 의하여 수평 U형 보강철근(135)은 삽입볼트에 의하여 반원형 절곡부위가 지지, 고정되도록 하고 있음을 알 수 있다.At this time, an insertion hole 136 is formed in the semicircular bent portion of the horizontal U-shaped reinforcing bar 135, and the horizontal U-shaped reinforcing bar 135 is inserted into the insertion bolt by an insertion bolt (not shown) inserted into the insertion hole 136. As a result, it can be seen that the semicircular bent portion is supported and fixed.

이러한 삽입볼트는 중간덧댐판(132)이 일측 PC 슬래브(120)의 중간삽입홈(124)에 임시로 고정 세팅하기 위한 용도로도 사용하게 된다.These insertion bolts are also used for temporarily fixing the intermediate padding plate 132 to the intermediate insertion groove 124 of the PC slab 120 on one side.

이에 중간덧댐판(132)은 일측 PC 슬래브(120)의 중간삽입홈(124)에 완전히 삽입된 상태가 되어 타측 PC슬래브(120)가 일측 PC 슬래브(120)로 인접하는 과정에서 방해 요인이 되지 않도록 하게 된다.Accordingly, the intermediate pad 132 is completely inserted into the intermediate insertion groove 124 of the PC slab 120 on one side, so that the PC slab 120 on the other side is not a disturbing factor in the process of adjoining the PC slab 120 on one side. make sure not to

이에 일측 PC 슬래브(120)의 중간삽입홈(124)에 완전히 삽입된 상태 중간덧댐판(132)을 이동공구(134)를 이용하여 작업자가 PC 슬래브(120) 상면쪽에서 잡아당켜 타측 PC 슬래브(120)의 중간삽입홈(124)쪽으로 중간덧댐판(132)이 이동 삽입되도록 하게 되는데,Accordingly, the intermediate padding plate 132 in a state completely inserted into the intermediate insertion groove 124 of the PC slab 120 on one side is pulled from the upper surface of the PC slab 120 by the operator using the moving tool 134 to remove the PC slab 120 on the other side. ) The middle padding plate 132 is moved and inserted toward the middle insertion groove 124 of the

이를 이해 중간덧댐판(132)은 도 3c를 참조하면, 수평판 형태로서 다수의 관통홀(132a)이 형성되어, 관통홀(132a)에 체결볼트(133)가 삽입되어 체결되도록 하게 되며, 체결볼트(133)가 삽입될 때, 제작 및 시공오차를 감안하여 상기 관통홀(132a)은 타원형의 슬롯형태로 형성시키는 것이 바람직하다.Understanding this, referring to FIG. 3C, the intermediate pad 132 has a plurality of through holes 132a formed in the form of a horizontal plate, so that the fastening bolts 133 are inserted into the through holes 132a to be fastened, fastening When the bolt 133 is inserted, it is preferable to form the through hole 132a in an elliptical slot shape in consideration of manufacturing and construction errors.

또한 중간덧댐판(132)의 수평 이동을 위한 이동공구(134)를 설치하기 위해 일측단의 측면에 고정홀이 형성되어 있고, 고정홀에 ㄹ자 형태의 봉부재의 일측이 고정되어 ㄹ자 형태의 봉부재의 타측에 형성된 손잡이를 이용하여,In addition, in order to install the moving tool 134 for horizontal movement of the intermediate pad 132, a fixing hole is formed on the side of one side end, and one side of the L-shaped rod member is fixed to the fixing hole to obtain a L-shaped rod Using the handle formed on the other side of the member,

일측 PC 슬래브(120)의 중간삽입홈(124)에 완전히 삽입된 상태 중간덧댐판(132)을 수평 이동시킬 수 있게 된다.It is possible to horizontally move the intermediate padding plate 132 in a state completely inserted into the intermediate insertion groove 124 of the PC slab 120 on one side.

즉, 상기 손잡이는 PC 슬래브(120)의 상면쪽으로 인출되도록 하여 손잡이를 잡아당기게 되면 중간덧댐판(132)은 수평 이동하여 타측 PC 슬래브(120)의 중간삽입홈(124)에 삽입될 수 있게 된다.That is, when the handle is pulled out toward the upper surface of the PC slab 120, the middle pad 132 moves horizontally and is inserted into the middle insertion groove 124 of the other PC slab 120. .

이와 같은 중간덧댐판(132)의 원할한 수평 이동을 위하여 도 3c를 참조하면, 중간덧댐판(132)의 양 측단은 중간삽입홈(124)과 접하는 부분에 커팅된 테이퍼링부가 형성되도록 하여 걸림현상이 발생하지 않도록 하게 된다.Referring to FIG. 3C for smooth horizontal movement of the intermediate pad 132, both side ends of the intermediate pad 132 are cut at the portion in contact with the intermediate insertion groove 124 so that a tapering portion is formed to form a jamming phenomenon to prevent this from happening.

이로서 도 3c를 참조하면, 서로 인접한 일측 및 타측 PC 슬래브(120)의 중간삽입홈(124)에 중간덧댐판(132)이 연결단부면(B)를 경유하도록 한 이후에는 상부덧댐판(131)을 상부수용홈(123)에 삽입하여 역시 서로 인접한 일측 및 타측 PC 슬래브(120)의 연결단부면(B)을 상부덧댐판(131)이 경유하도록 세팅시키게 된다.As such, referring to FIG. 3C, after the intermediate padding plate 132 passes through the connecting end surface (B) in the intermediate insertion groove 124 of one side and the other PC slab 120 adjacent to each other, the upper padding board 131 By inserting into the upper receiving groove 123, the connection end surface (B) of one side and the other side PC slab 120 adjacent to each other is set so that the upper padding plate 131 passes through.

이에 상부덧댐판(131)에 형성시킨 관통홀(131a), 중간덧댐판(132)에 형성시킨 관통홀(132a)를 관통하도록 체결볼트(133)를 체결시키게 된다.Accordingly, fastening bolts 133 are fastened to pass through the through-holes 131a formed in the upper padding plate 131 and the through-holes 132a formed in the middle padding plate 132.

이러한 체결볼트(133)의 하단은 중간덧댐판(132)에 형성시킨 관통홀(132a) 내부에 체결되도록 하여 볼트머리부는 상부덧댐판(131) 상면에 접하면서 조여지도록 하여 연결성능을 충분히 확보할 수 있게 된다.The lower end of the fastening bolt 133 is fastened to the inside of the through hole 132a formed in the middle pad 132 so that the bolt head is tightened while in contact with the upper surface of the upper pad 131 to ensure sufficient connection performance be able to

이에 도 3c에 의하면 무수축모르타르를 포함하는 충전재(148)가 상부수용홈(123), 삽입홀(136), 중간삽입홈(124), 연결단부면(B)이 충전되도록 하여 마감시키고 있음을 알 수 있으며, 충전재가 누출되지 않도록 서로 인접한 일측 및 타측 PC 슬래브(120)의 연결단부면(B)의 하부에는 실링재를 더 설치할 수 있다.Accordingly, according to FIG. 3C, the filler 148 containing non-shrinkage mortar fills the upper receiving groove 123, the insertion hole 136, the middle insertion groove 124, and the connection end surface B. As can be seen, a sealing material may be further installed in the lower portion of the connection end surfaces B of the PC slabs 120 on one side and the other side adjacent to each other so that the filler does not leak.

이러한 충전재(148)의 충전은 PC 슬래브(120)의 상면쪽에서 압입될 수 있도록 중간삽입홈(124)과 연통된 충전홀을 PC 슬래브(120)의 상면에 추가로 형성시키는 것이 바람직하다.It is preferable to additionally form a filling hole communicating with the intermediate insertion groove 124 on the upper surface of the PC slab 120 so that the filling of the filler 148 can be press-fitted from the upper surface of the PC slab 120.

상기 체결볼트(133)는 도 3b를 참조하면, 상부덧댐판(131), 중간덧댐판(132)에 형성된 관통홀(131a,132a)을 상,하로 관통하여 중간덧댐판(132) 내부에 관입 체결된다.Referring to FIG. 3B , the fastening bolts 133 penetrate through holes 131a and 132a formed in the upper and middle backing plates 131 and 132 vertically and downward to penetrate the inside of the middle backing plate 132. is concluded

이러한 체결볼트(133)를 이용함으로서 보다 신속한 PC 슬래브(120)의 종방향 연결이 가능하게 된다.By using these fastening bolts 133, more rapid longitudinal connection of the PC slab 120 is possible.

다음으로 상기 바닥판 높이조절장치(140)는 도 2 및 도 3d와 같이, 인양 후 교량용 거더(110)의 상면에 설치된 PC 슬래브(120)의 설치 높이를 조절하기 위한 것이다.Next, the floor plate height adjusting device 140 is for adjusting the installation height of the PC slab 120 installed on the upper surface of the bridge girder 110 after lifting, as shown in FIGS. 2 and 3D.

이는 PC 슬래브(120)를 미리 제작하여 교량용 거더(110) 상면에 인양하여 세팅후 종방향 연결 및 횡방향 구배를 조절해야 하기 때문에 필요하다. This is necessary because the PC slab 120 must be manufactured in advance and lifted to the upper surface of the bridge girder 110 to adjust the longitudinal connection and lateral gradient after setting.

즉, 다수의 PC 슬래브(120)의 상면에 서로 단차가 형성되지 않도록 하기 위해서 필요한 것이라 할 수 있다.That is, it can be said that it is necessary to prevent a step difference from being formed on the upper surface of the plurality of PC slabs 120.

도 3d를 참조하면, 상기 바닥판 높이조절장치(140)는 분리형 매립너트 방식으로 설치된다.Referring to FIG. 3D, the floor plate height adjusting device 140 is installed in the form of a separable landfill nut.

이러한 분리형 매립너트 방식으로 도 3d를 참조하면, 2개가 예시(TYPE 1, TYPE 2)되어 있으며, PC 슬래브(120) 제작 시 내부에 미리 세팅하여 매립되도록 설치하게 되며 하부 매립너트(142)를 채택하여 높이조절볼트(147)를 제거할 수 있도록 한 것이라 할 수 있다.Referring to FIG. 3D as such a separable buried nut method, two are exemplified (TYPE 1 and TYPE 2), and when the PC slab 120 is manufactured, it is installed in advance to be buried, and the lower buried nut 142 is adopted It can be said that the height adjustment bolt 147 can be removed.

이에 첫 번째 분리형 매립너트(TYPE 1)는 도 3d와 같이, 수직원통형의 매립너트인 상부 매립너트(141)와 하부 매립너트(142)가 서로 연통되며, 상,하로 분리 가능하도록 형성된 것이다.Accordingly, the first separable buried nut (TYPE 1) is formed such that the upper buried nut 141 and the lower buried nut 142, which are vertically cylindrical embedded nuts, communicate with each other and can be separated vertically, as shown in FIG. 3D.

상부 매립너트(141)는 수직 원통부재로서 내측면에 나사부가 형성되어 있고 하단에는 수평판 형태의 인양하중 저항용 플랜지(144)가 일체로 형성되고, The upper buried nut 141 is a vertical cylindrical member with a threaded portion formed on the inner surface and a horizontal plate-shaped lifting load resistance flange 144 integrally formed at the lower end,

하부 매립너트(142)는 상부 매립너트(141) 하부에 분리 가능하도록 연결된 수직 원통부재로서 하부매립 플랜지(145)가 하부에 형성된 것으로서, 하부매립 플랜지(145)는 PC 슬래브(120) 내부로부터 저면에 노출되도록 초기 세팅된다.The lower buried nut 142 is a vertical cylindrical member detachably connected to the lower part of the upper buried nut 141, and a lower buried flange 145 is formed at the lower part. It is initially set to be exposed to

이에 상부 매립너트(141)와 하부 매립너트(142)가 매립된 PC 슬래브(120)를 교량용 거더(110) 상면에 스페이서와 인양볼트를 이용하여 초기 세팅시키게 되며, Accordingly, the PC slab 120 in which the upper buried nut 141 and the lower buried nut 142 are embedded is initially set on the upper surface of the bridge girder 110 using a spacer and a lifting bolt,

인양하중에 대하여 상기 상부 매립너트(141)의 인양하중 저항용 플랜지(144)와 하부 매립너트(142) 하부매립 플랜지(145)가 지지판으로서 저항하게 된다.The lifting load resistance flange 144 of the upper buried nut 141 and the lower buried flange 145 of the lower buried nut 142 resist the lifting load as a support plate.

이에, 도 3d와 같이, PC 슬래브(120)를 교량용 거더(110)에 거치 후, 상부 매립너트(141) 내부로 타격봉(146)을 삽입하고, 타격봉(146)의 하단이 하부 매립너트(142)를 관통하여 하부매립 플랜지(145) 내측 상면에 접한 상태에서 타격봉(146)의 상단을 타격하면, Therefore, as shown in FIG. 3D, after the PC slab 120 is mounted on the bridge girder 110, the impact rod 146 is inserted into the upper landfill nut 141, and the lower end of the impact rod 146 is embedded in the lower part. When the upper end of the striking rod 146 is hit in a state in contact with the inner upper surface of the lower buried flange 145 through the nut 142,

상부 매립너트(141)로부터 하부 매립너트(142)의 하부매립 플랜지(145)가 분리되면서 교량용 거더(110) 상면에 접하게 된다. As the lower buried flange 145 of the lower buried nut 142 is separated from the upper buried nut 141, it comes into contact with the upper surface of the bridge girder 110.

이때 상기 하부매립 플랜지(145)는 PC 슬래브(120) 저면에 노출되도록 세팅되어 타격에 의하여 상부 매립너트(141)로부터 분리 가능하도록 하게 되며, 하부 매립너트(142)의 상단은 PC 슬래브(120) 내부에 그대로 위치하도록 하여 타격 시 이탈되지 않을 수 있다.At this time, the lower buried flange 145 is set to be exposed on the bottom surface of the PC slab 120 so that it can be separated from the upper buried nut 141 by hitting, and the upper end of the lower buried nut 142 is the PC slab 120 As it is located inside, it may not escape when hitting.

이에 타격봉(146)을 제거하고, 높이조절볼트(147)를 상부 매립너트(141)와 하부 매립너트(142)에 체결시키면서 회전에 따라 PC 슬래브(120)의 설치 높이가 조절되도록 하게 되며, 미도시 하였지만 교량용 거더(110)와 PC 슬래브(120) 사이의 공간인 베딩층에는 충전재를 미리 채워지도록 할 수도 있다.Accordingly, the striking rod 146 is removed, and the height adjustment bolt 147 is fastened to the upper embedded nut 141 and the lower embedded nut 142 so that the installation height of the PC slab 120 is adjusted according to rotation, Although not shown, the bedding layer, which is the space between the bridge girder 110 and the PC slab 120, may be pre-filled with a filler.

이에 높이조절볼트(147)를 제거하고 나서, 무수축모르타르를 포함하는 충전재(148)를 상부 매립너트(141)와 하부 매립너트(142)의 내부로 충전시킴과 더불어 교량용 거더(110)와 PC 슬래브(120) 사이 공간 역시 충전되도록 하여 최종 높이 조절된 PC 슬래브(120)이 교량용 거더(110) 상면에 설치될 수 있게 된다.Accordingly, after removing the height adjustment bolt 147, the filling material 148 containing non-shrinkage mortar is filled into the upper landfill nut 141 and the lower landfill nut 142, and the bridge girder 110 and The space between the PC slabs 120 is also filled so that the final height-adjusted PC slab 120 can be installed on the upper surface of the bridge girder 110.

다음으로 두 번째 분리형 매립너트(TYPE 2)는 도 3d와 같이, 수직 원통형의 매립너트가 상,하로 연통 및 분리 가능하도록 연결시킨 상부 매립너트(141)와 하부 매립너트(142)로 형성되어 있음은 앞서 살펴본 분리형 매립너트(TYPE 1)와 동일하며, 인양하중 저항용 플랜지(144)가 제외되어 있음에 차이가 있다.Next, as shown in FIG. 3D, the second separable buried nut (TYPE 2) is formed of an upper buried nut 141 and a lower buried nut 142 connected so that vertical cylindrical buried nuts can communicate and separate upwards and downwards. is the same as the separable buried nut (TYPE 1) discussed above, with a difference in that the lifting load resistance flange 144 is excluded.

이에 상부 매립너트(141)는 도 3d를 참조하면, 수직 원통부재로서 내측면에 나사부가 형성되어 있고 하부 매립너트(142)와 그대로 연결 및 연통된다.Accordingly, referring to FIG. 3D , the upper buried nut 141 is a vertical cylindrical member having a threaded portion formed on the inner surface and connected and communicated with the lower buried nut 142 as it is.

하부 매립너트(142)는 도 3d를 참조하면 역시 상부 매립너트(141) 하부에 분리 가능하도록 연결된 수직 원통부재로서 하부매립 플랜지(145)가 하부에 형성된 것으로서, 하부매립 플랜지(145)는 PC 슬래브(120) 내부로부터 저면에 노출되도록 초기 세팅되도록 하는 것은 TYPE 1과 동일하고, 인양하중 저항용 플랜지(144)만 제외되어 있을 뿐임을 알 수 있다.Referring to FIG. 3D, the lower buried nut 142 is also a vertical cylindrical member detachably connected to the lower part of the upper buried nut 141, and a lower buried flange 145 is formed at the lower portion, and the lower buried flange 145 is a PC slab (120) It can be seen that the initial setting to be exposed to the bottom surface from the inside is the same as TYPE 1, and only the lifting load resistance flange 144 is excluded.

이에 역시 상부 매립너트(141)와 하부 매립너트(142)가 매립된 PC 슬래브(120)를 교량용 거더(110) 상면에 스페이서와 인양볼트를 이용하여 초기 세팅시키게 되며, Accordingly, the PC slab 120 in which the upper embedded nut 141 and the lower embedded nut 142 are embedded is initially set using a spacer and a lifting bolt on the upper surface of the bridge girder 110,

인양하중에 대하여 상기 하부 매립너트(142)의 하부매립 플랜지(145)만 지지판으로서 저항하게 된다.Only the lower buried flange 145 of the lower buried nut 142 resists the lifting load as a support plate.

이에, 도 3d와 같이, 역시 상부 매립너트(141) 내부로 타격봉(146)을 삽입하고, 타격봉(146)의 하단이 하부 매립너트(142)를 관통하여 하부매립 플랜지(145) 내측 상면에 접한 상태에서 타격봉의 상단을 타격하면,Accordingly, as shown in FIG. 3D, the striking rod 146 is also inserted into the upper buried nut 141, and the lower end of the striking rod 146 penetrates the lower buried nut 142 to reach the inner upper surface of the lower buried flange 145. If you hit the top of the baton while in contact with

상부 매립너트(141)로부터 하부 매립너트(142)의 하부매립 플랜지(145)가 분리되면서 교량용 거더(110) 상면에 접하게 된다. 이때 상기 하부매립 플랜지(145)는 PC 슬래브(120) 저면에 노출되도록 세팅되어 타격에 의하여 상부 매립너트(141)로부터 분리 가능하도록 하게 되며, 하부 매립너트(142)의 상단은 PC 슬래브(120) 내부에 그대로 위치하도록 하여 타격 시 이탈되지 않을 수 있도록 함은 동일하다.As the lower buried flange 145 of the lower buried nut 142 is separated from the upper buried nut 141, it comes into contact with the upper surface of the bridge girder 110. At this time, the lower buried flange 145 is set to be exposed on the bottom surface of the PC slab 120 so that it can be separated from the upper buried nut 141 by hitting, and the upper end of the lower buried nut 142 is the PC slab 120 It is the same that it is located inside so that it can not escape when hitting.

이에 타격봉(146)을 제거하고, 높이조절볼트(147)를 상부 매립너트(141)와 하부 매립너트(142)에 체결시키면서 회전에 따라 PC 슬래브(120)의 설치 높이가 조절되도록 하게 된다.Accordingly, the striking bar 146 is removed, and the installation height of the PC slab 120 is adjusted according to rotation while the height adjustment bolt 147 is fastened to the upper embedded nut 141 and the lower embedded nut 142.

이에 높이조절볼트(147)를 제거하고 나서, 무수축모르타르를 포함하는 충전재(148)를 상부 매립너트(141)와 하부 매립너트(142)의 내부로 충전시킴과 더불어 교량용 거더(110)와 PC 슬래브(120) 사이 공간 역시 충전되도록 하여 최종 높이 조절된 PC 슬래브(120)가 교량용 거더(110) 상면에 설치될 수 있게 됨은 동일하다.Accordingly, after removing the height adjustment bolt 147, the filling material 148 containing non-shrinkage mortar is filled into the upper landfill nut 141 and the lower landfill nut 142, and the bridge girder 110 and It is the same that the space between the PC slabs 120 is also filled so that the final height-adjusted PC slab 120 can be installed on the upper surface of the bridge girder 110.

다음으로 상기 횡방향구배용 새들(150)은 도 2 및 도 3e와 같이, 인양 후 교량용 거더(110)의 상면에 설치된 PC 슬래브(120)의 횡방향 구배를 조절하기 위한 것이다.Next, as shown in FIGS. 2 and 3E, the saddle 150 for lateral gradient is for adjusting the lateral gradient of the PC slab 120 installed on the upper surface of the bridge girder 110 after lifting.

이때 상기 횡방향구배용 새들(150)은 교량용 거더(110)의 상면에 설치되도록 하는 것이기 때문에, 미리 횡방향구배용 새들(150)을 교량용 거더(110) 제작 시 일체로 형성시켜도 되고, 현장에서 별도로 설치해도 상관은 없다.At this time, since the saddle 150 for the lateral gradient is installed on the upper surface of the girder 110 for the bridge, the saddle 150 for the lateral gradient may be integrally formed during the production of the girder 110 for the bridge in advance, It doesn't matter if you install it separately on site.

이러한 교량용 거더(110)는 도 3e를 참조하면, 높이조절용 지지블록(151), 바닥판지지부재(152)를 포함하게 된다.Referring to FIG. 3E, such a bridge girder 110 includes a support block 151 for height adjustment and a floor plate support member 152.

상기 높이조절용 지지블록(151)은 도 3e와 같이, 교량용 거더(110)의 상부플랜지 양 측방 상면에 형성되도록 한 것으로서,As shown in FIG. 3E, the height adjustment support block 151 is formed on both side upper surfaces of the upper flange of the bridge girder 110,

횡방향으로 이격 설치된 좌측과 우측의 높이조절용 지지블록(151)은 서로 높이에 차이가 있게 되며, PC 슬래브(120)의 양 높이조절용 지지블록(151)에 의하여 자연스럽게 횡방향으로 경사지도록 설치할 수 있게 된다.The left and right side height adjustment support blocks 151 spaced apart in the lateral direction have a difference in height from each other, and by the both height adjustment support blocks 151 of the PC slab 120, it can be installed to be inclined in the transverse direction naturally do.

상기 바닥판지지부재(152)는 도 3e와 같이, 높이조절용 지지블록(151) 상면에 설치되어 PC 슬래브(120)를 직접 지지하는 역할을 하게 되는데, 반원형 곡면구로 형성시키고 있음을 알 수 있으나 형상과 재질에는 달리 제한이 없다.As shown in FIG. 3E, the bottom plate support member 152 is installed on the upper surface of the support block 151 for height adjustment and serves to directly support the PC slab 120. It can be seen that it is formed in a semicircular curved sphere, but the shape and materials are not otherwise limited.

이때 중요한 점은 바닥판지지부재(152)가 PC 슬래브(120)의 저면에 형성시킨 지지홈(126)에 바닥판지지부재(152) 상단이 밀실하게 접하면서 횡방향구배용 새들(150)에 의하여 베딩층(153)이 커지는 것을 방지하고, 충전재를 베딩층에 충전시킬 때, 누출되지 않도록 하는 역할도 하도록 하게 된다.At this time, the important point is that the top of the bottom plate support member 152 closely contacts the support groove 126 formed on the bottom surface of the PC slab 120 by the floor plate support member 152, and the saddle 150 for lateral gradient This prevents the bedding layer 153 from growing, and also serves to prevent leakage when the filling material is filled in the bedding layer.

이를 위해 상기 바닥판지지부재(152)는 상기 상부플랜지 상면에 연속으로 연장되도록 하고, 바닥판지지부재(152)를 지지하는 높이조절용 지지블록(151)은 다수를 이격시켜 설치하는 것이 바람직하다.To this end, it is preferable that the floor plate support member 152 continuously extends on the upper surface of the upper flange, and a plurality of height adjustment support blocks 151 supporting the floor plate support member 152 are spaced apart from each other.

또한 교량의 다양한 횡구배와 관계없이 PC 슬래브(120)에 헌치부(하방으로 만곡되도록 형성)를 형성시키지 않아도 되고, 이에 헌치부 배제에 따라 PC 슬래브(120) 제작용 거푸집 활용성을 높일 수 있게 된다.In addition, regardless of the various lateral gradients of the bridge, it is not necessary to form a haunch portion (formed to be curved downward) on the PC slab 120, and thus, the PC slab 120 according to the exclusion of the haunch portion To increase the usability of the formwork for manufacturing do.

[ 본 발명의 PC 슬래브(120) 시공방법][PC slab 120 construction method of the present invention]

도 4는 본 발명의 PC 슬래브(120) 시공방법 순서도를 도시한 것이다.Figure 4 shows a flow chart of the PC slab 120 construction method of the present invention.

상기 본 발명의 PC 슬래브(120) 시공방법은 도 2 및 도 4를 참조하면, 교량하부구조(200)를 먼저 시공한 후, 교량하부구조(200)에 교량용 거더(110)를 거치하고, 교량용 거더(110) 상면에 종방향으로는 PC 슬래브(120)를 바닥판 높이조절장치(140)를 이용하여 높이조절함과 더불어 횡방향구배를 횡방향구배용 새들(150)를 이용하여 맞춘다음, 종방향으로 PC 슬래브(120)를 바닥판체결구(130)를 이용하여 조립 연결시키는 방법이라 할 수 있다.Referring to FIGS. 2 and 4, in the construction method of the PC slab 120 of the present invention, the bridge lower structure 200 is first constructed, and then the bridge girder 110 is mounted on the bridge lower structure 200, In addition to adjusting the height of the PC slab 120 in the longitudinal direction on the upper surface of the bridge girder 110 using the floor plate height adjusting device 140, the lateral gradient was adjusted using the saddle 150 for lateral gradient Next, it can be referred to as a method of assembling and connecting the PC slab 120 in the longitudinal direction using the bottom plate fastener 130.

이에 먼저 도 4와 같이 몸통부(122)의 연결단부면(B) 주위의 상면에 상부수용홈(123)이 형성되고, 상기 연결단부면(B)의 중간에 중간삽입홈(124)이 형성되어 연결단부면(B)에서 상부수용홈(123)과 중간삽입홈(124)이 서로 수평으로 접하여 연통되도록 인접 설치되는 양 PC 슬래브(120)를 교량용 거더(110)에 거치하게 된다.First, as shown in FIG. 4, an upper receiving groove 123 is formed on the upper surface around the connection end surface B of the body portion 122, and an intermediate insertion groove 124 is formed in the middle of the connection end surface B. Thus, both PC slabs 120 installed adjacent to each other are mounted on the bridge girder 110 so that the upper receiving groove 123 and the intermediate insertion groove 124 horizontally contact and communicate with each other on the connection end surface (B).

구체적으로는 시공된 교량하부구조(200)에 교량용 거더(110)를 거치하되, 전단연결장치(A)인 하우징(112)을 교량용 거더(110)의 상부플랜지(111) 상면에 노출되도록 형성시키게 된다.Specifically, the bridge girder 110 is mounted on the constructed bridge substructure 200, but the housing 112, which is the shear connecting device A, is exposed on the upper surface of the upper flange 111 of the bridge girder 110. will form

즉, 도 2를 참조하면, 상기 교량하부구조(200)는 앞서 살펴본 바와 같이 교각, 교대를 포함하게 되며 현장에 미리 역시 철근콘크리트 구조물로 시공하면 된다.That is, referring to FIG. 2, the bridge substructure 200 includes piers and abutments as described above, and may be constructed as a reinforced concrete structure in advance at the site.

또한, 상기 교량용 거더(110)는 상부플랜지(111) 상면에 전단연결장치(A)인 하우징(112)이 스터드(113)에 의하여 위치 세팅되어 내부가 노출되도록 미리 형성시키게 되며, 상기 하우징(112)은 교량용 거더(110)의 연장방향인 종방향으로 연속하여 형성되어 있음을 알 수 있다.In addition, the bridge girder 110 is formed in advance so that the housing 112, which is the shear connection device A, is positioned on the upper surface of the upper flange 111 by the stud 113 to expose the inside, and the housing ( 112) is formed continuously in the longitudinal direction, which is the extension direction of the bridge girder 110.

이에 거치된 교량용 거더(110) 상면에 노출된 하우징(112)과 PC 슬래브(120)의 전단포켓(121)이 서로 연통되도록 PC 슬래브(120)를 초기 세팅하게 된다.The PC slab 120 is initially set so that the housing 112 exposed on the upper surface of the bridge girder 110 mounted thereon and the shear pocket 121 of the PC slab 120 communicate with each other.

즉, 도 2를 참조하면 상기 전단포켓(121)은 PC 슬래브(120)에 다수가 서로 이격되도록 형성되어 있지만 하우징(112)은 종방향으로 연속으로 형성되어 있기 때문에 다소의 시공오차가 발생해도 PC 슬래브(120)를 교량용 거더(110)에 강결시키는에는 달리 문제가 없게 된다.That is, referring to FIG. 2, the shear pockets 121 are formed so as to be spaced apart from each other on the PC slab 120, but since the housing 112 is formed continuously in the longitudinal direction, even if some construction errors occur, the PC There is no other problem in stiffening the slab 120 to the bridge girder 110.

이로서 전단포??(121)과 교량용 거더(110) 상면에 노출된 하우징(112)은 서로 상,하로 연통되어 전단연결재(114)를 작업자가 PC 슬래브(120) 상면에서 바로 전단포켓(121)과 하우징(112)을 관통하여 설치할 수 있게 된다.As a result, the shear fabric?? ) and can be installed through the housing 112.

또한 도 4와 같이 전단포켓(121)과 하우징(112)이 서로 연통되도록 거치된 PC 슬래브(120)의 높이와 횡방향구배를 바닥판 높이조절장치(140)와 횡방향구배용 새들(150)를 이용하여 조절하게 된다.In addition, as shown in FIG. 4, the height and lateral gradient of the PC slab 120 mounted so that the shear pocket 121 and the housing 112 communicate with each other are adjusted by the bottom plate height adjusting device 140 and the saddle 150 for lateral gradient is adjusted using .

즉, PC 슬래브(120)는 교량용 거더(110) 상면에 거치할 때 간격재로 초기 세팅하면서 횡방향구배용 새들(150)를 이용하여 횡방향 구배를 조절한 다음, 바닥판 높이조절장치(140)를 이용하여 설치높이를 정확하게 세팅하게 된다.That is, when the PC slab 120 is initially set as a spacer when mounted on the upper surface of the bridge girder 110, the lateral gradient is adjusted using the saddle 150 for lateral gradient, and then the floor plate height adjusting device ( 140) to accurately set the installation height.

이에 상기 횡방향구배용 새들(150)은 높이조절용 지지블록(151) 상부에 바닥판지지부재(152)이 형성된 것을 이용하게 되고,Accordingly, the saddle 150 for the horizontal gradient uses the bottom plate support member 152 formed on the top of the support block 151 for height adjustment,

상기 바닥판 높이조절장치(140)는 도 3b와 같이, 상부 매립너트(141)와 하부 매립너트(142)를 이용한 TYPE 1,2를 이용할 수 있음을 알 수 있다.As shown in FIG. 3B, the bottom plate height adjusting device 140 can use TYPE 1 or 2 using an upper embedded nut 141 and a lower embedded nut 142.

다음으로 상기 양 PC 슬래브(120)의 상부수용홈(123) 및 중간삽입홈(124)에 상부덧댐판(131) 및 중간덧댐판(132)이 삽입되어 상,하로 관통홀이 연통되도록 세팅되는 종방향 바닥판체결구(130)를 설치하게 된다(S120).Next, the upper pad 131 and the middle pad 132 are inserted into the upper receiving groove 123 and the intermediate insertion groove 124 of the PC slabs 120, and the upper and lower through-holes are set to communicate The longitudinal bottom plate fastener 130 is installed (S120).

구체적으로 도 4와 같이 종방향 바닥판체결구(130)를 이용하여 PC 슬래브(120)를 종방향으로 연결시키게 된다.Specifically, as shown in FIG. 4, the PC slab 120 is connected in the longitudinal direction using the longitudinal bottom plate fastener 130.

즉, PC 슬래브(120)를 먼저 1개 설치하고, 나머지 PC 슬래브(120)를 종방향으로 서로 연속하여 설치하고, 후 설치되는 PC 슬래브(120)는 역시 설치높이와 횡방향구배를 ??추면서 세팅하게 된다.That is, one PC slab 120 is installed first, the remaining PC slabs 120 are installed consecutively with each other in the longitudinal direction, and the PC slab 120 to be installed after also adds the installation height and lateral gradient. while setting.

이에 상기 종방향 바닥판체결구(130)는 상부덧댐판(131), 중간덧댐판(132)이 상,하로 세팅되어 체결볼트(133)를 이용하여 간단하게 설치할 수 있고, 최종 충전재를 이용하여 삽입 설치된 상부수용홈(123), 중간삽입홈(124)을 마감시키면 된다. Accordingly, the longitudinal bottom plate fastening hole 130 can be simply installed using the fastening bolt 133 by setting the upper padding plate 131 and the middle padding board 132 up and down, and using the final filler The upper receiving groove 123 and the intermediate insertion groove 124 may be closed.

이에 도 4와 같이 전단포켓(121)을 통해 하우징(112)에 전단연결재(114)를 고정 설치하고, 전단포켓(121)에 무수축모를타르와 같은 충전재(148)를 충전시켜 교량용 거더(110)와 PC 슬래브(120)를 서로 강결시키게 된다.Accordingly, as shown in FIG. 4, the shear connector 114 is fixedly installed in the housing 112 through the shear pocket 121, and the shear pocket 121 is filled with a filler 148 such as non-shrinkable mortar for the bridge girder ( 110) and the PC slab 120 are hardened to each other.

즉, 전단포켓(121)과 하우징(112)은 이미 서로 연통되어 있으므로 하우징(112) 저면에 전단연결재(114)의 하단을 용접 등의 방법으로 고정 설치하고,That is, since the shear pocket 121 and the housing 112 are already in communication with each other, the lower end of the shear connector 114 is fixed to the bottom of the housing 112 by welding or the like,

연통된 전단포켓(121)과 하우징(112)을 메워주는 충전재(148)를 충전시킴으로서 베딩층도 함께 마감하는 방식으로 강결시키게 된다.By filling the filler 148 that fills the communicating shear pocket 121 and the housing 112, the bedding layer is also hardened in a manner of finishing together.

전술한 본 발명의 설명은 예시를 위한 것이며, 본 발명이 속하는 기술분야의 통상의 지식을 가진 자는 본 발명의 기술적 사상이나 필수적인 특징을 변경하지 않고서 다른 구체적인 형태로 쉽게 변형이 가능하다는 것을 이해할 수 있을 것이다. 그러므로 이상에서 기술한 실시예들은 모든 면에서 예시적인 것이며 한정적이 아닌 것으로 이해해야만 한다. 예를 들어, 단일형으로 설명되어 있는 각 구성 요소는 분산되어 실시될 수도 있으며, 마찬가지로 분산된 것으로 설명되어 있는 구성 요소들도 결합된 형태로 실시될 수 있다.The above description of the present invention is for illustrative purposes, and those skilled in the art can understand that it can be easily modified into other specific forms without changing the technical spirit or essential features of the present invention. will be. Therefore, the embodiments described above should be understood as illustrative in all respects and not limiting. For example, each component described as a single type may be implemented in a distributed manner, and similarly, components described as distributed may be implemented in a combined form.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is indicated by the following claims rather than the detailed description above, and all changes or modifications derived from the meaning and scope of the claims and equivalent concepts should be construed as being included in the scope of the present invention. do.

100: PC 슬래브 시공방법을 이용하여 제작된 교량
110: 교량용 거더
111: 상부플랜지 112: 하우징
113: 스터드 114: 전단연결재
120: PC 슬래브
121: 전단포켓 122: 몸통부
123: 상부수용홈 124: 중간삽입홈
130: 종방향 바닥판체결구
131: 상부덧댐판 131a: 관통홀
132: 중간덧댐판 132a: 관통홀
133: 체결볼트 134: 이동공구
135: 수평 U형 보강철근 136: 삽입홀
137: 삽입볼트
140: 바닥판 높이조절장치
141: 상부 매립너트 142: 하부 매립너트
144: 인양하중 저항용 플랜지 145: 하부매립 플랜지
146: 타격봉 147: 높이조절볼트
148: 충전재 150: 횡방향구배용 새들
151: 높이조절용 지지블록 152: 바닥판지지부재
200: 교량하부구조
A: 전단연결장치 B: 연결단부면
100: Bridge made using PC slab construction method
110: girder for bridge
111: upper flange 112: housing
113: stud 114: shear connector
120: PC slab
121: shear pocket 122: body
123: upper receiving groove 124: middle insertion groove
130: longitudinal bottom plate fasteners
131: upper back plate 131a: through hole
132: middle pad 132a: through hole
133: Fastening bolt 134: Moving tool
135: horizontal U-shaped rebar 136: insertion hole
137: insertion bolt
140: bottom plate height adjustment device
141: upper buried nut 142: lower buried nut
144: flange for lifting load resistance 145: buried flange
146: batting rod 147: height adjustment bolt
148: filler 150: saddle for transverse gradient
151: support block for height adjustment 152: bottom plate support member
200: bridge substructure
A: shear coupling device B: connection end face

Claims (10)

(a) 몸통부(122)의 연결단부면(B) 주위의 상면에 상부수용홈(123)이 형성되고, 상기 연결단부면(B)의 중간에 중간삽입홈(124)이 형성되어 연결단부면(B)에서 상부수용홈(123)과 중간삽입홈(124)이 서로 수평으로 접하여 연통되도록 인접 설치되는 양 PC 슬래브(120)를 교량용 거더(110)에 거치하는 단계; 및
(b) 상기 양 PC 슬래브(120)의 상부수용홈(123) 및 중간삽입홈(124)에 상부덧댐판(131) 및 중간덧댐판(132)이 삽입되어 상,하로 관통홀이 연통되도록 세팅되는 종방향 바닥판체결구(130)를 설치하는 단계;를 포함하여
상기 상부덧댐판(131)과 중간덧댐판(132)은 서로 인접한 PC 슬래브(120)의 연결단부면(B)에서 상,하로 연통된 관통홀(131a,132a)을 통해 체결볼트(133)가 체결되도록 하여 PC 슬래브(120)를 종방향으로 연결하면서 설치되도록 하며, 상기 (b)단계의 중간덧댐판(132)은 일측 PC 슬래브(120)의 중간삽입홈(124)에 삽입시켜 놓은 상태에서, 연결되는 타측 PC 슬래브(120)의 중간삽입홈(124)쪽으로 이동시켜 중간덧댐판(132)의 중간부분이 연결단부면(B)을 경유하도록 세팅하여, 중간덧댐판(132)은 일측 PC 슬래브(120)의 중간삽입홈(124)에 완전히 삽입된 상태가 되어 타측 PC슬래브(120)가 일측 PC 슬래브(120)로 인접하는 과정에서 방해 요인이 되지 않도록 하는 PC 슬래브 시공방법.
(a) An upper receiving groove 123 is formed on the upper surface around the connection end surface (B) of the body portion 122, and an intermediate insertion groove 124 is formed in the middle of the connection end surface (B), so that the connection end Mounting both PC slabs 120 installed adjacent to the bridge girder 110 so that the upper receiving groove 123 and the intermediate insertion groove 124 horizontally contact and communicate with each other on the side surface (B); and
(b) the upper receiving groove 123 and the intermediate insertion groove 124 of both PC slabs 120 are inserted with the upper padding plate 131 and the intermediate padding board 132, so that the upper and lower through-holes are in communication Installing a longitudinal bottom plate fastener 130 that is; including
The upper padding plate 131 and the middle padding board 132 are fastened bolts 133 through through-holes 131a and 132a communicating up and down at the connection end surface B of the PC slab 120 adjacent to each other. It is fastened so that it is installed while connecting the PC slab 120 in the longitudinal direction, and the intermediate pad 132 of the step (b) is inserted into the intermediate insertion groove 124 of the PC slab 120 on one side , Move toward the middle insertion groove 124 of the PC slab 120 on the other side to be connected, and set the middle portion of the middle pad 132 to pass through the connection end surface (B), so that the middle pad 132 is one PC A PC slab construction method that is completely inserted into the intermediate insertion groove 124 of the slab 120 so that the other side PC slab 120 does not become an obstacle in the process of adjoining one side PC slab 120.
제1항에 있어서,
상기 (a) 단계의 양 PC 슬래브(120)는,
전단연결장치(A)가 구비된 교량용 거더(110) 상면에 거치되도록 하되, 상기 전단연결장치(A)는, 교량용 거더(110)의 상부플랜지(111) 상면에 상부가 노출되도록 매립된 형강부재를 이용하여 상부플랜지(111)의 종방향으로 연속하여 형성된 하우징(112);
상기 하우징(112)의 저면으로부터 하방으로 연장되어 하우징(112)이 교량용 거더(110)의 상부플랜지(111)에 고정 설치되도록 하는 스터드(113); 및
PC 슬래브(120)에 형성된 전단포켓(121)을 통해 하우징(112) 저면에 고정되도록 하되 전단포켓(121) 내부로 연장되도록 설치되는 전단연결재(114);를 포함하는 PC 슬래브 시공방법.
According to claim 1,
Both PC slabs 120 in step (a),
It is mounted on the upper surface of the bridge girder 110 equipped with the shear connection device (A), but the shear connection device (A) is buried so that the upper part is exposed on the upper surface of the upper flange 111 of the bridge girder 110 A housing 112 continuously formed in the longitudinal direction of the upper flange 111 using a section steel member;
A stud 113 extending downward from the bottom surface of the housing 112 so that the housing 112 is fixed to the upper flange 111 of the bridge girder 110; and
A PC slab construction method including a shear connector 114 fixed to the bottom of the housing 112 through the shear pocket 121 formed in the PC slab 120 but extending into the shear pocket 121.
제1항에 있어서,
상기 (a) 단계와 (b) 단계 사이에, 교량용 거더(110)의 상면에 설치된 PC 슬래브(120)의 설치 높이를 조절할 수 있도록 바닥판 높이조절장치(140)를 설치하는 단계를 더 포함하도록 하며, 상기 바닥판 높이조절장치(140)는,
수직 원통부재로서 내측면에 나사부가 형성되어 있고 하단에는 수평판 형태의 인양하중 저항용 플랜지(144)가 일체로 형성된 상부 매립너트(141); 및
상부 매립너트(141) 하부에 분리 가능하도록 연결된 수직 원통부재로서 PC 슬래브(120) 내부로부터 저면에 노출되도록 초기 세팅된 하부매립 플랜지(145)가 하부에 형성된 하부 매립너트(142);를 포함하여,
인양하중에 대하여 상기 상부 매립너트(141)의 인양하중 저항용 플랜지(144)와 하부 매립너트(142)의 하부매립 플랜지(145)가 지지판으로서 저항하도록 하는 PC 슬래브 시공방법.
According to claim 1,
Between the steps (a) and (b), a step of installing a floor plate height adjusting device 140 to adjust the installation height of the PC slab 120 installed on the upper surface of the bridge girder 110 is further included. And the floor plate height adjusting device 140,
An upper embedded nut 141 having a threaded portion formed on the inner surface as a vertical cylindrical member and a flange 144 for lifting load resistance in the form of a horizontal plate integrally formed at the lower end; and
As a vertical cylindrical member detachably connected to the lower part of the upper buried nut 141, a lower buried nut 142 having a lower buried flange 145 initially set to be exposed to the bottom surface from the inside of the PC slab 120 is formed therein; including ,
A PC slab construction method in which the flange 144 for resisting the lifting load of the upper buried nut 141 and the lower embedded flange 145 of the lower embedded nut 142 resist the lifting load as a support plate.
제1항에 있어서,
상기 (a) 단계와 (b) 단계 사이에, 교량용 거더(110)의 상면에 설치된 PC 슬래브(120)의 설치 높이를 조절할 수 있도록 바닥판 높이조절장치(140)를 설치하는 단계를 더 포함하도록 하며, 상기 바닥판 높이조절장치(140)는,
수직 원통부재로서 내측면에 나사부가 형성되어 있고 하부 매립너트(142)와 연결 및 연통되는 상부 매립너트(141); 및
상부 매립너트(141) 하부에 분리 가능하도록 연결된 수직 원통부재로서 PC 슬래브(120) 내부로부터 저면에 노출되도록 초기 세팅된 하부매립 플랜지(145)가 하부에 형성된 하부 매립너트(142);를 포함하여,
상기 하부 매립너트(142)의 하부매립 플랜지(145)가 지지판으로서 인양하중에 저항하도록 하는 PC 슬래브 시공방법.
According to claim 1,
Between the steps (a) and (b), a step of installing a floor plate height adjusting device 140 to adjust the installation height of the PC slab 120 installed on the upper surface of the bridge girder 110 is further included. And the floor plate height adjusting device 140,
an upper buried nut 141 as a vertical cylindrical member having a threaded portion formed on an inner surface and connected to and communicating with the lower buried nut 142; and
As a vertical cylindrical member detachably connected to the lower part of the upper buried nut 141, a lower buried nut 142 having a lower buried flange 145 initially set to be exposed to the bottom surface from the inside of the PC slab 120 is formed therein; including ,
A PC slab construction method in which the lower buried flange 145 of the lower buried nut 142 resists the lifting load as a support plate.
제1항에 있어서,
상기 (a) 단계와 (b) 단계 사이에, 교량용 거더(110)의 상면에 설치된 PC 슬래브(120)의 횡방향 구배를 조절할 수 있도록 횡방향구배용 새들(150)를 설치하는 단계가 더 포함하도록 하며, 상기 횡방향구배용 새들(150)은,
교량용 거더(110)의 상부플랜지 양 측방 상면에 형성되도록 한 것으로서, 횡방향으로 서로 높이에 차이가 형성되도록 이격 설치된 높이조절용 지지블록(151); 및 높이조절용 지지블록(151) 상면에 설치되어 PC 슬래브(120)가 지지홈(126)에 직접 지지하는 역할을 하는 반원형 곡면구를 포함하는 바닥판지지부재(152);를 포함하며,
PC 슬래브(120)의 저면에 형성시킨 지지홈(126)에 바닥판지지부재(152) 상단이 접하면서 횡방향구배용 새들(150)에 의하여 횡구배와 관계없이 PC 슬래브(120)에 헌치부를 형성시키지 않을 수 있도록 하는 PC 슬래브 시공방법.
According to claim 1,
Between the steps (a) and (b), there is a further step of installing a saddle 150 for lateral gradient to adjust the lateral gradient of the PC slab 120 installed on the upper surface of the bridge girder 110 To include, the saddle 150 for the transverse gradient,
Height-adjusting support blocks 151 spaced apart to form a difference in height from each other in the transverse direction as formed on the upper surfaces of both sides of the upper flange of the bridge girder 110; And a bottom plate support member 152 including a semicircular curved sphere installed on the upper surface of the support block 151 for height adjustment and serving to directly support the PC slab 120 in the support groove 126; including,
The upper end of the bottom plate support member 152 is in contact with the support groove 126 formed on the bottom surface of the PC slab 120, and the saddle 150 for horizontal gradient makes the PC slab 120 regardless of the horizontal gradient. A PC slab construction method that allows not to form.
(a) 시공된 교량하부구조(200)에 교량용 거더(110)를 거치하되, 전단연결장치(A)인 하우징(112)을 교량용 거더(110)의 상부플랜지(111) 상면에 노출되도록 형성시키는 단계;
(b) 거치된 교량용 거더(110) 상면에 노출된 하우징(112)과 PC 슬래브(120)의 전단포켓(121)이 서로 연통되도록 설치되는 것으로서, 몸통부(122)의 연결단부면(B) 주위의 상면에 상부수용홈(123)이 형성되고, 상기 연결단부면(B)의 중간에 중간삽입홈(124)이 형성되어 연결단부면(B)에서 상부수용홈(123)과 중간삽입홈(124)이 서로 수평으로 접하여 연통되도록 인접 설치되는 PC 슬래브(120)를 초기 세팅하는 단계;
(c) 전단포켓(121)과 하우징(112)이 서로 연통되도록 거치된 PC 슬래브(120)의 높이와 횡방향구배를 바닥판 높이조절장치(140)와 횡방향구배용 새들(150)를 이용하여 조절하는 단계;
(d) 종방향 바닥판체결구(130)를 이용하여 PC 슬래브(120)를 종방향으로 연결시키는 단계; 및
(e) 전단포켓(121)을 통해 하우징(112)에 전단연결재(114)를 고정 설치하고, 전단포켓(121)에 무수축모를타르를 포함하는 충전재(148)를 충전시켜 교량용 거더(110)와 PC 슬래브(120)를 서로 강결시키는 단계;를 포함하며,
상기 (d) 단계의 종방향 바닥판체결구(130)는 PC 슬래브(120)들의 상부수용홈(123) 및 중간삽입홈(124)에 상부덧댐판(131) 및 중간덧댐판(132)이 삽입되어 상,하로 관통홀(131a,132a)이 연통되도록 세팅되어 상기 상부덧댐판(131)과 중간덧댐판(132)은 서로 인접한 PC 슬래브(120)의 연결단부면(B)에서 상,하로 연통된 관통홀(131a,132a)을 통해 체결볼트(133)가 체결되도록 하여 PC 슬래브(120)를 종방향으로 연결하면서 설치되도록 하며, 상기 중간덧댐판(132)은 일측 PC 슬래브(120)의 중간삽입홈(124)에 삽입시켜 놓은 상태에서, 연결되는 타측 PC 슬래브(120)의 중간삽입홈(124)쪽으로 이동시켜 중간덧댐판(132)의 중간부분이 연결단부면(B)을 경유하도록 세팅하여, 중간덧댐판(132)은 일측 PC 슬래브(120)의 중간삽입홈(124)에 완전히 삽입된 상태가 되어 타측 PC슬래브(120)가 일측 PC 슬래브(120)로 인접하는 과정에서 방해 요인이 되지 않도록 하는 PC 슬래브 시공방법.
(a) Place the bridge girder 110 on the constructed bridge substructure 200, but expose the housing 112, which is the shear connector (A), to the upper surface of the upper flange 111 of the bridge girder 110 forming;
(b) The housing 112 exposed on the upper surface of the mounted bridge girder 110 and the shear pocket 121 of the PC slab 120 are installed so that they communicate with each other, and the connection end surface of the body portion 122 (B) ) An upper receiving groove 123 is formed on the upper surface of the circumference, and an intermediate insertion groove 124 is formed in the middle of the connection end surface (B), so that the upper receiving groove 123 and the intermediate insertion groove 124 are formed on the connection end surface (B). Initial setting of the adjacent PC slabs 120 so that the grooves 124 are in horizontal contact with each other and communicate with each other;
(c) The height and lateral gradient of the PC slab 120 mounted so that the shear pocket 121 and the housing 112 are in communication with each other using the floor plate height adjusting device 140 and the saddle 150 for lateral gradient Adjusting by doing;
(d) connecting the PC slab 120 in the longitudinal direction using the longitudinal bottom plate fastener 130; and
(e) The shear connector 114 is fixedly installed in the housing 112 through the shear pocket 121, and the shear pocket 121 is filled with a filler 148 containing non-shrinkable mortar to bridge the girder 110 ) and the step of hardening the PC slab 120 to each other; including,
The longitudinal bottom plate fastener 130 in step (d) has an upper pad 131 and an intermediate pad 132 in the upper receiving groove 123 and the intermediate insertion groove 124 of the PC slabs 120 It is inserted and set so that the upper and lower through-holes 131a and 132a communicate, so that the upper and middle backing plates 131 and 132 are connected up and down on the connection end surface B of the PC slab 120 adjacent to each other. The fastening bolt 133 is fastened through the communicating through holes 131a and 132a so that the PC slab 120 is installed while connecting in the longitudinal direction, and the intermediate pad 132 is one side of the PC slab 120 In the state of being inserted into the intermediate insertion groove 124, move toward the intermediate insertion groove 124 of the other side PC slab 120 to be connected so that the middle portion of the intermediate padding plate 132 passes through the connection end surface (B) By setting, the intermediate pad 132 is completely inserted into the intermediate insertion groove 124 of the PC slab 120 on one side, and the other side PC slab 120 is an obstacle in the process of adjoining the PC slab 120 on one side. PC slab construction method to prevent this.
제6항에 있어서,
상기 (c) 단계의 바닥판 높이조절장치(140)에 의한 PC 슬래브(120)의 높이는,
수직 원통부재로서 내측면에 나사부가 형성되어 있고 하단에는 수평판 형태의 인양하중 저항용 플랜지(144)가 일체로 형성되는 상부 매립너트(141)와 상부 매립너트(141) 하부에 분리 가능하도록 연결된 수직 원통부재로서 하부매립 플랜지(145)가 하부에 형성된 것으로서, 하부매립 플랜지(145)는 PC 슬래브(120) 내부로부터 저면에 노출되도록 하부 매립너트(142)를 세팅하는 단계;
상부 매립너트(141)와 하부 매립너트(142)가 매립된 PC 슬래브(120)를 교량용 거더(110) 상면에 스페이서와 인양볼트를 이용하여 세팅하는 단계;
상부 매립너트(141) 내부로 타격봉(146)을 삽입하고, 타격봉(146)의 하단이 하부 매립너트(142)를 관통하여 하부매립 플랜지(145) 내측 상면에 접한 상태에서 타격봉(146)의 상단을 타격하여, 상부 매립너트(141)로부터 하부 매립너트(142)의 하부매립 플랜지(145)가 분리되면서 교량용 거더(110) 상면에 접하도록 하는 단계; 및
타격봉(146)을 제거하고, 높이조절볼트(147)를 상부 매립너트(141)와 하부 매립너트(142)에 체결시키면서 회전에 따라 PC 슬래브(120)의 설치 높이가 조절되도록 하는 단계;를 포함하는 PC 슬래브 시공방법.
According to claim 6,
The height of the PC slab 120 by the floor plate height adjusting device 140 in step (c),
As a vertical cylindrical member, a threaded portion is formed on the inner surface, and a horizontal plate-shaped lifting load resistance flange 144 is integrally formed at the bottom and is detachably connected to the lower part of the upper embedded nut 141 and the upper embedded nut 141 As a vertical cylindrical member, a lower buried flange 145 is formed at the lower portion, and the lower buried flange 145 is exposed to the bottom surface from the inside of the PC slab 120. Setting the lower buried nut 142;
Setting the PC slab 120 in which the upper buried nut 141 and the lower buried nut 142 are buried using spacers and lifting bolts on the upper surface of the bridge girder 110;
The striking rod 146 is inserted into the upper embedded nut 141, and the lower end of the striking rod 146 penetrates the lower embedded nut 142 to contact the upper inner surface of the lower embedded flange 145. ) by hitting the upper end of the buried nut 141 so that the lower buried flange 145 of the lower buried nut 142 is separated from the upper buried nut 141 and brought into contact with the upper surface of the bridge girder 110; and
Removing the striking rod 146 and fastening the height adjustment bolt 147 to the upper embedded nut 141 and the lower embedded nut 142 so that the installation height of the PC slab 120 is adjusted according to rotation; PC slab construction method including.
제6항에 있어서,
상기 (c) 단계의 바닥판 높이조절장치(140)에 의한 PC 슬래브(120)의 높이는,
수직 원통부재로서 내측면에 나사부가 형성되어 있고 하부 매립너트(142)와 그대로 연결 및 연통되는 상부 매립너트(141)와 상부 매립너트(141) 하부에 분리 가능하도록 연결된 수직 원통부재로서 하부매립 플랜지(145)가 하부에 형성된 것으로서, 하부매립 플랜지(145)는 PC 슬래브(120) 내부로부터 저면에 노출되도록 하부 매립너트(142)를 세팅하는 단계;
상부 매립너트(141)와 하부 매립너트(142)가 매립된 PC 슬래브(120)를 교량용 거더(110) 상면에 스페이서와 인양볼트를 이용하여 세팅하는 단계;
상부 매립너트(141) 내부로 타격봉(146)을 삽입하고, 타격봉(146)의 하단이 하부 매립너트(142)를 관통하여 하부매립 플랜지(145) 내측 상면에 접한 상태에서 타격봉의 상단을 타격하여, 상부 매립너트(141)로부터 하부 매립너트(142)의 하부매립 플랜지(145)가 분리되면서 교량용 거더(110) 상면에 접하도록 하는 단계; 및
타격봉(146)을 제거하고, 높이조절볼트(147)를 상부 매립너트(141)와 하부 매립너트(142)에 체결시키면서 회전에 따라 PC 슬래브(120)의 설치 높이가 조절되도록 하는 단계;를 포함하는 PC 슬래브 시공방법.
According to claim 6,
The height of the PC slab 120 by the floor plate height adjusting device 140 in step (c),
As a vertical cylindrical member, a threaded part is formed on the inner surface, and an upper embedded nut 141 connected and communicated with the lower embedded nut 142 as it is and a vertical cylindrical member detachably connected to the lower portion of the upper embedded nut 141, the lower buried flange Setting the lower buried nut 142 so that the lower buried flange 145 is exposed to the lower surface from the inside of the PC slab 120;
Setting the PC slab 120 in which the upper buried nut 141 and the lower buried nut 142 are buried using spacers and lifting bolts on the upper surface of the bridge girder 110;
The striking rod 146 is inserted into the upper embedded nut 141, and the lower end of the striking rod 146 passes through the lower embedded nut 142 to contact the upper inner surface of the lower embedded flange 145, and the upper end of the striking rod By striking, the lower buried flange 145 of the lower buried nut 142 is separated from the upper buried nut 141 so that it comes into contact with the upper surface of the bridge girder 110; and
Removing the striking rod 146 and fastening the height adjustment bolt 147 to the upper embedded nut 141 and the lower embedded nut 142 so that the installation height of the PC slab 120 is adjusted according to rotation; PC slab construction method including.
(a) 몸통부(122)의 연결단부면(B) 주위의 상면에 상부수용홈(123)이 형성되고, 상기 연결단부면(B)의 중간에 중간삽입홈(124)이 형성되어 연결단부면(B)에서 상부수용홈(123)과 중간삽입홈(124)이 서로 수평으로 접하여 연통되도록 인접 설치되는 양 PC 슬래브(120)를 교량용 거더(110)에 거치하는 단계; 및 (b) 상기 양 PC 슬래브(120)의 상부수용홈(123) 및 중간삽입홈(124)에 상부덧댐판(131) 및 중간덧댐판(132)이 삽입되어 상,하로 관통홀이 연통되도록 세팅되는 종방향 바닥판체결구(130)를 설치하는 단계;를 포함하는 PC 슬래브 시공방법에 의하여,
상기 상부덧댐판(131)과 중간덧댐판(132)은 서로 인접한 PC 슬래브(120)의 연결단부면(B)에서 상,하로 연통된 관통홀(131a,132a)을 통해 체결볼트(133)가 체결되도록 하여 PC 슬래브(120)가 종방향으로 연결하면서 설치되며, 상기 중간덧댐판(132)은 일측 PC 슬래브(120)의 중간삽입홈(124)에 삽입시켜 놓은 상태에서, 연결되는 타측 PC 슬래브(120)의 중간삽입홈(124)쪽으로 이동시켜 중간덧댐판(132)의 중간부분이 연결단부면(B)을 경유하도록 세팅하여, 중간덧댐판(132)은 일측 PC 슬래브(120)의 중간삽입홈(124)에 완전히 삽입된 상태가 되어 타측 PC슬래브(120)가 일측 PC 슬래브(120)로 인접하는 과정에서 방해 요인이 되지 않도록 하는 PC 슬래브 시공방법을 이용하여 제작된 교량.
(a) An upper receiving groove 123 is formed on the upper surface around the connection end surface (B) of the body portion 122, and an intermediate insertion groove 124 is formed in the middle of the connection end surface (B), so that the connection end Mounting both PC slabs 120 installed adjacent to the bridge girder 110 so that the upper receiving groove 123 and the intermediate insertion groove 124 horizontally contact and communicate with each other on the side surface (B); and (b) the upper receiving groove 123 and the intermediate insertion groove 124 of the two PC slabs 120 are inserted with the upper padding plate 131 and the intermediate padding board 132 so that the through holes are in communication with each other up and down. By the PC slab construction method including; installing the longitudinal floor plate fastener 130 to be set,
The upper padding plate 131 and the middle padding board 132 are fastened bolts 133 through through-holes 131a and 132a communicating up and down at the connection end surface B of the PC slab 120 adjacent to each other. It is installed while connecting the PC slab 120 in the longitudinal direction by fastening, and the intermediate pad 132 is inserted into the intermediate insertion groove 124 of the PC slab 120 on one side. PC slab on the other side to be connected (120) by moving it toward the middle insertion groove 124 and setting the middle portion of the middle padding plate 132 to pass through the connection end surface (B), the middle padding board 132 is in the middle of the PC slab 120 on one side A bridge manufactured using a PC slab construction method that is completely inserted into the insertion groove 124 so that the other PC slab 120 does not become an obstacle in the process of adjoining the one PC slab 120.
(a) 시공된 교량하부구조(200)에 교량용 거더(110)를 거치하되, 전단연결장치(A)인 하우징(112)을 교량용 거더(110)의 상부플랜지(111) 상면에 노출되도록 형성시키는 단계; (b) 거치된 교량용 거더(110) 상면에 노출된 하우징(112)과 PC 슬래브(120)의 전단포켓(121)이 서로 연통되도록 설치되는 것으로서, 몸통부(122)의 연결단부면(B) 주위의 상면에 상부수용홈(123)이 형성되고, 상기 연결단부면(B)의 중간에 중간삽입홈(124)이 형성되어 연결단부면(B)에서 상부수용홈(123)과 중간삽입홈(124)이 서로 수평으로 접하여 연통되도록 인접 설치되는 PC 슬래브(120)를 초기 세팅하는 단계; (c) 전단포켓(121)과 하우징(112)이 서로 연통되도록 거치된 PC 슬래브(120)의 높이와 횡방향구배를 바닥판 높이조절장치(140)와 횡방향구배용 새들(150)를 이용하여 조절하는 단계; (d) 종방향 바닥판체결구(130)를 이용하여 PC 슬래브(120)를 종방향으로 연결시키는 단계; 및 (e) 전단포켓(121)을 통해 하우징(112)에 전단연결재(114)를 고정 설치하고, 전단포켓(121)에 무수축모를타르를 포함하는 충전재(148)를 충전시켜 교량용 거더(110)와 PC 슬래브(120)를 서로 강결시키는 단계;를 PC 슬래브 시공방법에 의하여 상기 (d) 단계의 종방향 바닥판체결구(130)는 PC 슬래브(120)들의 상부수용홈(123) 및 중간삽입홈(124)에 상부덧댐판(131) 및 중간덧댐판(132)이 삽입되어 상,하로 관통홀(131a,132a)이 연통되도록 세팅되어 상기 상부덧댐판(131)과 중간덧댐판(132)은 서로 인접한 PC 슬래브(120)의 연결단부면(B)에서 상,하로 연통된 관통홀(131a,132a)을 통해 체결볼트(133)가 체결되도록 하여 PC 슬래브(120)가 종방향으로 연결하면서 설치되며, 상기 중간덧댐판(132)은 일측 PC 슬래브(120)의 중간삽입홈(124)에 삽입시켜 놓은 상태에서, 연결되는 타측 PC 슬래브(120)의 중간삽입홈(124)쪽으로 이동시켜 중간덧댐판(132)의 중간부분이 연결단부면(B)을 경유하도록 세팅하여, 중간덧댐판(132)은 일측 PC 슬래브(120)의 중간삽입홈(124)에 완전히 삽입된 상태가 되어 타측 PC슬래브(120)가 일측 PC 슬래브(120)로 인접하는 과정에서 방해 요인이 되지 않도록 하는 PC 슬래브 시공방법을 이용하여 제작된 교량.


(a) Place the bridge girder 110 on the constructed bridge substructure 200, but expose the housing 112, which is the shear connector (A), to the upper surface of the upper flange 111 of the bridge girder 110 forming; (b) The housing 112 exposed on the upper surface of the mounted bridge girder 110 and the shear pocket 121 of the PC slab 120 are installed so that they communicate with each other, and the connection end surface of the body portion 122 (B) ) An upper receiving groove 123 is formed on the upper surface of the circumference, and an intermediate insertion groove 124 is formed in the middle of the connection end surface (B), so that the upper receiving groove 123 and the intermediate insertion groove 124 are formed on the connection end surface (B). Initial setting of the adjacent PC slabs 120 so that the grooves 124 are in horizontal contact with each other and communicate with each other; (c) The height and lateral gradient of the PC slab 120 mounted so that the shear pocket 121 and the housing 112 are in communication with each other using the floor plate height adjusting device 140 and the saddle 150 for lateral gradient Adjusting by doing; (d) connecting the PC slab 120 in the longitudinal direction using the longitudinal bottom plate fastener 130; And (e) fixedly installing the shear connector 114 to the housing 112 through the shear pocket 121, and filling the shear pocket 121 with a filler 148 containing non-shrinkable mortar to bridge the girder ( 110) and the step of hardening the PC slab 120 to each other; by the PC slab construction method, the longitudinal bottom plate fastener 130 of the step (d) is the upper receiving groove 123 of the PC slabs 120 and The upper backing plate 131 and the middle backing plate 132 are inserted into the middle insertion groove 124 and set so that the upper and lower through holes 131a and 132a communicate with each other, so that the upper backing plate 131 and the middle backing plate ( 132) allows the fastening bolts 133 to be fastened through through-holes 131a and 132a communicating upward and downward on the connection end surface B of the PC slab 120 adjacent to each other so that the PC slab 120 is longitudinally It is installed while connecting, and the intermediate padding plate 132 moves toward the intermediate insertion groove 124 of the PC slab 120 on the other side to be connected while being inserted into the intermediate insertion groove 124 of the PC slab 120 on one side. so that the middle part of the intermediate pad 132 passes through the connection end surface B, so that the intermediate pad 132 is completely inserted into the middle insertion groove 124 of the PC slab 120 on one side A bridge manufactured using a PC slab construction method that prevents the other side PC slab 120 from being an obstacle in the process of adjoining one side PC slab 120.


KR1020220042145A 2022-04-05 2022-04-05 Precast concrete slab construction method and bridge fabricated by usinr the same KR102486675B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020220042145A KR102486675B1 (en) 2022-04-05 2022-04-05 Precast concrete slab construction method and bridge fabricated by usinr the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020220042145A KR102486675B1 (en) 2022-04-05 2022-04-05 Precast concrete slab construction method and bridge fabricated by usinr the same

Publications (1)

Publication Number Publication Date
KR102486675B1 true KR102486675B1 (en) 2023-01-11

Family

ID=84892436

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020220042145A KR102486675B1 (en) 2022-04-05 2022-04-05 Precast concrete slab construction method and bridge fabricated by usinr the same

Country Status (1)

Country Link
KR (1) KR102486675B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102568964B1 (en) * 2023-03-28 2023-08-23 주식회사 태정엔지니어링 Precast Deck Coupling Structure for Reducing Differential Settlement

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06299706A (en) * 1993-04-13 1994-10-25 Jio Star Kk Level adjusting device of member
JPH11350431A (en) * 1998-06-08 1999-12-21 Nihon Samicon Kk Joint construction of precast concrete floor slab
KR100538832B1 (en) 2003-11-24 2005-12-26 (주)대우건설 Installation Structure of Precast Deck and Girder Using Railing System
KR20080093261A (en) 2007-04-16 2008-10-21 (주)석탑엔지니어링 Composite bridge construction method
KR100876388B1 (en) * 2008-06-02 2008-12-29 (주)한맥기술 Stay in place deck precast panel
KR20110108126A (en) * 2010-03-26 2011-10-05 주식회사 다산컨설턴트 Continuous bridge using multiple stage displacement and taper member psc slab girder connected by member rigid connection portions and method for constructing the same
KR20150039970A (en) * 2013-10-04 2015-04-14 산이건설 주식회사 Pre-cast panel bond structure of bridge extension slab
KR20160053289A (en) * 2014-11-03 2016-05-13 (주)삼현피에프 Precast half-slab for bridge and method of constructing bridge superstructure using same
JP2018188918A (en) * 2017-05-11 2018-11-29 東洋ゴム工業株式会社 Jack device, jack jig unit, and support method
KR102073169B1 (en) 2019-07-05 2020-02-04 김찬녕 Precast slab for pavement construction method
KR102144400B1 (en) 2020-02-05 2020-08-13 주식회사 신원알피씨 Psc girder for precast slab and construction method thereof
KR102313351B1 (en) * 2021-01-18 2021-10-15 (주)상보 Rahmen bridge using composite girder with concrete girders at both ends and construction method thereof

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06299706A (en) * 1993-04-13 1994-10-25 Jio Star Kk Level adjusting device of member
JPH11350431A (en) * 1998-06-08 1999-12-21 Nihon Samicon Kk Joint construction of precast concrete floor slab
KR100538832B1 (en) 2003-11-24 2005-12-26 (주)대우건설 Installation Structure of Precast Deck and Girder Using Railing System
KR20080093261A (en) 2007-04-16 2008-10-21 (주)석탑엔지니어링 Composite bridge construction method
KR100876388B1 (en) * 2008-06-02 2008-12-29 (주)한맥기술 Stay in place deck precast panel
KR20110108126A (en) * 2010-03-26 2011-10-05 주식회사 다산컨설턴트 Continuous bridge using multiple stage displacement and taper member psc slab girder connected by member rigid connection portions and method for constructing the same
KR20150039970A (en) * 2013-10-04 2015-04-14 산이건설 주식회사 Pre-cast panel bond structure of bridge extension slab
KR20160053289A (en) * 2014-11-03 2016-05-13 (주)삼현피에프 Precast half-slab for bridge and method of constructing bridge superstructure using same
JP2018188918A (en) * 2017-05-11 2018-11-29 東洋ゴム工業株式会社 Jack device, jack jig unit, and support method
KR102073169B1 (en) 2019-07-05 2020-02-04 김찬녕 Precast slab for pavement construction method
KR102144400B1 (en) 2020-02-05 2020-08-13 주식회사 신원알피씨 Psc girder for precast slab and construction method thereof
KR102313351B1 (en) * 2021-01-18 2021-10-15 (주)상보 Rahmen bridge using composite girder with concrete girders at both ends and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102568964B1 (en) * 2023-03-28 2023-08-23 주식회사 태정엔지니어링 Precast Deck Coupling Structure for Reducing Differential Settlement

Similar Documents

Publication Publication Date Title
JP4844918B2 (en) Construction method of steel / concrete composite deck using precast concrete board
CN108914715B (en) Assembly type ballastless track structure for vibration reduction zone and assembly method
KR20050064049A (en) Method for connecting continuously p.s.c-ibeam by steel bracket and its structure
JP2007077630A (en) Continuous girder using precast main-girder segment, and its erection method
KR100986207B1 (en) Precast psc t-type girder bridge and its construction method
JP2009041227A (en) Structure and method for joining precast floor slabs together
JP2007239301A (en) Method of integrating precast concrete members interposed by filling concrete
CN110761119A (en) Cold-pressed longitudinal-connection-containing assembly type ballastless track structure of vibration reduction section and assembly method
KR102144400B1 (en) Psc girder for precast slab and construction method thereof
KR101860512B1 (en) Method for reinforcing cross section installation of ground and underwater structure using integral mold module
KR101204040B1 (en) precast concrete member and assembled concrete abutment of bridge
KR100693872B1 (en) Connection structure and construction method for steel and concrete composite deck with a blocked out
CN108914716B (en) Wet-joint type assembling method for prefabricated sleeper slab or track slab ballastless track
KR102486675B1 (en) Precast concrete slab construction method and bridge fabricated by usinr the same
CN108914713B (en) Wet-connection type assembling method for ballastless track of vibration reduction zone
KR101326170B1 (en) Psc girder segment with connecting anchor block, psc girder and modular psc girder bridge construction method using the same
JP4834890B2 (en) Prestressing method for filling part between precast concrete members
US20120222375A1 (en) Method to Compress Prefabricated Deck Units by Tensioning Elements at Intermediate Supports
KR101133420B1 (en) Precast concrete connection block and the continuity method of composite bridges using it
KR101013009B1 (en) Apparatus having a girder connection anchor plate and the continuous construction method for a psc girder bridge by using the same apparatus
JP2750556B2 (en) Manufacturing method of prestressed concrete girder
CN110761123A (en) Assembly type ballastless track structure containing longitudinal connecting structure of vibration reduction section and assembly method
KR101522610B1 (en) Underground box structure for strengthening reinforced-concrete wall and slab using preflexion of bracing member, and method for reinforcing the same
KR102462488B1 (en) Precast slab with interrocking shear member and construction method using the same
JPH0782709A (en) Reinforcing method for concrete structure, employing hollow pc steel bar

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant